UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA
Transcript
Page 1: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

U T I L I Z I N G

CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA

Page 2: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

INTRODUCTION

Team City of Greensboro HDR Constructors Garney

Capital Improvement Needs Townsend WTP TZO WRF

CMAR vs. Alternate Delivery Methods

Page 3: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

PROJECT BACKGROUND

Construction Manager at Risk (CMAR) in Greensboro Owner Objectives / Goals RFQ Process

CM Selection Design and Partnering

Designer and CM Pre-Construction Timeline

Page 4: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

DESIGN-BID-BUILD Traditional Baseline for Project Delivery Proven Procurement Solution

DIFFERING DELIVERY METHODS

PRELIMINARY DESIGN

FINAL DESIGN BID CONSTRUCTION

PROCESS

Page 5: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

Design-Bid-Build ADVANTAGES Competitively Bid Separate Contracts Self-Performance Capabilities Time-Tested Process / Used in All States Maximizes Owner Input

DIFFERING DELIVERY METHODS

Page 6: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

Design-Bid-Build DISADVANTAGES Limited Collaboration / Teamwork Eliminates Qualifications-Based Selection No Contractual Relationship Adversarial Approach

Low Bid Value Engineering Design

DIFFERING DELIVERY METHODS

Page 7: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

DESIGN-BUILD Design and Construction Fixed Price Based on Concept Design and/or

Description from Procurement Documents

DIFFERING DELIVERY METHODS

PRELIMINARY DESIGN FINAL DESIGN

CONSTRUCTION

PROCESS

Page 8: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

Design-Build ADVANTAGES Team Qualifications-Based Selection Accelerated Schedule Public Acceptance for Lump-Sum Contract Self-Performing Contractor Controls

Schedule Known Performance Criteria Final GMP

DIFFERING DELIVERY METHODS

Page 9: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

Design-Build DISADVANTAGES Longer Procurement Process Eliminates or Reduces Participation in

Procurement Process Inefficient Use of Municipal Funds and Staff

Time Bidding Process

DIFFERING DELIVERY METHODS

Page 10: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

CMAR Qualifications-Based Selection Contractor Engaged Early in Design Phase Two-Contract Relationship

DIFFERING DELIVERY METHODS

PRELIMINARY DESIGN FINAL DESIGN

CONSTRUCTABILITY REVIEW

CONSTRUCTION

PROCESS

Page 11: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

CMAR ADVANTAGES Owner Control of Project Goals Provides for Value Engineering (VE) and

Constructability Reviews Contractor-Led Estimates Reduces Overall Risk Schedule Acceleration Competitive Selection

DIFFERING DELIVERY METHODS

Page 12: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

CMAR DISADVANTAGES Engineer’s Estimate for Initial Project Costs Potential Cost Increase with VE and

Constructability Review Preconstruction Services Cost Double-Bonding Separate Contracts Increased Design Duration

DIFFERING DELIVERY METHODS

Page 13: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TZO WATER RECLAMATION FACILITY

Retrofitting Existing Anthracite Media Filters with new Aqua-Aerobic Systems Diamond Cloth Filter Equipment

New Chlorine Contact Tank

Chemical System Upgrades

Site-Wide Stormwater Improvements

Electrical Improvements

Page 14: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

PRECONSTRUCTION AT TZO

Estimates at 90% Document Phase

Development of CPM Schedule

Executed Mentor / Protégé Program with Local MBE, SRS

M/WBE Work Packages

Page 15: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TZO CHALLENGES AND BENEFITS

Challenges & Benefits

Dividing Competitive Work Packages

Flexibility with NCDEQ Filter Construction Sequencing - Eliminating

Option to Bypass Filters

Increasing Minority Participation

Constructability / Cost Review at 90%

Page 16: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TZO SCHEDULE

Work Packages Constraints of Existing Plant Operations

Minimal Shutdowns / Uninterrupted Access

Effluent Filter Modifications One Bank

of Filters Off-Line Per Time

Page 17: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND WATER TREATMENT PLANT

Lime / PAC Facility Flocculation & Sedimentation Basins Filter Upgrades Backwash Process Upgrades

MAY 16 –

DEC 17

JAN 15 –

DEC 15PRECONSTRUCTION CONSTRUCTION

Page 18: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND PRECON METHODOLOGY

Cost Models 60% Documents VE

Early Project Schedule Development Input from O&M Staff, Engineer and

Subcontractors Determines General Conditions Duration

Subcontracting Packages Facilitate Area Market Clear Scope Delineation

Page 19: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND CHALLENGES/BENEFITS - GMP

Open Book Environment

Collaborative Preconstruction Workshops

Proactive Project Execution Planning - Plant Production Restrictions

Constructability and Value Analysis Procurement (Buy-Out)

Plan

Start-Up and Commissioning Plan

Page 20: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND CHALLENGES/BENEFITS – M/WBE

Aspirational Goals

Commitment to M/WBE Program

Outreach and Communication with Interested Individuals

Provide Guidance during Bidding, Contracting and Construction Phases

Ensure Parties Follow City’s Guidelines for Implementation

Page 21: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

CMAR AT TOWNSEND WTP

Qualifications-Based Selection

Better Control of Construction

Implementation of M/WBE Program

Collaborative and Team-Oriented Project Delivery

Less Adversarial Construction Environment

Page 22: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND – ENGAGING THE CMAR EARLY

60% Design Documents Understand Project Budget Ability to Value Engineer Project Early Development of CPM

Page 23: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND – CHALLENGES/BENEFITS - MOPO

Maintenance of Plant Operations (MOPO) Ability to Redesign Identify Schedule Constraints Minimize Timeframe for Outages Ability to Understand Construction

Sequencing

Page 24: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

TOWNSEND PROJECT SCHEDULE

Early Development of CPM Schedule Identified Sequencing Incorporated Peak Times Sequenced MOPOs

Page 25: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

OWNER CHALLENGES - LEGAL

Contract Vehicle State Standard Contract vs. CMAA vs. AIA

Prequalification Process State Statute Requirements Criteria to Prequalify Target Audience for the Process

Page 26: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

OWNER CHALLENGES – M/WBE

Disparity Study Hispanic Participation - Goal Achievement

Setting of Goals GMP Estimate or Trade Packages

Bid Responsiveness Prequalification vs. Bids

HUB Understanding of Formal Bid Process

Page 27: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

OWNER CHALLENGES – M/WBE (CONT.)

Mentor – Protégé City Procedure Goal Achievement

New Process for Evaluating Good Faith CM Level and Sub-Tier Level

Mandatory Prequalification Participation Responsiveness Education

Page 28: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

OWNER CHALLENGES - DESIGN

Design Completion Level 60% Townsend vs. 90% TZO

Self-Performance State Statute

Team Cohesiveness Experience Receptiveness to Feedback

Design Review Process Constructability and VE

Page 29: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

GMP Finalization / Sub-Contract Execution Budgeting Value Engineering

Construction Phase NTP and Duration

NEXT STEPS

Page 30: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

M/WBE Understanding Budgeting / Value Engineering Prequalification Process Staff Understanding of CMAR Process

Educate Key Departments / Staff Develop Procedures to Support Delivery

Method

KEY TAKEAWAYS

Page 31: UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.

QUESTIONS?