Date post: | 12-Jul-2016 |
Category: |
Documents |
Upload: | rampw14581 |
View: | 44 times |
Download: | 8 times |
CHANDRAPUR SUPER THERMAL POWER STATION
CHANDRAPUR
ISO 9001- 2000, ISO 14001 and OHSAS 18001 UNIT
A PROJECT REPORT
CAPITAL OVERHAUL JAN - 2016UNIT # 5
(PERIOD: 27.12.2015 TO 30.01.2016)
SUBMITTED BY
Er. P.V.GOSAVI Executive Engineer
Er. S.S.BHANSE Assistant Engineer
Er. P.D.HAJARE Assistant Engineer
Er. S.S.DHERE Assistant Engineer
Er. N.S.KSHIRSAGAR Assistant Engineer
1
CHANDRAPUR SUPER THERMAL POWER STATION
QUALITY POLICY:
Chandrapur Super Thermal Power Station of Maharashtra State Power Generation CO. Limited
recognizes its prime role in state power grid and is committed to produce economical and reliable
power in an environmentally sustainable manner with continual improvement in effectiveness of quality
management system.
We shall endeavor to upgrade knowledge and skill of our staff and strive for safe working practices
and minimum occupational health hazards.
QUALITY OBJECTIVES:
Increase in station generation.
Increase in plant load factor.
Reduction in auxiliary power consumption.
Reduction in loss of generation due to O&M problem.
Reduction in forced outages factor.
Increase in station availability.
Reduction in total Nos. of tripping.
Reduction in numbers of tripping due to boiler tube leakage.
Reduction in loss of man days due to accidents excluding fatal accidents.
Imparting training for engineers and workers.
ENVIRONMENTAL POLICY:
Chandrapur Super Thermal Power Station of Maharashtra State Power Generation Co.Limited is
committed to produce power to the use modern technology and work practices for prevention of
pollution.
2
We are committed to:
Carry out with environment legislation and regulation.
Carry out with C. R. E, P. and corporate policy.
Reduction in consumption of natural resources by optimum utilization of coal, oil and water.
Conservation of water by recycling water for ash disposal.
Minimization of pollution by promoting fly ash utilization.
Prevention of pollution by increasing green belt area.
Reduction of SPM level of stack emission.
Continual improvement in effectiveness of environment management system.
The environment al policy will be reviewed for objectives and targets at appropriate time.
OCCUPATIONAL HEALTH AND SAFETY POLICY:
Chandrapur Super Thermal Power Station of Maharashtra State Power Generation Co. Limited is
committed for continual improvement in health and safety performance of all our employees.
We are committed to continually improve the OHSMS by:
Identifying and assessing all types of OHS risk and take proactive step to reduce the significant risks,
in turn reduce occurrences of accidents.
Identifying, updating and Carried outlying with all applicable statutory requirements.
Creating awareness about occupational health and safety amongst all employees, contractors and
contract labors and training them adequately for safe work practices.
Preventing injury, loss of property and controlling occupational health problems, following appropriate
measures in respective areas of work.
3
CHANDRAPUR SUPER THERMAL POWER STATION
UNIT-V CAPITAL OVERHAUL
PREFACE
CSTPS is a quality conscious, thermal power station. It is the First Power Station in the history of
MSPGCL and first amongst all the State Electricity Board's in INDIA to get prestigious ISO-9002
certification, then ISO-9001 certification And ISO-14000 for its Environmental Management System
and OHSAS 18000.
In order to continuously upgrade and maintain the quality, Capital overhaul of unit-V was declared
W.E.F. 27.12.2015. Boiler validity was up to 03.04.2016.
During this overhaul, major thrust was given on:
1. Replacement/Servicing of passing valves of boiler and turbine side.
2. Removal, servicing, calibration & restoration of SADC Power Cylinder.
3. Overhauling of CCW 5C & BFV seal ring replacement.
4. Work of separation of ACW return line from CCW hot water outlet line.
5. Servicing of APH including basket replacement.
6. Servicing of Burner Tilt including coal compartment assemblies replacement.
7. Seal trough cleaning.
8. Maintenance/Servicing of ESP.
9. Work of repairing /replacement of riser valves of cooling tower.
10. Servicing/ Calibration of Boiler and Turbine side control valves.
11. CONDENSER TUBE CLEANING BY SULPHAMIC ACID.
12. Cleaning of Pent house, Repair of pent house, dog house & cat house.
13. A-type of C/M-A, B, C & H mills.
14. Bottom Ash hopper refractory replacement.
15. Arrest air ingress in the boiler.
16. Complete overhauling of BT mechanism .
17. Repairs of overheated / eroded water wall tubes, SH / RH tubes, LTSH tubes, economizer tubes.
18. Turbine all bearing inspection and LP turbine overhaul.
19. Calibration of various instruments.
20. TDBFP-6B over-haul work.
21. HPT Module servicing work.
4
THIS OVERHAUL REPORT OF U # 5 IS DISTRIBUTED IN FOUR PARTS.
Part I : Pre overhaul report, unit history and planned O/H activities.
Part II : Actual overhaul activities.
Part III : Post overhauls activities.
Part IV : Overhaul expenditure.
5
INDEX
PART-I
PRE OVERHAUL REPORT, UNIT HISTORY AND PLANNED O/H ACTIVITIES :
A. Staff arrangement.
B. Unit History.
C. Set withdrawn activities.
D. Problems faced during operation.
E. Major activities planned.
PART-II
ACTUAL OVERHAUL WORKS CARRIED OUT :
A. Boiler maintenance - II
B. Turbine maintenance - II
C. ODP - II
D. Electric Maintenance - II
E. Instrumentation& Control – II
F. Testing – II
PART- III
A. LIGHT UP, ROLLING AND SYNCHRONIZATION OF UNIT.
B. POST OVERHAUL ACHIEVEMENTS.
C. POST OVERHAUL PENDING DEFECTS.
PART- IV
A. OVERHAUL EXPENDITURE.
6
PART - I
PRE OVERHAUL REPORT, UNIT HISTORY AND PLANNED O/H ACTIVITIES:
A. Staff arrangement.
B. Unit History.
C. Set withdrawn activities.
D. Problems faced during operation.
E. Major activities planned.
UNIT-5 OPERATION STAFF ARRANGEMENT:
PROJECT MANAGEMENT:
Er. P. V. GOSAVI Executive Engineer Project Manager
Er. S.S. BHANSE Assistant Engineer
Er. N.S. KSHIRSAGAR Assistant Engineer
Er. S. S. DHERE Assistant Engineer
Er. P.D. HAJARE Assistant Engineer
ISOLATION & NORMALIZATION:
Er. A.M. KATHOYE Executive Engineer Team Manager
Er. M.H. ALI Assistant Engineer
Er. S.R.GITE Assistant Engineer
Er. G.B. NIMKAR Junior Engineer
Er. V.K.CHAUDHARI Junior Engineer
7
TURBINE SIDE ACTIVITIES:
Er. G.S.KULSANGE Executive Engineer Team Manager
Er. A.D.MOHOKAR Dy Executive Engineer
Er. H.S. GHUGE Assistant Engineer
Er. Y.W.ASAWALE Junior Engineer
BOILER SIDE ACTIVITIES:
Er. A.V.YELE Executive Engineer Team Manager
Er. P.W. RAMTEKE Addl. Executive Engineer
Er. N.S.KADAM Addl. Executive Engineer
Er. S.B. KAMBLE Dy. Executive Engineer
Er. V.B.RAMTEKE Assistant Engineer
ODP ACTIVITIES:
Er. P.N. WARUDKAR Executive Engineer Team Manager
Er. K.Y. UIKE Dy. Executive Engineer
Er. R.R. KALE Assistant Engineer
Er. P.P.ROY CHAUDHARY Assistant Engineer
SHIFT STAFF ARRANGEMENT:
1) Shift In Charge In overhaulPeriod:
Er. J.D. BAWANE Addl. Executive Engineer
Er. R.S. NAIDU Addl. Executive Engineer
Er. V.M. JOSHI Dy. Executive Engineer
Er. D.D. KAMBLE Dy. Executive Engineer
Er. M.T. BULKUNDE Dy. Executive Engineer
8
2) Control Desk Engineer in Shift:
Er. P.P. PATIL Dy. Executive Engineer
Er. S.K. TETWAR Assistant Engineer
Er. S.V. MESHRAM Assistant Engineer
Er. G.S. CHIKANKAR Assistant Engineer
Er. S.S. THOMBARE Assistant Engineer
3) Deputation to other section:
A) TURBINE MAINTENANCE:Er. B.S. PETKAR Junior Engineer
B) BOILER MAINTENANCE-II:
Er. D.M. CHANDAVALE Assistant Engineer
C) INSTRUMENT&CONTROL-II:
Er. J.A. DHANGAR Assistant Engineer
9
UNIT HISTORY:
M.S.E.B. (Now Maharashtra State Power Generation Co. Limited) has constructed a Coal Based
Thermal Power Station at Chandrapur, in Maharashtra State. This is on the Broad Gauge rail route of
the Central Railway, on Delhi-Chennai trunk route. A site is situated near village Neri and Durgapur on
Chandrapur Tadoba road at a distance of 6-7 km. from Chandrapur. Broad gauge railway siding and
all weather approach road connect the project site.
Chandrapur Super Thermal Power Station of generating capacity of 2340 MW has adequate water
apart from the huge coal reserve in Chanda - Wardha Valley.
STAGE UNIT SANCTION COMMISSIONING COMMERCIAL OPERATED
I1 JUL-1976 15/08/1983 01/11/1985
2 JUL-1976 11/07/1984 16/09/1985
II3 FEB-1979 03/05/1984 01/04/1986
4 FEB-1979 08/03/1986 04/11/1986
III5 JUN-1981 22/03/1991 01/12/1992
6 JUN-1981 11/03/1992 01/12/1993
7 FEB-1991 01/10/1997 01/03/1998
CLIMATIC CONDITION
The climatic condition of Chandrapur is as follows-
a)Elevation : 192.3 meters above MSL
b)Maximum temperature : 50 0C
c)Minimum temperature : 6 0C
d)DBT / WBT
Summer : 112.5 0F dbt/81.5 0F wbt
Winter : 88.2 0F dbt/78.2 0F wbt
e)Annual rainfall : 750 millimeters
10
UNIT DETAILS :
(1) Boiler Registration No : MR 11729
(2) Boiler
Type- Controlled Circulation with Rifled Tubing CC+, Radiant Reheat, Dry Bottom, Top
Supported.
Design pressure : 204 kg/cm2
SH outlet : 179 kg/cm2 / 540 0C
(3) Furnace
Type- Balanced Draft Furnace with Fusion Welded Water Walls
Width : 18034 mm.
Depth : 15289 mm.
Volume : 14580 m3
Fuel Heat Input : 1225.5 X 106 kcal / hrs.
(4) Turbine
o Three cylinders reheat condensing Turbine.
o Single - flow HP turbine with 18 reaction stages. Type: H30 - 63 - 2
o Double - flow IP turbine with 14 reaction stages per flow. Type: M30 - 50
o Double - flow LP turbine with 6 reaction stages per flow. Type: N30 - 2x10 – 2
RATING:
Normal rating 500 MW
TMCR 524.4MW
11
SPEED:
Rated speed : 3000 rpm.
Standard over speed trip setting : 3330 rpm max.
Generator & Exciter:
Generator Type THDF 115 / 59
Main Exciter Type ELR 70 / 90 -30 / 6 -20E5
Pilot Exciter Type ELP 50 / 42 - 30 / 16 E7
Rated Data & OutputsTurbo-Generator
Main Exciter Pilot Exciter
Apparent Power 588 MVA 65 kVA
Active power 500MW 3840 kW
Current 16.2kA 6300A 195 A
Voltage 21±1.05 kV 600 V 220 ± 22 V
Speed 50 s -1 50 s -1 50 s -1
Frequency 50 Hz 400 Hz
Power factor 0.85
Inter conn. of Stator winding YY
H2 Pressure 3.5 Bar
Cont. Perm. Unbalanced Load 8 %
GENERATOR VOLUME AND FILLING:
Generator volume (Gas volume): 80 M3
CO2 Filling Quantity: 160 M3 (STP),
H2 Filling Quantity: 480 M3 (STP)
12
HISTORY OF THE UNIT # 5:
ParticularsUNIT - 5
(500 MW)
Boiler No. MR-11729
Comms. date 22-03-91
Coal firing 31-03-92
Commr. op 01-12-92
SR.NO. TRIPPED SYNCHRONISED REASONS / REMARKS DATE & TIME DATE & TIME
1 06/07/94 20.15 13/09/94 04.05 CAPITAL OVERHAUL
2 05/10/96 22.30 22/10/96 13.47 ANNUAL OVERHAUL
3 01/12/97 22.10 16/12/97 07.40 ANNUAL OVERHAUL
4 13/06/99 00.45 29/07/99 00.45 CAPITAL OVERHAUL
5 11/08/00 22.30 19/08/00 16.15MINI
OVERHAUL
6 18/07/01 00.00 14/08/01 18.40 ANNUAL OVERHAUL
7 31/07/03 03.20 16/09/03 06.05 CAPITAL OVERHAUL
8 01/07/05 00.00 15/12/06 22.54
ANNUAL OVERHAUL
( Extended due to
turbine breakdown)
9 14/08/08 19.30 19/09/08 05.50
ANNUAL OVERHAUL /
LPT & IPT inspn and
Reheater Girdling Loop
& LTSH coil repl'nt.
10 16/04/2010
11 29/12/11 12.13 08/01/12 19.54 MINI OVERHAUL
1214/07/2013
00:00/02/2014 ANNUAL OVERHAUL
13
14
Year wise Generation, PLF, AVF:
Year GEN PLF AVF
(Mus) (%) (%)
1991-92 1.224 16.88
1992-93 1035.820 23.65 44.43
1993-94 1877.224 42.86 78.71
1994-95 2130.928 48.65 73.85
1995-96 3194.136 72.73 90.81
1996-97 3383.520 77.25 89.63
1997-98 3279.445 74.87 89.74
1998-99 3115.664 71.13 88.27
99-2000 3049.040 69.42 80.76
2000-01 3428.528 78.28 90.26
2001-02 3376.464 77.09 87.14
2002-03 3493.448 79.76 93.11
2003-04 3335.120 75.94 83.62
2004-05 3734.357 85.26 90.78
2005-06 989.873 22.60 24.20
2006-07 1121.927 25.61 27.45
2007-08 3384.122 77.05 89.81
2008-09 2958.086 67.54 85.44
2009-10 3158.904 72.12 94.31
2010-11 2325.151 53.09 72.46
2011-12 3144.648 71.60 92.26
2012-13 3208.469 73.25 96.19
2013-14 1170.367 26.72 36.17
15
2014-15 3039.905 69.40 91.07
ANALYSIS OF GENERATION & LOSSES
16
Loss Of Generation Report For Unit-V For The Period: 23/08/2012 To 27/12/2015
17
SR NO
P A R T I C U L A R S
2013-14
(Aug-13 to Mar-14)
2014-152015-16
(Till Jan-16)Total
Mus. % Mus. % Mus. % Mus. %
1 Possible generation 2544.000 100.00 4380.000 100.00 3300.000 100.0010224.00
0100
2 Actual generation 361.369 14.20 3039.905 69.40 2178.224 66.01 5579.498 54.57
3 Loss of generation 2182.631 85.80 1340.093 30.60 1121.776 33.99 4644.500 45.43
A] Unit overhauls 0.000 0.00 0.000 0.00 50.583 1.53 50.583 0.49
B] External factors 72.699 2.86 707.706 16.16 477.202 14.46 1257.607 12.30
i) Low system demand 20.764 0.82 147.846 3.38 239.454 7.26 408.064 3.99
ii) Poor coal receipt 0.000 0.00 232.341 5.30 0.000 0.00 232.341 2.27
iii) Poor coal quality 51.935 2.04 276.127 6.30 201.250 6.10 529.312 5.18
iv) Wet coal problems 0.000 0.00 16.084 0.37 36.368 1.10 52.452 0.51
v) System problem 0.000 0.00 35.308 0.81 0.130 0.00 35.438 0.35
vi) Water Shortage
problems0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00
vii) Excessive Rains 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00
C] Op. & Mt factors 2109.932 82.94 632.387 14.44 593.991 18.00 3336.310 32.63
1) Boiler tube leakage 26.840 1.06 167.141 3.82 236.101 7.15 430.082 4.21
2) Pr.parts/pipes/valves 0.000 0.00 78.798 1.80 0.000 0.00 78.798 0.77
3) Coal mills 0.115 0.00 2.120 0.05 2.753 0.08 4.988 0.05
4) ID/FD/PA fan 0.000 0.00 10.936 0.25 1.392 0.04 12.328 0.12
5) Flame fail/Furnace
pr0.000 0.00 0.000 0.00 1.308 0.04 1.308 0.01
18
SR NO
P A R T I C U L A R S
2013-14
(Aug-13 to Mar-14)
2014-152015-16
(Till Jan-16)Total
Mus. % Mus. % Mus. % Mus. %
1 Possible generation 2544.000 100.00 4380.000 100.00 3300.000 100.0010224.00
0100
2 Actual generation 361.369 14.20 3039.905 69.40 2178.224 66.01 5579.498 54.57
3 Loss of generation 2182.631 85.80 1340.093 30.60 1121.776 33.99 4644.500 45.43
A] Unit overhauls 0.000 0.00 0.000 0.00 50.583 1.53 50.583 0.49
B] External factors 72.699 2.86 707.706 16.16 477.202 14.46 1257.607 12.30
i) Low system demand 20.764 0.82 147.846 3.38 239.454 7.26 408.064 3.99
ii) Poor coal receipt 0.000 0.00 232.341 5.30 0.000 0.00 232.341 2.27
iii) Poor coal quality 51.935 2.04 276.127 6.30 201.250 6.10 529.312 5.18
iv) Wet coal problems 0.000 0.00 16.084 0.37 36.368 1.10 52.452 0.51
v) System problem 0.000 0.00 35.308 0.81 0.130 0.00 35.438 0.35
vi) Water Shortage
problems0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00
vii) Excessive Rains 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00
C] Op. & Mt factors 2109.932 82.94 632.387 14.44 593.991 18.00 3336.310 32.63
1) Boiler tube leakage 26.840 1.06 167.141 3.82 236.101 7.15 430.082 4.21
2) Pr.parts/pipes/valves 0.000 0.00 78.798 1.80 0.000 0.00 78.798 0.77
3) Coal mills 0.115 0.00 2.120 0.05 2.753 0.08 4.988 0.05
4) ID/FD/PA fan 0.000 0.00 10.936 0.25 1.392 0.04 12.328 0.12
5) Flame fail/Furnace
pr0.000 0.00 0.000 0.00 1.308 0.04 1.308 0.01
TRIPPING REPORT FOR UNIT-V THE PERIOD: 20/02/2014 TO 09/06/2015 :
UNIT-5 TRIPPING OH TO OH
SR.TRIPPED DATE
& TIMESYNCHRONISED
DATE & TIMEREASONS / REMARKS
1 20/02/14 20.51 21/02/14 03.56Unit tripped on Gen. H2 cold gas temp.
After cooler very high. (Other Problem)
2 28/02/14 18.37 03/03/14 13.39
Unit withdrawn to attend Boiler Tube
Leakage
(Zone - Steam Cooled Wall). The
synchronization delayed due to Barring
gear jamming problem. (Turbine
misc/others - 6.825 Mus)
3 05/05/14 00.40 08/05/14 06.20
Unit tripped on "Condenser pressure
very very high" due to tripping of all
CEP's. CEP-5C R-Phase lug detached
and cable touched to body, due to
sulfation effect. CEP-5B R-phase earth.
CEP-5A R/C valve stuck up due to
positioner failure. Turbine barring stalled
on 05-05-2014 @ 08:20 hrs. (Electrical
Problem - 11.667 Mus, Turbine
Brg./CV/rotor/bal - 27.166 Mus from
00:00 hrs of 06-05-2014.)
4 17/05/14 23.20 18/05/14 11.00
Unit Withdrawn to attend hot spot at
GTR Y phase. The work is carried out
by MSETCL 400 KV R/S. (System
Problem)
5 21/05/14 12.46 25/05/14 14.37Unit withdrawn due to Boiler tube
Leakage (Zone : Economizer)
19
SR NO
P A R T I C U L A R S
2013-14
(Aug-13 to Mar-14)
2014-152015-16
(Till Jan-16)Total
Mus. % Mus. % Mus. % Mus. %
1 Possible generation 2544.000 100.00 4380.000 100.00 3300.000 100.0010224.00
0100
2 Actual generation 361.369 14.20 3039.905 69.40 2178.224 66.01 5579.498 54.57
3 Loss of generation 2182.631 85.80 1340.093 30.60 1121.776 33.99 4644.500 45.43
A] Unit overhauls 0.000 0.00 0.000 0.00 50.583 1.53 50.583 0.49
B] External factors 72.699 2.86 707.706 16.16 477.202 14.46 1257.607 12.30
i) Low system demand 20.764 0.82 147.846 3.38 239.454 7.26 408.064 3.99
ii) Poor coal receipt 0.000 0.00 232.341 5.30 0.000 0.00 232.341 2.27
iii) Poor coal quality 51.935 2.04 276.127 6.30 201.250 6.10 529.312 5.18
iv) Wet coal problems 0.000 0.00 16.084 0.37 36.368 1.10 52.452 0.51
v) System problem 0.000 0.00 35.308 0.81 0.130 0.00 35.438 0.35
vi) Water Shortage
problems0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00
vii) Excessive Rains 0.000 0.00 0.000 0.00 0.000 0.00 0.000 0.00
C] Op. & Mt factors 2109.932 82.94 632.387 14.44 593.991 18.00 3336.310 32.63
1) Boiler tube leakage 26.840 1.06 167.141 3.82 236.101 7.15 430.082 4.21
2) Pr.parts/pipes/valves 0.000 0.00 78.798 1.80 0.000 0.00 78.798 0.77
3) Coal mills 0.115 0.00 2.120 0.05 2.753 0.08 4.988 0.05
4) ID/FD/PA fan 0.000 0.00 10.936 0.25 1.392 0.04 12.328 0.12
5) Flame fail/Furnace
pr0.000 0.00 0.000 0.00 1.308 0.04 1.308 0.01
6 12/06/14 10.05 12/06/14 12.38Unit tripped due to generator rotor E/F
relay 64F tripped.(Electrical Problem)
7 12/06/14 19.14 16/06/14 12.25
Unit withdrawn due to Boiler tube
Leakage
(Zone : Super heater)
8 23/06/14 22.00 24/06/14 06.05Unit withdrawn due to abnormal sound
in Primary Air-Heater-B.
9 01/08/14 11.48 04/08/14 16.12Unit withdrawn due to Boiler Tube
Leakage at Steam Cooled Wall.
10 04/08/14 23.19 05/08/14 04.23Unit Withdrawn due to condenser
vacuum very low.
11 05/08/14 05.17 05/08/14 18.02Unit Withdrawn due to Primary Water
Temp. very High.
12 06/09/14 18.3008/09/14 00.10
Unit withdrawn to attend HPH FD-41
Valve problem
13 09/09/14 05.15 14/09/14 12.51
Unit withdrawn to attend HPH FD-41
Valve problem & due to critical coal
stock
14 14/09/14 21.02 15/09/14 10.58 Unit Withdrawn due to PA Fan problem
15 19/09/14 19.13 20/09/14 01.25Unit withdrawn due to PAH-5B rotor
stopped
16 05/12/14 14.58 05/12/14 22.28Unit withdrawn for GTR B Phase jumper
work by MSETCL. (System problem)
20
17 18/12/14 11.01 18/12/14 14.02Unit tripped on "Loss of fuel indication"
(T&IC problem)
18 22/02/15 11.36 25/02/15 18.44Unit withdrawn due to condenser tube
leakage.
19 26/02/15 21.39 03/03/15 14.27Unit withdrawn due to BTL. (Zone -
Super heater)
20 26/03/15 16.44 27/03/15 14.03Unit Tripped due to Starting Device
Card Failure
21 12/04/15 14.38 14/04/15 19.18Unit withdrawn due to BTL. (Zone -
Economizer)
22 29/04/15 08.07 30/04/15 09.39
Unit withdrawn to jamming of SAH-5A
due to dislocation of one no of grating, 1
basket fall down on GD & 1 basket
entrapped in rotor & sector plate . (Air-
Preheater)
23 01/05/15 04.30 10/05/15 17.25Unit withdrawn due to SAH-5B roter
jam.(Air heater Problem)
24 04/06/15 01.01 04/06/15 05.45Unit tripped due to malfunctioning of
FSSS card (T&IC Problem)
25 04/06/15 06.05 04/06/15 08.43
Unit tripped on cold gas temp high due
to closing of H2 temp control valve.
(Others Problem)
26 24/06/15 01.23 26/06/15 02.02Unit withdrawn due to BTL. (Zone -
Economizer )
27 11/07/15 04.43 14/07/15 12.51Unit withdrawn due to BTL. (Zone -
Economizer )
21
28 25/09/15 21.40 28/09/15 22.02Unit Withdrawn due to BTL (Zone - WW
&Economizer)
29 30/09/15 17.36 05/10/15 05.07 Unit Withdrawn due to BTL (Zone - RH)
30 15/10/15 18.00 19/10/15 23.55Unit Withdrawn due to BTL (Zone -
Water Wall)
31 03/11/15 03.28 03/11/15 09.45
Unit tripped as EHG got zero due to
malfunctioning of EHG control final
output card. (T&IC Problem)
32 17/11/15 21.13 18/11/15 05.34
Unit tripped on Condenser Pressure
very High as all running CCW Pumps
tripped due to DC control supply failure
(Electrical Problem)
33 18/11/15 06.35 18/11/15 09.23
Unit tripped as EHG got zero due to
malfunctioning of EHG control final
output card. (T&IC Problem)
34 17/12/15 17.18 17/12/15 19.55 Unit tripped on Flame Failure
35 21/12/15 23.47 22/12/15 05.15Unit tripped on Condenser vacuum very
low
22
C. SET WITHDRAWAL ACTIVITIES:
a) OPERATIONAL ACTIVITIES:
TG Set withdrawn on 27/12/2015 at 18:55Hrs.forcapital overhaul work.
Before withdrawing TA set was sharing 371.01 MW load.
And following were the unit parameters at 13.58hrs.on 26/12/2015.
GENERATOR TRANSFORMER PARAMETERS AS ON 26/12/2015 AT 19:15.00HRS
Sr No PARAMETER GTR-R GTR-Y GTR-B
1 OIL TEMP (Deg. C) 43 47 47
2 WDG TEMP (Deg. C) 48 52 52
3 OIL PUMP RUNNING 1 & 3 1 & 3 1 & 3
4 OIL LEVEL 50 % 40 % 40 %
5 SILICA COLOR BLUE BLUE BLUE
6 TAP POSITION 3 3 3
23
BOILER TURBINE GENERATOR
TUR THR PR
126.01 Kg/cm2.HPT TOP / BOT TEMP.
515 / 518 0C
Gen. Voltage
21.00 KV
MS TEMP
525.770C
IPT TOP / BOT TEMP
326 / 3410C
Gen phase current
R- 10.1, Y- 10.3, B-10.3 K Amp
HRH PR. –
31.51Kg/cm2.
HRH Temp-
5280C
HPT FIRST STG PR.
125 Kg/cm2.
Exciter field current
1942 AMP
MAX. TG BRG VIBR.
23.71 MIC (BRG NO. 07)
GEN FREQ. 50.10 Hz MVA
7.13MVAR
MAX. SHAFT VIBR.
61 MIC.( No. 01)GEN FREQ. 50.10 Hz
Condenser Vacuum
-8630 MMWCLMAX GEN. SLOT TEMP 72.510C
MAX CORE TEMP 51.100C
NEG. PHASE SEQ CURRENT 0.5 %
ESP PARAMETERS ON DT: 18/12/2015:
PASS A – FIELD VOLTAGES IN KV & CURRENT IN mA :
FIELD 1A1 1A2 2A1 2A2 3A1 3A2 4A1 4A2 5A1 5A2 6A1 6A2
VOLT 30 U/V U/V 36 40 53 42 U/V 42 44 39 42
mA 237 U/V U/V 221 352 00 278 U/V 590 41 426 65
PASS B – FIELD VOLTAGES IN KV & CURRENT IN mA :
FIELD 1B1 1B2 2B1 2B2 3B1 3B2 4B1 4B2 5B1 5B2 6B1 6B2
VOLT 30 35 36 28 55 33 42 44 37 41 28 32
mA 32 65 172 82 08 16 04 90 00 123 24 467
PASS C – FIELD VOLTAGES IN KV & CURRENT IN mA :
FIELD 1C1 1C2 2C1 2C2 3C1 3C2 4C1 4C2 5C1 5C2 6C1 6C2
VOLT 16 16 22 45 U/V 32 34 42 U/V U/V 54 51
mA 00 00 00 82 U/V 24 442 574 U/V U/V 24 73
PASS D - FIELD VOLTAGES IN KV & CURRENT IN mA :
FIELD 1D1 1D2 2D1 2D2 3D1 3D2 4D1 4D2 5D1 5D2 6D1 6D2
VOL
T36 34 U/V 26 04 37 39 34 35 36 39 35
mA 98 205 U/V 32 728 303 328 295 295 426 221 418
24
TURBINE BEARING AND SHAFT VIBRATIONS IN MICRONS ON DT: 18/12/2015,AT: 23.09 HRS.
Time
HRS
ABSOLUTE BEARING SHAFT
1
HPT F
2
HPT R
3
IPT R
4
LPT R
5
GEN F
6
GEN R
7
EXC R
1
HPT F
2
HPT R
3
IPTR
4
IPT R
7
EXC
23.09 4.83 3.46 6.70 5.8 25.09 3.89 16.1 70.91 36.31 50.72 58.5 24.4
FOLLOWING ACTIVITIES WERE CARRIED OUT AFTER TRIPPING OF TA SET : BOILER SIDE ACTIVITIES :
1. Boiler draining started on 28/12/2015 at 14:20Hrs.at drum metal temp top/bottom-78/740C.
2. Furnace pressurasation test was carried out on dated 29/12/2015 from 10:45 Hrs. to 12:30 Hrs. at
1424 T/Hr air flow and +52 mmwcl furnace draftwith 2 I.D.fan and 2 F.D. fan in service and leakages
observed were marked with paint.
3. CAVT was carried out in second pass of boiler with 3 I.D.fan and 2 F.D. fan in service on dtd.
29/12/2015 from 14:00 to 18:00 Hrs. at air flow 1436 T/Hr. and -5.9 mmwcl furnace draft.
TURBINE SIDE ACTIVITIES : A. ACW, CCW system :
1. CCW sump make up stopped on dated 30/12/2015 at 14:30Hrs.& level was 190.300 MSL.
2. CCW sump level low alarm not appeared even if sump level drop down to 191.300MSL (Alarm setting
25
191.300 MSL). And CCW pump has to stop manually as no pump was tripped even if sump level
drops down to 190.300 MSL.
3. ACW-5C withdrawn at 10:00 AM on 30.12.2015.ACW-B TRIPPED at 23:30 on 31.12.2015. Sump level
very low (189.600 MSL).
4. MOT coolers, seal oil coolers, IA Compressor & SA Compressor, F/F water supply was provided for
cooling purpose during above period.
B. HYDROGEN PURGING :
1. On dated 27/12/2015 at 18:58 Hrs. unit withdrawn for Capital overhaul work.
2. H2 purging started (at pr.3.1 kg/cm2) at 10:07hrs.on29/12/2015 by opening H2 purging valve from
turbine basement.
3. CO2 filling started at (0.2kg/cm2)13:20Hrs. on Dated 29/12/2015
4. CO2 purity 100.0% achieved on dtd 30.12.2015. Total CO2 cylinders consumed 65Nos.
5. Dry instrument air filling started at 00:50hrs, Dated 31/12/2015 and stopped at 08:15hrs. On
31/12/2015and CO2 purity obtained 0% and air pressure boost-up to 3 kg/cm2 at 08:15hrs.
6. Generator leak test and depressurization of air started dated 01/01/2016 from 09:15hrsand air
pressure kept 0.5 kg/cm2, on dated 01/01/16 at 12.20 hrs.
7. Turbine Barring stopped at 02:45 hrs. On 01/01/2016.HPT top/bottom casing temperatures were
109/110oC.
HPT COOLING CURVE :
HPT CASING COOLING CURVE
Set withdrawn on Dt. 27/12/2015 AT 18:50Hrs.Barring stop on dt.01/01/2016, AT 02:45Hrs.Average
rate of cooling 3.20C per hour.
26
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 540
50
100
150
200
250
300
350
400
450
500
HPT TOPHPT BOTTOM
HPT Casing top / bottom cooling temp ( 0 C ) :
Sr.No. Hrs. TOP Bottom Sr. No Hrs. Top Bottom
1 0 463 448 19 36 293 260
2 2 451 434 20 38 284 252
27
3 4 438 420 21 40 277 244
4 6 426 404 22 42 270 237
5 8 417 385 23 44 262 230
6 10 409 374 24 46 255 223
7 12 400 363 25 48 248 217
8 14 391 352 26 50 241 211
9 16 383 347 27 52 234 204
10 18 375 338 28 54 227 198
11 20 367 329
12 22 358 320
13 24 349 311
14 26 341 302
15 28 332 293
16 30 321 288
17 32 314 276
18 34 307 268
PROBLEMS FACED DURING OPERATION:
TURBINE SIDE :
1) SAC-5A, DIS NRV PASSING
2) SAC-5B, SAFETY VLV LEVER NOT AVALABLE
28
3) SAC-5C, BELTS LOOSE
4) IAC-5A OIL LEAKAGE FROM FIY WHEEL SHAFT
5) IAC-5B,SOUND FROM NRV
6) AIR WASHER -1A, SAFETY GUARD N.A.
7) ALL COMPR ACW VLV REQ LUBRICATION
8) AIR DRYER BLOWER NO-2,HAVING VIBRATION & ABNORMAL SOUND
9) BOILER FILLING PUMP U5 & U6 HAVING GLAND LEAKAGE
10) COMPR SV -3 AIR LEKAGE FROM PLUNGER
11) AIR DRYER 4WAY VLV REQ SERVICING
12) MDBFP-5C,R/C VLV BONET LEAKAGE
13) MDBFP-5C,BOOSTER PUMP MECH SEAL STEAM ,WATER LEAKAGE
14) MDBFP-5C,BOOSTER PUMP END DROP BY DROP OIL LEAKAGE
15) MDBFP-5C R/H & S/H SPRAY NRV PASSING
16) CEP-5B, HAVING STUFFING BOX LEAKAGE
17) MAIN CRH LINE,IMPULSE LINEABOVE MAL STATION HAVING LEAKAGE
18) EX-32,VLV SEAL WATER LEAKAGE FROM ACTUATOR
19) CEP-5A,5B,5C SUCTION LINE DRAIN TO BE MODIFIED
20) VACCUME PUMP -5A SEPERATOR TANK VENTGUARD N.A.
21) GTR –B PH ,ACW I/L STRAINER HOLE OBSERVED
22) MOT COOLER NO-2,HAVING DROPWISE LEAKAGE FROM FLANGE
23) MS ATMOSHERIC DRAINS VLV 3NOS PASSING
24) ALL MAL STATION ISOL VLV & MOTORISED VLV NEED SERVICING
25) CD-31 & 34 VLV DROPWISE LEAKAGE FROM BONET
26) MDBFP-5D ,WORKING COOLER CHOCK UP
27) PRIMARY WATER PUMP STN RASIN TANK I/L VLV PASSING ,NOT ISOLATES WHILE RASIN
CHANGEING
28) G.D. PUMP NO-1,DIS VLV LEAKAGE
29) G.D.PUMP NO-1.DIS LINE LEAKGE NEAR FLANGE
30) MOT COOLER I/L & O/L ACW LINE VENT VLV NEED REPLACEMENT
31) MD BFP-5C,SH SPRAY LINE DRAIN VLV PASSING
32) MDBFP-5C,HAVING LEAKAGE FROM MAIN PUMP BODY FLANGE
33) MDBFP-5D,MECH SEAL COOLER CHOCKUP
34) EX- 10 VLV IN OPERATIVE35) EX – 6 VLV IN OPERATIVE36) TDBFP-5B,MAIN PUMP HAVING HIGH VIBRATIONS AS PER CMC REPORT
29
37) PROVISION OF FIRE FIGHTING WATER FOR U5 COMPR OPERATION
ODP-II SIDE DEFECT: 1) CCW PUMP SUMP MAKEUP VLV (OLD) NOT WORKING2) CCWPH PNEUMATIC MAKEUP VLV JAM3) ACW PUMP R/C, DIS VLV HAMMERNG SOUND4) CCW-5B PUMP, DIS BFV NOT OPENING ON AUTO MODE5) COOLING TOWER -5A & 5B RISER VLV JAM6) CCW-5C PUMP GLAND FOLLOWER DAMAGE.
EM-II SIDE DEFECTS :
1) 5CWXA & 5CTXA TRANSFORMER OIL GAGE FAULTY (LVL NOT SEEN)
2) 5CWXA TRANSFORMER TAP CHANGER TANK OIL LVL NOT SEEN
3) COOLING TOWER TRANSFORMER AREA POOR LIGHTING
4) COMPR BKR PANEL (ALL) LOCK KEY JAM
5) BUS DUCT DRYER TOWER HEATER NOT WORKING
6) ALL GTR,UAT,STN TRANSFORMER GAGE GLASS NEEDS CLEANING
I&C-II SIDE DEFECTS :
1) BRG DE SIDE TEMP GAGE FAULTY
2) CCW-5A, 5B COLD AIR TEMP GAGE N.A.
3) ALL IAC & SAC DIS PRESS GAGE REQ CALIBRATION
4) SERVICE AIR CCW-5B,MOTOR RECIVER TANK PRESS GAGE FAULTY
5) CONDENSER I/L & O/L TEMP & PRESS GAGES REQ REPLACEMENT
6) BUS DUCT DRYER TEMP & PRESS GAGES NEED CALIBRATION
7) GD PUMP DIS LINE PNEUMATIC VLV NOT OPERATING ON AUTO
8) H2 PRESS GAGE AT LOCAL REQ CALIBRATION
9) HOT WELL TEMP GAGE RHS NEED CALIBRATION
10) EX-10 VLV , NOT WORKING ON AUTO
11) MAIN TG EHG HAVING HUNTING
ET-II SIDE DEFECTS
1) IAC-A SAC-A, ANNOUNSATION N.A.
2) GT-5, CW FLOW LOW ALARM FAULTY YET PERSIST ON CUP-19
3) GT COOLER TROUBLE FAULTY ALARM ON CUP-19
30
4) BUS DUCT DRYER HEATER NOT WORKING
CM SIDE DEFECTS :
1) 5CTXA AND 6CWXC TRANSFORMER SLAB LEAKAGE ABOVE DUCT
2) ACW & CCW PUMP HOUSE TERES LEAKAGE
3) TERES DRAIN PIPE NEAR H2 ROOM ,HEAVY LEAKAGE ON LIGHING PANEL
F/F SIDE DEFECTS :
1) F/F VLV ABOVE HOTWELL MAKEUP STATION HEAVY LEAKAGE.
BOILER SIDE : 1. A-4 PIPE FROM FURNANCE HEAVY LEAKAGE AND FLAME COMING OUTSIDE.( SPARK)
2. WIND BOX DUCT LEAKAGES AT RHS/LHS. ALL CORNOR EXP.JOINTBOILER INSULATIONS
DAMAGED AT CORNERS, ESPECIALLY AT 23 MTRS UNIT #6 SIDE AND AT OVERFIRED
DAMPERS (ALL CORNERS), CONTINEOUS ASH COMING OUT OF FURNACE AND GETTING
ACCUMULATED AT CORNERS.
3. ESP HOPPER D31– FOREIGN MATERIAL.
4. DRUM VENT LINE PUNCTURE
5. DRUM VENT B-56, B-72 JAM / INOPERATIVE.
6. SH DRAIN STATION DRAIN V/V GLAND LEAKAGES – 3 NOS.
7. SOOT BLOWER FALNGE JOINT GASKET HEAVY LEAKAGES 29,31,64.
8. SOOT BLOWER FALNGE JOINT GASKET LEAKAGES 23,51,54,55,61,69,85,88,103
9. ESP FIELD 4D2. 2A1, 1D2, 4B1, 1A1, 1A2 – NEED INTERNAL INSPECTION
10. CRM 1A SHAFT SHIFTED/JAM
11. CBD V/V AT 23 MTRS GLAND LEAKAGE
12. PAH 5A & 5B –HOT AIR LEAKAGE FROM MANHOLES & EXPANSION JOINTS
13. OIL GUN AB3 STEAM ISOLATING V/V BONET LEAKAGE
14. ISO V/V TO SH SPRAY V/V SS12 BODY LEAKAGE
15. FO STATION ATOM STEAM TRACING LINE V/V GLAND LEAKAGE
16. BCW PUMP NO.1 COOLING LINE V/V GLAND LEAKAGE
17. ISO V/V TO RH SPRAY V/V R11 BODY LEAKAGE
18. ALL CLINKER GRINDERS NEED INTERNAL INSPECTION
19. SEAL TROUGH HAVING LEAKAGE ABOVE C/G 1B, 2A & 2B
31
20. C/A TANK NO. 1 & 2 WALKING GRILL BROKEN
21. C/A FLUE GAS HOPPER NO 3 & 4 - RAILING & GRILL BROKEN
22. C/A TANK NO. 1 - TEALEPIECE CHOKEUP.
23. BV C/A TANK NO. 1 - TEALEPIECE CHOKEUP.
24. ALL COLD AIR DAMPERS TO BE PROVIDED WITH CHAIN & HANDLE & MAKE THEM FREE
25. ALL B/ASH MANUAL HYJECTOR V/V NEED TO MADE FREE
26. C/M 5E LOP OIL SEAL LEAKAGE. C/M 5A & 5B HAVE MINOR LOP LEAKAGE.
27. C/M 5B J2 ASSY SHAFT SEAL LEAKAGE
28. BOILER FILLING STATION ALL V/V NEED SERVICING
29. SLURRY TRENCH STRAINER NEEDS TO BE REPLACED
30. ID FAN A,B,C,D ACW LINE VALVE INOPERATIVE
31. ID FAN A DUCT LEAKAGE AT LOWER SIDE NEAR INSPECTION DOOR
32. ID FAN D DUCT LEAKAGE AT UPPER SIDE NEAR INSPECTION DOOR
33. ID FAN A LOP II OIL LEAKAGE THROUGH INSPECTION GLASS
34. ID FAN C OIL LEAKAGE THROUGH OIL LEVEL GAUGE
35. ALL ID FAN INSPECTION DOOR ROPE NEEDS TO BE REPLACED
36. SUMP SELECTION VALVE FOR BOTTOM ASH, FLY ASH NOT FREE
37. BOTTOM ASH, FLY ASH SUMP SELECTION VALVE A,B,C SERIES NEEDS SERVICING
38. ASH WATER MAKE UP VALVE PASSING
39. ESP HOPPER C-11,C-21 HOPPER ASH LEAKAGE ANS INPEC. DOOR CHECKING REQ.
40. SIDE HEAVY LEAKAGE AND HEATER BELOW LINE STEAM AND OIL LEAKAGE
41. LDO/HFO TANK SCALE PATTY PROPER FITTING . SCREW FITTING REQ.
42. TANK HEATING MAIN AND TANK HEATING INDIV. V/V PASSING REPL. AND CHECKING REQ.
43. FD FAN-A/B, PA FAN-A/B ACW LINE PRESSURE AND TEMP. GUAGE ISO. V/V NOT
OPEN/CLOSE/JAM ALL PUMP ACW INLET AND OUTLET V/V SERVICING REQ.
44. SUPER HEATER ALL DRAIN V/V JAM SERVICING REQ. AND MAKE FREE
45. PAH-5A/5B,SAH-5A/5B ACW LINE TEMP.AND PRESSURE ISO. JAM AND REPL. REQ. AND AIR
HEATER ALL ACW INLET AND OUTLET AND DRAIN V/V JAM NOT OPEN/CLOSE REPL. REQ
46. GD-6A1/6A2,6B1/6B2,6C1/6C2,6D1/6D2 AND 7A/7B/7C/7D SERVICING REQ.
47. NEW FITTING DUCT HOPPER NOT INOPERATIVE I&C=II U=5 HEAD TOLD NO INFORMATION
AND NOT DONE PROTOCAL
48. SUPER HEATER SPRAY DRAINS V/V ARE PASSING AND NOT OPEN/CLOSE JAM AND REPL.
REQ.
49. C/M-5A TO 5H HOT AIR GATE SEAL PASSING AND DUCT LEAKAGE, C/M 5B - HOT AIR DUCT
RUPTURED.
32
50. ALL ID FAN ACW LINE DRAINS V/V AND INLET AND OUTLET V/VS ARE JAM AND THREAD
DAMAGED SERVICING AND REPL. REQ.
51. GH ELEVATION GH-2/3 OIL GUN NO PROPER SPACE TO BE FIT OIL GUN AND RAILLING
CUT REQ.
52. ALL DRUM VENT AND STARTUP VENT SERVICING REQ.
53. F.O HEATING U=5 MAIN V/V AND INTER CONNECTION V/V AT OHP JAM MAKE FREE
54. PAH-5A/5B SAH-5A/5B AIR HEATER FLUSHING LINE ALL V/VS ARE JAM NOT OPEN/CLOSE
AND SAH-5A FLUSHING LINE HEAVY LEAKAGE NEAR AIR HEATER
55. GAS DAMPER GD-4B2 UNDER PERMIT ABOVE ONE YEAR GD-4A1,4A2,4B1 FULL NOT OPEN
CLOSE FROM LOCAL AND LEVER NOT ENGAGE SERVING REQ.
56. BSWBOOSTER PUMP-5A NRV PASSING AND SERVING REQ.
57. PRI GAS INLET DAMPER GD1A - INOPERATIVE FROM DESK
58. C/M 5D & 5F HAVE ONLY ONE LUB OIL COOLER
59. BOTTOM RING HEADER INSULATION ESP SIDE - SHEETS HANGING
60. HFO PUMP 5C - STEAM LEAKAGE NEAR SUCTION V/V
61. IMPULSE LINE OF ECONOMISER FEED LINE HEAVY LEAKAGE
62. ID FAN A,B,C,D - DROP BY DROP OIL LEAKAGE FROM PRESSURE GAUGES
63. BCW PUMP 5A/5B/5C ITS ACW COOLER INLET AND OUTLET V/V JAM SERVICING REQ.
64. PAH-5A/5B SAH-5A/5B ITS PRESSURE GUAGE AND TEMP. GUAGES LOP CALIBRATION
REQ.
65. ACW FD-5A/5B PA FAN-5A/5B PRESSURE AND TEMP. GUAGES FAULTY AND CALIBRATION
REQ.
66. C/M-5A TO 5H MOTOR TEMP. GUAGES ARE FAULTY AND CALIBRATION REQ.
67. ESP PASS -A/B/C/D FIELD AND CRM/ERM PANEL BOX DISPLACED AND GROUND
POSITIONCALIBRATION AND REPL. REQ.
LIST OF THE MAJOR WORKS PLANNED DURING ANNUAL OVERHAUL:
BOILER MAINTENANCE SECTION :
1) BOILER PRESSURE PARTS:
33
a) Repairs of Water Wall :
1. Tubes with more than 25% erosion will be replaced.
2. Tubes with more than 25% erosion will be replaced.
3. Sacrificial S.S. shields are put in coal/Air Carried out and also at 9 M level.
4. Welding of trapezoidal wear bar between two tubes of side wall near neck tubes.
5. Repair of Z panel hangers in cat house
6. Attending air ingress through Z panel scallop bar
7. Replacement of damaged insulation in SB and pent house area
8. Metallurgical analysis of WW tubes for deposit analysis.
b) Wall RH :
1. Eroded RH Bends and liners will be replaced.
2. Alignment of wall RH tubes near div. Panel will be done.
c) Repairs of Div.Panels : 1. Replacement of eroded S.C. spacer tube.
2. Fitting of flexible connectors.
3. Replacement of distorted girdling loops and fitting of flexible connectors.
d) Repairs of PSH :1. Radiography of site welding joints in ckt no 1 of thick 9.5 mm
2. Replacement of eroded and distorted tubes.
3. Refitting of damaged flexible connectors
4. Replacement of SC spacer
5. Welding of SS pads.
e) Repairs of RH (rear) :1. Position of mechanical binders in rear RH will be changed to avoid further fretting
2. Visual Inspection of RH outlet header stubs for overheating
3. Alignment of coils no 41 to 46 without cutting the tubes
34
f) Repairs of RH (Front) : 1. Inspection steam cooled spacer tube and its connectors for fretting
g) Repairs of screen tube :
1. Replacement of eroded tubes and bends at bottom and top.
h) Repairs of LTSH :
1. Lifting of assay no 1,3,56 and 58 for inspection in upper LTSH.
2. Eroded tubes and bends at inlet and terminal will be replaced as per thickness report.
i) Repairs of ECO (upper) :1. Lifting of assy no 1,3,63,65 for inspection
2. Lifting of coils with misaligned tubes
3. Eroded tubes and bends will be replaced.
4. Inspection of eroded 90 deg. bends near header of coil no 1, 2, 3, 128, 129, 130
j) Repairs of ECO (middle and lower) :
1. Lifting of coils with misaligned tubes
2. Eroded tubes and bends will be replaced.
3. Repairs of cassette baffles
h) Repairs of steam cooled wall :
1. Inspection of bends of manholes and LRSB openings and replacement of eroded bends
35
2) Other : a) Inspection of drum :1. Inspection and cleaning of drum internally.
2. Checking of phosphate dozing line, feed line for any damage.
b) Inspection of bottom ring header : 1. Inspection of orifices from bottom ring header, after blowing air and after hydraulic test for any
blockage.
c) Repairs in pent house :
1. DP and MPI testing of all stub welding of Pl. S.H. inlet header will be carried out.
2. Sealing ropes of peep holes and manholes will be replaced.
3. Replacement of gaskets of peep holes and manholes
4. Leakages through skin welding of roof will be attended by replacing warped skin plate.
5. Cleaning of Sky climber rope opening in pent house.
d) BCW P umps : 1. Cleaning of coolers- 3 nos
e) Servicing of safety valve :
1. Servicing of Drum, SH, RH, PRDS, SB safety valves
2. In-site seat cutting if required
3. Pressure testing of safety valves
f) Servicing of HP valves :
1. Servicing of SH spray Isol. Valves- 8 no’s
2. Servicing of RH spray Isol. Valves- 8 no’s
36
3. Servicing of SH drain valves at 26 m- 16 no’s
4. Servicing of drum vents, SH vents, RH vents, Boiler drain valves at 0 m
5. Servicing of PRDS inlet isol. Valve, NRV and ASP16
6. Replacement of gland packing of 2" valves- 50 no’s
7. Replacement of gland packing of 1" valves- 50 no’s
g) Servicing of burner tilt : 1. Servicing of burner tilt
2. Synchronization of all coal and air tips will be ensured.
3. Freeness of burner tilt operation for ± 30 degree will be ensured.
h) Servicing of APH :1. Inspection of guide bearing in position.
2. Inspection of support bearings in position
3. Replacement of all radial and bypass seals.
4. Replacement of axial seals
5. Cleaning of all baskets by hydro jetting
6. Replacement of rotor angle, T-bar, support grills
i) Servicing of dampers / gates : 1. Repair of APH inlet and outlet gas dampers
2. Servicing of APH inlet and outlet air dampers
3. Servicing of actuators-16 no’s
j) Servicing of ID,PA,FD Fans
1. Inspection of bearings.
2. Checking bearing clearances.
37
3. Servicing of IGV.
4. Replacement of PA Fan-A both bearings along with housing.
5. Servicing of PA/FD discharge dampers/gate
3) ESP:
a) Repairs of Bottom Ash Hopper :
1 Inspection& repairs of damaged refractory.
2. Inspection & repairs of SS wire mesh.
3. Inspection & repairs of SS seal plates.
4. Inspection & repairs of refractory cooling water system.
5. Inspection & repairs of hopper flushing nozzles.
6. Repairs of bottom ash hopper by welding.
b) Servicing of ash feed gates, bottom ash hyjectors& HP / LP Water Valves.
1. Inspection & repairs of ash feed gate.
2. Overhaul of bottom ash hyjectors.
3. Overhaul of SG roll clinker grinder.
4. Servicing of HP & LP water valves.
5. Replacement of damaged HP & LP water pipe lines.
c) Servicing / Repairing of Corse Ash Evacuation System
1. Servicing of feeder ejectors.
2. Gland 6 mm:
3. Valve plates:
4. Consumable set:
5. Jet pump spares
6. MSERW Pipes 200, 100, 80 NB
d) Servicing / Repairing of Fly ash Evacuation System :
1. Servicing of feeder ejectors assembly.
2. Servicing of feeder ejectors
38
3. Gland 6 mm
4. Valve plates
5. Consumable set:
6. Replacement of damaged HP water Pipe lines.
e) Repairs of Flue Gas duct from Eco outlet to ESP inlet area (LHS & RHS). Removal of ash & debris from duct & stack hopper :
1. MS plates 3.15 to 12 mm thick
2. Bracing pipes of various Dia.
f) Overhauling / Repairs of complete Electrostatic Precipitator :1. CRM shafts
2. CRM Hammers
3. ERM shafts (V/H): Sets each.
4. ERM hammers
5. Set ring
6. Shock bar guide angle
7. Shock bar assembly
8. Inner arms
9. Plain brgs
10. Bush bearings
11. Thrust bearing
12. Cup Washers
13. Sleeve Tube 50mm.
14. Sleeve Tube 40 mm.
15. GD Screens.
g) CFD of flue gas & hot gas duct & rectication thereoff : i) Diversion plates, chemical bonded refractory.
h) Replacement of Metallic Expansion Joints of flue gas duct : 1. Eco O/L, PAH Horizantal duct, ESP I/L duct
39
i) Replacement of Fabric Expansion Joints of flue gas duct : 1. APH vertical duct, PAH Horizantal duct, APH O/L horizantal duct
j) Replacement of Worn out coal pipes and bends :
1. Proper scaffolding for replacement of pipes and bends.
2. Replacement of coupling rubber gaskets
k) Servicing & replacement of classifier vanes :1. Proper scaffolding
2. Inspection of vanes
3. Replacement of vanes
4. Servicing of vanes
l) Servicing of coal mill drive air system :
1. Removal of bowl hub skirt.
2. Check the gap between inner ring and outer ring and fitment as per requirement.
3. MDV flap
m) Servicing / Repairing HAG/CAD/ actuators /CF gates / seal air fan filters-
1. Servicing / repairing of hot air gates and dampers.
2. Servicing / repairing of cold air gates and dampers.
3. Servicing / repairing of CF inlet and bunker outlet gates.
4. Cleaning of seal air fan filters.
4) CAPITAL OH of coal mill & coal feeder of 5A/5B/5C/5F
TURBINE MAINTENANCE SECTION
40
1) HP TURBINE OVERHAUL:
1. Removal of Spray Insulation & Piping
2. Dismantling of HP module .
3. Re-Assembly
4. Steam Flow Path Clearance Checking
5. Assembly Checks and Correction
2) IP TURBINE OVERHAUL:
1. Removal of Spray Insulation & Piping
2. Dismantling of IP Module & Dismantling checks
3. Alumina Blast Cleaning of Rotor and casing
4. IP Gland seal clearance checking & setting.
5. Steam Flow Path checking
6. Inspection of Blades and Fact Finding
7. Assembly checks and correction
8. Assembly of IP module & Restoring of piping.
9. Checking & Correction of Pipe Pull in HRH pipes.
3) LP TURBINE OVERHAUL :1. Dismantling of LP & Dismantling Checks
2. Removal of rotor, inspection & Alumina Blasting
3. DPT & MPI of Free Standing Blades of LP
4. NFT of Free Standing Blades of LP
5.Casing Alumina Blasting
6. Inner-Inner casing Ovality & Steam Flow Path Check
7. Placement of Rotor in Position, checking of clearance
8. Box up of LPT turbine
9. LP Gland Box Clearance adjustment of Labyrinth
10. Hot well inspection
4. GENERATOR & EXCITER :
41
1. Generator Rotor Thread out .
2. Leakages test of Hydrogen System
3. Inspection of Seal Bearing
5. TURBINE VALVES : 1. HP Stop & Control Valve
2. IP Stop & Control Valve
3. LP Bypass Stop & Control Valves
4. CRH & Exraction FCNRV's
6. HP BYPASS VALVE SERVICING : 1. Valves Servicing and Internal inspection
7. GOVERNING SYSTEM : 1. Setting of Governing System Charecterstics
2. All Accumalators N2 Pressure Checking & Filling
8. BEARING (7 NOS ) : 1. Dimensional checks of journal /bearings/keys etc
2. Bearing UT & DPT, Bearing Bedding Inspection
3. Oil Catcher Fins Renewal
4. Replacemnt of Jacking Oil Hoses
5. Bottom Saddle & Torus piece checking & correction
6. Bearing no. 5 ,6 & 7 -IR cheaking of bearing insulation
7. Check Labyrinth Rings and replace seal strips
9. LUB OIL SYSTEM : 1. Bucket strainer cleaning & Lub Oil filter cleaning
2. JOP ilter Cleaning / Replacement.
10. MOT COOLER : 1. Cooler Cleaning.
42
11. MAIN OIL PUMP (MOP) : 1. Inspection and Overahuling of MOP.
2. Checking of various parts of MOP for clearance.
3. Checking of Bearing and matching
12. COOLERS : 1. H2 cooler Cleaning & Hydraulic testing.
2. Exiter Coolers Cleaning & Hydraulic testing.
13. HPT/IPT & VALVES : 1. Spray insulation of HPT/IPT & Valves
14. HRH / MS STRAINER : 1. Inspection & Bonnet Seal Replacement
15. COOLERS CLEANING & HYDRAULIC TEST : 1. MDBFP Coolers ( 8 Nos. )
2. TDBFP Coolers ( 4 Nos. )
3. Vaccum Pump Coolers ( 2 Nos. )
4. Primary Water Coolers( 3 nos. )
5. Seal oil Coolers ( H2+ Air Side ) 4 Nos
6. GTR Coolers ( 6 Nos. )
7. FRF Coolers( 2 Nos. )
16. CONDENSER TUBE CLEANING : 1. Cleaning By Bullet Shot
2. Gravity Test
17. HP VALVES / NRV INSPECTION & SERVICING :
43
1. MS & HRH strainer drain valves (MS-502, 504, 506 & 508 HR - 113, 502, 504, 506 & 508 , MAL
11,12,13,14, 22,26,28,34,54,65,66) ,MS 104.
2. HP Heater Extraction Valves ( EX : 1A & 2A) & EX-1,2,3,4,5,
3. BD ( Iso.), BPE-1 & 2, HPB 101 & 102 FD : 56 & 58.
4. AS-2, 3, 4, 9, 10, 11 & 12.
5. TDBFP Valve EX27,28,29,30, 31 & 32.
6. Passing Valves as per defect list.
18. ACW LINE VALVES SERVICING : 1. H2 Cooler I/L & O/L ( 8 + 1 nos. )
2. Exciter cooler I/L & O/L ( 4 nos. )
3. Vacuum Pump Coolers I/L & O/L ( 4 Nos. )
4. MOT coolers I/L & O/L ( 4 nos. )
5. TDBFP A & B coolers ( 16 nos. )
6. MDBFP C & D coolers main I/L & O/L (4nos. )
7. Seal Oil Coolers ( H2 + Air ) 8 nos.
8. SAC / IAC ( 21 nos )
9. LPBP Water Injection ( 5 nos. )
10. FRF coolers ( 4 + 1 nos. )
11. PW Coolers ( 6 + 1 nos. )
12. GTR R-Y-B I/L ( 9 nos. )
19. FEED STORAGE TANK ,DEAERATOR INSPECTION: 1. Inspection and cleaning of FST & Deaerator
2. Checking of Deaerator Nozzle and replacement
20.HP & LP HEATERS : 1. Internal inspection, Conducting Tube leakage test
21. CEP -5A : 1. Pump Overhaul
22. CEP RC VALVES :
44
1. Recirculation Valve Internal Inspection
23. ALL BFP'S VALVE SERVICING : 1. Suction Valve
2. Superheater Spray Valve
3. R/H Spray Valve
4. TDBFP-5A & 5B RC valve replacement
5. TDBFP-5BMain
6. Pump Cartridge Replacement
24.VACUUM PUMP 5A : 1. Pump Overhaul
25.TDBFP A & B : 1. Tank Cleaning
2. All AOP & JOP Filter Cleaning
OUT DOOR PLANT MAINTENANCEA. VALVE REPLACEMENT/SERVICING:1. A, B Series suction KGV servicing /Replacement work
2. Fly ash Sump Selection Valve replacement/servicing.
3. Bottom ash Sump Selection Valve servicing/replacement.
4. RAW water inlet valve 500 NB servicing/replacement.
5. RAW water inlet valve 350NB servicing
6. ETP v/v servicing
7. Series drain Valve replacement/ servicing work
8. Seal water line, cooling water line valves replacement/ servicing work
a) HPAWP/LPAWP Inlet & outlet valve servicing work
b) HPSWP/LPSWP Inlet& outlet valve servicing work
45
B.CLEANING WORK : 1. Ash water Tank cleaning work
2. Seal water Tank cleaning work
3. Drain sump Cleaning Work
4. Ash Surry sump cleaning work
C.FLUSHING NOZZLE REPLACEMENT :
1. Bottom Ash sump, Fly Ash Sump, A, B, C sump, flushing nozzle And its line replacement work
D. STRAINER AND NRV SERVICING :1. HPAWP/LPAWP NRV & strainer servicing work.
E. GRATING AND SUPPORT REPLACEMENT : 1. A, B, C sump damaged grating replacement work
2. Bottom ash & Fly ash trench grating Replacement work
3. Various Pipe support replacement/ strengthening work
F. PIPES REPLACEMENT: 1. 5A line- sump suction bends checking, suction pipe replacement, ASDP-3 expander to bend & bend to
reducer replacement, ASDP-4 bend to bend repl.
2. 5B line- sump suction bend checking, sump suction pipe replacement, BSDP-1 HP repl, BSDP-2 HP & VP repl, BSDP-3 expander to bend, bend to reducer repl, BSDP-4 bend to bend repl.
3. 5C line-sump suction bend checking, sump suction pipe replacement, CSDP-1 HP & VP repl, CSDP-2 HP & VP repl, CSDP-3 expander to bend, bend to bend, bend to reducer repl, CSDP-4 expander to bend, bend to bend repl.
4. Seal water pump eroded line replacement work
5. Seal water, cooling Water, air system rusted line replacement work
G.CT FAN O/H :1. CT FAN O/H
2. CT FAN GB O/H
46
H. CT POND :1. Work of cleaning of CT pond area, outlet strainer of CT Pond Repairing.
2. Work of both side nozzle replacement which are missing & nozzle cleaning of tower 5A & 5B
3. Overhauling of CCW 5A
4. ACW Pumps Thrust bearing oil replacement 5A, B, C
5. CCW Pumps Thrust bearing oil replacement 5B, C, D
6. CCW Pumps gland replacement 5B, C, D
7. ACW Pumps gland replacement 5A, B, C
8. CCW Pump Butterfly valve Hydraulic system servicing & power pack oil replacement 5B, C, D
9. ACW/CCW pumps suction strainer repairing & fitting work
10. ACW/CCW SUMP CLEANING WORK and hydro cone checking
I. VALVE SERVICING/REPLACEMANTWORK: 1. Work of ACW recirculation / outlet line's valves, discharge line valves, vent valve checking,
repairing/replacement
2. Work of repairing /replacement of riser valves of cooling tower 5A & 5B
3. Work of checking, repairing/replacement of Blow down valves of CT 5A & 5B
4. CCW pump butterfly v/v seal ring replacement
J. SUPPORT AND APPROACH PROVIDING: 1. Work of CT fan cells approach way railing & gear box protection cage railing repairing work
2. Drift eliminator cleaning
3. CT Fan foundation frame replacement/ reconditioning CT Fan
4. Hot water asbestos cement (broken) pipe replacement
5. Hot water pipe Header painting & riser v/v painting
6. Work of cleaning of Hot water Basin of cooling tower Unit-5 at cstps, Chandrapur.
ELECTRICAL MAINTENANCE1. GENERATOR / GEN. EXCITER : Preventive Maintenance of Generator PT cubicle & NGR.
PMG & Pilot excitor
Diode wheel assemble
Preventive Mainenance of Generator PT cubicle & NCR"
47
2. BATTERY MAINTENANCE: P/M & Capacity Test of +/- 24V G1/G2 Battery sets.
P/M & Capacity Test of Station Battery set for battery set1&2 and UPS Battery set.
3. HT TRANSFORMERS: A. 400KV Connections : 400KV side HV bushing & LA connection tightness of GTR-5R/5Y/5B.
B. Internal inspection of GTR 5Y, UAT-5B & 5D : Complete draining of oil.
Internal inspection through inspection window carried out& attending defect if any found.
Replacement of MOG along with float, gauge glass, PRV.
Replacement of gasket & activated alumina if required.
Oil Filteration work.
Assistance in cooler testing if required.
External cleaning of surface,Applying first coat of red oxideand two coat of epoxy paint, writing
identification/name plate.
Replacement of rubber bellow if required.
C. Oil filteration of GTR-5R, UAT-5A,5C,SAT-3B: Oil folteration arrangement and filteration of oil to be carry out.
Leakage attending or attending defect if any found.
Oil Filteration
Assistance in cooler testing if required.
External cleaning of surface.
Replacement of rubber bellow if required.
D. P/M of X'mers , M. B. & NGRs of GTR-5R/ 5Y/ 5B, UAT-5A /5B/ 5C/5D, Stn-3, SAT 3A/B: Tightness checking of HV / LV connections
Silica gel replacement.
Oil topping up , if required
Oil lekage attending , if any
48
Rubber bellow replacement , if required
NGRs / MBs Preventive maintainance.
E. Painting of GTR-5R,5Y,5B : Cleaning of transformer .
Painting of transforrmer as per scope of work.
F. Preventive Maintenance of Generator & UAT Bus Duct and painting of Generator and UAT bus duct outside A-axis:
Opening and closing of inspection window covers.
Checking & cleaning of insulators, rubber bellows and replacement if required.
Sealing of unwanted openings using sealant.
External & internal cleaning of bus duct.
Cleaning and painting of outer surface with one coat red oxide and two coat of paint
G. Work of replacement of black metal of GTR-5R,5Y,5B;UAT-5A,5B,5C,5D; ST-3;SAT-3A,3B Removing of old black metal
Cleaning of surafce , removing of bush tree
Spreading of new black metal of existing size.
Dumping of removed black metal as per instruction of site incharge.
H. P/M of Dry Type Transformer 5XA, 5XB, OXA1, OXA2 LXA1, LXA2 : Opening of doors of the X'mer
Cleaning of X'mer with air
Tightness checking of HV / LV connections
including tap changer
Rubber bellow replacement, if required
NGRs / MBs Prev. Maint.
IR measurement
49
4. HT MOTORS: A. Overhauling of HT motors ID fan 5A,5D ; PA FAN 5A ; FD FAN 5B : Removal of power cable, earthing connections, control cables etc
Shifting of motor to repair bay.
Dismentalling of motor completely
Replacement of bearings, if required.
Stator & rotor varnishing.
Box up of motor completely
Shifting of motor to the location.
Alignment of motor with the gear box
Normalization of motor & trial.
Coal mill motors 5A, 5B, 5F.
B. P/M of HT Motors :COAL MILL- 5C,5D,5E, 5G, 5H; BCW-5A, 5B, 5C; CEP-5A/5B/5C; MDBFP 5C,5D; ID 5B, 5C:
Cleaning & Connection Tightness checking at motor and switchgear end& rectification, if required.
IR value measurement
Silica gel replacement of power JB .
C. Cooler Cleaning of HT motors, PA-5A, 5B; MDBFP-5C, 5D: Dismantling of I/L & O/L pipelines.
Removal of coolers with Hydra or EOT crane.
Cleaning of coolers with brush, cleaning agent.
Hydraulic testing of cooler.
Restoration of cooler along with pipelines.
50
5. LT MOTORS A. Overhauling of critical LT motors SAF-5A,5B; Vaccum pump-5A; AC scanner fan;
control fluid-5A,5B; AC-JOP; Main Turbine AOP-1,2; SOP-1,2; PAH 5A/5B 1,2; SAH5A/5B 1,2; TDBFP AOP 5A/5B 1,2:
Shifting of motor to repair bay.
Removal of power cable, earthing
connections, control cables etc
Dismentalling of motor completely
Replacement of bearings, if required.
Stator & rotor varnishing.
Box up of motor completely
Shifting of motor to the location.
Alignment of motor with the gear box
Normalization of motor & trial.
B. Coal Feeder motor overhauling works along with DE side pinion hrading and check nut provision:
Removal of power cable, earthing
connections, control cables etc
Shifting of motor to repair bay.
Dismentalling of motor completely
Replacement of bearings, if required.
Stator & rotor varnishing.
DE side pinion check nut provision works.
Box up of motor completely
Shifting of motor to the location.
Alignment of motor with the gear box
Normalization of motor & trial.
C. Preventive Maintenance of LT Motors of unit # 5 :
51
Cleaning & Connection Tightness checking at motor and switchgear end & rectification , if required.
6. HT/LT SWITCH-GEARS :A. P/M of Unit Board 5A, 5B,5C, 5D,5E: Cleaning of panels & Power Connection Tightness checking and rectification, if required.
Servicing of Breakers.
Replacement of faulty component.
IR measurement.
B. PM of 5PA , 5MA , 5MB, 5MC, 5MD, 5EMPA , 5ME, 5MG, Soot blower Boards: Cleaning of panels & Power Connection Tightness checking and rectification, if required.
Servicing of Breakers.
Replacement of faulty components.
IR measurement.
C. PM of DCDBbs ODA, ODB Boards Cleaning of panels & Power Connection Tightness checking and rectification, if required.
Servicing of Breakers.
Replacement of faulty components.
IR measurement.
7. AHP/ESP MAINTENANCE :
A. Maintenance of ESP A Pass, B Pass, C Pass, D Pass: Prev.Maint.of 5EPPA,5EPPB,5EPPC,5EPPD/ ACP panels
Prev.Maint.of ESP A-Pass/B-Pass/C-Pass/D-pass fields,hopper heaters / support & shaft
insulators heaters
Prev.Maint.of all ERM / CRM of A-Pass/B-Pass/C-Pass/D-Pass
Prev. Main. of 5EPXA X'mer/5EPXB X'mer/5EPXC X'mer/5 EPXD X'mer.
B. Retrofitting of 3.3 KV HV Breaker by HT contactor : Retroffiting work as per order.
52
C. Maintenance of AHP : P/M of 5AHS 3.3 KV BOARD
P/M OF 5AHPA 415 VOLTS BOARD.
D. Preventive maintenance of rectiformer: Checking of power connection & rectify if found defective.
Oil leakge arresting by tightening of gasket.
Replacement of HV bushing oil if found leakage .
Through Cleaning of rectiformers.
E. PM of ESP Heater along with replacement if required & preventive maintenance of ERM/CRM motors:
Checking of all ESP heater and replacement if required.
Cleaning of Insulator.
PM of all CRM/ERM motor and replacement if required.
8. COMPRESSOR ROOM :
A. Preventive Maintenance of DG set:
Cleaning of panels & Power Connection Tightness checking and rectification, if required
Servicing of Breakers.
9. LIGHTING / WELDING SUPPLY: Electrical supply to various Agencies woking for capital O/H of the unit.
INSTRUMENTATION & CONTROLSA. Removal, Servicing and Normalization of 16 Nos. of HEA Igniters with Power Cylinder, Limit
Switches and Igniter Transformer. Removal and restoration of 16Nos. HEA spark rod assemblies after Servicing, Repairing if Reqd,
Testing Healthiness of Spark Tip, HT Cable with Transformer & Limit Switches with remote Trials.
B. Removal, Servicing, cleaning, checking, calibration and Normalization of 28 Nos. of Flame scanners.
53
Removal, Servicing, cleaning, replacement of PCBs, sensing glass etc., checking healthiness of flame sensitivity, calibration and Normalization of 28 Nos. of Flame scanners.
C. Servicing of SADC Power Cylinder. Removal & restoration of 64 nos. SADC power cylinders after servicing of Positioners, Pilot assembly,
painting Stroke Calibration with remote joint trial. 8 nos. of air line filter regulators servicing & restoration ( 2nos. in each corner)
D. Mill O/L Temp. T/C’s checking, Thermo well checking , replacement if found faulty and both point availability/checking.
Removal , Cleaning , Re-mounting, Connection normalization of Mill O/L T/C’s with T/W’S. Cable laying for T/C – 2nd point.
E. Flushing of 100 nos. Impulse Line. Disconnection of instrument impulse pipe , Flushing & re-connection with Teflon tape.
F. Servicing of Bottom Ash / Burner Tilt / PA Fan guide vane power cylinder. De-linking, Removal, Dismantling, Servicing of Power Cylinder, Seal replacement, Assembling ,
Testing for Zero leakage’s with full air pressure.
G. TRB’s / TRT’s / JB’s cleaning, Painting Sealing, connections tightening & Broken TB’s replacement.
Cleaning and Painting of TRB’s / JB’s Broken T.B’s replacement connection tightening after rail cleaning.
H. Removal and Restoration of all corner solenoid/C/M HAG & reject gate solenoid along with tubing & leak isolating valve checking/ replacement.
Removal, cleaning and restoration of all solenoid valves along tubing of all corner-56nos. Removal, cleaning and restoration of all solenoid valves along tubing of C/M HAG-8no. Removal, cleaning and restoration of all solenoid valves along tubing of C/M RG sol-16no All leak/passing instrument isolating valves checking/ replacement.-100nos
I. Servicing of C/M’s HAG/ all corner solenoid, Limit Switches & air line, oil filter cleaning and oil top up.
Removal, cleaning & contact functional checking of L/S(16 no) Filter element removal, cleaning & fresh oil top up.
54
All corner solenoid- 56nos.
J. Servicing/ Calibration of Boiler and Turbine side control valves- 75 nos. Removal, Servicing , Remounting, Calibration of Stroke with PFT. servicing/cleaning and calibration of E/P converters, Air lock relays, Air filter regulators
K. Calibration of Servicing of Positioners, pilot assemblies, an lock relays, E/P converters, Air line regulators.1. C/M’S CAD/HAD – 16nos. Calibration of stroke with PFT& remote trial.1. Burner tilt.2. PA Fan vane
L. Servicing and calibration of ID/FD/PA/BCWP/ CWBP all instruments & protection trial. Removal, Servicing, Calibration. Re-mounting as per B/M ,T/M & E/M Schedule
M. Removal / Calibration & Re-mounting of Removal, Cleaning, Calibration(a) PA Hdr Press. Switches. Re-mounting after impulse line flushing(b) Furnace Press. Switches. Connections normalization & isolating manifold valve position normalization
N. Servicing of C/M’s Seal air valve power cylinders with Solenoids & Limit Switches Removal, Servicing Testing of Power Cylinders Servicing & Testing of Solenoids and Limit Switches
O. Removal & Normali-sation of Boiler side Instruments as per B/M – II , E/M – II requirement . Removal of Connections/ Instruments Normalization after clearance
P. Internal Inspection of O2 Probe & Replacement of guide pipes & V guards. O2 LHS/RHS disconnection removal, inspection. Replacement of Protective tube & V guard strengthening. Calibration
Q. Removal & Restoration of all elevation pressure gauges. Removal of all corners press gauges.
55
Cleaning of all gauges. Calibration of all Gauges.
R. Removal, mounting, laying, dressing & checking of SH/RH metal temp thermo-couples as per BM-II schedule.
Removing of T/C as per BM-II. Checking and Replacement if found faulty. Restoration after BM-II clearance Connection cleaning, tightening, signal checking upto panel.
Attending of all S/D defects /Modifications:-S. Calibration of critical and Non-critical Instruments as per List / Schedules – 200 nos. Confirm validity of MCAL/ SMCAL Removal; of Instrument & Cleaning Calibration & ISO Tagging Remounting & Normalization
T. Removal of ESP / Coarse Ash / FGDH / Economizer A/V & W/V Solenoid after B/M – II clearance
B/M – II Clearance & removal of Solenoids.
U. Removal, Servicing and painting of ESP/Coarse ash power cylinder. Servicing & Testing of Solenoids Removal cleaning, servicing, checking and painting of power cylinder. Re- installation of Solenoids after B/M – II clearance Local Remote Joint Trial. ESP all rows air filter regulators servicing & accumulator oil level top up.
V. Removal / Servicing & Remounting of AHP Ash water make up valves, series sump make valves, ETP valves, RC valves, suction valves solenoids as per ODP – II schedules.
Removal, cleaning / Servicing of Solenoids. Remounting & joint trial
W. AHP A/B/C Series & HP Ash water tank Level controller testing after Sensor Cable & bolt replacement
Removal of Old cables with bolts & replacement by new. Ckt testing & Protection trial
56
Calibration of all series seal Water Press Switches, HP Ash Water Disch. Press. Switches
X. Calibration of Bottom ash/PAH/SAH/FGDH/Economizer/ESP/AHP all instrument. Removal &cleaning of press. gauges. Calibration & tagging. Remounting & connection normalization.
Y. Calibration of Boiler drum press. Gauges. Removal, Cleaning & Calibration.
Z. ID/FD/PA/BCWP protection Trials
AA. Boiler protection Trial.
BB. Replacement/ Retrofitting of MOT and FRF tank Level Amplifiers with Cali-bration. Removal, Cleaning, Calibration of probe with amplifier units & tagging.
CC. Removal, Servicing/ Testing & restoration of HPT/ITP top/bottom & TSE thermocouples with T/W.
Removal, Cleaning & testing of T/C’S with T/W’S & Tagging. Restoration after T/M-II clearance.
DD. Removal, Cleaning, testing & restoration of LPT exhaust Hood T/C’S & RTD. Removal, Cleaning, testing, tagging & restoration after T/M-II Clearance.
EE. Disconnection of HP/IP stop & Control valves Limit switches & PFTS. Disconnection of HP/IP stop & Cv’s LS & PFT’s Restoration after T/M-II Clearance.
FF. Disconnection & removed of HP/IP ATT valves motors. Disconnection & Removal of ATT motors. Restoration after T/M-II clearance.
GG. Disconnection & removal of LPBP 1 & 2 stop control & water Injection Limit switches & PFT’S. Disconnection & Removal of Limit switches & PFT”S. Cleaning, testing & restoration after T/M-II clearence.
57
HH. I.P. inner casing TSE T/C – 4 Nos. Removal, testing and replacement Removal of T/C’S & replacement by new terted T/C’s.
II. Removal,Calibration and normalisation ,Retrofit-ting of main turbine turbovisory instru-ments and EHG unit.
Removal of existing instrument. Installation of new instruments. Made such facility so that Signal of instruments available upto panel.
JJ. Disconnection, removal, servicing of HPBP1, HPBP2, FOD-1 & 2, BPE1, BPE2, BD valve servo & Blocking element, both tank & suction filter cleaning.
Depressurization, disconnection of hoses & removal of servo/blocking element, servicing line & micro filter
Line filters removal & line flushing. Fresh oil top up, valves Calibration after T/M-II clearance & servo/ blocking unit restoration.
KK. Seal /leak off steam valve sump, Filter & Servo-unit Cleaning, Calibration, and Normalization. Sump oil removal, cleaning. Filter cleaning. Servo unit cleaning New oil top up Stroke with PFT calibration. Remote trial.
LL. Removal and Normalization of Turbine side instru-ments as per TM-II & EM–II requirement Supply isolation, connec-tion removal and cleaning. Restoration & trial after TM-II/EM-II Clearance.
MM. Removal, Cleaning, Calibration of HOT & Cold gas Primary water RTD’S/ Temp. Switches & Acw I/L/OL RTD’S
Supply isolation, dis-connection & instruments removal Cleaning, Calibration Restoration after T/M-II Clearance.
NN. Disconnection, Removal & restoration of Generator seal oil TE & EE RTD’S, Prechamber Level Probe Gas Cooler I/L & O/L RTD’S.
Supply isolation, dis-connection & instruments removal
58
Cleaning, checking & Calibration Restoration after T/M-II Clearance.
OO. Main Exciter Hot/Cold air instruments removal, Calibration & restoration as per TM-II schedule. Supply isolation, dis-connection & instruments removal Cleaning, checking & Calibration Restoration after T/M-II Clearance.
PP. Removal & Servicing of CRH NRV’s Limit switches assemblies LHS & RHS. Dis-connection & removal of LS assemblies. Servicing & testing Restoration after T/M-II Clearance.
QQ. Removal, Cleaning, Calibration of all Press. Switches, Press. Gauges,Temp. switches temp. gauges, transmitters, RTD’s of-
Dis-connection, removal Cleaning, checking & Calibrationi) Lub. Oil& Turbine drain oil system.
Repair / Replacement of defective instrumentsii) Control Fluid system.
Restoration after T/M-II Clearance.i. Governing racksii. LP bypass systemiii. HP bypass systemiv. Primary water systemv. Gas systemvi. Seal Oil system inclusive of new ckt.
RR. TDBFP A/B, MDBFP C/D , CEP A/B/C instruments checking, calibration and protection trials.
SS. Provision of PVC tubes for condenser hydraulic test & Hot-well level switches functional checking.
PVC tube to be provided as per requirements.
TT. LPH -1/2/3, GSC Level switches functional testing with Protocol with operation and TM-II
UU. TDBFP A & B Governing Characteristics & protection trial
59
VV. Governing Characteristics through EHC & Hydraulic with TM-II & operation
WW. LP bypass stop & CV’s with water injection valves remote trials.
XX. Turbine Protection trial. CPU all valves solenoid checking, trial & replacement if necessary. CPU bypass valve & DP transmitter calibration & interlock checking .
YY. CPU instrument air valves checking & replacement if necessary.
ZZ. SWAS room pH & conductivity meters sensors cleaning & ensuring availability of these signals on DCS.
AAA. All air heaters flue gas inlet thermocouple guide pipe provision
BBB. Sample isolating valves & blow down needle valves(Whitey make) replacement
TESTING SECTION
A. Generator relay testing by secondary injection & CT/PT resistance checking. Current relay testing
Voltage Relay Testing
Power Relay & frequency relay Testing
Impedance Relay Testing
PT fuse replacement and connection tightening
CT/PT Resistance measurement & connections Checking
Annunciations and SOE points checking
B. Generator Testing a Stator Rotor
Main & pilot execitor
60
diode and fuses
GCB Trial and Dynamic Testing of Generator
C. HT Switch gear Relays testing a Unit Board A Unit Board B Unit Board C
Unit Board D
Compressor Switch gear
Station Switch gear(11KV)
AHP switchgear
D. HT Circuit Breaker operation time & contact resistance measurement and connection tightening ( Unit Boards)
Unit Board A & B
Unit Board C & D
BTS A/B/C/D Trial
E. LT Switchgear Relay testing PA/EMPA board relay testing MA/ME/MD Board relay testing
AHP LT board relay Testing
mics works of HT/LT switchgear
PA/EMPA Auto changeover trial and DG set auto pick up trial
F. GTR / UAT Transformer testing, OTI/WTI calibration and. Protection trials. GTR R/Y/B Testing
UAT A/B/C/D Testing
SAT 4A/4B Testing
OTI/WTI calibration,and Mech.Protection trials
GTR WATER FLOW , oil pump trial
GTR Bushing
G. Checking of Battery Chargers. 220 V chargers
24 V chargers
UPS
Misc. works of Transformer side
61
Motorised valves
Bottom Ash panel/Air compressor panel
Services to operation and other sections and Misc. works
H. ODP WORKS CCW transformer testing
CTPA Relay Testing and connection tightening and reguler running work of ODP
CTFAN Panel checking and control room control panel checking/connection tightening
ODP RELAY TESTING WORKS
Regular and other ODP works
PART – II
ACTUAL OVERHAUL ACTIVITIES
WORKS CARRIED OUT DURING ANNUAL OVERHAUL OF UNIT # 5
BOILER MAINTENANCE
FURNACE
1. Ring headers orifices checking carried out. Screen fitting work carried out.
2. Drum internal inspection carried out.
a) FIRST PASS :1. Hydrojetting in WW, Divisional panel , wall reheater, PSH, RH, carried out.
2. Thickness survey at all elevation Water wall, Repeater (RHS) Repeater (LHS), Super heater (RHS)
Super heater (LHS) carried out. Damaged & eroded tubes cuttng and welding at all elevations of WSB
carried out.
3. Burner corner bend welding carried out.
4. DP & PSH repair work carried out.
5. Ash removal work in Pent House carried out.
6. Cat house and Dog house cleaning is carried out.
b) SECOND PASS :
1. Screen tubes inspection completed.
2. Economizer upper assy. repair work carried out
62
As per thickness survey conducted Furnace various tubes marking, Radiography, Repairs/replacement
carried out as follows
JOINT STATUS IS AS BELOW-
ZONE AGENCY EX.JONT MRKD JONT
JT. COMPL RADIOGRAPHY RAPAIR
WATER WALL SHEL 1500 878 878 878
ADORE 587 587 587
DIV PANEL SHEL 50 60 60 60
ADORE 48 48 48
PSH SHEL 250 23 23 23
ADORE 47 47 47
RE HEATER SHEL 50 4 4 4
ADORE 4 4 4
SCREEN TUBE BCC 50 4 4 4
VK
ECO(UPPER
ADDNL)
BCC 600 548 520 474
VK 532 532 481
63
LTSH BCC 500 536 536 536
VK 440 440 440
ECO (MIDD
&LOW REP.
SH VERT. SP.
ASSY REP.
STEAM
COOLED WALL
BCC 50
VK 14 14 14
RLA SHEL 100 83 82 82
TOTAL 3150 3808 3779 3682
c) ID FAN 5A, 5B, 5C & 5D :
1. Lube oil tank, filter and cooler cleaning work carried out.
2. DE & NDE side bearing inspection work completed. Bearing boxed up.
3. Cooler cleaning completed.
4. Impeller cleaning done.
d) FD FAN - 5A, 5B :
1. FD Fan 5B bearing inspection work completed.
2. FD Fan 5A DE side bearing replacement work completed.
3. Duct and Impeller cleaning done.
e) PA FAN -5A, 5B :
1. Bearing inspection work completed.
2. Impeller and IGV gate cleaning done.
3. Gate servicing done.
64
f) BURNER TILT :
1. Corner No. 1 –
Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.
2. Corner no. 2 –
Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.
3. Corner no. 3-
Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.
4. Corner no. 4 –
65
Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.
g) AIR HEATERS :
1. Air Preheater-5A :
I. Primary :
All old baskets replaced with new basket
Support and guide bearing inspection work carried out.
Support bearing replacement work completed.
Rotor and sector plate leveling completed.
Guide and Support bearing cooler cleaning done.
Gearbox insp. carried out. Hot & cold end radial seal setting done
II. Secondary :
All old baskets replaced with new basket
Support and guide bearing inspection work carried out.
Rotor and sector plate leveling completed.
Guide and Support bearing cooler cleaning done.
Gearbox insp. carried out. Hot & cold end radial seal setting done
66
2. Air Preheater-5B:
I. Primary :
All old baskets replaced with new basket.
Hot& Cold end side sector plates repairs works carried out.
Grating repairs’ work carried out.
Support and guide bearing inspection completed.
Guide and Support bearing cooler cleaning work completed.
Rotor and sector plate leveling completed.
Seal fitting work is in progress.
II. Secondary :
All old baskets replaced with new basket.
Hot& Cold end side sector plates repairs works carried out.
Grating repairs’ work carried out.
Support and guide bearing inspection completed.
Guide and Support bearing cooler cleaning work completed.
Rotor and sector plate leveling completed.
Seal fitting work is in progress.
h) AIR / GAS DAMPERS :
GD-1A, GD-1B servicing done. GD-2A, 2B servicing done. GD-3A, 3B servicing done. GD-4A1, 4A2 replaced by new one. GD-4B1,4B2 servicing done.
67
i) HP VALVES :
Following V/V’s servicing / repairing / replacement carried out
High Pressure valves—% completed
Sr Valve descriptions
Qty dismantling Machining Lapping Box up HANDOVERTO
I&C / TEST
1 MS VALVE 2 2 2 2 2
2 SH Spray control v/v
5 5 5 1
3 RH Spray control v/v
5 5 5
4 SH MANUAL ISO V/V
4 4 4 4
5 SH drain valve 10 10 10 10
6 Safety valve 16 16 16 8
68
7 Zero meter drain valve
8 8 8 8
8 RH MANUAL ISO V/V
4 4 4 4
9 RH SPRAY MOT ISO. VALVE
4 4 4 3
10 DRUM VENT 8 8 8 8 4
11 STARTUP VENT 4 4 4 4 4
12 PRDS STATION VALVE
3 1 1 1
13 SH SPRAY MOT ISO. VALVE
4 4 4 4 4
14 SB moto, man & CV
3 2 2 1
15
TOTAL 80 77 0 77 58 14
j) BCW PUMPS :
1. BCW pump cooler cleaning done
k) COAL MILLS :
I. COAL MILL – A :
1. Type-A overhaul carried out.
2. Air port assembly replaced
3. Air deflectors and vane wheel segment welding carried out.
4. Extension ring top plated welding carried out.
5. Inner seal air ring replaced.
6. Gear box side coupling replaced.
7. Hot air damper close/zero position done.
8. PA duct cleaning done.
9. Scrapper area cleaned.
69
II. COAL FEEDER - 5A :
1. Internal inspection carried out.
2. Bunker outlet gate and C/F inlet gate servicing done.
3. Rubber skirt fitting done.
4. Modification of COC base plate done.
5. Belt, pulley, bearings replaced.
6. G/B oil seal and stud plate modification work carried out.
III. COAL PIPE A :
1. Pipe and bend 2A1 replaced.
2. 4.5 mtr. pipe on duct and bend 45 degree replaced.
3. Centre pipe replaced, MOE A3, A2 and A4 replaced.
4. 4th corner second bend 2A4 and pipe 2m and 1 m long after and before respect replaced.
I. COAL MILL – B :
1. Type-A overhaul carried out.
2. Center pipe replaced.
3. Ventury joint patch welding done.
4. PA duct cleaning done.
5. Scrapper area cleaned.
6. 5 Nos. of ICP replaced.
7. Coal Mill Lube oil cooler cleaning done.
8. MOE B3 and MOE B2 replaced.
9. HAG/CAG servicing/ calibration done.
II. COAL FEEDER - B
1. Internal inspection carried out.
70
2. Bunker outlet gate/inlet gate and C/F inlet gate servicing done.
3. Rubber skirt fitting done.
4. Bunker outlet gate all stud roller replaced.
III. COAL PIPE - B :
1. Fire corner 1B2 pipe replaced.
2. Send pipe second corner after MOE 4.55 mtr. replaced.
3. 3ed pipe 3ed corner after MOE 1.900 mtr replaced.
4. 4th pipe 4th corner after MOE 6.700 mtr replaced.
5. 3ed corner 6th B3 pipe and 2 coupling and 3B3 bend at 9mtr level and 2B2 bend and pipe on duct
replaced.
6. MOE B2 replaced
7. 3ed corner on 9 mtr level 5.5 mtr pipe 6.2 mtr pipe and bend replaced.
I. COAL MILL – C :
1. Type-A overhaul carried out.
2. CAD seal replaced.
3. Centre pipe replaced.
4. MOE C1 and MOE C3 replaced.
5. Inner seal ring replaced.
6. PA duct cleaning done.
7. Scrapper area cleaned.
8. Lop cooler cleaning done
9. Inner coal leakages and ventury patching done.
II. COAL FEEDER - 5C :
1. Internal inspection carried out.
71
2. C/F inlet and bunker O/L gate servicing done.
3. Rubber skirt fitting done
4. BOG/FOG bearing and sprocket shaft replaced.
5. COC base plate modification done.
6. Inlet skirt, side skirt, LH-RH 2 nos. extended skirt plate replaced.
7. Rubber belt with 2 nos. bearings replaced.
8. Gear box servicing done.
III. COAL PIPE C: 1. Centre pipe replaced.
2. C1 post pipe replaced
3. MOE C1, C4 and C3 replaced
4. 3ed pipe 3ed corner after MOE 1.700 mtr replaced.
5. Pipe on duct replaced.
6. C1 post pipe 2.7mtr replaced.
7. 1st corner 6.17mtr pipe replaced.
I. COAL MILL – D :
1. Type-A overhaul carried out.
2. PA duct cleaning carried out.
3. Scrapper area cleaned.
4. Center pipe replaced.
5. MOE D3 replaced.
6. 1 nos. inner seal replaced.
7. Bowl hub skirt replaced.
8. Inner cone checked, found fallen in cone same was refitted.
9. Lop cooler cleaning done
II. COAL FEEDER – D :
1. Internal inspection carried out.
72
2. C/F inlet and bunker o/l gate servicing done.
3. Rubber skirt fitting done.
4. Belt replaced.
III. COAL PIPE D:
1. Center pipe replaced.
2. MOE D3replacd
3. 2nd bend 2D2 and 2nd pipe after 2D2 bend 1mtr replaced.
4. 4th pipe 4th corner 9.00mtr replaced.
5. 3ed corner 45 degree bend and 2.3mtr pipe (over mill) replaced.
I. COAL MILL – E :
1. Type-C overhaul carried out.
2. Bull ring segment replaced.
3. J/A-J2 and J3 replaced.
4. Vane wheel top plate clamping hard facing done.
5. Bowl hub cover top plate welding done.
6. Lop cooler cleaning done
7. PA duct cleaning done.
8. Scrapper area cleaned.
9. Door liner replaced
10. Inner cone and ventury checked found worn out, patching and welding done.
73
II. COAL FEEDER - 5E :
1. Internal inspection carried out.
2. Belt replaced.
3. C/F inlet and bunker o/l gate servicing done.
4. Rubber skirt fitting done
5. COC base plate modification done.
6. Center skirt plate (inlet) replaced.
7. Support roller bearing and gear box oil replaced.
III. COAL PIPE E: 1. 1st pipe 1st corner after MOE 5.5 mtr. replaced.
2. 3ed corner after MOE 1.500mtr replaced.
3. 3ed corner 2E3 pipe and bend 30degree and 1.5mtr pipe replaced
4. 4th corner 1E4 replaced.
5. 1st corner MOE replaced.
6. 4th corner 4.2mtr pipe replaced.
7. 3ed corner 1.4 mtr pipe and 30 degree bend replaced.
8. MDV flap E1, E4 replaced.
I. COAL MILL – F :
1. Type-A overhaul carried out.
2. Scrapper liner replaced.
3. Lop cooler cleaning done
4. PA duct cleaning done.
5. Scrapper area cleaned
II. COAL FEEDER – F :
1. Internal inspection carried out.
2. C/F inlet and bunker o/l gate servicing done.
3. Rubber skirt fitting done.
74
4. Belt replaced
5. COC base plate modification done.
6. Center skirt plate (inlet) and side skirt plate with rubber and extended skirt replaced.
7. Support roller bearing and support rollers replaced.
III. COAL PIPE F: 1. pipe 1st corner after MOE 2.400mtr replaced.
2. 1st corner 1.2mtr pipe after MOE and MOV replaced.
3. MDV flaps F1, F2, F3 replaced.
I. COAL MILL – G :
1. J1 AND J2 OIL REPLACED.
2. PA duct cleaning done.
3. Scrapper area cleaned.
4. Lube oil cooler cleaning done.
5. MDV flap G1 and G3 replaced.
II. COAL FEEDER - G
1. Internal inspection carried out.
2. C/F inlet and bunker O/L and I/L gate servicing done.
3. Rubber skirt fitting done.
4. COC base plate modification done
5. Skirt plate center, LH-RH, extended modification done.
6. G/B servicing done
III. COAL PIPE G: 1. 2nd pipe 1G2 2nd corner 3.00mtr replaced.
2. 1st corner 2.4 mtr pipe and 30 degree bend after MOV replaced.
3. MDV flaps G1, G4 replaced.
75
I. COAL MILL – H :
1. Type-A overhaul carried out.
2. MDV flap H3 and H4 replaced.
3. LOP filter and breather cleaning done.
4. Lop cooler cleaning done
5. PA duct cleaning done.
6. Scrapper area cleaned.
II. COAL FEEDER – H :
1. Coal Feeder internal inspection done.
2. C/F inlet and bunker O/L gate servicing done.
3. Rubber skirt fitting done
4. COC base plate modification done.
5. Skirt plate with rubber replaced.
6. Rubber belt with support roller bearing replaced.
III. COAL PIPE H: 1. 1st corner 2.9mtr pipe and 1B1 bend, 2.4mtr pipe replaced.
2. MDV flaps H3 and H4 replacd.
l) CAG / CAD :
1. All mills CAG servicing done.
2. All CAD made free.
m) SEAL AIR FANS 5A & 5B :
1. Bearing internal inspection of both fans done.
2. Fan brg. Greasing done.
3. Suction filter cleaning carried out.
76
4. Damper servicing done.
n) ESP PASS - A, B, C, D :
1. Water washing carried out.
2. Inlet GD screen replacement work done.
3. All fields internal inspection done.
4. All fields damaged/worn out collecting plates, ERM / CRM top & bottom hammers, bearings, shock
bars, guide angles, pads & pin wheels repairs/replacement work carried out.
U = 5 E.S.P. PASS REPAIRED AND REPLACEMENT REPORT-
1. E.S.P. A PASS :
S.NO.WORK
DISCRIPTION1A1 1A2
2A1 2A2
3A1 3A2
4A1 4A2
5A1 5A2
6A1 6A2
TOTAL REMARK
1 C.R.M.Hammer
57 57 20 15 11 09 230 Replaced
2 C.R.M.Bearings
12 12 12 12 7 4 45 Replaced
3 Shock Pads 13 5 16 12 13 6 38 Replaced
4 Shock Bars 12 14 5 8 7 3 13 Repaired
5 C.R.M.Shafts
1 0 0 0 0 0 5 Replaced
6 C.R.M. 0 1 1 1 1 1 5 Alignment
77
Shafts
7 Guide Angles 10 0 0 30 10 7 78 Replaced
8 Guide Angles 0 12 12 0 0 0 52 Alignment
9Hoppers Gas Screens
0 2 0 0 0 0 2 Repaired
10 E.R.M.Hammers
56 56 13 20 17 18 233 Replaced
11 E.R.M.Bearings
29 24 18 12 12 12 98 Replaced
12 E.R.M.Shafts
10 0 0 0 0 0 0 Replaced
13 E.R.M.Shafts
1 1 1 1 1 1 6 Alignment
14 Pin Wheel Big 4 4 3 1 1 2 17 Repaired
15 Pin Wheel Small 4 4 7 6 0 0 19 Repaired
16 Bush Bearings 4 8 4 2 2 0 22 Replaced
17 Vertical Shafts 2 2 2 0 0 0 0 Replaced
18 Notching Of Plates 18 24 21 10 10 9 80 Repaired
19 Collecting Plates 36 8 8 3 60 0 2 Repaired
20 E.R.M.Electrodes
94
150
72
128
94 Replaced
21 "U"Clamps
150 Replaced
22 G.D.Screens
40 Replaced
23 Deflector Plates 128 Replaced
2. E.S.P. B PASS :
S.NO. WORK 1B1 2B1 3B1 4B1 5B1 6B1 TOTAL REMARK
78
DISCRIPTION 1B2 2B2 3B2 4B2 5B2 6B2
1C.R.M.
Hammer57 57 31 27 23 9 204 Replaced
2C.R.M.
Bearings12 12 14 12 3 3 56 Replaced
3 Shock Pads 13 12 8 6 3 9 51 Replaced
4 Shock Bars 13 11 7 07 5 5 48 Repaired
5C.R.M.
Shafts0 0 0 0 0 0 0 Replaced
6C.R.M.
Shafts1 1 1 1 1 1 6 Alignment
7 Guide Angles 10 10 10 10 7 10 57 Replaced
8 Guide Angles 0 0 0 0 3 0 3 Alignment
9Hoppers Gas Screens
50 0 2 0 0 0 50 Repaired
10E.R.M.
Hammers56 56 56 31 32 21 202 Replaced
11E.R.M.
Bearings24 24 24 11 12 12 107 Replaced
12E.R.M.
Shafts0 0 0 0 0 0 10 Replaced
13E.R.M.
Shafts4 16 4 8 14 17 63 Alignment
14 Pin Wheel Big 4 2 2 4 2 1 18 Repaired
15 Pin Wheel Small 4 4 4 4 2 0 18 Repaired
16 Bush Bearings 8 8 8 8 8 0 40 Replaced
79
17 Vertical Shafts 8 8 6 4 0 0 26 Replaced
18 Notching Of Plates 11 7 11 8 13 10 60 Repaired
19 Collecting Plates 10 6 3 5 6 0 30 Repaired
20E.R.M.
Electrodes 48
100
45
128
48 Replaced
21 "U"Clamps
100 Replaced
22 G.D.Screens
45 Replaced
23 Deflector Plates 128 Replaced
3. E.S.P. C PASS
S.NO.WORK
DISCRIPTION
1C1 1C2
2C1 2C2
3C1 3C2
4C1 4C2
5C1 5C2
6C1 6C2
TOTAL REMARK
1C.R.M.
Hammer57 57 57 21 7 12 211 Replaced
2C.R.M.
Bearings12 12 22 12 4 3 65 Replaced
3 Shock Pads 15 14 12 10 8 7 66 Replaced
4 Shock Bars 14 10 12 2 0 2 40 Repaired
5 C.R.M. 0 0 12 0 0 0 12 Replaced
80
Shafts
6C.R.M.
Shafts1 1 1 1 1 1 6 Alignment
7 Guide Angles 10 10 10 0 10 10 50 Replaced
8 Guide Angles 0 0 0 0 0 0 0 Alignment
9Hoppers Gas Screens
50 0 0 0 0 0 50 Repaired
10E.R.M.
Hammers56 56 37 32 24 23 228 Replaced
11E.R.M.
Bearings24 24 24 24 12 12 120 Replaced
12E.R.M.
Shafts16 16 12 12 6 0 62 Replaced
13E.R.M.
Shafts8 8 6 6 12 0 40 Alignment
14 Pin Wheel Big 4 4 4 4 4 4 24 Repaired
15 Pin Wheel Small 4 4 4 4 4 4 24 Repaired
16 Bush Bearings 8 8 8 8 8 8 48 Replaced
17 Vertical Shafts 8 6 6 6 2 4 32 Replaced
18 Notching Of Plates 11 8 11 7 9 6 52 Repaired
19 Collecting Plates 4 5 5 2 6 2 24 Repaired
20E.R.M.
Electrodes
25
100
50
100
25
21 "U"Clamps
100
22 G.D. 50
81
Screens
23 Deflector Plates 100
4. E.S.P. D PASS
S.NO.
WORK
DISCRIPTION
1D1 1D2
2D1 2D2
3D1 3D2
4D1 4D2
5D1 5D2
6D1 6D2
TOTAL REMARK
1C.R.M.
Hammer57 57 40 11 9 9 183 Replaced
2C.R.M.
Bearings12 12 12 4 3 3 46 Replaced
3 Shock Pads 19 10 18 9 9 9 74 Replaced
4 Shock Bars 10 8 10 13 5 3 49 Repaired
5C.R.M.
Shafts0 0 0 0 0 0 0 Replaced
6C.R.M.
Shafts1 1 1 1 1 1 6 Alignment
7 Guide Angles 10 10 10 10 10 10 60 Replaced
8 Guide Angles 0 0 0 0 0 0 0 Alignment
9Hoppers Gas Screens
160 0 0 0 0 0 160 Repaired
10E.R.M.
Hammers56 56 56 20 21 12 212 Replaced
11E.R.M.
Bearings24 24 24 12 12 12 108 Replaced
12 E.R.M. 0 0 0 0 0 0 0 Replaced
82
Shafts
13E.R.M.
Shafts4 4 4 8 8 6 34 Alignment
14 Pin Wheel Big 4 4 4 4 4 4 24 Repaired
15 Pin Wheel Small 4 4 4 4 4 4 48 Repaired
16 Bush Bearings 8 8 8 8 8 8 48 Replaced
17 Vertical Shafts 8 8 8 8 8 8 48 Replaced
18 Notching Of Plates 6 5 7 9 6 6 39 Repaired
19 Collecting Plates 4 4 3 6 2 3 22 Repaired
20E.R.M.
Electrodes 400
150
160
39
400
21 "U"Clamps
150
22 G.D.Screens
160
23 Deflector Plates 39
U = 5 E.S.P. PASS REPAIRED AND REPLACEMENT REPORT:
S.NO. WORK DISCRIPTION
E.S.P. A PASS
E.S.P. B PASS
E.S.P. C PASS
E.S.P. D PASS
TOTAL CONSUME REMARK
1C.R.M.
Hammer230 204 211 183 828 Replaced
2C.R.M.
Bearings45 56 65 46 212 Replaced
3 Shock Pads 38 51 66 74 229 Replaced
4 Shock Bars 13 48 40 49 150 Repaired
83
5C.R.M.
Shafts5 0 12 0 17 Replaced
6C.R.M.
Shafts5 6 6 6 23 Alignment
7 Guide Angles 78 57 50 60 245 Replaced
8 Guide Angles 52 3 0 0 55 Alignment
9Hoppers Gas Screens 2 50 50 160 262 Repaired
10E.R.M.
Hammers233 202 228 212 875 Replaced
11E.R.M.
Bearings98 107 120 108 433 Replaced
12E.R.M.
Shafts0 10 62 0 72 Replaced
13E.R.M.
Shafts6 63 40 34 143 Alignment
14 Pin Wheel Big 17 18 24 24 83 Repaired
15 Pin Wheel Small 19 18 24 48 109 Repaired
16 Bush Bearings 22 40 48 48 158 Replaced
17 Vertical Shafts 0 26 32 48 106 Replaced
18Notching Of
Plates 80 60 52 39 231 Repaired
19Collecting Plates 2 30 24 22 78 Repaired
20E.R.M.
Electrodes94 48 25 400 567 Replaced
21"U"
Clamps150 100 100 150 500 Replaced
22G.D.
Screens40 45 50 160 295 Replaced
23 Deflector Plates 128 128 100 39 395 Replaced
84
o) BOTTOM ASH HOPPER:
1. Seal trough cleaning done.
2. Seal trough corner and center C/M side leakage attended.
3. Seal trough inner side plate repaired.
4. Bottom ash hopper cleaning done.
5. Bottom ash hopper strengthening done.
6. Dome repairing done.
7. 50 N.B. line seal trough line and inspection glass flushing line replaced.
8. 100 N.B. seal trough filling header at seal trough header level and bottom ash flushing line 90 m and 9
m bend fabricated.
9. Damaged LP ash water pipe line 150NB replaced.
10. 200 N.B HP line 17 m and 5 bend replaced.
11. 178 tons refractory gun netting done.
12. 4 No. of surge box repaired.
13. Refractory cooling water line, hopper flushing line 100 NB replaced, 02Nos.bendfabricated.
14. Bottom ash refractory replacement works carried out.
15. 210 RMT M.S. welding done.
p) CLINKER GRINDERS AND ASH GATES:
1. C/G-1A and 1B, 2Ahyjector manual valve servicing done.
2. C/G-2B hyjector manual valve replaced.
3. C/G -1A, 1B, 2A, 2B ash feed gate repairing done.
4. C/G -1A, 1B, 2A, 2B feed chute hopper repair and welding done.
5. C/G -1A, 1B, 2A, 2B ash gate shaft gland replaced.
6. Flushing water valve 100 N.B. 02 replaced.
7. Feed Chute hard facing carried out.
85
8. All C/G ash feed gate indicating rod box repaired.
9. Discharge line, ground level up to bend replacement work carried out.
10. 200 N.B.3 valve replaced and 13 valve servicing done.
11. 100 N.B.3 valve replaced and 3 valve servicing done.
12. Seal water line 4 no of valve servicing done.
13. 4 no. of man door servicing done.
q) FLUE GAS DUCT :
1. All duct cleaning done.`
2. Ash &debris removed from duct.
3. Flue gas path damaged bracing replacement carried out.
4. Hot air duct damaged bracing replaced.
5. Worn out MS plate’s replacement done.
6. Cover plates of expansion joint replaced.
7. Damaged expansion joints at ESP outlets repairing work carried out.
8. Flue gas duct hoppers repairing work carried out.
9. Diversion plates at ESP inlet replaced.
10. PAH vertical duct has hole at 27 m level and hot air duct U # 5 side in front of ECO duct its corner
expansion joint bottom leaf found damaged same attended by patch welding
r) COARSE ASH EVACUATION SYSTEM :
1. All eco hoppers, duct hoppers cleaning carried out.
2. ECO hopper common discharge pipe 200 N.B.8 m replaced.
3. ECO hopper common vertical pipe 200 N.B.60 m replaced.
4. ECO hopper h. p. line damage pipe replaced.
5. All course ash distance piece fitting done.
6. Course ash hopper feeder ejector 22 no. servicing done.
7. 44 no. of air heater chain valve servicing and jamming removal done.
86
8. 18 no. of servicing water 100 N.B. done.
9. 20 no. of servicing water 150 N.B. done.
10. 12 no. of servicing water 200 N.B. done.
11. 2 no. of servicing of hyjector of C/A tank done.
12. 400 m2 hopper structure and pipe painting done.
13. 2 no. of course ash tank cleaning done.
14. Course ash hopper both side common slurry tank strengthening done.
15. 12 no. feeder ejector nozzle set replaced.
16. All eco hoppers, duct hoppers ash / chain v/v servicing carried out.
17. Eco hoppers trench repairs carried out.
s) FLY ASH EVACUATION SYSTEM :
1. Feeder ejector servicing done -72 no.
2. Ash valve and chain valve servicing done -144 no.
3. ESP all hoppers choke up removal done – 1 no.
4. Total welding done – 200 RMT
5. Replacement of pipe line 150 NB- 112 m
6. Servicing of water valve 350 NB - 4 no.
7. Servicing of water valve 250 NB - 48 no.
8. Servicing of water valve 100 NB - 72 no.
t) ESP INLET AND OUTLET GATE:
1) ESP A, B, C, D passes inlet gate both side gear box servicing done. Old oil replaced by fresh oil.
2) ESP A, B, C, D pass inlet gate support welding done.
3) ESP inlet gate 6A1, 6A2, 6B1, 6B2, 6C1, 6C2, 6D1, 6D2 manual trial found ok.
4) ESP outlet gate 7A, 7B, 7C, 7D manual trail taken found ok.
87
88
TURBINE MAINTENANCE
A) MAIN TG:
1) Seal oil Bearing DPT taken.
2) Generator Pressurization test completed at 6kg/cm2, leakage found in Bushing.
3) MOP bearing clearance correction done.
4) Governing- Hydraulic convertor, EHG Convertor servicing was done no abnormality seen.
a) HPT :
1) HPT Horn drop, Swing check, Roll check, CRO test, Bump test completed.
2) Alumina blasting carried out
3) HP rotor MPI Completed
4) Inner Casing quality taken.
5) HP rotor flow path taken
b) IPT: 1) IP-LP CRO Completed. Roll check taken.
2) Rotor Flow path completed
3) Rotor Alumina blasting completed
4) IPT rotor MPI was Completed
c) LPT: 1) LPT-Gen CRO completed. Roll check taken.
2) LPT flow path checking completed.
3) Alumina blasting done.
4) Free standing blades all MPI completed.
5) blade No 34 from 2L was found defective. Replaced with new blades.
6) NFT of free standing blades taken.
7) Inlet bellow found defective, replace with new bellow.
89
d) GENERATOR/EXCITER : 1) CRO & Swing check of Exciter & Generator Coupling taken.2) Exciter rotor leak test taken.3) Compressor assembly Blade rings inspection done.4) CC Bolt found leakage. Same was attended.5) Conical filters cleaning done.6) Pressurization of stator was carried out.7) Primary water magnetic filter cleaned.
B) TANK CLEANING:
1) Control fluid tank bucket strainer cleaning done.
2) Main Turbine MOT tank cleaning carried out.
3) 3 TDBFP-6A and 6B tank cleaned.
B) HP /LP VALVES:
1) HPCV 3 & 4 seat found damage.
2) HPBP valve 1 & 2 servicing done.
3) HPBP 1 & 2 servo motor servicing done.
4) LPBP-1, 2 valve servicing done.
5) LPBP spray valve V1, V2, V3, V4 servicing carried out.
6) BPE-1 &BPE-2 valve servicing done.
7) BPE 1 & 2 servo motor servicing done.
8) BD valve servicing done
9) BD isolating valve servicing done.
C) CONDENSER :
1) Cleaning work completed.
2) Installation of Cathodic protection completed.
3) End Plate coating work completed.
4) Condenser gravity test completed
D) BOILER FEED PUMPS :a) TDBFP 5B1) Turbine overhaul done.
2) Rotor sand blasting done.
90
3) Cartridge replacement done.
E) CEP -5A:
1) Mechanical Seal servicing completed.
G) HP HEATERS:
1) HPH 5A, 5B, 6A & 6B internal inspection Carried out and air leak test taken.
H) LP HEATERS :1) LPH 1, 2 & 3 internal inspections carried out.
2) LPH 2&3 Air leak test Carried out & found normal. No leakage found.
I) MS AND HRH STRAINERS :1. All MS strainer servicing done. Bonnet seal ring replaced by new one.
2. All HRH strainer servicing done. Bonnet seal ring replaced by new one.
J) DEAERATOR AND FST :1. Deaerator & FST internal insp. carried out.
2. Damaged nozzles replaced with new.
K) COOLERS : 1. Exciter cooler (2 Nos.) Cleaning / brushing / flushing / cleaning done.
2. Exciter cooler (4 Nos.) ACW valve internal inspection & servicing done.
3. Hydrogen coolers (4 Nos.): Acid / brushing / flushing / cleaning done.
4. H2 coolers- 4 Nos. of ACW outlet valve & 2 Nos. of inlet valve servicing done.
5. H2 cooler temperature control valve servicing done.
6. Primary water cooler- 3 Nos. of valves internal inspection & servicing done.
7. Primary water cooler- 3 Nos. Cleaning/ brushing /flushing carried out.
8. Primary water cooler temp. Control valve servicing done.
9. Seal oil cooler both air side &hydrogen side cleaning/ brushing /flushing carried out.
10. Seal oil rack ACW VALVE servicing done.
11. GTR R Y B Phases both coolers cleaning/ brushing /flushing Carried out.
12. GTR R Y B Phases coolers ACW valve servicing work Carried out.
13. GTR R Y B Phases ACW strainers cleaning done.
14. MOT coolers brushing / flushing / cleaning done. Air test taken at 6.0 kg/cm2.
15. Both MOT coolers ACW Inlet & Outlet valve servicing done.
91
16. FRF both coolers cleaning carried out both cooler gasket replaced.
17. FRF cooler temp control v/v servicing done
18. TDBFP 6A & 6B - Both oil coolers cleaning/ brushing /flushing carried out.
19. TDBFP6A And 6B Both oil coolers ACW Inlet & Outlet valve servicing done
20. MDBFP-6C, Lub oil coolers and working oil cooler ACW Inlet & Outlet valve servicing done.
21. MDBFP-6C, Lub oil & Working oil cooler brushing / flushing done.
22. MDBFP-6D, Lub oil coolers ACW Inlet & Outlet valve servicing done.
23. MDBFP-6D, Lub oil & Working oil cooler cleaning / brushing / flushing done.
STATUS OF COOLER ACW VALVES
STATUS OF HP VALVES
11
Valves Details Category
Valves for Servicing
Replacement of valves
Remark
1 TDBFP 5A S/H iso Gate Valve
Boxup done.
2 TDBFP 5A R/H iso Gate Valve
Boxup done.
3 TDBFP 5B S/H iso Gate Valve
Boxup done.
4 TDBFP 5B R/H iso Gate Valve
Boxup done.
5 MDBFP 5C S/H iso Gate Valve
Boxup done.
6 MDBFP 5C R/H iso Gate Valve
Boxup done.
7 MDBFP 5D R/H iso Gate Valve
Boxup done.
8 MDBFP 5D S/H iso Gate Valve
Boxup done.
9 MDBFP 5C R/H NRV NRV Boxup done.
10
MDBFP 5C S/H NRV NRV Boxup done.
11
MDBFP 5D S/H NRV NRV Boxup done.
12
MDBFP 5D R/H NRV NRV Boxup done.
13
TDBFP 5A R/H NRV NRV Boxup done.
14
TDBFP 5A S/H NRV NRV Boxup done.
15
TDBFP 5B R/H NRV NRV Boxup done.
16
TDBFP 5B S/H NRV NRV Boxup done.
17
TDBFP 5A Suction Gate Valve
Boxup done.
18
TDBFP 5B Suction Gate Valve
Boxup done.
92
19
MDBFP 5C Suction Gate Valve
Boxup done.
20
MDBFP 5D Suction Gate Valve
Boxup done.
21
TDBFP 5B Discharge Iso
Gate Valve
Boxup done.
22
TDBFP 5B Discharge NRV
NRV Boxup done.
23
BPE1 NRV NRV Boxup done.
24
BPE2 NRV NRV Boxup done.
25
CD 22 Globe Boxup done.
26
BD Isolating Valve Gate Boxup done.
27
CD 17 Globe Boxup done.
28
EX 02 Gate Boxup done
29
EX 01 Gate Boxup done
30
EX 03 Gate Boxup done.
31
EX 05 Gate Boxup done
32
EX 04 Gate Boxup done
33
EX 06 Gate Boxup done.
34
EX 07 Gate Boxup done.
35
AS 13 Gate Boxup done.
36
EX 13 Gate Boxup done.
37
DR 11 Globe Boxup done.
38
DR 27 Globe Boxup done.
39
Mal 11 Globe Boxup done.
40
Mal 12 Globe Boxup done.
41
Mal 13 Globe Boxup done.
42
Mal 14 Globe Boxup done.
43
Mal 22 Globe Boxup done.
44
Mal 26 Globe Boxup done.
45
Mal 28 Globe Boxup done.
46
Mal 65 Globe Boxup done.
47
Mal 66 Globe Boxup done.
48
HR 115 Globe Boxup done.
93
49
HR 113 Globe Boxup done.
50
MS 104 Globe Boxup done.
51
MS 502 Globe Boxup done.
52
MS 504 Globe Boxup done.
53
MS 506 Globe Boxup done.
54
MS 508 Globe Boxup done.
55
HR 502 Globe Boxup done
56
HR 504 Globe Boxup done.
57
HR 506 Globe Boxup done.
58
HR 508 Gloe Boxup done.
Operating Mode Quantity Completed
Motorized 23 23
Manual 23 16
Pneumatically 1 1
Hydraulically 0 0
NRV 11 11
Total 58 53
DEPARTMENTAL
1. DR 17,25 Bonnet leakage attended
2. All BFP RC line NRV Servicing completed.
3. Vacuum pump A & B Gland replacement done.
4. DR 32 Valve servicing completed.
5. EX 31 & 32 Diaphragm replaced& Seal inspection is in progress.
6. CEP RC Valves inspection.
7. HPBP Bladder replacement work.
94
ODP SECTIONA. AHP : 1. HP-LP ASH WATER PUMP VALVE SERVICING –completed.
2. Line A – 500NB B/F SERVICING completed.
3. Line B – 500NB B/F SERVICING completed.
4. Tank inlet- 350NB B/F SERVICING completed.
5. Tank inlet- 500NB B/F SERVICING completed.
6. Sump make up main isolating Valve servicing completed.
7. B/A & F/A Sump selection valve servicing completed.
8. Seal water line B-series replacement completed.
9. Seal water line A-series replacement completed.
10. Seal water suction header replacement completed.
11. Flushing line to A, B & C sump adding completed.
12. HPSWP-1,2 & LPSWP-1,2 Preventive maint. completed.
13. HPAWP-2 O/H completed.
14. 5CSDP-1 O/H completed.
15. 5ASDP-1 OH WIP.
16. Raw water tank cleaning.
17. Ash water tank cleaning completed.
B. SUMP CLEANING WORK : 1. 5B Sump cleaning completed.
2. 5A sump cleaning completed.
3. 5C sump cleaning completed.
C. OIL COOLER CLEANING: 1. B SERIES completed.
2. A SERIES completed.
D. ADL: 1. 5BSDP-4 bend to bend pipe replaced.
2. 5BSDP-4 bend to bend no.1 pipe replaced.
95
3. 5BSDP-3 expander to bend pipe replaced.
4. Pipe rotation done from CP. -4 to CP. 19.
5. Slope pipe replaced at CP. 21.
6. 5BSDP-2 horizontal pipe replaced.
7. 5B pipe replacement from CP.422 backward to CP.419 completed.
8. 5BSDP-2 vertical pipe replacement completed.
9. 5B slope pipe replacement at CP.-33 completed.
10. 5BSDP-4 discharge pipe replaced.
11. 5B sump suction pipe & suction bend replacement completed.
12. 5B pipe replacement from CP.414 to CP.419 completed.
13. 5B pipe replacement from CP.414 to CP.408 completed.
14. 5B pipe replacement from CP.93 to CP.99 completed.
15. 5B pipe replacement in pump house -pump s/c valve to reducer completed.
16. 5B pipe replacement from CP.440 to CP.441 completed.
17. 5B pipe replacement from CP.456 to CP.462 completed.
18. 5BSDP-2 vertical & horizontal pipe replacement completed.
19. 5B pipe replacement from CP.86 to CP.94 completed.
20. 5B pipe replacement from CP.462 to CP.467 completed.
21. 5B pipe replacement from CP.468 to CP.472 completed.
22. 5A suction pipe replacement completed.
23. 5A suction bend re-irection completed.
24. 5A pipe rotation from CP 90 to CP 95 completed.
25. 5C suction pipe at sump replacement completed.
26. 5B pipe replacement from CP.323 to CP.330 completed.
27. 5B pipe replacement from CP.472to CP.477 completed.
28. 5A & 5B pipe replacement -44 to -43 completed.
29. 5C suction pipe replacement completed.
30. 5C suction bend re-irection completed.
31. 5A ASDP-2 horizontal pipe repl. completed.
32. 5C suction valve to reducer pipe repl. completed.
33. 5A pipe replacement CP -40 to CP -38 completed.
34. 5B pipe replacement CP -30 to CP -23 completed.
96
35. 5B pipe replacement CP 319 to CP 313 completed.
36. 5B pipe replacement CP.593 to CP.595 completed.
E. CT FAN: 1. CT Fan 5A/1, 5A/5, 5B/1, 5B/6-O/H completed. 5B/1 trial pending.
2. CT Fan 5B/5- Blade repl. (5A/7, 5B/5, 5B/8 completed).
3. CT 5A nozzle cleaning completed.
5. CT 5B nozzle cleaning completed. (5B/1, 5B/2, 5B/3, 5B/4, 5B/5 completed)
6. CT 5A- Hot water basin Cleaning completed.
7. CT 5B- Hot water basin Cleaning Completed.
8. Riser valve sericing / repl. completed. (5A/1,2,3,4 Padmapur side & 5A/1, 3, 4, 6, 7, 8
chandrapur completed.) (Valve servicing completed.)
9. CT 5B-Riser valve sericing / repl. completed. (5B/2,4,7 Chandrapur side & 5B/4, 5, 6
Padmapur side repl. completed)
10. CT Fan 5A fan splash bar cleaning .(Padmapur & chandrapur side completed)
11. CT Fan 5B fan splash bar cleaning complted .
12. CT Fan 5A- broken hot water pipe replacement completed.
13. CT Fan 5B- broken hot water pipe repl. completed.
F. ACW / CCW PUMP : 1. ACW /CCW sump cleaning completed & strainer repairing / cleaning completed.
2. CCW-5C column pipe inspection & BFV servicing completed.
3. CCW-5D column pipe inspection completed. BFV servicing completed. Expansion joint repl.
completed.
4. CCW-5B BFV servicing completed.
5. CCW, ACW-thrust bearing oil replacement completed.
6. ACW-gland repl. completed.
7. CCW-5A, 5B gland repl. completed.
8. CCW-power pack oil replacement completed.
9. ACW line separation from CCW hot water line-completed.
10. Interconnection of existing CCW pipeline to CT 5C-completed
11. ACW underground line leakage-Attended.
97
G. SUMP MAKE UP, ACW, CCW, R-C VALVE SERVICING WORK 1. ACW air vent valve on disch. side servicing completed.
2. CCW air vent valve on disch. side servicing completed) bend replaced.
3. ACW R/C valve servicing 4nos. completed.
4. ACW return line drain valve 2 nos. servicing completed.
5. Sump make valve 2 no. servicing completed.
ELECTRICAL MAINTENANCE II
A) GENERATOR: 1. Exciter current carring bolt found leakage,same leakage attended.
2. Stator weidge tightness works done. Rotor wedge tightning carried out. Hydrogen compressor hub ir
value checked
3. Genertor stator winding hydraulic test along with bushings and phase connectors carried out. Leakage
at B phase bushing and stator inlet pressure valve found, leakage rate was 2 kg/cm2 per 24 hours,
same was attaneded. Generator stator IR value taken. IR value is in the range of 280 to 300 kohms.
4. Exciter rotor leakage test taken after attending c.c. Bolts leakage. 0.5 kg/cm2 n2 pressure drop
observed in 6 hrs.
5. Exciter air gaps checked
B) BATTERY CAPACITY TEST DURING COH-2015:
Sr.
No.
Battery Set
Name
Work Carried out Voltage (After Test)
Sp. Gravity (After Test)
Battery CapacityStart Stop
1Battery Set No. 1
01.01.16 02.01.16 246 Volts 1220 -1230 >100%
2Battery Set No. 2
04.01.16 07.01.16 246 Volts 1220 -1230>100%
3UPS Battery Set
12.01.16 19.01.16 243 Volts 1220 -1230>100%
98
G1 Battery Set
4
+24 V G1 Set23.01.16 24.01.16 28 Volts1 200-1205 >100%
-24 V G1 Set1 Damage cell found as per EXIDE battery, no capacity test was taken
G2 Battery Set
5
+24 V G2 Set17.01.16 18.01.16 28 Volts1 200-1205 >100%
-24 V G2 SetCleaning carried out, desulphation done, and battery charged
C) LT TRANSFORMERs COH-2015:
99
Sr.No. NAME OF TRANSFORMER
DATE OF P/M
1 LXB1 20.01.2016
2 LXA2 21.01.2016
3 XA 20.01.2016
4 XB 15.01.2016
5 OXA1 20.01.2016
6 OXA2 21.01.2016
D) HT TRANSFORMER WORK DURING COH-2015: 1. GTR – 5R:- Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
2. GTR– 5Y:- Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
3. GTR – 6B:- Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
4. UAT – 5A:-Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
5. UAT -5B:-transformer internal inspection, gasket and oil seal replacement, testing, cleaning and
painting carried out.
6. UAT – 5C:-Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
7. UAT – 5D:- transformer internal inspection, gasket and oil seal replacement, testing, cleaning and
painting carried out
8. SAT – 3A:-Transformer oil filtration, testing carried out.
9. SAT – 3B :-Transformer oil filtration, testing carried out.
E) BUSDUCT INSPECTION COH-2015
All above bus cleaning
work carried out as a preventive measure. Also 21KV Bus duct inspection carried out during COH-
2015, No abnormality found.
100
Sr.No.
NAME OF BUS
1 BUS OF UNIT BOARD 5A TO STN. BOARD SE 13
2 BUS OF UNIT BOARD 5A TO UAT A
3 BUS OF UNIT BOARD 5B TO STN. BOARD SE 15
4 BUS OF UNIT BOARD 5B TO UAT B
5 PT CUBICAL(GENERATOR)
6 BUS OF UNIT BOARD 5D TO UAT D
7 BUS OF UNIT BOARD 5D TO STN. BOARD SE 12/2
8 BUS OF UNIT BOARD 5C TO UAT C
F) PREVENTIVE MAINTENANCE OF HT MOTOR COH U # 5:
G) OVERHAUL / PREVENTIVE MAINTENANCE OF LT MOTOR COH-2015 :
101
Sr.No. NAME OF HT MOTOR OVERHAUL / P/M
1 ID FAN-5A Overhaul
2 ID FAN-5B PM
3 ID FAN-5C PM
4 ID FAN-5D Overhaul
5 CEP 5A PM
6 CEP 5C PM
7 BCW 5A PM
8 BCW 5B PM
9 BCW 5C PM
10 FD FAN 5A PM
11 FD FAN 5B Overhaul
12 PA FAN 5A Overhaul
13 PA FAN 5B PM
14 COAL MILL 5A Overhaul
15 COAL MILL 5B Overhaul
16 COAL MILL 5C PM
17 COAL MILL 5D PM
18 COAL MILL 5E PM
19 COAL MILL 5F Overhaul
20 COAL MILL 5G PM
21 COAL MILL 5H PM
22 MDBFP-5C PM
23 MDBFP-5D PM
24 ASDP 1 2 3 4 PM
25 BSDP 1 2 3 4 PM
26 CSDP 1 PM
Sr.No. NAME OF LT MOTOR Work
1 SEAL AIR FAN 5A O/H
2 SEAL AIR FAN 5B O/H
3 SEAL OIL PUMPAIR SIDE 1 MOTOR REPLACED
4 SEAL OIL PUMP AIR SIDE 2 O/H
5 PAH 5B S/B MOTOR O/H
6 PAH 5B MAIN MOTOR O/H
7 PAH 5AMAIN MOTOR O/H
8 PAH 5A S/B MOTOR O/H
9 CONTROL FLUID 5A O/H
10 CONTROL FLUID 5B O/H
11 BCW BOOSTER NO.1 O/H
12 BCW BOOSTERNO.2 O/H
13 CLINKER GRINDER 1A O/H
14 CLINKER GRINDER 1B O/H
15 CLINKER GRINDER 2A O/H
16 CLINKER GRINDER 2B O/H
17 VACUUM PUMP 5B PM
18 MOT AOP-1 O/H
19 MAIN JOP AC O/H
20 DC SEAL WATER PUMP 1 & 2 PM
21 IAC-5A, B, C PM
22 TDBFP-5A-AOP-1 & 2 O/H
23 TDBFP-5B-AOP-1 & 2 O/H
24 HP AWP-1 & 3 PM
25 MDBFP-5C AOP O/H
26 MAIN DC JOP PM
27 C/M LOP – 5 C, D, G, H PM
28 C/F- 5A, B, C, F PM
29 AC SCANNER O/H
30 SAH-5A MAIN O/H
31 SAH-5B MAIN O/H
H) REVENTIVE MAINTENANCE OF BOARDS in COH U # 5:
Sr. No. NAME OF BOARDS
1 UNIT BOARD-5A
2 UNIT BOARD-5B
3 UNIT BOARD-5C
4 UNIT BOARD-5D
5 UNIT BOARD-5E
6 5MB BOARD
7 5MC BOARD
8 5MD BOARD
9 5ME BOARD
10 5MF BOARD
11 5MG BOARD
12 SOOT BLOWER BOARD
13 EMPA SECTION -I
102
13 EMPA SECTION -II
14 PA SECTION -I
15 PA SECTION-II
16 STATION BOARD INCOMER BREAKER
17 ESP A PASS LT BOARD
18 ESP B PASS LT BOARD
19 ESP C PASS LT BOARD
20 ESP D PASS LT BOARD
21 AHP HT SECTION-I
22 AHP HT SECTION -II
INSTRUMENTATION AND CONTROL
1. ALL HAG SOLENOID SERVICING DONE.
2. C/M DP S/W’S CALIBRATED.
3. BURNER TILT ALL INST. SERVICING DONE
4. FRF TANK LVL. S/W CALIBRATED
5. ALL C/M SEAL/PA DP S/W’S IMPULSE LINE FLUSHING DONE
6. ALL C/M SEAL/PA DP JB CLEANING DONE
7. SADC P/C AND POSITIONER SERVICING DONE
8. C/M THRUST PAD RTD, SEAL AIR V/V CHECKING AND TRIAL TAKEN. LUB. OIL SYSTEM
PRESS. S/W AND GAUGESCALIBRATION DONE
9. MOT LVE S/W’SCALIBRATED
103
10. ESP PASS, ECONOMISER DUCT HOPPER ASH V/V POWER CYLINDER AND SOLENOID
SERVICING DONE.
11. ID – A TO D SUCTION/DISCHARGE PRESSURE TRANSMITTERS IMPULSE LINE FLUSHING
DONE
12. PA FLOW TRANSMITTERS CALIBRATED
13. REJECT GATE & HAG GATE SERVICING DONE & TRIAL TAKEN.
14. ID – A TO D JB CLEANING DONE.
15. ESP ASH valve POWER CYLINDER AND SOLENIED SERVICING AND TRIAL TAKEN.
16. SECONDARY AIR FLOW TRASNMITER AND FURNACE PRESSURE TRANSMITTER
CALIBRATION DONE.
17. PA HEADER PRESSURE SWITCHES CALIBRATED
18. C/M A, B, C LOP PRESS. S/W’S CALIBRATED AND RESTORED.
19. ALL A/H,FURNACE DRAFT PRESSURE/DP TRANSMITTERS IMPULSE LINE FLUSHING DONE
20. FURNACE PRESSURE SWITCHES CALIBRATED.
21. FUR /WB, A /H FG DP TRANSMITTER CALIBRATED.
22. ELEATION CORNER SOLENOID AND HAG SOLENOID REPAIR/SERVICING DONE
23. ESP- ASH VALVE SEAL KIT REPLACED WITH NEW ONE. ESP MAIN WATER V/V P/C REPLACED
WITH HEALTHY P/C SINCE OLD ONE was PASSING.
24. FIRST STAGE PRESS. TRANSMITTER AND THROTTLE PRESS. TRANSMITTER CALIBRATION
done.
25. ALL IGNITOR ASSEMBLY SERVICING COMPLETED.
26. HP BYPASS SYSTEM BP-1&2, FOD-1&2, BD V/V SERVO/SOLENOID V/V SERVICING done.
27. MAIN TURBINE L.O. SYSTEM PRESS. S/W’S, HPCF PUMP PRESS S/W’S calibrated. SEAL OIL
SYSTEM PRESS. S/W CALIBRATION done.
28. BOTTOM ASH P/CSERVICING done.
29. ID FAN-A, B, C, D PRESS. S/W’S CALIBRATED.
30. SEAL OIL SYSTEM PRESS S/W’S CALIBRATED.
31. IPT OUTER CASING T/C, HPT CASING T/C AND IPT CASING CHECKING DONE
32. HPSV AND IPSV LIMIT SWITCHES REPAIRING/ CHECKING DONE.
33. INST. AIR DRIER P/C CHECKED, FOUND PASSING, REPAIR WORK done.
34. C/M LRG & TIG P/C CHECKING DONE.
35. FLAME SCANNER SERVICING done.
36. ALL A/H JB AND TRB CLEANING AND IMPULSE LINE REPAIR WORK done.
37. ID FAN A, B, C, D LO FILTER DP S/W’S CALIBRATED.
104
38. DEAERATOR SHELL PRESS. TRANSMITTER, CONDENSATE FLOW TO DEAERATOR
TRANSMITTER, DM MAKEUP FLOW TRANSMITTER, SEAL STM. HDR PRESS. TRANSMITTER
CALIBRATED.
39. C/M CONTROL DAMPER CALIBRATED.
40. HPCV & IPCV LIMIT S/W’S SERVICING AND REPAIRING DONE.
41. GEN. LIQUID LEVEL DETECTOR, LLD CHECKED FOUND HEALTHY
42. FD FAN-A IGV ACTUATOR MOTOR CHECKED
43. SEC. AIR FLOW AEROFILE (LEFT SIDE) FLUSHING DONE.
44. HP BYPASS SYSTEM SERVO VALVE LINE FLUSHING DONE.
45. INST. AIR DRIER EXHAUST V/V (SV3) P/C SEAL KIT REPLACED.
46. BOTTOM ASH P/C SEAL KIT REPLACEMENT WORK DONE.
47. SEC. AIR FLOW AEROFILE (RIGHT SIDE) FLUSHING DONE.
48. IPT INNER CASING T/C REMOVED.
49. PRIMARY WATER PUMP PRESS. S/W’S CALIBRATED AND RESTORED.
50. BFP-A, B, C, D SUCTION FLOW TRANSMITTER, CEP DISCHG. FLOW TRANSMITTER
CALIBRATED.
51. DAS PEM PACKAGE VALIDATION AND DAS CONTROLLER CHECKING WORK CARRIED OUT.
PEM PACKAGE OUTPUT REPORT SEND TO POG FOR VALIDATION.
52. CEP DISCHG. FLOW TRANSMITTER, CONDENSOR VACCUM TRANSMITTER CALIBRATED.
53. SEAL STEAM SYSTEM MAW-10, 50 V/V FILTER CLEANING, and OIL TOP UP DONE.
54. C/M D MILL O/L T/C AND ITS CABLE REPLACED WITH NEW ONE.
55. GEN. EXCITER TEMP. S/W’S CALIBRATED.
56. HOTWELL LEVEL VERY LOW S/W’S HEALTHINESS CHECKED FOUND OK.
57. GEN. EXCITER TEMP. S/W’S CALIBRATED.
58. S/H & R/H FLOW TRANSMITTER, FEED WATER FLOW TRANSMITTER CALIBRATED.
59. DR-17, 25 V/V INST. CALIBRATED.
60. O2 IN FG (LEFT AND RIGHT SIDE) PROBE INSPECTION, CLEANING AND CONNECTION
TIGHTENING CARRIED OUT.O2RIGHT SIDE PROBE SHIELD FOUND WORN OUT, SAME IS
REPAIRED BY PATCH WELDING.
61. HP BYPASS SYSTEM SERVO V/V SERVICING/REPAIRING DONE.
62. C/M HOT AIR GATE TRIAL TAKEN AND FEED BACK LIMIT SWITCHES CHECKED. 03 NOS.
FEED BACK LIMIT SWITCHES FOUND MALFUNCTIONING; ITS REPAIR WORK DONE.
63. ID FAN-A, B, C, D DISCHG. PRESS. TRANSMITTER CALIBRATED.
64. DR-39, 43 AND DM-2, 17, 21 V/V INST. SERVICING AND CALIBRATION DONE.
65. DEAERATOR LVL.TRANSMITTER CALIBRATED.
105
66. SADC POSITIONER CALIBRATED.
67. “A” SERIES SUMP LVL SENSOR SERVICED AND REPAIRED.
68. CD-81, 85, MDBFP-D R/C V/V INST. SERVICING AND CALIBRATION DONE.
69. MAIN TURBINE STARTING DEVICE LIMIT SWITCHES SERVICING DONE.
70. MAIN TURBINE GOVERNING RACK PRESSURE GAUGES CLEANING AND CHECKING DONE.
03 NOS. FAULTY GAIGES REPLACED WITH NEW ONE.
71. MAIN TURBINE JOP LINE PRESSURE GAUGES (03 NOS.) REPLACED WITH NEW ONE.
72. FSSS PANEL BNC CONNECTOR TIGHTENING CARRIED OUT.
73. BFP-A, B, C R/C V/V INST. SERVICING, NORMALISATION AND CALIBRATION DONE.
74. DR-32 V/V CALIBRATED.
75. GENERATOR PRE CHAMBER LLD AND RTD RESTORED.
76. MDBFP-C,D R/C V/V REMOTE TRIAL TAKEN.
77. MAIN TURBINE TSE SYSTEM T/C (50% AND 100%) CHECKING DONE.
78. MAIN TURBINE SPEED PROBE CHECKING CARRIED OUT.
79. FD-49 P/C SEAL KIT REPLACED AND V/V CALIBRATED.DR-6,13 V/V INST. SERVICING AND
CALIBRATION DONE.
80. BOILER STM. O/L PRESS. TRANSMITTER ,GEN. MAIN BUSHING FLOW TRANSMITTER
CALIBRATED.
81. FSSS FLAME FAILURE TRIP LOGIC ALL ELEVATION “ELEVATION 2/4 FLAME” INPUT
SIGNAL RELOCATED(DISTRIBUTED) IN TWO I/P CARDS (EARLIER SIGNAL IS INPUTTED
THROUGH SINGLE I/P CARD) AND ACCORDINGLY PROGARM IS MODIFIED.
82. HPCF TEMP. CONTROL V/V CALIBRATION DONE.
83. GEN. MAIN BUSHING FLOW TRANSMITTER AND STATOR WATER FLOW TRANSMITTER
CALIBRATED.
84. FD FAN-5B FAN BRG NDE SIDE RTD FOUND FAULTY, REPLACED WITH NEW ONE.
85. PA FAN-5A 01 NOS. JB FOUND RUSTED AND DAMAGED, SAME IS REPLACED WITH NEW
ONE.
86. OHP R/C V/V HO-11 & LO-11 INST. SERVICING AND CALIBRATION DONE.
87. 02 NOS. DAS CONTROLLER (REMAINING FAULTY CONTROLLER) CHECKED , 01 NO. DAS
CONTROLLER REPAIRED AND PUT IN SERVICE.01 NO. DAS CONTROLLER
MOTHERBOARD FOUND FAULTY.
88. MAIN TURBINE IPT BOTTOM CASING T/C (04 NOS) HEALTHINESS CHECKED,FOUND OK. ITS
CABLE DRESSING DONE.
89. HPBP SYSTEM OSU-1 ACUUMULATOR N2 GAS FILLING DONE. OSU-2 ACUUMULATOR N2
GAS FILLING DONEAAFTEWR BLADDER REPLACEMENT.
106
90. HPBP SYSTEM FOD BOTH ACCUMULATOR BLADDER FOUND PUNCTURED.
91. DR-02,,09,21,29,32 V/V INST. SERVICING AND CALIBRATION DONE.
92. HOT WELL TRANSMITTER CALIBRATION CARRIED OUT.
93. FD FAN-5A MOTOR ALONG WITH DRIVE CHECKED, MOTOR FOUND HEALTHY.
.
TESTING II
A) GENERATOR:
1. Generator Protection Panel Micom Relay testing.
2. Generator PT fuses replacement.
3. Generator Stator, Rotor, Main exciter, Pilot exciter – IR and Winding Resistance.
4. Exciter Diode Wheel diodes and Fuses checking.
5. Generator, GTR and UAT— protection/metering CT resistance measurement.
6. GCB ON/OFF and protection Trip Trial from PCR in co-ordination with 400KV GCR.
7. Unit Switchgear A, B, C and D – Incomer, Tie I/C and outgoing feeder Relay testing
8. Generator Rotor Earth Fault (REF) protection, CarbonBrush holder assembly internal wiring checking
9. Generator Dynamic testing completed at 0055 Hrs on 30.01.2016 and unit synchronized at 02.06.Hrs
on 30.01.2016.
Gen. Stator Resistance by TRM 104 using LR Meter wires:
R1-R2 resistance Y1-Y2 resistance B1-B2 resistance
1.694 mΩ 1.581 mΩ 1.589mΩ
B) GENERATOR ROTOR :
a) Gen. Rotor IR
Rotor IR values taken at ambient temp. = 32.00 C by 250 V Megger = > 50 MΩ
107
b) Gen. Rotor Resistance
Rotor winding resistance by LR 205 micro ohmmeter= 113.61 mohm and
Ambient temperature 320C
c) Gen. Rotor Impedance (Taken by Single phase Variac 15amp range)
Sr.
No.
AC volt applied Current in Amps.
V/I
Impedence
Freq.
Hz
1 10.35 2.99 3.461 49.96
2 20.45 5.96 3.431 49.96
3 30.43 8.79 3.461 49.97
4 40.23 11.59 3.471 49.99
5 45.06 12.93 3.484 49.95
Megger after rotor imp test > 50 MΩ
C) MAIN EXCITOR :
a) Exciter Upper & lower half field winding
Excitor Field Winding LOWER & UPPER Half Connected to each other
Megger value by 250 V Megger > 50 Mohm
Resistance by LR 205 Meter = 540 mohm ( Temp = 320 C )
b) Exciter Stator resistance
Main Exciter Armature Windings
R - Y 0.218 mohmMeasured at + Ve Wheel side
( + Ve WHEEL Towards Exciter )Y - B 0.214 mohm
B - R 0.226 mohm
Main Exciter Armature Windings
TEST RESULT OF GEN. TESTING (STATOR, ROTOR, EXC, PILOT EXC. & CAPA.
108
Main Excitor Armature Windings
R - Y 0.220 mohmMeasured at -- Ve Wheel side
(- Ve WHEEL Towards Generator )Y - B 0.222 mohm
B - R 0.225mohm
c) Exciter IR Values
A) Megger By 250 V Megger : Neutral To Shaft > 50 Mohm
B) Megger By 250 V Megger : + Ve Wheel To
- Ve Wheel = 0 Mohm ( Rev.Bias)
C) Megger By 250 V Megger : + Ve Wheel To - Ve Wheel => 50 Mohm (Forward Bias)
D) + Ve Wheel To Body > 50 Mohm
E) - Ve Wheel To Body > 50 Mohm
d) Quadrature coil
Quadrature Coil Res. Measurement IR Value
A) COIL 1 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C ) IR > 50 Mohm
B) COIL 2 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C ) IR > 50 Mohm
Main Excitor Armature Windings
R - Y 0.220 mohm Measured at -- Ve Wheel side
109
(- Ve WHEEL Towards Geneator )Y - B 0.222 mohm
B - R 0.226mohm
e) Exciter IR Values
A) Megger By 250 V Megger : Neutral To Shaft > 50 Mohm
B) Megger By 250 V Megger : + Ve Wheel To - Ve Wheel = 0 Mohm ( Rev.Bias)
C) Megger By 250 V Megger : + Ve Wheel To - Ve Wheel => 50 Mohm(Forward
Bias)
D) + Ve Wheel To Body > 50 Mohm
E) - Ve Wheel To Body > 50 Mohm
f) Quadrature coil
Quadrature Coil Res. Measurement IR Value
A) COIL 1 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C ) IR > 50 Mohm
B) COIL 2 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C ) IR > 50 Mohm
D) PMG (Pilot Exciter)
a) Pilot exciter resistance measured by LR-205 At Temp.= 32 0C
R-Y Res. B-Y Res. R-B Res. R-N Res. R-N Res. R-N Res.
5.68mOhm 5.70mOhm 5.69mOhm3.10mOhm 3.14mOhm 3.15mOhm
110
b) IR Value by 250 V hand operated megger > 50 Mohmc) Unit Aux Boards1. Unit Board A, B, C &D – Incomer and Tie I/C Breaker timing and contact resistance measurement.2. Unit Boards - A, B, C & D – Bus Transfer Scheme (BTS) trials
E) VALVES : 1. ACTUATOR VALVES - TURBINE SIDE
SNValve
no.Description
Connections removed
Cabling
& LS setting
Trials taken
1 FD 44 HPH 5A-6A Inlet valve
2 EX 31 TDBFP 6A Exhaust valve
3. EX 1 Extraction to HPH 6A
111
4. EX 2 Extraction to HPH 6B
5. EX 2A Extraction to HPH 6B
6. EX 3 Extraction common to HPH 6A & 6B
7. EX 4 Extraction to HPH 5A
8. EX 4A Extraction to HPH 5A
9. EX 5 Extraction to HPH 5B
10. EX 5A Extraction to HPH 5B
11. EX 6 Extraction to Deareator
12. AS 2 Aux. steam to Gland Steam Iso Valve
13. AS 4 Aux. steam to Deareator Main Iso
14. AS 12 Aux. steam to Deareator Bypass Iso
15. EX 34 Gland steam from CRH Iso valve
16. DR 4 HPH 6A Drip to HPH 5A Bypass Already removed
17. DR 11 HPH 6B Drip to HPH 5B Bypass
18. DR 19 HPH 5A Drip to Deareator Bypass
19. DR 27 HPH 5A Drip to Deareator Bypass
20. MS 502 HPCV 1 Strainer Drain
21. MS 504 HPCV 2 Strainer Drain
22. MS 506 HPCV 3 Strainer Drain
23. MS 508 HPCV 4 Strainer Drain
24. HR 502 IPCV 1 Strainer Drain
25. HR 504 IPCV 2 Strainer Drain
26. HR 506 IPCV 3 Strainer Drain
27. HR 508 IPCV 4 Strainer Drain
28. HR 113 LPBP Warm up Drain
29. HR 115
30. HR 108
31. Mal 11 HPCV1 to Turbine Line Drain
32. Mal 12 HPCV2 to Turbine Line Drain
33. Mal 13 HPCV3 to Turbine Line Drain
112
34. Mal 14 HPCV4 to Turbine Line Drain
35. Mal 22 HP Turbine Casing Drain
36. MS-104
2. ACTUATOR VALVES - BOILER SIDE
SN Valve
no.Description Connections
removedCabling & LS setting
Trials taken
1) . MS201 Main Steam
2) MS203 Main Steam
2) S 37 Superheat Spray
3) S 38 Superheat Spray
4) S 39 Superheat Spray
5) S 40 Superheat Spray
6) B 55 Drum Vent
7) B 56 Drum Vent Motor NA
8) B 57 Drum Vent
9) B 58 Drum Vent
10) B 72 Drum Vent
11) B 73 Drum Vent
12) B 74 Drum Vent
13) B 75 Drum Vent
14) S 76 Start-up Vent
15) S 77 Start-up Vent
16) S 78 Start-up Vent
17) S 79 Start-up Vent
18) R 19 Reheat Spray
19) R 20 Reheat Spray
20) R 21 Reheat Spray
21) R 22 Reheat Spray
113
22) FD 50 Feed line Main
23) FD 50A Feed line Main
24) GD 1A Gas Damper
25) GD 1B Gas Damper
26) GD 3A Gas Damper Actuator
NA27) GD 3B Gas Damper Actuator
NA28) FD 40 Feed line Main
29) BS 4 EBD
30) BS 5 EBD
31) E 19 Economizer Inlet
32) FD 47 Full Load Line
33) GD41
34) GD4A1
35) GD4B2
36) GD 4B2
37) GD 6A1 ESP A-Pass inlet damper
38) GD 6A2 ESP A-Pass inlet damper
39) GD 6B1 ESP B-Pass inlet damper
40) GD 6B2 ESP B-Pass inlet damper
41) GD6C1 ESP C-Pass inlet damper
42) GD6C2 ESP C-Pass inlet damper
43) GD6D1 ESP D-Pass inlet damper
44) GD6D2 ESP D-Pass inlet damper
45) GD 7A ESP A-Pass outlet damper
46) GD 7B ESP B-Pass outlet damper
47) GD 7C ESP C-Pass outlet damper
48) GD 7D ESP D-Pass outlet damper
F) GTR R, Y, B :
114
1. GRP cubical panel 1-GT, Transformer Differential relay (87GT-1, 87GT-2) and Transformer
overall differential relay (87OA-1, 87OA-2) testing work carried out. Cubical panel 1G, Relay 50Z1
and 50Z2 testing work carried out.
2. GTR- Y phase, UAT-5A transformer testing work carried out.
3. GTR- R, Y and B oil pumps auto pick-up trials taken.
G) PLANT AUXILIARIES
1. GTR - R, Y, B Transformer testing and Buchholz protection Trial.
2. GTR - R, Y, B – HV Bushing Tan-delta and Capacitance measurement.
3. GTR R, Y and B,oil pumps ON/OFF and changeover trial.
4. UAT- A, B, C and D Transformer testing.
5. GTR - R, Y, B – Water flow switch servicing.
6. GTR and UAT – OTI and WTI calibration.
7. UAT- A, B, C and D Transformer Buchholz protection Trial.
8. GTR R, Y, B and UAT A to D, Buchholz local JB and RTD JB, polythene wrapping.
9. Generator Protection Panel Micom Relay testing.
10. Generator PT fuses replacement.
11. Generator Stator, Rotor, Main exciter, Pilot exciter – IR and Winding Resistance.
12. Exciter Diode Wheel diodes and Fuses checking.
13. Generator, GTR and UAT— protection/metering CT resistance measurement.
14. GCB ON/OFF and protection Trip Trial from PCR in co-ordination with 400KV GCR.
15. Unit Switchgear A, B, C and D – Incomer, Tie I/C and outgoing feeder Relay testing.
16. MDBFP-5C and D, Motor feeders relay testing.
17. Unit Board A, B, C &D – Incomer and Tie I/C Breaker timing and contact resistance measurement.
18. Unit Boards - A, B, C & D – Bus Transfer Scheme (BTS) trials.
19. LT Boards - EMPA,PA,ME Incomer feeder relay testing.
20. LT Boards - EMPA, PA control connection tightening.
21. PA Boardoutgoing feeders relay testing.
22. MA, MB, MC, MD, ME and MG Board I/c and Control supply panel indication lamp replacement.
23. DG set auto pick up trial.
24. Station Boards – SE11/1, SE11/2, SE12/1 and SE12/2 –normal I/C relay testing.
25. Station Transformer ST-3,HT side Protection Panel relay testing.
26. Station Transformer ST-3, R & B phase Lightening arrester checked found OK and Y phase
Lightening arrester replaced by 400 KV GCR.
27. Compressor Board - 5E Incomer and motor feeder relay testing work.
115
28. Generator Rotor Earth Fault (REF) protection, CarbonBrush holder assembly internal wiring checking.
29. UPS filter cleaning and Fan replacement.
30. Bottom Ash panel cleaning and connection tightening.
31. IAC/SAC Compressor control panel cleaning and TB tightening work.
32. AHP HT Board Relay testing.
33. 220 V Battery charger No.2, panel cleaning and condenser replacement.
34. 220 V Battery charger No.1 panel cleaning.
35. +/- 24V Battery charger G1 and G2 panel cleaning and condenser replacement.
36. PAH and SAH, Rotor stop indication L/S restoration.
37. Hot keys provided for DC Seal water pump A/B and EOP of TDBFP A/B.
38. ALL ESP fields OC test after clearance from BM-II and EM-II.
39. ID, FD, PA, CEP, BCW, MDBFP and C/M breaker protection trial.
40. Motorized valve L/S setting and trials after completion of BM (38) and TM (35) work.
41. CCW pump house,CW(11 KV) and CWS(3.3KV) Board Incomersand outgoing feeders relay testing.
42. ACW, CCW control panelcleaning and connection tightening.
43. CCW BFV local panel connection tightening and local JB polythene wrapping.
44. CTPA Board relay testing and connection tightening.
45. CWX-A &B Transformer, OTI/WTI calibration.
46. 5CWXA/XB/XC and 5CTXA/XB, transformer Buchholz’s alarm and trip protection trials.
47. CCW-A, CCW-C and CCW-D control panel annunciator replacement.
48. ACW and CCW pumps breaker protection trial.
49. Major modifications carried out
50. 100% Stator E/F protection, 40MW interlock introduced in MICOM 343 relay as approved by
competent authority.
51. Hot keys provision at PCR for EOP of TDBFP A/B and DC seal water pump A/B.
52. Following relays found faulty, same replaced with spare relays.
SE11/1, Incomer Y phaseOver current relay (CDG63).
PA Fan 5A, Motor protection relay (SPAM150)
5DBoard, TIE to CCW, E/F Relay (IBX164)
RWP- NDM pump B, Motor protection relay(CTMM)
53. Works carried out from 400 KV GCR side,
54. The Measurement of Tan delta & capacitance of R-phase synchronizing PT is done.
55. The IR of R, Y & B-phase L.A.'s of GT-5 is carried out. During, taking IR, the IR value of B-phase L.A.
of GT-5 is found low and hence, the B-phase L.A. is replaced by new ALSTOM make L.A.
56. Maintenance of CB & PG isolators is carried out.
116
57. The 01 no. disc insulator string of R-phase in gantry near to canteen is replaced.
58. Generator Dynamic testing completed at 0055 Hrs on 30.01.2016 and unit synchronized at 02.06.Hrs
on 30.01.2016.
U # 5 GENERATOR SCC : Date of test :- 29/01/2016
SR. NO. GEN. AMP
QUADRATURE. COIL
VOLT( CJN04
PANEL ) TB- LA005- 101 &
102
MANUAL
POT. POSN( CJN0
4 PANEL
)
AUX. EXC.VOLT( - L TO +
L)( CJN
01 PANE
L )
AUX. EXC. FIELD AMP. (mV ACROSS
SHUNT)( CJN01 PANEL
)CA003(m)
(150A/60 mv)CA004(a)
(150A/60 mv)
UST (DQ069-
H2)( CJN04 PANEL
)
GENERATOR PT VOLTAGE FIELD AMP
PT ICJJ09-
X01-RY/YB/B
RVolts
PT IICJJ09-
X01-RY/YB/B
RVolts
PT III CJJ09-
X01-RY/YB/B
RVolts
COD 8
METER
Previous 2100 A 2.75 V 0.854.56
V2.65mV/2.4mV (-)448
mV1.81 V (avg)
1.79 V (avg)
1.79 V (avg) 200 A
1 1997 A 3.60 V 0.85.13
V2.71 Mv/2.73mV (-)425
mV1.72V (avg)
1.69 (avg)
1.70 (avg) 180 A
Previous 9900 A 16.22 V 3.77 23.46 V 14.5mV/14.4mV (-)765
mV8.48 V (avg)
8.45 V (avg)
8.44 V (avg)
1600 A
2 10110 A 16.34 V 3.8 22.32
V15.13 mV/15.20
mV(-)746
mV8.62 (avg)
8.58 V (avg)
8.60 V (avg)
1400 A
U # 5 GENERATOR OCC :
SR. NO. GEN. VOLT
QUADRATURE. COIL VOLT
( CJN04 PANEL ) TB- LA005- 101 &
102
MANUAL POT. POSN
( CJN04 PANEL )
AUX. EXC.VOLT
DC( - L TO
+ L)( CJN01 PANEL
)
AUX. EXC. FIELD AMP.
(mV ACROSS SHUNT)( CJN01 PANEL )
CA003(m) (150A/60mv)
CA004(a) (150A/60 mv)
UST DC Volts
(DQ069-H2)MAN( CJN04 PANEL )DC091-S2(A)
AVR PT VOLT ( CJN-04 )
FIELD AMP
COD 8 METER
RYLA010-251A-252A
& WA-511-512
YBLA010-252A-253A
& WA-512-513
BRLA010-253A-251A
& WA-513-511
Previous 19.5 KV 11.42 V 2.55 16.17 9.1mV/9.2mV (-)635mV/
95.1/94.9 V
95.2/95.2 V
95.2/95.2 V 0
117
(-)1.01 V
1 21.1 KV 13.08 V 2.98 18.71 11.14 mV/10.91 mV
(-)660mV/ 105.06 / 105.37 / 105.38 / 0
(-)9.2 V(pot 4.5) 105.28 V 105.31 V 105.35 V
GENERATOR DYNAMIC TEST :Date of test :29/01/2016
* GENERATOR SHORT CKT TESTGENERATOR PROTECTION RELAY GPR-1 & 2 ( P-343 )
Sr. No
RELAY CT NO. & CTR
NEW TB NO.
MEASURED CURRENT READINGPrevious( 210
0 A)Previous( 9900
A )Current (2008A)
Current (10080A )
Measure-1
GPR-1 (Pri.)
GPR-2 (Sec.)
GPR-1 (Pri.)
GPR-2 (Sec.)
GPR-1 (Pri.)
GPR-2 (Sec.)
GPR-1 (Pri.)
GPR-2 (Sec.)
1 GPR 1&2, P-343,
87G AND OTHER
PROTECTION (GEN.
DIFF.)
CT D1 20000/5
A NEU.SIDE BIAS-1
1G,TB-1-15 IA-1
2105 A 526 mA 9881 A 2.47 A
1990 A
0.497 A 10000 2.52 A
13 IB-12101
A 524 mA 9887 A 2.47 A1986
A0.498
A 10000 2.53 A
11 IC-12112
A 526 mA 9927 A 2.48 A1994
A0.498
A 10000 2.53 ANeutral-
9Measur
e-3
CT D2 20000/5
A HV SIDE
BIAS-2
1G,TB-1-1 IA-2
2111 A 527 mA 9886 A 2.47 A
1970 A
0.495 A 10000 2.52 A
3 IB-22105
A 526 mA 9865 A 2.47 A1978
A0.495
A 10000 2.51 A
5 IC-22099
A 528 mA 9926 A 2.47A1991
A0.497
A 10000 2.51 ANeutral-
7Measur
e-3
SPILL
I(A) Diff. 0 mA 0 mA 0 mA 0 mA 0 0 0 0I(B) Diff. 0 mA 0 mA 0 mA 0 mA 0 0 0 0
I(C) Diff. 0 mA 0 mA91.50
A 18 mA 0 0 0 0.017Measur
e-3I(A) Bias 2104
A526 mA 9883 A 2.47 A 1974
A0.497
A10000 2.52 A
118
I(B) Bias 2099 A 525 mA 9877 A 2.47 A
1971 A
0.496 A 10000 2.52 A
I(C) Bias 2115 A 529 mA 9930 A 2.48 A
1978 A
0.498 A 10000 2.52 A
Measure-1
CT P 200/1 A
1G,TB-1-18
IN Measure Magnitu
de
0.0 A 0.0 A 0.0 A 0.0 A 0 0 0 0
19NGT(95
%) 18K/24
0V
1G-TB1-48
VN Measure Magnitu
de
0 V 663 mV 3.2 V 0.0 V 0 0 0 0
49Measur
e-3100% S-
E/FVN 3rd Hrm. 49 V
652.2 mV
237.9 V
3.171 V
46.84 V
621.7 V 254
3.229 V
GEN. TRANSFORMER RELAY 87GT-1 and 87GT-2 ( P-642 )
Sr. No
RELAY CT NO. & CTR
NEW TB NO.
Previous ( 2100 A )
Previous( 9900 A )
Current (2010 A)
Current ( 10000A )
Measure-1
87GT-1 (Pri.)
87GT-2 (Sec.)
87GT-1 (Pri.)
87GT-2 (Sec.)
87GT-1 (Pri.)
87GT-2 (Sec.)
87GT-1 (Pri.)
87GT-2 (Sec.)
2
87GT 1&2,
P-642, AND
OTHER PROTECTI
ON ( TRANS.
DIFF. )
BCT-2 1000/
5 A HV
SIDE BIAS-1
1GT-TB1-45 IA-1 107 A 535 mA 508 A 2.54 A
101.1 A
0.506 A
0.519 A 2.59 A
47 IB-1 105 A 530 mA 505 A 2.52 A100.3
A0.505
A0.518
A 2.58 A
49 IC-1 107 A 533 mA 507 A 2.53 A100.8
A0.502
A0.518
A 2.58 ANeutral-
51
Measur
e-1
BCT-6+7
12000/5 A LV
SIDE BIAS-2
1GT-TB1-57 IA-2 2100 A 875 mA 9913 A 4.13 A 1982 A
0.827 A
10140 A 4.22 A
59 IB-2 2100 A 872 mA 9897 A 4.12 A 1977 A0.828
A10120
A 4.21 A
61 IC-2 2130 A 879 mA 9965 A 4.15 A 1993 A0.840
A10180
A 4.23 ANeutral-
63
Measur
e-2 SPILL I(A) 0.003 0.004 0.016 0.016 0.004 0.004 0.017 0.017
119
Diff. PU PU PU PU PU PU PU PU
I(B) Diff.
0.004 PU
0.004 mA
0.016 PU
0.016 PU
0.004 PU
0.004 PU
0.017 PU
0.017 PU
I(C) Diff.
0.004 PU
0.004 mA
0.016 PU
0.016 PU
0.004 PU
0.004 PU
0.017 PU
0.016 PU
Measur
e-2
I(A) Bias
0.125 PU
0.125 PU
0.594 PU
0.593 PU
0.119 PU
0.120 PU
0.607 PU
0.607 PU
I(B) Bias
0.125 PU
0.125 PU
0.593 PU
0.594 PU
0.119 PU
0.119 PU
0.604 PU
0.602 PU
I(C) Bias
0.125 PU
0.125 PU
0.594 PU
0.594 PU
0.119 PU
0.119 PU
0.607 PU
0.606 PU
GT HV SIDE S/B BACKUP E/F(51 NGT)
Measur
e-1 BCT-4 1000/
1 A
1GT-TB1-53
IN-HV Measd Mag.
0 03.124
A 0.0 A2.163
A 0 0 055
GENERATOR AND TRANSFORMER PROTECTION 870A-1 & 2 ( P-645 )
Sr. No
RELAY CT NO. & CTR
NEW TB NO.
Previous(2100 A)Previous(990
0 A)Current(2010
A)Current(1001
0A)
Measure-1 87OA-1
(Pri)
87OA-2 (Sec) 87OA-
1 (Pri)
87OA-2
(Sec)87OA-1 (Pri)
87OA-2
(Sec)87OA-1 (Pri)
87OA-2
(Sec)3 87 OA 1
& 2 P645 CT
CORE-1 1GT-
TB1-1IA-1 106 A 107 mA 509 A 508
mA100 A 0.101
A520.8
A0.518
A
120
AND OTHER
PROTECTION
1000/1 A HV SIDE BIAS-1
3 IB-1 106 A 107 mA 506 A507 mA 98 A
0.103 A
518.5 A
0.514 A
5 IC-1 106 A 106 mA 508 A507 mA 100 A
0.102 A
520.4 A
0.520 A
Neutral-7
Measu
re-1
CT A 20000/5 A GEN.(N)SIDE BIAS-2
1GT-TB1-9 IA-2 2100 A 521 mA
9920 A 2.48 A
1988 A
0.496 A
10130 A
2.526 A
11 IB-2 2100 A 521 mA9900
A 2.43 A1979
A0.497
A10110
A2.523
A
13 IC-2 2100 A 520 mA9970
A 2.49 A2009
A0.502
A10170
A2.543
ANeutral-
15
Measu
re-3
SPILL
I(A) Diff.
0.003 mA
0.002 mA
0.015 mA
0.014 mA
0.004 mA
0.003 mA
0.019 mA
0.016 mA
I(B) Diff.
0.003 mA
0.002 mA
0.015 mA
0.015 mA
0.003 mA
0.004 mA
0.016 mA
0.015 mA
I(C) Diff.
0.003 mA
0.004 mA
0.016 mA
0.015 mA
0.003 mA
0.003 mA
0.014 mA
0.015 mA
Measu
re-3
I(A) Bias 0.125 A 0.125 A
0.595 A
0.595 A
0.120 A
0.118 A
0.607 A
0.607 A
I(B) Bias 0.125 A 0.125 A
0.594 A
0.594 A
0.119 A
0.118 A
0.606 A
0.606 A
I(C) Bias 0.125 A 0.126 A
0.595 A
0.595 A
0.119 A
0.118 A
0.607 A
0.605 A
GTR REF 64GT
Measure-1
BCT 3+5 R ph
1000/1A
1GT, TB1-33
IN-TV(R
Ø) 0 0 0 0 35
Spill Across Stab. Res. ( 1GT-Panel )
SRR - 122 mV/ 0.42 mA
SDR - 122 mV
SRR - 132.6 mV
SDR - 132.8 mV
BCT 3+5 Y ph
1000/1A
1GT,TB1-37
IN-LV(Y
Ø) 0 0 0 0 0 0 0 039
Spill Across Stab. Res. ( 1GT-Panel )
SRY - 322 mV/ 1.46 mA
SDY - 322 mV
SRY - 337.8 mV
SDY - 313.01 mV
BCT 3+5 B ph
1000/1A
1GT,TB1-41
IN-HV(B
Ø) 0 0 0 0 0 0 0 043
121
Spill Across Stab. Res. ( 1GT-Panel )
SRB - 157 mV/ 0.255 mA
SDB - 156 mV
SRB - 157.33 mV
SDB - 156.8 mV
GENERATOR LBB PROTECTION RELAY 50Z1 & Z2 (P-141)
Sr. No
RELAY CT NO. & CTR
NEW TB NO.
Previous(2100 A)
Previous(9900 A)
Current(2000 A)
Current( 10000 A)
Measure-1
50Z-1 (Pri)
50Z-2 (Sec)
50Z-1 (Pri)
50Z-2 (Sec)
50Z-1 (Pri)
50Z-2 (Sec)
50Z-1 (Pri)
50Z-2 (Sec)
4
50Z1&Z2 LBB
PROT. P141
CORE 4 1000/1
A
1G, TB1-21 IA-1
106.5 A
106.8 mA
503.8 A
504.2 mA 101 A
0.101 A 516.1 A 0.514 A
23 IB-1106.9
A105.6
mA502.8
A502.2
mA 99.9 A0.102
A 512.8 A 0.512 A
25 IC-1105.5
A106.9
mA505.0
A504.1
mA100.7
A0.100
A 515.6 A 0.513 ANeutral-27
CJJ-09 PANEL MEASURED CURRENT READING
2100 A 9900 A (1997 A) (10000 A)
Previous Previous Current Current
5 Metering CT
CT F 20000/5A
CJJ09-X02-1 499.2 mA 2.35 A 0.460 A 2.40 A5 500.2 mA 2.37 A 0.473 A 2.46 A7 504.5 mA 2.39 A 0.454 A 2.39 A
6 EHG+AVR CT
CT G 20000/5A
CJJ09-X02-11 491.7 mA 2.29 A 0.452 A 2.34 A16 499.5 mA 2.34 A 0.454 A 2.41 A20 504.7 mA 2.38 A 0.460 A 2.41 A
7 EHG CT CT H 20000/5A
CJJ09-X02-25 501.7 mA 2.37 A 0.471 A 2.47 A27 507.2 mA 2.36 A 0.472 A 2.43 A29 496.7 mA 2.39 A 0.455 A 2.37 A
DURING OC TEST
MEASUREMENT-1 UAT-A UAT-B UAT-C UAT-D
VAB / IA - 1 12.23 mA 12.51 mA 10.01 mA 11.36 mA
VBC / IB - 1 13.80 mA 13.33 mA 10.03 mA 10.70 mA
VCA / IC - 1 18.07 mA 17.58 mA 11.74 mA 12.30 mA
122
U # 5 GENERATOR SCC ( READINGS OF COD 8 )
SR.NO
.
CT NO.&
CTR
LOCATION TB NO.
CT CURRENT for
2100 A / 9900A
CT CURRENT for
2012 A /10100 A
GEN. CURRENT ON COD8/TRIVECTOR Previous
Current
Previous Current
2100 A 2012 A 9900 A 10010 A
1
METERING CT
CT ' F '20000/5
COD 8
1T - 82 (R) 484 mA/2.33 A 460 mA/2.40
A 2103A 2007 A 9890A 10010 A
1T - 83 (Y) 500 mA/2.37 A 473 mA/2.46
A 2102A 2011 A 9897A 10003 A
1T - 84 (B) 502 mA/2.38 A 454 mA/2.39
A 2105A 2012 A 9905A 10010 A
U # 5 GENERATOR OCC ( READINGS OF COD 8 )
SR.NO. PT III LOCATIO
N TB NO. PT VOLTAGE AT 19.5KV
PT VOLTAGE AT 21.1KV
GENERATOR KV ON COD8
RY YB BR
1 METERING PT COD 8
1T - 91 & 92 ( RY ) 94.9 V 105 V
19.5 KV (Previous)
19.5 KV (Previous)
19.5 KV (Previous)1T - 91 & 93
( BR ) 95.2V 105.2 V
1T - 92 & 93 ( YB ) 95.3V 105.3 V
21.32 (current)
21.05 (current)
20.91 (current)2 GEN. SYN.
PT COD 8 3T - 105 & 106 54.4 V 65.3 V
PART- III1. LIGHT UP, ROLLING AND SYNCHRONIZATION OF UNIT: A) BOILER HYDRAULIC TEST:
123
1. DepartmentaL : Date : 24/01/2016 at 17:58Hrs Boiler press : 250Kg/CM2. And drum depressurised at
18:26 Hrs.
2. In presence boiler inspector : Date ; 26/01/2016 at 14.38Hrs., Boiler press ; 250Kg/CM2 kept for 3
minute and that pressure reduced to 50 kg/cm2 at 15:00 hrs. and boiler hydraulic test done at 15:45
hrs.
B) REHEAT HYDRAULIC TEST: Date – 24/01/2016 at 19:00Hrs. Press – 50Kg/cm2
C) OTHER ACTIVITIES :
Generator Filling:
CO2 filling
Starting Date &Time : 27/01/16 at 23.31hrs
Cylinder consumed : 70Nos with purity 100%.
Filling done : 28/01/16 at 14.25hrs
H2 filling activity carried out.
Starting Date &Time : 28/01/16 at 15.00 Hrs
Cylinder consumed : 171+52=123Nos. (pressure-3.25 kg/cm2)
Filling done : 29/01/16 at 11.45hrs
First Boiler Light up on 29/01/16 at 06.45hrs, Second Boiler Light up on 21/07/15 at 00.42hrs,
First blow down given at 10kg/cm2 at11:42hrs., second blow down given at 20kg/cm2 at 12:50 hrs
and third blow down given at 30kg/cm2 at15:19 hrs.,
Fourth blow down given at 40kg/cm2 (i) 16:21hrs
Fifth blow down given at 40kg/cm2 (ii) 16:47hrs
Sixth blow down given at 40kg/cm2 (iii) 17:46hrs
At 14:04 vacuum pump-A and at 14:15 vacuum pump –B started
Stop valve opened at 18:40, turbine rolled to 3000 rpm at 21:42 hrs.
Set synchronized on 30/02/16 at 02.07 hrs.
3. POST OVERHAUL ACHIEVEMENTS : PERFORMANCE OF UNIT- V BEFORE AND AFTER
124
Sr. No.
Parameters Design Values
Before OH
After
OH
13-Dec-15
24-Feb-16
A Turbine Side Performance
1 Load (MW) 500 423 424
2 Main Steam Flow 1524 1298
3 Steam Flow / MW (T/MW) 3.05 3.06
4 Main steam Temp (Deg C) 537 530 540
5 HRH steam Temp (Deg C) 537 535 532
6 HP Cylinder Efficiency (%) 85.96
7 IP Cylinder Efficiency (%) 91.41
9 Gross Unit Efficiency (%) 38.37
10 Vacuum (mm of Hg) 670.60 8753 8843
11 CW Temp I/L (Deg C) 30.00 30.4 33
12 CW Temp O/L (Deg C) 40.20 42.0 44.2
13 Air ingress kg/hr 40.00 64 64
14 Cleanliness Factor 89.00 56 61
15 Gross Turbine Efficiency (%) 43.61 39 44
B Boiler Side Performance
1 Gas inlet temp (PAH A/B) º C 356 339/317 331/334
2 Gas Outlet temp (PAH A/B) º C 136 101/96 97/112
3 Gas inlet temp (SAH A/B) º C 356 372/371 353/352
4 Gas Outlet temp (SAH A/B) º C 136 199/176 135/151
6 Pri.Air temp after (PAH A/B) º C 332 235/207 265/254
7 Sec.Air temp after (SAH A/B) º C 326 313/312 330/332
8 Pri. Air / Sec Air I/L Temp º C 42/43 39/41
9 Gas side effy (PAH A/B) % 67 74/76 70/70
10 Air side effy (PAH A/B) % 92 69/65 76/75
11 Gas side effy(SAH A/B) % 67 54/52 70/55
12 Air side effy (SAH A/B) % 92 79/84 85/90
125
13 Seal leakage (PAH A/B) % 15.56 23 10
14 Seal leakage (SAH A/B) % 6.10 23 8
15 Total Air Flow (T/hr) 1853 1476 1813
16 Total Coal Flow (T/hr) 300 341 330
17 Excess air % 20 11 16
18 Economizer inlet temp º C 253 204 241
19 SH Spray T/hr 0 157 131
20 RH Spray T/hr 0 62 15
C Performance Indicators
1 Boiler Efficiency 88.1 81.1 83.9
2 Corrected Boiler Efficiency 88.1 85.6 87.1
3 Gross Turbine Heat rate 1972 2170 2016
4 GCV of Coal 3750 3168
5 Gross Unit Heat rate 2241
6Sp Coal Consumption (As per Heat rate)
0.598 0.804 0.77
Last Overhaul: 14-07-13 to 31-08-13 (AOH)
Current Overhaul Started from: 27-12-2015 (18:50 hrs) to 30-01-2016 (02:07 Hrs) (33 Days)
Following Major Works are being carried out :• Complete Air Heater Basket assembly is replaced.
• Total 32 coal compartment assemblies replacement with Upgraded coal compartment assemblies.
• TDBFP-5B Cartridge replacement & Overhaul.
• ACW & CCW header separated.
• IDCT new cell interconnection with CCW return line of tower 5A & 5B is completed successfully during
COH.
Unit-5 (COH) – Surprises : • LPT 2R blade no. 35 found damaged
• HPCV no. 3 cone found damaged.
• HP Bypass 1 & 2 Seat found Damaged.
• IPT B/H casing inlet 1st stage stationary blades one bolt observed entangled in blade.
• Pitting marks observed on Gen Rotor exciter end face.
126
• Compressor stationary blades 1st row observed denting marks.
• Leakage observed in 2 nos Current Carrying bolts. Generator rotor & Exciter rotor 1 no. each
Works Carried out :1. Resolving ESV 1 To 4 Opening Problem
• ESV 1 to 4 pilot Valve found jam, 3 Nos. of ESV valves pilot opened & made free after servicing, One
No ESV found jam to open so replaced by new.
2. Resolving Turbine Speeding Problem
• HPCV 3 seat Damage – Seat Repaired & IPSV Seat damage repaired by machining.
3. Resolving Factors Responsible For Poor Vacuum
• LPT inlet bellow found puncture – Replaced with new
• Condenser tubes found chocked/blocked - Tube cleaning by Hydro jetting & Bullet shot
4. Resolving Factors Responsible For Poor Vacuum
• Both TDBFP diaphragm found raptured replaced with new
• Both TDBFP Exhaust butterfly valve found damaged so sealing ring replaced.
• Vacuum pump 5A/5B diaphragm observed rupture, replaced with new.
5. Resolving EHC hunting problem
• Cleaning and servicing of EH amplifier block
6. Condenser Cathodic Protection –
• 80 nos. of Condenser cathodic protection elements installed in Waterbox to avoid (Hydrogen
embrittlement) deposition of hard scales in condenser & Improving condenser performance and
reduction in fouling factor
7. GTR Cooler Cleaning By SILICO6 –
• GTR coolers observed fully chocked up causing high temperature problem. Lot of Ash deposition
observed in tubes from ACW sump. Cleaned by new technique organic compound SILICO6.
8. New soot blowing line from PRDS station to A/H is provided for effective air heater soot blowing.
(previously soot blowing was done through service air)
127
9. 100% Stator earth fault protection which was initially bypassed during synchronization, since last two
and half years is now put in service after trial. Now 40 MW interlock introduced.
PERFORMANCE • Condenser Side
Date Design 03/12/2015 05/02/2016
Load (MW) 500 420 459
Vacuum -670 631 652
C.W Inlet temp 30 32.67 30.55
C.W Outlet temp
(mean)40.2 43.89 41.97
LPT Exhaust Temp 43 51.37 47.84
Condensate Temp 43.1 50.36 46.27
Actual TTD 2.9 8.62 5.82
Condenser
Efficiency77.86 56.6 66.2
Cleanliness Factor 89.29 56 61
• Air Heater Side
Air heater performance Design 03/12/2015 05/02/2016
128
L R L R
a) O2 at AH inlet (%) 3.5 3.4 3.6 5.0 5.2
b) O2 at AH outlet (%) 6.0 6.7 6.8 6.2 6.6
d) Flue gas temp at PAH I/L (Oc) 356 340 312 331 334
e) Flue gas temp at SAH I/L (Oc) 356 373 354 376 354
f) Flue gas temp at AH Comn O/L (Oc)
136 173 154 134 154
g) PA temp at AH outlet (Oc) 332 246 216 261 261
h) SA temp at AH outlet (Oc) 326 303 305 326 322
i) Gas side effy (%) (PAH / SAH)
67 74.8/54.7 76.2/52.8 69.9/70.1 70.2/54.2
j) Air side effy (%) (PAH / SAH) 92 69.2/79.3 65.3/84.6 76.4/85.3 75.6/90
k) Air inleakage (%) --- 23 23 8 10
Excess Air (%) 20 11 16
• Boiler Side
129
Date Design 03/12/2015 05/02/2016
Load (MW) 500 420 459
Operating boiler Effy. (%) 88.1 81.05 83.96
a) Unburnt loss (%) 0.60 0.30 0.33
b) Dry flue gas loss (%) 4.64 9.85 7.48
c) Coal (Moisture+H2) loss (%) 5.61 7.46 7.03
d) GCV of COAL 3750 3215 3416
Corrected blr effy (Design coal) 88.1 85.58 86.74
• Turbine Side
Date Design 03/12/2015 05/02/2016
MS flow at HPT inlet-T/Hr 1524.3 1326 1310
MS temp at HPT inlet-Deg C 537 534.73 536.96
MS press. at HPT inlet-kg/cm2 170 141.64 140.92
HRH temp at IPT inlet Deg C 537 528.00 526.70
HRH press. at IPT inlet-kg/cm2 39.4 33.65 36.99
HPT exhaust steam temp Deg C 342.6 350.91 346.95
130
CRH pressure-kg/cm2 43.90 39.69 40.03
Gross Turbine Heat Rate 1972 2170 2016
Gross Turbine Efficiency 43.61 39.63 44.09
• HR Deviations
Date 03/12/2015 05/02/2016 Saving (Rs/Day)
Deviation in GUHR (Controllable)
Loss due to un burnt carbon -9.73 -7.40
Loss due to dry flue gas 183.83 81.25 6,45,337
Radiation & other losses -7.20 -10.02
MS temp at HPT inlet 0.78 0.10
MS pressure at HPT inlet 26.99 27.65
Re heater pressure drop 7.97 -4.10
Condenser vacuum 52.55 22.92 1,90,768
Loss due to Partial Loading 43.87 15.65
FW Temp at Eco Inlet 6.01 6.01
SH Spray 4.27 4.60
Deviation in GUHR (Un-Controllable)
Loss due to moisture in fuel 46.05 46.88
Loss due to H2 in fuel 16.18 -6.48
HRH temp 4.54 4.58
RH Spray 14.75 4.90 65,010
POG Observations1. Improvement in ID/PA Current by @15 & 10 Amp Respectively.
131
Auxiliary Unit Before After Reduction in Current
ID Fan-A Amp 122 105 14
ID Fan-B Amp 123 95 23
ID Fan-C Amp 122 105 14
ID Fan-D Amp 120 110 8
PA Fan-A Amp 145 125 14
PA Fan-B Amp 139 130 6
2. Increase in ID margin by 30% from 82% at 373 MW load to 52% at 443 MW load.
Auxiliary Before AfterGain in Vane
Position
ID Fan-A 81.6% 52.1% 29%
ID Fan-B 82.1% 52.5% 30%
ID Fan-C 81.7% 52.2% 30%
ID Fan-D 82.0% 52.4% 30%
IMPREOVEMENTS
132
1. Condenser Vacuum improved by @ 21 mmHg
2. Condenser cleanliness factor improved by @ 5 %
3. Improvement in Air side efficiency of Air heater observed.
4. Reduction in air in leakages @ 14 %
5. Reduction in RH spray by @ 52 T/hr resp.
6. Boiler efficiency improved by 2%
7. Improvement in Gross turbine heat rate by @154 Kcal/Kwh
8. Now after COH no boiler side drain valves are passing as per last test.
9. Windbox DP improved by @25 mmwcl i.e from 75 / 80 to 105 / 100
133
Unit-5 COH-2015 EXPENDITURE (In lakhs)
Unit-5 COH-2015-16 Expenditures (In Lakhs)
Section R & M Expenditures Total(R & M
Expenditures)
Capex Expenditures Total(Capital
Expenditures)
Supply Works Supply Works
BM-II 1322.977 669.231 1992.209 540.898 52.582 593.481
TM-II 284.303 388.395 672.698 NIL NIL NIL
EM-II 52.75 50.63 103.38 NIL NIL NIL
I & C-II 14.46 21.72 36.18 NIL NIL NIL
Test-II 5.47112 7.97110 13.44222 NIL NIL NIL
ODP-II 119.58 46.51 166.09 NIL NIL NIL
Total 1799.54112 1184.4571 2983.99922 540.898 52.582 593.481
Grand Total (Rs. in Lakhs) 3577.48022
134
DETAIL COSTING OF EACH SECTION AS FOLLOWS:
Expenditures of Boiler Maintenance-II during COH-U5 in 2015-16R & M EXPENDITURE
Sr. No.
Works carried out Name of Contractor
Supply Cost
Works Cost
Total Cost
1 Work of repairs of HP parts in Furnace
Zone ( I Pass)
M/S. Sunil Hi-
Tech
2665330 6810350 9475680
2 Work of repairs of HP parts in Furnace
Zone ( I Pass)
M/S. Adore
Contractors
1777155 6817666 8594821
3 Work of repairs of HP parts repairs in
LTSH & Eco.(II Pass)
M/S. Bhavana
Const. Co.
727685 2615503 3343188
4 Work of repairs of HP parts repairs in
LTSH & Eco.(II Pass)
M/S. V. K.
Enterprises
698920 2615503 3314423
5 Work of Repairs of Air Pre-heaters (PAH
& SAH) RHS
M/S. Bhavana
Const. Co.
42448061 2138610 44586671
6 Work of Repairs of Air Pre-heaters (PAH
& SAH) LHS
M/S. Sunil Hi-
Tech
1710888 1710888
7 Servicing of BT Mechanism (Corner 1 &
2)
M/S. Bhavana
Const. Co.
12051737 788930 12840667
8 Servicing of BT Mechanism (Corner 3 &
4)
M/S. Adore
Contractors
631144 631144
9 Servicing of FG & Air Dampers of PAH &
SAH
M/S. Ganesh
Engg.
289350 469232 758582
10 Servicing of ID, FD, PA Fans M/S. Ganesh
Engg.
170550 467858 638408
11 In-Situ repairs of Control and HP Isolating
valves.
M/S. Ideal
Engineering
6875865 1663489 8539354
12 Work of Radiographic Inspection of weld
joints.
M/S. Parikshak
Nirikshak
0 111015 111015
135
13 Work of Ultrasonic Thickness
Measurement of Boiler Tubes
M/S. P R
Sahare
0 1891444 1891444
14 Carrying out CAVT & Implementation of
Erosion Control Device
M/S. Favourite
Fabricators
5756006 1078656 6834662
15 Inspection & Scanning of WW Tubes by
LFET
M/S. MRP Nair
Engineers
0 2724730 2724730
16 Complete RLA Study of Boiler M/S. BHEL 0 8696894 8696894
17 Providing Assistance to BHEL Team for
RLA Study
M/S. Ganesh
Engg.
0 320816 320816
18 Work of Replacement of BCWP motor &
its cooler cleaning
M/S. V.A.
Constructions
95000 170328 265328
19 Work of Replacement of SAH FG Outlet
damper GD 4A
M/S. Bhavana
Const. Co.
4614645 574164 5188809
20 Servicing of Actuators M/S. S. K. Sales
Corp.
65000 330550 395550
TOTAL Rs. र 78,235,30
4
र 42,627,77
0
र 120,863,074
COAL MILLS
S.No Particular Supply Cost Work Cost Consumables
1 All Coal Feeder Iso Gates Servicing 138400 49595 4,655,550
2 All Coal Feeder COC Modifications 246400 25000
3 All HAG/HAD Servicing 0 24812
4 All CAG/CAD Servicing 0 18609
5 CAD Hastalloy Seal replacement 2040000 552400
6 C/M 5A Airport replacement 400000 80000
7 C/M 5E 'C' Type 3471682 300000
136
8 Coal Pipe/Bends/Orifice Repl 12554266.96 4531156
9 Classifier Vanes Servicing 0 93903
10 Seal Air Fan Suction Filter Cleaning 0 46028
11 Painting of Coal Mills & Structures
12 Repair/Replacement of Drive Air Seal
System, MDV, MOE
2687304 1294541
र 21,538,053 र 7,016,044 र 4,655,550
र 33,209,647
ESP
S.NO DESCRIPTION OF WOK COSTING SUPPLY
COSTING WORKS
TOTAL
1 REPAIRS OF FLUE GAS DUCT FROM
ECO O/L TO ESP I/L, HOT AIR DUCT
AND ESP O/L DUCT
3760500 2173954 5934454
2 SERVICING OF BOTTOM ASH
EVACUATION SYSTEM INTERNAS AND
REPLACEMENT OF DAMAGED
REFRACTORY
2558246 3130324 5688570
3 WORK OF SERVISING OF COARSE
ASH EVACUATION SYSTEM AND
REMOVAL OF ASH & DEBRIES.
1554000 407000 1961000
4 WORK OF SERVISING OF FLY ASH
EVACUATION SYSTEM.
1475000 365000 1840000
5 WORK OF SERVISING AND
OVERHAULING OF COMPLETE ESP.
5150000 1791098 6941098
6 WORK OF SERVISING OF GUILLITINE
GATES OF ESP I/L & O/L.
200000 904616 1104616
137
7 WOKRK OF REPLACEMENT OF
METALLIC EXPANTION JOINTS
4516352 1204616 5720968
8 WORK OF SERVISING OF ASH FEED
GATE.
850150 355000 1205150
9 WOKRK OF REPLACEMENT OF FABRIC
EXPANTION JOINTS
2859350 1523184 4382534
10 WORK OF CFD ANALYSIS &
INSTALATION OF DIVERTER PLATES
4945250 5472400 10417650
र 27,868,848 र 17,327,192 र 45,196,040
TOTAL R & M COST
र 199,268,761
CAPITAL EXPENDITUREPRESSURE PARTS
S.No. ITEMS Supply Cost Works Cost Total Cost
1 BASKETS 38943998 1710888 40654886
1710888 1710888
2 CCA 10531200 631144 11162344
631144 631144
3 FG DAMPER 4614645 574164 5188809
54089843 5258228
Capital Exp. Total र 59,348,071
COAL MILL
S.No.
ITEMS Supply Cost Works Cost Total Cost
1 NIL 0 0 0
138
ESP
S.No.
ITEMS Supply Cost Works Cost Total Cost
1 NIL 0 0 0
TOTAL SUPPLY COST 78235304
TOTAL WORKS COST 42627770
TOTAL COST 120863074
Less Capex Cost 59348071
Total R&M Cost (Total Cost - Capex) र 61,515,003
Consumables R&M CAPEX
Supply Works Supply Works
PP र 4,655,550 र 78,235,304 र 42,627,770 र 54,089,843 र 5,258,228
CM र 21,538,053 र 7,016,044 र 0 र 0
ESP र 27,868,848 र 17,327,192 र 0 र 0
Total र 4,655,550 र 127,642,205 र 66,971,006 र 54,089,843 र 5,258,228
र 132,297,755
GRAND
TOTAL
र
258,616,832
139
TURBINE MAINTENANCE - II
SR. NO
E-CODE MATERIAL DESCRIPTION UNIT QTY AMOUNT
1 A115050250050004 PMP OIL TUSHACO T3SA38/36 PMP CTDG ASSY EA 1 2,112,078.21
2 A036020220010003 FIRE RESISTANT FLUID REOLUBE TURBOFLUID KG 690 1,995,273.00
3 A093240010050013 TBN STEAM MODULE CASING COMPENSATOR DN
60
EA 1 1,500,000.00
4 VALVE CONE FOR HPCV NO 3 EA 1 1,200,000.00
5 A133190010010025 DRG 09-SHF2 / 162-E5 COMPLETE MECH SEAL EA 1 1,175,697.29
6 A031020010010001 HEATEXCH CRFLOW CONDNSR TUBE EA 154 956,878.69
7 A133190010020001 M/SEAL BFP NDE COMPLT MECH SEAL EA 1 944,763.38
8 A093590010010009 TBN LPT BLADE MOVING MOVING BLADE 2L EA 2 886,206.90
9 A115090380050142 PMP WTR WEIR THRUST BRG EA 2 742,320.00
10 A093590010010013 MVNG BLADE CLAMPING PIECE P.N.007 EA 504 737,409.32
11 A093290040010021 PILOT VALVE DRG.NO. 0-114-04-2000C PN 17 EA 4 661,396.04
12 A093290040010025 IPCV SM PILOT VALVE ASSY EA 4 661,396.04
13 A115090380050122 PMP WTR WEIR RING SECTION SECOND STAGE EA 2 444,182.13
14 A036020130010003 LUBRCNT OIL SP HYDR IOC SERVO SYS HLP 32 L 2730 408,004.01
15 A075170140170006 VLV CL2500WC9 65NB VALVE ASSY MANUAL BW EA 1 407,818.95
16 A066010080030003 SIZE 8 X 6 MODEL-67-91222 - PLUG SEAL RI EA 3 382,653.00
17 A036020160020011 LUBRCNT OIL TURB IOC SERVO PRIME 46 L 2310 371,576.49
18 A115090380050040 CU-MS GASKET 605 O / D X546 I / D X 3 TH EA 2 306,658.40
19 A023010020100005 FRF SUPERFINE FILTER (SIZE 18"x5"x1") EA 14 288,456.00
20 A023010020100002 ANY MAKE AS PER IS STANDARD DUPLEX FILER EA 2 257,308.50
140
21 A036020160010008 LUBRCNT OIL TURB HPCL TURBINOL 46 L 1470 241,403.40
22 A035020050070016 LONG TRAVEL DRIVE SHAFT EA 3 209,322.96
23 A118080080010011 TBTDJ2M CIRCLIP PN 2480061150 EA 33 195,525.00
24 A093290010100022 MODULE SHFT SEAL SCREW HEX PM 12 X 60 EA 55 192,555.00
25 A115090380050108 PMP WTR WEIR OUTLET GUIDE EA 1 179,416.73
26 A066010080030002 SIZE 8 X 6 MODEL-67-91222 - BONNET SEAL EA 2 174,277.20
27 A133300020010021 M/S CEP EB SILICONE CARBIDE FACE EA 2 161,700.39
28 A115090380050135 PMP WTR WEIR SHEAR RING EA 10 143,694.48
29 A093590010010014 MVNG BLADE CLAMPING PIECE P.N.008 EA 202 128,669.41
30 A075010030020006 VLV ENER SEAL RING (PLUG) PN 13 EA 1 127,551.00
31 A107080020010006 CR PLAIN SHEET SIZE 5000 X 1250 X 3.15MM TO 2 123,200.00
32 A075190190100008 VLV 40NB ASSY RISING SPINDLE MANUAL SW EA 4 121,961.31
33 A075170100030005 VLV CL150WCB CS 150NB VLV ASSY MANUAL FL EA 3 117,959.51
34 A133300010010001 M/S CEP EN7J40D EB CARBON FACE (PN-B) EA 3 106,150.28
35 A075190190110008 VLV 50NB ASSY RISING SPINDLE MANUAL SW EA 3 102,372.07
36 A093510100010001 BLADDER 50L CAPACITY/35 KG/CM2 PRESSURE EA 1 100,974.90
37 A107010010010110 ANGLE MS EQUAL 50 X 50 X 6 MM TO 3 96,900.00
38 A075190190030008 VLV 15NB ASSY RISING SPINDLE MANUAL SW EA 7 90,663.44
39 A115090380050098 PMP WTR WEIR OIL THROWER EA 3 83,910.94
40 A088010040010017 TG500MW SEALING HALF RING BOTTOM EA 124 82,138.00
41 A093290010100028 TBNSTEAM MODULE SHFT SEAL SEALING RING EA 120 80,856.00
42 A075170100030005 VLV CL150WCB CS 150NB VLV ASSY MANUAL FL EA 2 78,639.67
43 A031020010020003 SPONGE RUBBER BALL DIA 29 MM MEDIUM ELAS EA 4400 75,488.55
44 A093530060040023 TEST VALVE FOR SERVOMOTOR LINER ITEM 01 EA 1 74,959.80
45 A093510090010004 STEAM TURB OIL REGEN SYS FULLER EARTH KG 1950 70,609.50
46 A093560010030009 BRG HOSE EXTR BRG DRG 1142140100000001 EA 1 70,541.26
141
47 A027010010230006 JOINTINGSHET SUPER MET1525X1650MMTH3.0MM KG 214 70,245.94
48 A133050010010003 M/S BOOSTR BFP EB SEAL FACE CARBON PN 11 EA 1 63,328.15
49 A036020020010027 LUBRCNT OIL CIRC IOC SERVO SYSTEM 68 L 420 62,654.38
50 A115090380050099 PMP WTR WEIR OIL THROWER NDE EA 2 62,318.31
51 A075190160100008 VLV 40NB ASSY RISING SPINDLE MANUAL SW EA 2 59,702.89
52 A133300010010005 M/S CEP EN7J40D EB MATING RING ( PN-2) EA 1 58,933.64
53 A078010010030001 CHEM ADH COMP ST-SEL JOINT PASTE TYPE B KG 19 58,860.48
54 A075010020040007 PTFE BACKUP RING P.N. 079003552-940 EA 3 56,132.71
55 A093390010040015 MODULE CASING STUD BM 80X 6X 600-25X 551 EA 2 53,915.00
56 A003060010020015 ACT HYD SLZ ASM100-10 PSTN SEAL PN 6078 EA 3 53,172.89
57 A066010080030009 8 X 6 -67-91222 - SEAT GASKET EA 3 45,379.80
58 A115030230020039 PMP CHEM SHAPO DP-60-PNM WORMWHEEL EA 3 45,000.00
59 A133050020010010 BFP PUMP FA-1B-75 INSERT MOUNT VITON PN6 EA 8 44,450.76
60 A133050020010009 BFP PUMP MOD FA-1B-75 INSERT CARBON PN.2 EA 3 42,656.66
61 A093390010070034 TRBN STM FITTED KEY PN 36 EA 2 41,642.00
62 A115030230010022 PMP CHEM SHAPO MAIN HD,NUT,PLNGR ASY EA 1 41,600.00
63 A115030230010046 PMP SHAPOTOOL DP30PNM CRANK SHAFT EA 2 40,000.00
64 A036020020010023 LUBRCNT OIL CIRC IOC SERVO SYSTEM: 176 L 250 39,943.46
65 A107040010030014 MS ISMC CHANNEL SIZE 150 X 75 MM TO 1 39,205.95
66 A003060010010006 ACT HYD SLZ ASM250-10 PSTNROD SEL PN6021 EA 3 37,151.06
67 A027010010240007 GSKT&PCK JNT SHT1525 X 1650 MM TH 3.0 MM EA 150 36,045.82
68 A093530020030020 TUR MOP RING D185 PN 41 EA 2 35,326.89
69 A003060010010008 ACT HYD SLZ ASM250-10 SCRPR RNG PN 6023 EA 3 34,212.56
70 A035020050070017 MICRO COUPLING GEARBOX SIDE HUB EA 1 33,879.78
71 A027010010230007 JOINT SHEET 1525X1650MMTH4.0MM KG 100 32,511.63
72 A093250010050002 MODULE CASING BOLT HEX PM 56 X 200 EA 7 31,925.93
142
73 A118080080080007 COMPR TBTDJ2M VLV SEAT DEL LP 2480070150 EA 12 31,920.68
74 A028040050010026 GLAND RING GRAFOIL 50 X 32 X 10 MM EA 56 31,864.00
75 A003060010020008 ACT HYD SLZ ASM100-10 SCRPR RNG PN 6023 EA 3 30,434.48
76 A118080080050009 COMPR TBTDJ2M PISTON RING LP 2481033550 EA 6 30,223.48
77 A035020050070018 MICRO COUPLING MOTOR SIDE HUB EA 1 30,115.36
78 A027010010240010 JOINTG SHEET STYLE 54 1525 X 1650 X 4 MM KG 120 29,449.64
79 A075220030110006 VLV NRV FLAP CL150WCB CS SWING 80NB ASSY EA 1 29,161.00
80 A070040040270001 WELDSOLBRAZ ELECTRODE CI CINOD160 2.5MM KG 5 28,631.96
81 A133050010010004 H75F2/100E3 O-RINGS SET 1.2,3,5,7 ST 3 28,614.89
82 A003010040010004 ACTUAT MOTORD ROTORK BUSH EA 6 28,554.24
83 A028120010030042 GSKT SEAL RING GRAFOIL ANG 680X635X40 MM EA 5 28,521.75
84 A010010070020002 SPC NO 4500 SET OF 27 BELT EA 29 28,146.03
85 A118080080080012 COMP TBTDJ2M VALVE GUARD DELIVERY H P EA 53 27,354.36
86 A078020130070001 LUBRICANT MOLYKOTE MOLYKOTE 1000 EA 17 26,010.00
87 A118080080050018 COMPR TBTDJ2M GUIDE RING HP 2480038751 EA 16 25,344.00
88 A093590010010016 MVNG BLADE LOCKING PLATE P.N.010 EA 10 25,221.98
89 A003060010010007 ACT HYD SLZ ASM250-10 GUIDE RNG PN 6022 EA 4 25,187.16
90 A070040090100001 ELECTRODE SPRG ST UNILOY 624 2.5MM KG 10 24,474.65
91 A133300010010019 MECH SEAL CEP EN-7-J-40-D CUP EA 1 24,437.98
92 A028040050010048 GLAND RING GRAFOIL 68 X 44 X 12 MM EA 42 23,898.00
93 A078020130070008 MOLYKOTE HSC PLUS PASTE KG 7 23,669.10
94 A078010010050040 CHEM ADH COMP SEAL HY UBLUN-SET ST 100GM EA 47 23,011.20
95 A093250010010013 TBNSTEAM 500MW MODULE CASING FITTED KEY EA 2 22,942.00
96 A093390010070031 TRBN STM FITTED KEY PN 03 EA 2 22,942.00
97 A093390010070033 TRBN STM FITTED KEY PN 35 EA 2 22,942.00
98 A093390010070032 TRBN STM FITTED KEY PN 04 EA 2 22,501.00
143
99 A115090380050005 PMP WTR WEIR BAFFLE PLATE EA 2 22,474.24
100 A115090380050079 IMPELLER WEAR RING KICKER STAGE EA 1 22,285.24
101 A115050020010167 PMP OIL ALF/LVL MAB103 WTR ADNG DVIC CMP EA 1 21,234.51
102 A093510010020007 MOP BRG BUSH EA 1 19,590.01
103 A093240010090001 TBNSTEAM 500MW MODULE ATM DIAPH DIAPHRAG EA 2 19,246.34
104 A115030160010026 PMP MC2/R LIQUID HEAD 25PBLH01 EA 1 18,872.54
105 A115080050020008 PMP VACCUM SIEMENS RETAINING RING EA 4 18,660.00
106 A003060010020006 ACT HYD SLZ ASM100-10 PSTNROD SEL PN6021 EA 2 18,657.15
107 A027010010220007 JOINTINGSHET OIL NONMET1525X1650MMTH3MM KG 71 18,413.46
108 A118080080040013 T-BTD-JM 06 PIECE PACKING TAN 2480102050 EA 20 16,000.00
109 A075010030020012 VLV SEAT RING GASKET PN 20 EA 1 15,126.60
110 A028040050010045 GLAND RING GRAFOIL 66 X 42 X 12 MM EA 26 14,794.00
111 A003060010020007 ACT HYD SLZ ASM100-10 GUIDE RNG PN 6022 EA 8 13,526.43
112 A115090380070012 DE OIL GUARD IN BOARD PN 11 EA 1 13,361.04
113 A028040050010019 GLAND RING GRAFOIL 41.3 X 17.2 X 12 MM EA 23 13,087.00
114 A118080080080006 COMPR TBTDJ2M VLV SEAT SUC HP 2480065150 EA 5 12,637.57
115 A115080040020014 PMP VCUM FIXED BEARING P/N 120 EA 1 12,500.00
116 A114010050020081 FASTNRS M 30 X 110 EA 13 11,850.16
117 A093390010070021 MODULE SHFT SEAL SCREW HEX AM 36 X 180 EA 10 11,720.64
118 A115090380050154 PMP WATER LUB OIL FILTER EA 9 11,704.50
119 A003010040010054 ACTUAT MOTORD ROTORK K1000 THRUST BRG EA 1 11,503.64
120 A118080080020002 AIR COMPR TBTDJ2M BRG PN 2510041850 EA 5 11,496.45
121 A036020160020009 LUB OIL TURBINE IOC SERVO PRIME 68 L 70 11,256.80
122 A093560010030006 BRG HOSE DN 16x2500 DRG 011814-02000/50 EA 2 11,025.59
123 A023010020100003 ANY MAKE AS PER IS STANDARD GOVERNING OI EA 3 10,924.20
124 A072020010070058 BRG MET BALL SADR 2309 ETN9C3 EA 4 10,264.00
144
125 A028040050010014 GLAND RING GRAFOIL 35 X 25 X 08 MM EA 18 10,242.00
126 A028100030010182 SPIRAGATE SS304 ASBT 5285 X 5025 X 45 MM EA 8 10,000.00
127 A028100030010222 GSKT SS 304 ASBESTOS FILL 95 X80X 3.2 MM EA 8 10,000.00
128 A115030230020038 PMP CHEM SHAPO DP-60-PNM WORM SHAFT EA 1 10,000.00
129 A093560010030002 BRG HOSE DN 16x2200 DRG 011703-27000/31 EA 2 9,900.53
130 A115090380050001 PMP WTR WEIR AIR VENT 3 / 4" NPT EA 2 9,831.97
131 A118080080080031 COMP TBTDJ2M VALVE GUARD SUCTION H P EA 9 9,432.00
132 A003010040040029 ACTUAT MOTORD K600 L_SWITCDRIVESHFT EA 10 9,151.58
133 A072020010070060 BRG MET BALL SADR 2310 C3 EA 3 8,935.20
134 A114070050020001 FASTNRS M 12 X 40 EA 346 8,650.00
135 A115090380050061 PMP WTR WEIR FLOATING SEAL EA 2 8,571.25
136 A003010040010005 ACTUAT MOTORD ROTORK CENTRE COLUMN EA 1 8,520.08
137 A028120010030035 GSKT SEAL RING GRAFOIL ANG 330X280X35 MM EA 4 8,213.07
138 A072020010030016 BRG MET BALL DRANGCONT 3310 A EA 3 8,172.57
139 A115050400010027 PMP OIL SHARPLES AS 12 FLEXIBLE COUPLING EA 3 8,100.00
140 A072020010080065 BRG MET BALL SRACONT 7318 BEP EA 1 7,800.39
141 A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 40 7,559.05
142 A036020100010018 LUBRCNT OIL IND GEAR IOC SERVOMESH SP68 L 50 7,548.00
143 A028100030010195 GSKT SS 304 ASBESTOS FILL 65 X25X 3.2 MM EA 6 7,500.00
144 A027010010220005 GSKT&PCK JNT SHT1525 X 1650 MM TH 1.5 MM KG 30 7,282.86
145 A134010060050003 CLOTH GENERAL CANVAS CLOTH M 22 7,068.60
146 A119020180010002 NORMEX 128 COUPLING SPIDER EA 2 7,038.00
147 A003010040040004 ACTUAT MOTORD ROTORK K600 BUSH EA 3 6,884.44
148 A115090380050003 PMP WTR WEIR BAFFLE DE EA 1 6,500.00
149 A093560010030001 BRG HOSE DN 16x2500 DRG 011604-18000/04 EA 1 6,311.59
150 A028040050010007 GLAND RING GRAFOIL 26.3 X 13.5 X 6.2 MM EA 11 6,259.00
145
151 A118080080100001 AIR COMPR TBTDJ2M OIL WIPER RING EA 43 6,235.00
152 A078010010030008 STEAM SEAL RTV 1080 NEUTRAL EA 35 5,997.60
153 A036020060010011 LUBRCNT OIL ENGINE IOC SERVO PREM 15W40 L 32 5,712.00
154 A028040050010006 GLAND RING GRAFOIL 25 X 16 X 05 MM EA 10 5,690.00
155 A028040050010029 GLAND RING GRAFOIL 54 X 32 X 11 MM EA 10 5,690.00
156 A093560010030003 BRG HOSE DN 16x1200 DRG 011818-27000/49 EA 2 5,344.04
157 A072020050020006 BRG MET SPHR SEALGN 22207 E EA 3 5,274.60
158 A001020010010005 ABR COMP CARLAP MESH SIZE80,200GMTIN PAC 10 5,148.95
159 A075430200020003 BALL VALVE 40MM(CS BODY) EA 3 5,102.89
160 A133300010010020 MECH SEAL CEP EN-7-J-40-D T-WASHER EA 1 4,771.80
161 A075430200020006 BODY CS COMPLETE BALL VALVE 15 MM EA 7 4,769.52
162 A003010040010029 ACTUAT MOTORD K1000 L_SWITCHDRIVESHFT EA 4 4,655.15
163 A003010040040005 ACTUAT MOTORD K600 CENTRECOLACTUAT EA 1 4,628.40
164 A027070010090001 GSKTMTRL 1000 MM X 2000 MM KG 50 4,608.11
165 A072020010080039 BRG MET BALL SRACONT 7309 BEP EA 3 4,520.85
166 A027130060070002 PTFE SHEET TH 3.0 MM 300 MM X 300 MM EA 6 4,279.72
167 A003010040010035 ACTUAT MOTORD ROTORK K1000 OIL SEAL EA 2 4,279.37
168 A107070010010027 RECTANGULAR TH 0.80 MM, 14" X 48" EA 6 4,180.20
169 A028040050010062 GLAND RING GRAFOIL 85 X 60 X 12.5 MM EA 7 3,983.00
170 A115030160020014 PMP CHEM MEATCHEM MC3/R PLNGR RNG PI D20 EA 4 3,926.61
171 A075430200020005 BALL VALVE CS COMP ASLY SIZE-20 MM EA 4 3,813.57
172 A107070010010025 RECTANGULAR TH 0.70 MM, 14" X 48" EA 6 3,799.79
173 A027190010010001 GSKTMTRL 3 MM THICK KG 14 3,635.26
174 A075430200020004 BALL VALVE CS COMP ASLY SIZE-25 MM EA 3 3,607.89
175 A115050020010171 PMP OIL ALF/LVL WORMWHEEL, PN:515799-04 EA 1 3,500.00
176 A028040050010004 GLAND RING GRAFOIL 19 X 13 X 07 MM EA 6 3,414.00
146
177 A027070010080001 GSKTMTRL 1000 MM X 2000 MM KG 35 3,341.02
178 A115050400010035 PMP OIL SHARPLES AS 12 IDLER SPINDLE EA 1 3,200.00
179 A093560010090032 SHIM PN 118180200000016 EA 4 3,132.07
180 A027070010070001 GSKTMTRL 1000 MM X 2000 MM KG 35 3,130.71
181 A028020060010001 GSKT H2 COOLR SILICON RUBBR 245x214x15 ST 1 3,060.00
182 A115090380050149 NEOPRENE RUBBER GASKET FOR CI QUENCH FIL EA 6 3,037.00
183 A114010050010048 FASTNRS M 24 X 60 EA 40 3,030.92
184 A130060050010003 DUMMY PLUG TAPER SIZE 30 X 26.5 X 50 MM EA 22 3,029.93
185 A115080050020015 PMP VACCUM SIEMENS THREADED PIN EA 2 3,000.00
186 A070040080030001 ELECTRODE MS CHROMOTHERM II 2.5MM KG 6 2,959.97
187 A115050020010206 PMP OILMAB-103 O-RING PN 66554 EA 20 2,900.00
188 A118080080040014 T-BTD-JM 03 PIECE PACKING RAD 2480102150 EA 3 2,850.00
189 A028040050010036 GLAND RING GRAFOIL 56 X 40 X 08 MM EA 5 2,845.00
190 A001020010010006 ABR COMP CARLAP MESH SIZE140,200 GMTIN PAC 8 2,801.27
191 A107070010010019 RECTANGULAR TH 0.45 MM, 14" X 48" KG 6 2,796.84
192 A093560010090047 SHIM S=2 PN 118180200000011 EA 3 2,743.76
193 A028120010030021 BONNET SEAL RING 150 X 135 X 15 MM EA 5 2,717.60
194 A114030080040014 FASTNRS M 4 KG 70 2,660.00
195 A072020020050007 BRG MET CYLROL NUTYPE NU 211 EA 2 2,575.05
196 A133300020010014 M/S CEP EN7J40D EB "O" RING - 25 EA 1 2,565.00
197 A093590020030041 PLATE PN 0107440200000048 EA 2 2,553.70
198 A028120010030004 GSKT SEAL RING GRAFOIL ANG 105 X91X14 MM EA 3 2,535.00
199 A028080020030004 SERRTD METAL RING CIRCLR 104 X86X 3.2 MM EA 2 2,512.00
200 A028080020030006 SERRTD METAL RING CIRCLR 105 X95X 3.2 MM EA 2 2,512.00
201 A028100030010087 SPIRAGATE SS304 ASBT 149 X 133 X 4.5 MM EA 2 2,500.00
202 A028100030010126 SPIRAGATE SS304 ASBT 224 X 198 X 35 MM EA 2 2,500.00
147
203 A115030230010017 PMP CHEM SHAPO DP-30-PNM GLAND NUT EA 2 2,500.00
204 A115050400010008 PMP OIL SHARPLES AS 12 BEARING SLEEVE EA 1 2,500.00
205 A093560010090044 SHIM S=0.5 PN 118180200000012 EA 3 2,461.59
206 A118080080030002 COMPR TBTDJ2M SUC FILTER 500X500X50 EA 1 2,450.00
207 A027010010030006 1525 X 1650 MM, STYLE 59 / K SOE OIL KG 12 2,423.52
208 A114070050010093 FASTNRS M 8 X 20 EA 307 2,410.48
209 A028040020020092 GLAND RING GRAFOIL 55 X 28 X 14 MM ST 50 2,318.54
210 A114010050010047 FASTNRS M 24 X 100 EA 25 2,282.27
211 A118080080080005 TBTDJ2M VLV SPRING DEL HP 2460067250 EA 11 2,264.00
212 A070040080030002 ELECTRODE MS CHROMOTHERM II 3.15MM KG 5 2,245.84
213 A107070010010166 SHIM SS N-M RECTAN TH 0.02MM 48X14 INCH EA 5 2,177.70
214 A114010050010040 FASTNRS M 20 X 50 EA 45 2,169.98
215 A107070010010037 RECTANGULAR TH 3.00 MM, 14" X 48" KG 1 2,148.75
216 A093560010090033 SHIM PN 118180200000017 EA 4 2,143.24
217 A027010010220006 STYLE 59 OIL NON METALLIC 1525X1650MM TH KG 11 2,130.92
218 A107070010010036 RECTANGULAR TH 2.50 MM, 14" X 48" KG 1 2,106.30
219 A115030160020032 PMP MC3/R LOCK NUT 35PA23L EA 3 2,100.00
220 A114030120010007 FASTNRS M 16 EA 270 2,025.66
221 A114010090010146 FASTNRS M 33 X 175 KG 25 1,989.00
222 A114010090010145 FASTNRS M 33 X 150 KG 25 1,983.00
223 A115050020030070 PMP OIL ALF/LVL GLASS TUBE73921 EA 1 1,912.28
224 A093560010090042 SHIM S=0.2 PN 118180200000013 EA 3 1,884.39
225 A070040100060001 WELDSOLBRAZ ELECTRODE SS RUTOX B 2.5MM KG 2 1,880.00
226 A072020010090008 BRG MET BALL SRDG 6309 EA 3 1,845.92
227 A093560010090034 SHIM PN 118180200000018 EA 4 1,813.24
228 A107070010010031 RECTANGULAR TH 1.00 MM, 14" X 48" KG 2 1,766.45
148
229 A114010090010117 FASTNRS M 24 X 100 KG 20 1,724.29
230 A028040020020097 GLAND RING GRAFOIL 60 X 38 X 11 MM ST 50 1,724.04
231 A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG KG 8 1,723.82
232 A028040050010065 GLAND RING GRAFOIL 115 X 92 X 9.5 MM EA 3 1,707.00
233 A107070010010123 SHIM RECT TH 0.30 MM, 48 X 14 INCH KG 5 1,677.90
234 A047010080100029 VITON O-RING CS DIA 4 MM ID 297 MM EA 4 1,671.19
235 A114010050010030 FASTNRS M 16 X 50 EA 94 1,665.86
236 A072020080010044 METRIC ADAPTER SLEEVE WITH LOC NUT H3124 EA 2 1,650.02
237 A093560010090035 SHIM PN 118180200000019 EA 4 1,647.66
238 A072020060010137 METRIC TAPER ROLLER SINGLE ROW 30306 J2 EA 2 1,645.60
239 A093560010090040 SHIM S=0.1 PN 118180200000014 EA 3 1,640.67
240 A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML EA 7 1,612.72
241 A115050020010173 PMP OILMAB-103 BUSHING PN 523644-03 EA 4 1,600.00
242 A107070010010035 RECTANGULAR TH 2.00 MM, 14" X 48" KG 1 1,596.77
243 A010010030380001 BELT V-BELT C NO 204 SET OF 4 BELT EA 3 1,580.73
244 A115030160010021 PMP CHEMICAL METACHEM CIRCLIP FOR CONTRO EA 20 1,580.00
245 A078020160070001 CHEM 1 GALLION TIN PACK EA 1 1,547.34
246 A027190030010002 GSKTMTRL 5 MM X 50 MM IN 5 KG PK KG 5 1,538.14
247 A115030160020007 PMP CHEM MEATCHEM MC3/R ECCENTRIC 35PA13 EA 1 1,499.00
248 A028120010030020 GSKT SEAL RING GRAFOIL ANG 145X127X18MM EA 4 1,435.25
249 A114010090010088 FASTNRS M 20 X 100 KG 17 1,427.93
250 A075430180010001 VLV BALL SS 1/2INCH VALVE ASSY EA 1 1,418.37
251 A114010050010120 FULL THREAD M 20 X 90 EA 30 1,415.25
252 A029090020010011 POWDER FORM DETERGENT SURF 0.5 KG PACK EA 20 1,372.80
253 A115050020010221 PMP OILMAB-103 SPLIT PIN PN 16434 EA 18 1,350.00
254 A072020010030008 BRG MET BALL DRANGCONT 3305 AP EA 1 1,342.91
149
255 A107070010010033 RECTANGULAR TH 1.50 MM, 14" X 48" KG 1 1,326.00
256 A047010080050015 O-RING VITON CS DIA 3 MM ID 92 MM EA 10 1,304.29
257 A114010090010078 FASTNRS M 18 X 50 KG 14 1,261.10
258 A028080020030012 SERRTD METAL RING CIRCLR 360 X 345 X 2MM EA 1 1,256.00
259 A028100030010094 SPIRAGATE SS304 ASBT 160 X 138 X 35 MM EA 1 1,250.00
260 A028100030010113 SPIRAGATE SS304 ASBT 199 X 173 X 32 MM EA 1 1,250.00
261 A115050020010226 PUMP OILMAB-103 WEAR GASKET PN 535743-02 EA 4 1,250.00
262 A028040020020102 GLAND RING GRAFOIL 80 X 55 X 12 MM ST 20 1,236.55
263 A114030080040004 FASTNRS M 16 KG 15 1,233.10
264 A031020010010005 DUMMY PLUG 31.5X 27.5X 45 MM L BRASS EA 7 1,207.41
265 A072020010090236 BRG MET BALL SRDG 6310 ZC3 EA 2 1,195.05
266 A114010090010014 FASTNRS M 12 X 100 KG 13 1,171.84
267 A114030120010005 FASTNRS M 12 EA 220 1,169.04
268 A115090380050125 PMP WTR WEIR SET PIN M 24X110 LG EA 2 1,144.02
269 A028120010030039 GSKT SEAL RING GRAFOIL ANG 505X465X40 MM EA 1 1,138.48
270 A028040050010011 GLAND RING GRAFOIL 32 X 20 X 08 MM EA 2 1,138.00
271 A028040050010052 GLAND RING GRAFOIL 73 X 47 X 13.5 MM EA 2 1,138.00
272 A028040020020057 GLAND RNG GRAFOIL 64X44X10 MM EA 35 1,123.60
273 A028120010030003 GSKT SEAL RING GRAFOIL ANG 325X290X40 MM EA 2 1,110.00
274 A078020200030001 CHEM CLG AGNT DET PWDR SURF 1/2 KG PKT EA 18 1,101.59
275 A028040020020053 GRAFOIL GLAND RING SIZE 75 X 50 X12.5 MM EA 20 1,070.10
276 A027130060050002 PTFE SHEET TH 2.0 MM 300 MM X 300 MM EA 2 1,060.80
277 A114010090010049 FASTNRS M 16 X 100 KG 13 1,042.20
278 A107070010010124 SHIM RECT TH 0.15 MM, 48 X 14 INCH KG 5 1,030.20
279 A114010050010013 FASTNRS M 12 X 50 EA 95 1,020.54
280 A114010090010025 FASTNRS M 12 X 50 KG 12 1,000.14
150
281 A115050020010236 PMP ALPHALAVAL MAB103 GASKET PN-62812 EA 8 1,000.00
282 A115050400010025 PMP OIL SHARPLES AS 12 FEED NOZZLE EA 1 1,000.00
283 A047010080050037 O-RING VITON CS DIA 3MM ID 66 MM EA 10 996.78
284 A027130040010006 PTFE BAR ROUND 30 MM EA 2 991.44
285 A072020010090048 BRG MET BALL SRDG 6311 C3 EA 1 972.63
286 A072020010100011 BRG MET BALL THRST 51111 EA 1 968.64
287 A078010010050013 CHEM ADH COMP SEAL ARALDITE 1.8 KG EA 1 968.27
288 A114060100020043 FSTNR HEX SOC CAP SCREW M 20X150 EA 8 960.00
289 A119020040030018 FLEXIBLE LOVEJOY RUBBER SPIDER L 100 EA 9 937.18
290 A107070010010006 RECTANGULAR TH 0.07 MM, 14" X 48" KG 6 936.36
291 A114030080040002 FASTNRS M 12 KG 11 904.34
292 A003010010550009 AUMA SA12A32 THRUST BRG PN 4403, 4404 ST 1 897.00
293 A028100030010054 SPIRAGATE SS304 ASBT 100 X 60 X 32 MM EA 1 895.00
294 A010010020080001 BELT VBLT TYPB 62 SET OF 2 BELT EA 8 889.77
295 A114060100020045 FSTNR HEX SOC CAP SCREW M 24X140 EA 6 870.00
296 A115050020010031 PMP OIL ALF/LVL CAP NUT, PN: 522997-01 EA 1 858.92
297 A115050400010039 PMP OIL SHARPLES AS 12 MALE CLUTCH B-512 EA 1 850.00
298 A115090300110017 PMP WATER SAM HEX SCREW EA 1 840.00
299 A036020110040026 LUBRCNT OIL LUB IOC SAE-30 L 5 837.90
300 A093560010090046 SHIM S=1 PN 118180200000010 EA 1 819.75
301 A114010090010021 FASTNRS M 12 X 30 KG 10 794.02
302 A047010080100028 VITON O-RING CS DIA 4 MM ID 228 MM EA 4 776.21
303 A114190060010008 FASTNRS M 24 KG 11 769.87
304 A028040020020089 GLAND RING GRAFOIL 48 X 30 X 9MM ST 40 760.96
305 A115090390120002 PMP WATERIAK5089 BEARING FOR PACKING BOX EA 3 750.00
306 A098130020010003 HNDTOOL HKSAW BLAD HSS 1/2"X12"X18TPI EA 19 718.80
151
307 A114030120010011 FASTNRS M 24 EA 25 711.99
308 A114190060010004 FASTNRS M 16 KG 10 692.75
309 A003010040010006 ACTUAT MOTORD ROTORK CIRCLIP EA 1 690.90
310 A001040030060001 ABR EMRY TAPE ROUG 50MMWIDTH50MTRROL EA 1 684.18
311 A114030120010013 FASTNRS M 30 EA 12 656.29
312 A028120010030015 GSKT SEAL RING GRAFOIL ANG 120X107X14 MM EA 3 652.76
313 A078020160040002 CHEM 5 LTR TIN PACK EA 1 650.07
314 A114010090010198 FASTNRS M 6 X 40 KG 7 649.32
315 A114030120010004 FASTNRS M 10 EA 175 647.24
316 A078010010090001 CHEM ADH COMP AQB AQUASEAL FAST CURE 1KG EA 1 605.21
317 A114010090010216 FASTNRS M 8 X 50 KG 8 604.33
318 A078010010050014 CHEM ADH COMP SEAL ARALDITE 180 GM EA 3 600.81
319 A114010050010006 FASTNRS M 10 X 50 EA 75 590.68
320 A001040030040001 ABR EMRY TAPE MED 50MMWIDTH50MTRROL EA 1 587.13
321 A111160010010002 CS ELBOW 90 DEG 100 MM NB EA 1 573.24
322 A114010090010008 FASTNRS M 10 X 50 KG 7 569.95
323 A028040050010047 GLAND RING GRAFOIL 68 X 44 X 10 MM EA 1 569.00
324 A078020160070002 CHEM 340 GM SPRAY CAN EA 3 551.06
325 A115050400010014 PMP OIL SHARPLES AS 12 BOWL BOSS SLEEVE EA 1 550.00
326 A111160070010001 CS UNION 1 1/2 IN HEVY DUTY MS SOCKT TYP EA 1 542.64
327 A072020010090009 BRG MET BALL SRDG 6310 EA 1 541.58
328 A119020040030009 COUPL COUPLING NO L 95 EA 1 530.73
329 A115050400010005 PMP OIL SHARPLES AS 12 BEARING FILLER B- EA 1 520.00
330 A133300010010011 M/S CEP EN7J40D EB SPRNG (PT NO-1C) ST 2 512.00
331 A078020050060001 CHEM CLN PEN DVP FC CLEANER PC-21B EA 3 506.85
332 A078020160040001 CHEM 1 / 2 LTR TIN PACK EA 7 502.76
152
333 A114030120010009 HT 12.9 GR METRIC NUT PLAIN M 20 EA 20 501.47
334 A115050400010026 PMP OIL SHARPLES AS 12 FEMALE CLUTCH EA 1 500.00
335 A028120010030010 GSKT SEAL RING GRAFOIL ANG 112 X96X13 MM EA 1 494.70
336 A107070010010021 RECTANGULAR TH 0.50 MM, 14" X 48" KG 1 489.60
337 A028120010030022 GSKT SEAL RING GRAFOIL ANG 175X151X24 MM EA 1 475.74
338 A047010080080009 VITON O-RING CS DIA 3.55 MM ID 53 MM EA 10 466.58
339 A114010050020014 FASTNRS M 12 X 55 EA 50 437.95
340 A114010050020007 FASTNRS M 10 X 80 EA 20 433.92
341 A114190060010001 FASTNRS M 10 KG 6 428.17
342 A047010080050007 O-RING VITON CS3MM ID 28 MM EA 13 427.34
343 A114030080040018 FASTNRS M 6 KG 4 422.24
344 A114190060010020 FASTNRS M 8 KG 6 419.24
345 A114030080040019 FASTNRS M 8 KG 5 418.51
346 A028120010030040 GSKT SEAL RING GRAFOIL ANG 64 X44X 10 MM EA 10 416.15
347 A003010040200003 ROTORK K 150 HAND WHEEL RETAINER EA 1 412.00
348 A114010090010068 FASTNRS M 16X 80 KG 5 405.82
349 A114010090020076 FASTNRS M 16 X 100 KG 5 402.31
350 A115050400010021 PMP OIL SHARPLES AS 12 DRAG BUSHING-6372 EA 1 400.00
351 A133300010010008 M/S CEP EB SOCKET EST SCREW P NO12 EA 2 400.00
352 A028120010030016 GSKT SEAL RING GRAFOIL ANG 125X111X14 MM EA 1 395.06
353 A114010090010011 FASTNRS M 10 X 75 KG 5 391.17
354 A114010090010196 FASTNRS M 6 X 30 KG 4 376.45
355 A072020010100004 BRG MET BALL THRST 51103 EA 1 368.00
356 A029080010010001 HARDWR MARK IDENTI BLUE PASTE TUBESIZE EA 9 363.17
357 A003010040040078 ACTUAT MOTORD ROTORK TORSION SPRG EA 2 363.09
358 A115050020010099 PMPOILALF/LVL ORING RUB3034-73D3X292MM EA 1 350.00
153
359 A072020010090163 BRG MET BALL SRDG 6305 C3 EA 2 345.01
360 A114060100010020 FASTNRS M 12 X 50 EA 30 320.49
361 A028120010030018 GSKT SEAL RING GRAFOIL ANG 140X126X14 MM EA 1 315.58
362 A047010080050032 VITON O-RING CS DIA 3 MM ID 74 MM EA 4 313.88
363 A047010080050033 VITON O-RING CS DIA 3 MM ID 80 MM EA 4 313.88
364 A107070010010004 RECTANGULAR TH 0.05 MM, 14" X 48" KG 2 312.12
365 A114010050010031 FASTNRS M 16 X 60 EA 15 305.42
366 A028040020020100 GLAND RING GRAFOIL 74 X 48 X 13 MM ST 5 303.19
367 A072020010100005 BRG MET BALL THRST 51104 EA 1 302.65
368 A114030120010006 FASTNRS M 14 EA 50 287.93
369 A072020010100001 BRG MET BALL THRST 51100 EA 1 281.13
370 A115050020010180 PUMP OILMAB-103 GASKET PN 14161 EA 2 280.00
371 A047010080080008 VITON O-RING CS DIA 3.55 MM ID 42.5 MM EA 6 279.95
372 A072020010090160 BRG MET BALL SRDG 6305 EA 2 276.42
373 A028040020020087 GLAND RING GRAFOIL 38 X 22 X 8MM ST 23 273.47
374 A114190060010018 FASTNRS M 6 KG 4 265.32
375 A003010010030010 ACTUATOR AUMA SA6A22 WORM GEAR PN 26 EA 1 258.00
376 A115090190820006 PMP KBL RKB65-19L4 OIL SEAL 65 X 54 X 12 EA 1 256.00
377 A003010040150010 ROTORK ACT K60 CIRCLIP FOR CENTER COLUMN EA 2 250.00
378 A114030120010003 FASTNRS M 8 EA 125 224.51
379 A078010010070004 CHEM ADH COMP GSKT SPEB-7 500ML TIN EA 2 211.17
380 A003060010010018 ACT HYD SLZ ASM250-10 O-RNG PN 6080 EA 1 198.23
381 A078020050060003 CHEM CLN PEN DVP FC PENETRANT PP-15B EA 1 192.40
382 A078010010050015 SEALENT ANABOND 666 100 GM PKT EA 2 191.72
383 A107070010010003 RECTANGULAR TH 0.04 MM, 14" X 48" KG 1 179.52
384 A119020040030010 FLEXIBLE LOVEJOY COUPLING PAD FOR L 95 ST 2 179.52
154
385 A078020050060002 CHEM CLN PEN DVP FC DEVELOPER PD-31B EA 1 171.10
386 A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M EA 10 170.10
387 A098130020010004 HNDTOOL HKSAW BLAD HSS 1/2"X12"X24TPI EA 5 166.01
388 A114010090010031 FASTNRS M 12 X 80 KG 2 156.79
389 A107070010010007 RECTANGULAR TH 0.08 MM, 14" X 48" KG 1 156.06
390 A115050400010010 PMP OIL SHARPLES AS 12 BEARING SPACERS A EA 1 150.00
391 A072020080010028 BRG MET SLV ADPTSLV H 2308 EA 2 140.00
392 A114070050010079 FASTNRS M 6 X 12 EA 35 140.00
393 A072020010090086 BRG MET BALL SRDG 6200 2Z EA 2 136.99
394 A072020010090087 BRG MET BALL SRDG 6201 EA 2 135.53
395 A047010080050027 VITON O-RING CS DIA 3 MM ID 25 MM EA 4 127.25
396 A115090191430018 PMP KBL BHR28/2STG BRG NUT PN 33501A3 EA 1 126.00
397 A032010020010007 HOSE RUBBER SSBRD 3/8"X3/8" BSP,L500MM EA 2 125.67
398 A072020010090098 BRG MET BALL SRDG 6204 2Z EA 1 116.40
399 A072020010090092 BRG MET BALL SRDG 6202 C3 EA 2 115.19
400 A111160010010005 CS ELBOW 90 DEG 90 DEG 25 MM NB EA 2 97.92
401 A114090050010005 FASTNRS M 10 X 25 EA 20 96.06
402 A072020010090001 BRG MET BALL SRDG 6000 EA 1 92.12
403 A114030080040001 FASTNRS M 10 KG 1 85.69
404 A072020010090148 BRG MET BALL SRDG 6301 EA 1 82.59
405 A115030160010022 PMP CHEMICAL METACHEM CIRCLIP FOR CRANK EA 1 80.00
406 A114010050010023 FASTNRS M 14 X 50 EA 3 78.21
407 A072020010090089 BRG MET BALL SRDG 6202 EA 1 77.81
408 A114190060010002 FASTNRS M 12 KG 1 70.91
409 A114030120010002 FASTNRS M 6 EA 50 65.59
410 A111030130020006 MS CONECTR 3/8"BSP(M)X3/8"BSP(M) EA 3 56.06
155
411 A114090050010079 FASTNRS M 6 X 10 EA 20 41.26
412 A098130020020001 HNDTOOL HKSAW BLAD ALOY 1/2"X12"X18TPI EA 5 40.51
413 A114090050010094 FASTNRS M 8 X 16 EA 20 30.60
414 A098130020020002 HNDTOOL HKSAW BLAD ALOY 1/2"X12"X24TPI EA 5 22.53
415 A115080050020020 PMP VAC SIEMENS COUPLING PADS EA 1 12.00
416 A115090380050117 PUMP SHAFT EA 1 1,947,946.65
417 A115090380050086 LABYRINTH BUSH (DE/NDE) EA 2 419,069.72
418 A115090380050042 3RD STAGE DIFFUSER EA 1 408,895.37
419 A115090380050173 DIFFUSER 1ST STG EA 1 408,895.37
420 A115090380050073 IMPELLER 4TH STAGE EA 1 371,286.66
421 A115090380050072 IMPELLER 1ST STAGE EA 1 332,160.59
422 A115090380050077 IMPELLER 3ED STAGE EA 1 327,347.34
423 A115090380050065 GLAND SLEEVE NDE EA 1 312,371.49
424 A115090380050076 IMPELLER SECOND STAGE EA 1 286,595.90
425 A115090380050075 IMPELLER KICKER STAGE EA 1 273,001.61
426 A115090380050168 SET OF FASTERNERS EA 1 166,464.00
427 A115090380050172 PMP BFP THRUST PADS (16 NOS.) EA 1 160,490.38
428 A115090380050171 BFP PMP CU-MS GSKT 605 X 546 X 4.2 EA 1 153,902.32
429 A115090380050033 CASING WEAR RING EA 4 105,489.04
430 A115090380050006 BALANCE DRUM EA 1 99,931.15
431 A115090380050143 THRUST COLLAR EA 1 99,115.64
432 A115090380050094 IMPELLER WEAR RING (NECK) EA 4 94,913.36
433 A115090380050153 DISC SPRING EA 1 92,562.30
434 A115090380050078 IMPELLER WEAR RING (EYE) EA 4 85,100.24
435 A115090380050064 GLAND SLEEVE DE EA 1 66,203.56
436 A115090380050044 DIFFUSER WEAR RING EA 4 63,109.64
156
437 A115090380050157 SET OF OIL GUARDS EA 1 56,637.53
438 A115090380050009 BALANCE DRUM RESTRICTION BUSH EA 1 53,983.18
439 A115090380050156 INTERSTAGE TAP OFF BUSH EA 1 44,368.69
440 A115090380050085 JOURNAL BEARING DE EA 1 36,088.70
441 A115090380050160 JOURNAL BEARING NDE EA 1 34,118.56
442 A115090380050088 METAFLEX GSKT EA 1 30,581.82
443 A115090380050034 CASING WEAR RING KICKER STAGE EA 1 24,735.95
444 A115090380050176 SET OF KEYS SET 1 22,054.20
445 A115090380050133 SHAFT NUT THROWER M 115 X 2 LH (NDE) EA 1 18,707.32
446 A115090380050175 ROTOR LOCKING CHANNEL ASSLY SET 1 15,542.96
447 A115090380050002 SET OF O RINGS & BACK UP RINGS EA 1 15,001.06
448 A115090380050134 SHAFT NUT THROWER M 140 X 2 RH (DE) EA 1 14,833.04
449 A115090380050114 PLUG FOR OUTLET GUIDE EA 1 14,772.11
450 A115090380050119 RESTRICTION BUSH (DE/NDE) EA 1 10,713.14
451 A115090380050145 THRUST COLLAR NUT M 80 X 2 LH EA 1 8,212.13
452 A115090380050110 PACKING RING FOLLOWER EA 1 6,826.30
453 A115090380050008 BALANCE DRUM LOCK WASHER EA 1 5,368.29
454 A115090380050067 SET OF LOCKING SCREWS EA 1 2,415.46
455 A115090380050109 PACKING RING EA 1 1,575.30
456 A115090380050144 THRUST COLLAR LOCK WASHER EA 1 1,542.13
457 A115090380050007 BALANCE DRUM NUT EA 1 0.01
TEMPORARY IMPREST 48,109.00
TOTAL COST 28,430,313.37
157
UNIT-5 COH COSTING – WORKS :
Sr.
No.Details of Work PO No.
Amount spent in
Unit-5 COH
1Work of the surface painting of Turbine Auxiliaries in
Unit-5, 6 & 7.4500045011 104,110.00
2
Provision of work assistance for CEP strainer / filter
cleaning and turbine side routine miscellaneous
works in Unit-5, 6 & 7.
4500046230 11,129.00
3
Work of cleaning coolers of various auxiliaries of
Unit-5, 6 & 7 during Unit Overhauling, outages or as
& when required.
4500057747 78,652.00
4
Work of Condenser Hot well Inspection, Condenser
Tube Leakage Attending & CEP Suction Strainer
Cleaning as & when required or during outages of
Unit-5, 6 & 7.
4500050968 10,496.00
5
Work of HP Welding of Valves & Pipelines during
routine maintenance, short shutdown & overhaul of
Unit-5, 6 & 7.
4500050531 4,400.00
6 Work of Replacement of Fuller’s Earth, Bucket
Strainer Cleaning & Superfine Filter
4500056607 12,023.00
158
Cleaning/Replacement in FRF system as & when
required or during outages of Unit-5, 6 &7.
7Work of Servicing/Overhauling of Various Pumps
Unit-5, 6 & 7 on as & when required basis.4500060249 -
8Work of replacement of High Pressure Valves in U-
5, 6 & 7.4500057930 -
9Work of repairing of BFP, CEP & FRF strainers at
Unit-5, 6 & 7.4500059534 157,940.00
10Work of fitting cathodic elements in condenser
during AOH/COH Overhaul Unit-6.4500062431 217,550.00
11
Work of Machining of Turbine Fitted Keys, HPBP
valve Stem , hydrogen Seal Brg & Reconditioning of
Recirculation valve of BFP of U # 5, 6 & 7 on as &
when required basis.
4500061735 672,198.00
12Work of inspection and servicing of ACW valves
during Capital Overhauling of Unit-5.4500062874 350,719.00
13
Work of internal inspection & repairs of Deaerator,
FST and HP/LP heater & Oil Tank Cleaning during
COH Unit-5.
4500065165 170,107.00
14
Work of Machining of TG Set Bearing Oil Catchers
& Machining & matching of stellited bush of Control
Valves as per dimensions during overhauls of U-5,
6 & 7.
4500050958 197,636.00
15Work of cleaning / revisioning of MS / HRH strainers
during Capital overhaul of Unit-5.4500062260 1,923,124.00
16
Work of spray insulation of HP / IP turbine module,
connected piping, HP / IP / LPBP stop and control
valves during Capital Overhaul of U-5
4500062823 1,250,366.00
17 Work of cleaning of GTR coolers with De-scaling
agent Silico-6 during respective overhaul of Unit-5, 4500063667 616,815.00
159
6 & 7
18
Work of Overhauling of HP/IP/LP Turbine,
Generator, Exciter& Associated Works during
Capital Overhaul of Unit-5.
4500062595 27,474,447.00
19
Work of inspection and servicing of Steam & Feed
line valves during Capital Overhauling of Unit-5 and
as & when required during shut down of Unit-5, 6 &
7.
4500062886 1,941,399.00
20
Work of Cleaning of Condenser Tubes by High
pressure water jetting followed by bullet shot
cleaning of Main Condenser Unit-5 during Overhaul.
4500063652 576,910.00
21Work of Machining of TG Set Bearing Oil Catchers
& as per dimensions during Overhauls of U-5, 6 & 7.4500062876 183,171.00
22Work of complete overhauling of TDBFP turbines
Unit-5, 6 & 74500064237 977,012.00
23Work of Cleaning of Condenser tubes by high
pressure Hydro-jetting at Unit-6 during COH4500061659 65,664.00
24Work of in-situ machining repair & reconditioning of
HP Control Valves of Unit-5.4500066156 1,011,608.00
25
Work of carrying out Overhauling & various
miscellaneous inspections & replacements in
Condensate Extraction Pump in Unit-5, 6 & 7 on as
& when required basis.
4500056401 332,050.00
26
Work of cleaning of Control Fluid Tank &
Overhauling, Preventive Maintainance of Control
Fluid Pumps in Unit-5, 6 & 7.
4500041950 -
27
Work of thermal insulation of heat exchangers,
turbine pipings, valves etc. of turbine house U-5, 6
& 7.
4500066293 500,000.00
38,839,526.00
160
ODP-II (AHP) :
SN
WORK
AUXILLARY NATURE OF WORK AGENCY/GROUP Unit QTY RATE Amount
1 Raw water tank cleaning Tank cleaning workM/S Babu
EnterprisesEA 1 2704.19 2704.19
2 5 A,B,C sumpSump cleaning
work
M/S Babu
EnterprisesEA 3 4924.98 14774.94
3Raw water Line A & B –
500NB B/FServicing M/s Aarti EA 2 10171.4 20342.7
4 Tank inlet- 350NB B/F Servicing M/s Aarti EA 1 9595.95 9595.95
5 Tank inlet- 500NB B/F Servicing M/s Aarti EA 2 10171.4 20342.7
161
6HP R-C VALVE Plug valve
250NBServicing M/s Aarti EA 2 4970.7 9941.4
7 Sump selection valve
Fly ash sump
selection v/v
servicingM/s Dwiwedi
EA 3 66717.8200153.3
7
Bottom ash sump
selection v/v
servicing
EA 3 11424.8 34274.31
8Sump Make up main
isolation Valve
Servicing/
ReplacementM/s Aarti EA 2 9595.95 19191.9
9 HPAWP-1
Suction valve
servicing
M/s Aarti
EA 1 9595.95 9595.95
Discharge valve
servicingEA 1 9596.95 9596.95
NRV servicing EA 1 9597.95 9597.95
1
0HPAWP-2
Suction valve
servicing
M/s Aarti
EA 1 9595.95 9595.95
Discharge valve
servicingEA 1 9596.95 9596.95
NRV servicing EA 1 9597.95 9597.95
Strainer cleaningdeparmental
workEA 1
1
1
HPAWP-3 Suction valve
servicing
M/s Aarti EA 1 9595.95 9595.95
162
Discharge valve
servicingEA 1 9596.95 9596.95
NRV servicingEA 1 9597.95 9597.95
Strainer cleaningdeparmental
workEA 1
1
2LPAWP-1
Suction valve
servicing
M/s Aarti
EA 1 4970.7 4970.7
Discharge valve
servicingEA 1 4971.7 4971.7
NRV servicing EA 1 4972.7 4972.7
Strainer cleaningdeparmental
workEA 1
1
3LPAWP-2
Suction valve
servicingM/s Aarti EA 1 4970.7 4970.7
Discharge valve
servicingM/s Aarti EA 1 4971.7 4971.7
NRV servicing M/s Aarti EA 1 4972.7 4972.7
Strainer cleaningdeparmental
workEA 1
1
4HPSWP-1
Suction valve
servicing
deparmental
workEA 1 ------ ------
Discharge valve
servicing
deparmental
workEA 1 ------ ------
NRV servicingdeparmental
workEA 1 ------ ------
1
5
HPSWP-2 Suction valve
servicing
deparmental
work
EA 1 ------ ------
163
Discharge valve
servicing
deparmental
workEA 1 ------ ------
NRV servicingdeparmental
workEA 1 ------ ------
1
6LPSWP-1
Suction valve
servicing
deparmental
workEA 1 ------ ------
Discharge valve
servicing
deparmental
workEA 1 ------ ------
NRV servicingdeparmental
workEA 1 ------ ------
1
7LPSWP-2
Suction valve
servicing
deparmental
workEA 1 ------ ------
Discharge valve
servicing
deparmental
workEA 1 ------ ------
NRV servicingdeparmental
workEA 1 ------ ------
1
8
Bottom ash & fly ash sump
strengthning work &Grating
replacement work
Bottom ash & fly
ash sumpM/s Dwiwedi T 3 11195.1 33585.3
1
9
Flushing line header ,
flushing line, Seal water
header, seal water line
replacement.
Flushing line heade
& Nozzle replacedM/s Adore
M 20 587.33 11746.6
80 473.57 37885.6
30 473.57 14207.1
2
0
Fly ash strench strainer &
support fabrication work
Sump grill &
support
replacement
M/s Dwiwedi T 4.5 11195.1 50377.95
2
1Painting Work various paining
workM/s Dwiwedi Sq.
mtr
463.9
6
231 107173.8
4
164
2
2
LPAWP Header line
modification
LPAWP Header line
modificationM/s Adore M 60 587.33 35239.8
2
3
HPAWP Header line
replacement work
HPAWP Header
line replacement
work
M/s Adore M 46 587.33 27017.18
SUPPLY
E CODE SPARE Unit QTY. RATE AMOUNT
A028140010010021 NON METALLIC ROUND- ID 400 OD 600 THK 5M EA 8 436.52 3492.13
A028140010010006 NON METALLIC ROUND- ID 400 OD 600 THK 3M EA 5 336.60 1683.00
A028140010010001 NON METALLIC ROUND- ID 350 OD 530 THK 1M EA 10 71.40 714.00
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 2 187.68 375.36
A027100010080001 GSKTMTRL 1000 MM X 2000 MM KG 5 218.73 1093.64
A028140010010031 NON METALLIC ROUND- ID 300 OD 600 THK 1M EA 10 109.09 1090.94
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 5 187.68 938.40
A028140010010027 NON METALLIC ROUND- ID 300 OD 595 THK 5M EA 5 412.70 2063.52
A028140010010022 STYLE -20N/M ROUND-ID 300 OD600 TH5MM EA 13 450.21 5852.79
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 4 214.58 858.31
A075270150010001 VLV PLUG 150CI FG200 600NB COMP ISOLATION VALVE EA 3 298390.78 895172.34
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 5 187.68 938.40
A028140010010022 STYLE -20N/M ROUND-ID 300 OD600 EA 12 450.21 5402.57
165
TH5MM
A028140010010051 METALLIC ROUND-ID300 OD 530THK 5.0 MM EA 6 355.00 2130.00
A028140010010036 NON METALLIC ROUND- ID 350 OD 530 THK 3. EA 20 183.76 3675.23
A028140010010033 NON METALLIC ROUND- ID 300 OD 530 THK 3. EA 11 207.20 2279.17
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 2 214.58 429.15
A027050010050005 GSKTMTRL 16 MM SQ IN PACK OF 5 KG KG 3 374.63 1123.90
A028140010010051 METALLIC ROUND-ID300 OD 530THK 5.0 MM EA 6 355.00 2130.00
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 2 214.58 429.15
A028140010010036 NON METALLIC ROUND- ID 350 OD 530 THK 3. EA 20 183.76 3675.23
A028140010010033 NON METALLIC ROUND- ID 300 OD 530 THK 3. EA 11 207.20 2279.17
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 2 187.68 375.36
A027100010080001 GSKTMTRL 1000 MM X 2000 MM KG 3 218.73 656.18
A028140010010051 METALLIC ROUND-ID300 OD 530THK 5.0 MM EA 6 355.00 2130.00
A027050010050005 GSKTMTRL 16 MM SQ IN PACK OF 5 KG KG 2 374.63 749.26
A028140010010036 NON METALLIC ROUND- ID 350 OD 530 THK 3. EA 20 183.76 3675.23
A028140010010033 NON METALLIC ROUND- ID 300 OD 530 THK 3. EA 11 207.20 2279.17
A027100010080001 GSKTMTRL 1000 MM X 2000 MM KG 3 218.73 656.18
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 1 187.68 187.68
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 1 187.68 187.68
166
A027100010080001 GSKTMTRL 1000 MM X 2000 MM KG 2 218.73 437.45
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 1 187.68 187.68
A027100010080001 GSKTMTRL 1000 MM X 2000 MM KG 2 218.73 437.45
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 1 214.58 214.58
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 1 214.58 214.58
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 1 214.58 214.58
A027100010070001 GSKTMTRL 1000 MM X 2000 MM KG 1 214.58 214.58
A036010010050001 LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03 KG 1 187.68 187.68
A107040010030014MS ISMC CHANNEL SIZE 150 X 75 MM TO 0.600 39204.03023 23522.42
A107030010040005 BEAM MS ISMB 200 X100 MM TO 1.000 39793 39793.00
A111010020040003 MSERW/PIPE/IS-3589/SIZE-200X219.1X7.9 MM M 20 1857.02 37140.42
A111010020030011MSERW/PIPE/IS-1239/SIZE-80X89.5X4.85 MM M 80 455.6625 36453.00
A111010020030001MSERW/PIPE/IS-1239/SIZE-100X115X5.4 MM M 30 670.50 20115.00
A027010010240007 GSKT&PCK JNT SHT1525 X 1650 MM TH 3.0 MM EA 7 253.60 1775.19
A027010010220007 JOINTINGSHET OIL NONMET1525X1650MMTH3MM KG 10 265.94 2659.42
A107030010040005 BEAM MS ISMB 200 X100 MM TO 1.540 39793 61281.22
A107040010030014MS ISMC CHANNEL SIZE 150 X 75 MM TO 1.000 39204.03023 39204.03
A111010020040003MSERW/PIPE/IS-3589/SIZE-200X219.1X7.9 MM M 60 1857.02 111421.26
A027010010220007 JOINTINGSHET OIL NONMET1525X1650MMTH3MM KG 5 265.94 1329.71
A111010020040011MSERW/PIPE/IS-3589/SIZE-400X406.4X9.5 MM M 46 4800.00 220800.00
167
A027010010220007 JOINTINGSHET OIL NONMET1525X1650MMTH3MM KG 5 265.94 1329.71
Total 1547656.10
ODP-II WHP:
SUPPLY EXPENDITURES
MATERIAL SAP CODE QTY. RATE AMOUNT
1
U#5 CT 5A/5B RISER
VALVE REPLACEMENT
WORK (600NB
BUTTERFLY)
STYEL 54 SUPER
NON METAL
A027010010240008 115 212.82 24474.30
FASTNER M 20 X
120
A114010090020124 100 88.38 8838.00
GASKET 1000MM X
2000MM
A027070010070001 105 89.44 9391.20
JOINT SHEET NON
METAL
A027010010190005 34 110.41 3753.94
BUTTERFLY VALVE
600NB
A075030020110001 10 125657.6
0
1256576.00
2
CT 5A/5B HOT WATER
PIPE REPLACEMENT
WORK 150 NB & 200 NB
ASBESTOS
CEMENT PIPE
150NB
A083050010010003 109 3241.75 353350.75
ASBESTOS
CEMENT PIPE
200NB
A083050010010004 31 4095.63 126964.53
3 U# 5 CT 5A/5B NOZZLE
CLEANING & REPL
WORK
COOLTWR NOZZLE A083050050010002 8000 16.32 130560.00
COOLTWR
MODIFIED NOZZLE
A083050050010001 5000 114.01 570050.00
4 CT FAN 5B/6 & 5B/8
COMPLETE GEAR BOX
REPLACE WORK
GB GRV VH
M1700R15-1 I/P
BEVEL & PINION
A097080090010002 2 659886.5
9
1319773.18
168
GB GRV VH
M1700R15-1 CSNG
UPR & LWR SET
A097080090010003 2 268482.7
0
536965.40
GB GRV VH
M1700R15-1
OUTPUT WHEEL
A097080090010004 2 711181.2
0
1422362.40
5
CT FAN 5A/5 GEAR
BOX OVERHAUL WORK
- RADICON ( BRG
REPL )
I/P FRONT( WORM
SHAFT)
A072020060010104 2 17263.50 34527.00
I/P BACK (WORM
SHAF)
A072020020050054 1 8524.00 8524.00
O/P shaft Top &
BOTTOM
(WORM WHEEL)
A072020060010110 2 26637.30 53274.60
6
CT FAN 5B/1 GEAR
BOX OVERHAUL WORK
- PREMIUM ( BRG
REPL )
TAPER ROLLER
SINGLE ROW BRG
32321 J2
A072020060010207 2 23116.87 46233.74
BRG MET TAPROL
SR 32319 J2
A072020060010060 2 16022.00 32044.00
GEAR BOX OIL SP-
320
A036020100010013 560 167.52 93811.20
COUPLING BUSH A119010010010122 59 524.89 30968.51
7 U#5 ACW/CCW SUMP
SUCTION STRAINER
REPAIRING WORK
BAR MS ROUND 10
MM
A107020070010003 0.3 36954.27 11086.28
8 CT FAN 5A/1 & 5B/1
MOTOR FOUNDATION
FRAME REPLACEMENT
CHANNEL MS ISMC
100X50
A107040010030002 1 42464.58 42464.58
9 U#5 ACW RETURN LINE
SEPARATION WORK AT
5A & 5B TOWER
GATE VALVE 150NB A075170080070001 30 16445.00 493350.00
MSERW PIPE AC04309001004001 90 12263.00 1103670.00
169
600NBX2000MM 0
MSERW PIPE 400NB A111010020040011 60 4800.51 288030.60
MSERW PIPE 350NB A111010020040009 280 4177.02 1169565.60
MSERW PIPE
300NBX323.9X9.5M
M
A111010020040007 100 3525.93 352593.00
MSERW PIPE 300NB A111010020040006 100 3094.77 309477.00
MSERW PIPE 150NB A111010020040001 210 1813.88 380914.80
CHANNEL MS ISMC
150 X 75
A107040010030014 1 39205.94 39205.94
MS PLATE 25MM A107060010020012 0.2 40000.00 8000.00
Paint 150000.00
TOTAL SUPPLY 10410800.55
WORK ITEM TOTAL
1 U#5 CT 5A/5B RISER VALVE REPLACEMENT WORK (600NB BUTTERFLY) 37020
2 U# 5 CT POND CLEANING WORK & U#5 ACW/CCW SUMP CLEANING WORK & U#5 ACW/CCW SUMP SUCTION STRAINER REPAIRING WORK 592204
3 U# 5 CT 5A/5B HOT WATER BASIN CLEANING WORK 242000
170
4 CT 5A/5B SPLASH BAR CLEANING & REMOVAL BY SCRAPPING 405,466
5 U#5 CCW/ACW PUMP HOUSE VARIOUS VALVE SERVICING WORK 200000
6 U#5 ACW RETURN LINE SEPARATION WORK & anchoring of pipes 1600000
7 CCW BFV servicing by VAG 810000
TOTAL WORKS 3886690
INSTRUMENTATION & CONTROL - II :
WORKS
SN
RP No. P.O.No. Vendor Name Description Amount B. Code
1 T-766 450005927 Shubham Enterprises,
Servicing of Power cylinder in bottom ash
Rs. 525,271
CHN/WP/OH/E07
171
5 Chandrapur system, burner tilt, PA general gate
2 T-1954 4500063621
Dharma B. Chanekar, Chandrapur
Work contract for cleaning and painting of JB, TRB/ TRT Panel,Instrument racks & impulse Line flushing during AOH/ COH of unit-5.
Rs. 569,759
CHN/WP/OH/E07
3 T-1956 4500063752
Panchajanya Services, Kolkata
Work contract for modification in coal mill DP measurement system of unit-5
Rs. 433,200
CHN/WP/OH/E07
4 T-2092 4500063781
Panchajanya Services, Kolkata
Work of servicing and modification of complete Gland Drain Tank levelcontrol system of Unit 5
Rs. 68,700
CHN/WP/OH/E07
5 T-1938 4500065339
Panchajanya Services, Kolkata
Work of servicing and calibration of pneumatic control valves, dampers and various transmitters during AOH/COH of Unit-5.
Rs. 720,339
CHN/WP/OH/E07
6 T-1955 4500065281 J. P. Nagdeve
Work contract for servicing of Igniter, Flame Scanners and SADC during AOH, COH of unit-5.
Rs. 128,741
CHN/WP/OH/E07
7 T-1957 4500065546
PRIYA ENGINEERING WORKS
Work contract for servicing of HP Bypass system instruments with FOD during 500MW U-5, AOH / COH.
Rs. 247,303
CHN/WP/OH/E07
8 T-331 4500044300
PRIYA ENGINEERING WORKS
Work contract for servicing of solenoid valves
Rs. 67,415
CHN/WP/OH/E07
9 T-741 4500048613
PRIYA ENGINEERING WORKS
Work contract for servicing of solenoid valves
Rs. 74,050
CHN/WP/OH/E07
Total Rs. 2,834,778
SUPPLY :S/N Material Material Description
Quantity
Amount in LC Text
1 A11419006001000 FASTNRS M 16 -3 -207.82 UNIT # 5
172
4
2A114030080040017 FASTNRS M 5 -2 -183.01 UNIT # 5
3A114030080040004 FASTNRS M 16 -4 -328.83 UNIT # 5
4A114010090010196 FASTNRS M 6 X 30 -1 -94.11 UNIT # 5
5A114010090010181 FASTNRS M 5 X 30 -1 -47.00 UNIT # 5
6A114010090010043 FASTNRS M 14 X 65 -2 -167.20 UNIT # 5
7A114010050010015 FASTNRS M 12 X 65 -1 -8.57 UNIT # 5
8A114010050010006 FASTNRS M 10 X 50 -1 -7.88 UNIT # 5
9A111120270010009 REDUCER MALE 1 / 4 TUBE X 3 / 8 -7 -1176.23 UNIT # 5
10A111120260010007 MALE X MALE 1 / 4 TUBE X 3 / 16 TUBE -4 -320.00 UNIT # 5
11A111120200020027 CONECTR FEMALE 1 / 4" X 3 / 8" BSP -1 -241.77 UNIT # 5
12A111120200010008 CONNECTOR MALE 1 / 4 TUBE X 3 / 8 NPT -3 -504.10 UNIT # 5
13A111120200010006 CONNECTOR MALE 1 / 4 TUBE X 1 / 4 NPT -2 -411.78 UNIT # 5
14A111120200010006 CONNECTOR MALE 1 / 4 TUBE X 1 / 4 NPT -2 -411.78 UNIT # 5
15A111120200010006 CONNECTOR MALE 1 / 4 TUBE X 1 / 4 NPT -1 -205.89 UNIT # 5
16A111120200010006 CONNECTOR MALE 1 / 4 TUBE X 1 / 4 NPT -4 -823.57 UNIT # 5
17A111120200010005 CONNECTOR MALE 1 / 4 TUBE X 1 / 2 NPT -5 -1102.71 UNIT # 5
18A111120150020014 TEE BRANCH MALE 1 / 4 TUBE X 1 / 4 BSP -2 -551.41 UNIT # 5
19A111030130020035 MS CONNECTOR 1/2" BSP (M) X 1/2" NPT (M) -1 -24.48 UNIT # 5
20A111030130020033 MS CONNECTOR 1/4" BSP (M) X 1/2" NPT (M) -3 -73.44 UNIT # 5
21A111030130020033 MS CONNECTOR 1/4" BSP (M) X 1/2" NPT (M) -1 -24.48 UNIT # 5
22A111030130020033 MS CONNECTOR 1/4" BSP (M) X 1/2" NPT (M) -2 -48.96 UNIT # 5
23A111030130020033 MS CONNECTOR 1/4" BSP (M) X 1/2" NPT (M) -3 -73.44 UNIT # 5
24A111030130020033 MS CONNECTOR 1/4" BSP (M) X 1/2" NPT (M) -5 -122.40 UNIT # 5
25 A11103013002003 MS CONNECTOR 1/4" BSP (M) X 1/2" NPT (M) -1 -24.48 UNIT # 5
173
3
26A111030130020032 MS CONNECTOR 1/2" BSP (M) X 3/8" NPT (M) -1 -24.48 UNIT # 5
27A111030130020031 MS CONNECTOR 1/2" BSP (M) X 1/4" NPT (M) -2 -48.96 UNIT # 5
28A111030130020018 PIP FT FE CNCTR 4 / 8" X 1 / 4" -3 -68.18 UNIT # 5
29A111030130020007 MS CONECTR TUBEOD1/4"X1/4"NPT(M) -1 -13.26 UNIT # 5
30A111030030030002 MS REDUCER 1 / 4" BSP (M) X 3 / 8" BSP ( -54 -1350.00 UNIT # 5
31A111020010010006 PIPE SCH 10 FLEXIBLE OD 8 MM X ID 6 MM -1.500 -134.14 UNIT # 5
32A110060130030004 MS 80 NB FLANGE DUMMY -2 -507.96 UNIT # 5
33A110060130030004 MS 80 NB FLANGE DUMMY -2 -507.96 UNIT # 5
34A104030400010002 LUG CU I/L CNCTR WITH SLV 2.5SQMM -10 -30.62 UNIT # 5
35A104030400010002 LUG CU I/L CNCTR WITH SLV 2.5SQMM -25 -76.55 UNIT # 5
36A104030400010001 LUG CU I/L CNCTR WITH SLV 1.5SQMM -10 -30.60 UNIT # 5
37A104030390010002 LUGS CU FL WITH SLV 2.5SQMM -50 -156.16 UNIT # 5
38A104030390010001 LUGS CU FL WITH SLV 1.5SQMM -10 -30.09 UNIT # 5
39A104030380010002 LUG CU PIN TYPE WITH SLV 2.5MM2 -25 -36.33 W T PLANT
40A104030380010002 LUG CU PIN TYPE WITH SLV 2.5MM2 -60 -87.20 UNIT # 5
41A104030380010001 LUG CU PIN TYPE WITH SLV 1.5MM2 -10 -26.07 UNIT # 5
42A104030380010001 LUG CU PIN TYPE WITH SLV 1.5MM2 -25 -65.18 W T PLANT
43A104030380010001 LUG CU PIN TYPE WITH SLV 1.5MM2 -10 -26.07 UNIT # 5
44A104030370020002 LUGS CU U-TYPE WITH SLV 1.5SQMM -50 -68.70 UNIT # 5
45A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
46A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -25 -45.37 UNIT # 5
47A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
48A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
49 A10403006003000 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
174
1
50A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -25 -45.37 W T PLANT
51A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
52A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
53A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -50 -90.74 UNIT # 5
54A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -79 -143.38 UNIT # 5
55A104030060030001 CU RECT FRK SLDRLES 2.5MMSQ LUG-7928 -10 -18.15 UNIT # 5
56A103130040010002 TOP PIN PVC PLUG TOP V240 5 AMP -4 -101.87 UNIT # 5
57A103070140010009 LMP FT LAMP IND V 30 A 50 MA -31 -62.00 UNIT # 5
58A103070140010006 LMP FT LAMP IND TYPE V 30, A -5 -50.00 UNIT # 5
59A102240010010006 300 (L) X 315 (B) X 170 (H) MM WITH HING -1 -3473.08 UNIT # 5
60A102230020020017 LLGS,CEE EM45 SERIES WITH NORMAL ROLLER -1 -265.00 UNIT # 5
61A102230020010001 JAI BALAJI 2 NO + 2 NC TYPE-JB2700DPDT -1 -3120.00 UNIT # 5
62A102230010020001 INSTRFLD LMTSWT BCH 1NO+1NC TYPE: LTPR -1 -771.43 UNIT # 5
63A102180030020003 PR SWITCH-DIFF SWITZER 0.2TO 4 BAR -1 -8200.00 UNIT # 5
64A102180030010031 INST FLD PR SW DIF 5-60 PSI MP55 -3 -8070.00 UNIT # 5
65A102180010020006 SWITCH GEORGIN RANGE - 0 TO 5000 PA -1 -111384.42 UNIT # 5
66A102160120010016 INSTRFLD TEMP THERMOWEL HP IL: 250 MM -1 -0.01 UNIT # 5
67A102160090010012 TC-MI SIMPLEX K-TYPE L 4 METER OD 3 MM -4 -29281.20 UNIT # 5
68A102160080010020 K-TYPE NIPPLE FOR IP TURBINE T / C -4 -2066.67 UNIT # 5
69A102160070020002 TC-MI WELDING PAD OD 6 MM T / C -1 -272.34 UNIT # 5
70A102160060020221 TC-DUPLEX, K-TYPE, IL 300 MM, EL 100 MM -1 -15403.86 UNIT # 5
71A102160060020180 INST FLD TMP SNSR HP OUTER CASING -5 -30550.00 UNIT # 5
72A102160060020105 K-TYPE L 840 MM, OD 8 MM ELEMENT -1 -0.01 UNIT # 5
73 A10216006002005 K-TYPE IL 700 MM, EL 140 MM ASSY -1 -5507.44 UNIT # 5
175
1
74A102160060020025 K-TYPE IL 150 MM, EL 90 MM ASSY -1 -0.01 UNIT # 5
75A102160010010351 RTD-DUP, PT-100, L13 MM, OD3MM, 2WIRE -4 -3366.00 UNIT # 5
76A102160010010350 RTD L 70 MM, OD 6.5 MM, 3 WIRE ELEMENT -1 -1535.54 UNIT # 5
77A102160010010299 INST FLD TMP SNSR OD8MM,L400MM,3WIRE -1 -1312.74 UNIT # 5
78A102160010010299 INST FLD TMP SNSR OD8MM,L400MM,3WIRE -2 -2625.48 UNIT # 5
79A102160010010299 INST FLD TMP SNSR OD8MM,L400MM,3WIRE -1 -1312.74 UNIT # 5
80A102160010010299 INST FLD TMP SNSR OD8MM,L400MM,3WIRE -1 -1312.74 UNIT # 5
81A102160010010299 INST FLD TMP SNSR OD8MM,L400MM,3WIRE -1 -1312.74 UNIT # 5
82A102160010010299 INST FLD TMP SNSR OD8MM,L400MM,3WIRE -1 -1312.74 UNIT # 5
83A102160010010267 PT100 L 100 MM, OD 8 MM, 3 WIRE ELEMENT -1 -982.26 UNIT # 5
84A102160010010226 PT100 L 306 MM, OD 6 MM, 3 WIRE ELEMENT -1 -954.72 UNIT # 5
85A102160010010226 PT100 L 306 MM, OD 6 MM, 3 WIRE ELEMENT -1 -954.72 UNIT # 5
86A102160010010109 PT100 L 220 MM, OD 8 MM, 3 WIRE ELEMENT -1 -783.96 UNIT # 5
87A102160010010109 PT100 L 220 MM, OD 8 MM, 3 WIRE ELEMENT -1 -783.96 UNIT # 5
88A102150060020029 0 TO 120 DEG C, DIA-6 MM, STEM L 300 MM -1 -2236.86 UNIT # 5
89A102150020020204 0 TO 250 DEG C, BULB DIA-8 MM, CAP L 5.0 -1 -2236.86 UNIT # 5
90A102150020020081 0 TO 120 DEG C, BULB DIA-8 MM, CAP L 5.0 -1 -2236.86 UNIT # 5
91A102150020020081 0 TO 120 DEG C, BULB DIA-8 MM, CAP L 5.0 -1 -2236.86 UNIT # 5
92A10214049001000
2 REPAIR KIT ASCO P / N A302 322 -1 -3540 UNIT # 5
93A10214049001000
1 COMPLETE SOLENOID VALVE ASSY ASCO P / N -1 -4446.36 UNIT # 5
94A10214047001000
2 REPAIR KIT ASCO P / N A316 753V -1 -6239.64 UNIT # 5
95A10214043001000
2 REPAIR KIT ASCO P / N A302 725 MO -1 -816 UNIT # 5
96A10214043001000
2 REPAIR KIT ASCO P / N A302 725 MO -1 -816 UNIT # 597 A10214043001000 REPAIR KIT ASCO P / N A302 725 MO -1 -816 UNIT # 5
176
2
98A10214043001000
2 REPAIR KIT ASCO P / N A302 725 MO -1 -816 UNIT # 5
99A102130050060078 INST FLD PR GAUG 0-2.5KG/CM2,CON1/2"BSP -1 -845.42 UNIT # 5
100
A102130050060078 INST FLD PR GAUG 0-2.5KG/CM2,CON1/2"BSP -1 -845.42 UNIT # 5
101
A102130050060016 0-25 KG/CM2, CON 1 / 2" BSP -3 -2274.01 UNIT # 5
102
A102130050030098 PR GAUGE DIAL 100 MM 0-2.5 KG / CM2 -2 -1397.46 UNIT # 5
103
A102130050020060 0 TO 6 KG/CM2, CON 1 / 2" BSP -1 -698.73 UNIT # 5
104
A102130050020059 0 TO 40 KG/CM2, CON 1 / 2" BSP -1 -698.73 UNIT # 5
105
A102130050020059 0 TO 40 KG/CM2, CON 1 / 2" BSP -1 -698.73 UNIT # 5
106
A102130050010017 0-16 KG/CM2, CON 1 / 2" BSP -1 -698.73 UNIT # 5
107
A102130050010017 0-16 KG/CM2, CON 1 / 2" BSP -1 -698.73 UNIT # 5
108
A102130050010001 0-10 KG/CM2, CON 1 / 2" BSP -1 -698.73 UNIT # 5
109
A102130050010001 0-10 KG/CM2, CON 1 / 2" BSP -4 -2794.92 UNIT # 5
110
A102130040040001 0-10 KG/CM2, CON 1 / 2" BSP -1 -789.17 UNIT # 5
111
A102130040040001 0-10 KG/CM2, CON 1 / 2" BSP -1 -789.17 UNIT # 5
112
A102130040010025 0-250 KG/CM2, CON 1 / 2" BSP -3 -2034.67 UNIT # 5
113
A102130040010001 0-10 KG/CM2, CON 1 / 2" BSP -1 -763.00 UNIT # 5
114
A102130040010001 0-10 KG/CM2, CON 1 / 2" BSP -1 -763.00 UNIT # 5
115
A102120020050002 ILK MODEL HTPWO / BP -1 -0.01 UNIT # 5
116
A102080070030003 ROTAMETER 0 TO 45 LPH FOR SWAS -2 -6485.16 UNIT # 5
117
A102080070030003 ROTAMETER 0 TO 45 LPH FOR SWAS -1 -3242.58 UNIT # 5
118
A102070010020002 ELECTRONIC PFTRANSM. MODEL EPT002, I / P -2 -40166.28 UNIT # 5
119
A102070010020002 ELECTRONIC PFTRANSM. MODEL EPT002, I / P -1 -20083.14 UNIT # 5
120
A102060010010001 I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG / SQ.C -1 -14040.50 UNIT # 5
12 A10206001001000 I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG / SQ.C -1 -14040.50 UNIT # 5
177
1 1122
A102060010010001 I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG / SQ.C -1 -14040.50 UNIT # 5
123
A102060010010001 I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG / SQ.C -1 -14040.50 UNIT # 5
124
A102050010060017 FORBE MARSHALL DIGITAL INDICATOR ASSY -1 -4584.29 UNIT # 5
125
A102020040050001 FORBES MARSHAL CONDUCTIVITY METER -1 -34382.16 UNIT # 5
126
A100120010010019 I&C TRBVSRYSENSOR PROBE ASSY -1 -0.01 UNIT # 5
127
A100090040020059 TRIP INDICATION LAMP IDENT CODE3SB12 91 -5 -765.00 UNIT # 5
128
A100070040010004 PRESSURE FILTER ELEMENT PN 60 / 00018. -2 -15140.00 UNIT # 5
129
A100070030060015 SET OF PICKINGS OF SERVO VALVE ST-10.65 -1 -19683.96 UNIT # 5
130
A100070030060015 SET OF PICKINGS OF SERVO VALVE ST-10.65 -1 -19683.96 UNIT # 5
131
A100070030060010 SET OF PICKINGS TO SERVO VALVE ST10 4+R6 -1 -6921.93 UNIT # 5
132
A100070030060009 SB FILTER FOR SERVO VALVE ST10-63 / 4 -1 -22172.76 UNIT # 5
133
A100070030060006 SERVO VALVE FIXING BOLT M6 X 130 WITH WA -1 -1131.18 UNIT # 5
134
A100070030050064 FILTER INSERT FOR HC9020 OIL UNIT -4 -47209.19 UNIT # 5
135
A100070030050064 FILTER INSERT FOR HC9020 OIL UNIT -1 -11802.30 UNIT # 5
136
A100070030050008 FILTERS FILTER INSERT BIG HC9600 FUP4H H -2 -35233.69 UNIT # 5
137
A100070030040006 SULZER HOSE O' RING SET -2 -2262.36 UNIT # 5
138
A100070030020005 BL-10 SET OF PACKING CODE 97450240 -1 -2899.12 UNIT # 5
139
A100060080010014
COAL FEEDER CONTROL PANEL TRANSFORMER, O -1 -8000.00 UNIT # 5
140
A100060060020016 PROCESSOR POWER SUPPLY -3 -0.03 UNIT # 5
141
A100060060020016 PROCESSOR POWER SUPPLY -1 -0.01 UNIT # 5
142
A100060060020015 I&C FSSS MODICON MA-0185-100 -1 -0.01 UNIT # 5
143
A100060010050014 I&C FSSS BHEL SPARK ROD TIP-IMPORTED -4 -227430.81 UNIT # 5
144
A100060010050001 ALLAN SCREW FOR IGNITOR 4 MM -2 -36.72 UNIT # 5
14 A10006001005000 ALLAN SCREW FOR IGNITOR 4 MM -4 -73.44 UNIT # 5
178
5 1146
A100060010050001 ALLAN SCREW FOR IGNITOR 4 MM -10 -183.60 UNIT # 5
147
A100060010040015 FSSS HEA ADV/RET ASSY SPARK ROD CLAMPS -4 -913.92 UNIT # 5
148
A100060010040014 AS PER SPEC HEA ADV/RET ASSY SPARK ROD -2 -5672.16 UNIT # 5
149
A100060010040014 AS PER SPEC HEA ADV/RET ASSY SPARK ROD -3 -8508.24 UNIT # 5
150
A100060010040014 AS PER SPEC HEA ADV/RET ASSY SPARK ROD -4 -11344.32 UNIT # 5
151
A100060010040012 AS PER SPEC HEA ADV/RET ASSY PC SEAL KIT -1 -2688.14 UNIT # 5
152
A100060010040012 AS PER SPEC HEA ADV/RET ASSY PC SEAL KIT -2 -5376.29 UNIT # 5
153
A100060010040012 AS PER SPEC HEA ADV/RET ASSY PC SEAL KIT -2 -5376.29 UNIT # 5
154
A100060010030020 HEAI EXCITER COMPLETE ASSY -2 -62393.76 UNIT # 5
155
A100060010020042 SAFE SCAN II LITTLE FUSE FOR LAMP & METE -5 -472.68 UNIT # 5
156
A100060010020040 SAFE SCAN II FLAT LENS THK 1.5 MM X OD 2 -5 -640.71 UNIT # 5
157
A100060010020040 SAFE SCAN II FLAT LENS THK 1.5 MM X OD 2 -18 -2306.54
SCANNER REPAIR
158
A100060010020039 SAFE SCAN II COLLIMETER LENS & BARREL AS -15 -18054.00
SCANNER REPAIR
159
A100060010020035 SAFE SCAN II FIBRE OPTIC CABLE -16 -49543.68
SCANNER REPAIR
160
A100060010020022 SAFE SCAN II HOUSING ELECTRONIC CARD -18 -132192.00
SCANNER REPAIR
161
A100060010020015 SAFE SCAN II COLLIMATOR TUBE -5 -3069.33
SCANNER REPAIR
162
A100060010020015 SAFE SCAN II COLLIMATOR TUBE -5 -3069.32
SCANNER REPAIR
163
A100060010020005 FLAME SCANNER SAFE SCAN II ALLAN SCREWS -2 -20.00
SCANNER REPAIR
164
A100040010020009 I&C DCS ABBPRO POWER AMPFR AVL-AA -1 -88700.00
SCANNER REPAIR
165
A100030010020009 I&C DAS SIEMEN HARD DISK DRIVE 160GB -1 -3000.00 UNIT # 5
166
A100010020010009 I&C ACS H&B AV-42:PROT&ANLG SIGNL DISTR -1 -0.01 UNIT # 5
167
A098170010010001 HNDTOOL OILCAN FIXSPOUT WESCO 1/2 -1 -1236.24 UNIT # 5
168
A098130020020001 HNDTOOL HKSAW BLAD ALOY 1/2"X12"X18TPI -5 -40.51 UNIT # 5
16 A09813002001000 HNDTOOL HKSAW BLAD HSS 1/2"X12"X24TPI -5 -166.01 UNIT # 5
179
9 4170
A098130020010003 HNDTOOL HKSAW BLAD HSS 1/2"X12"X18TPI -3 -113.49 UNIT # 5
171
A098110010010009 HNDTOOL DRILBIT MET PARALLSHANK 6MM -1 -115.20 UNIT # 5
172
A098050010020002 HNDTOOL FILE FLAT SMOOTH 200MM/8" -1 -663.00 UNIT # 5
173
A098030050010003 HNDTOOL PLIR COMB ELEC 8" -2 -655.20 UNIT # 5
174
A098030050010003 HNDTOOL PLIR COMB ELEC 8" -1 -327.60 UNIT # 5
175
A098020010010074 ELECTRICAL PATTERN TAPARIA PRODUCT -1 -95.68 UNIT # 5
176
A098020010010025
HNDTOOL SCRWDRIVER FLAT ELEC 125MMELECT -1 -77.28 UNIT # 5
177
A098020010010025
HNDTOOL SCRWDRIVER FLAT ELEC 125MMELECT -1 -77.27 UNIT # 5
178
A098010030010003 HNDTOOL SPANNER SINGLEND 300MM/12" -1 -490.12 UNIT # 5
179
A098010030010003 HNDTOOL SPANNER SINGLEND 300MM/12" -1 -490.12 UNIT # 5
180
A095770080010001 VSLOW-BLOW GLASS FUSE 500 VAC FNO-6 TIME -1 -900.00 UNIT # 5
181
A095130040010002 FUSE FUSE, TYPE: HF, CAT NO: SF 90152 -1 -56.00 UNIT # 5
182
A091010090070001 ROT2W2P 16A SWITCH KAYCEE RP125B -1 -520.00 UNIT # 5
183
A085060070120016 ELECTINSU FOR 4.0 SQ.MM WIRE -1 -48.86 UNIT # 5
184
A085060070120014 ELECTINSU FOR 2.5 SQ.MM WIRE -1 -34.68 UNIT # 5
185
A085060070060028 SLEEVE GLASS FIBER VARNISHED 10 SQ MM -1 -12.24 UNIT # 5
186
A078020160070002 CHEM 340 GM SPRAY CAN -2 -367.37 UNIT # 5
187
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
188
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
189
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
190
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
191
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
192
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
19 A07802016007000 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
180
3 2194
A078020160070002 CHEM 340 GM SPRAY CAN -1 -183.69 UNIT # 5
195
A078020160040001 CHEM 1 / 2 LTR TIN PACK -1 -71.82 UNIT # 5
196
A078020160040001 CHEM 1 / 2 LTR TIN PACK -1 -71.82 UNIT # 5
197
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.75 UNIT # 5
198
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.74 UNIT # 5
199
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.74 UNIT # 5
200
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.74 UNIT # 5
201
A078020160010001 CHEM 340 ML SPRAY CAN -2 -347.49 UNIT # 5
202
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.74 UNIT # 5
203
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.75 UNIT # 5
204
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.74 UNIT # 5
205
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.75 UNIT # 5
206
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.75 UNIT # 5
207
A078020160010001 CHEM 340 ML SPRAY CAN -1 -173.74 UNIT # 5
208
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
209
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
210
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
211
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
212
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
213
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
214
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
215
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
216
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
21 A07802006003000 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
181
7 1218
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
219
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
220
A078020060030001 CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML -1 -230.39 UNIT # 5
221
A078020030010008 CHEM COLIN BOTTLE -1 -57.85 UNIT # 5
222
A078020030010008 CHEM COLIN BOTTLE -2 -115.69 UNIT # 5
223
A078010010080002 CHEM ADH COMP GP FEVICOL 100ML -4 -103.54 UNIT # 5
224
A078010010080002 CHEM ADH COMP GP FEVICOL 100ML -5 -129.43 UNIT # 5
225
A078010010070004 CHEM ADH COMP GSKT SPEB-7 500ML TIN -2 -211.17 UNIT # 5
226
A078010010050015 SEALENT ANABOND 666 100 GM PKT -1 -95.86 UNIT # 5
227
A078010010050015 SEALENT ANABOND 666 100 GM PKT -1 -95.86 UNIT # 5
228
A078010010050012
CHEM ADH COMP SEAL INDIAN HDSHELLAC 60ML -3 -39.00 UNIT # 5
229
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 UNIT # 5
230
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -3 -646.43 UNIT # 5
231
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 UNIT # 5
232
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 UNIT # 5
233
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -1 -215.48 UNIT # 5
234
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 UNIT # 5
235
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 W T PLANT
236
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -1 -215.48 UNIT # 5
237
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -3 -646.43 UNIT # 5
238
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 UNIT # 5
239
A078010010020017 CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG -0.250 -53.87 UNIT # 5
240
A077110010020002 CBLMTL CONCTR BKLT 12WAY 2.5 SQMM -8 -530.00 UNIT # 5
24 A07711001002000 CBLMTL CONCTR BKLT 12WAY 1.5 SQMM -9 -321.30 UNIT # 5
182
1 1242
A077040030010001 CABLE CBLE TIE NYLON 2 MM TH TIE 2.5 MM -35 -89.25 UNIT # 5
243
A051030780010002 POW CYL SEAL KIT -1 -1122.00 UNIT # 5
244
A051030250010008 PWR CYL BR330MMXSTR 600MM SEAL KIT -1 -1530.00 UNIT # 5
245
A051030250010008 PWR CYL BR330MMXSTR 600MM SEAL KIT -2 -3060.00 UNIT # 5
246
A051030020010004 PWR CYL 1ACT,ON-OFF SHAFT SL -3 -198.90 UNIT # 5
247
A051020110010006 PWR CYL PISTN ROD,DISC,LCK,CHCKNUT -1 -32211.83 UNIT # 5
248
A051020110010004 MAKE WIPRO SLEEVE -1 -39688.20 UNIT # 5
249
A050020020110001 WITHOUT SLEEVE 8 MM DIA TH 1.0 MM -2 -120.00 UNIT # 5
250
A048010040380001 PAINT STANDARD WHITE 1 LITRE PACK -1 -279.48 UNIT # 5
251
A048010040030003 PAINT STANDARD LIGHT GREY 1 LITRE PACK -1 -279.48 UNIT # 5
252
A048010040010003 PAINT STANDARD BLACK 1 LITRE PACK -2 -546.72 UNIT # 5
253
A047060010010001 SQUARE NEOPRENE 7 MM IN CONTINEOUS L -50 -7650.00 UNIT # 5
254
A039080010010004 DIGITL MLTIMTR STD MOTWANE DM 6K3 -1 -6538.20 UNIT # 5
255
A039080010010001 DIGITL MLTIMTR STD MOTWANE LEAD ACCSRS -1 -213.74 UNIT # 5
256
A039080010010001 DIGITL MLTIMTR STD MOTWANE LEAD ACCSRS -1 -213.74 UNIT # 5
257
A036020160020001 LUBRCNT OIL TURB IOC SERVO PRIME: 32 -5 -895.50 UNIT # 5
258
A036020130010002 LUBRCNT OIL SP HYDR IOC SERVO SY HLP:68 -50 -7211.35 UNIT # 5
259
A036020090030006 LUBRCNT OIL CV HYDR IOC SERVO CONVAL-46 -60 -9654.24 UNIT # 5
260
A033030010360012 INSTPNL INDCTRANLG1SCL O/P0-199.50A -2 -0.02 UNIT # 5
261
A033020060060018 INSTPNL DESK PUSH BUTTONS FOR CPU -1 -0.01 UNIT # 5
262
A033020040090027 LED INDICATOR 24 VAC MINIATURE LAMP -10 -1224.00 UNIT # 5
263
A033020040090027 LED INDICATOR 24 VAC MINIATURE LAMP -10 -1224.00 UNIT # 5
264
A033020040090027 LED INDICATOR 24 VAC MINIATURE LAMP -5 -612.00 UNIT # 5
26 A03201005002000 HOSE FLX SSCORRU 1/4"BSP(F),L 0.8 M -2 -580.00 UNIT # 5
183
5 2266
A032010050020002 HOSE FLX SSCORRU 1/4"BSP(F),L 0.8 M -3 -870.00 UNIT # 5
267
A032010050020002 HOSE FLX SSCORRU 1/4"BSP(F),L 0.8 M -2 -580.00 UNIT # 5
268
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -1 -42.84 UNIT # 5
269
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -3 -128.52 UNIT # 5
270
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -3 -128.52 UNIT # 5
271
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -4 -171.36 UNIT # 5
272
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -10 -428.40 UNIT # 5
273
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -12 -514.08 UNIT # 5
274
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -1 -42.84 UNIT # 5
275
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -5 -214.20 UNIT # 5
276
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -2 -85.68 UNIT # 5
277
A032010020010039 SS BRAIDED LOW PR RUBBER HOSE -4 -171.36 UNIT # 5
278
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -6 -171.36 UNIT # 5
279
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -4 -114.24 UNIT # 5
280
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -4 -114.24 UNIT # 5
281
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -6 -171.36 UNIT # 5
282
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -5 -142.80 UNIT # 5
283
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -1 -28.56 UNIT # 5
284
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -4 -114.24 UNIT # 5
285
A032010020010038 SS BRAIDED LOW PR RUBBER HOSE -2 -57.12 UNIT # 5
286
A032010020010007 HOSE RUBBER SSBRD 3/8"X3/8" BSP,L500MM -4 -251.33 UNIT # 5
287
A032010020010007 HOSE RUBBER SSBRD 3/8"X3/8" BSP,L500MM -2 -125.67 UNIT # 5
288
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
28 A02912002002000 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
184
9 2290
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
291
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
292
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -10.05 UNIT # 5
293
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -10.05 UNIT # 5
294
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
295
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
296
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
297
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
298
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -10.05 UNIT # 5
299
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
300
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
301
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -2 -18.77 UNIT # 5
302
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 W T PLANT
303
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
304
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -2 -18.77 UNIT # 5
305
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -2 -18.77 UNIT # 5
306
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
307
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -2 -18.77 UNIT # 5
308
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
309
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
310
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -9.38 UNIT # 5
311
A029120020020002 ELECT INSUL TAPE STEEL GRIP BLACK -BHOR -1 -10.05 UNIT # 5
312
A029100030010006
HARDWR TORCH CELL PAPERSEAL NORMAL1,5VCE -3 -30.45 UNIT # 5
31 A02910003001000 HARDWR TORCH CELL PAPERSEAL -3 -30.45 UNIT # 5
185
3 6 NORMAL1,5VCE314
A029100030010006
HARDWR TORCH CELL PAPERSEAL NORMAL1,5VCE -3 -30.45 UNIT # 5
315
A029100030010006
HARDWR TORCH CELL PAPERSEAL NORMAL1,5VCE -2 -20.30 UNIT # 5
316
A029100030010006
HARDWR TORCH CELL PAPERSEAL NORMAL1,5VCE -3 -30.45 UNIT # 5
317
A029100010010005 TORCH EVEREADY DIGILED -2 -306.00 UNIT # 5
318
A029070030020005 POLYTHENE BAG THK 0.2 MM 12 X 18 INCH -6 -1158.95 UNIT # 5
319
A029070030020004 HARDWR POLY BAG 0.2MM SIZE24X24 INCH -20 -3266.99 UNIT # 5
320
A029070030020001 HARDWR POLY BAG 0.2MM 6X9 INCH -3 -502.90 UNIT # 5
321
A029070030010003 HARDWR POLY BAG 0.1MM 12X18 INCH -5 -712.55 UNIT # 5
322
A029070030010001 HARDWR POLY BAG 0.1MM 6X9 INCH -8.500 -1164.20 UNIT # 5
323
A029070010010002 HARDWR POLY PAPER 0.2MM 1.5 M WIDE -2 -398.80 UNIT # 5
324
A029070010010002 HARDWR POLY PAPER 0.2MM 1.5 M WIDE -5 -996.99 UNIT # 5
325
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
326
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
327
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
328
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.55 UNIT # 5
329
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
330
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
331
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -2 -67.71 UNIT # 5
332
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
333
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.85 UNIT # 5
334
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -2 -67.71 UNIT # 5
335
A027130070010003 PTFE TAPE ROLL 25 MM W 12 M -1 -33.55 UNIT # 5
336
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
33 A02713007001000 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
186
7 1338
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
339
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
340
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
341
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.01 UNIT # 5
342
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
343
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
344
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
345
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
346
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.01 UNIT # 5
347
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 W T PLANT
348
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.01 UNIT # 5
349
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
350
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
351
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
352
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -9 -153.09 UNIT # 5
353
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
354
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
355
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
356
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
357
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.01 UNIT # 5
358
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
359
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
360
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
36 A02713007001000 PTFE TAPE ROLL 12.5 MM W 12 M -1 -17.32 UNIT # 5
187
1 1362
A027130070010001 PTFE TAPE ROLL 12.5 MM W 12 M -2 -34.64 UNIT # 5
363
A027010010190004 STYLE 20 STEAM NON METALLIC 1525X1650MM -17 -1707.99 UNIT # 5
364
A023040010040011
COMPLETE REGULATOR HIGH FLOW WITH PRESSU -1 -920 UNIT # 5
365
A023040010040011
COMPLETE REGULATOR HIGH FLOW WITH PRESSU -2 -1840 UNIT # 5
366
A023040010040011
COMPLETE REGULATOR HIGH FLOW WITH PRESSU -1 -920 UNIT # 5
367
A023040010040011
COMPLETE REGULATOR HIGH FLOW WITH PRESSU -1 -920 UNIT # 5
368
A023040010030001
COMPLETE REGULATOR WITH PRESSURE GAUGE 1 -6 -9487.74 UNIT # 5
369
A019010010070038 CNTCTR&STRTR 3TH 30-22-0AF0 -1 -0.01 UNIT # 5
370
A016040020020003 CBLINS CMPN TC KTYPE PVC-UARMR PR2 -4 -440 UNIT # 5
371
A016010020030001 CBLINS 1.1SCR CUMLTUAR CR4 1.50SQMM -3 -302.94 UNIT # 5
372
A014040020210001 CORE 1 1.5 SQMM -20 -387.6 UNIT # 5
373
A003020090140001 ACTUATOR PNEUMATIC ILP M-SPA1M SEAL KIT -1 -1530 UNIT # 5
Total 1446401.00
TESTING - II :
SUPPLY
SR. NO.
MATERIAL DESCRIPTION AMOUNT
1. Relays 1,53,799
2. Ammeter / Annunciators 26,246
188
3. Capacitor / Fuses 32,972
4. Push buttons/ LEDs 17,332
5. Actuator spares 3,13,763
6. Consumables 3,000
Total Amount in Rs. 5,47,112
WORKS
SR. NO.
Order details AMOUNT
1. Work of servicing of actuator limit switch assembly of motorised valves, gates & dampers
CSTPS/4500060623, Dtd. 23.09.15
1,97,110
2. Work contract for testing of ABB/EE make switchgear protection relays
CSTPS/4500061878, Dtd. 26.09.15
6,00,000
Total Amount in Rs. 7,97,110
Total R&M expenditure during Unit#5 COH in Rs. = Rs. 5,47,112 + Rs. 7,97,110
= Rs. 13,44,222/-
= Rs. 13.44 lakhs
189