VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009
Transcript
Page 1: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

VA Southern Nevada Healthcare System

New Hospital Construction Progress May 16, 2009

Page 2: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Aerial photographs of the New Hospital construction

site from the cardinal directions.

November, 2006

Start of Construction

Page 3: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Aerial photographs of the New Hospital construction site from the cardinal directions. The Community Living Center is structurally complete. November, 2008

Two Years Progress

Page 4: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

April 2009

Page 5: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

April 2009

• Steel Decking forming first floor

Page 6: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

April 2009

• Basement level, Warehouse, CLC

Page 7: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

April 2009

• Basement level

Page 8: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

April 2009

• Community Living Center (NHCU)

Page 9: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

New Medical Center Complex Target Award Dates

Phase 1 – Central Plant and Offsite PackageAwarded: September, 2006 – CompletedCompleted: April, 2008

Phase 2 – Foundation Package Awarded: September, 2007 – CompletedCompleted: May, 2008

Phase 3 – Nursing Home RFP PackageAwarded: September, 2007

Scheduled Completion: September, 2009

Phase 4 – Main Hospital PackageAwarded: September, 2008

Scheduled Completion: September 2011

Activation – 6 to 12 months following construction completion

Page 10: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

New CBOCsWhere will they be?

4 New Primary Care Clinics

Planned Locations

Page 11: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Proposed Locations

• Southwest Southwest – Buffalo and Warm SpringBuffalo and Warm Spring

• SoutheastSoutheast– Boulder Highway and RacetrackBoulder Highway and Racetrack

• NorthwestNorthwest– Rancho and AlexanderRancho and Alexander

• NortheastNortheast– Charleston and LambCharleston and Lamb

Page 12: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Primary Care Clinic – Artist rendering

Page 13: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Primary Care Clinic (CBOC) Design

Opening Early 2011

Page 14: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Ambulatory Care Lobby

Page 15: VA Southern Nevada Healthcare System New Hospital Construction Progress May 16, 2009.

Inpatient Room