Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015
Transcript
Page 1: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Vacuum and cryogenic systems in R5.2 for MICE

Presentation tothe MICE/ISIS Operations meeting on

16/03/2015

Page 2: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

The Vacuum Group

• Hardware: Tom Weston (DL), Roy Preece (RAL), Mike Courthold (RAL), Mark Tucker (RAL)

• Controls: Ian Mullacrane (DL), John Webb (DL), Peter Owens (DL), Phil Warburton (DL)

• Integration into local EPICS: Pierrick Hanlet (LTV from FNAL)

• Integration with Hall services: Andy Nichols (RAL), Andy Gallagher (DL), and others

Page 3: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Overall description

• The turbomolecular pumps (TMPs) are as close as possible to each cryostat.

• The TMPs are outside the PRY, protected from magnetic fields.• The TMPs are backed by a shared backing manifold system.• DN100 (CF) pipework connect them with the cryostats.• The backing line pipework is DN100 (LF).• There are two backing pumps, one of which will be running

whilst the other is spare. Each pump contains a 500m3/hr ROOTS backed by an 80m3/hr dry iDQ pump.

• The vacuum system will be fully automated with in-built safety via interlocks.

Page 4: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

The Vacuum System

Page 5: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Edwards iQ backing pumps, pipework towards cryostats, and the controls rack in the North-West corner of R5.2

Page 6: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Along the South side of the cryostats

The branch with gate-valve to the North side at the EMR/KL position.

The TMP rigs will be placed on the aluminium plates adjacent to the innermost PRY legs.

Page 7: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Model view of South side of cryostats

Jason Tarrant

Page 8: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Model view of North side of cryostats

Jason Tarrant

Page 9: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

The TMP rigs and the controls rack have been tested together at Daresbury. The rigs are temporarily in the NW corner of Hall, ready for the system to be tested on the local EPICS controls software, before being placed in their correct positions: two along the South side

of cryostats; and one on the North side.

Page 10: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Cryogenics

Page 11: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Gantry for filling operations

Thanks to Jason Tarrant for these drawings and 3d view

Page 12: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

ODH

• There will be an ODH system (supplied by Crowcon)

• Audible warning inside Hall• Warning lights at entrance to Hall• Required for filling operations with liquid N

and liquid He• Required for quenches (each SS contains 300

litres of liquid He, FC contains 20 litres)

Page 13: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Bank of cryocooler compressors

Page 14: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Decay Solenoid

Dates• 16/02/2015• 16/03 to 20/03/2015• 09/04/2015• 05/05 to 29/05

Tasks• Helium compressor (8000h) service• Linde refrigerator (8000h) service• Decay solenoid cold• Exchange and service scroll pumps

for vacuum.

Page 15: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Operations Schedule

Date

• 13/03• 10/04• 20/04 to 24/04• 24/04• 01/05• 05/05 to 15/05• 18/05• 21/05• 26/05• 01/06 to 07/06• 08/06

Operation• Begin pump-out of FC• Begin cool-down of FC• Repairs of SS current leads• Begin pump-out of SSs• FC at base temperature• Verify FC magnet operation• Begin FC training• Pre-cool SSs with liq. N• Cool SSs with liq. He• Verify SS magnet operation• Begin SS training

Page 16: Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.

Liquid helium (maximal?) consumption

Dates• 15/04 to 30/04• 01/05 to 15/05• 16/05 to 31/05• 01/06 to 30/06• 01/07 to 31/07• 01/08 until May 2016

Quantities• 1,000 litres• 2,000 litres• 4,000 litres• 10,000 litres• 5,000 litres• 1,000 litres per quench