+ All Categories
Home > Documents > VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

Date post: 21-Oct-2021
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
46
VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN ROADS AND HIGHWAYS CONSTRUCTION BEHROUZ ANDABIZADEH A thesis submitted in fulfilment of the requirements for the award of the Degree of Doctor of Philosophy (Civil Engineering) Faculty of Civil Engineering Universiti Teknologi Malaysia APRIL 2017 brought to you by CORE View metadata, citation and similar papers at core.ac.uk provided by Universiti Teknologi Malaysia Institutional Repository
Transcript
Page 1: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN ROADS

AND HIGHWAYS CONSTRUCTION

BEHROUZ ANDABIZADEH

A thesis submitted in fulfilment of the

requirements for the award of the Degree of

Doctor of Philosophy (Civil Engineering)

Faculty of Civil Engineering

Universiti Teknologi Malaysia

APRIL 2017

brought to you by COREView metadata, citation and similar papers at core.ac.uk

provided by Universiti Teknologi Malaysia Institutional Repository

Page 2: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

iii

Specially Dedicated To…

My Wife and My Children

Thanks for all the love, support, motivation and always being there

whenever I need them

My Supervisor

Assoc. Prof. Dr. Abdul Kadir Bin Marsono

For his guidance and assistance throughout the whole thesis

Page 3: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

iv

ACKNOWLEDGEMENT

By praising the Almighty Allah SWT and the Seal of the Prophets Allah

SAW and his progeny RA.

At first, I would like to thank my supervisor and advisor, Assoc. Prof. Dr.

Abdul Kadir Bin Marsono, for his kind encouragement, earnest guidance,

appreciative advices, and friendly motivations. Without continuous support from my

supervisor, this research would not be the same as presented in this thesis.

In second, I would like to thank the Dean, staff of the Faculty of Civil

Engineering UTM for the facilities provided by them that support me to do this

research.

Last but not least, I want to express grateful thanks to my family; specially

my wonderful wife, their unlimited supports. Without their consistent supports and

encouragement, it was impossible for me to accomplish this work.

Page 4: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

v

ABSTRACT

Value Engineering (VE) is a total management approach to improve the

quality of construction projects. It increases the efficiency and performance of the

projects to gain the best integrated benefits. The VE focuses on function analysis of

the researched subjects and strives to achieve the required function reliably at the

lowest Life Cycle Cost (LCC). It seeks optimizing and improving decision making

to realize the optimal expenditure of owner funds while meeting required function.

The VE teamwork involving construction, design and maintenance staff reviewed

the construction project features and acquire for ways to improve quality, control

costs and time. This study focused on investigating the role of VE for existing main

road construction projects. It uses the Drainage Engineering Systems (DES) and

Surface Stream Way Drain (SSWD) after rainfall in the environmental health view

point related to VE. It predicates to decrease the air pollution and increasing the

health of environment. The main goal of this study is to design an enhanced VE

framework with main factors of drainage management in the main road. In this

study, VE questionnaire was sought to determine the overall thoughts, vistas, notion,

comprehending and understanding in addition to the connection to LCC price for

drainage and runoff of main roads, highways and streets. The quantitative data were

analyzed using one-way ANOVA technique and Factor Analysis of smart PLS. The

expert respondent provides scientific data, on the initial questionnaire with thirty

perfect answers. The qualitative data was used to support the quantitative results to

provide a mathematical framework between the twelve important main factors of

VE, DES and SSWD related to the factors of Construction Management (CM),

Materials (M), Environment (E), Human Resource (HR), Quality (Q), Aesthetic (A),

Cost (C), Time (T), Waste Materials (WM), Safety and Safety Driving (S and SD)

and Recycling (R). The findings revealed that the VE by working team can increase

performance and increase runoff collection of main roads, highways and streets. The

framework also decrease within the lowest possible cost, time, waste materials and

increase possible quality, aesthetic, safety driving and most possibly can effect

construction management, materials, recycling, human resource and environment.

The new framework of VE accepts all twelve main factors with only aesthetics factor

being rejected. The new VE framework is capable to save cost, time and increase

quality of road drainage system.

Page 5: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

vi

ABSTRAK

Kejuruteraan Nilai (VE) adalah pendekatan pengurusan untuk meningkatkan

kualiti projek pembinaan. Ia meningkatkan kecekapan dan prestasi projek untuk

mendapatkan manfaat terbaik secara bersepadu. VE memberi tumpuan kepada

analisis fungsi subjek yang dikaji dan berusaha untuk mencapai fungsi yang

diperlukan pada tahap kos kitar hayat (LCC) yang paling rendah. Ia bertujuan

mengoptimum dan meningkatkan proses membuat keputusan untuk merealisasikan

perbelanjaan optimum pemilik di samping memenuhi fungsi diperlukan. Pasukan

kerja VE yang melibatkan staf pembinaan, reka bentuk dan penyelenggaraan

pembinaan memperoleh jalan untuk meningkatkan kualiti, kawalan kos dan masa.

Kajian ini memberi tumpuan kepada penyelidikan tentang peranan VE untuk projek

pembinaan jalan utama sedia ada. Ia menggunakan Sistem Kejuruteraan Saliran

(DES) dan Laluan Peparitan Permukaan (SSWD) selepas hujan dari sudut

pandangan kesihatan alam sekitar yang berkaitan dengan VE. Ia juga mengurangkan

pencemaran udara dan meningkatkan kesihatan alam sekitar. Matlamat utama kajian

ini adalah untuk merekabentuk rangka kerja VE baru dengan faktor-faktor utama

pengurusan perparitan di projek jalan utama. Dalam kajian ini, soal selidik VE telah

di peroleh dari pendapat, pandangan, tanggapan dan pemahaman responden yang

berkaitan dengan harga pada LCC untuk saliran dan air larian jalan raya utama,

lebuh raya dan jalan biasa. Data kuantitatif dianalisis menggunakan teknik ANOVA

sehala dan Faktor Analisis PLS pintar. Responden pakar menyediakan data saintifik

pada soal selidik awal dengan tiga puluh jawapan yang munasabah. Data kualitatif

telah digunakan untuk menyokong keputusan kuantitatif dalam menyediakan rangka

kerja matematik di antara kedua belas faktor utama. Faktor utama VE pada DES dan

SSWD adalah berkaitan dengan faktor-faktor Pengurusan Pembinaan (CM), Bahan-

bahan (M), Alam Sekitar (E), Sumber Manusia (HR), Kualiti (Q), Estetika (E), Kos

(C), Masa (T), Bahan sisa (WM), Keselamatan dan Keselamatan Memandu (S and

SD) dan Kitar Semula (R). Dapatan kajian menunjukkan bahawa VE oleh pasukan

kerja boleh meningkatkan prestasi dan meningkatkan pengumpulan air larian jalan

raya utama, lebuh raya dan jalan biasa. Rangka kerja ini juga berkemungkinan dapat

mengurangkan kos, masa, merendahkan bahan sisa dan meningkatkan kualiti,

estetika, keselamatan memandu. Ia juga memberi kesan terhadap pengurusan

pembinaan, bahan-bahan, kitar semula, sumber manusia dan alam sekitar. Rangka

kerja baru VE ini menerima kesemua dua belas faktor utama dengan hanya menolak

faktor Estetika di dalam rangka kerjanya. Rangka VE baru ini mampu untuk

menjimatkan kos, masa dan meningkatkan kualiti sistem saliran jalan raya.

Page 6: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

vii

TABLE OF CONTENTS

CHAPTER TITLE PAGE

DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENT iv

ABSTRACT v

ABSTRAK vi

TABLE OF CONTENTS vii

LIST OF TABLES xiii

LIST OF FIGURES xv

LIST OF ABBREVIATION xvii

LIST OF APPENDICES xxi

1 INTRODUCTION 1

1.1 Introduction 1

1.2 Problem Background of The Study 3

1.3 Objectives of The Study 8

1.4 Scopes of Study 8

1.5 Research Significant 10

1.6 Operational refinition of Terms 10

1.7 Brief of Research Methodology 12

1.8 Structure of Thesis 13

2 LITERATURE REVIEW 15

2.1 Introduction 15

2.2 Engineering Economic 16

2.3 Review of Relevant Research on VE 19

Page 7: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

viii

2.3.1 VE in construction 19

2.3.2 VE in Main Roads and Highways

Construction 23

2.3.3 Value Planning 26

2.4 Value Management (VM) 27

2.5 Value Engineering (VE) 28

2.5.1 Main Characteristics of Value

Engineering 28

2.5.1.1 Value 28

2.5.1.2 Worth 29

2.5.1.3 Function 29

2.5.1.4 Life Cycle Costs 30

2.5.1.5 Systematic and Organized 31

2.5.1.6 Alternatives 31

2.5.1.7 Cost 31

2.5.1.8 Quality 33

2.5.1.9 Time Scheduling (TS) 33

2.6 Value Creation (VC) 34

2.7 Methodology of VE 34

2.8 Potential Applications For VE 37

2.8.1 Criteria for Evaluating VE In Main Roads

and Highways Construction 39

2.8.2 VE In Design of Main Roads and

Highways Construction 40

2.8.3 Rules Of Design And Build for Main

Roads And Highway Construction 41

2.9 Value Management and Decision Making 44

2.10 VE in Pre-Construction for Main Roads and

Highways Projects 46

2.10.1 Project Selection 46

2.10.2 Time 47

2.10.3 Participation 48

2.10.4 Standard Plans (SP), Specifications and

Design Criteria (DC) 48

2.10.5 VE Teams 48

2.10.6 Owner’s Engineering Scope 49

2.10.7 Front-End Engineering 49

Page 8: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

ix

2.10.8 Framework of Cost 51

2.11 Value Engineering Workshops In Main Roads and

Highways Construction 51

2.11.1 Information Phase (IP) 52

2.11.2 Function Phase (FP) 53

2.11.3 Creative Phase (CP) 53

2.11.4 Judgment Phase (JP) 54

2.11.5 Development Phase (DP) 54

2.11.6 Recommendation Phase (RP) 55

2.12 Post-Study Procedures 56

2.12.1 Value Engineering Study Time Schedule 56

2.12.2 Relations Between Value And Worth 56

2.12.3 The Function Analysis System Technique

(FAST) Diagram 57

2.13 Integration with Various other Initiatives 58

2.13.1 Main Road Safety (MRS) 59

2.13.2 Value Opportunities During Construction 59

2.13.3 Accelerated Development of Construction 60

2.13.4 Best Value Contracting 61

2.13.5 Design and Build 61

2.13.6 Relationship of Value, Function, Cost

And Worth 61

2.14 Benefit of Value Analyze 62

2.15 Life Cycle Cost (LCC) Analysis 63

2.16 VE During Operations And Support 65

2.17 Criteria of Cost, Time and Quality) of VE for

Highways and Main Roads Projects 67

2.18 Drainage Engineering System (DES) and Surface

Stream Way Drain (SSWD) 69

2.18.1 Expression Related to the DES and

SSWD 70

2.18.2 Road Drainage Engineering System

Components 73

2.18.3 Requirements and tasks of drainage

engineering 74

2.18.4 Drainage criteria 77

2.19 Domain work area 78

Page 9: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

x

2.20 Clearing and Cleaning 78

2.21 Summary 79

3 RESEARCH METHODOLOGY 80

3.1 Introduction 80

3.2 Development VE Framework 80

3.3 Framework Methodology 81

3.3.1 First Part for Framework of Research

Methodology 81

3.3.1.1 Literature review on VE for

Main Roads Construction

Projects 81

3.3.1.2 Investigation of VE for main

roads construction projects 82

3.3.1.3 Identify VE criteria for main

roads construction Projects 82

3.3.1.4 Priority of VE criteria in main

roads construction Projects 82

3.3.1.5 Quantitative Criteria 82

3.3.1.6 Qualitative Criteria 83

3.3.2 Second Part for Framework of Research

Methodology 83

3.3.2.1 The selection of VE criteria in

Main Roads Construction

projects for DES & SSWD 83

3.3.2.2 Design of questionnaire and Data

analysis 83

3.3.3 Hypothesis and Develop of a framework

of VE for main roads construction

projects of DES and SSWD 84

3.3.4 Validation 85

3.4 General Format of Questionnaires Study 86

3.4.1 The Content Questionnaire for VE of

DES & SSWD 87

3.4.2 Zone of Data collection 88

3.5 Statical Package Science Statistical Package for

the Social ( SPSS) and Smart Partial Least

Squares ( Smart PLS) 89

3.5.1 Exploratory factor analysis with SPSS 90

Page 10: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xi

3.5.2 Confirmatory factor analysis with Smart

PLS 90

3.5.3 Target Respondent for Pilot 90

3.6 Data Analysis for Initial Study 92

3.7 List of hypothesis of main factors 97

3.8 Respondents' Categories For Actual Study 98

3.8.1 Response Rate of actual study 101

3.8.2 Sampling Respondent of actual study 102

3.9 Tools and Methods of Data Collection of VE for

Actual study 102

3.9.1 Respondent of Study 103

3.9.2 Software 103

3.10 Sample Space 103

3.11 Questionnaires Format for the Pilot Study 104

3.12 Selection of Province Main Roads, Highways and

Street Construction Projects 104

3.13 Quantitative Criteria for VE and DES, SSED in

Roads, Highways and Streets Construction

Projects 105

3.14 The measurement of variables 105

3.15 Summary 106

4 DATA ANALYSIS AND RESULTS 108

4.1 Introduction 108

4.2 Exploratory Analysis of main factors 109

4.3 Descriptive analysis of main factors and

corresponding sub factor 114

4.3.1 Construction Management (CM) Sub

Factor Analysis 114

4.3.2 Drainage Engineering System and Surface

Stream Way Drain (DES & SSWD) at

main roads, highways and streets sub

factor analysis 115

4.3.3 Recycling (REC) Sub factors Analysis 116

4.3.4 Human Resource (HR) Sub factor

Analysis 117

4.3.5 Cost (Cost) Sub factor Analysis 118

4.3.6 Quality (QL) Sub factor Analysis 119

Page 11: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xii

4.3.7 Material (MT) Sub factor Analysis 119

4.3.8 Time (Time) Sub factor Analysis 120

4.3.9 Environment (ENV) sub factor analysis 120

4.3.10 Waste Materials (WM) sub factor analysis 121

4.3.11 Aesthetic and Safety and Safe Driving

(S&SD) sub factor analysis 122

4.4 Preliminary Data Analysis 122

4.4.1 Normality test 122

4.4.2 Outliers 122

4.4.3 Common-method variance 123

4.4.4 Multi - Collinearity 123

4.5 Structural Equation Modeling (SEM) 124

4.5.1 Measurement model 125

4.5.2 Convergent Validity 126

4.5.3 Discriminant validity 131

4.6 Path Analysis 135

4.6.1 Predictive Relevance Q2 140

4.6.2 Effect Size f 2 140

4.6.3 The Importance-Performance Matrix

Analysis (IPMA) 141

4.7 Summary 146

5 CONCLUSION 147

5.1 Introduction 147

5.2 Discussion 147

5.3 Conclusion 153

5.4 Limitation of the Research 155

5.5 Recommendations and Future Research 155

REFERENCES 157

APPENDIX A-B 169-231

Page 12: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xiii

LIST OF TABLES

TABLE NO. TITLE PAGE

2.1 he difference between value engineering and engineering

economics (Opencourseware, 2009) and (Galloway, 2007) 18

2.2 he previous studies of quality and the VE in Construction 22

2.3 he continue previous studies of quality and the VE in

Construction 24

2.4 Summary of Criteria for Evaluating VE in Main Roads and

Highways projects (AASHTO, 1987) 39

2.5 Summary of past VE savings Federal- Aid Lands Highway

Programs (SIVE, 2016) 60

3.1 Scale ranking of questionnaire 86

3.2 Characteristics of Tehran Province (Kavosi et al., 2012) 89

3.3 Respondent categories for pilot study 91

3.4 Initial component analysis put Variance for factor extaction 93

3.5 Respondents of VE actual study 99

3.6 Education level of respondents for qualitative criteria in

highways projects criteria 100

3.7 Experiences of respondents for qualitative criteria in actual

study 101

3.8 Survey responses of second study 102

4.1 Results of EFA with Varimax rotation for 56 items related

to value engineering dimension (N = 160) 111

4.2 Descriptive statistic for related items to Construction

Management (CM) (n=160) 115

4.3 Descriptive statistic for related items to DES & SSWD at

main roads, highways and streets (n=160) 116

4.4 Descriptive statistic for related items to recycling (n=160) 117

4.5 Descriptive statistic for related items to human resource

(n=160) 118

4.6 Descriptive statistic for related items to Cost (n=160) 118

Page 13: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xiv

4.7 Descriptive statistic for related items to Quality (QL)

(n=160) 119

4.8 Descriptive statistic for related items to Material (MT)

(n=160) 120

4.9 Descriptive statistic for related items to Time (n=160) 120

4.10 Descriptive statistic for related items to Environment

(ENV) (n=160) 121

4.11 Descriptive statistic for related items to waste materials

(n=160) 121

4.12 Common-method variance result 123

4.13 Multicollinearity test based on correlation coefficients 124

4.14 Multicollinearity test based on VIF 124

4.15 The result of Convergent Validity 127

4.16 T-Statistics of Outer Loadings based on boot strapping

method 129

4.17 T-Statistics of Outer weight based on boot strapping

method 130

4.18 Correlation of latent variables and discriminant Validity 133

4.19 Cross Loading Output Using SmartPLS 134

4.20 List of Hypotheses and Relative Paths 136

4.21 Test of the total effects using bootstrapping for model 1 139

4.22 Results of R2 and Q2 Values in the model 140

4.23 Results of effect size f2 for all exogenous variables 141

4.24 Importance and Total Effects for the IPMA of DES &

SSWD 142

4.25 List of Hypotheses and Relative Path 144

5.1 Discussion and Result Data Analysis 152

5.2 The objectives and conclusions of the study 154

Page 14: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xv

LIST OF FIGURES

FIGURE NO. TITLE PAGE

1.1 Water stream effect source; in (Flooding rainfall in Tehran,

2011). 6

1.2 Tehran Province in the North of Iran 9

1.3 Steps of the methodology 13

2.1 Differences between Value Planning (VP) and Value

Engineering (VE)(Othman, 2008) 27

2.2 Potential Savings in Lifecycle of a Project (AASHTO,

1987) 40

2.3 Relations between increase value and cost or saving (Daniel

P, 2006) 43

2.4 Relations between Value Increment, Cost and Function

(Aminzadeh Rahim, 2013) 45

2.5 Improvement to the project with implementation of Front-

End Engineering (Aminzadeh, 2013) 50

2.6 Technical-Oriented FAST Diagrams (Miles, 2015) 58

2.7 Criteria influencing Main Roads performance (Chen et al,

2010) 68

2.8 Configuration of the paved and unpaved road (Mahbub,

1994) 69

2.9 Slopes on Pavement of Cross-Section for Main Roads(Yang

et al., 2013) 70

2.10 DES & SSWD implementation(Mahbub, 1994) 70

3.1 Twelve factor framework for Research Methodology 85

3.2 Map of Iran whit neighboring countries 88

3.3 Provinces of Iran 88

3.4 Tehran’s highways and streets 89

3.5 Respondent categories in initial study 91

3.6 Initial framework path 95

Page 15: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xvi

3.7 Initial framework of intraction between DES & SSWD with

other factors 96

3.8 Initial framework of intraction between DES & SSWD and

CM with other factors 97

3.9 Respondent categories for qualitative criteria in highways

projects of actual study 99

3.10 Education levels of respondents for qualitative criteria of

actual study 100

3.11 Experiences of respondents for qualitative criteria in actual

study 101

4.1 Path model between independent variables and dependent

variable 138

4.2 Importance and Total Effects for the IPMA of DES &

SSWD 143

4.3 Path model between independent variables and dependent

variable 145

Page 16: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xvii

LIST OF ABBREVIATION

A

AHCO

ASHTTO

-

-

-

Aesthetic

American Heritage College Dictionary

American Association of State Highway and Transportation

Officials

BV - Best Value

C - Cost

CBR - Case-Based Reasoning

CC - Conduct Current

CM - Construction Management

CP - Creative Phase

CPII - Construction Project In IRAN

CPM - Critical Pass Method

CR - Cost Reduction

DB - Design Build

DBD - Decision Build Design

DC - Design Criteria

DES - Drainage Engineering System

DES &

SSWD

- Drainage Engineering System and Surface Stream Way

Drain

DOD - Department Of Defence

DOT - Department Of Transportation

DP - Development Phase

DSS - Decision Support System

Page 17: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xviii

E - Environment

EC - Energy Cost

EE - Engineering Economic

EFA - Exploratory Factor Analysis

EOOI - Engineering Organization Of IRAN

EP - Evaluation Phase

EP - Expensive projects

EVM - Earned Value Management

FAH - Federal -Aid Highway

FAP - Function Analysis Phase

FAS - Federal -Aid System

FH - Federal Highway

FHWA - Federal High Way Administration

FLHP - Federal Lands Highway Programs

FM - Framework Methodology

FP - Functional Performance

FP - Function Phase

GEC - General Electric Corporation

HR - Human Resource

IC - Initial Cost

IDA - Institute Defence Analysis

IVES - Indian Value Engineering Society

IP - Implementation Phase

IPABO - Iranian Programming And Budget Organization

JP - Judgment Phase

LCA - Life Cycle Assessment

LCC - Life Cycle Cost

Page 18: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xix

LCIA - Life Cycle Impact Assessment

LCP - Life Cycle Project

MA - Maintenance Ability

M - Materials

MCR - Main Construction Roads

MRCP - Main Road Construction Projects

MRS - Main Road Safety

MS - Mathematical Standard

NCHRP - National Cooperative Highway Research Program

NHS - National Highway Systems

O - Operability

OP - Orientation Phase

OR - Owner Requirement

PMBOK - Project Management Body Of Knowledge

PMO - Project Management Office

PP

PV

-

-

Presentation Phase

Present Value

Q - Quality

QM - Quality Management

R - Recycling

RFP - Request For Proposals

RM - Runoff Management

ROA & V - Regard Of Aesthetics and Environment

ROI - Return On Investment

ROP - Return Of Profit

RP - Recommendation Phase

S - Safety

Page 19: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xx

S & SD - Safety and Safe Driving

SAVE - Society American Value Engineering

S - Scalability

SIVE - Society Iranian Value Engineering

SP - Standard Plans

SSWD - Surface Stream Way Drain

SW - Support Weight

SWS - Surface Water Stream

T - Time

TS - Time Scheduling

TT - Transmit Torque

VA - Value Analysis

VC - Value Creation

VD - Value Design

VE - Value Engineering

VECP - Value Engineering Change Proposal

VEITPM - Value Engineering Information Technology Project

Management

VEP - Value Engineering Plan

VI - Value Iimprovements

VI - Value Index

VM - Value Methodology

WM - Waste Materials

Page 20: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

xxi

LIST OF APPENDICES

APPENDIX TITLE PAGE

A Pilot study for Factor Analysis 169

B Actual Study 231

Page 21: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

CHAPTER 1

1 INTRODUCTION

1.1 Introduction

Value Engineering (VE) is a way of evaluating a process by studying the

functions of. It includes a critical evaluation of processes carried out in terms of

components, equipment and all cost occurring items in producing a product or

projects. The implementation of the VE procedure on a project typically involves

some combination of performance evaluation such as; quality, reliability,

durability, safety, effectiveness, or other desirable characteristics. The main aim of

VE is to focus on cost saving, and on the other areas of a client needs during the

constructional projects such as building, dams, and transportation. VE introduces

sub- systems and makes a relationship among them in order to highlight the most

prominent aspect of construction project. Consequently, the efficiency and quality of

the project can be enhanced (Chung et al., 2009). VE can be presented as a pre-

designed model to conquer the challenges of the construction projects (Abidin and

Pasquire, 2007). VE also helps to reduce costs and manage time ((Robichaud and

Anantatmula, 2011) and at the similar time enhances quality and effectiveness with

the addition of benefit to the projects. It is truly carried out to stabilize price and

offers a very well-considered method by using of functional plan and team of

specialists (Issa et al., 2013)

VE helps corporations to be more efficient in handling initiatives both

locally and globally by:

Detailing on cost breakdown;

Usefulness and profitability;

Page 22: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

2

Enhancing Quality and Values;

Managing time (scheduling) efficiently;

Enhancing team working;

Optimizing Design and Operation (production);

Using all resources efficiently and

Solving methodically for problematic projects and special projects

VE is an inventive and also problem-solving soft application, also it is a

systematic framework to optimize values within a particular scope of work through

process engineering (Ross and Rhodes, 2008). The profit of VE application tend to

be superiorly realized from the project’s goals by getting much more worthy with

investment along with the particular client’ desires for improve spacing the

characteristics and challenges, (Chi et al., 2014).

A VE program typically involves a several specific venture and course of

action to create merchandise through a simple and effective ideas and productive

venture decision (Davis, 2013).

During the World War II (1939-1945), due to the shortage of resources for

reconstruction of the buildings, the development was connected to an innovation

based on the idea of VE. The solution was often sorted in situation along with fewer

change. After that, analytical discipline had been formulated in exclusive market

sectors which are targeted to be able to question the standard ways of design to find

the less price alternatives (Zarandi et al., 2011a). In the 1940s, the VE was initially

used by Lawrence D. Miles who discussed one method, which has been applied in

the General Electric Corporation (GEC) by considering a different problem -solving

solution to fulfill the actual asks. This particular action spied out the door

(throughout World War II) with regard to other new methods to watch out to any

work needed within multiple methods.

Page 23: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

3

In 1947, Mr. Miles and his team developed a step-by-step system, called

Value Analysis (VA) it analyze a product’s cost that relate to a function to ferret out

unnecessary costs. As a result of substantial investment in knowledge, the new

methodology called Value Analyze (VA) was developed, tested, and proven to be

highly effective. However, until 1952 that VA began its growth throughout various

industries. The Federal-Aid Highway (FAH) act of 1970 in USA to made as the first

Federal Highway (FH) reference to VE. It is requiring that in such cases the

Secretary of determines an advisable plans, specifications and estimation for

proposing projects on any Federal-Aid System (FAS) which is accompanied by a VE

or other cost reduction analysis. The USA congress extended the federal VE role

with the passage of the National Highway Systems (NHS) (Aminzadeha and Ismailb,

2011).

It was absolutely determined that all federally financed Country National

Highway System (NHS) projects worth more than US$25 million (RM 75 million)

should be worked with VE in order to calculate price tag as well as budget. It was

then considered to apply VE in every government assignments or, particularly

assignments wherever price tag is cut and received possibility for cost savings. It

absolutely was the decision through Federal Highway Administration (FHWA) that

every condition will utilizes VE, within their interstate along with highway

undertaking design advancement and constructing (Chi et al., 2014).

1.2 Problem Background of The Study

Annually, an enormous sum of money is needed on investing of

infrastructure and building advancement that needs to be completed with lowest

price tag and in the smallest moment doable. There is a requirement to Return On

Investment (ROI) as the particular challenge that need to support financial savings a

high. VE has been defined as a cost lowering process which is able to discover and

determine price lowering methods across the challenge of prerequisite decreasing the

Life Cycle Cost (LCC) projects, Life Cycle Assessment (LCA) and Life Cycle

Impact Assessment (LCIA). All of mentioned issues feasible by means of method of

Page 24: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

4

assessing which impacts on product or service during its life in VE (Hischier et al.,

2009; Finnveden et al., 2009). Also, one of the key requirements of each project is to

define ROI that VE recognised as most appropriate value to avoid on increasing cost

(Giel and Issa, 2011). Clearly such actions are usually obtained to optimize cash to

build the main roads, freeways, highways and streets construction projects. VE is

usually one in a position to resolve conditions that may appear throughout the project

implementation; spending additional tasks. VE affords the alternative to choose the

easiest method to enhance efficiency for the lowest probable cost by supporting a

good quality (Miles, 2015).

VE is associated with project management body of knowledge “Project

Management Body Of Knowledge (PMBOK)” and Earned Value Management

(EVM) as a powerful project management method that is implemented in

engineering and construction projects. There are various recommended methods and

frameworks for EVM practices, such as ANSI/EIA-748, PMI’S and the practice

standard for EVM (Kwak and Anbari, 2012).

However, VE is not being fully utilized in developing countries, because

there is a little technical knowledge and expertise in this area that are available in

these countries. In the construction project such as highways, main roads and

freeways, Iran is considered as one of the developing country which suffering from

the need to implement of new concept such as VE. Performing the VE in roads and

highways in developed countries indicate that repeating the same procedure of Iran

as developing country is a promising idea. Introducing VE can dedicate the

functionality to the Engineering Organization Of Iran (EOOI). Observing VE in

construction of roads and highways by introducing a true model including the key

constructs cause, the estimation of project can become close to the final

implementation of the project by saving time, money and other capital advantages.

Moreover, a reliable model of VE can be regarded as novel paradigm for other

Construction Project In Iran (CPII). Some are dilemma regarding to the construction

project in Iran are as follow:

Page 25: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

5

The average life of the nation’s main roads and highways is 2 to 9

years(Larson, 1993);

The number of unfinished projects is 8000;

27% of highway projects was implemented partially;

28% of projects have difficulties in the operation; every year due to

lack of proper and efficient operation of the construction system,

the country loses an equivalent of US$1650 million (RM4950

million)(IHWTI, 2009), (Institute High Ways Transportation Iran,

2009). Therefore, most problems are caused by the following:

Lowest quality in main roads and highways construction (Xia,

2013).

Wastage in construction materials.

Cost construction more than budgeted (Kelly and Male, 1991); and

Lack of human expert in main roads and highways construction

VE might be utilised in deriving worth for main road, freeway and highway

projects. It can be made through technology associated with design in order to

optimize the purposes. VE model keep a value for money technique with regard to a

Life Cycle Project(LCP) and time (Petroutsatou et al., 2012).

Some researchers who have study on the main road construction projects by

applying VE to include: cost management and reduction, quality improvement,

resource optimization implementation, the detailed costs breakdown, improve

teamwork, improve the quality and quantity indicators, methodical system for

specific projects and problematic projects (Vilasini, 2014).

But there is not any research from the view point of VE on the Surface

Stream Way Drain (SSWD) after each rainfall. Surface waters are one of the most

noticeable polluted waters and are deranging the road and highway. Therefore, this

research focused on investigating the role of VE of main road construction projects

that uses the Surface Stream Way Drain (SSWD). Figure 1.1 show the uncontrolled

Page 26: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

6

water stream on the surface of the roads and highways that create difficulties to

driver and pedestrian.

Figure 1.1 Water stream effect source in Flooding rainfall, Tehran, 2011.

Construction projects have numerous dependencies that come from concept

of construction operations such as policy, environment, culture, budget, and many

other that cause changes in the construction project consequently. In such varying

condition any proposed method and algorithm by specialist in construction field need

revision and improvement by others for a new situations. Therefore, this work would

be treated differently, but the main architecture or prime framework would be

preserved.

The absolutely obvious challenge with respect to the VE method in main road

construction in Tehran is a Surface Water Stream (SWS) (handling the main road

SWS). The influential remedy of that could be executed explicitly is including the

VE principles in this case. The surface water stream drain is not alone in a prominent

component of VE in the main road construction instead, a technical part, costs,

environment, human resource and quality are also a parameter in order to cast a

complete algorithm. This matter is the main consideration of this study.

Soil, water and weather are also the main parameters in SWS study, in

contrast to the structures, but less attention to the water effects (drainage and stream

way) in highways and roads (Jochimsen et al. 2004) are also found. Various studies

Page 27: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

7

have been done on the main road construction projects by implementing

VE including: cost management and reduction, quality improvement, resource

optimization implementation, the detailed costs, improve teamwork, enhance the

quality and quantity indicators, methodical system for particular projects and

problematic projects. However, there is not any research from the VE point of view

on the Surface Stream Way Drain (SSWD) and Drainage including a Runoff

Management (RM) there are very important after each rainfall. Surface water is one

of the most polluted waters and have very noticeable effect on the environment.

Therefore, this research focused on investigating the role of VE of main road

construction projects specifically, the Surface Stream Way Drain (SSWD) to

decreasing the air pollution and increasing the health of environment.

Main roads and highways construction projects regulation may vary not only

among countries but also between regions on state in a country. As matter of fact,

streets, main roads and highways drainage has becomes a controversial issue for

highways and roads in Iran (Tajrishi Masoud, 2013). The Iran government has

introduce a DES&SSWD that associated items as the main part of a construction

projects such as; cost, time, human resource, construction management, aesthetic,

quality, safety and so on. In other word, DES & SSWD is not only pivoted on

deviation of water from surface but also can be regarded as influential matter in

construction of roads and highways as discussed in this chapter.

According to Iranian Programming And Budget Organization (IPABO) (PBO

country, 2016), drainage is a special item from designing and execution of

construction. Thus it is crucial to know the relationship between DES & SSWD and

other items then may in dude. Climate and environment situation in Iran that causes

DES & SSWD implementation become more flexible than other items. In DES &

SSWD the traditional material and novel material can be used to provide desired

design characteristics. Different engineering methodology is used as well. Clearly,

DES & SSWD is regarded as one of the prime factor and can develop VE concept in

Iran.

Page 28: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

8

1.3 Objectives of the Study

The aim of this study is to develop a framework for value engineering in road

construction projects. This framework is to include drainage eingineering system,

surface stream way drain in construction management of main roads, highways and

streets to increase projects value while reducing costs, maintaining quality and

implementing the manpower efficiently, reduce the construction materials and

materials disposal. The proposed framework can be generalised and implemented for

other type of construction projects as well.

The following are the key objectives of this research work:

1. To identify the criteria of value engineering and drainage

eingineering system, surface stream way drain for main roads

construction in Iran.

2. To categorize and prioritize the extracted criteria of value

engineering and drainage eingineering system, surface stream way

drain for main roads, highways and streets at construction projects

in Iran.

3. To develop a new framework of value engineering and drainage

eingineering system, surface stream way drain for main roads,

highways and streets in construction projects.

4. To validate the framework for value engineering and drainage

eingineering system, surface stream way drain for main road

construction

1.4 Scopes of Study

The provincial selected for this study for (pilot and actual survey) is Tehran,

as one of the large-population province of Iran, It is located in the north. (Figure

1.2). As one of the most strategically important investment and development areas.

Page 29: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

9

Figure 1.2 Tehran Province in the North of Iran

In this study a total of twelve criteria for VE considered are as follow for

exising roads network:

1. Drainage Engineering System (DES) and Surface Stream Way

Drain (SSWD)

2. Construction Management (CM)

3. Time ( T )

4. Cost ( C )

5. Quality ( Q )

6. Safety and Safe Driving (S & SD)

7. Environment ( E )

8. Human Resource (HR)

9. Materials (M)

10. Aesthetic (A)

11. Recycling ( R )

12. Waste Materials (WM)

Page 30: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

10

Other VE criteria such as reduce design problem, trouble-free project

implementation, durability and stability, increase life cycle projects, performance

improvement, investment improvement, reduced amount of rework, flexibility,

increase maintenance, satisfaction of project stakeholders and development plan, etc.

are not included in this study.

The criteria of VE of Aesthetic (A), Safety and Safe Driving (S&SD),

environment (E) and quality (Q) one included to create an acceptable and

comfortable level for customer and users. Human Resources (HR) is criteria to

improve the relationship between engineering and experts. In Materials (M) criteria

the scope is to find a simple method of solution to material consumption efficiently

in doing the projects and implementation. In SWS, DES and SSWD criteria is to find

a technical solution for sustainability to achieving its values. The Time (T), Cost (C)

and Construction Materials (CM) and Waste Materials (WM) is to reach a minimum

value during construction.

1.5 Research Significant

This study is important in determining the following benefit:

1. Identification of VE criteria for main road construction.

2. Prioritization of VE criteria for main road construction.

3. Finding the relationship among main road construction criteria.

4. Introducing a new VE framework for main road construction.

1.6 Operational definition of Terms

There are various businesses that apply the VE techniques such as product

and process procedure system in manufacturing industry, service in business or

economy activity in construction, governance, health care, and other service sector.

Page 31: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

11

The focuses of value features are actually from the client point of view or to fulfil the

stakeholder requirement. Obviously, VE can provide maximum benefits for

stakeholders, and especially for government in infrastructure projects. Then VE is an

expert procedure of finding the most effective technique for the engineering in

finding the most effective technique for doing the work. By focusing on function, the

maximum value from the activity is achieved with identification, processing and

innovation of the work, that benefit the stakeholders and government. There are

some definitions about VE as follows:

According to Kelly, Male and Graham, (2004), VE is the process

of making explicit functional benefits a client requires from the

whole or parts of a project at an appropriate cost during design and

construction. VE is also identifying and reducing unnecessary cost

calculation method during design and construction of the project.

VE is a systematic procedure aimed at achieving the required

functions at the least, cost. In VE, all parties should realize the

functions required and conditions of all design alternatives mast

fulfill the same performance and selecting the best one(Dell isola,,

A, 1969).

According to the Indian VE Society (INVEST, 1977) (Gordon et

al., 1977), VE is a function oriented, systematic team approach and

a study to provide a good value in a product, system or services.

This improvement is also focused on cost reduction; however,

other important areas such as customer perceived quality and

performance are also of paramount importance in the value

equation.

According to the International Society of American Value Engineering

(Save, 1972) (Michel and Woodhead, 1997), VE is a systematic application of

recognized techniques, which identify the monetary value for a particular function,

and provide the necessary function reliability at lowest overall cost.

Page 32: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

12

Based on the definition of VE, it can be summarized that VE is systematic

techniques of procedures to get the best alternative or improvement of design at the

lowest cost with the same or better quality and performance during the assigned

construction phase.

1.7 Brief of Research Methodology

This research will be carried according to Figure 1.3 to propose and develop

a new framework of Value Engineering (VE) based on Surface Water Stream

(SWS), Drainage Engineering System (DES) and Surface Stream Way Drain

(SSWD) for existing main roads, highways and streets construction. It also check the

validity of VE framework for drainage management system in main roads

construction. The obtain VE characteristics way also useable for a new main roads

constructions. VE for SWS, DES and SSWD one also mean that drainage

construction.

Page 33: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

13

Figure 1.3 Steps of the methodology

1.8 Structure of Thesis

The thesis is structured into five chapters to include; Chapter 1 that mentions

about the issue of the study. The chapter also includes the study aim and objectives.

In addition, scope of the study brief of methodology and overall thesis structure are

also introduced in this chapter.

Chapter 2 reviews the literature and previous works on VE for Highways and

Main Roads and Streets construction. It review a development of VE in order to

obtain comprehensive framework for VE in drainage constructions, Therefore this

chapter has two section of one section about a VE in a few construction work

Page 34: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

14

industry, and another section is about Drainage and Surface Stream Way Drain. Both

sections are focusing on VE in existing Highways, Main Roads and Streets for

Drainage and Surface Stream Way Drain.

Chapter 3 presents the research methodology, data collection explaining,

statistical analysis technique and tools, respondent's characteristics, sampling

explaination survey, and response rate and framework test.

Chapter 4 is about the data analysis. It include the primitive data analysis

such as Exploratory Factor Analysis (EFA), descriptive data analysis and inferential

data analysis encompassing correlation test and multiple linear regressions. The

gathered data is analyzed using computer tools for interpretation.

Chapter 5 presents a conclusion of the entire thesis and derived

the suggestions and recommendations for future research.

Page 35: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

REFERENCES

Ã, J.Y., Peng, S., 2008. Development of a customer satisfaction evaluation model for

construction project management 43, 458–468.

doi:10.1016/j.buildenv.2006.07.044

Aapaoja, A., Haapasalo, H., Söderström, P., 2013. Early stakeholder involvement in

the project definition phase: case renovation. ISRN Ind. Eng. 2013.

AASHTO, L., 1987. LRFD bridge design specifications. Washington, DC Am.

Assoc. State Highw. Transp. Off.

AASHTO, T., 2003. 307 (2003) Determining the Resilient Modulus of Soils and

Aggregate Materials. Am. Assoc. State Highw. Transp. Off. Washington, DC.

Abidin, N.Z., Pasquire, C.L., 2007. Revolutionize value management: A mode

towards sustainability. Int. J. Proj. Manag. 25, 275–282.

doi:10.1016/j.ijproman.2006.10.005

Ageron, B., Gunasekaran, A., Spalanzani, A., 2012. Sustainable supply management:

An empirical study. Int. J. Prod. Econ. 140, 168–182.

Ahlin, B., Drnovšek, M., Hisrich, R.D., 2014. Exploring the moderating effects of

absorptive capacity on the relationship between social networks and innovation.

J. East Eur. Manag. Stud. 213–235.

Ahuja, R., 2013. Sustainable construction: is lean green?, in: ICSDEC 2012:

Developing the Frontier of Sustainable Design, Engineering, and Construction.

pp. 903–911.

Allen, T.M., Bathurst, R.J., 2013. Design and performance of 6.3-m-high, block-

faced geogrid wall designed using k-stiffness method. J. Geotech.

Geoenvironmental Eng. 140, 4013016.

Aminzadeh, Rahim and Esmaeil, A., 2013. Value Engineering in Highways

Construction.

Aminzadeh, Rahim and Ismailb, Amirruddin and Arshad, I., 2011. Development

Value Engineering Modeling in Construction Transportation Rahim

Page 36: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

158

Aminzadeha , 2 Amirruddin Ismailb , 3 Ishak Arshad PhD student / Department

of Civil and Structural Engineering , Faculty of Engineering and Department of

Civil and Structural Eng. Aust. J. Basic Appl. Sci. 5, 397–402.

Ankrah, N.A., 2007. AN INVESTIGATION INTO THE IMPACT OF CULTURE

ON CONSTRUCTION PROJECT. University of Wolverhampton.

Anthny, O.S., 2015. THE IMPACT OF CHANGE MANAGEMENT PRACTICES

ON CONSTRUCTION PROJECT PERFORMANCE.

Bangi, U.K.M., Ehsan, S.D., 2010. Value Engineering Application in Highway

Projects Amiruddin Ismail , Rahim Aminzadeh , Ali Aram and Ishak Arshad

Department of Civil and Structural Engineering , Faculty of Engineering and

Built Environment , 3, 699–703.

Barnes, M., 2014. THE MANAGEMENT AND ADAPTATION OF A LEGACY

TRANSIT SYSTEM FOR WEATHER EXTREMES IN THE PHILADELPHIA

METROPOLITAN REGION. J. Chem. Inf. Model.

doi:10.1017/CBO9781107415324.004

Begg, S., Vos, T., Barrke, B., Stevenson, C., Stanley, L., Lopez, A.D., 2007. The

burden of disease and injury in Australia.

Bench-Capon, T.J.M., 2015. Knowledge-based systems and legal applications.

Academic Press.

Bergmiller, G.G., 2006. Lean manufacturers transcendence to green manufacturing:

Correlating the diffusion of lean and green manufacturing systems. Diss. Abstr.

Int. Vol. 68, no. 01, suppl. B, 294 p. 2006. 294.

Bill de Blasio, M., Dr. Feniosky Peña-Mora, C., 2015. Design Consultant Guide.

Bim, M., Jones, S. a, 2009. Building Information Modeling. Civ. Eng. Vol.1, pp 225-

231. doi:10.1002/9780470432846

Booth, A.D., 2014. Digital Computers in Action: The Commonwealth and

International Library: Computing Science and Cybernetics Division. Elsevier.

Brown, J.D., 2011. Likert items and scales of measurement? SHIKEN JALT Test.

Eval. SIG Newsl. 15, 10–14.

Chen, W.T., Chang, P.-Y., Huang, Y.-H., 2010. Assessing the overall performance of

value engineering workshops for construction projects. Int. J. Proj. Manag. 28,

514–527.

Chi, S., Murphy, M., Zhang, Z., 2014. Sustainable Road Management in Texas :

Network-Level Flexible Pavement Structural Condition Analysis Using Data-

Page 37: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

159

Mining Techniques 156–165. doi:10.1061/(ASCE)CP.1943-5487.0000252.

Chin, W.W., Dibbern, J., 2010. An introduction to a permutation based procedure for

multi-group PLS analysis: Results of tests of differences on simulated data and

a cross cultural analysis of the sourcing of information system services between

Germany and the USA, in: Handbook of Partial Least Squares. Springer, pp.

171–193.

Chua, D.K.H., 2003. Value Improvement Methods.

Chudley, R., Greeno, R., 2013. Building construction handbook. Routledge.

Chung, B.Y., Syachrani, S., Kwak, Y.H., 2009. Applying Process Simulation

Technique to Value Engineering Model : A Case Study of Hospital. Trans. Eng.

56, 549–559.

Clough, R.H., Sears, G.A., Sears, S.K., Segner, R.O., Rounds, J.L., 2015.

Construction contracting: A practical guide to company management. John

Wiley & Sons.

Coffin, A.W., 2007. From roadkill to road ecology: a review of the ecological effects

of roads. J. Transp. Geogr. 15, 396–406.

Conference, I., 2014. RECENT ADVANCES in ECONOMICS , MANAGEMENT

and DEVELOPMENT RECENT ADVANCES in ECONOMICS ,

MANAGEMENT and DEVELOPMENT.

Cullen, J.M., 2014. Final Value Engineering Study Report.

Cunningham, G.B., 2011. The LGBT advantage: Examining the relationship among

sexual orientation diversity, diversity strategy, and performance. Sport Manag.

Rev. 14, 453–461.

Cunningham, T., 2013. Choosing an Appropriate Main Contract for Building Work

in the Republic of Ireland - an Overview, Dublin Institure of Technology 0–24.

Daniel P, F., 2006. Value Engineering Study Services In a Design Build World 1–10.

Davis, J.L., 2013. TMGT 458 – Project Management COURSE SYLLABUS : Spring

, 2013 Instructor : Jason Lee Davis , PhD – Associate Prof . & Sr . Grad .

Faculty Office Location : Charles Austin Engineering Building ( Ag / IT ), 213C

Office Hours : See Instructor Schedule on fac.

De Smith, M.J., 2015. STATSREF: Statistical Analysis Handbook-a web-based

statistics.".

Dell isola,, A, J., 1969. VALUE Engineering.

Discovery, E., Project, I.H., 2016. Request for Proposals 17011 Construction

Page 38: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

160

Manager Entrepreneurship , Discovery and Innovation Hub Project Saint Mary ’

s University Halifax , Nova Scotia Request for Proposals 17011 Construction

Manager Entrepreneurship , Discovery and Innovation Hub Proje.

Division, D.& C., 2014. PROJECT MANAGEMENT & DESIGN

ADMINISTRATION MANUAL Department of Transportation & Works

Prepared By Design & Construction Division January 2014 6th Edition Project

Management & Design Administration Manual - 6th Edition Table of Contents

Revised January 20.

Emeasoba, U., Ogbuefi, J., 2013. Sustainable socio-economic development in

Nigeria: a case for road infrastructure maintenance. J. Environ. Earth Sci. 3,

129–137.

Erdo\ugdu, M.M., Karaca, C., Kurultay, A., 2016. Economic Potentials of Energy-

Efficient Residential Building Envelope Retrofitting in Turkey, in: Handbook of

Research on Green Economic Development Initiatives and Strategies. IGI

Global, pp. 340–367.

Ewing, R., Dumbaugh, E., 2009. The built environment and traffic safety a review of

empirical evidence. J. Plan. Lit. 23, 347–367.

Federal High Way Administration (FHWA), 1996. StewardshipPlan(FHWA).pdf.

Field, C., Genton, M.G., 2006. The multivariate g-and-h distribution. Technometrics

48, 104–111.

Finnveden, G., Hauschild, M.Z., Ekvall, T., Guinée, J., Heijungs, R., Hellweg, S.,

Koehler, A., Pennington, D., Suh, S., 2009. Recent developments in Life Cycle

Assessment. J. Environ. Manage. 91, 1–21. doi:10.1016/j.jenvman.2009.06.018

Flooding rainfall in Tehran, 2011. No TitleFlooding rainfall in Tehran, 2011 Report

No. 267.

Fortune, J., White, D., Jugdev, K., Walker, D., 2011. Looking again at current

practice in project management. Int. J. Manag. Proj. Bus. 4, 553–572.

doi:10.1108/17538371111164010

Forture, J & White, D., 2006. No TitleFraming of project critical success factors by a

systems model. Int. J. Proj. Manag. 24 (1): 53.

Fountain, Roy E, Barlow, D.P., 1959. 424.pdf.

Fuller, S., 2010. LCC and Life-Cycle Cost Analysis (LCCA).

Galloway, P.D., 2007. The 21st-century engineer: A proposal for engineering

education reform. Civ. Eng. Mag. Arch. 77, 46–104.

Page 39: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

161

GAO, 2009. GAO Cost Estimating and Assessment Guide. GAO Cost Estim. Assess.

Guid. 440.

Garratt, A., 2009. Value Engineering PROGRAM. Manag. Decis. 1, 49–54.

doi:10.1108/eb000807

Giel, B.K., Issa, R.R.A., 2011. Return on investment analysis of using building

information modeling in construction. J. Comput. Civ. Eng. 27, 511–521.

Gómez, M., Macchione, F., Russo, B., 2011. Methodologies to study the surface

hydraulic behaviour of urban catchments during storm events. Water Sci.

Technol. 63, 2666–2673. doi:10.2166/wst.2011.174

Gorantiwar, S.D., Smout, I.K., 2005. Closure to “Allocation of Scarce Water

Resources Using Deficit Irrigation in Rotational Systems” by SD Gorantiwar

and IK Smout. J. Irrig. Drain. Eng. 131, 305–306.

Gordon, T., Castelli, W.P., Hjortland, M.C., Kannel, W.B., Dawber, T.R., 1977.

High density lipoprotein as a protective factor against coronary heart disease:

the Framingham Study. Am. J. Med. 62, 707–714.

Hair, J.F., Ringle, C.M., Sarstedt, M., 2011. PLS-SEM: Indeed a silver bullet. J.

Mark. theory Pract. 19, 139–152.

Hair, J.F., Sarstedt, M., Ringle, C.M., Mena, J.A., 2012. An assessment of the use of

partial least squares structural equation modeling in marketing research. J.

Acad. Mark. Sci. 40, 414–433.

Hair Jr, J.F., Hult, G.T.M., Ringle, C., Sarstedt, M., 2016. A primer on partial least

squares structural equation modeling (PLS-SEM). Sage Publications.

Harkey, D.L., Program, N.C.H.R., of State Highway, A.A., Officials, T., 2008.

Accident modification factors for traffic engineering and ITS improvements.

Transportation Research Board.

Harris, F., McCaffer, R., 2013. Modern Construction Management (Google eBook).

doi:10.1515/9783990434550

Hines, P., Rich, N., 2008. mapping tools.

Hischier, R., Editors, B.W., Althaus, H., Bauer, C., Doka, G., Dones, R.,

Frischknecht, R., Hellweg, S., Humbert, S., Jungbluth, N., Köllner, T.,

Loerincik, Y., Margni, M., Nemecek, T., 2009. Implementation of Life Cycle

Impact Assessment Methods.

Holweg, M., 2000. Value Analysis, Value Engineering 0–31.

Hulland, John, R.I.S., 1999. Use of partial least squares (PLS) in strategic

Page 40: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

162

management research: A review of four recent studies. Strateg. Manag. J. 20,

195–204.

Ibusuki, U., Kaminski, P.C., 2007. Product development process with focus on value

engineering and target-costing: A case study in an automotive company. Int. J.

Prod. Econ. 105, 459–474.

Ihs, A., Gustafsson, M., Eriksson, O., Wiklund, M., Sjögren, L., 2011. Road user

effect models: the influence of rut depth on traffic safety.

IHWTI, 2009, 2009. One of comments Viva; IHWTI (Institute High Ways

Transportation Iran, 2009.

Ismail, Amiruddin and Aminzadeh, Rahim and Aram, Ali and Arshad, I., 2010.

Value Engineering Application in Highway Projects Amiruddin Ismail , Rahim

Aminzadeh , Ali Aram and Ishak Arshad Department of Civil and Structural

Engineering , Faculty of Engineering and Built Environment , 3, 699–703.

Issa, M.H., Attalla, M., Rankin, J.H., Christian, A.J., 2013. Detailed Analysis of the

Construction , Operating , Maintenance , and Rehabilitation Costs of Green

Toronto Schools 1–11. doi:10.1061/(ASCE)AE.1943-5568.0000093.

Jungerius, P.D., Matundura, J., Van De Ancker, J.A.M., 2002. Road construction and

gully erosion in West Pokot, Kenya. Earth Surf. Process. Landforms 27, 1237–

1247.

Kajitvichyanukul, P., Ananpattarachai, J., Amuda, O.S., Alade, A.O., Hung, Y.,

Wang, L.K., 2006. Value Engineering and Value Management. Management.

Kampmann, M.W., 2009. Predicting IPTV usage: an SEM approach.

Kavosi, Z., Rashidian, A., Pourreza, A., Majdzadeh, R., Pourmalek, F., Hosseinpour,

A.R., Mohammad, K., Arab, M., 2012. Inequality in household catastrophic

health care expenditure in a low-income society of Iran. Health Policy Plan. 27,

613–623.

Kelly, J., Male, S., Graham, D., 2014. Value management of construction projects.

John Wiley & Sons.

Kelly, J.R., Male, S., 1991. The Practice of Value Management: Enhancing Value or

Cutting Cost? Royal Institution of Chartered Surveyors.

Kenley, R., 2010. Construction Cost Management: Learning from Case Studies,

Construction Management and Economics. doi:10.1080/01446190903552502

Kerzner, H.R., 2013. Project management: a systems approach to planning,

scheduling, and controlling. John Wiley & Sons.

Page 41: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

163

Kibert, C.J., 2016. Sustainable construction: green building design and delivery. John

Wiley & Sons.

Klein, K.J., Knight, A.P., 2005. Innovation implementation: Overcoming the

challenge. Curr. Dir. Psychol. Sci. 14, 243–246.

Ko, C.-H., Chung, N.-F., 2014. Lean design process. J. Constr. Eng. Manag. 140,

4014011.

Kobus, P.H., Plate, P.E., Hsieh, P., Shen, W., Szöllösi-nagy, A., 2013. Education of

Hydraulic Engineers Education of Hydraulic Engineers Formation des

ingenieurs hydraulic . iens 1686.

Kousky, C., Walsh, S., Zeckhauser, R., Kousky, C., Walsh, S., Zeckhauser, R., 2007.

Issues in Legal Scholarship Options Contracts for Contingent Takings Options

Contracts for Contingent Takings ∗ .

Kulak, G.L., Fisher, J.W., Struik, J.H.A., 1988. Guide to design criteria for bolted

and riveted joints, American Institute of Steel Construction, Inc.

doi:10.1139/l88-018

Kwak, Y.H., Anbari, F.T., 2012. History, practices, and future of earned value

management in government: Perspectives from NASA. Proj. Manag. J. 43, 77–

90.

Labit, B., Furno, I., Fasoli, A., Diallo, A., Müller, S.H., Plyushchev, G., Podestà, M.,

Poli, F.M., 2007. Universal statistical properties of drift-interchange turbulence

in TORPEX plasmas. Phys. Rev. Lett. 98, 255002.

Larson, L.L.C.N.-F.-54, 1993. Lower Kenai Peninsula Dolly Varden and steelhead

trout studies during 1992.

Laufer, A., 2009. Breaking the code of project management. Springer.

Lee, J.S., Miller, L.E., 2007. INCOSE - Systems Engineering Handbook. Syst. Eng.

304.

Lee, M.R., Ismail, S., Hussaini, M., 2013. Key Performance Indicator ( KPI ) of

Contractor on Project Performance for Housing Construction in Malaysia.

Li, X., 2008. Application of Value Methodology to Improve Preservation of

Infrastructural Assets in Rijkswaterstaat.

Limón, D.H., 2014. Comparative Analysis of Practices in Airspace and Construction

Industries.

Mahbub, V.J., 1994. International Road Maintenance Handbook Volume I,

Highways Maintenance.

Page 42: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

164

Mak, C.M., Leung, W.K., Jiang, G.S., 2010. Measurement and prediction of road

traffic noise at different building floor levels in Hong Kong. Build. Serv. Eng.

Res. Technol. 31, 131–139.

Mandelbaum, J., 2006. Value Engineering handbook 1–41.

Mandelbaum, J., Reed, D.L., Leader, P., 2006. Value Engineering Handbook.

Marsden, J.E., Ratiu, T., 2013. Introduction to mechanics and symmetry: a basic

exposition of classical mechanical systems. Springer Science & Business

Media.

Marszal, A.J., Heiselberg, P., 2011. Life cycle cost analysis of a multi-storey

residential net zero energy building in Denmark. Energy 36, 5600–5609.

Melorose, J., Perroy, R., Careas, S., 2015. Sustainable Development in Low-Income

Housing: A New Technology. Statew. Agric. L. Use Baseline 2015 1.

doi:10.1017/CBO9781107415324.004

Michel, J., Woodhead, R., 1997. Jean MICHEL Conseil.

Miles, L.D., 2015. Techniques of value analysis and engineering. Miles Value

Foundation.

Mirmoradi, S.H., Ehrlich, M., 2014. Numerical Evaluation of the Behavior of GRS

Walls with Segmental Block Facing under Working Stress Conditions. J.

Geotech. Geoenvironmental Eng. 8, 1–8. doi:10.1061/(ASCE)GT.1943-

5606.0001235.

Nadasdi, F., 2012. CAN VALUE METHODOLOGY ENHANCE THE

COMPETITIVENESS OF THE SUPPLY CHAIN ?

Nevada DOT, 2012. Risk management and risk-based cost estimation guidelines.

O’Farrell, P., 2010. Value Engineering-An Opportunity for Consulting Engineers to

Redefine Their Role 148.

Office of Deputy Assistant Secretary of Defense Systems Engineering, 2011. Value

Engineering : A Guidebook of Best Practices and Tools.

Opencourseware, M.I.T., 2009. MIT Project Management.

Order, C.T.O., Approval, M., 2014. MCHENRY COUNTY FINANCE & AUDIT.

Othman, A.A.E., 2008. Incorporating value and risk management concepts in

developing low cost housing projects. Emirates J. Eng. Res. 13, 45–52.

Owens, J.A., 2010. Project management for complex transportation projects.

PBO country, 2016. PBO Country Iran (Organization Program Budget in Iran) that

before was vice president.

Page 43: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

165

Pecht, M., 2009. Product reliability, maintainability, and supportability handbook.

CRC Press.

Perlovsky, L., 2002. Physical theory of information processing in the mind: Concepts

and emotions. Seed 2, 36–54.

Petroutsatou, K., Ph, D., Georgopoulos, E., 2012. Early Cost Estimating of Road

Tunnel Construction Using Neural Networks 679–687.

doi:10.1061/(ASCE)CO.1943-7862.0000479.

Pica, M.M., 2015. Project Life Cycle Economics: Cost Estimation, Management and

Effectiveness in Construction Projects. Ashgate Publishing, Ltd.

Podsakoff, P.M., Organ, D.W., 1986. Self-reports in organizational research:

Problems and prospects. J. Manage. 12, 531–544.

Ranjbaran, Y., Moselhi, O., 2014. 4D-Based Value Engineering, in: Construction

Research Congress 2014: Construction in a Global Network. pp. 1606–1615.

Rhem, K.T., Boyer, J., 2012. Loglines. September-October 2012 (techreport).

Robichaud, L.B., Anantatmula, V.S., 2011. Greening Project Management Practices

for Sustainable Construction. J. Manag. Eng. 48–57, 48–57.

Ross, A.M., Rhodes, D.H., 2008. Using Attribute Classes to Uncover Latent Value

during Conceptual Systems Design 1–8.

Rumane, A.R., 2010. Quality management in construction projects. CRC Press.

Salem, O., Solomon, J., Genaidy, A., Luegring, M., 2005. Site Implementation and

Assessment of Lean Construction Techniques. Lean Constr. J. 2, 1–21.

Sarstedt, M., Ringle, C.M., Smith, D., Reams, R., Hair, J.F., 2014. Partial least

squares structural equation modeling (PLS-SEM): A useful tool for family

business researchers. J. Fam. Bus. Strateg. 5, 105–115.

SAVE International, 2007. Value standard and the Body of Knowledge. SAVE Int.

Value Stand.

Scott, S., 2011. Guidelines for the use of pavement warranties on highway

construction projects. Transportation Research Board.

Scott, S., 2006. Best-value procurement methods for highway construction projects.

Transportation Research Board.

Soetanto, R., Proverbs, D.G., Soetanto, R., Proverbs, D.G., 2002. Engineering ,

Construction and Architectural Management Article information : To cite this

document : About Emerald www.emeraldinsight.com Modelling the satisfaction

of contractors : the impact of client performance.

Page 44: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

166

Stakgold, I., Holst, M.J., 2011. Green’s functions and boundary value problems. John

Wiley & Sons.

States, U., Forces, J., 2010. Handbook for Military Support to Governance ,

Elections , and Media Handbook Series Book Three.

Strictest, I., Confidence, C., One, P., Strictest, I., Confidence, C., 2016. Design Build

(DB). doi:10.1002/ejoc.201200111

Strozzi, F., Coppini, M., Rossignoli, C., Rossi, T., 2011. r P Fo r R w On ly.

Tajrishi Masoud, kamali M. and G.S., 2013. New ways of managing urban runoff

surface.

Teece, D.J., 2010. Business models, business strategy and innovation. Long Range

Plann. 43, 172–194.

Thom as Huw &Piccolo, L.F., 2000. i y Best Value , Planning and Race Equality

Vol. 15, N.

Thomson, D.S., 2013. Practitioner understanding of value in the UK building sector.

Eng. Constr. Archit. Manag. 20, 214–231. doi:10.1108/09699981311323970

Tobergte, D.R., Curtis, S., 2013. No title no title. J. Chem. Inf. Model. 53, 1689–

1699.

Tohidi, H., KhedriLiraviasl, K., 2012. Six sigma methodology and its relationship

with lean manufacturing system. Adv. Environ. Biol. 6, 895–906.

Tom, S., 2012. Persuasive business proposals: writing to win more customers,

clients, and contracts. AMACOM Div American Mgmt Assn.

Utley, R.E., 2016. Perspectives and problems. Routledge.

Utne, I.B., 2009. Life cycle cost (LCC) as a tool for improving sustainability in the

Norwegian fishing fleet. J. Clean. Prod. 17, 335–344.

Van Son, B.I.M., 2013. The Success of Systems Engineering in Public Private

Partnerships (phdthesis). TU Delft, Delft University of Technology.

Venkataraman, R.R., Pinto, J.K., 2008. Cost and Value Management in Projects,

Cost and Value Management in Projects. doi:10.1002/9780470261033

Vilasini, N., 2014. Generating value in alliance contracts through the lean concept.

Vujovic, A., Krivokapic, Z., Jovanovic, J., Lifvergren, S., Bergman, B., Dumitrascu,

A.-E., Nedelcu, A., Alves dos Santos, E., Zeydan, M., Toğa, G., Adeoti, J.O.,

Kostogryzov, A., Nistratov, G., Nistratov, A., Moracanin, V., Yang, C.-C.,

Chakraborty, A., Tan, K.C., Cartwright, G., Oakland, J., 2012. Total quality

management and six sigma. doi:http://dx.doi.org/10.5772/2559

Page 45: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

167

Walker, Derek HT and Walker, Derek HT and Rahamani, Farshid and Rahamani, F.,

2016. +VE Workshop Northern Water Plant-post-review-R2-final.

White, D., Fortune, J., 2002. Current practice in project management Ð an empirical

study 20.

Williams, M.L., 2012. Attachment 1 Notice to LEAs of Intent to Apply for Waivers

under Section 9401.

Xia, J.J., 2013. Research on the Key Technology of Road Machinery Intelligent

Compaction. Appl. Mech. Mater. 373–375, 142–145.

doi:10.4028/www.scientific.net/AMM.373-375.142

Xu, Y.G., Qian, C., 2014. Lean Cost Analysis Based on BIM Modeling for

Construction Project, in: Applied Mechanics and Materials. Trans Tech Publ,

pp. 1444–1447.

Yang, B., Fang, L., Li, J., 2013. Semi-automated extraction and delineation of 3D

roads of street scene from mobile laser scanning point clouds. ISPRS J.

Photogramm. Remote Sens. 79, 80–93.

Yap, C.L., 2016. Application of value management by IBS contractors in Malaysia

(phdthesis). UTAR.

Younker, D., 2003. Value engineering: analysis and methodology. CRC Press.

Yunker, D., 2003. Value Engineering Analysis and Methodology.

Zarandi, M.H.F., Razaee, Z.S., Karbasian, M., 2011a. Expert Systems with

Applications A fuzzy case based reasoning approach to value engineering.

Expert Syst. Appl. 38, 9334–9339. doi:10.1016/j.eswa.2011.01.124

Zarandi, M.H.F., Razaee, Z.S., Karbasian, M., 2011b. A fuzzy case based reasoning

approach to value engineering. Expert Syst. Appl. 38, 9334–9339.

Zhang, X., Chen, S., 2013. A systematic framework for infrastructure development

through public private partnerships. IATSS Res. 36, 88–97.

Zhang, X., Mao, X., AbouRizk, S.M., 2009. Developing a knowledge management

system for improved value engineering practices in the construction industry.

Autom. Constr. 18, 777–789.

Zhuang, J., Liang, Z., Lin, T., Guzman, F. De, 2007. Theory and Practice in the

Choice of Social Discount Rate for Cost-Benefit Analysis: A Survey 51.

Zimina, D., Ballard, G., Pasquire, C., 2012. Target value design: using collaboration

and a lean approach to reduce construction cost. Constr. Manag. Econ. 30, 383–

398.

Page 46: VALUE ENGINEERING FOR DRAINAGE AND STREAM WAY IN …

168

Zolin, R., Cheung, Y.K.F., Turner, J.R., 2012. Project Managers’s understanding of

Stakeholder’s satisfaction. Proj. Perspect. Annu. Publ. Int. Proj. Manag. Assoc.

XXXIV, 10–15.


Recommended