5/15/17 Final
Vanderbilt Drive Beautification MSTU FPL
Utility Burial Project
Vanderbilt Drive/Cul-de-sacs Public Utility Renewal Project
(Water/Wastewater/Stormwater)
12
3
4567
Project Area Water%
Sewer / FM / PS*%
Stormwater%
Restoration 1st Lift Asphalt
MSTU Energizing
FlamingoAve. 100 100 / 100 / 95 50 Mid-June to
Mid-July 2017 May 2017
June thru August 2018
HeronAve. 100 100 / 100 / 95 95 May to
Mid-June 2017 May 2017
EgretAve. 100 75 / 0 / 0 0 July to Mid-
August 2017 July 2017
ConnersAve. 100 Moved to Phase 5 September
2018 (water) Moved to Phase 5
Vanderbilt Dr. Phase 1 100 95 / 5 / NA 0 July to Mid-
August 2017 July 2017 June toAugust 2018
Vanderbilt Dr. Phase 3 May 2017 through April 2018 March to April
2018 March 2018 February to March 2019
Vanderbilt Dr. Phase 4 June 2017 through March 2018 March 2018 March 2018 September to
October 2018
Phase 5 May 2018 through September 2018 July to Sept 2018
July to Sept 2018
September to October 2018
Phase 6 April 2018 through January 2019 Oct 2018 to Jan 2019
Oct 2018 toJan 2019
February toMarch 2019
Phase 7 December 2018 through Feb 2019 Feb 2019 Feb 2019 April 2019
*FM = Force Main, PS = Pump Station
Conners Ave. moved to Phase 5
286 Heron Ave. staging moving to Conner Park
New Phase 1 – 7
Staging Area
152 Heron Ave. paver storage to
remain until September 2017
Flamingo Ave. & Heron Ave. 1st lift asphalt May 2017
Egret Ave. & Vanderbilt Dr. 1st lift
asphalt July 2017
Anticipated May 2017 – April 2018
Anticipated June 2017 – March 2018
Anticipated April – May 2018
Anticipated May – June 2018
Anticipated June – Aug 2018
Anticipated May – September 2018
Anticipated Sept. – Oct. 2018
Anticipated April 2018 – January 2019
Anticipated Feb. – March 2019
Anticipated Dec. 2018 – Feb. 2019
Anticipated April 2019
Stormwater Management
Stormwater Management
Stormwater Management
Stormwater Management
Stormwater Management
Project Area MSTU Energizing
Main Feeder (Vanderbilt Dr., Bluebill, & VBR)
April - May 2018
Bluebill Ave. May 2018
VBR & GulfShore Dr. June 2018
Flamingo Ave., Heron Ave., & Egret Ave.
June - August 2018
Conners Ave., Seabee Ave., Germain Ave., Seagull, & Willet
September -October 2018
Tradewinds Ave., Lagoon Ave., Bayside Ave., Pine Ave. & Oaks Ave.
February -March 2019
Palm Court, 9207 Vanderbilt Dr. & Chateau Vanderbilt
April 2019
www.CollierPUR.com
*FM = Force Main, PS = Pump Station