+ All Categories
Home > Documents > Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling...

Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling...

Date post: 23-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
23
1 Vauxhall Station 12 FEBRUARY 2018 James Pickard Old Street Roundabout
Transcript
Page 1: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

1

Vauxhall Station

12 FEBRUARY 2018

James Pickard

Old Street

Roundabout

Page 2: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

2

Background

• Old Street roundabout is a complex multiple lane

roundabout, linking the A5201 Old Street and the

A501 City Road.

• The roundabout is located within the London

Borough of Islington, however the area

immediately to the east falls within the London

Borough of Hackney.

• The Old Street area as a whole suffers from a lack

of open green space, as identified in the London

Borough of Islington’s Opportunity Area Planning

Framework.

Page 3: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

3

Background

• The proposed layout will contribute towards

significant economic opportunities and the

Gateway to ‘Tech City’ and supporting economic

growth in the area.

• The scheme will help deliver the Mayor’s Transport

Strategy commitment of providing Healthy Streets

by helping to encourage Londoners to walk, cycle

and use public transport.

• Our Principal Contractor, Morgan Sindall will carry

out the works with close supervision from TfL.

Page 4: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

4

Public Consultation

• We consulted on the scheme in early 2015.

• 87 per cent of respondents felt the proposed

changes would improve conditions for pedestrians

and cyclists.

• 63 per cent of respondents felt the scheme would

improve conditions for bus and tube passengers.

• There were a wide a range of written comments,

including a number of different suggestions for

what use we might make of a new peninsula space

that would be created.

Page 5: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

5

Transformation

Page 6: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

6

Proposed Scheme

• Remove the existing roundabout and close the

northwest arm to create a new public space.

• Switch road traffic movements to two-way operation.

• Improve facilities for cyclists travelling through the

junction with segregated cycle lanes and safe traffic

signal controlled crossings at surface level.

Page 7: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

7

Proposed Scheme

• Build a new main entrance and a new lift to Old Street

Station connecting to the retail concourse below, both

accessible from the new public space.

• Close three of the four existing station subway

entrances. The existing stepped entrance on the north-

west side of the junction will be retained and the

south-east subway will be modified to create a new

stepped access in Cowper Street.

• Install urban realm improvements in the new public

space. Plans to be finalised and agreed with the

Islington Council.

Page 8: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

8

Existing Junction

Page 9: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

9

New Main Station Entrance, Lift & Public

Space

Page 10: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

10

New Cowper Street Station Entrance

Page 11: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

11 What is happening and when

• Phase A – Enabling Works (Nov 2018 to Mar 2019)

o Trial holes and utility diversions at Cowper Street.

o Required to facilitate construction of new stepped

entrance.

o Working hours: Mon – Fri, 8am to 5pm.

• Phase B – Advanced Works (Mar 2019 to Apr 2019)

o Removal of traffic islands on all arms of the

roundabout and relocation of existing bus stops.

o Required to facilitate safe movement of traffic when

main works commence.

o Proposed Working hours: Mon to Sun, 8.30pm to

5.30am. Night works required to minimise traffic

impact during the day.

Page 12: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

12

Phase B – Advanced Works (Mar 2019 to Apr

2019)

TM Phase 4 – City road North island

removal TM Phase 3 – Old street West island removal

TM Phase 1 – Old street East island

removal TM Phase 2 – City road South island

removal

Page 13: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

13

What is happening and when

• Phase C – Main works (May 2019 to Nov 2019)

o Closure of the south eastern arm of the roundabout

to traffic. Two-way traffic flow

o Creation of dedicated cycle and pedestrian routes

through the works site

o Required to build the new station entrance at Cowper

Street and subway works

o Proposed Working hours: Mon – Sat, 7am to 7pm

o Some night time works between 8.30pm and 5.30am

due to LU operations

Page 14: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

14

Phase C – Main Works (May 2019 to Nov

2019) TM Phase 5 – Traffic Switch to two way

operation

Page 15: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

15

What is happening and when

• Phase D – Main works (Nov 2019 to Oct 2020)

o Closure of the north western arm of the roundabout

to traffic. Two way traffic flow

o Required to build the new main station entrance

o Required to build the new station lift

o Required to transform the roundabout into a new

public space

o Required to close Subways 1 and 3 permanently

o Proposed Working hours: Mon – Sat, 7am to 7pm

o Some night time works between 8.30pm and 5.30am

due to LU operations

Page 16: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

16

Phase D – Main Works (Nov 2019 to Oct

2020) TM Phase 7A – Traffic Switch to two way

operation (permanent)

TM Phase 7B – Subway 1 closed & filled

TM Phase 8 – Subway 3 closed & filled

Page 17: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

17

Programme

Milestone Date

Start Phase A Enabling Works Nov 2018

Start Detailed Design Jan 2019

Start Phase B Advanced Works (traffic island removals) Mar 2019

Start Phase C Main Works (new station entrance at Cowper Street) May 2019

Start Phase D Main Works (new main station entrance, lift, open space) Nov 2019

New Cowper Street entrance opened Feb 2020

Subway 1 closed Mar 2020

New main station entrance opened Jul 2020

Subway 3 closed Aug 2020

New lift operational Sep 2020

Construction completed Oct 2020

Page 18: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

18 During construction

• Our main priority is the health and safety of all road and

station users throughout the works.

• We will continue to maintain safe pedestrian access to

Old Street Station throughout the works.

• We will continue to provide safe cycle and pedestrian

provision throughout the works.

• We will minimise disruption keep traffic moving by

monitoring the road network via our 24/7 traffic control

centre, balancing queues protecting buses.

• We will keep noise and dust levels to a minimum.

Page 19: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

19 Local Impacts during construction

• Phase B – Night works and noisy works (Mar to Apr

2019)

• Traffic and pedestrian management:

o Changes to your usual walking and cycling routes

o Changes to your subway/station access routes

o Advance signage will be in place

• Bus stop relocations on Old Street:

o On the western arm of the roundabout the

eastbound bus stop is being relocated 30m towards

the west

o On the eastern arm of the roundabout the

westbound bus stop moving 65m towards the east

• Relocation of cycle hire station, capacity will be

maintained.

Page 20: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

20

Communications & Engagement

• We will keep the public and stakeholders up to date

throughout the project.

• We are working closely with the London Boroughs of

Islington and Hackney to make sure we inform as many

affected people as possible of the upcoming works.

• Our Communications teams will look at how we can

minimise disruption for the travelling public as well as

local residents and businesses.

• We will be helping customers to understand the

changes before, during and after construction and

helping them to plan their journeys in advance and by

knowing their travel options.

Page 21: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

21

Communications & Engagement

• A host of channels will be used to publicise the works

in advance of each stage.

• TfL website - tfl.gov.uk/travel-

information/improvements-and-projects/old-street-

roundabout

• Social media and press announcements

• Station and bus stop posters and leaflets

• Drop in sessions

• Customer emails - including our weekly information in

the weekly multi-modal email

• Metro and other press articles

• Regular letters drops to the local community – 2 wks in

advance

• Use of temporary and permanent VMS signage

• Attendance at Ward Partnership and Residents Forums

Page 22: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

22

Who to contact?

• PLO: David Kingston

([email protected] - 07811

200919) – Available on Tuesdays and Thursdays

(this will be enhanced as works progress). The

PLO will be based in a surface level office for

public to ask questions.

• TfL Contact Centre : 0343 222 1234

• TfL Local Communities and Partnerships team:

[email protected]

Page 23: Vauxhall Station Old Street Roundabout · 11 What is happening and when •Phase A –Enabling Works (Nov 2018 to Mar 2019) o Trial holes and utility diversions at Cowper Street.

23

Questions


Recommended