V.C. Summer Nuclear Station ITAAC Commissioner Briefing AD Torres 1
Transcript
Page 1: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

V.C. Summer Nuclear StationITAAC Commissioner Briefing

AD Torres

1

Page 2: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

• 10 CFR Part 52 – ITAAC provide reasonable assurance that the facility “has been constructed and will be operated in conformance with the License.”

• ITAAC originate from the COL, including those from the referenced DCD, and ESP (if applicable)

– There are approximately 900 ITAAC per unit for V.C. Summer 2&3

Requirements for ITAAC Performance

Page 3: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Requirements for ITAAC Performance

• The technical work for ITAAC completion is performed in accordance with normal work processes, requirements, and guidance:

– 10 CFR 50 Appendix B

– NRC Regulatory Guides

– ASME Code Section III

– ANSI, IEEE, AWS, ACI and other Industry Standards

– Licensee Programs and Procedures

Page 4: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

ITAAC Completion Process

ITAAC established in COL

Fuel Load & Operation

Construction/InspectionLicensing Operation

ITAAC Hearing

Opportunity

Combined License (COL) Issued Section

52.103(g) Finding that all ITAAC are met

180 days prior toScheduled Fuel Load

ITAAC Maintenance

ITAAC Closure

Page 5: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Types of Standard Plant ITAAC

5

Engineering 220

As-Built Analysis 31

ASME 70

EQ Reconciliation 40

Engineering Analysis 34

Equipment Qual. 45

Construction 187

Construction Inspection 67

Electrical Separation 24

System Turnover Inspection 96

Initial Test Program 274

Preoperational Testing 136

Component Testing 138

Licensing 81

Reference 81

Multiple 44

Vendor 44

Security 17

Security 17

*Classified by the group producing the final documentation utilized to close the ITAAC

Page 6: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Milestones with ITAAC

• Placement of Ring 1 on Unit 2• ITAAC 2.2.01.01 - Functional Arrangement CNS• ITAAC 2.2.01.02a - ASME III Components• ITAAC 2.2.01.03a - Pressure Boundary Weld NDE ASME III• ITAAC 2.2.01.05.i - Seismic Cat 1 Equipment on Nuclear Island

• Placement of CA-20 on NI-2• ITAAC 3.3.00.01 - Physical Arrangement of Structures• ITAAC 2.3.07.07b.i - Spent Fuel Pool Volume• ITAAC 2.3.07.07b.ii - Cask Washdown Pit Volume• ITAAC 3.3.00.02a.ii.d - As-Built Concrete Wall Thicknesses

Page 7: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Milestones with ITAAC• Placement of the Unit 3 CVBH

• ITAAC 2.2.01.01 - Functional Arrangement CNS• ITAAC 2.2.01.02a - ASME III Components• ITAAC 2.2.01.05.i - Seismic Cat 1 Equipment on Nuclear Island• ITAAC 3.3.00.02a.ii.b - As-Built Concrete Thickness of Shield Building

• Exterior wall placements begin in Unit 3• ITAAC 3.3.00.02a.ii.c - As-Built Concrete Wall Thicknesses (Non-Rad)• ITAAC 3.3.00.02a.ii.d - As-Built Concrete Wall Thicknesses (Rad)• ITAAC 3.3.00.03c - Shield Wall and Floor Thickness (Non-Rad)• ITAAC 3.3.00.03d - Shield Wall and Floor Thickness (Rad)

• Turbine Building Foundation Start Unit 3• ITAAC 3.3.00.01 - Physical Arrangement of Structures

Page 8: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Lessons Learned

• Clarification of ITAAC requirements to Vendors

• Importance of common understanding of documentation requirements

• Validation in Vendor shops

• Completeness of critical information

• Closure package preparation

• Periodic assessment on process

8

Page 9: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Lessons Learned

• NEI 08-01, Rev. 5, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, endorsed by NRC Regulatory Guide 1.215

• ITAAC Integrated Project Teams

• Monthly and quarterly NRC inspection planning meetings

• Alignment with Vogtle

9

Page 10: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

VCS Units 2 & 3 – approx. 18 months agoNND Site Aerial View (From Plant Southeast)

Turbine Building

Nuclear IslandCooling Towers

HLD

MAB

Ring 2

Unit 2

Unit 3Nuclear Island

2A

2B

3B

3A

Page 11: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

CA20 Transport 11

Page 12: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Module CA01 (Unit # 2)

Page 13: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Placement of the Containment

Vessel Bottom Head

Placement of Containment Vessel

Ring 1

Placement of Module CA-20

Unit 2 Nuclear Island

Page 14: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Unit 2 Nuclear Island – Layer 2 Concrete in Containment

Page 15: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Unit 2 CA05 Set

Page 16: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Steam Generator Lift

Page 17: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Mangiarotti Manufacturing

Unit 3 Pressurizer Prep for Ship

Page 18: V.C. Summer Nuclear Station ITAAC Commissioner … · AD Torres 1 •10 CFR Part 52 –ITAAC provide reasonable assurance that the facility “has been constructed ... Ring 1 Placement

Questions

18