+ All Categories
Home > Documents > VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required...

VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required...

Date post: 11-Oct-2018
Category:
Upload: dotram
View: 216 times
Download: 0 times
Share this document with a friend
52
t L 0 ;•; VELSICOL CHEMICAL CORPORATION PERMEABILITY DURABILITY TESTING of Soil/Bentonite Backfill Mix St. Louie, Michigan January, 1983 Ref. No. 0803 CONESTOGA-ROVERS ft ASSOCIATES LIMITED
Transcript
Page 1: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

t L 0 ;•;

VELSICOL CHEMICAL CORPORATION

PERMEABILITYDURABILITY TESTINGofSoil/Bentonite Backfill MixSt. Louie, Michigan

January, 1983Ref. No. 0803 CONESTOGA-ROVERS ft ASSOCIATES LIMITED

Page 2: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

TABLE OF CONTENTS

Paqe

1 .0 INTRODUCTION 1

1.1 CONTAINMENT WALL CONSTRUCTION 11.2 TESTING PROTOCOL 2

1.3 TESTING LABORATORY 3

2.0 SAMPLE COLLECTION 5

2.1 SOIL 52.2 GROUNDWATER 8

3.0 LABORATORY ANALYSIS 10

4.0 CONCLUSION 12

APPENDIX A SECTIONS 6, 7 AND 8 AND FIGURES 2A & 2BTECHNICAL APPENDIX - CONSENT JUDGMENT

APPENDIX B MATERIALS TESTING REPORT

Page 3: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

LIST OF TABLES

TABLE 1 SUMMARY OF SOIL/BENTONITE BACKFILLTESTING 9a

LIST OF FIGURES

FIGURE 1 PLANT SITE CONTAINMENT WALL la

FIGURE 2 SOIL SAMPLING LOCATIONS - PLANT SITE 6a

FIGURE 3 SOIL SAMPLING LOCATIONSPROJECT BORROW PIT 7a

Page 4: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

1.0 INTRODUCTION

1.1 CONTAINMENT WALL CONSTRUCTION

Under the provisions of the

Technical Appendix to the Consent Judgement for the

environmental securement of its St. Louis, Michigan

plant site, Velsicol Chemical Corporation (Velsicol) is

required to construct a continuous soil/bentonite

containment wall, having a permeability equal to or

less than 1 x 10~7 cm/sec, along the entire

perimeter of the plant site property.

The containment wall has been

subdivided into an upgradient and downgradient section.

Figure 1 presents the proposed alignment of both the

upgradient and downgradient containment walls.

As stipulated by the Technical

Appendix within Section 6, Figures 2A and 2B, and

Exhibit D entitled "Containment Wall Specifications",

the containment wall must be constructed through a

level clay working platform and must be a minimum of 21

inches (nominal 24 inches) wide and keyed into the

underlying clay till a minimum of 30 inches (nominal

Page 5: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

UPGRAOIENTCONTAINMENT WALL

DOWNGRAOtENTCONTAINMENT WALL

figurePLANT SITE CONTAINMENT WALL

S/. Louis Plant Site

0«G3-22/l2/«

Page 6: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

36 inches). Figures 2A and 2B, and Exhibit D are

presented in Appendix A of this report.

Backfill material for the

containment wall must be a soil/bentonite mix having as

a minimum 25% plastic fines (minimum of 25% of soil

particles passing a Standard U.S. #200 sieve). The

backfill mix must maintain a permeability of not

greater than 1 x 10~7 cm/sec when exposed to the

plant site groundwater.

1.2 TESTING PROTOCOL

Section 8 of the Technical

Appendix outlines the testing procedures to be utilized

to determine the adequacy of the containment wall

backfill material with respect to durability and

permeability subsequent to installation of the

containment walls. These tests are to be performed on

soil samples obtained from continuous cores collected

from specified points along the line of the containment

wall.

Page 7: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

In addition, soil samplescollected from the project borrow pit by continuous

core sampling are to be tested for durability and

permeability in a similar fashion. Material from the

project borrow pit will be used as backfill to the

containment wall in sections where native material is

judged unsuitable for such a purpose.

Using the collected samples an

optimum soil/bentonite mixing ratio is to be determined

such that the designed backfill mix will have a

permeability less than or equal to 1 x 10~7 cm/sec.

The ability of the soil/bentonite backfill mix tomaintain the specified permeability will then be tested

with the use of plant site groundwater to determine if

the groundwater will have any adverse effect on the

backfill mix permeability.

1.3 TESTING LABORATORY

Conestoga-Rovers & Associates

Limited (CRA) retained the services of Michigan Testing

Engineers Inc. (MTE) for all physical laboratory

testing.

Page 8: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

This report presents the

laboratory results of the permeability and durability

tests performed on soil/bentonite mixtures using soil

samples obtained from the line of the proposed

upgradient containment wall and the project borrow pit

and using groundwater obtained from Plant Site

monitoring wells.

Page 9: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

2.0 SAMPLE COLLECTION

2.1 SOIL

Between May 20 and May 26, 1982

CRA conducted a sampling program along the line of the

proposed upgradient containment wall to determine the

depth to the underlying clay till and to determine the

integrity of the upper 3 feet of till (absense of sand

lenses having a thickness of 4 inches or greater) and

I to collect soil samples for physical and chemical

analysis. Details of the sampling program and results

J are presented in the report entitled "Sampling Program

- Upgradient Containment Wall - Plant Site, St. Louis,11 Michigan". This report was presented to the Michigan

1 Department of Natural Resources (MDNR) and the United

States Environmental Protection Agency (USEPA) in July,

j 1982.

As part of this sampling program

soil samples from sampling stations UGW-4, UGW-9,

UGW-15 and UGW-21 were collected by continuous split

1 spoon sampling for permeability and durability tests

for the design soil/bentonite backfill mix. The entire

I continuous core sample from UGW-4 and UGW-21 was

retained for use in the permeability test. The

I continuous core sample from UGW-9 and UGW-15 was split

i

Page 10: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

in the field. One half of each sample was retained for

use in the permeability testing and the other half was

retained for use in the durability testing. Figure 2

indicates the sampling locations along the line of the

upgradient containment wall.

Chemical analysis of the soil

samples collected along the upgradient wall were

performed as specified in Section 7 of the Technical

Appendix. Results of the soil sample chemical analysis

was presented to the MDNR and the USEPA in December,

1982, in the form of a report entitled "Upgradient

Containment Wall - Chemical Analysis of Soil Samples -

St. Louis, Michigan".

Between August 4 and August 12,

1982 CRA supervised a sampling program along the line

of the downgradient containment wall. Soil samples

were not collected for permeability and durability

testing during this sampling program since a field

inspection along the proposed alignment indicated that

native soils were unsuitable for incorporation into the

containment wall backfill. This necessitated the

Page 11: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

SAMPLE FOR CHEMICALANALYSIS ONLY

HOLE FOR TtLLELEVAT|ON DETERMINATION

GROUNDWATERCOLLECTION WELL

UPGRADIENTCONTAINMENT WALL

DOWNGRADIENTCONTAINMENT WALL

CONTINUOUS CORESAMPLE (DURABILITY6. PERMEABILITYTESTING )

CONTINUOUS CORESAMPLE( PERMEABILITY TESTING

ONLY )

CRA

figure 2SOIL SAMPLING LOCATIONS

PLANT SITE0103-22/12/82

Page 12: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

* importation of backfill material from the project

I borrow pit for the downgradient wall. The depth to the

underlying clay till was identified during this

I sampling program. Details of the downgradient wall

sampling program are presented in the report entitled

I "Sampling Program - Downgradient Containment Wall -

. Plant Site, St. Louis, Michigan", presented to the MNDR

* and USEPA in September, 1982.

iIn addition to sampling at the

*) ""^ plant site, four continuous core samples were collected

at the project borrow pit during the May, 1982 sampling

I program. Permeability and durability testing for the

. design soil/bentonite backfill mix was performed on

this material to determine compliance with

1 specifications. The entire continuous core sample was

retained from sampling stations BHS-1 and BHS-4 for use

J in the permeability test. The continuous core sample

. from sampling stations BHS-2 and BHS-3 was split in the

» field longitudinally. One half of the sample was

1 retained for the permeability test and the other half

was retained for the durability test. Figure 3

I presents the sampling locations at the project borrow

pit.

Page 13: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

too' zoo'

BORROW AREA FORIMPORTED BACKFILLFOR UPGRADIENT £DOWNGRADIENTCONTAINMENT WALL

AD

CONTINUOUS CORE SAMPLE(PERMEABILITY B DURABILITY TESTING

CONTINUOUS CORE SAMPLE(PERMEABILITY TESTING ONLY)

CRA

figure 3SOIL SAMPLE LOCATIONS

PROJECT BORROW PIT

OS03-22/I2/S2

Page 14: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

All collected soil samples were

delivered to the MTE testing laboratory in Detroit,

Michigan by commercial courier under Chain of Custody

protocol.

2.2 GROUNDWATER

Section 8 of the Technical

Appendix specifies that plant site groundwater must be

used during durability testing of the soil/bentonite

backfill mix.

Groundwater for durability testing

was obtained from two on-site wells developed during

the upgradient wall sampling program of May, 1982.

Figure 2 indicates the location of the two on-site

wells.

Samples were composited on a

50%-50% basis from each well into a 5 gallon glass jars

prior to shipping to the testing laboratory. The glass

jars were cleaned with an acetone-hexane-acetone-

distilled water wash and were air dried prior to sample

collection.

Page 15: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

Samples were composited on a

50%-50% basis from each well into 5 gallon glass jars

prior to shipping to the testing laboratory. The glass

jars used for sampling collection were cleaned with an

acetone, hexane, acetone, distilled water wash adn were

air dried prior to sample collection.

A total of 20 gallons of

groundwater was shipped to the laboratory for use in

the durability testing of the backfill mix. Shipment

was by commercial courier under Chain of Custody

protocol.

Page 16: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

TABLE 1

SUMMARY OF SOIL/BENTONITE BACKFILLTESTING

SamplingLocation

BHS-1

BHS-2

BHS-3

BHS-4

UGW-4

UGW-9

UGW-15

UGW-21

% Plastic% Moisture Fines

14.1

12.2

12.4

13.5

9.9

10.2

11.1

10.6

44

52

56

45

24

42

44

59

Backfill MixPermeability(cm/sec)

18 Days(Hydration)

7.6 x 10-8

9.9 x 10"8 1 . 1 x 10"7

7.9 x 10-8 9.0 x 10-3

7.7 x 10-8

8.0 x 10"8

9.2 x 10"8 2.1 x 10~7

8.9 x 10~8 1.05 x 10"7

8.0 x 10-8

Durability (cm/sec)

18 Days 90 Days 90 Days(No Hydration) (Hydration) (No Hydration)

_

1.1 x 10"7 7-0 x ID"8 6-7 x 10"8

9.0 x 10"8 7.0 x ID"8 7.0 x 10~8

_

_

8.8 x 10"8 7.0 x ID"8 7.4 x 10"8

1.1 x 10~7 7.6 x TO"8 6.0 x 10~8

_ — —

Note: 1) Plastic Fines - particle sizes passing a Standard U.S. |200 sieve

Page 17: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

3.0 LABORATORY ANALYSIS

The natural moisture content of

each soil sample received from the line of the upgradient

containment wall and from the project borrow was initially

identified to determine the required bentonite concentration

necessary to provide a backfill mix with a permeability of

1 x 10"? cm/sec. The moisture content for each sample

is presented in Table 1.

From this data Slurry Gel 1125

supplied by International Minerals and Chemical Corporation

was added to the appropriate soil samples at a concentration

of 3% by dry unit weight. Representative samples from each

soil/bentonite mix were selected for grain size analysis.

The percent plastic fines for each sample is presented in

Table 1.

The soil/bentonite backfill mix of

3% slurry Gel #125, and native material was tested to

determine permeability using the falling head permeability

testing procedure as specified in ASTM D-2434. This testing

procedure was in lieu of the triaxial permeability testing

procedure specified in Section 8 of the Technical Appendix.

10

Page 18: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

The consistency of the soil/bentonite mix was such that a

suitable sample could not be formed to use in the triaxial

test. Results of the permeability tests are presented in

Table 1.

Durability testing was carried out

on the soil/bentonite backfill mix using ASTM D-2434

procedures for falling head permeability testing.

Initially, soil samples from BHS-2, BHS-3, UGW-9 and UGW-15

^" were prehydrated in clean water for 18 days with the

permeability of each sample being monitored daily. At the

completion of the prehydration period the clean water was

drained from samples and replaced with groundwater from the

plant site. The permeability of the soil/bentonite samples

were monitored for an additional 72 days.

In addition to the prehydrated

samples four duplicate samples were prepared which were

exposed to the plant site groundwater without any

prehydration period. Permeability of these samples were

1 monitored for 90 days. The results of the durability

testing are also presented in Table 1.iThe soil laboratory testing report

1I is presented in its entirety within Appendix B.

1 1

Page 19: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

I 4.0 CONCLUSION

It is concluded that:

A) A blend of three percent bentonite (IMC Slurry Gel 125)

by dry weight with native material obtained either from

the line of the upgradient containment wall, or from the

» Project borrow pit, will produce a containment

wall backfill matrix having an initial permeability no

^ greater than 1 x 10~7 cm/sec.

IB) The bentonite/soil matrix as described in A) abovei

I exhibited a general decrease in permeability over time

• when Plant Site groundwater was used as the permeate.

This is true for both no hydration and prehydration of

1 the design soil/bentonite matrix prior to the addition

of the Plant Site groundwater permeate.is""" C} The soil/bentonite containment wall design mix will meet

I the specifications of the Technical Appendix to the

| Consent Judgment for the environmental securement of the

Velsicol Chemical Corporation Plant Site in St. Louis,

I Michigan.

ii

12

i

Page 20: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

All of Which is Respectfully Submitted,

CONESTOGA-ROVERS & ASSOCIATES LIMITED

Richard G. Shepherd, P. Eng.

Frank A. Rovers, P. Eng

13

Page 21: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

APPENDIX A

SECTIONS 6, 7, AND 8

AND

FIGURES 2A & 2B

TECHNICAL APPENDIX

CONSENT JUDGMENT

Page 22: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

CONTAINMENT WALLS

Velsicol shall submit, for review and subject to approval byEPA and Michigan, plans, specifications and methods andtechniques of emplacement for continuous containment wallsalong the entire boundary of the main Plant Site to controlthe infiltration of groundwater through, and abate thefurther migration of contaminants from, the main Plant Site.The containment walls shall be constructed within Velsicolproperty lines of the main Plant Site, as shown in attachedFigures 1 and 2. Upon approval Velsicol shall construct andinstall said containment walls in accordance with such plans,specifications and methods and techniques of emplacement.Such plans and specifications shall include but not belimited to the provisions detailed in Exhibit D, ContainmentWall Specifications. The containment walls shall beconstructed to a minimum thickness of twenty-one (21) inches(nominal 24 inches) of suitable bentonite soil mixture, orequivalent, achieving a permeability of 1 x 10~7 cm/sec,or less, and shall be keyed a minimum of thirty (30) inches(nominal 36 inches) into the underlying till layer. If sandlenses having a minimum thickness of 4 inches are found alongthe containment wall route, the wall shall be keyed to aminimum of thirty (30) inches (nominal 36 inches) into theunderlying till layer beneath such sand lenses. Soilsexcavated along the containment wall route shall be visuallyexamined by the supervising Engineer in consultation withrepresentatives of EPA or Michigan and, if determined to beunsuitable for slurry wall construction, shall be removed fordisposal upon the plant site within the containment walls.

The plans and specifications which Velsicol is required todevelop pursuant to Paragraph 6, above, shall includeprovisions for pre-construction borings and core samplings(or backhoe excavation and sampling), chemical testing alongthe line of the upgradient wall, and construction qualitycontrol and field testing methods. Such activities shall bedesigned to locate sand lenses, to locate contaminated soilson the line of the upgradient wall, and to assure properdesign and construction of the containment walls. Chemicaltesting of soil for HBB, PBB, total DOT and Tris shall beconducted along the line of the upgradient wall at onehundred and fifty (150) foot intervals at depths below one(1) foot, using the protocols defined in Exhibit C,Analytical Protocols for HBB, DOT, PBB and Tris. The top ofthe till and consistency of the till to a depth of thirty-six(36) inches shall be defined by bore hole testing with visualdefinition and logging of the spoon sampling (or backhoeexcavation with visual definition and logging of the openexcavation) at 150 foot centers along the line of containmentwall construction.

Page 23: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

Velsicol shall excavate that soil lying between thecontainment wall and adjacent roadways owned by the City ofSt. Louis (Watson Street, Center Avenue, Washington Avenueand North Avenue) to a one (1) foot depth and shall disposeof such soils upon the plant site within the containmentwalls. Soil below such one (1) foot depth lying between thecontainment wall and adjacent roadways owned by the City ofSt. Louis, shown on Figure E-1 to Exhibit E, Storm SewerSystem, which is assumed to contain significant levels ofchemical contamination (as determined by EPA, Michigan andVelsicol following chemical testing along the line of theupgradient containment wall), shall be excavated and disposedof by Velsicol upon the plant site within the containmentwalls. The maximum depth of excavation shall be to the topof the water table.

In the area where private property abutts the main PlantSite, Velsicol shall, if granted permission by the owner ofsuch property, excavate that soil lying within the drainagearea of the storm sewer on the private property on WatsonStreet, and that soil lying within the limit of fifty (50)feet outside the Plant Site on the private property adjacentto the northeast corner of the main Plant Site, as shown onFigure E-2, Exhibit E, Storm Sewer System, to a depth of one(1) foot and shall dispose of such soil upon the plant sitewithin the containment walls. Soil below such one (1) footdepth lying between the containment wall and both the limitof drainage of the storm sewer and the limit of fifty (50)feet outside the main Plant Site, as shown on Figure E-2 toExhibit E, Storm Sewer System, which is assumed to containsignificant levels of chemical contamination (as described byEPA, Michigan and Velsicol following chemical testing alongthe line of the upgradient containment wall) shall beexcavated by Velsicol, if it is granted permission by theOwner of such property, and disposed of by Velsicol, withinthe containment walls. The maximum depth of excavation shallbe to the top of the water table.

All such excavated areas shall be backfilled with importedfill, and where appropriate, with topsoil, and shall beseeded or sodded.

8. The following testing procedures shall be utilized todetermine the adequacy of the containment wall material withrespect to durability and permeability both during andsubsequent to installation, and to ensure that proper mixtureratios, blending and injection rates are maintained duringcontainment wall installation:

a) Durability Testing

The testing procedure to deterimine the durability of thecontainment wall material to maintain a permeability of

Page 24: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

1 x 10"^ cm/sec, or less, as well as predict theexpected in situ life of the containment wall shall be asfollows:

1) Prepare four permeameter specimens: two by mixing theselected grade of bentonite at the design mix ratiowith native material obtained from borings takenalong the line of the containment wall, and two bymixing the selected grade of bentonite with theimported fill.

2) Prepare permeameter specimens of 1) by dehydratingwith water for 13 days.

3} Prepare duplicate permeameter specimen of 1) withoutprehydration with water as per 2).

4) Under the falling head permeability test, set up inaccorance with ASTM D 2434, add groundwater from themain Plant Site to the permeameter specimens of 1),2), and 3) and monitor the permeability for 90 days.Analysis of the data shall be carried out as outlinedin the reference text "Laboratory Soils Testing",Department of Army Engineering ManualEM-1110-2-1906.

5) Native material from the route of the containmentwall, where native material is to be used incontainment wall construction, shall be obtained fromtwo bore hole locations jointly agreed to by Velsicoland EPA/Michigan. Imported fill material from theimported fill site location for use in containmentwall construction shall be obtained from two borehole locations jointly agreed to by Velsicol andEPA/Michigan. At each location at the main PlantSite, continuous split spoon samples shall be takenfrom the surface to a point three feet below the topof the clay till. At each location at the importedfill site continuous split spoon samples shall betaken through the depth of the soil deposit to beused. The material contained with each continuoussample shall be thoroughly blended prior to theaddition of bentonite.

6) Plant site groundwater shall be collected fromexisting on-site wells. The groundwater to be usedin this testing procedure shall be approved byEPA/Michigan prior to initiation of the test.

b. Permeability Testing

The testing procedure to determine the permeability ofthe design mix for the containment wall backfill shall beas follows:

Page 25: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

1) From four locations agreed to by Velsicol andEPA/Michigan, along the route of the containment wallcontinuous samples of native material shall beobtained. In addition, imported fill samples shallbe obtained from four locations at the imported fillsite. The soil samples shall be continuous from theground surface to a point three (3) feet below thetop of the clay till at the main Plant Site, and fromthe surface through the depth of the soil deposit tobe used at the imported fill site.

2) Each continuous sample shall be thoroughly blendedprior to addition of bentonite. A grain sizeanalysis shall be performed on each blended sample inaccordance with ASTM D 422-63 as reapproved in 1972.

3) Bentonite shall be blended with each sample at thespecified design ratio.

4) One triaxial consolidation test, set up in accordancewith ASTM D 2580 with samples saturated, shall beperformed on a portion of each sample to determinepermeability. Calculations of test results shall becarried out as outlined in the reference text"Laboratory Soils Testing", Department of ArmyEngineering Manual EM-1110-2-1906.

c. Construction Testing

1) From each 500 lineal feet of installed containmentwall, a triaxial consolidation test to determinepermeability, set up in accordance with ASTM D 2850with samples saturated, shall be performed. Wellcorings for testing purposes shall be collectedwithin seven to ten days of backfill placement.Calculations of test results shall be as specified insubparagraph 8.b.4, above.

2) Slump cone tests, carried out in accordance withAP1-RP-13B, shall be performed during construction atthe rate of one test for each twenty-five (25) cubicyards of backfill mix.

3) Gradation tests for determination of plastic finescontents (passing the 1200 sieve) shall be performedat the rate of four (4) tests per eight (8) hourshift.

4) A Methylene Blue Test, carried out in accordance withAPI-RP-13B, shall be performed four (4) times eacheight (8) hour shift on backfill mixture samplesselected at the same time as the gradation test.

Page 26: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

5) Slurry samples which shall be pumped from the bottomof the trench, and backfill samples from mix beingadded to the trench, shall be tested for unit weight,in accordance with API-RP-13B, at least once eachhour of the working shift.

d. Post Construction Testing

Following installation, falling head laboratory testing,set up in accordance with ASTM D 2434, on a singlecollected sample of the installed containment wall shallbe done every three (3) months for thirty-six (36) monthsto evaluate maintenance of a permeability of1 x 10"? cm/sec., or less. Analysis of the datashall be carried out as specified in subparagraph 8.a.4,above.

Page 27: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

.SECURITY FENCE ONVELSICOL EASTERLY PROPERTY LINE

•PRIVATE PROPERTY-

10'

- t

-CLAY SEAL

-VELSICOL PROPERTY-13' _J

6 MIN. 6 MIN.

CLAY WORKING PLATFORM (PERM.t| x IO'7cm/sec..—'i

18" to 21 "0STORM SEWER

ALLUVIAL DEPOSITSOR FILL

12 MIN.

MATERIAL OF PERMEABILITY —.':o.EQUAL TO Ixl0-7cm/sec. OR LESS'

12 MIN.

GRANULAR FILTERBEDDING & BACKFILL

24"NOMINAL

-TRENCH LINE FORCONTAINMENT WALL

CRA

figure 2AUPGRADIENT CONTAINMENT WALLS STORM SEWER CROSS SECTION

St. Louis Plant SiteI07B-OI/OT/82

Page 28: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

CLAY WORKING PLATFORM (PERM. Ix 10" cm/see.)

TRENCH LINE FORCONTAINMENT WALL

MATERIAL OF PERMEABILITYEQUAL TO lxIO-7cm^ec.OR LESS

ALLUVIAL DEPOSITSOR FILL

CRA

figure 28DOWNGRADIENT CONTAINMENT WALL

Louis Plant She

9-0*4«-08/08/82

Page 29: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

APPENDIX B

LABORATORY STUDY

MICHIGAN TESTING ENGINEERS

Page 30: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEERS, INC24355 CAPITOL AVENUE • DETROIT, MICHIGAN 48239

PHONE: (313) 255-4200

SOILS EXPLORATIONS AND FOUNDATION ENGINEERINGMATERIALS TESTING AND INSPECTION

NON-DESTRUCTIVE TESTING and MATERIALS EVALUATION

November 9, 1982

Conestoga-Rovers § Associates Limited651 Colby DriveWaterloo, Ontario, Canada N2V IC2

Attn: Mr. Rick Shepard

Subject: Bentonite StudyVelicol Chemical CorporationSt. Louis, Michigan

Gentlemen:

As requested, we have completed a study on the bentonite materialsproposed for use during the containment wall construction on the aboveproject.

The results of our study are to be found in the accompanying report,three copies of which are being transmitted herewith.

If there are any questions, please do not hesitate to call.

Very truly yours,

MICHIGAN TESTING ENGINEERS, INC.

Randall K. DeRuiterBranch Manager

James H. Standen, P.E,Division Manager

RKD/dgd

Page 31: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEER*. INC.

BENTONITE STUDY

PROPOSED CONTAINICm' WALL CONSTRUCTION

VELICOL CHEMICAL CORPORATION

ST. LOUIS, MICHIGAN

CONESTOGA-ROVERS S ASSOCIATES LIMITED

651 COLBY DRIVE

WATERLOO, ONTARIO, CANADA N2V IC2

NOVEMBER 9, 1982

BY

MICHIGAN TESTING ENGINEERS, INC.

Page 32: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING CNGINCKRC. INC.

TABLE OF CONTENTS

SYNOPSIS

Page

•- I

INTRODUCTIONAuthorization ———— ———————————————— —— 2General—- — — ..._..-._.._. — __-.._._._....._ 2

GENERAL DISCUSSIONMaterials------ — -- — .-- — -----.-.-. — --....--_ 4Preparation of Test Specimens-------------------- 4Permeability Determinations---------------------- 5Durability Determinations------------------------ 6

APPENDIXReport of Soil Analysis - Figures I thru Figure 8Permeability Graphs - Figure 9 thru Figure 16

Page 33: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEERS. INC.

SYNOPSIS

An evaluation of the proposed bentonite-soil mixture to be utilized

for construction of the containment wall at the Velicol Chemical Company

in St. Louis, Michigan has been conducted. This testing was conducted by

Michigan Testing Engineers with the cooperation of International Minerals

and Chemical Corporation.

Soil test borings have been drilled and the soil samples subjected to

laboratory tests. The data has been carefully analyzed and the following

conclusions made.

1) Addition of 3% Slurry Gel #125, produced by International

Minerals and Chemical Corporation, to both the native material

from the alignment of the containment wall and the proposed

borrow materials from the project borrow pit will produce a

containment wall backfill material with a permeability of less

than 1.0 x 10~ cm/sec.

2) Prehydration of the soil-bentonite mixture prior to addition of

plant site ground water has no apparent effect on the

permeability of the mixture.

3) There is a decline in the permeability of the soil-bentonite

mixture with time and therefore, it is not expected that the

plant site ground water will have a detrimental effect on the

permeability of proposed containment wall.

Detailed description of test methods are found on the following pages

of this report.

-I-

Page 34: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEER*. INC.

INTRODUCTION

Authorization

This report presents the results of a laboratory investigation

conducted on the proposed soil-bentonite mixture to be utilized as a

backfill for the containment wall construction at the Velicol Chemical

Corporation Plant Site in St. Louis, Michigan. This report was conducted

for Conestoga-Rovers & Associates Limited.

Authorization to perform this investigation was in the form of a

verbal agreement on May 29, 1982 between Conestoga-Rovers & Associates

and Michian Testing Engineers, Inc.

The purpose of this study was to determine the following:

A. If the proposed bentonite-soil design mix will provide a

containment wall backfill material having a permeability of less

than I x 10" cm/sec.

B. If the proposed design soil-bentonite backfill material will

provide a long term permeability of less than I x 10" cm/sec

when in contact with onsite ground water.

GeneraI

The conclusions submitted are based on the available soil information

and the preliminary design details furnished by the Conestoga-Rovers §

Associates for the proposed containment wall. Any revision in the plans

for the proposed containment wall should be brought to the attention of

the engineer to determine what effect the changes may have on the

proposed wall.

-2-

Page 35: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEERS, INC.

If deviations in the subsurface conditions are encountered during

construction, they should also be brought to the attention of the soils

engineer.

The soil engineer warrants that the findings, recommendations,

specifications or professional advice contained herein, have been

prepared in accordance with generally accepted professional engineering

practice in the fields of foundation engineering, soil mechanics and

engineering geology. No other warranties are implied or expressed.

This report has been prepared for the exclusive use of

Conestoga-Rovers § Associates, Limited for the specific application to

the proposed containment wall construction, in accordance with generally

accepted soil and foundation engineering practices.

-3-

Page 36: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEERS. INC.

GENERAL DISCUSSION

Materials

Soil samples, designated S-l, S-2, S-3, S-4, UGW-4, UGW-9, UGW-15 and

UGW-21 were collected by Conestoga Rovers 6 Associates Limited within the

plant site property and the project borrow pit. The plant site ground

water was supplied to Michigan Testing Engineers and was sampled from

onsite wells by Conestoga-Rovers § Associates. The samples were labeled

as composite samples from UGW-9 and UGW-15. The proposed bentonite

product. Slurry Gel #125 produced by International Minerals and Chemical

Corporation was supplied to Michigan Testing Engineers by the producer.

Preparation of Test Specimens

At the start of the testing program, the natural moisture content of

each soil sample was determined. This test was conducted in accordance

with ASTM D-2216. The moisture content of each samples are listed below:

Sample t Moisture

S-l 14.1

S-2 12.2

S-3 12.4

S-4 13.5

UGW-4 9.9

UGW-9 10.2

UGW-15 11.1

UGW-21 10.6

Utilizing this data, 3% Slurry Gel #125 was added to the test

specimens based on a dry soil weight. Representative samples of the

soil-bentonite mixture were selected for grain size analysis. Grain size

-4-

Page 37: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

M I C H I G A N TESTING ENGINEERS. INC.

distribution curves for each specimen are presented in the Appendix,

Figures I through 8. The grain size distribution of each sample was

determined in accordance with ASTM D-422.

Sufficient water was added to the soil-bentonite mixture to obtain a

4 inch slump as measured by ASTM C-143. The soil-bentonite mixture was

then placed in a FVC permeameter and permeability tests were conducted.

Permeability Determinations

Each soil-bentonite mixture was placed in a permeameter and the flow

monitored. The testing was set-up and the permeability calculated as

outlined in ASTM D-2434. The specifications for the project suggested

utilizing the triaxial method of determining the permeability of the

mixture. However, due to the consistency of the soil-bentonite mixture,

we were unable to form a test specimen. Therefore, methods outlined in

ASTM D-2434 were utilized. Results of permeability tests are tabulated

below.

Specimen

S-lS-2S-3S-4UGW-4UGW-9UGW-15UGW-21

Permeability OfSoil-Bentonite Mixture

cm/sec

7.6 x 109.9 x 107.9 x 107.7 x 108.0 x 109.2 x 108.9 x 108.0 x 10

-8-8-8-8

-8

Page 38: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEERS. INC.

Durability Determinations

During this portion of the testing program, the effects of

prehydration on the slurry was studied. Also, the long term effects of

plant site ground water on the soil-bentonite slurry was investigated.

This testing was conducted on samples S-2, S-3, UGW-9 and UGW-15 only.

Permeabilities were determined in accordance with ASTM D-2434 and the

following test procedure followed.

1. Four test specimens were prepared as described above and allowed

to hydrate for 18 days. During this period, the permeability of

the sample was calculated. A graph of the permeability -vs-

time characteristics of the specimen have been presented on

Figures 9, II, 13 and 15.

2. After the hydration period, the fluid in the permeability

apparatus, fresh water, was drained and replaced with plant site

ground water. The test was continued for about 72 additional

days. The permeability was calculated at regular intervals.

Results of the extended testing have also been present on

Figures 9, II, 13 an 15.

3. At the end of the hydration period explained in point I, four

duplicate samples were prepared. In these tests, plant site

ground water was added to the system at the start of the test

and the sample not allowed to prehydrate. Flow was monitored

ana permeability calculated at regular intervals for a period of

90 days. Figures 10, 12, 14 and 16 present results of the

testing on the unhydrated samples.

Page 39: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING CNGrNEEMS. INC.

The following conclusions have been made from the results of this

portion of the testing:

1. No significant variations were noted in the permeability

characteristics of the hydrated -vs- unhydrated soil samples.

2. The general trend for the permeability of the samples was to

decrease with time. Therefore, the plant site ground water does

not appear to adversely affect the permeability of the

soil-bentonite mixture.

Page 40: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

MICHIGAN TESTING ENGINEERS. INC.

APPENDIX

Page 41: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

100

to

70

S CO

fiS „i80

*" *30

10

051

U. t, fTAMMM) «Vt OKMMC• « ) 2 1 + 1

' "1*- ——* -U•»•€»« US.STAKWIDMVC NUMBERS HVMOHCTCR

4 i 3 4 « 1 10 14 11 20 10 40 M 70 100 140 MO

• ^

']

1

-- *- ^

1

**»

1

" x

1 1

"X" s

1

Sk

I

\\

1 '

v

\\

n too u 10 s asGRAM SIZE IN MILUMETERS

COBBLES

Boring No.

S-l

OUVtLcount | nut

1

S

I

sS,

sjs

\^^ ^*>• -«: - . * —— , —

1

I

0

10

m

30

«S6

so 1

BO §

70

80

90

1000.1 005 001 OO05 0-001

SANDCOMIt HttMUM | nM

Claiiification

Sandv Clav with 3%Slurry Gel #125 added

REPORT OF SOIL ANALYSIS

Nat w

_

% U

_

Pt

_

F1

_

SIlTOft CLAt

P oj«d ProposedContainment Wall

F ,.No. 406-25027D»te November 1982 .

§3781M

Figure 1

Page 42: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

U.1STAHOAMDSKVC OKNMI M WCHES U. & STANMM) «OC NUMKltS HYWUMtlUI• 4) 1 li 1 i 4 4 1 4 i 1 10 14 1« » JO 40 » 70 100 1*0 MO

n

•0

70

1.&

i *°

30

20

10

0s

1

— H

- .

1 T~"T

1- -

:

\-

1 1

-

1 I I

-

:

sN

1

N

'

N

1 1

\.

\\

V

» 100 50 10 5 | OSGRAIN SUC IN ftHLUHEtEftS

OWBLU

Boring No.

S-2

GftAVELCOWK | f«C

1

H,

*

,

t

\,xj

1

s*sj

v ,

s, r

1.

1 . ^^- —i

; :

0

u

20

30

«*fi

» 2

70

B

90

1000.1 045 001 0.006 0001

SANDcomas

Classification

Sandy Clay with 3%Slurry Gel #125 added

REPORT OF SOIL ANALYSIS

MDKM 1 nNf

Nat w

_

% U

.

PL

_

PI

_

SH.T Of! CLAY

proi«t ProposedContainment Wall

FII.NO. 406-25027DM. November 1982

§3781M

Figure 2

Page 43: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

100

JC

•0

70

* «

&

I*6

30

20

10

0S<

U. t STAMMMO SKVC OfCNM• 41 > l| 11

—— i

i

1 1

MMCHO

F — L. .

h T

U. 1 STAMMRD SKVE NUMKRS HTOIOHTtt34 * 1 10 14 1« 20 30 40 90 70 100 140 100

-!• — »

i i

f-

1

~ -

1 1 1

•V

N

VN

1

.S

1

s

1

\

1 i

\\

'

4

» 100 SO 10 5 OSGRAM SIZE IN MILLIMETERS

COBBLES

Boring No.

S-3

GIUVELCOWH | r*c

1

.>

i

,

-iJ-i

S sS

1

k\

N^*> s

!

,

^-^ -"-...ii

,

0

10

20

30

40 £

C

so §

•cr70

BO

90

10001 0.05 0.01 0005 0001

SANOCOMISt KMM

ClanifiCBtion

Sandy Clay with 3%Slurry GP! 41?R aHHpH

REPORT OF SOIL ANALYSIS

Nat w

.

n*

'/« it

-

PI

_

Fl

_

SILT OR CLAY

p,0j«f ProposedContainment Wall

Fi,eN<,. 406-25027o«i. November 1982 .

§3781M

Figure 3

Page 44: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

U 1 STANDARD HEVE OffMHI,„ « * 3 Z t| 1100 —————————————— M—

•0

70

S CO

fc

I"

1.e

re

10

0s

1 1

i

T— •

M ROCS U. S. STANDARD SIEVE NUMtCRS HHWOMETOI_| 4 3 4 « 1 10 14 1* » 30 40 30 70 WO 140 »0

^ I. - »

-

•«i

1

*^

I

"-,1 1 1

•-

• 5

—— 1-

.s

'

s

-

s

'

N

:

I I

V,\

\

'

:

!i

M 100 50 10 S 05GRAIN SIZE IN MILLIMETERS

COBBLES

Boring No.

S-4

GRAVELCCWttt | FM

'

s

, :

I .

^

\^k

1 i

k,-*

-^^^ *•— ~_

ii

S 8

6

8

8

S

'tN

T CO

MSE

R IT

WEI

GHT

70

B

90

1000.1 005 001 0005 0-001

SANDCOMSI

Clarification

Sandv Clav with 3%Slurry Gel #125 addpd

REPORT OF SOIL ANALYSIS

WOIUH | fltlt

Nat w

_

% U

^

PL

PI

SUTOR CLAT

Pr0i.ci ProposedContainment Wall

Fii.No. 406-25027o*t« November 1982 .

§37B1M

Figure 4

Page 45: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

U. & STANOMO S«C OHNMCl/TL « « 1 I 1+ I

to

70

&s M

I"X

to

10

0Si

1

JT

' ' "

MMCHCS

Ltl""-"— L

1

U. 1 STANDARD SIEVE MMBCIB HVDM1MCTU1 4 « 1 10 14 U JO 30 «» 70 100 140 W)1

•* •—

1

"-s

'

s»_-*

i i i

r\\ •> s

1

:1 "

S

\

1

s\

1

\

\

i i

\X

1

30 100 SO 10 S 1 05GMIN StZC IN MILLIMETERS

COBBLES

Bormg No,

UGW-4

GUVELOOMK fut

- t

1

kTV

4^^^-r-^ U.

ia 11

;

5 8

6

8

B S

'

tNT

COAR

SEII

BT W

EIGH

T

£

TO

10

90

10001 006 001 0005 0.001

SANDCDMnt MEMNt

. Classification

Clayey Sand with 3%Slurry Gel #125 added

UEPORT OF SOIL ANALYSIS

Nat w°

r**

LL

_

PL

_

PI

_

SILT Off OAT

project ProposedContainment Wall

FII.NO. 406-25027D«. November 1982 .

f3781M

Figure 5

Page 46: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

4 *•-

U.1 STAMUM) SKVC OPCNMO,„ • 4 3 Z l| 1100 ——————————————————————— • ————— '

K

•0

70

* «

|tt

£

20

10

051

I ————• "~* —MMCHCS

L—— —

U. 8. STAMOMO SKK MWKn HVMOHCTCII34 • 1 10 14 1< 10 30 40 SO 70 100 140 1001

^-*

1

*-

-•

1

1

~^

1 1 I

' 1

I

N|S

1

S\

1

\^

1 1

1\

\\

30 100 90 10 S 1 05GRAIN SIZE IN HILUMETERS

COMES

Boring No.

UGW-9

GRAVtlOMMM | FM

-I

1

i

s,s,^"^ [

N»x^

--.^

--

-,

0

10

30

40 |

S

90 I

te

70

10

90

1000.1 0.05 001 0005 00)1

SANOCQMH KtMJH

Clanification

Clayey Sand with 3£Slurry fiel #125 added

REPORT OF SOIL ANALYSIS

Nat w

-

fM

'/„ U

-

PL

-

Pt

-

StlTOM CUT

project ProposedContainment Wall

Fi.«No. 406-25027D.,e November 1982

§3781M

Figure 6

Page 47: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

U.I STANOMD KVt OKNH.„ * « 3 1 1+ 1 '

•0

70

2 CO

c•tI"fi

30

20

10

0V

1 1

p

1

M MCHES 0. 1 STANOMD SKVE HUMMS HVMOUCTEJt41 34 t 1 10 14 1« 20 30 « 90 JO 100 140 100

t

———— 1

-i

-,1-- •—.

!

|

"T

*i^

i i 1

^k

!

SS,

1

\ \S

'

\

' '

V

\

\

\

» 100 90 10 5 QJGRAIN SIZE IN MILLIMETERS

COMICS

Boring No.

UGW-15

GHAVCLCOMH fM|

-i

1

s s

t

Nv\

\^-

1

• - , < n — • — ,

1

0

10

30

40 |

t50 I

60 §

70

80

90

1000.1 003 001 OJXA 0001

SAHOtaunt •RNUK

Clarification

Clayey Sand with 3%Slurrv GeT #1?5 addpd

REPORT OF SOIL ANALYSIS

Nat w

.

fME

% LL

_

PI

_

PI

_

SILT OR OAT

prefect ProposedContainment Wall

M.N«. 406-25027D.« November 1982 .

§3781M

Figure 7

Page 48: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

U&STANOMOSKVC OKMNG M MCHES U 1 STAMDMO SKVE NUMBERS H1MOMETER« « J J If 1 4 + 4 3 4 « 1 10 14 1* » JO 40 SO TO 100 140 WO

K

BO

TO

fi

i50

§ ,„K

20

10

0S

i

1T

1 1 1 r '7 -a •-

M-

— • Z=*^^

i i i

• ^• .

s.S

1

s's

1

^^J

t I

X^ .

i —— —:

- ——— -10 100 50 10 5 OS

GRMN SUE IN fcHUJMETEW

COBBLES

Boring No.

UGW-21

cwvacount | 'me

1

' S

!

,

s

i-

S^k

~T-

V.

s^ sX X^

"

t1

M

»

30

« 1fi

so E

t70

n

90

10001 006 001 00ft 000!

SANDcownc MOM* | KM

CUiiif cation

Sandy Clay with 32Slurrv Gel #1?5 addpd

REPORT OF SOIL ANALYSIS

N»lw

_

% U

_

PL

F1

_

SM.TORCLAY

projMi ProposedContainment Wall

FJI.NO. 406-25027o.t. November 1982 .

§3781M

Figure 8

Page 49: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

PERMEABILITY (CM/SEC) PERMEABILITY (CM/SEC)

Page 50: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

PERMEABILITY (CM/SEC)

roo

g01o

eno

-< o —

00o

g

PERMEABILITY (CM/SEC)

Page 51: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

PERMEABILITY (CM/SEC) PERMEABILITY (CM/SEC)

roo

01o

~ o

g"" Jl/> O

oo

roo

CJo

eno

en>~* o

§

oo

Page 52: VELSICOL CHEMICAL CORPORATION · plant site, Velsicol Chemical Corporation (Velsicol) is required to construct a continuous soil/bentonite ... testing procedure as specified in ASTM

PERMEABILITY (CM/SEC) PERMEABILITY (CM/SEC)


Recommended