+ All Categories
Home > Documents > VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe...

VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe...

Date post: 27-Mar-2020
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
67
VIDEO INSPECTION AND LASER DEFLECTION TESTING FOR POST CONSTRUCTION QC/QA SPECIFICATIONS AND MAINTENANCE INSPECTIONS BY JOHN FLECKENSTEIN PIPELINE AND DRAINAGE CONSULTANTS
Transcript
Page 1: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

VIDEO INSPECTION AND LASER DEFLECTION TESTING FOR POST

CONSTRUCTION QC/QA SPECIFICATIONS

AND MAINTENANCE INSPECTIONS

BY JOHN FLECKENSTEIN

PIPELINE AND DRAINAGE

CONSULTANTS

Page 2: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

INTRODUCTION

• History Of Post Construction Inspections

• Recent Specification Changes (New AASHTO Specification)

• Laser Deflection Testing and KY Case Studies

• Economic Cost/Cost Benefits and Maintenance Inspection Needs

INTRODUCTION

• History Of Post Construction Inspections

• Recent Specification Changes (New AASHTO Specification)

• Laser Deflection Testing and KY Case Studies

• Economic Cost/Cost Benefits and Maintenance Inspection Needs

Page 3: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Video Inspection Edge Drains (Mid 1990’s)

Page 4: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

0

5

10

15

20

25

30

35

40

45

Perc

en

t F

ailu

res

Failures Prior to

Cameras

Failures After

Design Changes

Failures After

QC

Failures at Final

Inspection

Failures Prior to Video Inspection/Quality Control

Single Wall Flexible Outlet Pipe

Double Wall Flexible Outlet Pipe

With no Video Inspection

Double Wall Flexible Outlet Pipe

With Video Inspection

(Late 1980’s)

(Early 1990’s)

(Mid 1990’s)

History of Edge Drain Failure Rates

Page 5: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Quality Control and Quality Assurance Specifications for Cross Drains,Storm Drains, and Culverts Were

Initiated in the Early 2000’s

Page 6: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Section 701.03.08

701.03.08 Testing of Pipe. The Engineer will visually inspect all pipe. The Department

may require camera or mandrel testing, KM 64-114, for any pipe when deflection,

cracking, joint faulting, or any other interior damage is suspected. If the pipe shows damage,

repair or replace as the Engineer directs. If the pipe shows deflection of 10 percent or greater,

remove and replace the pipe. If the pipe shows deflection greater than 5 percent but less than

10 percent, the Department will allow the pipe to remain in place at a reduced unit price. Do

not pave over any pipe until inspection and any required testing is completed. When paving

will not be delayed by the wait, test pipe 30 days or more after backfilling is completed.

Developed in 2000 during QC/QA specifications, has not been widely enforced

Page 7: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

PIPE DEFLECTION DETERMINED BY CAMERA TESTING

Amount of Deflection (%) Payment

0.0 to 5.0 100% of the Unit Bid Price

5.1 to 7.5 75% of the Unit Bid Price

7.6 to 8.5 50% of the Unit Bid Price

8.6 to 9.9 25% of the Unit Bid Price

10 or greater Remove and Replace

PIPE DEFLECTION DETERMINED BY MANDREL TESTING

Amount of Deflection (%) Payment

0.0 to 5.0 100% of the Unit Bid Price

5.1 to 9.9 50% of the Unit Bid Price

10 or greater Remove and Replace

The Department will consider payment as full compensation for all work

required under this section.

Section 701.05

Page 8: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

AASHTO SECTION 30.5.6NEW INSPECTION REQUIREMENTS FOR HDPE PIPE(AS ADOPTED BY THE AASHTO SUBCOMMITTEE ON BRIDGES AND STRUCTURES – JUNE 29, 2005)

AASHTO SECTION 30.5.6NEW INSPECTION REQUIREMENTS FOR HDPE PIPE(AS ADOPTED BY THE AASHTO SUBCOMMITTEE ON BRIDGES AND STRUCTURES – JUNE 29, 2005)

� All pipes shall undergo inspection during and after installation.

� Final inspections shall be conducted no sooner than 30 days after completion of installation and final fill.

� The pipe shall be evaluated to determine whether the internal diameter of the barrel has been reduced more than 5 percent when measurednot less than 30 days following completion of installation.

� For locations where pipe deflection exceeds 5 percent of the inside diameter, an evaluation shall be conducted by the Contractor andsubmitted to the Engineer for review and approval considering the severity of the deflection, structural integrity, environmental conditions, and the design service life of the pipe. Pipe remediation or replacement shall be required for locations where the evaluation finds that the deflection could be problematic. For locations where pipe deflection exceeds 7.5 percent of the inside diameter, remediation or replacement of the pipe is required.

� Installed pipe deflections that exceed 5 percent of the initial inside diameter may indicate that the installation was substandard. appropriate remediation, if any, will depend upon the severity of the deflection.

� In all pipe installations, at least 10 percent of the total number of pipe runs representing at least 10 percent of the total project footage on the project shall be randomly selected by the Engineer and inspected for deflection. Also, as determined by the 100 percent visual inspection in Section 30.5.6.1, all areas in which deflection can be visually detected shall be inspected for deflection.

� All pipes shall undergo inspection during and after installation.

� Final inspections shall be conducted no sooner than 30 days after completion of installation and final fill.

� The pipe shall be evaluated to determine whether the internal diameter of the barrel has been reduced more than 5 percent when measurednot less than 30 days following completion of installation.

� For locations where pipe deflection exceeds 5 percent of the inside diameter, an evaluation shall be conducted by the Contractor andsubmitted to the Engineer for review and approval considering the severity of the deflection, structural integrity, environmental conditions, and the design service life of the pipe. Pipe remediation or replacement shall be required for locations where the evaluation finds that the deflection could be problematic. For locations where pipe deflection exceeds 7.5 percent of the inside diameter, remediation or replacement of the pipe is required.

� Installed pipe deflections that exceed 5 percent of the initial inside diameter may indicate that the installation was substandard. appropriate remediation, if any, will depend upon the severity of the deflection.

� In all pipe installations, at least 10 percent of the total number of pipe runs representing at least 10 percent of the total project footage on the project shall be randomly selected by the Engineer and inspected for deflection. Also, as determined by the 100 percent visual inspection in Section 30.5.6.1, all areas in which deflection can be visually detected shall be inspected for deflection.

Page 9: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

AASHTO SECTION 26.5.7NEW INSPECTION REQUIREMENTS FOR CMP

(AS ADOPTED BY THE AASHTO SUBCOMMITTEE ON BRIDGES AND STRUCTURES – JUNE 29, 2005)

AASHTO SECTION 26.5.7NEW INSPECTION REQUIREMENTS FOR CMP

(AS ADOPTED BY THE AASHTO SUBCOMMITTEE ON BRIDGES AND STRUCTURES – JUNE 29, 2005)

� CMP shall be inspected after placement in the trench, as required during backfilling, and after completion of installation to ensure that final installation conditions allow the pipe to perform as designed.

� Final internal inspections shall be conducted on all buried CMP installations to evaluate issues that may affect long term performance. Final inspections shall be conducted no sooner than 30 days after completion of installation and final fill.

� It should be noted that the AASHTO Flexible Culvert Liaison Committee has been directed to write deflection criteria for inclusion in the installation specification for CMP next year.

� CMP shall be inspected after placement in the trench, as required during backfilling, and after completion of installation to ensure that final installation conditions allow the pipe to perform as designed.

� Final internal inspections shall be conducted on all buried CMP installations to evaluate issues that may affect long term performance. Final inspections shall be conducted no sooner than 30 days after completion of installation and final fill.

� It should be noted that the AASHTO Flexible Culvert Liaison Committee has been directed to write deflection criteria for inclusion in the installation specification for CMP next year.

Page 10: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

AASHTO SECTION 27.6.1NEW INSPECTION REQUIREMENTS FOR RCP

(AS ADOPTED BY THE AASHTO SUBCOMMITTEE ON BRIDGES AND STRUCTURES – JUNE 29, 2005)

AASHTO SECTION 27.6.1NEW INSPECTION REQUIREMENTS FOR RCP

(AS ADOPTED BY THE AASHTO SUBCOMMITTEE ON BRIDGES AND STRUCTURES – JUNE 29, 2005)

� Internal inspections shall be conducted on all buried rigid pipeinstallations to evaluate issues that may affect long-term performance, such as cracks, joint quality and alignment. Inspections shall be conducted no sooner than 30 days after completion of installation and final fill.

� Hairline longitudinal cracks in the crown or invert indicate that the steel has accepted part of the load. Cracks equal to or less than 0.01 in. (0.25 mm) in width are considered minor and only need to be noted in the inspection report.

� Inspection records for pipes with crack widths exceeding 0.01 in. (0.25 mm), shall be kept on file for monitoring conditions during subsequent inspections. Crack measurements and photographs shall be taken for monitoring conditions during subsequent inspections.

� Internal inspections shall be conducted on all buried rigid pipeinstallations to evaluate issues that may affect long-term performance, such as cracks, joint quality and alignment. Inspections shall be conducted no sooner than 30 days after completion of installation and final fill.

� Hairline longitudinal cracks in the crown or invert indicate that the steel has accepted part of the load. Cracks equal to or less than 0.01 in. (0.25 mm) in width are considered minor and only need to be noted in the inspection report.

� Inspection records for pipes with crack widths exceeding 0.01 in. (0.25 mm), shall be kept on file for monitoring conditions during subsequent inspections. Crack measurements and photographs shall be taken for monitoring conditions during subsequent inspections.

Page 11: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

New AASHTO VIDEO INSPECTION REQUIREMENTS

Visual inspection of all structures, video inspect 24-inch and smaller

Deflection testing on flexible pipes and crack testing on rigid pipes

How do we measure

and quantify?

Page 12: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Measuring Pipe Deflection

Page 13: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

MANDREL TESTINGMANDREL TESTING

� Go-No-Go device.

� 5% Deflection.

� Stuck if deflection is exceeded.

� 30+Days

� Prior to Final Acceptance

� Takes two men approx. 10 minutes to do 100 yards.

� Go-No-Go device.

� 5% Deflection.

� Stuck if deflection is exceeded.

� 30+Days

� Prior to Final Acceptance

� Takes two men approx. 10 minutes to do 100 yards.

Page 14: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Laser Deflection Testing

Page 15: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Laser Process

Page 16: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 17: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

ClearLine Profiler Accuracy (inches)

0

20

40

60

80

100

120

0.04 0.08 0.12 0.16 0.2 0.24 0.28 0.32 0.36 0.4 0.44 0.48

Accuracy (inches)

Pip

e S

ize (

inch

es)

Pipe Size (in) Accuracy (in) Percentage

8 0.04 0.5

16 0.08 0.5

24 0.12 0.5

32 0.16 0.5

40 0.2 0.5

48 0.24 0.5

56 0.28 0.5

64 0.32 0.5

72 0.36 0.5

80 0.4 0.5

88 0.44 0.5

96 0.48 0.5

The WRc (ref: PT/235/0904) has certified the ClearLine Profiler to accuracy of 1mm

in 200mm pipe (0.5%) for manual measurements. Similar accuracy obtained for the automated graphs

(Ovality, capacity etc).

Page 18: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

36-Inch HDPE Pipe (MH 5 to MH 4)

-20.00

-15.00

-10.00

-5.00

0.00

5.00

10.00

15.00

20.00

0 25 50 75 100 125 150 175 200 225 250 275 300 325

Distance (Ft.)

% D

eflection

Horizontal Vertical Design Deflection Limits

Page 19: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 20: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 21: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Horizontal Deflection 10%Vertical Deflection Approx. 11%

Page 22: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 23: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 24: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 25: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 26: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 27: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

CASE STUDIES

MSD LOUISVILLE, KENTUCKY

12-INCH THROUGH 24-INCH

STORM DRAIN

MARCH 25, 2005

Page 28: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

HDPE Pipe

Page 29: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Selinda D

r.

Poplar L

evel

Illinois

Page 30: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

MH 1-MH 2

Page 31: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

NOISEDEFLECTION

DEFLECTIONNOISE AND WATER

Page 32: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 33: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 34: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Laser Test Site No. 1,

Louisville, Kentucky

Laser Test Site No. 1,

Louisville, KentuckyVIDEO/LASER DEFLECTION

TEST SITE NO. 1

LOUISVILLE, KENTUCKY

36-INCH AND 42-INCHSTORM DRAIN

OCTOBER 12, 2004

Page 35: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Site Layout, Aireal ViewSite Layout, Aireal View

OUTLET

MH 1

MH 2

MH 3

MH 4

MH 5

MH 6

MH 3A

Page 36: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

36-Inch HDPE Pipe (MH 3 to MH 2)

-15.00-12.50-10.00-7.50-5.00-2.500.002.505.007.50

10.0012.5015.0017.50

0 20 40 60 80 100 120 140

Distance (Ft.)

% D

eflection

Laser Deflection Method Comparison MH 3 to MH 2

Page 37: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Laser Ring MH 3 to MH 2

Page 38: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

13.6% Change in Ovality

% Ovality Change = 100 x Max I.D-Mean I.D

Mean I.D

Laser Ring MH 3 to MH 2

Page 39: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

10.8% Ovality Change

MH 3 to MH 2

Crown Flattening

Page 40: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

14% Ovality Change

MH 3 to MH 2

DIMPLING SHOWN AT 3 O’CLOCK

Page 41: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

8.1% Ovality Change

MH 3 to MH 2

Page 42: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

9.8% Ovality Change

MH 3 to MH 2

Page 43: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

36-Inch HDPE Pipe (MH 5 to MH 4)

-20.00

-15.00

-10.00

-5.00

0.00

5.00

10.00

15.00

20.00

0 25 50 75 100 125 150 175 200 225 250 275 300 325

Distance (Ft.)

% D

efl

ec

tio

n

Horizontal Vertical Design Deflection Limits

Measured Vertical

Deflection -17.5% (-17.5%)

Page 44: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Estimated Percent of Pipe Deflected

Over 5% and 10%

56

93

100

25

100

38

53

89

17

46

17

0

50

25

7

23

0

20

40

60

80

100

120

MH 6 - MH 5

MH 5 - MH 4

MH 4 - MH 3A

MH 3A 0 MH 3

MH 3 - MH 2

MH 2 - MH 1

MH 1 - Outle

t

Average

% o

f P

ipe

De

fle

cte

d

>5% Deflection

>10% Deflection

Page 45: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

EVALUATION OF HDPE PIPE PERFORMANCEON KENTUCKY DOT CONSTRUCTION PROJECTS

Page 46: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

KY PROJECT LIST

LOCATION FEET INSPECTED

NICHOLASVILLE ROAD, LEXINGTON 983.6

US 68/KY 80, BOWLING GREEN 658.0

KY 210, HODGENVILLE 130.0

US 31E, HODGENVILLE 239.5

US 150, STANFORD 676.0

US 127, OWEN COUNTY 300.0

KY 207, FLATWOODS 905.0

3,727.1

Page 47: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

58 ft. Deflection Approx. 6.6%

Page 48: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Deflection Approximately 8.3%

Page 49: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Pipe Compressed and Racked

Bowling GreenUS 68/KY 80

Page 50: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Approximately 14% deflection

36” Cross Drain Bowling Green

Page 51: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Deflection Approximately 15%, Outfall Line

Page 52: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

MH 1-Outlet

Severe Pipe Deflection, 20 ft

Deflection Approximately 20%

Page 53: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

MH 1-MH 2

Severe Crown Flattening in Cross Drain

Near Manhole Vertical Deflection

Approximately 11%

US 31W, Hodgenville

x

Page 54: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

x

MH 2-MH 3

Failure 18-inch storm drain

Deflection Approximately 50%

US 31W, Hodgenville

Page 55: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Deflection Approx. 10%

Median Drain, US 150, Stanford

Page 56: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Crown flattening, crack in crown

MH1-MH2

18-inch cross drain

Crown flattening and cracking

at 41.5 ft.

KY 210, Hodgenville

Page 57: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Estimated Vertical Deflection 11%

KY 210, Flatwoods, KY

Page 58: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

KENTUCKY PROJECT SUMMARY

LOCATION DEFLECTION (MAX/MAX AVG)

NICHOLASVILLE ROAD, LEXINGTON 10/6

US 68/KY 80, BOWLING GREEN 20/12.4

KY 210, HODGENVILLE 15/12.5

US 31E, HODGENVILLE 50/17.1

US 150, STANDFORD 10/9

US 127, OWEN COUNTY 4.2/3.5

KY 207, FLATWOODS 11/8.4

17/9.8

Page 59: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Culvert Evaluation on

I-65, by KY Transportation Center

RCP and Galvanized Metal

Structures Inspected = 830

Structures Needing Remedial Action = 313 (37%)

Structures Needing Repair or Replacement = 134 (16%)

Structures Needing Cleaning/Possible Repair = 179

(21%)

Page 60: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Kentucky DOT is Currently Evaluating The Need For QC/QA Video Inspection Of All Drainage Structures.

(Includes Pavement Edge Drains, Embankment/

Bench Drains, Bridge End Drains, Cross Drains, Storm Drains, Etc.)

Page 61: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Benefit/Cost of Benefit/Cost of

Video Inspection of Under DrainsVideo Inspection of Under Drains

Cost Camera InspectionCost Camera Inspection $0.25 ft $0.25 ft -- $0.35 ft$0.35 ft

Per Mile $1,320 mile Per Mile $1,320 mile -- $1,848 mile$1,848 mile

4 Lane inside and outside 4 Lane inside and outside $5,280 $5,280 -- $7,392 mile$7,392 mile

Cost of Asphalt Overlay, 1 Cost of Asphalt Overlay, 1 ½½ AC AC -- $50,000 mile$50,000 mile

4 lane interstate overlay 4 lane interstate overlay -- $200,000 mile$200,000 mile

(not include shoulders and user delay cost)(not include shoulders and user delay cost)

Complete PCC RehabilitationComplete PCC Rehabilitation -- $2,000,000 mile$2,000,000 mile

(Delayed by 10 years)(Delayed by 10 years)

1/4$

$,$$$,$$$

Cost Camera InspectionCost Camera Inspection $0.25 ft $0.25 ft -- $0.35 ft$0.35 ft

Per Mile $1,320 mile Per Mile $1,320 mile -- $1,848 mile$1,848 mile

4 Lane inside and outside 4 Lane inside and outside $5,280 $5,280 -- $7,392 mile$7,392 mile

Cost of Asphalt Overlay, 1 Cost of Asphalt Overlay, 1 ½½ AC AC -- $50,000 mile$50,000 mile

4 lane interstate overlay 4 lane interstate overlay -- $200,000 mile$200,000 mile

(not include shoulders and user delay cost)(not include shoulders and user delay cost)

Complete PCC RehabilitationComplete PCC Rehabilitation -- $2,000,000 mile$2,000,000 mile

(Delayed by 10 years)(Delayed by 10 years)

$$$,$$$

3-7%

Page 62: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

CULVERT INSPECT COST VS.

EMBANKMENT REPAIR COST

(Video Inspection $1.00 - $1.45 ft.)

Total Cost = $507.00

200’ Embankment Repair

$300 - $3,000 per linear ft.

$60,000 - $600,000

(as >1.5 MILLION )

(Not Including Culvert Repair)

$$$,$$$

$507.00

Page 63: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Drainage Maintenance Inspection Needs

(Need to Inspect, Clean, and Repair Existing Structures Prior to Failure)

Page 64: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

The Economic Costs of Culvert Failures

Transportation Research Board

January 2004

Joseph Perrin Jr.

Research Assistant Professor

Civil Engineering Dept., University of Utah

Page 65: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department
Page 66: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

Conclusions

1. Laser deflection provides significantly more

Information than camera inspection alone.

2. Must set quality control video specifications

for all drainage structures.

3. Must set deflection limits on flexible

structures and crack limits on rigid structures.

4. Must Inspect, clean, and repair existing structures.

5. Reevaluate drainage specifications, and make

changes where necessary to insure the long-

term performance of the roadway system.

Page 67: VIDEO INSPECTION AND LASER DEFLECTION …sp.construction.transportation.org/Documents/...If the pipe shows deflection greater than 5 percent but less than 10 percent, the Department

John Fleckenstein

[email protected]

Cell: 859-393-4291


Recommended