External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project Prepared by VIETNAM WATER, SANITATION AND INVIRONMENT JSC (VIWASE) for the Ministry of Rural development and agriculture and the Asian Development Bank.
Transcript
Page 1: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

External Resettlement Monitoring

Document stage: Final Project number: 40190 December 2016

VIE: Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project

Prepared by VIETNAM WATER, SANITATION AND INVIRONMENT JSC (VIWASE) for the Ministry of Rural development and agriculture and the Asian Development Bank.

Page 2: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

2 | P a g e

ABBREVIATIONS

ADB Asian development Bank (ADB)

AusAID Australian Agency for International Development

BAH Affected household

CPO Central project office

CPMU Central Project Management Unit

RDD ResettlementDue Diligence

PPMU Provincial project management unit

DCCS District Committee for Compensation and Site Clearance

DCLFP District LFDC

IMO Independent monitoring organ

ODA Official development assistance

TOR Term of Reference

RF Resettlement frame

RP(s) Resettlement plans

uRP Update Resettlement plans

VIWASE Vietnam water, sanitation and environment JSC

CPC Commune People’sCommittee

Page 3: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

3 | P a g e

NOTE

(i) In this report, "$" refers to US dollars. This external resettlement monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 4: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

4 | P a g e

Contents I. INTRODUCTION ..................................................................................................................... 6 II. KEY CONTENTS OF RESETTLEMENT ............................................................................... 8 III. TARGET OF THE ASSIGNMENT AND SCOPE OF WORK ............................................ 13

3.1. Target of the Assignment ............................................................................................... 13

3.2. Scope of work .................................................................................................................. 13

IV. APPROACH AND METHODOLOGIES OF MONITORING IMPLEMENTATION ............ 17

4.1. Approach .......................................................................................................................... 17

4.2. Methodologies ofmonitoring implementation ............................................................. 17

4.3. Implementation arrangement:................................................................................... 18

V. MONITORING RESULTS .................................................................................................... 19

5.1. Results of Desk review ................................................................................................... 19

5.2. Results of site monitoring .............................................................................................. 24

5.2.1. Information disclosure and public consultation ...................................................... 24 5.2.3 Compensation plans ................................................................................................ 28 5.2.5 Restoration of the affected people’s lives and livelihood........................................ 38 5.2.6. Siteclearance and land hand-over ......................................................................... 56 5.2.7. Arrangement for resettlement ................................................................................ 57 5.2.8. Grievance Redress Mechanisms ........................................................................... 59 5.2.9. Satisfaction of the Affected People on Resettlement Implementation. ................. 59 5.2.10. Gender impacts and strategy . ............................................................................. 60

5.3. Outstanding issues ......................................................................................................... 61

5.4. Responsibility for implementing the action plans ...................................................... 61

VI. CONCLUSION AND RECOMMENTDATION .................................................................... 63

6.1. Conclusion ....................................................................................................................... 63

6.2. Recommendation ............................................................................................................ 64

APPENDIX

Page 5: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

5 | P a g e

TABLE Table1: The types of land affected by subproject Ba Rai – Phu An .......................................... 8 Table 2: Summary of affected households ................................................................................ 9 Table 3: The types of land affected by construction activities of the subproject ..................... 11 Table 4: Indicators for Monitoring............................................................................................ 13 Table 5. Status of Site Clearance of Ba Rai – Phu Ansubproject ........................................... 21 Table 6.Status of Site Clearance of Cai Cai channelsubproject ............................................. 23 Table 7: Numbers of Ba Rai –Phu An subproject Meeting Participants ................................. 25 Table 8: Numbers of Cai Cai channel works Meeting Participants ........................................ 26 Table 9: Compensation price of Subproject – Cai Lay town (unit: Dong per m2) .................. 31 Table 10: Compensation price of Subproject–Cai Lay district (unit: Dong per m2) ................. 31 Table 11: Assistances for PAHs ............................................................................................... 41

Page 6: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

6 | P a g e

I. INTRODUCTION

1. The GMS Flood and Drought Risk Management and Mitigation Project (the Project) will

be implemented in Cambodia, Lao PDR and Vietnam. The Project aims to improve the

capacity of the countries and communities to prepare for, respond to, and recover from

the negative impact of floods and droughts. For Vietnam, the investments proposed

comprise of three non-structural sub-projects and four structural subprojects to mitigate

the adverse impacts of extreme weather events in two provinces (Tien Giang, and Dong

Thap) in the Mekong Delta. The proposed structural subprojects are: (i) Go Cong water

management improvement; and (ii) flood control system for Ba Rai – Phu An area. With

Dong Thap, the subprojects to be considered include: (iii) Upgrading and rehabilitation of

four primary canals in Plain of Reeds; and (iv) Embankment erosion control in Thuong

Thoi Tien Town, Hong Ngu District, Dong Thap Province.

2. The impact of the project is reduced economic losses resulting from floods and droughts.

The outcome of the project is improved capacity and preparedness to manage and

mitigate the impacts of flood and drought events. The projecthasfour components: (i)

Component 1: Enhanced regional data, information, and knowledge base for the

management of floods and droughts; (ii) Component 2: Upgraded water management

infrastructure; (iii) Component 3: Enhanced capacity for Community-based Disaster Risk

Management (CBDRM); and (iv) Component 4: Effective Project Implementation. The

executing agency is MARD, through CPO. The implementing agencies (IAs) are the

provincial Department of Agriculture and Rural Development (DARD) of the two

participating provinces, Tien Giang and Dong Thap provinces. The project was approved

on 11 November 2012, signed on 21 December 2012 and declared effective on 10 May

2013. The project is expected to be complete by 31 March 2019.

3. Implementation ofComponent 2 of the Project shall result in the involuntary resettlement

through loss of land and assets of households, utilities and organization. To minimize

these impacts several Resettlement Plans (RPs) has been developed by the Technical

Assistance (ADB) and agreed by the Ministry of Agriculture and Rural Development

(MARD).

4. RPs of the 4 sub-projects have been prepared in the basic design phase. As required,

RPs shall be updated after Loan Agreement was signed and became effective to reflect

changes and requirements occurred recently. The updated RP shall be the base for the

implementation of Project resettlement activities by Central Project Management Units

(CPMUs); District Compensation, Assistance and Resettlement Boards (DCARBs) and

stakeholders.

5. The implementation of independent resettlement moritoring aims to ensure that

objectives, policies and principles on social safeguard (Involuntary resettlement),

entitlements of affected persons (APs) specified in the RPs will be complied.

Independent resettlement moritoring will be conducted on periodically base, two times

Page 7: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

7 | P a g e

per year. Periodic reports on independent resettlement moritoring shall be developed

aiming to provide the funding agencies, executing agency and stakeholders independent

review and assessment of: (i) achievement of resettlement objectives; (ii) changes in

living standards and livelihoods of affected people; (iii) restoration and/or improvement

of the economic and social base of the affected people; (iv) effectiveness and

sustainability of entitlements; and (v) the need for further mitigation measures of

project adverse impacts.

6. Two subprojects have been carried out the Independent monitoring program (IMO), 3rd

phase, including (1) Construction of flood controlling system in Ba Rai – Phu An region,

Tien Giang province and (2) Rehabilitation and upgrading for the flood drainage and

irrigation system to the Dong Thap Muoi region, Dong Thap province – Cai Cai canal

works. Those subprojects are carrying out compensation, support and resettlement for

the affected households according to regulations of updated RP dated August and

September 2016. For two subprojects “Embankment erosion control in Thuong Thoi Tien

Town, Hong Ngu District, Dong Thap Province”and “Upgrading the controlling system of

saltwater intrusion in Go Cong region, Tien Giang province” have been already

completed the compensation and adopted by ADB. It is expected the final independent

monitoring program for two subprojects would be carried out in Quarter 1, 2017. For the

Tan Cong Chi and Khang Chien channels – Rehabilitation and upgrading for the flood

drainage and irrigation system to the Dong Thap Muoi region has already completed the

plan of detailed measurement survey (DMS) and submitted it to Dong Thap province

DONRE. The updated RP for two works is expected to be completed in Quarter 1, 2017

7. Therefore, 3rdperiodic report on independent resettlement monitoring- IRM (for the

duration from the start of RP implementation till 30 November, 2016) is the resettlement

monitoring Report which is prepared for the above objectives and focused on two

subprojects (1) Construction of flood controlling system in Ba Rai – Phu An region, Tien

Giang province and (2) Rehabilitation and upgrading for the flood drainage and irrigation

system to the Dong Thap Muoi region, Dong Thap province – Cai Cai channel works.

The Report is developed on the basis of: ADB Safeguard Policy Statement (SPS

2009); policies and regulations of Viet Nam on compensation, support and land

recovery; RF; RP; reports, data and information provided by: (1) CPO; (2) Tien

GiangPPMU; (3) Go Cong DCCS/Go Cong LFDC; (4) Dong Thap PPMU; (5) Tan Hong

DLFDC; (6) Ward/commune PCs in project area: Ward No.2 PC, Tan Binh CPC, Thanh

Hoa CPC – Cai Lay town, Dong Hoa Hiep CPC in Cai Be district belong to “Construction

of flood controlling system in Ba Rai – Phu An region, Tien Giang province” and Tan

Phuoc CPC, Tan Thanh A CPC, Thong Binh CPC in Tan Hong district, Dong Thap

province belong to “Rehabilitation and upgrading for the flood drainage and irrigation

system to the Dong Thap Muoi region - Cai Cai channel works”; (7) RP experts and (8)

local people and persons affected by land acquisition of the subproject.

Page 8: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

8 | P a g e

II. KEY CONTENTS OF RESETTLEMENT

8. As mentioned above, 3rdperiodic independent resettlement monitoring report (during the

time from the start of RP implementation till 30 November, 2016) focused on monitoring

two subprojects (1) “Construction of flood controlling system in Ba Rai – Phu An region,

Tien Giang province” and (2) “Rehabilitation and upgrading for the flood drainage and

irrigation system to the Dong Thap Muoi region - Cai Cai channel works”.

Scope of land acquisition of the subproject:

9. 1. Subproject “Construction of flood controlling system in Ba Rai – Phu An region,

Tien Giang province”: The subproject acquired 90,939.21 m2 of land of 9

wards/communes in Cai Lay town, Cai Lay district and of Cai Be district, Tien Giang

province. In which, the subproject permanently acquired 47,902 m2 and temporarily

acquired 43,037.21 m2 of land (equivalent to 47%). There are 3,833.8 m2 of residential

land and 44,068.2 m2 of agricultural land in the total of 47,902 m2 of permanent acquired

land. The types of land affected by subproject are presented in the Table below.

Table 1: The types of land affected by subproject Ba Rai – Phu An

unit: m2

Name of Ward/Town Permanently

Affected Residential land (m2)

Permanently Affected

Agricultural land (m2)

Temporarily Afffected

Agricultural Land (m2)

(m2) I Cai Lay town 2,314.7 10.324,70 9.158,81

1 Thanh Hoa commune 611.2 3,795.7 4,680.16

2 Tan Binh commune 247.5 2,078.7 1,986.5

3 Ward no.2 1,456 4,450.3 2,492.15

II Cai Lay district 1,519.1 33,743.5 32,378.4

1 Cam Son commune 300 12,647.1 4,011.1

2 Hoi Xuan commune - 4,415.8 7,690.5

3 Hiep Duc commune - 1,760.2 3,914.5

4 Phu An commune 203.2 9,503.4 9,392.2

5 Binh Phu commune 1,015.9 5,417 7,370.1

III Cai Be district - - 1,500

1 Dong Hoa Hiep commune - - 1,500

Total 3,833.8 44,068.2 43,037.21

Source: Detailed Measurement Survey (DMS), January

2015

10. The implementation of sub-project affected lands and properties of 247 households

(1,159persons) specifically as follows:

- Among 247 affected households, 52 households (235 persons) have to displace

Page 9: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

9 | P a g e

to another place, 29 households would be resettled through building houses on

their remaining part of land. This will mitigate negative impacts on livelihood of the

affected households.

- Out of 247 affected households, 100 households (466 persons, accounting for

40.48%) are severely affected and 147 households (735 persons, accounting for

59.52%) are slightly affected.

- 67 households (337 persons) out of 100 severely affected households were

acquired their agricultural land, in which 37 households (185 persons) lose from

10 to under 30% their agricultural land area, 23 households (115 persons) lose

from 30 to under 70% their agricultural land and 7 households (35 persons) lose

over 70% their agricultural land.

- 19 households (95 persons) lose 10% or more area of agricultural land and shall

be displaced.

- 79 vulnerable households include: 46 female-headed households, 5 poverty

households (based on Government’s regulations), 01 disabled household and 27

households without land

- 118 households were temporarily affected by construction activities of the

subproject. During subproject implementation, the contractors will attempt to

minimize the temporary impacts caused by land acquisition of the subproject.

- 01 business household was affected a part of land area by construction activities

of the subproject

11. The summary of affected households by severity and vunaribility is shown at Table 2

below

Table 2: Summary of affected households

No

Ward/commune Number of AHs

Number of Aps

Number of

severely affected househo

lds

Households with Loss 10% of

agricultural land

Number of

displaced

households

Number of

vulnerable

households

10 - <30%

30 - <70%

More than 70%

I Cai Lay town 59 273 30 10 3 5 22 13

1 Thanh Hoa commune

20 84 7 2 2 - 5 3

2 Tan Binh commune

14 70 5 2 - - 4 2

3 Ward no.2 25 119 18 6 1 5 13 8 II Cai Lay district 184 871 70 27 20 2 30 66

1 Cam Son commune

26 141 10 4 4 2 1 8

2 Hoi Xuan commune

35 156 7 4 3 - 1 6

3 Hiep Duc commune

21 92 4 2 - - 2 11

Page 10: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

10 | P a g e

4 Phu An commune

76 361 36 9 11 - 21 34

5 Binh Phu commune

26 121 13 8 2 - 5 7

III Cai Be district 4 15 - - - - - -

1 Dong Hoa Hiep commune

4 15 - - - - - -

Total 247 1,159 100 37 23 7 52 79

Notes: 19 households lose 10% and more agricultural land holding and have to relocate.

Figure 1: Location map of project– red points are location of sewers

12. An updated Resettlement Plan for this subproject was prepared and concurred by Tien

Giang PPC, CPO on behalf of MARD, and ADB in August, 2016.

13. The tasks of compensation, support and resettlement for

organizations/individuals/households affected by land acquisition of subproject, have

been carried out by LDFC of Cai Lay town, Cai Lay and Cai Be districts, and Tien Giang

province.

14. 2. Subproject “Rehabilitation and upgrading for the flood drainage and irrigation

system to the Dong Thap Muoi region, Dong Thap province – Cai Cai channel

works”.

Page 11: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

11 | P a g e

15. Total households affected by construction works of subproject are 153 households (632

populations). Details on affected households are as follows:

- Impacts on land: Total permanently acquired land area is 136,156.2 m2, in which,

135,517.9m2 is agricultural land and 638.3m2 is residential. There are about 63,000 m2

land area would be affected temporarily at disposal site No.4. 55 households (233

persons) are acquired land permanently, in which, 51 households (222 persons) lose

their agrilcultural land, 3 households (10 persons) lose both agricultural and residential

lands, 1 household lose residential land only (1 person).

Table 3: The types of land affected by construction activities of the subproject

No Commune Agricultural land Residential land Total

1 Thông Bình 54,725.9 60.0 54,785.9

2 Tân Thành A 78,072.9 - 78,072.9

3 Tân Phước 2,719.1 538.9 3,297.4

Total 135,517.9 638.3 136,156.2

- Impacts on houses and shelters: 87 affected households (324 persons) located at

disposal site of soil no.4 in Tan Phuoc commune, shall be relocated temporarily at

another place during project implementation. After project completed, such households

would come back and rebuild their houses. 4 households located at bridge Ca Thap 2

and Ca Thap 3 shall be relocated to other places (3 out of 4 those households relocate

in resettlement area, 01 household resettles on the rest of their land area. 8 households

(34 persons), who located near construction area, could be affected by vibration due to

construction activities. Those 8 households will be received financial support for house

reinforcement.

- Impacts on structures on land: there are 682.41 m2 area of structural works on land of 36

households (148 persons) are affected, including 120.81 m2 kitchen area, 106.5 m2

stable area, 455.05 m2 area of other structural works (for example: bathrooms, toilets,

ditchs, etc); 56 graves of 15 affected households need to be relocated.

- Impacts on crops, trees: The subproject impacts on 2,050 perennial trees of 31

households, including 280 fruit trees and 1,670 timber trees

- Severely affected households: 114 households (501 persons), in which 36 households

(165 persons) lose 10% or more production land, 04 households (14 persons) must

relocate and 75 households (324 persons) temporarily relocate their houses. 01

household (1 person) lose 10% or more agriculture land and must relocate permanently.

- All affected households are Kinh ethnic.

16. 12 households (52 persons) are in vulnerable group, in which 10 households (44

Page 12: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

12 | P a g e

persons) belong to poverty group and 2 households belong to near-poor group1

17. An updated RP plan has been prepared and approved by Dong Thap PPCs, CPO (on

behalf of MARD), and ADB in September 2016.

18. Tasks of compensation, support and resettlement for organizations, individuals and

households affected by land acquisition of the subproject are being carried out by LFDC,

Tan Hong district, Dong Thap province.

Figure 2: Location map of the project– Cai Cai channel works

1 According to Vietnam GoV’s regulation, poverty threshold during 2016-2020 is below 700,000

VND/person/month and below 900,000 VND/person/month for rural area and urban area respectively.

Near-poor threshold varies from 700,000 to 1,000,000 VND/person/month for rural area and from 900,000 to

1,300,000 VND/person/month for urban area.

Page 13: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

13 | P a g e

III. TARGET OF THE ASSIGNMENT AND SCOPE OF WORK

3.1. Target of the Assignment

19. Target of independent monotoring for resettlement is to assess compliance with the

rules, regulations and requirements mentioned in the RP/uRP/RDD. Specifically:

- Identify and evaluate the payment of compensation, support and resettlement for

affected people as well as the process of community consultation and information

disclosure and grievance redress procedure of projects have been carried out in

accordance with principles, requirements and procedures have been presented in

the RPs/uRPs;

- Consider whether the objectives of the updated resettlement plan, specifically

livelihood of affected people has been improved or at least restored or not;

- Consider exist problems of the processes of updating the RPs and propose the

solutions to solve such problems to the implementing agencies.

3.2. Scope of work

20. Regarding to independent monitoring, IMO will carry out the following activities:

- Periodic Monitoring: IMO will carry out periodic monitoring with frequency 2 times

per year depending on the progress of updating the RPs, therefore, specific

schedule of periodic monitorings may be due to the CPO/ CPMU mobilization.

- Evaluate after resettlement: Six months (06) after the completion of implementation

of the RPs of the entire project, IMO will conduct post evaluation to assess results

of resettlement implementation and the impact of resettlement to the affected

households by the sub-projects.

- Join the ADB’s monitoring group with CPMU, upon request.

21. 3rd Independent Resettlement Monitoring Report has been prepared to carry out

objectives above and this monitoring mission focused on two sub-projects (1)

“Construction of flood controlling system in Ba Rai – Phu An region, Tien Giang

province” and (2) “Rehabilitation and upgrading for the flood drainage and irrigation

system to the Dong Thap Muoi region - Cai Cai channel works” during the period of RP

implementation till 30 November, 2016

22. Monitoring indicators: According to TOR, independent monitoring consultant shall review

the compliance during updated resettlement plan and implementation phases. For

details, please see in the following table.

Table 4: Indicators for Monitoring

Page 14: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

14 | P a g e

Monitoring

requirement Monitoring Indicators

1

Monitoring the

implementation of

DMS of affected

properties

� Whether or not land and affected properties are measured

accurately

� Whether or not affected households are invited to

participate in DMS process and sign in the minute of DMS

for their affected assets

� Whether or not grievances and questions of affected

household relating to DMS are addressed promptly and

satisfactorily

2

Monitoring the

compensation and

other supports by cash

� Compensation for affected land: if applying the form of

compensation is land for land, whether or not replacement

land will equal to the area and location as well as

production condition with affected land. If applying the form

of compensation is cash for land, whether or not ensuring

replacement cost.

� Whether or not compensation for affected works are equal

to the replacement cost of construction materials and labor

cost that built affected works, not exclude the old materials

utilized

� Whether or not compensation for trees/crops is equal to

market price.

� Whether or not applying and calculating properly the

compensation and supports as mentioned in RP/uRP to the

affected households;

� Compensation payment to affected households is complete

before civil work commencement and is paid one time or

many times.

3

Monitoring the

implementation of

community

consultation and

disclosure

� Whether or not project documents are provided to the

community (RF, RP, project brochures and other relevant

documents).

� Whether or not the information is disclosed in public places

(prices, paymentV.)

� Affected households must be consulted their ideals on land

acquistion, compensation policies, resettlement, restoration

of living standards as well as the way to access grievance

redress mechanism

Page 15: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

15 | P a g e

Monitoring

requirement Monitoring Indicators

� How issues, proposals, etcV of affected household during

resettlement implementation phase were solved

4

Monitoring the

resettlement of

affected households

� Verify the living conditions, income generation in

resettlement area and infrastructure condition such as road,

electricity, water supply/drainage systemV), livelihood

� Plan and implementation of relocation: consulting on the

resettlement plan with relocation households, implementing

and publicizing relocation plan, and providing support to the

relocation households

� Life and production stabilization of affected households after

resettlement

5

Monitoring the income

restoration, and

supports for stable life

� Whether or not the supports for income restoration such as

training, credit support provided to severely affected

households

� Identify issues that affected households have to face during

income restoration and life stabilization

6

Monitoring and assess

the level of sastifaction

of affected households

� The level of sastisfaction of inventory minutes of damaged

properties

� The level of sastisfaction of disclosure, community

consultation

� The level of sastisfaction of support, compensation

� The level of sastisfaction of supports for stable life and

income restoration

� The level of sastisfaction of new resettlement area

7 Grievance Redress

� A grievance redress mechanism is functional.

� Number of complaints and the natures of complaints on the

implementation of the uRP and land acquisition

� Number of solved complaints and satisfactions of the HHs on

resolving of complaints

Page 16: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

#3 PERIODIC REPORT

16 | P a g e

Monitoring

requirement Monitoring Indicators

Link between

resettlement plan

implementation and

construction progress

� Construction of works will be started when the land

acquisition and resettlement activities are complete

(compensation, support and relocation)

� All issues relating to project work items should be addressed

before starting such work items

� The income restoration programs should be set up before

civil work commencement

Monitoring Gender and

ethnic minority issues

� Number of participations of women in land acquisition and

resettlement activities; the impacts of land acquisition and

resettlement that affecte the livelihoods of women; issues

ofwomen’s income restoration.

� Consult ideal and inform to the affected ethnic minority

households and community (if any); measures had been

taken to avoid, minimize the adverse impacts of land

acquisition for local minority communities; complaints and

grievancesof ethnic minority households; issues of income

restoration for the affected ethnic minority households.

23. These monitoring indicators were specified through questions in survey forms and/or in-

depth interview, group discussion.

Page 17: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

17 | P a g e

IV. APPROACH AND METHODOLOGIES OF MONITORING IMPLEMENTATION

4.1. Approach

24. This approach requests the participation of community in the resettlement monitoring.

Following, the affected people were participated in monitoring process such as:

interviews, group discussions, visit the site of affected area with monitoring specialists.

Representative of CPO, PPMU and LFDCs, the affected commune People Committee

have also participated in monitoring process by the interviews and group discussions

with monitoring specialists.

4.2. Methodologies of monitoring implementation

25. In 3rd Periodic Monitoring Mission, following methods were applied:

26. Desk review

- IMO has collected documents and data that related to compensation and

resettlement of the subproject for the review, analysis and assessment. The

documents and data were collected from following sources:

+ CPO documents

+ Tien Giang PPMU documents; LFDCs of Cai Lay town, Cai Lay district and Cai

Be district; Ward/Commune PCs of Ba Rai – Phu An subproject: (1) Cai Lay town:

Ward no.2 PC, Thanh Hoa commune PC and Tan Binh district, (2) Cai Lay district:

Cam Son, Hoi Xuan, Hiep Duc, Phu An, Binh Phu commune PC, (3) Cai Be district:

Dong Hoa Hiep commune PC.

+ Dong Thap PPMU documents, LFDCs of Tan Hong district and documents of

commune PCs in subproject area of Cai Cai channel include: Thong Binh, Tan

Thanh A and Tan Phuoc commune.

+ The documents include: (i) RF, RP, updated RP (August - September, 2016) and

memorandums provided by CPO; (ii) reports, RP implementation documents of Tien

Giang PPMU; Dong Thap PPMU;(iii) documents provided by LFDCs of Cai Lay

town, Cai Lay district and Cai Be district (Tien Giang) and Tan Hong district (Dong

Thap), (decisions, reports on compensation and resettlement, minutes of inspection

inventory minutes,etc,V); (iv) policies of ADB, GoV and Tien Giang PPC and Dong

Thap PPC.

- IMO studied project documents and some other documents that are collected on

the field at the office (through form of hard copies and soft copies). The purposes of

this researchs are: (1) to study the process, regulations were proposed and

approved from project document, (2) to study the plans of compensation and

assistances for components of the Thuong Thoi Tien sub-project (3) to view field

reports and internal monitoring reports, (4) to study the actual processes have been

and will be carried out at sub-project’area.

27. Qualitative methods. IMO used the following qualitative methods in monitoring process

Page 18: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

18 | P a g e

for resettlement:

- Consultation, in-depth interview and group discussion with stakeholders,

implementing agencies, social organizations. Minutes of work are attached to the

Report at Appendix 1.

- Group discussion, in-depth interview with affected households (severely affected

households, displaced households, vulnerable households)

- Site inspection for the areas where the households have handed over the land to

contractor of two subprojects Ba Rai – Phu An and Cai Cai channel work. Besides,

temporary resettlement area also has been inspected in order to identify

difficultiesand potential adverse impacts for local people living in the resettlement

area during construction process.

28. Quantitative method. Beside the qualitative methods mentioned above, the quantitative

method also was used to carry out independent monitoring for resettlement:

- Household Survey using questionnaire with 100% of total severely affected

households and 20% of total slightly affected households (equivalent to about 247

households). In which the number of surveyed households of the subproject Ba Rai

– Phu An is 135 households and of the subproject Cai Cai Cannal is 114

households. List of interviewed households is shown at Appendix 2 of the Report.

- Use available statistical data at communes and District LDFC.

29. Data processing methods: Collected data and informantion from the field were

analyzed on the dedicated software such as SPSS (quantitative) and NVIVO

(qualitative). These parameters were used in monitoring report.

30. Writing report: Analyzed data and information has been synthesized and stored in

resettlement database folder. They were used as a basisline for the first periodic report

meeing requirements in the TOR.

4.3. Implementation arrangement:

31. Based on Official letter dated 1st October 2016 for mobilizing CPO’s monitoring

specialist, VIWASE had moblized a monitoring team including 4 specialists (01 leader,

01 resettlement specialist, 01 community development specialist, 01 gender/ethnic

minority specialist) and 2 supporting staffs for the implementation of monitoring mission.

The preparation for monitoring phase has been carried outimmediately after CPO’s

Official letter sent to. In VIWASE’s office, the specialist of monitoring team has prepared

monitoring tools including the guide documents for in-depth interviews and group

discussions, updated RP and other documents relating to land acquisition and

compensation of Project. Site monitoringfor implementing land acquisition and

compensationhas been started from 15 to 30 November 2016 on two subproject areas.

32. Monitoring consultant worked with Commune/ward PCs, village heads, 100% severely

affected households to participate in group discussions and individual interviews. The

Page 19: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

19 | P a g e

monitoring specialists of VIWASE conducted 12 group discussions to the affected

persons in 12 communes/wards (there were 244 participants); interviewed leaders and

officers of LFDCs of Cai Lay district, Cai Lay town and Cai Be district (Tien Giang) and

Tan Hong district (Dong Thap), interviewed Chairman/Deputy chairman CPCs, cadastral

officers and directly participated and supervised compensation, support and resettlement

in commune areas thereby gathering necessary information and people’s opinion as well

as complaints if any.

33. After finishing field monitoring, the monitoring team with the support of office staffs had

synthesized results of field monitoring and established a meeting with Tien Giang PPMU

and District and Town PCs and LFDCs of Cai Lay town, Cai Lay, Cai Be district, and a

meeting with Dong Thap PPMU, Tan Hong DPC, and Tan Hong LFDC to inform

preliminary monitoring result. In the meeting, Leader of monitoring team presented

feedbacks of affected persons and the outstanding issues need to be resolved (detail

see in the Section “oustanding issues”.

V. MONITORING RESULTS

5.1. Results of Desk review

34. Subproject “Construction of flood controlling system in Ba Rai – Phu An region, Tien

Giang province” located in Cai Lay, Cai Be districts and Cai Lay town. Tien Giang PMU

cooperates with LDFC of Cai Lay town, Cai Lay and Cai Be districts to implement land

acquisition and resettlement for the subproject “Construction of flood controlling system

in Ba Rai – Phu An region, Tien Giang province“.

35. Subproject “Rehabilitation and upgrading for the flood drainage and irrigation system to

the Dong Thap Muoi region - Cai Cai channel works” are implemented in three

communes (Thong Binh, Tan Thanh A and Tan Phuoc) of Tan Hong district, Dong Thap

province. Dong Thap PPMU has coordinated with Tan Hong DLFDC to implement land

acquisition andresettlement for the subproject “Rehabilitation and upgrading for the flood

drainage and irrigation system to the Dong Thap Muoi region - Cai Cai channel works”.

36. Generally, land acquisition and resettlement procedures for two subprojects have been

implemented as stipulated in Decree No. 43/2014/ND-CP dated 15, May, 2014 and the

uRP of sub-project. Data of detailed measurement surveys, inventory and compensation

are stored at LFDCs of project district/town and Tien Giang PPMU under the forms of

document and computer database. A copy of minutes of inventory of loss with sufficient

signatures of the participants and heads of the households has been given to each

affected household. Plans of compensation, support and resettlement of subproject

“Construction of flood controlling system in Ba Rai – Phu An region, Tien Giang

province” have been approved in:

(1) Decision no.2183/QD-UBND dated 16 May, 2016 of Cai Lay town PC (For detail,

see Appendix 5);

(2) Decision no. 3067/QD-UBND dated 16 May, 2016 of Cai Lay DPC (For detail, see

Page 20: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

20 | P a g e

at Appendix 6) and

(3) Decision no.4232/QD-UBND dated 1 June, 2016 of Cai Be DPC (For detail, see

Appendix 7).

Plan of compensation, support and resettlement of subproject “Rehabilitation and

upgrading for the flood drainage and irrigation system to the Dong Thap Muoi region -

Cai Cai channel works” has been approved by Decision no.805/QD-UBND.HC dated 10

August 2016 of Tan Hong DPC (detail see at F – Appendix 8)

37. The public disclosure of decisions approving on compensation, support and resettlement

of two subprojects has been carried out in relevant communes/wards, the draft

compensation plan, compensation and assistance values were temporarily calculated for

individual households. District LDFC coordinates with ward/commune PCs to set up a

meeting in order to inform draft compensation plans, compensation and assistance

values to affected households. It took about two weeks for carrying out the public

disclosure. Ward/commune PCs and LFDC confirmed the period finising public posting

and received people’s opinion and complaints if any. After finishing the period of public

posting, if ward/commune PCs and LFDC had received any opinion and complaints of

people, the LFDC would finalize plans and submit it to DONRE and Provincial PC for

approval. In the case araising people’s opinions/complaints, LFDC would coordinate with

ward/commune PC in project area for adjustment and resolving (if complaints are

correct). After that, the LFDC would finalize plans and carry out the next steps for

approval as mentioned above. The minutes of disclosing compensation plans and

detailed compensation plan were shown in details in the following Appendixes:

Appendix 9: Minutes of disclosing the draft compensation and temporary value for

affected households

Appendix 10: Minutes of public posting of compensation and temporary value for

affected households

Appendix11: Minutes of confirmation for finishing the period of public posting on draft

compensation and temporary value for affected households

Appendix 12: Detail compensation plan for each affected households

38. Regarding the compensation, support and resettlement plan: the approved

compensation, support and resettlement plans of both Ba Rai - Phu An sub-project and

Cai Cai canal have followed the principles and requirements as in the RP’s entitlement

matrix. However, due to the long time of RP (2010), there are the changes in policy and

applied unit prices. All changes in scales, affected level, policies and unit prices at the

time of land acquisition were shown in the uRP. Accordingly, for the Cai Cai canal

subproject - the compensation and resettlement plan approved by the People's

Committee of Tan Hong district has followed the policies in the uRP's entitlement matrix.

For Ba Rai-Phu An subproject, compensation, support and resettlement plans approved

Page 21: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

21 | P a g e

by Cai Lay Town People's Committee, Cai Lay District People's Committee and Cai Be

DPCs were followed the principles of resettlement implementation process, requirements

for compensation land price, for compensation of affected assets which used market unit

price at the time of land acquisition in uRP.

39. For calculating support allowances such as life and production stabilization, support for

income restoration, support for vulnerable people, it takes time to verify the eligible

affected people, the rate of land loss of each household, to get the opinions of the

households on income restoration program, therefore, People's Committees of districts

and towns had the strategy to divide plans into different periods.

40. The policy for the support program has also been announced to the affected people

during the project preparation process, during implementation process in consultation

meetings to disseminate information of project, in consultation meetings on

compensation and resettlement assistance plans.

41. Accordingly, the approved resettlement compensation plan of People's Committees of

Cai Lay District, Cai Lay Town, Cai Be District includes the entire compensation plan,

support for land, assets on land, support for relocation and resettlement, support for job

change and creation, and livelihood support for households whose the production land

loss rate have already been determined. Support programs for AHs are being

implemented by the LFDCs and submit to DPC.

42. According to the report of Tien Giang PMU of Reta subprojects and LDFC of Cai Lay

district, Cai Lay town and Cai Be district, compensation, support and resettlement of the

subproject Ba Rai – Phu An till 30 November, 2016 has been carried out as following:

- Total households affected by subproject: 247 households. Those households

shall be acquired land for the construction of 28 sewers on 9 wards/communes of

Cai Lay town, Cai Lay district and Cai Be district.

- The number of affected households has received compensation, support and

resettlement: 126 households located in Cai Lay town and Cai Lay district and 04

temporarily affected households in Cai Be district.

- The areas where compensation, support and resettlement has been completed

already: 13 sewers belonged to wards/commune: Hiep Duc, Hoi Xuan, Cam Son,

Phu An (Cai Lay district), Thanh Hoa and Tan Binh (Cai Lay town) and Dong

Hoa Hiep (Cai Be district). Details on wards/communes are as following:

Table 5. Status of Site Clearance of Ba Rai – Phu Ansubproject

No Ward/commune Items with completion of compensation, support and resettlement

Items without completion of compensation, support and resettlement

I. Cai Lay district

Page 22: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

22 | P a g e

1 Hiep Duc commune Cay Sung, Cai Na and Giong Tre sewer

2 Hoi Xuan commune Khang Chien, Ba Gon, Hai Hue and Thay Thanh sewer

3 Cam Son commune Thay Thanh and Ong Bang sewer

Tham Rom and Ong Kham sewer

4 Phu An commune Thong Luu sewer Cống Bờ Keo, cống Rạch Rồng, cống Ranh Làng, cống Ấp 2, cống Đồng Sao-Cả Nứa

5 Binh Phu commune Giong Tre 1, Dap Chua, Rach Giong, Cay Me and Lo Hoa Thuong sewer

II Cai Lay town

1 Thanh Hoa commune

Cống Cả Chát, cống Cả Nứa 30 June sewer

2 Tan Binh commune Khach Minh and Lo Lang sewer

3 Ward no.2 Hai Liem, Kenh Dung and 30 June sewer

III Cai Be district

1 Dong Hiep Hoa Giong Tre 2 sewer

Note:

1. Giong Tre 2 sewer located in area of two communes Hiep Duc (Cai Lay district) and

Dong Hoa Hiep (Cai Be district)

2. Thay Thanh sewer located in area of two communes Hoi Xuan and Cam Son (Cai Lay district).

43. Total amount paid for affected households was 26.204.766.000 VND out of

54.394.096.000 VND. In which, the amount paid for affected households in Cai Lay

town was 14.060.000.000 VND/18.968.556.000 VND and for affected households in

Cai Lay District was 12.144.766.000 VND/35.425.540.000 VND.

44. The implementation of compensation, support, resettlement of Dong Thap PPMU and

Tan Hong DLFDC for subproject “Rehabilitation and upgrading for the flood drainage

and irrigation system to the Dong Thap Muoi region - Cai Cai channel works” till 30

Nomvember, 2016 has been carried out as following:

- Total households affected by the subproject: 153 households belong to three

communes Thong Binh, Tan Thanh A and Tan Phuoc, Tan Hong district

- Affected area includes: Plot no.1 (Thong Binh commune), plot no.2, plot no.3, At Bo

sewer, Ba Hai Mot sewer, Bay Thua sewer (Tan Thanh A commune), plot no.4, Ca

Trap 1, Ca Trap 2 bridges and Nga Tu sewer (Tan Phuoc commune).

- The number of households has been received compensation, support, and

resettlement: 145/153 households

- Areas with completion of compensation, support and resettlement are shown at Table

below:

Page 23: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

23 | P a g e

Table 6.Status of Site Clearance of Cai Cai channel subproject

No Ward/commune Items with completion of compensation, support and resettlement

Items without completion of compensation, support and resettlement

1 Thong Binh Plot no.1

2 Tan Thanh A Plot no.2

Plot no.3

At Bo sewer

Ba Hai Mot sewer

Bay Thua sewer

3 Tan Phuoc Ca Trap III bridge Plot no.4

Ca Trap II bridge

Nga Tu sewer

45. The area where the compensation, support and resettlement assistance have not been

complete was plot no 4 in Tan Phuoc Ward. Among 83 affected households in plot no

4, 75 households received compensation, support and resettlement cash and are

constructing their houses on the temporary resettlement area, the 8 remaining

households have been not received compensation, support and resettlement cash

because theses households requested compensation, support to relocate their houses

away from plot 4 as 75 household mentioned above. These households include:

1. Pham Anh Dung

2. Tran Van Phu

3. Nguyen Van Dung

4. Tran Buu Tai

5. Pham Thi Diem

6. Lam Thi Thu

7. Nguyen Thi Duyen

8. Tran Thi Hanh

46. According to the results of work between the monitoring consultant and the People's

Committee of Tan Phuoc Commune, Center for Land Development in Tan Hong

District, these 8 households are households with relatively stable builders and do not

want to move temporarily. Therefore, during the preparation of the compensation,

Page 24: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

24 | P a g e

support and resettlement plan for the subproject, these households did not want to

relocate and offered to get in cash support to strengthen the house. However, when the

Tan Hong district land fund disclosed the compensation and assistance plan and paid

for the AHs, these 8 households requested to have cash assistance to relocate as

other households living in same land area No. 4. After receiveing such request of

stated above 8 households, the People's Committee of Tan Hong district has directed

the LFDC of Tan Hong district in coordination with the Tan Phuoc CPC to invite these

households to CPC office to dialog. As a result, 6 households (including Tran Van

Phuc, Tran Buu Tai, Tran Thi Hanh, Pham Thi Diem, Pham Anh Dung and Nguyen Van

Dung) agreed to receive cash support for house and assiatance for life stabilization

(rice support) according to approved policy; Such households require competent

authorities to consider to provide additional support for solid fencing around the home

and if during the construction process, the house are collapsed, the competent

authority should consider compensation, support as prescribed. The remaining two

households (including Nguyen Thi Duyen, Lam Thi Thu): requested the state to

compensate and relocate the house becasue they are afraid of collapse. From the

requirements of these 8 households, Tan Hong LFDC and the Tan Phuoc CPC agreed

to submit to the Tan Hong DPC to consider the requests of households. (Annex 12-

Minutes of working between these 8 households with Tan Hong District LFDC and Tan

Phuoc CPC).

47. Tien Giang and Dong Thap PPMUs have assigned a staff in charge of resettlement-

compensation accompanying with compensation council/LFDC in subproject area to

carry out compensation and Clearance. This staff has worked at the site to receive and

respond to the affected people’s queries. By doing this, the Tien Giang and Dong Thap

PPMU have been proactive in implementing resettlement, land acquisition, site

clearance, and resolves the complaints timely

5.2. Results of site monitoring

5.2.1. Information disclosure and public consultation

48. Information that related to land acquisition, compensation, assistances and resettlement

was provided sufficiently to the affected households and communities by effective

manners such as publicly posted at the commune/ward, project leaflets sent to AHs,

public consultation meeting:

49. For Bai Rai -Phu An subproject, the information providing for affected people includes:

- Project documents, regulations related to the compensation, support and resetlement

of the subproject (Policies of the project, law, regulations of Vietnam gorverment,

current regulations of Tien Giang People's Committee at the time of the RP and at the

present time); were provided;

- The information such as results of DMS, draft compensation plan which was updated

unit price for compensation, support and resettlement, and current policies of the

Page 25: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

25 | P a g e

government and Tien Giang People's Committee) was adopted in public consultations

and posted publicly at the commune/ward People's Committee for consultation with

APs. Information on livelihoods support programs, vulnerability assistance and

livelihood restoration programs were also reported to villagers and were further

publicized and informed to individual households through local consultation meetings.;

50. For Cai Cai Canal sub-project: Information provided to AHs in community consultations

also includes project policies, current regulations of the Government, of Dong Thap

Provincial People's Committee and the updated draft compensation, support and

resettlement plan according to the project policy (updated according to the draft

Resettlement Plan).

- Consultation with the affected households about land acquisition, compensation

policies, support and relocation, livelihood restoration program and grievance redress

procedure

51. The opinions, suggestions and concerns of the affected households and communities

were addressed in the process of land acquisition, compensation, assistances and

resettlement. Local people actively participated in the related activities. The numbers of

participants of the consultative meetings are presented in the Table 7 and 8 below.

Table 7: Consultation meetings conducted for Ba Rai –Phu An subproject

Content of consultation

meetings Location Time

Participant

Male Female Total

Consultation on goals and resettlement policies

Thanh Hoa 5/2015 11 8 19 Tan Binh 5/2015 7 7 14 Ward 2 5/2015 18 10 28 Cam Son 5/2015 12 14 26 Hoi Xuan 5/2015 20 15 35 Hiep Duc 5/2015 9 12 21 Phu An 5/2015 45 31 76 Binh Phu 5/2015 14 12 26 Đong Hoa Hiep 5/2015 3 1 4

Consultation on compensation, support and resettlement

Thanh Hoa 9/2015 11 8 19 Tan Binh 9/2015 7 7 14 Ward 2 9/2015 18 10 28 Cam Son 9/2015 12 14 26 Hoi Xuan 9/2015 20 15 35 Hiep Duc 9/2015 9 12 21 Phu An 9/2015 45 31 76 Binh Phu 9/2015 14 12 26 Đong Hoa Hiep Sep./2015 3 1 4

Consultation on income restoration program

Thanh Hoa Oct./2015 6 5 11 Tan Binh Oct./2015 3 4 7 Ward 2 Oct./2015 12 8 20 Cam Son Oct./2015 8 8 16

Page 26: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

26 | P a g e

Content of consultation

meetings Location Time

Participant

Male Female Total

Hoi Xuan Oct./2015 7 5 12 Hiep Duc Oct./2015 8 5 13 Phu An Oct./2015 26 19 45 Binh Phu Oct./2015 10 6 16

Consultation on draft compensation plan, support and resettlement

Thanh Hoa Jan./2016 11 8 19 Tan Binh Jan./2016 7 7 14 Ward 2 Jan./2016 18 10 28 Cam Son Jan./2016 12 14 26 Hoi Xuan Jan./2016 20 15 35 Hiep Duc Jan./2016 9 12 21 Phu An Jan./2016 45 31 76 Binh Phu Jan./2016 14 12 26 Đong Hoa Hiep Jan./2016 3

1 4

Cai Lậy town 8/Aug./2016

6

0 6

Table 8: Numbers of Cai Cai channel works Meeting Participants

Content of consultation

Location Time Participant

Male Female Total

Consultation before conducting DMS

Provincial PMU office

April/2014 6

6 Tan Hong DPC April/2014 8 8 Thong Binh commune

April/2014 22 9

31 Tan Thanh A commune

April/2014 24 13

37 Tan Phuoc commune

April/2014 35 15

50

Consultation after conducting DMS

Provincial PMU office

April/2014 8 - 8

Tan Hong DPC March/2015 12 - 12 Thong Binh commune

March/2015 23 7 30

Tan Thanh Acommune

March/2015-April/2015

38 17 55

Tan Phuoc commune

March/2014 12 10 22

Consultation on compensation plan and resettlement

Provincial PMU office

July/2015 7 - 7

Tan Hong DPC July/2015 10 - 10 Thong Binh commune

July/2015 30 21

51

Page 27: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

27 | P a g e

The rate of women participants in the meeting of the subproject Ba Rai – Phu An and

subproject Cai Cai channel works respectively is 43.67% and 30.4%.

52. The results of surveying households by questionnaireshow that: 100% respondents said

that Project information, policies, options and entitlements for compensation, assistance

and resettlement were provided to AHs during these meetings and posted at public area.

Besides, information on project implementation and preparation, affected scope,

implementation plan, current laws/policies of Vietnam Govement and Donor’s safeguard

policies also were provided to Ahs through meetings. By this way, AHs have aware of

their rights. Results obtained from focus group discussion and interviews with officers

indicated that the cooperation between local relevant stakeholders and updated

resettlement plan consultants to carry out the public consultation, and disclosure

information of the project. In general, the public consultation process and content of both

the Ba Ra- Phu Rai and Cai Cai canals were implemented in accordance with the

updated project policy in the uRP benefits matrix, satisfied the regulations of Vietnam

and also conformity to with the requirements of the approved resettlement documents

and the ADB Safety Policy Declaration (SPS, 2009).

5.2.2 Detailed Measurement Survey (DMS) of affected assets

53. Detailed Measurement Survey (DMS) of affected assetshas been carried out in line with

Government’s regulations. DMS of subproject Ba Rai-Phu An has been completed in

January, 2015. DMS of subproject Cai Cai channel works has been completed in

January, 2014. The form was completed by the households presenting all the affected

lands and assets of the household and with signatures of husband and wife (Appendix

14 and Appendix 15). Afterthat, District/town LFDC conducted the detailed

measurements to verify the impacts for the households with participations of the heads

of the households, village leaders, organizations and PPMU. At the same time, LFDC

also coordinated with ward/commune PC to identify origin of land and affected

properties.

54. After DMS completion, LFDC prepared a draft compensation plan and estimated amount

for individual affected assets of each AHs. Information on draft compensation and

estimated amount announced to AHs through official meetings and a hard copy of draft

compensation and estimated amount would be given to AHs. After meetings, draft

compensation and estimated amount also was disclosed publicly at public areas

(ward/commune office, street, hamlet). In consultation meetings, AHs’ queries and

Tan Thanh A commune

July/2015 50 23

73 Tan Phuoc commune

July/2015 60 34

94

Consultation with displaced households

Tan Phuoc commune’s conference hall

26/August/2016 23 8

31 26/ August/2016 12 9 21

Page 28: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

28 | P a g e

complaints on DMS and draft compensation plan would be cleared. People’s option

would be recorded and integrated into final compensation plan before it was approved by

DPC.

55. According to the survey results, which were investigated by household questionnaires,

showed that:

- 100% respondents said they attended to the DMS process to measure the properties

affected and signed minutes of loss inventory and kept a copy of minute of loss inventory

and disclosed document with full signature of the participants.

- Results from household survey and interview of staff CPC show that there are some

AHs’ opinions on DMS. Those opinions have been solved by District/town LFDC and

Commune PCs. For example: Subproject Ba Rai – Phu An: Mrs. Pham Thi Nguyet (Hoi

Xuan commune) requested to resurvey the clearance milestone because its location is

too close with pigsty so this activity would affect livestock of her household. Another

opinion arising in DMS process, there was a new stone-grave two years ago of Mr. Tran

Van Giau household. This grave would be lost a part according to the marks of land

acquisition. Therefore, Mr.Tran Van Giau household proposed to adjust the scope of

land acquisition to avoid the impact on the grave

56. The implementation of DMS for two subprojects was consistent with national laws and

regulations. The process of carrying out DMS was also conformity to requirements of the

approved resettlement documents and the SPS, 2009.

5.2.3 Compensation plans

57. The detailed compensation plans made based on the entitlements and resettlement

policies proposed in uRP that were the reconcilation between the legal documents of the

Government of Vietnam, decisions of Tien Giang PPC, Dong Thap PPC on

compensation, support, resettlement and ADB’s safeguard policies. Regarding the

approval of compensation, support and resettlement plans of subprojects, in order to

satisfy the progress of the project, the People's Committees of districts/towns had

approved the compensation, support and resettlement regime for sub-projects before

the updated resettlement plan was approved by ADB. However, this regime was in

accordance with the project policy. Specifically, the LAR implementation of the Cai Cai

canal subproject and Ba Rai-Phu An subproject, has followed the principles of

compensation price, policies and regulations on compensation, support and resettlement

of government, of PPC mentioned in the updated resettlement plan. Particularly for such

ADB policy support programs as mentioned in the entitlement matrix of the updated RP,

the relevant stakeholders including Tien Giang PPMU, Cai Lay DPC, Cai Lay town PC,

Cai Be District, Đồng Tháp PPMU, Tan Hong DPC all agreed that in the next round this

plan was also disseminated to the public through community consultation meetings.

Accordingly, the policies and regulations used in land acquisition and resettlement for

two sub-projects are as follows:

Page 29: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

29 | P a g e

Vietnam GoV’s regulations

- Land Law dated 29/11/2013

- Decree 43/2014/ND-CP, dated 15/5/2014 of the Government regulated in detail

some regulations of Law on land;

- Decree 47/2014 / ND-CP dated 05/15/2014 of the Government regulations on

compensation, support and resettlement when the State recovers land/TT-BTNMT

dated 30 June, 2016 of MONRE regulated in detail on compensation, support and

resettlement when the State acquires land

- Circular no.37/2014

Tien Giang PPC’s regulation

- Decision No. 40/2014/QD-UBND dated 12/16/2014 of People's Committee of Tien

Giang province issued regulations on compensation, support and resettlement

when the State acquires land in Tien Giang province.

- Decision No.44/2015/QD-UBND dated 21/12/2015 of People's Committee of Tien

Giang province issued the prices for various land types in the area of Tien Giang

province for the period 2016-2020.

- Decision No.350/QD-UBND dated 17/1/2016 of Tien Giang PPC for approval of

land compensation price to implement land acquisition and compensation for

subproject Ba Rai – Phu An.

- Decision No.18/2016/QD-UBND dated 20/4/2016 of Tien Giang PPC regulated on

amendment and supplement of the content of compensation, support and

resettlement when the State acquires land on Tien Giang PPC regulated in

Decision No.40/2014/QD-UBND dated 16 December, 2014 of Tien Giang PPC.

- Decision No.05/2015/QD-UBND dated 02/9/2015 Tien Giang provincial regulations

on damage compensation unit prices of fruit, vegetables and aquatic animals when

the State acquires land.

- Decision No.29/2015/QD-UBND dated 09/04/2015 of Tien Giang Province People's

Committee issued the unit price of housing construction and common structures in

Tien Giang province area.

- Official letter no.1796/UBND-KTN dated 4/5/2016 of Tien Giang PPC regulated on

compensation and support for durian to implement land acquisition and

compensation for subproject Ba Rai – Phu An.

- Official Letter No.2966 dated 26/6/2014 of Tien Giang PPC regulated on specific

unit price for subproject “Upgrading the controlling system of saltwater intrusion in

Go Cong region, Tien Giang province”.

- Official Letter No.3654/UBND-KTN dated 4/8/2015 of Tien Giang PPC regulated on

Page 30: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

30 | P a g e

additional approval for policy of compensation, support and resettlement of

Subproject “Upgrading the controlling system of saltwater intrusion in Go Cong

region, Tien Giang province”.

Dong Thap PPC’s regulation

- Decision no.27/2014/QD-UBND dated 27/11/2014 of Dong Thap PPC issued

regulation on compensation, support and resettlement when the State acquires land

on Dong Thap province area

- Decision no.37/2016/QD-UBND dated 26/7/2016 of Dong Thap PPC regulated on

amendment and supplement of regulation on compensation, support and

resettlement when the State acquires land on Dong Thap province area

- Decision No.34/2014/QD-UBND of Dong Thap PPC dated 19/12/2014 issued the

regulation on table of land prices in Dong Thap province area every 05 years

(period 2015-2019).

- Decision No.16/2012/QD-UBND dated 12/06/2012 of Dong Thap PPC issued the

prices of housing and structure in Dong Thap province area.

- Decision No.36/2014/QD-UBND dated 25/12/2014 Dong Thap PPC regulated on

compensation prices for crops, aquatic, the grave relocation costs when the

Stateacquires land in Dong Thap province.

- Official Letter No.314/UBND-KTN dated 26/05/2016 of Dong Thap PPC regulated

on approving the replacement cost of sub-project Cai Cai canal works (phase 1)

and the level of support for vulnerable groups in subproject Plain of Reeds

58. For the Ba Rai – Phu An subproject: Base on legal documents mentioned above, LFDCs

of Cai Lay town, Cai Lay district and Cai Be district, Tien Giang province have prepared

the detailed compensation, support and resettlement plans and these plans have been

approved by Cai Lay town PC, Cai Lay and Cai Be DPCs according to Decision No.

2183/QD-UBND dated 16/5/2016; Decision No.3067/QD; and Decision No.4232/QD-

UBND dated 1/6/2016 respectively:

- Compensation for land

+ Compensation prices for various kinds of land have been approved specifically

for sub-project “Construction of flood controlling system in Ba Rai – Phu An

region, Tien Giang province” in Cai Lay town, Cai Lay district and Cai Be district

based on the results of the market price survey under Decision No.350/QD-

UBND dated 17/2/2016 issued by Tien Giang PPC. Compensation prices of

subproject Ba Rai – Phu An are higher than land prices stipulated periodically by

PPC. These prices have been updated in the updated RP August, 2016 of

subproject. Details of compensation prices for Cai Lay town, Cai Lay district and

Cai Be district are shown in the Table below:

Page 31: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

31 | P a g e

Cai Lay town area

Table 9: Compensation price of Subproject – Cai Lay town (unit: Dong per m2)

No Ward

/commune Name of

street/area/location

Land price under

Decision no. 44/2015

Compensation price according to

Decision No.350/QD-UBND

Perennial crop land 1 Tan Binh Khach Minh, Lo Lang sewer

KV1-KV3 105,000 585,000 KV3-VT3 50,000 219,000

2 Ward no.2 Kenh Dung, Hai Liem sewer KV1-VT4 90,000 602,000 KV1-VT4 90,000 273,000 30 June sewer KV1-VT4 90,000 314,000 KV1-VT4 90,000 241,000

3 Thanh Hoa 30 June sewer, Ca Chat sewer, Ca Nua sewer KV2-VT2 65,000 285,000 KV2-VT3 55,000 219,000

Residential land 1 Tan Binh Khach Minh sewer, Lo Lang sewer

1 Ward road 57B

450,000 946,000

2 KV2-VT3 120,000 410,000 2 Ward no.2 Kenh Đung, Hai Liemsewer

Tay Ba Rai road 600,000 903,000

KV1-VT4 350,000 539,000 30 June sewer Tay Ba Rai road 600,000 614,000

KV1-VT4 350,000 428,000

3 Thanh Hoa 30 June sewer,Ca Chat sewer, Ca Nua sewer Tây Ba Rài road 230,000 585,000 KV1-VT3 120,000 408,000

4 The cost to hire temporary land for the construction of works subproject is 20,000 VND/m2/year and its duration is about 02 year.

Cai Lay district area

Table 10: Compensation price of Subproject–Cai Lay district (unit: Dong per m2)

Rural land price

No Ward

/commune

Name of street/area/l

ocation

Land price under Decision

no. 44/2015

Compensation price

according to Decision

No.350/QD-UBND

Note

1 Cam Son Ong Ban sewer, Tham Rom sewer, Ong Kham sewer, Thay Thanh sewer West of Ba

Rai river 280,000 525,000 NearWest road of Ba

Rài river (asphalt,

Page 32: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

32 | P a g e

3.0m of width) West of Ba

Rai river 280,000 500,000 NearWest road of Ba

Rài river (broken stone, 4.0m of width)

KV1-VT3 120,000 394,000 Near Dall road, made by broken stone, 1.5m of width (NearWest road of Ba Rài river, 4.0m of width)

KV1-VT4 100,000 280,000 Remaining locations 2 Hoi Xuan Thay Thanh sewer, Ba Gon sewer, Hai Hue sewer West of Ba

Rai river 280,000 500,000 NearWest road of Ba

Rài river(broken stone, 4.0m of width)

KV1-VT3 120,000 394,000 Near Dall road, made by broken stone, 1.5m of width(Near West road of Ba Rài river, 4.0m of width)

Khang Chien sewer Provincial

road 864 600,000 1,177,000 Near provincial road

864 (the segment from Ba Rài river to Dong Hoa Hiep commune)

KV1-VT2 160,000 526,000 Near broken stone road, 3.0m of width, over 15m of channel width (near provincial road 864)

KV1-VT3 120,000 407,000 Near Dall road, made by broken stone, 15m of width (near provincial road 86).

3 Hiep Đuc Cay Sung sewer, Cai La sewer, Giong Tre 2 sewer Provincial

road 864 600,000 1,177,000 Near provincial road

864 (the segment from Ba Rai to Dong Hoa Hiep commune)

KV1-VT2 160,000 526,000 Near Dall road, made by broken stone, 15m of width (near provincial road 86).

KV1-VT3 120,000 407,000 Near Dall road, made by broken stone, 1.5m of width (near provincial road 86).

4 Phu An Đong Sao- Ca Nua sewer, Bo Keo sewer, Thong Luu sewer, Ap 2 sewer, Ranh Lang sewer

District road 67

550,000 1,027,000 Near district road 67 (the segment from provincial 75 to Phu An bridge)

Page 33: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

33 | P a g e

East of Phu An river

280,000 454,000 Near the East road of Phu An river (broken stone, 3.0m of width) over 15m of channel width

KV1-VT3 120,000 373,000 Near Dall road made be brokenstone, 1.5m of width (near the East road of Phu An river, 3.0m of width)

5 Binh Phu Rach Giong- Ba So sewer, Đap Chua sewer, Cay Me sewer, Giong Tre 1 sewer

East of Phu An river

280,000 454,000 Near district road 67 (The segment from provincial road 875 to Phu An bridge)

KV1-VT3 120,000 373,000 Near East road of Phu An bridge (broken stone, 3.0m of width), over 15m of channel width

Lo Hoa Thuong sewer KV1-VT2 220,000 468,000 Near Dall road, 2.0m

of width KV1-VT3 120,000 373,000 Near broken stone

road, 2.01.5mm of width

Agricultural land price (Perennial crop)

No Commune Name of street/area/location

Land price under Decision no. 44/2015

Compensation price according to Decision No.350/QD-UBND

Note

1 Cam Son Ong Ban sewer, Tham Rom sewer, Ong Kham sewer, Thay Thanh sewer KV2-VT1 80.000 273.000 NearWest road of Ba

Rài river (asphalt, 3.0m of width)

KV2-VT2 65.000 260.000 NearWest road of Ba Rài river (broken stone, 4.0m of width)

KV2-VT3 55.000 206.000 Near Dall road, made by broken stone, 1.5m of width (Near West road of Ba Rài river, 4.0m of width)

KV2-VT4 50.000 159.000 Remaining locations 2 Hoi Xuan Thay Thanh sewer, Ba Gon sewer, Hai Hue sewer KV2-VT1 80.000 273.000 Near Dall road, 3.0m

of width KV2-VT2 65.000 260.000 Near West road of Ba

Rai river (broken

Page 34: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

34 | P a g e

stone, 4.0m of width) KV2-VT3 55.000 206.000 Near Dall road, made

by broken stone, 1.5m of width (NearWest road of Ba Rài river, 4.0m of width)

Khang Chien sewer KV1-VT2 120.000 557.000 Near provincial road

864 (the segment from Ba Rài river to Dong Hoa Hiep commune)

KV2-VT 65.000 272.000 Near broken stone road, 3.0m of width, over 15m of channel width (near provincial road 864)

KV2-VT3 55.000 214.000 Near Dall road, made by broken stone, 15m of width (near provincial road 86).

3 Hiep Đuc Cay Sung sewer, Cai La sewer, Giong Tre 2 sewer KV1-VT2 120.000 557.000 Near provincial road

864 (the segment from Ba Rai to Dong Hoa Hiep commune)

KV1-VT2 120.000 557.000 Near Dall road, made by broken stone, 15m of width (near provincial road 86).

KV2-VT2 65.000 272.000 Near Dall road, made by broken stone, 1.5m of width (near provincial road 86).

KV2-VT2 55.000 214.000 Near provincial road 864 (the segment from Ba Rai to Dong Hoa Hiep commune)

4 Phu An Đong Sao- Ca Nua sewer, Bo Keo sewer, Thong Luu sewer, Ap 2 sewer, Ranh Lang sewer

KV1-VT3 105.000 416.000 Near district road 67 (the segment from provincial 75 to Phu An bridge)

KV2-VT2 65.000 230.000 Near the East road of Phu An river (broken stone, 3.0m of width) over 15m of channel width

KV2-VT3 55.000 185.000 Near Dall road made be brokenstone, 1.5m of width (near the East road of Phu An

Page 35: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

35 | P a g e

river, 3.0m of width) KV2-VT4 50.000 159.000 Remaining location 5 Binh Phu Rach Giong- Ba So sewer, Đap Chua sewer, Cay Me sewer, Giong Tre 1

sewer KV1-VT2 120.000 654.000 Near district road 67

(The segment from provincial road 875 to Phu An bridge)

KV2-VT2 65.000 230.000 Near East road ofPhu An bridge (broken stone, 3.0m of width), over 15m of channel width

KV2-VT3 55.000 185.000 Near Dall road made by broken stone, 1.5m of width (Near East road of Phu An river, 3.0m of width).

Lo Hoa Thuong sewer KV2-VT2 65.000 236.000 Near Dall road, 2.0m

of width KV2-VT3 55.000 185.000 Near broken stone

road, 1.5m of width

Cai Be district area

Clearance milestone at Giong Tre 2 sewer is coincident with clearance milestone of

provincial road 864 (Clearance implemented in 2008). Therefore, there is no land acquisition

and no compensation. The subproject only supported cost of hiring temporary agricultural

land during construction. Support shall be provide in compliance with policy in uRP, detail the

provisions of Clause 10, Article 1 of Decision No. 18/2016/QD-UBND dated 28/4/2016 of

Tien Giang PPC.

Compensation for housing, structures and graves:

+ Compensation for affected houses and structures applied the compensation rates

regulated in the Decision No.29/2015/QĐ-UBND, dated 4/9/2015 of Tien Giang PPC

and Article no.20 of Decision no.40/2014/QD-UBND dated 16/12/2014 of Tien Giang

PPC regulated on compensation, support and resettlement when the State acquires

land in Tien Giang province area.

- Compensation for crops/trees and cattles

+ Compensation for crops/trees and cattles affected by Subproject will be applied unit

price that issued on Decision no.05/2015/QD-UBND dated 9/2/2015 and Article no.28

of Decision no.40/2014/QD-UBND dated 16/12/2014 of Tien Giang PPC regulated on

compensation, support and resettlement when the State acquires land on Tien Giang

province area.

+ All the surveyed and consulted households confirmed that the compensation rates

made for affected annual crops/trees and cattles were equal to the values of the

Page 36: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

36 | P a g e

productivities of the crops/trees and cattles in that harvesting year; for affected

perennial trees, compensation unit rates were equal to the values of the trees in the

market at time of compensation. Affected households are satisfied with the applied

compensation rates and there is no complaint on the rates.

+ Due to the construction area of Giong Tre 2 sewer without land acquisition and no

impact on houses or buildings, support policies did not apply.

+ Support policies: Ba Rai-Phu An project is now being implemented in accordance

with the regulations of Tien Giang People's Committee. Supporting Program under the

policy of the project is arranged for implementation in the next period.

59. For the Cai Cai channel works subproject: Base on legal documents mentioned above,

Tan Hong DLFDC, Dong Thap province has established plan of compensation, support

and resettlement and this plan has been approved by Tan Hong DPC according to

Decision No. 805/QD-UBND dated 10/8/2016. Accordingly:

- Compensation for land: According to Official letter no. 574/UBND-KTN dated

23/11/2015, compensation prices for land have been approved specifically for sub-

project “Rehabilitation and upgrading for the flood drainage and irrigation system to

the Dong Thap Muoi region, Dong Thap province – Cai Cai channel works” in Tan

Hong district area, Dong Thap province. These prices were determined based on

site inspection and market price, under Decision No.574/QD-KTN dated 23/11/2016

issued by Dong Thap PPC. Accordingly, compensation price of subproject Cai Cai

channel works is higher than PPC’s compensation price. This price has been

updated in the updated RP August, 2015 of subproject. Details on compensation

price for Cai Lay town, Cai Lay district and Cai Be district are presented as

following:

+ Residential land in rural (plot 4, KV2): 150,000 VND/m2

+ Perennial crop land (KV2-KT2): 220,000 VND/m2

+ Paddy land (KV2-KT2): 180,000 VND/m2

For the affected agricultural land of AHs, those affected households not only receive

compensation cash based on replacement cost but also receive an amount of

money for job chagne with its value is more than three times the value of the

affected land. Affected households can immediately buy a new agricultural plot with

its area is larger than their old agricultural plot, after received compensation cash of

the subproject.

- Compensation price for affected housings and structures on land: applied according

to the Decision No.16/2012/QĐ-UBND, dated 12/6/2012 issued by Dong Thap PPC.

- Compensation price for crops, livestock, relocating grave: applied according to

Decision no.36/2014/QD-UBND dated 25/12/2014 of PPC regulated on

compensation price for crops, livestock when the State acquires land on Dong Thap

Page 37: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

37 | P a g e

province area.

Amount of money to support vulnerable groups: 8 millions per household. Supporting

program under the project policies such as supporting to stabilize production and life,

to vulnerable groups has been approved to such households to comply with the

contents mentioned in entitlement matrix of the updated resettlement plan.

5.2.4 Compensation payment

60. Payment time: payment of compensation of Ba Rai-Phu An Subproject started on

21/7/2016. Payment compensation of Cai Cai Canal sub-project commenced in

September 2016.

61. Payment organization

- The order of execution, payment of compensation and support for sub-projects shall

comply with the following 3 steps. Accordingly:

+ Step 1: Notify the affected households about the location of compensation

payment. When the AHs come to receive the payment, it is necessary to

present their ID card or household residential registration book and to bring

LUR certificates to adjust or withdraw. In case of household head is unable to

go, who is representative of household head must show authorization paper

certified by competent authority.

+ Step 2: Carry out payment for households, persons who receive money must

sign and inscribe their names clearly on the payment vouchers that issued by

Compensation Council. In case the household heal is unable to sign, person

who receives money must fingerprint in the payment record. For the Ba Rai –

Phu An subproject, LDFC of Cai Lay town, Cai Lay district and Cai Be district

directly paid compensation cash, support for AHs. For the Cai Cai channel

works subproject, the payment of compensation cash, support for AHs also

has been carried out by Dong Thap PPMU.

+ Step 3: Completing settlement procedure. For the Cai Cai channel works

subproject, PPMU carried out payment, thus, after completing the payment,

PPMU has responsible to complete settlement procedure of the subproject.

Settlement procedure would be sent to Compensation council and

Compensation council will synthesize the whole payment vouchers to pay with

Investor according to regulations

- Implementing agency of administrative procedures: LDFC of districts/towns,

compensation council of districts/town

- Profile compostion:

+ Compensation, support and resettlement for two subprojectshas been approved

by PPC

Page 38: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

38 | P a g e

+ Decisions approved for compensation, support and resettlement of the

subproject include:

List of affected householdsreceiving compensation cash (Appendix 16)

+ Payment voucher (Appendix 17)

62. The monitoring results show that all affected households, those households have been

informed of the date, time and place of payment. Payment was implemented quickly with

simple procedures and favorable to PAHs. Compensation for land, affected

houses/structures, crops/trees, and affected assets by the subproject was compliant with

the provisions of national laws and regulations, conformity to requirements of the

approved resettlement documents and the SPS, 2009.

5.2.5 Restoration of the affected people’s lives and livelihood

63. In addition to compensation for land and assets on the affected land, Tien Giang PPMU

and Cai Lay town PC, Cai Lay DPC, Cai Be DPC and Dong Thap PPMU, Tan Hong

town PC also apply many other assistances (such as support for career change and

creating jobs, stabilization of production life, support for vulnerable groups, policy

households, support due to interruption of production and business activities) for affected

households for the stabilization of their lives and incomes

64. As mentioned in Section 5.1, due to the time of the resettlement plan of the two sub-

projects BaiRai – Phu An and Cai Cai canal (2010), beneficial policies proposed in the

resettlement plan has been changed and no longer appropriate. These changes in the

updated resettlement plan of the sub – projects have been adjusted to be adequate to

current regulations and policies of the project. Accordingly, the compensation, support

and resettlement plans of both subprojects adhered to the proposed principles and

policies in the benefit matrix of the updated resettlement plan. That also means the

compensation, support and resettlement plans of both sub – projects have been

adequate to policies in the previous resettlement plans. However, the progress of

deploying the compensation, support and resettlement work of the two sub-projects was

divided into two different stages. The first phase includes the compensation of land,

houses, building, and assets, changing occupation and creation jobs program,

stabilization production life in accordance with Provincial People's Committee, support to

policy families, families of war invalids / martyrs, poor households according to PPC. The

support program under policies of the project (proposed in benefit matrix) containing

support for stabilization production life of BAHs, income restoration program, support for

vulnerable households were additionally implemented for the next phase. According to

LFDC of district/wards of the sub-project Ba Rai – Phu An Tien Giang and LFDC of Tan

Hong District of the subproject Cai Cai canal, locality had to implement periodically to

create the policy uniformity among projects on area, avoiding complaints of affected

households belonging to other projects in the area.

Page 39: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

39 | P a g e

65. For the Cai Be Canal subproject, support programs for APs under the policy of Dong

Thap Province People's Committee have been completed including programs to support

occupation change and job creation, support poor households, policy households,

support production life stabilization for AHs. Currently, the program to support livelihoods

and production for severely affected households in accordance with the regulations of

the People's Committee of Dong Thap province has higher levels than the proposed

support level in the uRP entitlement matrix. Specifically, at the rate of over 70% of

agricultural land, BAHs are supported to 12 months of allowance for non-relocation, 24

months for relocation households; while regulation in uRP is 9 months for non-relocation

and 12 months for relocation households. Or at the acquisition rate of 30-70% of the

agricultural land, according to the regulations of Dong Thap province, the support is 6

months without relocation, lower than the 9-month support offered by the URP. For

mobility, 12 months are supported by the level of support offered in uRP. The difference

in support against the proposed policy in uRP will be added in the next phase when

implementing other policies under the uRP including support for 10- 30% of agricultural

land, income restoration programs and support for vulnerable households.

66. For Ba Rai -Phu An sub-project, such programs as assistancefor job change and job

creation, for poor households, policy households and for productionand

livelihoodstabilizationof AHs. Are also implemented in accordance with the policy of

TienGiang Provincial People's Committee and in the first phase. The program to support

livelihoods and production for severely affected households under the uRP proposed

benefit policy in uRP, income restoration and support for vulnerable households

programsis also implemented in the next phases. According to the compensation,

support and resettlement plan approved by the People's Committees of Cai Lay, PC of

CaiBe and Cai Lay Town, the assistance for livelihood and production stabilization of

affected people having over 70% of the area of agricultural land is equal to the support

proposed in the uRP: 12 months support if non-relocation and 24 months support if

relocation; In cases affected by 30-70% of agricultural land, theallowance for relocation

according to the province regulations and according to the uRPis 12 months, if not

relocated, the support of Dong Thap province is 6 months, lower than 9 months in uRP;

In cases affected by 10-30% of agricultural land, the allowance according to the People's

Committee of Dong Thap province is 3 months if no relocation and 6 months if

relocation, lower than the support level proposed in uRP which is 6 months if no

relocation and 9 months if relocation. However, the policy of Dong ThapPPC also has

advantages compared to the proposed policy in uRP that ispeople are still supported to

stabilize their life for 3 months if no relocation and 6 months if relocationin the case of

acquisition less than 10% of agricultural land. Meanwhile, according to the uRP benefit

policy, the affected people are not supportedwhen affected by less than 10% of

agricultural land. The differences in the support level between the regulation of

TienGiang PPC and uRP will be added and implemented in subsequent phases together

with the income restoration program and support program for vulnerable households.

Page 40: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

40 | P a g e

67. Details of the support program for affected people have been implemented and the

proposed benefit policy in the RP, uRP of the subprojects is detailed in the table below:

Page 41: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

41 | P a g e

Table 11: Assistances for PAHs

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

1 Assistance for job-change and job creation

Agricultural HHs do not receive compensation according to land for land when the State acquires land

Cash support equal to 2,5 times the agricultural land price for the whole area of agricultural land acquired but not exceeding the allocation of agricultural land at locality

Cash support equal to 3 times the agricultural land price for the whole area of agricultural land acquired but not exceeding the allocation of agricultural land at locality

Cash support equal to 3 times the agricultural land price for the whole area of agricultural land acquired but not exceeding the allocation of agricultural land at locality

Cash support equal to 3 times the agricultural land price for the whole area of agricultural land acquired but not exceeding the allocation of agricultural land at locality

Cash support equal to 3 times the agricultural land price for the whole area of agricultural land acquired but not exceeding the allocation of agricultural land at locality

Cash support equal to 3 times the agricultural land price for the whole area of agricultural land acquired but not exceeding the allocation of agricultural land at locality

2 Assistance for life stabilization

Support 30kg of rice/person/month Support 30kg of rice/person/month Over 70% of agricultural land area acquired

- Support 12 months if they are not required to move out - Support 24 months if they are required to move out - Support 36 months if they are required

- Support 12 months if they are not required to move out - Support 24 months if they are required to move out

- Support 12 months if they are not required to move out - Support 24 months if they are required to move out

Support 12 months

- Support 12 months if they are not required to move out - Support 24 months if they are required to move out

- Support 12 months if they are not required to move out - Support 16 months if they are required to move out

Page 42: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

42 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

to move to the difficult areas

- Support 36 months if they are required to move to the difficult areas

- Support 36 months if they are required to move to the difficult areas

- Support 24 months if they are required to move to the difficult areas

From 30% to 70% of agricultural land area acquired

- Support 6 months if they are not required to move out - Support 12 months if they are required to move out

- Support 6 months if they are not required to move out - Support 12 months if they are required to move out

- Support 6 months if they are not required to move out - Support 12 months if they are required to move out - Support 16 months if they are required to move out and in vulnerable group

Support 9 months - Support 6 months if they are not required to move out - Support 12 months if they are required to move out - Support 24 months if they are required to move to the difficult areas

- Support 6 months if they are not required to move out - Support 12 months if they are required to move out - Support 16 months if they are required to move out and in vulnerable group

From 10% tounder 30% of agricultural land area acquired

- Support 6 months - Support 3 months if they are not required to move out - Support 6 months if they are required to move out

- Support 6 months if they are not required to move out - Support 9 months if they are required to move out - Support 12 months if they are

Support 6 months - Support 6 months if they are not required to move out - Support 9 months if they are required to move out

- Support 6 months if they are not required to move out - Support 9 months if they are required to move out - Support 12 months if they are

Page 43: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

43 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

required to move out and in vulnerable group

required to move out and in vulnerable group

Under 10% of agricultural land area acquired

No support - Support 3 months if they are not required to move out - Support 6 months if they are required to move out

No support No support No support No support

3 Reloca

tion assistance

Households and individuals who lost housing and the rest of land area is not enough to rebuild new house/must to

For the households must relocate -The cost of relocation assistance in range of Province: 5,000,000 dong/household - The cost of relocation assistance to other Province: 7,500,000 dong/household

For the households must relocate -The cost of relocation assistance in range of Province: 7,000,000 dong/household - The cost of relocation assistance to other Province: 10,000,000 dong/household

For the households must relocate -The cost of relocation assistance in range of Province: 7,000,000 dong/household - The cost of relocation assistance to other Province: 10,000,000 dong/household

For the households must relocate + support 5,000,000 dong/household for the relocation + Cash benefits: 900,000 dong/household for for the relocation of the water meter and electricity meter -For the households, who affected a part

People affected by land acquisition/ temporary influence (75 households must carry out temporary relocation) For the households, who selected constructing a temporary house on channel bank under design of the GoV:

People affected by land acquisition/ temporary influence (75 households must carry out temporary relocation) For the households, who selected constructing a temporary house on channel bank under design of the GoV:

Page 44: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

44 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

relocate to other place/ resettle on the rest of their land area

residential land and the rest of land area is enough to rebuild house: + support 5,000,000 dong/household for the relocation + Cash benefits: 900,000 dong/household for for the relocation of the water meter and electricity meter

• Financial support (based on replacement cost) to build a safety temporary house on channel bank2

• Give an allowance for the relocation to new house

• Give an allowance for severely affected households

-Households resettled in province, will receive an allowance as following:

• Financial support (based on replacement cost) to build a safety temporary house on channel bank3

• Give an allowance for the relocation to new house

• Give an allowance for severely affected households

-Households resettled in province, will receive an allowance as following:

2 Should ensure that those houses would meet the minimum standards of housing – Similar or better than the old one with facilities such as hygienic toilet, electricity and

clean water source 3 Should ensure that those houses would meet the minimum standards of housing – Similar or better than the old one with facilities such as hygienic toilet, electricity and

clean water source

Page 45: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

45 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

+ Housing area under 15m2: 2,000,000 VND/household + Housing area from 15m2 to 30m2: 3,000,000 VND/household + Housing area from 31m2 to 45m2: 4,000,000 VND/household + Housing area over 45m2: 6,000,000 VND/household

+ Housing area under 15m2: 2,000,000 VND/household + Housing area from 15m2 to 30m2: 3,000,000 VND/household + Housing area from 31m2 to 45m2: 4,000,000 VND/household + Housing area over 45m2: 6,000,000 VND/household

b. Assistance for renting house

Applied for households, and individuals who have got housing before .

a) Relocation to the resettlement area - For the household has 01-04 members, will be supported 900,000 dong/month/household. - The household has more 04 members:

a) Relocation to the resettlement area - For the household has 01-04 members, will be supported 1,200,000 dong/month/household; - The household

a) Relocation to the resettlement area - For the household has 01-04 members, will be supported 1,200,000 dong/month/household;

- For the household must relocate to other place: support cash for renting house in 6 months according to regulation of PPC - For the household must relocate the

For the households, who affected a part or entire residential land and the rest of land area is

enough to rebuild house, they

For the households, who affected a part or entire residential land and the rest of land area is

enough to rebuild house, they

Page 46: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

46 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

5th person will be received 200,000 dong/month/person - Time of support is calculated at the time of handing over the land until they receive land for resettlement and adds 04 months to build housing, while the minimum supporting periodis 06 months b) Resettlement on their plot - For the household has 01-04 members, will be supported 900,000 dong/month/household. - The household has more 04 members: 5th person will be received 150,000 dong/month/person. - The maximum

has more 04 members: 5th person will be received 200,000 dong/month/person - Time of support is calculated at the time of handing over the land until they receive land for resettlement and adds 04 months to build housing, while the minimum supporting periodis 06 months b) Resettlement on their plot - For the household has 01-04 members, will be supported 1,200,000 dong/month/household. - The household has more 04

- The household has more 04 members: 5th person will be received 200,000 dong/month/person - Time of support is calculated at the time of handing over the land until they receive land for resettlement and adds 04 months to build housing, while the minimum supporting periodis 06 months b) Resettlement on their plot - For the household has 01-04 members, will be supported 1,200,000 dong/month/household.

shelter to the rest of their land: support cash for renting house in 3 months

would be

received an allowance for

renting house:support 6

months allowance for renting house for households, who

must dismantle totally their house

would be

received an allowance for

renting house:support 6

months allowance for renting house for households, who must

dismantle totally their house

Page 47: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

47 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

support period is 6 months

members: 5th person will be received 200,000dong/month/person - Support period is 6 months

- The household has more 04 members: 5th person will be received 200,000dong/month/person; - Support period is 6 months

c Support for resettlement, relocation

Support for HHs must relocate and make their own shelter

- No regulated - Support: 80,000,000 dong/household

- Support: 80,000,000 dong/household

No regulated No regulated

Support for HHs acquired a part of hosing land, must move housing

-No regulated - Support for the cost of foundation repair: 30,000,000 dong/household

- Support for the cost of foundation repair: 30,000,000 dong/household

Page 48: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

48 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

to the remaining land area Support for relocated HHs but they are incapable of resettlement4

- No regulated Support: 64,000,000 dong/household

Support: 64,000,000 dong/household

Support for poor households, who are required to move out

- Support 30kg of rice /month/household during 5 year.

- Support 30kg of rice /month/household during 60 months, equal to 21,600,000 dong/household.

- Support 30kg of rice /month/household during 60 months, equal to 21,600,000 dong/household.

4 Support for vulnera

Poor households,

- Support for stabilization by cash cash

- Support for stabilization by cash cash

- Support for stabilization by cash cash

- Support for stabilization by cash cash

For the vulnerable

4For HHs built housing on acquired agricultural land and had no other place in the commune area

Page 49: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

49 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

ble households

women headed households with dependents, social protection policies, the lonely elderly, landless people, ethnic minorities

equivalent to 30 kg of rice/person/month for 12 months

- AHs frequently receive social allowance of the GoV, will be received an allowance equivalent to 2,000,000 dong/household

- For the martyrs' families, if they are required to move out, they will be received an allowance equivalent to 6,000,000 dong/household

equivalent to 30 kg of rice/person/month for 24 months at the market price at the time of compensation.

- Beside, the poor will receive monetary support equivalent to 30 kg of rice/person/month for 6 months. Rice price: 12,000 VND / kg

- AHs frequently receive social allowance of the GoV, will be received an allowance equivalent to 2,000,000 dong/household

- For the martyrs' families,

equivalent to 30 kg of rice/person/month for 24 months at the market price at the time of compensation.

- Beside, the poor will receive monetary support equivalent to 30 kg of rice/person/month for 6 months. Rice price: 12,000 VND / kg

- AHs frequently receive social allowance of the GoV, will be received an allowance equivalent to 2,000,000 dong/household

equivalent to 30 kg of rice/person/month for 24 months

- Thepoor households will be received an amount of monetary support equivalent to 30 kg of rice/person/month for 6 months.

households,

those households would be

received an amount of money

ranging from 4,000,000 to 8,000,000 dong to improve their

economic condition (according to Decision no.27/2014/QD-

UBND dated 27 November, 2014

of Dong Thap PPC regulated on compensation, support and resettlement when the State

acquires land on

Page 50: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

50 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

if they are required to move out, they will be received an allowance equivalent to 6,000,000 dong/household

- For the martyrs' families, if they are required to move out, they will be received an allowance equivalent to 6,000,000 dong/household

Dong Thap

province area) as following:

- Family policy : 8,000,000

dong/household

- AHs frequently receive social

allowance of the GoV: 4,000,000 dong/household

- Near-poor household:

4,000,000 dong/household

If households are in both poverty household and family policy, they would be

Page 51: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

51 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

received the highest amount. Other vulnerable households: 8,000,000 dong/household

5 Assistance for income disruptions for the affected business households

Business households affected by land acquisition activities of the subproject

- For the business households with business license: Support 30% of income by cash (1 year) according to average income of Three consecutive years before (based ontax receipt). It is regulated at Section 4, Article 26, Decision no.36/2009/QD-UBND of Tien Giang PPC - For the business households have not been approved by tax authority: After-tax imcome of those business

- Organizations and business households with business license will be supported under Paragraph 5 of Article 31 of Decision No. 40/2014/QD-People's Committee of Tien Giang Province: + If relocation to

other places: Support 30% of after-tax income (1 year) according to average income of

- Organizations and business households with business license will be supported under Paragraph 5 of Article 31 of Decision No. 40/2014/QD-People's Committee of Tien Giang Province: + If relocation

to other places: Support 30% of after-tax income (1 year)

No regulated There is no affected business household so compensation plan does not mentioned

Support amount applied according

to Decision no.27/2014/QD-UBND of Dong Thap PPC

regulated on compensation,

support and resettlement

when the State acquires land on Dong Thap province area. - Support by

cash in

transition period. The

Page 52: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

52 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

households will be based on financial report, report on business result, which were submitted to tax authority

Three consecutive years before

+ If no relocation: Support 15% of after-tax income (1 year).

- Organizations and business household without business license but still paying tax: + If relocation to other places: Support 50% of after-tax income (1 year) + If no relocation: Support 10% of after-tax income (1 year).

according to average income of Three consecutive years before.

+ If no relocation: Support 15% of after-tax income (1 year).

- Organizations and business household without business license but still paying tax: + If relocation to other places: Support 50% of after-tax income (1 year) + If no relocation: Support 10% of after-tax income

support amount

is equivalent to 80% of

business household with

business license

- Workers working in

business facilities must leave off, will be received an minimum salary

level according to regulations

of current labor law (no more than 6 months for each person)

Page 53: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

53 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

(1 year). 6 Bonus Allowan

ce bonus if the land was handed over on schedule

According to Section 4 Article 30, Decisionno 36/2009/QĐ-UBND of Tien Giang PPC - Bonus 5,000,000

dong/household for households have affected housing land and house

- Bonus 3,000,000 dong/household for households have affected house

- Bonus 2,000,000 dong/household for for households having their land; fruit trees; flower color; Structures (not affecting home) affected

According to Section 7, Article 37, Decision no. 40/2014-QĐ-UBND of Tien Giang PPC - Bonus 5,000,000

dong/household for households have affected housing land and house

- Bonus 3,000,000 dong/household for households have affected house

- Bonus 2,000,000 dong/household for for households having their land; fruit trees; flower color; Structures (not affecting home) affected;

The bonus does not exceed the

According to Section 7, Article 37, Decision no. 40/2014-QĐ-UBND of Tien Giang PPC - Bonus

5,000,000 dong/household for households have affected housing land and house

- Bonus 3,000,000 dong/household for households have affected house

- Bonus 2,000,000 dong/household for for households having their land; fruit trees; flower color;

Award a bonus for households handling over their land on schedule: 2,000,000 dong/household

No regulated No regulated

Page 54: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

54 | P a g e

No Assistance

Subject for

assistance

Ba Rai – Phu An Subproject Cai Cai channel subproject Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

Assistance level according to RP

Assistance level according to

compensation, support and resettlement

approved

Assistance level according to updated RP

compensation value

Structures (not affecting home) affected;

The bonus does not exceed the compensation value

Page 55: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and

Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

55 | P a g e

68. Support for income loss of business households: According to the report of Tien

Giang PPMU, LDFCs of Cai Lay town, Cai Lay district and Cai Be district, there was 01

household out of 247 affected households (Mr.Doan Van Banh household) affected by

business interruption. This household located in the area for constructing Dap Chua

sewer, Cai Lay district. This household is doing the business in sector of supplying

agricultural material. Within the landmark of site clearance, Doan Van Banh household

has to relocate his warehouse of agricultural material and this will affect his household’s

income and business. According to regulations at Article 31, Decision no.40/2014/QD-

UBND dated 16 December 2014 of Tien Giang PPC, Mr. Doan Van Vanh household

only had to relocate his warehouse within his existing land plot. The householdhas

received 15% after-tax income (one year), according to three consecutive years. The

total amount he received is 5,180,000 dong (details see at Appendix 18 –

Announcement on confirmation of Mr. Doan Van Banh’s tax money submitted to the

State and detail table on support for interrupted business). The program of supporting

income loss would be carried out in line with regulations of Tien Giang PPC and project’s

policies.

69. According to report of Dong Thap PPMU, Tan Hong LFDC, there was no household

affected by business interruption out of 153 affected households.

70. Assistance for job-change and job creation in case of recovery of agricultural land in

cash equal to 3 times the agricultural land price for the whole area of recovered

agricultural land at 3 times the price support compensated by agricultural land is done

with all households and individuals directly engaged in agricultural production. With this

assistance, many households with affected agricultural land had purchased larger

replacement land for production than the acquired area. For other families, the area

remaining agricultural land is still enough to produce, they continue to cultivate in the

remaining land and acquired land of the sub-preojct. They have not purchased the

replacement land, but intend to purchase upon request of land hand over for

construction. Those having over 10% of the agricultural land area under use recovered

had received support for life and production stabilization by cash equivalent to 30kg of

rice for a month (from 6 to 24 months). Support to overcome poverty according to plan of

compensation, support and resettlement, which was approved by Tien Giang and Dong

Thap PPC and other PPCs in project area. Ba Rai –Phu An channel subproject, for the

households lost under 10% of their land, they also receive an amount for production

stabilization, 3 months and 6 months for relocation and no relocation respectively.

71. Livelihood restoration program: Tien Giang PPMU, Dong Thap PPMU coordinated

with consultant unit for updating Resettlement plan set up a livelihood

restorationprogram for severely affected households in project area, based on the results

of consultations with affected households, DCARB, local government and the

commune/district People's Committe.

Page 56: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

56 | P a g e

+ For the Ba Rai – Phu An subproject: There were 11 households interested in

supporting the improvement of agricultural production, in which 6 households interested

in cow breeding, 01 household interested in pig breeding and 04 households interested

in planting durian. In order to ensure that households are eligible to participate livelihood

restoration program and livelihood restoration program would be carried out, DCARB

and affected persons have agreed that livelihood restoration program would be

intergrated with vocational training policiesof Tien Giang PPC. However, payment of

compensation cash, support and resettlement for affected households in Ba Rai – Phu

An subproject are in process of implementation so livelihood restoration program has not

been carried out. It is expected to carry out livelihood restoration program after finishing

compensation for AHs. LFDC of Cai Lay district and Cai Lay town will cooperate with

wards/communes PC in project area to implement public consultation for AHs on

livelihood restoration program and redefine AHs’ demand. After that, an appropriate

livelihood restoration program will be set up.

+ For the Cai Cai works channel subproject: there were 02 models of income restoration

program selected, include training of high-quality rice production and Sind cow breeding.

There were 30 severely affected households interested in training of high-quality rice

production and 20 severely affected households interested in Sind cow breeding. It is

expected that 6 training courses would be established to carry out for households

interested in two models. Monitoring results show that payment for compensation cash,

support and resettlement for Cai Cai channel works subproject has almost done (except

8 households located at plot no.4 – Tan Phuoc commune, are recommending for more

support of compensation cost). However, according to opinions of local government and

people, the construction of byre will face diffcults or building barns near their housing

wouldn’t guarantee sanitation because of ordor arising from cattle’s waste due to small

construction area and not enough space to build barns. Hence, Dong Thap PPMU and

Tan Hong DLFDC will coordinate with commune governments Tan Binh, Tan Thanh A,

Tan Phuoc to identify the demand of livelihood restoration program for people,

72. Thus, although affected households in two subprojects had received compensation cash,

support and resettlement but cash support for livelihood restoration program has not.

Therefore, Tien Giang PPM, Dong Thap PPMU and relevant agencies should resolve

quickly and as soon as possible the outstanding issues in line the requirements of the

URP, Safety Policy Statement of ADB (SPS, 2009) and the regulations of the

Government of Vietnam.

5.2.6. Site clearance and land hand-over

73. As mentioned above, and monitoring results of IMO: compensation, support and

resettlement for two subprojects has not been completed 100%

+ For the Ba Rai – Phu An subproject: has completed payment for 130/247 affected

households at 13 sewers, in which 9 sewers located in Cai Lay district including: Cay

Page 57: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

57 | P a g e

Sung, Cai Na, Giong Tre 2 (Hiep Duc commune), Khang Chien, Ba Gon, Hai Hue (Hoi

Xuan commune), Thay Thanh (Hoi Xuan and Cam Son commune); Thong Luu (Phu An

commune), Ong Bang (Cam Son commune); 4 sewerslocated in Cai Lay town including:

Ca Chat, Ca Nua (Thanh Hoa commune), Khach Minh, Lo Lang (Tan Binh commune).

All AHs have received compensation, support and resettlement and committed that they

will hand over the land as regulated (Appendix 19).

+ For the Cai Cai channel works subproject: has completed payment for 145/153

AHs, in which 70 households located at plot no.1 (Thong Binh commune), plot no.2 and

no.3 (Tan Thanh A commune), At Bo sewer, Ba Hai Mot sewer, Bay Thua sewer (Thong

Binh commune), Nga Tu sewer (Tan Phuoc commune), Cau Ca Trap II, Cau Ca Trap III

and 75/83 AHs located at plot no.4 (Tan Phuoc commune). Therefore, there were 08

remaining households located at plot no.4 have not been received compensation

cash/support. AHs received cash compensation, support and resettlement and

committed to hand over the land as regulated

74. Monitoring results show that households had handed over their land after receiving

compensation in cash because they agree with compensation policies of the subproject.

Besides, those households also expected to receive a bonus for handing over the

ground on schedule as mentioned in subproject’s policies.

75. Currently, where the project locations have completed payment of compensation, LDFC

of towns/districts have handed over the ground to Employer and contractors. In the pre-

construction period, IMO recommended Employer managing tightly the site to avoid re-

encroachment in project area.

5.2.7. Arrangement for resettlement

76. According to the updated RP, 52 households must relocate due to land acquisition in Ba

Rai – Phu An subproject, in which 29 households shall not move to other place. Such

households only have to resettle in place and rebuild their houses on the remaining land

area. This significantly reduces negative impacts to their life, livelihood and income.

However, 23 remaining households have to relocate to new place. After public

consultation meeting, these households recommended to local authorities for staying

instead relocating to new resettlement area (because new resettlement area is quite far

from their current place). 53 households would be received compensation cash for

affected assets and support for livelihood restoration. For example, for the households

resettled in place, they are not only received compenstation cash for affected assets at

replacement cost and cash support for construction of new housing but also received

support for livelihood restoration. For the households who have to relocate to other

place, in addition to payment for affected assets, they will receive a financial support

higher than households who resettle in place. Those households also will receive an

amount 80,000,000 dong instead 64,000,000 dong for the households selected to build

housing on channel bank (illegal construction). All relocation households will be invited to

Page 58: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

58 | P a g e

participate to livelihood restoration program.

77. However, as mentioned above, compensation for AHs in Ba Rai – Phu An subproject is

being carried out. Therefore, some households located at construction area of sewers

had received compensation above in the first compensation phase of the subproject. The

households located at remaining communes would be received compensation above in

the next compensaton phase. For the households already received cash compensation,

they are rebuilding their new house. Survey results show that, households are satisfied

with resettlement policies, support of the subproject.

78. General, the support for relocation have not been provided to all relocation households.

Tien Giang PPMU and authorities at all levels have actively solved to ensure affected

people’s entitlements through compensation and assistance implementation was

compliant with the provisions of national laws and regulations, conformity to

requirements of the approved resettlement documents and the SPS, 2009 and

regulations of GoV.

79. For the Cai Cai channel works subproject, three (03) communes in low lying areas would

be embanked to ensure living condition for people in subproject area. This will reduce

negative impacts of inundation by leveling. Soil for leveling would be taken from channel.

75 households located at plot no.4, Tan Phuoc commune must temporarily relocate to

another place for leveling in this area. 75 households will lose their current housing but

their land would not. After leveling completed, these households will go back and rebuild

their housing. These households must resettle twice. There are 8 permanent houses (4

houses were made by reinforced concrete structure and remaining houses were made

by wood) of 8 households. Heads of the householdsare required to retain their house

instead of breaking down it. Therefore, such households would be reinforced to avoid the

influences of leveling process. 4 other households would lose their house by

construction of two bridges, in which, 3 households must relocate to new resettlement

area, the remaining household will rebuild house on their residentialland plot.

80. Monitoring results show that, 75 households located at plot no.4, Tan Phuoc commune

must relocate and conduct temporary resettlement at opposite side of river. These

households had already received compensation and are constructing their house on new

resettlement area as well as moving on temporary house at temporary resettlement

area. Some households are building new house in new resettlement area and they are

still staying at their current house till the subproject starts the construction. All

households are satisfied with compensation of the subproject. The current life of the

households does not change because the temporary resettlement location is opposite to

their old house (just across the road). However, some households recommended that

when project completed, they will go back to rebuild house. These households were

concerned that compensation cash is not enough to buy new house on old place if

occurring the incurred charges. For 04 households affected by construction of bridges

Ca Trap II and Ca Trap III, these households already received cash compensation,

Page 59: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

59 | P a g e

allowances and land plot in resettlement site and their life is stable in new place.

81. For 8 households located at plot no.4, according to initial plan, 08 permanent houses (4

houses were made by reinforced concrete structure and remaining houses were made

by wood) will be strengthened to avoid the impacts of leveling process. The cost for

strengthening these houses has been calculated, however, at the time of compensation

payment for 8 households, they desired to receive additional cost compared to initial

cost, 2/8 households have changed their options and want to be relocated in temporary

resettlement site like 75 AHs mentioned above. Currently, plan to provide additional

support cost for 8 households are being considered and submitted to Tan Hong PPC for

approval.

5.2.8. Grievance Redress Mechanisms

82. RP and RP updated of sub-projects have a well-defined grievance redress and

resolution mechanism has been established with 4 steps. Complaint Files are stored at

all levels. At commune level, The People Commitee is responsible for documenting and

keeping file of all complaints that it handles. At districtlevel, LFDC is responsible for

documenting and keeping file of all complaints that it handles.

83. Two subprojects didn’thave any complaints/claims, only issue of 8 households located at

plot no.4, Tan Phuoc commune in Cai Cai channel works subproject area. These

households recommended to have an additional cost and 2/8 households want to be

arranged in temporary resettlement area. Besides, some households complained

verbally during DMS process and requested to verify the legal status of land and

property. Most of these problems have been reviewed thourougly by DCFLPs in

coordination with local government communes/wards in the sub-project area, and

specific solutions have been provided as mentioned in paragraph 43 above.

84. Thus, excpet to the requests of 8 households located at plot no.4 for additional cost, the

subproject does not have any unresolved complaint relating to compensation, support

and resettlement. For Cai Cai canal works, Dong Thap PPMU and relevant agencies

should review fast and consider requests of 8 these households (if it is reasonable). For

Ba Rai – Phu An subproject, Tien Giang PPMU/LDFCs of Cai Lay town, Cai Lay district

and Cai Be district should coordinate with relevant departments to make payment of

compensation, support soon for AHs.

5.2.9. Satisfaction of the Affected People on Resettlement Implementation.

85. All affected households are aware the importance and benefit of Subproject. Hence,

affected people as well as non-affected people extremely welcome to this subproject,

they also recommend Tien Giang PPMU and Dong Thap PPMU shall deploy soon the

works.

86. The results of monitoring show that most of affected people are satisfactory with

compensation of project: i) All households that received compensation cash, support and

Page 60: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

60 | P a g e

resettlement are satisfied with project’s policies as well as compensation cost; ii) For the

households that have not received cash compensation or partial cash compensation,

they also feel satisfied to receive cash compensation, support and resettlement in the

next phase. Therefore, they want Tien Giang PPMU and Dong Thap PPMU will quickly

arrange payment for compensation, support and resettlement, so they can stabilize their

life soon.

87. According to IMO, Tien Giang PPMU, Dong Thap PPMU and LFDCs and authorities at

all levels have actively solved issues araising in land acquisition and resettlement

process to ensure that the implementation of affected people’s entitlements through

compensation and assistance was in compliance with the provisions of national laws and

regulations, conformity to requirements of the approved resettlement documents and the

SPS, 2009.

5.2.10. Impacts on gender and strategy .

88. The subproject “Construction of flood controlling system in Ba Rai – Phu An region, Tien

Giang province” has totally 247 households (309 populations) affected by agricultural

land acquisition, in which has 46/247 households with female-headed. For the Cai Cai

channel works subproject, total affected households is 153 households (632

populations), there is no female-headed household. Women are more affected than men

because the opportunity of finding new job of women are more difficult than men (due to

health, knowledge, awareness, and sometimes it also is prejudices).

89. In process of land acquisition and site clearance, Tien Giang PPC, LDFCs of Cai Lay

town, Cai Lay district and Cai Be district, CPCs in project area have focused on solving

issues above and supporting such affected people, especially affected households that

woman is female-headed. The following activities were conducted:

- Socio-economic data, labor distribution and scope of effect have been collected and

separated by gender

- Disclosure information and public consultation have been carried out to ensure the

participations of male and female in an effort encouraging female’s participation to

make a decision. Series of disclosure information and public consultation have been

implemented with 43.67% of total meeting participants are females.

- Assistance measures to protect economic-social status for vulnerable households

such as households headed by women, poor householdsV with an appropriate

cost.

- In case the project allocates new land or house rights for,relocated households,

land use right have to issue to both husband and wife.

- Compensation and assistance in cash was given to both husband and wife.

90. Besides, Women's Unions in Hong Ngu district, especially Thuong Phuoc 2 and Thuong

Thoi Tien commune have been frequently carried out well their own roles in

Page 61: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

61 | P a g e

implementation and coordination with PC at all levels to disseminate, propagate and

raise women’s role in supervision and social commentary. This Women’s Union also

participates in checking, monitoring the implementation of the policies that related to

women, children, elderly people, people with disabilityV. to protect the rights of

vulnerable groups and promote equal rights for women in province in general, and

affected people (mainly are women) by the subproject in particular.

5.3. Outstanding issues

91. As mentioned in Section 5.2, the outstanding issues to be solved can be summarized as

follows:

- For the 8 AHs located at plot no.4, Tan Phuoc commune in Cai Cai channel works

subproject, those households desire to receive additional cost for reinforcing their

house and 2/8 households want to be moved in temporary resettlement site similar to

75 households as mentioned above. Such cases would be reviewed and considered by

Dong Thap PPMU, Tan Hong DPC and local authorities for approval (if it is

reasonable).

- For Ba Rai – Phu An subproject, up to now, no complaints/claims of households do

existhowever, payment for compensation, support and resettlement is quite slow. Thus,

Tien Giang PPMU, Tien Giang PPC, LDFCs of Cai Lay town, Cai Lay district and Cai

Be district should coordinate with relevant agencies to accelerate the payment process

to the remaining AHs to avoid the influence to project progress.

- Both Ba Rai – Phu An and Cai Cai channel subprojects, livelihood and production

stabilization program for AHs (lost over 10% agricultural area). The AHs received an

amount according to regulation of Tien Giang and Dong Thap PPC. Thus, an plan for

additional fund to offset the difference between PPC’s regulations and the proposed

policies in uRPs needs to be quickly finalized, submitted for approval and implemented

for APs

- Income restoration program for severely affected households and vulnerable

households in two subprojects has not been carried out. Therefore, after compensation

completed, Tien Giang PPMU, Dong Thap PPMU and LFDC should coordinate with

local authorities to deploy livelihood restoration program, ensure a stable life for local

people after carrying out land acquisition.

5.4. Recommended action plan and responsibility for implementing action plan

92. After the report has been reviewed and disclosed by ADB, CPO/CPMU will take the

responsible to implement action plan to fix all findings.

93. CPO/CPMU will officially inform to DARD and Tien Giang PPMU, DARD and Dong Thap

PPMU all findings and request Tien Giang DARD/PPMU, Dong Thap DARD/PPMU for

action. Although Tien Giang DARD/PPMU and Dong Thap DARD/PPMU discussed and

agreed with the results and the actions needed in the monitoring reports, official letters

Page 62: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

62 | P a g e

from CPO/CPMU about the findings and request the executive action is crucial to

DARD/PPMU can work with PPCs participating to the project.

94. Tien Giang, Dong Thap Province People's Committee makes a decision for solving the

problem and allocate budget for the implementation of solving problems that still exist.

95. DARD/PPMU of Tien Giang and Dong Thap province, PCs of districts/towns, LDFC will

perform the action.

96. Independent monitoring consultant will monitor the implementation of the action plan.

Table 12: Proposed action plan and responsibility of stakeholders

STT Activites Responsible Time frame

1

Announcement/discussion with

CPO/CPMU on the findings and

necessary actions

ADB First week of

January, 2017

2

Announcement/discussion with Tien

Giang DADR/ Tien Giang PPMU on

the findings and necessary actions

CPO/CPMU Second week of

January, 2017

3

Working with Tien Giang/Dong Thap

Province People's Committee for

decision-making for solving the

problem

DADR/PPMU Fourth week of

January, 2017

4 Making decisions for solving the

problem and allocate budget

Tien Giang Province

People's Committee

Fourth week of

January, 2017

5

Summary the content of Monitoring

Report # 3on an one page

information paper

Tien Giang/Dong Thap

Province People's

Committee

Fourth week of

January, 2017

6

Annoucement the information

document and decision of Tien

Giang Province People

PPMU/ PCP, District

Fourth week of

January, 2017

7 Solving the problems PPMU/ PCP, District February, 2017

8 Monitoring implementation of the

action plans

Independent

monitoring consultant

Beginning of May,

2017

Page 63: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

63 | P a g e

VI. CONCLUSION AND RECOMMENDATION

6.1. Conclusion

97. As mentioned above, the compensation, support and resettlement plans of the two sub-

projects Bai Rai – Phu An and Cai Cai canal divided into several phases. The first phase

includes the compensation of land, houses, building, plans, animals and assets

compensation assistance for resettlement, changing occupation and creation jobs

program, stabilization production life in accordance with Provincial People's Committee.

The support program under policies of the project proposed in uRP containing income

restoration program, support for vulnerable households, the difference of the amount

supporting for livelihood and production stabilization program between PPC’s regulations

and the proposed policiesy in uRPs would be additionally implemented for the next

phases

98. Up to now, the Ba Rai – Phu An subproject has carried out payment of compensation

cash, support and resettlement for 126/247 households located at construction area of

13 sewers, in which 9 sewers located inCai Lay district including: Cay Sung, Cai Na,

Giong Tre 2 (Hiep Duc commune), Khang Chien, Ba Gon, Hai Hue (Hoi Xuan

commune), Thay Thanh (Hoi Xuan and Cam Son commune); Thong Luu (Phu An

commune), Ong Bang (Cam Son commune); 4 sewer located in Cai Lay town including:

Ca Chat, Ca Nua (Thanh Hoa commune), Khach Minh, Lo Lang (Tan Binh commune).

Total compensation cost, which has been directly paid to AHs, is about 26,204,766,000

VND out of 53,394,096,000 VND. The remaining AHs have not been received

compensation cash, support and resettlement because of the delay in allocating budget

for land acquisition.

99. The Cai Cai channel works subproject already completed payment of compensation,

support and resettlement for 145/153 AHs, including 70 AHs located in plot no.1 (Thong

Binh commune), plot no.2 and no.3 (Tan Thanh A commune), At Bo sewer, Ba Hai Mot

sewer, Bay Thua sewer (Thong Binh commune), Nga Tu sewer (Tan Phuoc commune),

Cau Ca Trap II, Cau Ca Trap III and 75/83 AHs located at plot no.4 (Tan Phuoc

commune). Total compensation cost, which has been directly paid to AHs, is about

31,600,000,000 VND out of 31,948,882,500 VND. Thus, only 08 remaining households

in the subproject have not received compensation and support. Currently, plan to provide

additional support cost for 8 households are being considered and submitted to Tan

Hong PPC for approval.

100. With the argument presented above, therefore Income restoration program for

severely affected households and vulnerable households and stabilization of production

life for severely affected households under policies in two subprojects has not been

carried out. After compensation completed, Tien Giang PPMU, Dong Thap PPMU and

LFDCs should coordinate with local authorities to immediately deploy plans to ensure

benefits and life stabilization for local people.

Page 64: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

64 | P a g e

101. Basically, Tien Giang PMU, Dong Thap PPMU and DCCS have complied with

the resettlement procedures presented in the sub-project RP and in Decree No.

84/2007/ND-CP by the Government of Vietnam. Representatives of the affected people

and relating sectors participate in and monitor the project information disclosure,

inventory, and compensation payment. Complaints by the affected people have been

received and settled timely by the PMU and the authorities. Internal monitoring has also

been implemented by Tien Giang PPMU, Dong Thap PPMU.

102. Resettlement data, documents are stored at DLFDCs and PPMU in form of

paper documents and computers for management and reporting purposes. Tien Giang,

Dong Thap PPMU has assigneda staff in charge ofCompensation and resettlement to

cooperate with DLFDCs in implementing compensation and clearance for the project.

With this operation, implementation of the project compensation and resettlement has

been precise, objective and easy, the affected people’s grievances have been treated

timely and the resettlement implementation progress has been ensured.

6.2. Recommendation

103. To ensure rights and benefits of the affected people, help them promptly

settling down, developing production and to be able to construct the sub-project at the

planned progress, IMO have some recommendations as follows:

For the Ba Rai – Phu An subproject:

- Tien Giang PPC should quickly approve and provide budget to Tien Giang PPMU

and LFDCs for the payment of compensation cash to 121 remaining AHs

- Tien Giang PMU, DCCS and DLFDC need make payment of compensation and

assistances to AHs quickly.

(i) Tien Giang PPMU needs to enhance monitoring during the construction phase to

ensure that any negative impacts on the local people during construction will be

measured and compensated timely in accordance with the project policies. During

this period, the PMU still needs to arrange specialized staff to perform the tasks of

internal supervision, uses the form 1 and 2 referred to in Annex 6 of this report.

For the Cai Cai channel works subproject

- For the 8 AHs located at plot no.4, Tan Phuoc commune in Cai Cai channel works

subproject, those households desire to receive additional cost for reinforcing their

house and 2/8 households want to be arranged in temporary resettlement area

similar to 75 households as mentioned above. Such cases shall be reviewed and

considered by Dong Thap PPMU, Tan Hong DPC and local authorities (if it is

reasonable) to avoid negative impacts to project progress.

General issues of two subprojects:

- Tien Giang PPMU/Dong Thap PPMU should enhance to supervise contractor to

ensure that there have no adverse impacts occurring during construction. In this

Page 65: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

65 | P a g e

stage, PMU should arrange staffs for performing internal supervision by using

forms no.1 and no.2, which have been attached to appendix 4 in the report.

- Income restoration and support for stabilization of production life program for

severely affected households and for vulnerable households in two subprojects

has not been carried out. Therefore, after compensation completed, request to

Tien Giang PPMU, Dong Thap PPMU and LFDC should coordinate with local

authorities to accelerate immediately after completing the first payment for BAHs

and implement livelihood restoration program after completing the compensation

payment for AHs to ensure stable life for local people after carrying out project

- The payment of compensation cash of two subprojects has not been completed

fully however, the payment of compensation cash had been carried out well at

several works of two subprojects such as construction area of sewers (Ba Rai –

Phu An subproject); plots, construction area of sewers and bridge (Cai Cai channel

works subproject). Therefore, in order to ensure project progress, Tien Giang

PPMU/Dong Thap PPMU should recommend CPO for the commencement of

construction in several locations, which had been completed payment of

compensation cash to AHs, These locations include:

+ Sewers in Ba Rai – Phu An subproject: 9 sewers belonged to Cai Lay district

include sewers as following: Cay Sung, Cai Na, Giong Tre 2 (Hiep Duc commune),

Khang Chien, Ba Gon, Hai Hue (Hoi Xuan commune), Thay Thanh (Hoi Xuan and

Cam Son commune); Thong Luu (Phu An commune), Ong Bang (Cam Son

commune); 4 sewers belonged to Cai Lay town include sewers as following: Ca

Chat, Ca Nua (Thanh Hoa commune), Khach Minh, Lo Lang (Tan Binh commune).

+ All items of Cai Cai channel works subproject, except area of plot no.4

Page 66: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #2 PERIODIC REPORT

66 | P a g e

1. Minutes of work between the IMO and the implementing agencies 2. Some typical images during monitoring 3. List the interviewed households 4. Internal monitoring form

5. Decision no.2183/QD-UBND dated 16 May, 2015 6. Decision No 3067/QD – UBND dated 16 May, 2016 7. Decision no 4232/QD-UBND dated 01 June, 2016 8. Decision No 805/QD – UBND dated 10 August, 2016 9. Minute of approving the draft compensation plan and the temporary

compensation value for households 10. Minute of public posting of the draft compensation plan and the temporary

compensation value. 11. Confirmation of the ending time of the public posting of the proposed

compensation plan and the value of temporary compensation for affected households.

12. Detail compensation plan for each affected households 13. Working miniute between 8 Ahs and LFDC of Tan Hong Dictrict with Tan Phuoc

CPC 14. Affected property declaration 15. Inventory minutes of land, housing, structure on land and crops, trees of AHs

16. List of BAHs receiving cash aid

17. Payment for AHs

18. Notification of the confirmation of sales, the amount of tax paid to state budget by Doan Van Banh’ household and details of support

19. Minutes of receiving and commiting to relocate

LFDCS

Page 67: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

67 | P a g e

Appendix 1–MINUTES OF WORK BETWEEN THE IMO AND THE IMPLEMENTING AGENCIES

Page 68: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

68 | P a g e

Page 69: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

69 | P a g e

Page 70: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

70 | P a g e

Page 71: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

71 | P a g e

Page 72: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

72 | P a g e

Page 73: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

73 | P a g e

Page 74: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

74 | P a g e

Page 75: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

75 | P a g e

Page 76: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

76 | P a g e

Page 77: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

77 | P a g e

Page 78: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

78 | P a g e

Page 79: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

79 | P a g e

Page 80: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

80 | P a g e

Page 81: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

81 | P a g e

Page 82: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #2 PERIODIC REPORT

82 | P a g e

Appendix 2–SOME TYPICAL IMAGES DURING MONITORING

Page 83: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #2 PERIODIC REPORT

83 | P a g e

Appendix 3– LIST OF THE INTERVIEWED HOUSEHOLDS

Page 84: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

84 | P a g e

Page 85: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

85 | P a g e

Page 86: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

86 | P a g e

Page 87: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

87 | P a g e

Page 88: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #2 PERIODIC REPORT

88 | P a g e

Page 89: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #2 PERIODIC REPORT

89 | P a g e

Appendix 4 - INTERNAL MONITORING FORM Sample 1: Monitoring the social security problem in the construction phase

(Applicable to the sub-projects in the construction phase)

PMU of VVVVVVVVVV. Date: VV./VV./VVV

Report period From: VV./VV./VVV To: VV./VV./VVV

Name of subproject:

Investment location:

No. The monitoring content The level / progress

1 Actual progress of ongoing projects (which stage?)

2 Site clearance and payment of compensation to affected people

3 The complaints related to compensation, support and resettlement of affected people by the time of reporting (if applicable)

The problems arise after completing the support policy of resettlement and livelihood recovery? (if any)

4 Assessment construction process, what effects that the project activities affect to the community (positive / negative)?

5 Conclusion, suggestions

[Signature and stamp]

Page 90: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #1 PERIODIC REPORT

90 | P a g e

INTERNAL MONITORING FORM

Sample 2: Settlement of complaints status.

PMU of VVVVVVVVVV. Date: VV./VV./VVV

Report period From: VV./VV./VVV To: VV./VV./VVV

Name of subproject:

Investment location:

Subproject/ Items

Commune level District level Board of compensation Ban QLDA tỉnh PPMU Cấp tỉnh Tòa án

Number of households complaint

Number of households were satisfactorily resolved

Number of households complaint

Number of households were satisfactorily resolved

Number of households complaint

Number of households were satisfactorily resolved

Number of households complaint

Number of households were satisfactorily resolved

Số hộ khiếu nại

Số hộ được giải quyết thỏa đáng

Số hộ khiếu nại

Số hộ được giải quyết thỏa đáng

Page 91: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1)

91 | P a g e

Appendix 5: Decision no.2183/QD-UBND dated 16 May, 2015

Page 92: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

92 | P a g e

Appendix 6: Decision No 3067/QD – UBND dated 16 May, 2016

Page 93: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

93 | P a g e

Appendix 7: Decision no 4232/QD-UBND dated 01 June, 2016

Page 94: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

94 | P a g e

Appendix 8 Decision No 805/QD – UBND dated 10 August, 2016

Page 95: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

95 | P a g e

Page 96: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

96 | P a g e

Appendix 9: Minute of approving the draft compensation plan and the temporary compensation value for households

Page 97: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

97 | P a g e

Page 98: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

98 | P a g e

Appendix 10: Minute of public posting of the draft compensation plan and the temporary compensation value.

Page 99: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

99 | P a g e

Appendix 11: Confirmation of the ending time of the public posting of the proposed compensation plan and the value of temporary compensation for

affected households.

Page 100: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

100 | P a g e

Appendix 12. Detail compensation plan for each affected households Phương án đền bù được lập chi tiết cho từng hộ BAH

Page 101: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

101 | P a g e

Appendix 13: Working miniute between 8 Ahs and LFDC of Tan Hong Dictrict with Tan Phuoc CPC

Page 102: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

102 | P a g e

Page 103: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

103 | P a g e

Page 104: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

104 | P a g e

Appendix 14: Affected property declaration

Page 105: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

105 | P a g e

Page 106: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

106 | P a g e

Appendix 15: Inventory minutes of land, housing, structure on land and crops, trees of AHs

Page 107: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

107 | P a g e

Page 108: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

108 | P a g e

Appendix 16: List of BAHs receiving cash aid

Page 109: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

109 | P a g e

Appendix 17: Payment for AHs

Page 110: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

110 | P a g e

Appendix 18: Notification of the confirmation of sales, the amount of tax paid to state budget by Doan Van Banh’ household and details of support money

UBND HUYỆN CAI LẬY CỘNG HÒA XÃ HỘI CHỦ NGHĨA VIỆT NAM

Page 111: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

111 | P a g e

TT PHÁT TRIỂN QUỸ ĐẤT

Độc lập - Tự do - Hạnh phúc

Cai Lậy, ngày tháng năm 2015

BẢNG TỔNG HỢP MẤT LỢI TỨC KINH DOANH ĐỐI VỚI HỘ ÔNG ĐOÀN VĂN BẢNH

TIỂU DỰ ÁN KIỂM SOÁT VÀ GIẢM RỦI RO DO LŨ VÙNG BA RÀI - PHÚ AN

Cống Đập Chùa - xã Bình Phú

STT Họ và tên Thu nhập chịu

thuế (đồng/tháng)

Đơn vị tính

(tháng)

Mức hỗ trợ (%)

Thành tiền (đồng)

Ghi chú

1 Đoàn Văn Bảnh (Cống Đập Chùa)

2013 5,264,000 12 15% 9,475,000

2014 2,340,000 12 15% 4,212,000

Quí I, II, III năm 2015

2,080,000 12 15% 3,744,000

Tổng: 03 năm 9,684,000 17,431,000

Tổng mức hỗ trợ (bình quân 3

năm) 3,228,000 12 15% 5,810,000

Bằng chữ: Năm triệu, tám trăm mười nghìn đồng đồng.

Page 112: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

112 | P a g e

Appendix 19: Minutes of receiving and commiting to relocate

Page 113: VIE: Greater Mekong Subregion Flood and Drought Risk ... · External Resettlement Monitoring Document stage: Final Project number: 40190 December 2016 VIE: Greater Mekong Subregion

GMS Flood and Drought Risk Management and Mitigation Project (ADB-GMS1) #3 PERIODIC REPORT

113 | P a g e