+ All Categories
Home > Documents > VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant...

VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant...

Date post: 06-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
20
Resettlement Monitoring Report Quarterly Report March June 2013 VIE: Mong Duong 1 Thermal Power Project Tranche 2 Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1.
Transcript
Page 1: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Resettlement Monitoring Report

Quarterly Report March – June 2013

VIE: Mong Duong 1 Thermal Power Project

– Tranche 2

Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1.

Page 2: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

EVN GENCO 3 Thermal Power Projects Management Board 1 (TPMB1)

MONG DUONG (2 x 500MW) THERMAL POWER PLANT PROJECT

INTERNAL RESETLEMENT MONITORING QUARTERLY REPORT Period 1st March to 30th June 2013

Contract No: TPMB1-EVN/ADB-2610L2MFF-Consulting-002

Page 3: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 2 of 19

Table of Contents

ABBREVIATIONS ................................................................................................................. 3

I. GENERAL INFORMATION OF THE PROJECT ........................................................ 4

1.1. Mong duong Thermal Power Plant Project ........................................................... 4

1.2. The Fresh Water Component .............................................................................. 4

1.3. The Scope of Land Acquisition and Resettlement ................................................ 4

II. DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS .............................. 6

2.1. Information Disclosure and Community Participation ........................................... 6

2.2. Detailed Measurement Survey ............................................................................. 6

2.3. Compensation payment, assistance and resettlement ......................................... 7

2.4. Process of resettlement and site clearance ......................................................... 7

2.5. Restoration of APs’ livelihoods and rehabilitation of APs’ lives ............................ 7

2.6. Assess degree of APs’ satisfaction of compensation and resettlement ................ 7

2.7. Conformity of resettlement implementation progress with civil works progress and next plan ......................................................................................................................... 8

2.8. Issues concerning gender and ethnic minority ..................................................... 8

III. PENDING ISSUES ..................................................................................................... 8

3.1. Outstanding problems .......................................................................................... 8

3.2. Solutions for pending issues and responsibility of relevant agencies ................... 8

IV. CONCLUSIONS AND RECOMMENDATIONS .......................................................... 9

4.1. Conclusions ......................................................................................................... 9

4.2. Recommendations ............................................................................................... 9

APPENDIX .......................................................................................................................... 10

Appendix 1 List of interviewed people ........................................................................... 10

Appendix 2: ................................................................................................................... 13

Page 4: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 3 of 19

ABBREVIATIONS

DCARB District compensation, Assistance, and Resettlement Board

DMS Detailed Measurement Survey

EVN Electricity of Viet Nam

FWC Freshwater Component

PAP Project Affected Person

PMU Project Management Unit

PPC Provincial People's Committee

RAP Resettlement Action Plan

TPP Thermal Power Plant

TPMB1 Thermal Power Plant Project Management Unit No. 1

TRC Town Resettlement Committee

Page 5: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 4 of 19

I. GENERAL INFORMATION OF THE PROJECT

1.1. Mong duong Thermal Power Plant Project

Mong Duong Thermal Power Plant complex with a total combined capacity of 2’200 MW, is located in the Mong Duong Ward (Cam Pha town, Quang Ninh province). It is situated along Highway 18, 300 km northeast of Hanoi and 18 km from the Center of Cam Pha town. The Project site is located at the mouth of the Mong Duong River and includes one ward (Mong Duong) and one commune (Cam Hai). The objective of building this Plant is to increase the capacity of the thermal electric power source and contribute to the stable supply of electricity throughout the year and especially in the dry season when the hydro plants do not generate much of their maximum capacity

1.2. The Fresh Water Component

The Mong Duong Thermal Generation Plant complex needs a large amount of fresh water from Quarter Four, 2013. It is calculated that, the combined Plant needs 15.000 m3 of fresh water per day. A fresh water supply system therefore must be constructed to serve the project. The system consists of the reservoir, the pumping station, the 10 KV power supply to serve for the pumping station, the water pipe line, and the access road.

Of which, only the Reservoir area and the Water Pineline area relate to land acquisition and resettlement.

1.3. The Scope of Land Acquisition and Resettlement

Based on the detailed design, a total area of 1,618,263.96 m2 with 183 households will be permanently affected. Among the permanently affected land, 1,163,813.86 m2 is affected by the reservoir in Mong Duong Ward and 454,450.1 m2 by the pipe-line and other works (access road, powerhouse, etc) in Cong Hoa Commune and Cam Hai Commune (Cam Pha City). 42.3% of affected area is productive forest land which is currently used for planting Acacia of 71 households (373 persons) in three communes/wards. FWC will also affect 6,903.30 m2 of residential land of 37 households (170 persons) in Village 10, Mong Duong Ward. Cong Hoa and Cam Hai communes will not have residential land affected by the FWCt. Area, number of households and persons of affected land are shown detailed in Table 1 and Table 2.

The categories of permanently affected lands are as below.

Table 1: Affected Land Area Categorized by Communes

No Categories of affected land

Reservoir Pipe line

Total (m2) Mong Duong Ward (m2)

Cong Hoa Commune

(m2)

Cam Hai Commune

(m2) Sub-total

(m2)

1 Residential land 6,903.30 - - - 6,903.30

2 Garden land 42,647.82 2,577.10 - 2,577.10 45,224.92

3 Land for annual crops 183,593.18 - - - 183,593.18

4 Land for perennial trees 434,044.01 5,653.00 17,559.00 23,212.00 457,256.01

5 Forest land (Acacia) 283,886.00 289,250.30 111,513.00 400,763.30 684,649.30

Page 6: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 5 of 19

No Categories of affected land

Reservoir Pipe line

Total (m2) Mong Duong Ward (m2)

Cong Hoa Commune

(m2)

Cam Hai Commune

(m2) Sub-total

(m2)

6 Aquaculture land 4,419.80 229.00 2,000.00 2,229.00 6,648.80

7 Public land 208,319.75 5,234.50 13,067.20 18,301.70 226,621.45

8 Land of Army 7,367.00 7,367.00 7,367.00

Total 1,163,813.86 310,310.90 144,139.20 454,450.10 1,618,263.96

(Source: Updated Resettlement Plan)

Table 2 Number of HHs and Persons whose land affected in each Commune

No Categories of affected land

Mong Duong Ward Cong Hoa Commune Cam Hai Commune Total

No. of AHs (HH)

No. of APs

(person)

No. of AHs (HH)

No. of APs

(person)

No. of AHs (HH)

No. of APs

(person)

No. of AHs (HH)

No. of APs

(person)

1 Residential land 37 170 0 0 0 0 37 170

2 Garden land 40 187 4 15 0 0 44 202

3 Annual crop land 61 272 0 0 0 0 61 272

4 Perennial tree land 90 360 2 7 2 6 94 373

5 Forest land (for acacia planting)

19 88 35 148 17 69 71 305

6 Aquaculture land 7 41 1 4 1 4 9 49

(Source: Updated Resettlement Plan)

Page 7: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 6 of 19

II. DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS

Detailed on the progress of Resettlement Plan Implementation is in the Annex 2

2.1. Information Disclosure and Community Participation

Information dissemination was conducted by Thermal Power Project Management Unit No.1 (TPMB1) and DCARB of Cam Pha city. Orientation meetings have been conducted since 2009 with relevant parties and affected households. Project information has been delivered to 100% affected households (such as introduction of detailed technical design, scope of impacts on land and asset upon on lands, entitlements for compensation, assistance and resettlement, implementation schedule of land acquisition, compensation, assistance and resettlement and grievance redress mechanism). The documents have also been placed in public places and in the house of village leaders and head of mass-organization

Consultation activities have been carried out in the form of public meetings. Participants of public meetings include all affected households, local authorities, head of mass- organizations and village leaders. There were many public meetings with the households affected by project organized from 2009 up to date. The total of participant is 615 people, of whom 235 people were female (accounting for 38.2%).

Consultations continue to be deployed in the project area through community meetings.-100% of affected households were consulted 3 times or more on the project’ policy of land acquisition, compensation, support, and resettlement.

For the households who have recommendations, inquiries or complaints, TPMB1 cooperated with the local government and leaders of the villages to organize meetings, direct dialogue, to resolve satisfactorily and ensure the entitlements of affected people.

Affected people have been consulted on the needs of participating in the income restoration program, however, many households are still not aware of the importance of the program, therefore, they are not ready to participate in the program. Propaganda, information disseminating to these households will be continuously performed during the implementation of the income restoration program.

The consultation process has also paid its attention to the needs of women and vulnerable groups such as the poor, single women headed household, elderly or some other policy objects.

Due to the Consultants providing information adequately and transparently on compensation entitlements the complaints of affected people are not considerable in numbers.

2.2. Detailed Measurement Survey

Detailed Measurement Survey was completed before November 10th, 2012. However some added surveys are still continueing due to changes in technical alternatives or some assets outside the project sites but is no longer valid for use left.

As of June 30th, 2013, the discrepancies and omissions in the loss inventory process or other damages arising due to changes in technical alternatives or some assets outside the project sites but is no longer valid for use caused by land acquisition was timely inventory replenishment to ensure the entitlements of the affected people, ensuring compliance RP framework of the project.

Page 8: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 7 of 19

2.3. Compensation payment, assistance and resettlement

As of June 30th, 2013, the total budget of approved compensation, assistance and resettlement is VND65,627,501,800 and VND44,046,332,200 has been paid for the affected people (including budget for the DCARB), reached 75%.

Compensation payment was completed for the Pipeline component. Total of unpaid budget is VND16,513,007,300, this will be paid for the Reservoir Component before September, 2013.

Specifically compensation schedule for each component is as follows: • Pipeline Component: Total amount approved is VND10,738,062,600, paid 100% to the

affected people

• Reservoir Component: The total amount approved is VND54,889,439,200, paid VND33,308,269,600, accounting for 60.7% of the approved budget.

2.4. Process of resettlement and site clearance

As of June 30th, 2013, the land acquisition and resettlement has achieved good results, the site clearance is completed for the Pipeline Component (Cộng Hoà and Cẩm Hải communes). Site clearance rate for Reservoir Component has completed 61.5%. And it is going to be completed in September 15th, 2013.

There are total 37 resettled households, concentrated in Reservoir Component and all of them agreed to resettle freely. 10/37 of households returned their fatherland in another province such as Hai Phong, Lang Son, Bac Giang. There are immigrant households those moved to this area during 15 -25 years ago.

There are 6 households completed their resettled house, 21 resettled houses are under construction. All these houses locate near the main road, school and health station. The electricity is available in the area from this month and these households can access national electricity system.

2.5. Restoration of APs’ livelihoods and rehabilitation of APs’ lives

All the affected households received full assistances according to project policies such as living stabilization assistance, occupation transmission assistance, and business stabilization assistance.

The project has conducted surveys for livelihood needs of households affected by the project. Based on the needs of people affected, the income restoration program is developing and will be submitted to the ADB for approval within September 2013. The program is intended to be fully implemented in October 2013.

2.6. Assess degree of APs’ satisfaction of compensation and resettlement

The local people in general are satisfied with the result of the lost inventory, compensation price assistance and resettlement policies of the Project.

As of June 30th, 2013, there is only one complaints from one affected household relates to misidentify the acquired land. And this issue was solved.

Page 9: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 8 of 19

2.7. Conformity of resettlement implementation progress with civil works progress and next plan

Compensation and relocation of resettled households have been delayed in comparison with the site clearance and construction progress as well as overall plan of the project. However, the Project tried ensuring the cleared sites for construction.

2.8. Issues concerning gender and ethnic minority

The Cam Pha Town Resettlement Committee (TRC) include women representatives from the Mong Duong Ward and Women Union of the Residential Area No.10 to represent the interests of women in the affected households. Capacity-building training were provided to the leaders of the Women's Union, by the social consultant of the TPMB1, to increase their participation in the TRC. The participation of women in leadership and decision making in resettlement planning were guaranteed through equal representation of men and women during the resettlement implementation.

The population of the commune mostly affected by the project, Ward No. 10, is inhabited predominantly by members of the two ethnic minorities living in this area, Dao and Tay, while in the area affected by the pipeline, the majority is Kinh. The community consultation, project information disclosure for all PAPs, including ethnic minorities have been conducted in the project during the project implementation by TPMB1, People Committee of Mong duong, and the Communes in the project regions. Seriously the Asian Development Bank has provided affected households in the vulnerable group including minorities with a certain amount to support their life and livelihood development in compliance with the updated RP and legal framework

III. PENDING ISSUES

3.1. Outstanding problems

The Community consultation for the project was conducted by the DCARB of Cam Pha city; however, such consultation is not regular and continuous and is limited during the project implementation. Therefore it is essential to do the community consultation during the project implementation, particularly, in the activities of resettlement, and also necessary to organize meetings to listen to the opinions of the households and communities to understand their opinion

According to the RP, compensation payment was planned within December 2012. However, the compensation payment have been delayed comparing to the RP. It is going to complete within September 2013.

The income restoration program is still not implemented due to the TPMB1 was not aware about the benefits of the Program to the affected households.

3.2. Solutions for pending issues and responsibility of relevant agencies

Meeting with the local people have to be more frequently organized

TPMB1 is cooperating with the Land Fund Development Center, City PPC, leaders of the villages and other stakeholders to accelerate the progress of compensation payment and resettlement for the affected households to hand over the sites for the contractors within September.

Income restoration program is developing and will be submitted to the ADB for approval in September and it is anticipated to start carrying out from October 2013.

Page 10: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 9 of 19

IV. CONCLUSIONS AND RECOMMENDATIONS

4.1. Conclusions

Implementing the activities on compensation, assistance and resettlement were delayed in comparison with the approved resettlement plan. Progress on compensation and resettlement implementation until August 20, 2013 is 79%. The compensation payment completed 75% of total of anticipated compensation budget. 25% of remaining budget is anticipated to be paid for the APs within September 2013. Up to date, there is only one complaint letter from one affected household and it was solved satisfactorily, ensuring the rights of the affected household.

Information dissemination, community consultation have witnessed the cooperation of DCARBs of Cam Pha city along with Mong Duong ward in the project region and have basically conducted as per the regulated process. resulting in the certain efficiency The complaints of affected people are not considerable

The income restoration program is developing and it’s intent is to be completed and implemented by October 2013.

4.2. Recommendations

The PC of Quang Ninh province, and DCARBs of Cam Pha city should pay special attention and put emphasis on households that have to move to another place. The PC should approve, make decisions and create favorable conditions for remaining households to move to the new place

TPMB1 should closely cooperate with the PC of Quang Ninh province, Cam Pha city, and DCARBs of city to support and create favorable conditions of compensation funds, to help the locality to resolve shortcomings related to land acquisition and resettlement in an effective and timely manner to ensure the planned implementation of the project

Information dissemination and community consultation should be continued during the project

Page 11: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 10 of 19

APPENDIX

Appendix 1 List of interviewed people

List of authorities

No Persons met Institution, contact Main Topics / Observations

1 Mr. Chuyen Chief, Land Management Office, Mong Duong

• Collect some general information on Mong duong community

2 Ms. Nguyen Thi Dang Mr. Nguyen Van Nuc

Village Leader, Ward 10 MD Party Leader, Ward 10 MD

• Organisation of interviews and public meeting

• Received some genera information on Ward 10 (village belonging to Mong Duong community, affected by project

3 Ms. Nguyen Thi Dang Mr. Nguyen Van Nuc

Village Leader, Ward 10 MD Party Leader, Ward 10 MD Village elder PAPs

• Explanation of envisaged procedure

• Carried out FGD with women (19 participants)

• Carried out individual interviews with representatives of affected HH

4 Mr. Ta Van Ngoc Chief of Health Post of Ward 10 village

• Discussed situation of health services in the village

• Health post is rather new construction, with sufficient space, but lack of equipment and infrastructure (no water, no toilets, no laboratory equipment, very limited stock of medicaments, few instruments.

• Women give birth in District Hospital (bad road conditions!) or at home, since health post is not equipped properly.

5 Mr. Thien Vice President of Community Committee, Cam Hai

• Received some general information on Cam Hai community (affected by pipe line)

• Mr. Thien organised interviews with PAPs

6 Mr. Dinh Van Luc Vice President of Community Committee, Cong Hoa

• Received some general information on Cong Hoa community (affected by pipe line)

• Received permission to carry out interviews with PAPs

7 Mr. Pham Van Chien Mr. Chuyen

Vice President of Community Committee, Mong Duong Chief, Land Management Office, Mong Duong

• Oriented the community officials on the outcome of the field mission.

• According to Mr. Pham Van Chen, there should be a specific policy for ethnic minorities, as is the case in provinces/districts in mountainous areas.

Page 12: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 11 of 19

List of interview of affected people

No Full name Position/address

Fresh Water component

1 Phoòng Cắm Công Mong duong ward

2 Phoòng Cắm Tắc Mong duong ward

3 Nông Quốc Khánh Mong duong ward

4 Nông Văn Toản Mong duong ward

5 Lý Văn Việt Mong duong ward

6 Lý Xuân Cảnh Mong duong ward

7 Lý Xuân Minh Mong duong ward

8 Phùn Văn Tư Mong duong ward

9 Tạ Hữu Hợi Mong duong ward

10 Tiến (Đặng Phúc Tiến) Mong duong ward

11 Triệu Chăn Thống Mong duong ward

12 Triệu Kim Tề Mong duong ward

13 Triệu Quang Sáu Mong duong ward

14 Triệu Quý Bình Mong duong ward

15 Triệu Quý Dếnh Mong duong ward

Cam Hai commune

1 Nguyen Duc Nhuan Cam Hai commune

2 Ha Van Duong Cam Hai commune

3 Pham Ba Quyet Cam Hai commune

4 Hoang Van Ngoc Cam Hai commune

5 Do Van Ly Cam Hai commune

6 Nguyen Van Viet Cam Hai commune

7 Nguyen Van Tan Cam Hai commune

8 Bui Van Tay Cam Hai commune

9 Dao Xuan Quang Cam Hai commune

Page 13: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 12 of 19

No Full name Position/address

10 Tran Thi Thuy Nga Cam Hai commune

11 Pham Thi Thu Anh Cam Hai commune

12 Truong Thi Diu Cam Hai commune

Cong hoa Commune

1 Be Van Mit Cong Hoa commune

2 Bui Huu Dai Cong Hoa commune

3 Bui Huu Luan Cong Hoa commune

4 Ha Thi Thuy Cong Hoa commune

5 Ha Van Luu Cong Hoa commune

6 Ha Van Thuy Cong Hoa commune

7 Hoang Van Toan Cong Hoa commune

8 Nguyen Van Thanh Cong Hoa commune

9 Nong Van Lan Cong Hoa commune

10 Phan Thi Nhat Cong Hoa commune

11 Nguyen Ngoc Hien Cong Hoa commune

12 Nguyen Van Phuong Cong Hoa commune

13 Ha Van Nam Cong Hoa commune

14 Hoang Thi Minh Cong Hoa commune

Page 14: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 13 of 19

Appendix 2

Form 1: Situation of Compensation Payment until 31/6/2013

No Component

Date of project imformation

dessemination Detailed Measurement

Survey Making compensation

plan Verify and approve the

compensation plan Situation of

Compensation payment Situation of Site

Clearance Contract

award (Anticipated) Starting

date Finishing

date Starting date Finishing

date

Starting date

Finishing date

Submiting

date Approval Starting date

Finishing date

(anticipated) Starting

date Finishing

date (Anticipated)

1 Pipeline 24/8/11 31/12/12 10/10/2011 10/11/2012 13/11/11 15/11/12 12/11/2012 13/11/12 24/12/12 15/2/13 14/1/13 5/3/2013 6/3/2013

Cộng Hòa 24/8/11 31/12/12 10/10/2011 10/11/2012 13/11/11 15/11/12 12/11/2012 13/11/12 24/12/12 15/2/13 14/1/13 5/3/2013 6/3/2013

Cẩm Hải 24/8/11 31/12/12 10/10/2011 10/11/2012 13/11/11 15/11/12 12/11/2012 13/11/12 24/12/12 15/2/13 14/1/13 5/3/2013 6/3/2013

2 Resevoir 24/8/11 10/8/2013 10/10/2011 10/8/2013 13/11/11 10/8/2013 12/11/2012 13/11/12 24/12/12 15/9/2013 14/1/13 4/10/2013 5/10/2013

Mông Dương 24/8/11 10/8/2013 10/10/2011 10/8/2013 13/11/11 10/8/2013 12/11/2012 13/11/12 24/12/12 15/9/2013 14/1/13 4/10/2013 5/10/2013

Page 15: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 14 of 19

Form 2: Number of Affected Households until 30/6/2013

No Components

Permanently affected households

Temporarily Affected

HHs

Total Affected HHs (both

long term and short term

Affected HHs

No. Of Severe HHs No. Of None-severe

HHs

Affected Business

HHs

No of Injured Impacted HHs

Total

Lost from 10% or more of

agricultural land

Number of

resettled HHs

/Poor HHs Ethic

Minorities HHs

Single Woman

headed HHs Social

Policy HHs

1 Pipeline 51 51 0 12 0 5 5 1 7 0 63

Cộng Hòa 36 36 0 6 0 3 4 0 5 0 42

Cẩm Hải 15 15 0 6 0 2 1 1 2 0 21

2 Resevoir 101 101 37 26 0 6 93 7 3 0 127

Mông Dương 101 101 37 26 0 6 93 7 3 0 127

Total 152 152 37 38 0 11 98 8 10 0 190

Page 16: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 15 of 19

Form 3: Area of the acquired land until 30/6/2013

No. Components/ Packages

Permanently Acquired Land Area (m2) Temporarily Acquired Land Area (m2)

Agricultural Land

Residential Land

Aquacultural Area Forest Land Other Land Total Agricultural

Land Residential

Land Aquacultural

Area Forest Land

Other Land Total

1 Pipeline 25,789.1 0.0 2,229.0 610,622.8 25,668.7 664,309.6 381.4

Cộng Hòa

8,230.1 0.0 229 464041.3 12,601.5 485,101.9 208.8

Cẩm Hải 17,559.0 0.0 2,000.0 146,581.5 13,067.2 179,207.7 172.6

2 Resevoir 660,285.0 6,903.3 4,419.8 283,886.0 208,319.8 1,267,793.6 0.0

Mông Dương 660,285.0 6903.3 4419.8 283886.0 208319.8 1,267,793.6 0.0

Total 686,074.1 6,903.3 6,648.8 894,508.8 233,988.5 1,932,103.2 381.4 0.0 0.0 0.0 0.0 0.0

Page 17: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 16 of 19

Form 4: Housing and other assets affected until 30/6/2013

No. Components/ Packages

Affected Housing

Area (m2)

Affected Shop Area

(m2)

Affected Factory

Area (m2)

Affected Rice and

crops area (m2)

Affected Tree (tree)

Affect Objects/ Architect

Works

Relocated Graves (pcs)

Affected Other Assets

1 Pipeline 0.0 0.0 0.0 658.0 88,677

Form 4.1

Form 4.1

Cộng Hòa 0.0 0.0 0.0 630.0 39,567

Cẩm Hải 0.0 0.0 0.0 28.0 49,110

2 Resevoir 6,711.1 0.0 0.0 19,555.8 99,893

Mông Dương 6711.1 0.0 0.0 19,555.8 99,893

Total 6,711.1 0.0 0.0 20,213.8 188,570.0 - 0.0 -

Form 4.1: Affected Other Assets until 30/6/2013

No. Components/ Packages

Toilet Kitchen Bathroom Wells Barns Cement roof Fence Water Tank Electric

Line (m2) (m2)/ (m2) (pcs) (m2) (m2) (m2) (m3) (m)

1 Pipeline 35 861.6 45.0 0.0 347.7 751.1 2,452.1 410.9 15,680.3

Cộng Hòa 4 349.2 15.0 0.0 211.3 324.5 1,328.8 213.4 7,235.8

Cẩm Hải 5 512.4 30.0 0.0 163.4 426.6 1,128.3 197.5 8,444.5

2 Resevoir 40 862.4 137.0 1.0 1,254.5 1,239.3 5,077.9 786.3 6,777.7

Mông Dương 40 862.4 137.0 1.0 1,227.0 1,239.3 5,077.9 786.3 6,777.7

Total 75 1,724.0 182.0 1.0 1,602.2 1,990.4 7,530.0 1,197.2 22,458.0

Page 18: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 17 of 19

Form 5: Situation of Compensation Payment until 30/6/2013

No Component

Compensation Cost (VND) Paid and None-paid yet (VND) Situation of Compensation Situation of Site Clearance

Total of cost estimation

approved by 31/6/2013

Total of cost accoding to the

compensation plan Paid until 31/6/2013 None-paid

No. of HHs received

compensation

No. of HHs none-received

compensation

No. of HHs handed over the

sites

No. of HHs have not been handed

over the sites

1 Pipeline 10738062600 10738062600 10738062600 0 63 0 63 0

Cộng Hòa 5917620000 5917620000 5917620000 0 42 0 42 0

Cẩm Hải 4820442600 4820442600 4820442600 0 21 0 21 0

2 Resevoir 46333115800 46333115800 29599895700 16733220100 78 49 78 49

Mông Dương 46333115800 46333115800 29599895700 16733220100 78 49 78 49

Total 57071178400 57071178400 40337958300 16733220100 141 49 141 49

Page 19: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 18 of 19

Form 6: Situation of Compensation Payment until 30/6/2013

Components/ Packages

Communal Level Distric Level Compensation Committee Provincial PMU Provincial Level Court

No.

of

Com

plai

ned

HH

S

No.

of H

Hs

are

satis

fact

orily

re

solv

ed

No.

of

Com

plai

ned

HH

S

No.

of H

Hs

are

satis

fact

orily

re

solv

ed

No.

of

Com

plai

ned

HH

S

No.

of H

Hs

are

satis

fact

orily

re

solv

ed

No.

of

Com

plai

ned

HH

S

No.

of H

Hs

are

satis

fact

orily

re

solv

ed

No.

of

Com

plai

ned

HH

S

No.

of H

Hs

are

satis

fact

orily

re

solv

ed

No.

of

Com

plai

ned

HH

S

No.

of H

Hs

are

satis

fact

orily

re

solv

ed

Resevoir 1 1 0 0 0 0 0 0 0 0 0 0

Pipeline 0 0 0 0 0 0 0 0 0 0 0 0

Total 1 1 0 0 0 0 0 0 0 0 0 0

Page 20: VIE: Mong Duong 1 Thermal Power Project Tranche 2 · Mong Duong (2 x 500MW) Thermal Power Plant Project Page 7 of 19 2.3. Compensation payment, assistance and resettlement As of June

Internal Resetlement Mornitoring Quarterly Report Mong Duong (2 x 500MW) Thermal Power Plant Project

Page 19 of 19

Form 7: Progress on compensation and resettlement implementaion till 30/6/2013

Component Pipeline Component Resevoir

Component

Cộng Hòa Cẩm Hải Mông Dương Activities on compensation and resettlement

Complete situation

Complete situation Complete situation

Information Dissemination and Community Participation 100.0% 100.0% 100.0%

Detailed Measure Survey (DMS) 100.0% 100.0% 100.0%

Setting Compensation Plan 100.0% 100.0% 100.0% Consulting and Counseling with the APs on compensation plan 100.0% 100.0% 100.0%

Update the RP and approve by ADB 100.0% 100.0% 100.0% Finalized the compensation plan and submit for approval 100.0% 100.0% 98.0%

Verify and approve the compensation plan 100.0% 100.0% 98.0% Consultate the APs on the approved compensation plan (to the agricultural land) 100.0% 100.0% 98.0%

Compensation Payment 100.0% 100.0% 63.9%

Resettlement and Site Clearance 100.0% 100.0% 63.9%

Independent Monitoring and Reporting 100.0% 100.0% 63.9%

Compensation Progress by component 100.0% 100.0% 63.9%

Compensation Progress of the Project 100.0% 100.0% 63.9%


Recommended