Social Monitoring Report July 2014
VIE: Power Transmission Investment Program,
Tranche 2
500kV Pleiku-My Phuoc-Cau Bong Transmission
Line (Gia Lai Province)
Prepared by Central Vietnam Power Projects Management Board for the National Power
Transmission Corporation and the Asian Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
NATIONAL POWER TRANSMISSION CORPORATION
CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD
PLEIKU – MY PHUOC – CAU BONG 500 KV TRANSMISSION LINE PROJECT
SECOND MONITORING REPORT
INDEPENDENT MONITORING ON RESETTLEMENT AND ETHNIC
MINORITY IN GIA LAI PROVINCE
July 2014
NATIONAL POWER TRANSMISSION CORPORATION
CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD
PLEIKU – MY PHUOC – CAU BONG 500 KV TRANSMISSION LINE PROJECT
SECOND MONITORING
REPORT
INDEPENDENT MONITORING ON
RESETTLEMENT AND ETHNIC MINORITY
GIA LAI PROVINCE
PROJECT OWNER
Central Vietnam Power Projects
Management Board
IMPELEMENTATION
Investment Consultancy and
Technology Transfer Co., Ltd
Deputy General Director
LE CHI CUONG
July 2014
INVESTCONSULT GROUP 3
TABLE OF CONTENTS
I. INTRODUCTION............................................................................................... 7
1.1. Objectives of the Project ........................................................................... 7
1.2. Scale and scope of the Project .................................................................. 7
II. SUMMARY OF RESETTLEMENT AND ETHNIC MINORITY
DEVELOPMENT PLAN (REMDP) ....................................................................... 8
2.1. Objectives of REMDP ............................................................................... 8
2.2. Impacts of resettlement from the Project ............................................... 8
2.3.1. Impact on land acquisition .................................................................. 9
2.3.2. The affected trees ................................................................................ 9
2.3.3. Affected houses and other structures ................................................ 10
2.3.4. Severely affected households ............................................................ 10
III. INDEPENDENT MONITORING ................................................................... 12
3.1. Independent monitoring the resettlement and ethnic minority
development plan ............................................................................................ 12
3.2. Objective of the independent monitoring .............................................. 12
3.3. Monitoring places .................................................................................... 13
3.4. Monitoring indicators ............................................................................. 13
3.4.1. Monitoring indicators for RP ............................................................... 13
3.4.2. Monitoring the implementation of EMDP ........................................... 15
3.5. Implementation method .......................................................................... 15
3.5.1. Information collection ....................................................................... 15
3.5.2. Sampling ............................................................................................ 16
IV. RESULTS/FINDINGS FROM THE REMDP MONITORING................... 18
4.1 Implementation progress .................................................................... 18
4.2 Implementation progress of REMDP ................................................ 19
4.3 Monitoring indicators ......................................................................... 19
4.3.1. Information dissemination ................................................................ 19
4.3.2. Inventory of losses ............................................................................. 20
4.3.4. Recovery of civil infrastructure ......................................................... 23
4.3.5. Impacts during construction phase ................................................... 23
4.3.6. Site for relocation .............................................................................. 23
INVESTCONSULT GROUP 4
4.3.7. Support for affected households ........................................................ 23
4.3.8. Gender, ethnic minority and vulnerable households issues.............. 25
4.3.9. Level of satisfaction .......................................................................... 27
4.4. Problems during the implementation ................................................ 27
4.5. Complaints and grievances ................................................................ 27
V. CONCLUSION AND RECOMMENDATIONS ............................................ 28
5.1. Conclusion ................................................................................................ 28
5.2. Recommendations ................................................................................... 28
ANNEX1: LIST OF OFFICIALS APPROACHED ............................................ 30
ANNEX 2: PHOTOS OF FIELD VISITS ............................................................. 31
ANNEX 3: APPRAISAL DECISION/COMPENSATION PLAN/MINUTES
OF INVENTORY .................................................................................................... 32
ANNEX 4: RECORD PAPER AND THE PETITION FROM HOUSEHOLDS39
ANNEX 5: SURVEY TOOL .................................................................................. 46
INVESTCONSULT GROUP 5
LIST OF TABLES
Table 1: Components of the Project .............................................................................. 7
Table 2: Summary of main features of 500kV Pleiku – My Phuoc – Cau Bong
Transmission line ............................................................................................................. 8
Table 3: Permanent land acquisition in 500 kV Pleiku – My Phuoc – Cau Bong
project ................................................................................................................................ 8
Table 4: Type of affected land ........................................................................................ 9
Table 5: Distribution of affected trees ........................................................................... 9
Table 6: Affected houses and other structures ............................................................. 10
Table 7: Impact of land acquisition on severely affected household ......................... 10
Table 8: Monitoring places ............................................................................................. 13
Table 9: Number of interviewed APs ............................................................................. 17
Table 10: Construction progress .................................................................................... 18
Table 11: Information dissemination methods ............................................................. 20
Table 12: Completeness in terms of AHs’ Assets ......................................................... 22
Table 13: Satisfaction level ............................................................................................. 27
INVESTCONSULT GROUP 6
ABREVIATIONS
ADB : Asian Development Bank
AHs : Project Affected Households
APs : Affected People
CLRD : Center for Land Resource Development
CPC : Communal People’s Committee
CPMB : Central Power Management Board
DMS : Detailed Measurement Survey
DPC : People Committee of District
IOL : Inventory of Losses
LURC : Land Use Right Certificate
MAH : Marginal Affected Households
MARD : Ministry of Agriculture and Rural Development
NPT : National Power Transmission Corporation
PC : People’s Committee
PECC4 : Power Engineering Consulting Company 4
PPC : People Committee of Province
REMDP : Resettlement and Ethnic Minority Development Plan
ROWs : Right of Ways
RP : Resettlement Plan
SAH : Severally Affected Household
SPS : Safeguard Policy Statement
INVESTCONSULT GROUP 7
I. INTRODUCTION
The Government of Vietnam (GOV) has requested the Asian Development Bank
(ADB) to provide a loan toconstruct new electricity distribution system including a
436.673 km - long Pleiku – My Phuoc – Cau Bong 500kV transmission line from
Pleiku to Cau Bong via My Phuoc in southern area of Vietnam. The proponent and
Executing Agency for the loan is the National Power Transmission Corporation
(NPT), Vietnam’s state-owned electricity transmission company which is
responsible for the planning and nationwide distribution of electricity. The Central
Vietnam Project Management Board (CPMB) is responsible for the operation of the
power system in central Vietnam and will be the Executing Agency of the Project.
NPT has identified the 500kV Pleiku–My Phuoc – Cau Bong transmission line as a
high priority project and one of several projects for construction in order to meet its
target of connecting 90% of the population to electricity by 2020 and 100% by
2025.The proposed 500kV transmission line in the Central Highlands to Ho Chi
Minh City – My Phuoc – Cau Bong will meet energy demand in the South of
Vietnam which is growing at 14% per year and expected to balloon out to 25% by
2015. The construction of 500 kV Pleiku – My Phuoc – Cau Bong transmission line
together with expansion of Pleiku substation will be an enhanced and more reliable
energy supply to the provinces in the South of Vietnam, especially to industrial
zones in the area.
1.1. Objectives of the Project
- The 500kV Pleiku – My Phuoc – Cau Bong Transmission Line Project, which
is a part of the National Electricity Network, maintains the supply of electricity
to the development need of the South of Vietnam in the 2014-2015 period.
Moreover, the Project also ensures the connectivity of the transmission
networks within Vietnam, Laos and Cambodia to 2015.
- The Project helps to increase the reliability of power supply, reducing the risk
of electricity losses. It will also optimize capacity of power plants in order to
provide electricity continuously and safely to the sub-loading lines of the South
in particular and the whole country in general.
1.2. Scale and scope of the Project
The Transmission Line (TL) takes place within the boundaries of 06 provinces and
city namely: Gia Lai, DakLak, DakNong, BinhPhuoc, Binh Duong and Ho Chi
Minh City. In Gia Lai area, the transmission line passes through 18 communes
which belong to districts: Chu Pah, IaGrai, Pleiku City, Chu Prong, and ChuPuh
with the length of 82.768km.
Table 1: Components of the Project
Component Length Starting point Ending point Number
of towers
TL passes Gia Lai
province
82,768 Bus bar 500kV
Pleiku
transmission
station
G15 + 403m 173
INVESTCONSULT GROUP 8
Table 2: Summary of main features of 500kV Pleiku – My Phuoc – Cau Bong
Transmission line
Item Technical Data
Length (km) 436.673
- Starting point At 500 kV bus bar at Pleiku 500 kV
substation
- End-point At 500 kV bus bar at Cau Bong
500kV substation
Right of Way width 16m from either side of the center line
Earth grounding width 60m from the 16
th meter from the
center line
Voltage 500 kV
Number of circuits 2
Conductor 4xACSR-330/43
Earth wire OPGW-90 & PHLOX-116
Optical repeater cable 24 fiber lines
Suspension towers (number) 808
- Height Average is 65m, the highest is 79m
- Area requirement/tower 337.62 m²
Tension towers (number) 118
- Height Average is 60m, the highest is 72m
- Area requirement/tower 653.4 m²
II. SUMMARY OF RESETTLEMENT AND ETHNIC MINORITY
DEVELOPMENT PLAN (REMDP)
2.1. Objectives of REMDP
Objectives of REMDP are summarized as follows:
- REMDP, which was made during project preparation stage, is to minimize
negative impacts of the Project on AHs;
- Land acquisition and resettlement caused by the Project must be minimized;
- Improve or at least maintain living standards of APs in comparison with those
prior to the Project.
2.2. Impacts of resettlement fromthe Project
The 500kV Pleiku – My Phuoc – Cau Bong transmission line went through 18
communes/4 districts and 1 city belong to the Gia Lai province. The Project had to
process to permanently acquire 128 households with 173 tower positions, mainly
agricultural land. The implementation of the Project also impacted on 39
households and other 43 works.
Table 3: Permanent land acquisition in 500 kV Pleiku – My Phuoc – Cau Bong
project
No Provinces Number of
permanent AHs
Number
of towers
Acquired land
(m2)
1 Gia Lai 128 173 46,220
INVESTCONSULT GROUP 9
2.3.1. Impact on land acquisition
Within 32m width of ROWs of 82,768 km in total in the province, there were
2,563,731m2
belong to ROW, in which 46,220 m2
land taken permanently for tower
construction.The following table presents project’s affected lands:
Table 4: Type of affected land
N
o
Provinces
and
Districts
Distribution in restricted Lands under
ROWs (m2)
Total of
restricted
Lands
under
ROWs
Permanentl
y Acquired
Lands Agricultu
ral Land
Paddy
Land
Forest
Land
Residen
tial
Land
1 Chu Pah 43,312 3,551 - - 46,864 4,121
2 IaGrai 443,148 52,361 - 1,402 496,911 15,966
3
Pleiku
City 118,883 - - - 118,883 5,389
4 Chu Prong 550,253 - 1,535 - 551,788 19,281
5 Chu Puh 21,532 - 48,060 - 69,592 1,463
Total 1,177,128 55,912 49,595 1,402 1,284,038 46,220
2.3.2. The affected trees There are about 31,389 trees affected by the Project, mainly industry trees with
highly economic value such as rubber, coffee, and cashew. The remaining trees are
several of fruit trees, forest trees, timber, and shade trees, etc.
Table 5: Distribution of affected trees
No District
Industrial
Trees
Fruit
Trees Others Total
1 Chu Pah 3,450 480 30 3,960
2 IaGrai 41,026 0 88 41,114
3 Pleiku City 6,783 0 0 6,783
4 Chu Prong 33,042 30 0 33,072
5 Chu Puh 1,270 0 0 1,270
Total 85,571 510 118 86,199
INVESTCONSULT GROUP 10
2.3.3. Affected houses and other structures
Besides 39 houses must be replaced, the TL also affects other 43 works including
kitchens, yards, huts, bathrooms/latrines, animal shelter, etc. Those affected houses
and other works were determined according to Decree 106/NĐ-CP and Decree
81/NĐ-CP on Protection of Safety corridor of High-Voltage Power Grid Works.
Table 6: Affected houses and other structures
No District
Number of Affected Houses and Other
Structures
Hou
ses
Kit
chen
s
Bath
room
s/
Latr
ines
Wel
ls
An
ima
l
Sh
elte
rs
Ya
rd
Oth
er
stru
ctu
res
Total
1 Chu Pah District 4 3 0 1 3 0 11
2 IaGrai District 17 6 3 2 1 4 33
3 Pleiku Town 2 0 0 1 3 0 6
4
Chu Prong
District 16 2 2 3 3 3 29
5 Chu Puh District 0 0 0 0 0
Subtotal 39 14 5 7 10 7 82
2.3.4. Severely affected households
According to REMDP and RP, severely affected households refers to affected
households who will lose 10% or more of their total productive land and/or assets,
have to relocate; and/or lose 10% or more of their total income sources due to the
Project. The permanent land acquisition affected to 5 severely affected households,
in which 01 household is the Kinh people and 04 households are ethnic minority
people.
Table 7: Impact of land acquisition on severely affected household
Province Number of SAHs Kinh’s people Ethnic
Minorities
Total 5 1 4
Legal framework
INVESTCONSULT GROUP 11
The legal and policy framework for compensation and resettlement under the
Project is defined by the relevant laws of the Government of Viet Nam.
- 2003 Law on Land, promulgated on November 26, 2003 by Vietnam’s National Assembly.
- Law on Complaints, approved by the National Assembly in 2011.
- Government’s Decree No.181/2004/ND-CP, dated October 29, 2004, Guiding
the Implementation of the Amended 2003 Law on Land.
- Government’s Decree No.84/2007/ND-CP, dated May 25, 2007, providing
additional guidance on the grant of land use right certificates, land recovery,
exercise of land use rights, order and procedures for compensation, support
and re-settlement when land is recovered by the State.
- Government’s Decree 197/2004/ND-CP, dated December 03, 2004, regulating
compensation, assistance and resettlement when the State acquires the land.
The Decree provides guidance on implementation of land compensation,
assets compensation, support and resettlement policy related to land
acquisition.
- Government’s Decree 188/2004/ND-CP, dated November 16, 2004, on
methods to identify land price and land price frame for different types of land.
- Government’s Decree 123/2007/ND-CP, amending and supplementing some
articles of Decree 188/2004/ND-CP.
- Government’s Decree 69/2009/ND-CP, dated August 13 2009, additionally
providing for land use planning, land acquisition, compensation, assistance
and resettlement in case of land acquisition, regulating the land price, land
allocation and lease, and additional requirements related to land use rights.
- Government’s Decree 106/2005/ND-CP dated August 17, 2005, regulating the
protection and safety corridor of high-voltage power grid works. Some articles
of this decree was amended and supplemented by Decree 81/2009/ND-CP
dated October 12, 2009.
- Circular 144/2004/TT-BTC, dated November 26 2004, of the Ministry of
Finance providing guidelines on the implementation of Government’s Decree 188 on land price evaluation.
- Circular No. 14/2009/TT-BTNMT of the Ministry of Natural Resources and
Environment, detailing the compensation, support and resettlement and order
of and procedures for land recovery, allocation and lease.
The above regulations form a framework that allows local authorities in each
province issues their own decisions and regulations. Through these decisions and
regulations, compensation rates and other supporting mechanism for households
affected by land acquisition and resettlement are regulated. The decisions in Gia Lai
province are as follow:
- Decision 05A/2011/QD-UBND dated 25th April 2011 of provincial PC on
promulgating compensation, support and resettlement regulations for
acquisition in Gia Lai province;
INVESTCONSULT GROUP 12
- Decision 19/2010/QD-UBND dated 28th September 2010 of Gia Lai
provincial PC on promulgating the support rate of living house, works for
daily living of households, individuals, types of land and tree were limited to
use during the construction of high-voltage volume in Gia Lai province;
- Decision No. 36/2011/QD-UBND dated 21December 2011 of Gia Lai
Provincial PC on Setting Land Price Brackets for Land Categories in Gia Lai
Province in 2012.
- Decision No. 31/2012/QD-UBND dated 20 December 2012 of Gia Lai
Provincial PC on Setting Land Price Brackets for Land Categories in Chu Pah
District in 2013.
- Decision No. 38/2012/QD-UBND dated 20December 2012 of Gia Lai
Provincial PC on Setting Land Price Brackets for Land Categories in IaGrai
District in 2013.
- Decision No. 51/2012/QD-UBND dated 28 December 2012 of Gia Lai
Provincial PC on Setting Land Price Brackets for Land Categories in Pleiku
City in 2013.
- Decision No. 30/2012/QD-UBND dated 20 December 2012 of Gia Lai
Provincial PC on Setting Land Price Brackets for Land Categories in Chu
Prong District in 2013.
- Decision No. 32/2012/QD-UBND dated 20 December 2012 of Gia Lai
Provincial PC on Setting Land Price Brackets for Land Categories in Chu Puh
District in 2013.
- Decision No. 10/2013/QD-UBND dated 22 May 2013 of Gia Lai Provincial
PC on Setting Price Brackets for Newly Built Houses and Structures on Lands.
III. INDEPENDENT MONITORING
3.1. Independent monitoring the resettlement and ethnic minority development
plan
To implement Resettlement and Ethnic Minority Development Plan (REMDP) is a
complicated task. It should be regularly monitored by the Project management unit
(PMU), local authorities related to the Project. Monitoring process is known as
internal monitoring. Besides internal monitoring, the ADB always requires an
objective source of information that separate from the internal report. This source is
called Independent Monitoring and will be implemented by an external monitoring
agency that is independent from the CPMB.
3.2. Objective of the independent monitoring
The main objective of the monitoring and consulting service is to make sure the
APs of the 500kV Pleiku – My Phuoc – Cau Bong Project will receive full supports
and benefits as stated in approved REMDP.
The monitoring activities are conducted in order to:
(i) Ensure the rehabilitation and improvement of APs’ livelihood; (ii) Supervise the whole Project to check if the current resettlement activities
are aligning with the RP or not. Propose solutions if necessary;
INVESTCONSULT GROUP 13
(iii) Assess if the rehabilitation and compensation methods are fully complied
with the REMDPand ADB’s SPS (2009 and other amended) or not; (iv) Detect arising problems during the implementation of the Project and
propose mitigation measures.
3.3. Monitoring places
The monitoring sites would be categorized into two types, which are (i) official
agencies related to the Project and (ii) at the construction sites. In particular:
(i) At the PMU office, Compensation Council/ Center for Land Resource
Development (CLRD) and PC of related districts/wards, communes.
(ii) At the Project sites: Interviewing AHs.
At the second monitoring phase, the Consultant discussed with representatives of
PMU, CLRD and PC of related districts/wards, communes as following:
Table 8: Monitoring places
No. District Commune
1 Chu Pah NghiaHung, PhuHoa
2 IaGrai IaDer, IaPech
3 Pleiku city IaKenh
4 Chu Prong IaVer, Ia Bang
3.4. Monitoring indicators
During the implementation of REMDP, the Consultant will conduct the monitoring
and evaluation based on the following indicators:
3.4.1. Monitoring indicators for RP
RP monitoring indicators includes but not limited to these indicators:
a) Monitoring of organizations, units implementing RP
- Organizations and units implementing RP (name, number of staffs, job
description of each organization, etc.).
- Related agencies (local authorities, departments and unions, etc.). The
cooperation mechanism within related agencies, responsibility of each
agency, etc.
b) Monitoring of compensation payment
- Payment in full amount for the assets losses; compensation based on
replacement cost;
- Payment on time for all Ahs (according to RP).
c) Monitoring the reconstruction of civil infrastructures
INVESTCONSULT GROUP 14
- All basic infrastructure (water supply, drainage system, roads, etc.) need to
be built in resettlement areas in a manner that is equal or better than the old
ones.
d) Monitoring the provision of resettlement places (if any)
- Interview APs who is qualified to be resettled in the resettlement places to
check if they were consulted on the location of the resettlement places,
houses and lands. Supervise to check if the resettlement places are located in
environmental sensitive areas or not;
- Supervise the selection of resettlement areas, designs, infrastructures and
location of lands (that allows APs to maintain/improve their living);
- Supervise the drainage system (if any) and its operation; supervise the waste
management activities including the method and process of waste disposal
applied in resettlement areas; observe and test smell of waste, aesthetic
issues, the gathering of rats, insects and other transmission vectors in the
resettlement areas;
- Check if APs have been receiving all their benefits on time;
- Check if displaced households are consulted at least 03 months before
replacement take place;
- And other issues stated in RP and other findings from reality observance.
e)Satisfaction level monitoring
- Assess the satisfactory level of the APs in terms of different aspects of RP
which are monitored and taken note; and
- Assess the problems of grievance and compensation and time framework(
time of settling complaints);
- Propose measures for remained problems
g) Monitoringof information publicity and communities consultation
- Check if they were consulted or not on issues related to their rights such as
compensation rate, policy of rights, location, designs and distribution of land
in resettlement areas;
- Involve in meeting of people organized by CPMB or Provincial/District’s Committee of Compensation to know more about current situation of the
implementation of RP as well as newly arose problems to give suggestion on
time;
- Check information related to RP at local agencies and supervise the
dissemination of information to APs.
h) Result of the communication activities for the prevention of HIV/AIDS and
human trafficking (such as the number of attendants, method, frequency of
promotion activities, etc.)
i) Level of living standard
- During the implementation, assess and report on the trend of living standard
recovery;
INVESTCONSULT GROUP 15
- Research on basic level of living standard of Ahs before and after the
resettlement to assess the improvement of APs’ living standard; - Predict the recovery of Ahs’ income and living standard; - The recovery of SAPs;
- Assess the financial supports to Ahs as stated in RP;
- Supervise the rehabilitation support to SAPs.
3.4.2. Monitoring the implementation of EMDP
The Consultant will monitor content of the EMDP from implementation to
management. Main monitoring indicator includes
a) Monitoring of compensation payment
- Pay in full amount for assets lost and replacement cost;
- Pay on time for AHs.
b) Satisfaction level
- Satisfaction level of AHs to different aspects in EMDP;
- Complaints on compensation and duration for its settlement.
c) Information publicity and community consultancy
- Whether AHs get enough information and were consulted on issues related to
their rights;
- Study the problems in the implementation of REMDP and provide
suggestions.
3.5. Implementation method
The monitoring is carried out by a combination of document analysis
method,quantitative method (Direct interview based on Questionnaire Survey) in
and qualitative methods (In–depth interview and Focus Group Discussion with key
persons and APs).
The Consultant has prepared a questionnaire and guidelines for in-depth interview.
The collection of information related to the resettlement will be carried out in the
CPMB, the district Compensation Board/ Center for Land Resources Development
(CLRD) and the affected households. The evaluation results are compared with the
field monitoring results.
3.5.1. Information collection
3.5.1.1. Document analysis
Before monitoring, the Consultant has thoroughly researched following documents:
- EMDP of the Project;
- TOR for monitoring activities;
- Compulsory resettlement policies of ADB (2009);
- Policies of Vietnam’s Government on land acquisition, compensation, support and resettlement as:
INVESTCONSULT GROUP 16
- Documents / memorandum related to REMDP implementation and resettlement
policy framework of compensation, support and resettlement which ADB were
not opposed and was approved by the Prime Minister; and
- Other related documents.
3.5.1.2. Qualitative method
Monitoring experts exchanged with PMU’s leaders and officials in charge of resettlement, officials in charge of land acquisition compensation of District Center
for Land Resource Development to gather information and related data. The in-
depth interviews APs are integrated in the interview questionnaire.
3.5.1.3. Quantitative method
The monitoring team conducted a survey to gather information and assess the
implementation of compensation and resettlement of the project.
Based on the list of AHs provided by CLRD, the Consultant selected randomly
numbers of households to interview. The objects of interview include women, the
elder and other vulnerable groups.
3.5.2. Sampling
Monitoring places of phase 1 were divided into 2 types: (1) the official agencies
related to the Project and (2) at project sites. These specific places are:
- At the Central Vietnam Power PMU office, Compensation and Site Clearance
Boardand communal PC of Gia Lai’s districts and CPCs;
- At the Project sites: Interviewing AHs in the Project area, taking some photos of
typical cases.
Selection and classification of objects
In the second monitoring phase, interview objectsthat staff of independent
monitoring unit have to contact and work with can be classified into 2 main groups:
Group 1:Officials that directly or indirectly involve in mitigating impacts on people
and the environment, especially officials of construction units. Besides it, it also
includes officials of CPMB and local authority.
Group 2: households that have assets affected by the construction of project
INVESTCONSULT GROUP 17
Sampling
Based on the contract between PMU and the Consultant, the sampling is to
interview 10% the number of APs along the whole route according to approved
compensation plan.
At the second monitoring, the Consultant has selected randomly AHs to ensure to
the involvement of vulnerable groups, the Consultant selected as follows:
(1) All communes in project area will be monitored;
(2) Interview 100% severely affected households;
(3) The selected AHs have included minority people and vulnerable households.
The number of households in the second monitoring phase as below:
Table 9: Number of interviewed APs
No. District Commune
Number of interviewed households
SAH MAH
Total Kinh
Ethnic
minorities Kinh
Ethnic
minorities
1 Chu Pah Nghia Hung - - 3 - 3
PhuHoa - - 3 - 3
2 IaGrai Ia Der - - 4 1 5
IaPech - - 4 1 5
3 Pleiku
city IaKenh 1 - 4 - 5
4 Chu
Prong
Ia Bang 1 - 4 - 5
IaVer - - 4 1 5
Total 2 - 26 3 31
The remaining communes belong to project area will be monitored in the following
monitoring phases.
INVESTCONSULT GROUP 18
IV. RESULTS/FINDINGS FROM THE REMDP MONITORING
4.1 Implementation progress
The project in Gia Lai province was divided into 2 packages numbered 01 and 02, which implemented by 02 different Constructors. Until
the monitoring time, the progress is as following:
Table 10: Construction progress
Package
name Constructor
Length
(km)
Number of
positions
Digging
position Mound
Tower
position
Foundatio
n ratio
(%)
Percentage
of tower
built (%)
Number
of towers
received
Number
of
completed
towers
Package
01 (ĐĐ-
G6
&NXT)
Power
Construction and
Engineering one
member limited
Company Number
4
27.220 58 58 58 58 100% 100% 58 58
NXT 500kV
Pleiku Completed
Package
02 (G6-
G13) Vietnam Power
Construction JSC.
38.630
142 142 142 142 100% 100% 142 142 Package
03 (G13-
G17)
28.410
INVESTCONSULT GROUP 19
4.2 Implementation progress of REMDP
Due to the Project only acquired permanently land for construction of foundation
tower, corridor, the compensation is only for works, tree and rice, the compensation
was divided into 2 phases (1) land compensation and other assets at tower position
(aims to site clearance) and (2) compensation and support for affected assets in
safety corridors.
The implementation of compensation and site clearance has been conducted since
2011. At that time, to speed up the construction schedule of the project, the investor
(AMT) paid part of the capital in advance (about 70% of the compensation plan) to
pay for the households affected by land acquisition to construct the foundation
towers (before the compensation plan was approved) to serve the construction
ground.After the plan had been approved, the other assets were compensated. From
2012, the compensation and payment to affected households was done once after
the compensation plan had been approved
AMT coordinating with Compensation and Site Clearance Board of Gia Lai’s districts have implemented following activities of RP for Pleiku – My Phuoc – Cau
Bong 500 kV transmission line Project:
- Establishment of the detailed compensation plan: inventory, applying prices for
each household;
- Submitting detailed compensation plan to PC of district so that it can issue the
Decision on land and detailed assets acquisition;
- Combining with the Project Owner to make compensation payment for AHs;
- Site clearance under grid safety corridor as regulated;
- Combining with AMT to settle hindrances and disputes, complaints of AHs on
compensation;
- Collecting all documents and costs of compensation and site clearance and
finalizing withAMT.
4.3 Monitoring indicators
4.3.1. Information dissemination
Information dissemination is an important part of ADB’s policies and the Government of Vietnam. Information dissemination is an important activity to
contribute to the success of the Project in general and the compensation payment,
resettlement in particular. Publicity aims to ensure all APs to reach the entire
project’s information, understand their benefits, reduce the complaints during the implementation of the Project and contribute to the Project’s progress. Through discussion with Compensation and Site Clearance Board in districts and
PCs of communes in the Project area, it was seen that the information dissemination
was done efficiently. The documents of safeguard policies were delivered to
affected communes and published in all PCs of communes.
INVESTCONSULT GROUP 20
To prepare for check and site clearance, CPMB had a document sending to
provincial PC to inform about land acquisition for project construction in the area of
province/city. After having the decision to create Compensation Council, CPMB
processed to work with compensation council, provincial PC, communal PC to
public construction plan. Those days was recognized as the close day of the Project.
After the construction plan announced, the officials of CPMB – Site clearance
department coordinated with Compensation and Site Clearance Board to organize
meetings in every affected commune. The contents were:
- Informing the scale of project in the area of commune;
- Informing about the compensation policies;
- Informing about the inventory plans;
In each communes, there are usually 3 meeting happens in different time: before
inventory, after inventory; after the construction plan published.
Table 11: Information dissemination methods
No. Information dissemination methods Implementation
RP Reality
1 Organize meetings to announce about the Project Yes Completed
2 Public speakers Yes Completed
3 Publicly posting policy framework in local places Yes Completed
4 Instruct grievance process and complaint settlement Yes Completed
This table has shown that the information dissemination was implemented in
accordance with the RP. Most of interviewed APs understood the supporting
policies and learn how to process the complaints as necessary.
As the result of the second monitoring, the local officials together with head of
villages have gone to the construction area and informed about the Project to every
APs. Besides, APshave also learned about the Project by the public information at
communal PC or listen to public speakers. After understand the Project’s information, 100% number of APs were invited to attend a meeting to have more
understanding about the Project.
4.3.2. Inventory of losses
During public community consultation in offices of communal PCs, representatives
of related agencies will inform AP about the time of inventory, simultaneously
invite them to take part in the inventory process. The unit participating in inventory
includes:
- Owners of the affected assets;
- Officials of the Compensation and Site Clearance Board and Resettlement;
- Officials of the Consultant performed REMDP (JSC Electrical construction No.4)
- Representatives of local authorities (commune / ward / district);
- Representatives of the Project Owner at local area.
INVESTCONSULT GROUP 21
After the inventory completed, all parties will certify in the working minute which
are considered as a basis of price application with damaged assets.
As noted by the monitoring team, all AHs have representatives participating in
inventory process and certification on the minute of working (details as in Annex
4).
On the basis of the inventory record at site area, Compensation and Site Clearance
Board will carry out the price application for the affected assets,assistances (if any)
for each AH and compensation plans. Compensation plans will be posted at the
communal/ward PC office, if households had any problem questions regarding to
compensation plans, they can contact the representative of local authority or Board
of Compensation, Assistance and Resettlement.
4.3.3. Compensation payment
4.3.3.1.Validity of compensation documents
Each compensation documents of AH include following papers:
(i) Minutes of asset inventory;
(ii) Minutes of situation identification;
(iii) Drawings;
(iv) Detailed compensation, supporting plan of each household;
(v) Minutes of compensation payment; and
(vi) Complaints in written (if any).
In addition to the above documents, some other materials/papers are also considered
such as compensation plan, decision on approving compensation plan,
supplemented compensation and support plan (if any), decisions on settling
complaints of local authorities, etc.
Validity of compensation documents is assessed through (i) completeness of above
administrative documents, (ii) appropriation in terms of time between
documents/papers, (iii) completeness of signatures and (iv) accuracy of calculations.
Result of random checking of compensation documents of AHs is as follow:
- Each document has all above-mentioned papers
- Calculate the complete benefits of AHs corresponds to the affected types
- Time between documents/papers is appropriate
- Data of documents is unified
- Calculations are accurate
- Having all related signatures.
4.3.3.2.Completeness in terms of quantity
Completeness in terms of quantity of AHs’ assets is assessed through (i) comparison between Minutes of asset inventory, compensation calculation
worksheet and Minutes of compensation payment, (ii) interviewing AHs.
INVESTCONSULT GROUP 22
Result of checking and comparing all documents and papers show that: all assets of
AHs that have been inventories have been calculated sufficiently in compensation
calculation worksheet. There is no difference in terms of quantity in the Minutes.
The amount of payment for households in the Minutes of compensation is totally
the same as the approved amount in the Decision of compensation approval.
Besides, the Consultant has interviewed some households received compensation to
assess the completeness in terms of quantity of affected assets. Result of checking
documents and interviewing AHs is summarized as follows:
Table 12: Completeness in terms of AHs’ Assets
Commune
s
1.
Participating
in
measurement/
inventory
2. Insufficient
measurement/
inventory
3.
Documents
clearly
show
figures
4.
Shortage
in
planning
5. No. of AHs
received
compensatio
n/ not fully
paid for
affected
assets
Yes No Yes No Yes No Yes No Yes No
ChuPah 6 0 0 6 6 0 0 6 6 0
IaGrai 10 0 0 10 10 0 0 10 10 0
Pleiku city 5 0 0 5 5 0 0 5 5 0
Chu Prong 10 0 0 10 10 0 0 10 10 0
Total 31 0 0 31 31 0 0 31 31 0
All checked documents are clear and sufficient, compensated assets are equal to the
inventoried assets. All interviewed households participated in the process of assets
measurement and inventory, before the Compensation committee of districts
established compensation plan and submitted to the local authorities for approval.
4.3.3.3. Compensation payment
Up to the time of monitoring, five districts of Gia Lai province had approved 59
compensation plans to compensate for foundation towers, corridors and other affect
during the construction. The detail is represented below.
Table 13: Compensation (VND)
No
. District Total amount Amount paid
In which
Compensation Support
1 Pleiku 3,920,453,279 3,920,453,279 3,880,713,279 39,740,000
2 IaGrai 28,104,113,198 28,100,461,259 27,640,790,885 463,322,313
3 ChuPuh 4,790,185,227 4,790,185,227 4,790,185,227
4 ChuPah 5,925,668,277 5,925,668,277 4,985,625,454 940,042,823
5 Chu Prong 24,779,018,261 24,779,018,261 23,954,773,336 824,244,925
INVESTCONSULT GROUP 23
Total 67,519,438,242 67,515,786,303 65,252,088,181 2,267,350,061
4.3.4. Recovery of civil infrastructure
In general, the construction work of the Project does not affect the local
infrastructure.
4.3.5. Impacts during construction phase
In addition to dig and mold foundation, constructing towers and wiring influenced
to part of agricultural land, trees and crops of the local people. All damages were
inventoried and calculated by the Construction Company and APs and then
coordinated with CLRD and CPMB to make compensation plan to conduct
compensation for AHs. Accordingly, damages caused by land acquisition for road
construction, materials site arecompensated by the Project Owner; the loss of trees
and crops by wiring is paid by the contractor. Currently, the related parties are
preparing compensation plan for these losses.
4.3.6. Site for relocation
In Gao commune, Pleiku city, the household headed by Mr. Huynh Van Cu has not
received the compensation as he did not agree with the unit price issued by PC of
the province. Relevant agencies identified and determined that this wasa special
case and hold a discussion, in which a recommendation to support Mr. Cu with 3
lots of resettlement location at Ngo Gia Kham road (Mr. Cu was supposed to pay
land use payment according to government’s regulation). However, this case has not
been solved definitely yet because AMT and the province’s PC do not have fund to
resolve such a special case.
According to record and observation of supervision group,Mr. Cu’s land plot
located on the street (60m frontage) and lied almost entirely within the safety
corridor. Through discussion with the household head, supervision team were
known that before the 500kV line running through, the family intended to use this
land plot for storage and processing of agricultural products, because of the line, the
householdcould not construct the work under power lines, which influenced
dramaticallyon production planning andbusiness of the family.
The 3 resettlement land plots that Pleiku city Land Development Center proposes
to support Mr. Cu were not regulated in REMDP as well as in the provincial
regulations or state guidelines on compensation, resettlement support;however
according to the monitoring group, this solutionwas flexible and completely
acceptable to mitigate the negative impact to the affected households
4.3.7. Support for affected households
The rate of support under REMDP that being applied in DakLak as below:
4.3.7.1. Life stability support
- In the locality of Pleiku city, there is only one householdseverely affected by
the project. This household has more than 10% of production land affected
and this household is Kinh
INVESTCONSULT GROUP 24
- Through consultancy, the consultant confirms that the severely affected
household received life stabilization support within three months with the
amount of 30 kg rice/person/month.
4.3.7.2. Support on job change
- Job changing support is applied to households that lose production land;
- LFDC in Pleiku city applied support for each m2of affected agricultural land.
Households having their agricultural land affected will receive a support
three times as much as compensation unit for job changing.
4.3.7.3. Rewards for hand over land on time
INVESTCONSULT GROUP 25
According to Decision No.28/QD-UBND dated 9th January 2012 of Pleiku People’s Committee commended for families and individuals that were exemplary in
relocation and handing over site for the 500kV Pleiku - My Phuoc - Cau Bong
Transmission Line Project (part passing Pleiku city) with the reward cost of
5,000,000.
By checking compensation plans and interview implementing staff as well as AHs,
the Monitoring team found that the support for APs had followed the current
regulations of the State and Gia Lai Provincial People’s Committee. Table 14: Support policy
No
. District Total amount
Number of household getting support
Job change Life
stability
House
moving
Support for
poor
households
1 Pleiku 39,740,000 2 12
2 IaGrai 463,322,313 65 15
3 Chu Pah 940,042,823 10 8 4
4 Chu
Prong 824,244,925
59
Total 2,267,350,061 75 8 80 12
All forms of assistance for affected households will be paid in cash (including
support for job change). It is recorded from the interviews with households getting
support tochange job thatproduction land withdrawal did not affect the total land
area of their production. The remaining land area was sufficient to produce and they
did not need to switch jobs, the amount of job change support would be invested in
reproduction.
4.3.8. Gender, ethnic minority and vulnerable households issues
In public community consultation on resettlement policy and minority development,
all issues related to gender, ethnic minority and vulnerable households were
presented for discussion. All AHs, social organization, etc. could take part in
contributing idea about project implementation, in particular:
4.3.8.1. Gender issues
INVESTCONSULT GROUP 26
Through community meeting minutes and list of participants in LFDC and
interviewing some affected females, the Consultant confirms that:
- Females in affected households have participated in project implementation
meetings;
- In the inventory process, females in households participated with the staff of
LFDC.
4.3.8.2. Ethnic Minority households
EM Action Plan is implemented according to REMDP from the preparation to
implementation step of the project. Accordingly, the affected EM households were
announced about the policies, benefit and choices of relocation, consulted fully
about the detailed inventory result.
Ethnic minority households provided conditions to develop their own culture and
economy, as well as participating in training classes, training on livestock and
cultivation knowledge. In fact, the project does not assess training needs of farming
and animal husbandry, these ethnic minority households had to find out about this
problem.
4.3.8.3. Vulnerable households
Up to present, it have been recorded that 12 poor households were affected by the
project. Based on clause 1,2 of Article 15 dated 25/4/2011 of Gia Lai
People’Committee on regulation of compensation, support and resettlement, the
support for poor family who do not relocate will receive the support of 30kg
rice/person/month during 3 months. Beside the compensation on land and assets and
the support on land use as regulated, these households were supported 30kg
rice/person/month (with 12,000 VND/kg rice)
INVESTCONSULT GROUP 27
4.3.9. Level of satisfaction
According to assessment of the Consultant, almost interviewed households are
satisfied with compensation plan that the Project proposed. Some households are
not satisfied with compensation price for land, crops or limit of support for
agricultural land. However, after considering and clarifying, PC of Gia Lai
concludes that compensation plan for those households are totally complied with
regulations of the State and PC of Gia Lai province. After that, those households
have received compensation and support as provided in the approved compensation
plan. The ratio of satisfaction of households is summarized in following table:
Table 15: Satisfaction level
No. District/City Satisfaction level
Satisfied Unsatisfied No opinion
1 Chu Pah 4 1 1
2 IaGrai 5 2 3
3 Pleiku 3 1 1
4 Chu Prong 7 1 2
Total 19 5 7
4.4. Problems during the implementation
Regarding support of agricultural land, PC of Gia Lai province has issued Decision
No. 532/QD-UBND dated 27/09/2013 on assistance level for non-acquired and
limited-use separate agricultural land under the ROW of 500kV Pleiku – MyPhuoc
– Cau Bong transmission line – Gia Lai component. Accordingly, for rubber trees
growing areas, besidesreceiving compensation and assistanceunder government’s regulation, affected households will receive additional assistance due to limited use
of land. The additional assistance is of 40% of the agriculture land price with the
same use purpose, which is acquired at the time of compensation and assistance. To
the other plants, the level of assistance is of 25%.
However, the beneficiary receiving the assistance was not mentioned in the
Decision, for instance, some enterprises hiring land to plant industrial trees or
households obtaining land from Nam PhuNhonProtective Forest Management Unit
(under Program 135) pay land tax annually as regulated. At present, there is no
document explaining clearlyabout types ofbeneficiaries for assistance under the
Decision No. 532/QD-UBND of Gia Lai PPC, this makes difficulties for project
implementation and disadvantages households.
Currently, Compensation support and resettlement Board is now requesting
opinions from PCP to make compensation plan and make payment to affected
organizations and individuals.
4.5. Complaints and grievances
INVESTCONSULT GROUP 28
Currently, four households in Ia Sao commune, IaGrai district which located in
tower 0110-0111 (Dao Quang Mao, Nguyen Xuan Thu, Pham Van Ha and Nguyen
Xuan Nam) has not received the compensation for not agreeing with the
compensation rate of agricultural land. These households said that their land, which
must be residential land, cannot be applied to agricultural land compensation rate.
At the moment, Compensation support and resettlement Board is verifying the
origin of the land for compensation.
According to records of the consultancy unit, despite being instructed about the
process and procedure of complaining and resolving complaints but the
complaining households often submit complaints/letters directly to Compensation
support and resettlement Board to solve and respond to complaints, therefore, to
avoid wasting time, the complaining households should not send complaints to the
CPC.
V. CONCLUSION AND RECOMMENDATIONS
5.1. Conclusion
To conclusion, REMDPimplementation in Gia Lai province basically followed
approved REMDP. The Consultant just has some comments as below:
- The organization structure: the relevant authorities stated in REMDP did
quite well their assignments, which contributed to the implementation of the
Project conveniently.
- The information of the Project’s dissemination information has been fully
implementedProject’s policies, complaint mechanism and resolving complaint to APs. By doing it, the Project hasn’t received any petition due to the lack of understanding of the Project.
- The property inventory, compensation plan and payment complied with the
agreement of most of APs. Most of interviewed APssaid that their assets was
counted and paid sufficiently, which proved that the compensation payment
was done timely and sufficiently.
- Compensation price: this is a sensitive matter and always being the reason
for complaints in many projects. By analysis and comparison between
compensation price and price stated in REMDPs, it was seen that the
compensation price was applied in accordance with the provisions of Gia Lai
province.
- Complaints and complaint settlement: all questions, complaints of AHs even
officially or via oral are all received and settled by the REMDP
implementation unit, following the regulated procedures.
5.2. Recommendations
In general, the implementation of REMDPs reached all requirements. Currently, the
project has closed the circuit, however it is recorded that some households
complained on compensation price. Base on the results of 2nd
monitoring, the
Consultant has some recommendations as below:
- In term of involuntary resettlement, it is requested that CLRD and other
relevant units to coordinate or solve the site clearance problems for safe
operation of power;
INVESTCONSULT GROUP 29
- In term of beneficiaries of assistance under Decision No. 532/QD-UBND,
relevant parties are recommended to clarify this issue in order to provide APs
with sufficient and accurate assistances.
- In term of households who has not agreed with the proposal compensation
plan,Compensation support& Resettlement Board is requested to urgently
verify the origin of land use, and provide satisfactory answer to the
households.
INVESTCONSULT GROUP 30
ANNEX1: LIST OF OFFICIALS APPROACHED
No. Responsible officials Title
1 Central Vietnam Power Project Management Board
Mr. Le DinhQuang Vice Director
Mr. Le Van Hieu Head of compensation department
Ms Vo NhatHuy Officials of appraisal chamber
Mr. Ong Van Tuan Compensation official on site
Mr. Nguyen My Duc Compensation official on site
2 CLRD of Pleiku city
Mr. Huynh Cong Quang Director
3 IaGrai District PC
Mr.PhanTrungTuong Vice President of District
4 Chu Prong district – Compensation council
Mr. Truong Quoc Dung Compensation Expert
5 Chu Puh district – Land Fund Development Centre
Mr. Nguyen Tan Trinh Chamber of economic infrastructure
INVESTCONSULT GROUP 31
ANNEX 2: PHOTOS OF FIELD VISITS
500 kV passing through the house of
Mr. Do Van Thin, Chu Prong district
Interview with Mr. Do Van Thin, Chu
Prong district
Work with Mr.TruongQuoc Dung –
Compensation and Site clearance Board
of Chu Prong district
Work with Mr.Nguyen Tan Trinh –
Compensation and Site clearance Board
of Chu Puh district