VISUAL MANAGEMENTDEC 1213
Topic 9:Obeya
Lecture 12Principles and Advantages
Obeya ApplicationsObeya Setup
A Member Of
LEARNING OUTCOMES
Upon completion of this session, students should be
able to:• Explain the principles and advantages of Obeya• Explain application of Obeya in real workplace• Describe how to set up the Obeya
• Obeya in Japanese means simply “big room.”
• Similar in concept to traditional “war rooms”.
• A major project management tool, used especially in product development, to enhance effective and timely communication.
What is Obeya?
Principles and Advantages
A Member Of
Principles and Advantages
A Member Of
• Contain highly visual charts and graphs on the wall showing program timing, milestones and progress to date and countermeasures to existing timing or technical problems.
• Gather the people from different functions in the room for regular face to face communication, problem solving and discussion about the project.
• Accessible to team members and customers only as confidential information is displayed.
Characteristics of Obeya
Principles and Advantages
A Member Of
• To monitor, ensure and keep track of ALL project activities so that the project is a success.
• To disseminate all project information to all relevant team members.
• To inform customer of project status and completion.
Objectives of Obeya
Principles and Advantages
A Member Of
• It is a team-oriented, promoting working together with people from different skill sets.
• It gives a full picture of the project situation.
• It is a decision making room.
• No functional area is left out of the product development process.
Functions of Obeya
Principles and Advantages
A Member Of
Principles and Advantages
Example of Obeya
A Member Of
Obeya SetupObeya Setup
Team members “SEE” the process and know where and when actions need to be completed and where the problem might be arise A Member Of
Obeya Setup
PROJECT INFORMATION• Shows all customers information- spec, quality requirement, delivery
requirement
OBEYA - Key Visual Management Items
A Member Of
Obeya Setup
PROJECT ORGANIZATION• Shows all relevant team members (with job function) and contact
details on the particular project.
OBEYA - Key Visual Management Items
A Member Of
PROCESS FLOW CHART• A schematic diagram showing all relevant process information and
flow of the current production product. Process flow chart is updated as per quality planning stage.
OBEYA - Key Visual Management Items (Continue)Obeya Setup
A Member Of
PROJECT MASTER SCHEDULE• A timeline showing the whole project timing with key customer and
supplier events. Updated weekly.
OBEYA - Key Visual Management Items (Continue)Obeya Setup
A Member Of
BILL OF MATERIAL• A breakdown of the complete assembly part for ease of
identification.
OBEYA - Key Visual Management Items (Continue)
Obeya Setup
A Member Of
TECHNICAL DRAWING• Engineering drawings updated as per revision and changes.
OBEYA - Key Visual Management Items (Continue)
Obeya Setup
A Member Of
PACKAGING INFORMATION• Details packaging information on the product.
OBEYA - Key Visual Management Items (Continue)
Obeya Setup
A Member Of
PRODUCTION LAYOUT & FLOW• Layout of the production area including the placement in the total
factory layout and it’s movement or flow.
OBEYA - Key Visual Management Items (Continue)
Obeya Setup
A Member Of
MINUTES OF MEETING• All minutes of meetings with team members, customers, and
suppliers.
OBEYA - Key Visual Management Items (Continue)
Obeya Setup
A Member Of
OBEYA - Key Visual Management Items (Continue)
HANSEI• Lesson learnt/past trouble that would be beneficial to the current
project
Obeya Setup
A Member Of
OBEYA - Example
A Member Of
OBEYA - Example
A Member Of
OBEYA - Example
A Member Of
OBEYA - ExampleObeya Setup
A Member Of
OBEYA - ExampleObeya Setup
A Member Of
OBEYA - ExampleObeya Setup
A Member Of
OBEYA - ExampleObeya Setup