Volume: II Section: 1I Page No: 7
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Bajir bawadi
Stretch Details
General Information:
Type of surface Rockfall , Soil slope with erosion, and road subsidence Average inclination of rock slope w.r.t. Horizontal
[°] Above the road Below the road
60 45°
Total Length of the stretch (L)
[m] 100 m
Total Sloping Height (H)
[m] Above the road Below the road
100 75
Vegetation (if any) Yes(Little) Debris type(soil/ boulders)
Soil and small sized rocks
Volume: II Section: 1I Page No: 8
Comprehensive CAT Plan of Satluj River Basin
Approach to top portion of Slope
Yes / No Yes
Distance required at the top of slope (for Top anchoring)
[m] 4
Type of strata at Top of Cutting slope
Soil/ Rock/Rock with Soil cover
Rock with soil cover
Distance between slope bottom and infrastructure
[m] <1.0 m
Whether any erosion control measures to be provided on the face:
Yes
No
Whether Toe protection measures are to be provided
Yes
No
Problem The slope in this area is of rock above the road and below the road the slope is made of soil. The rock slope has been eroded at some stretches leading to rockfall. The soil slope is posing a problem of stability and surface erosion. Also some parts of the stretch has the problem of road sudsidence. The toe of the slope is subjected to erosion by the river at the bottom of the slope
Proposed Solution To take account of the stability and erosion of the slopes below the road level, gabions walls and Bio Mat (erosion control mat) along with DT Mesh is proposed to be laid on the slope surface. A toe wall made of gabion can be constructed at the bottom of the slope to prevent any toe erosion or encroachment leading to the failure of the slope, which also helps in stabilizing the slope. For road subsidence, gabion walls are to be constructed below the road to improve the stability of the slope and Bio Mat is proposed to take care of erosion on the slope. U pins of 0.6 m length are used to adhere Bio Mat to the slope which are placed at spacing of 3 m c/c. Bio Mat acts as erosion control mats and which after covering with vegetative soil will aid the local shrubs to establish firm roots.
Volume: II Section: 1I Page No: 9
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Notes:
Gabion Wall for Mumbai-Pune Express way
Volume: II Section: 1I Page No: 10
Comprehensive CAT Plan of Satluj River Basin
Costing:
Location: Bajir Bawadi Stretch: Rockfall, Soil slope with erosion and Road subsidence Solution: Simple drapery system using Steel Grid MO and Erosion control Mat, Bio Mat on the failed slope and 5m High toe Gabion wall bove the Road level & Series of Gabion walls of height 5m Each for Toe protection and Slope retension ; Assumed Avg. Ht. 100.0m, length 200m; Total No. of Gabion walls : 3 No's
S.No Description Unit Qty Rate Amount (`)
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, with a thermally bonded geotextile at the rear of Gabions, etc complete.
Cum 6000 2700 16,200,000.00
2 Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 20000 250 5,000,000.00
3 Cutting of soil slope to required level and inclination as per drawing
Cum 6000 400 1,260,000.00
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 6000 250 1,500,000.00
5
Providing and laying of Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
Sq.m 20000 850 17,000,000.00
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
Sq.m 20000
-
7
Providing and laying of Simple Drapery System for protection of falling of loose boulder using SteelGrid-MO, Mesh type 10x 12, reinforced with 8.0mm steel cable over the entire slope, including providing anchors at the top and bottom, use of required accessories, complete.
Sq.m 20000 1500 7,500,000.00
8
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
LS
9,692,000.00
TOTAL
58,152,000.00
Volume: II Section: 1I Page No: 11
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Browni
Stretch Details Stretch-1
General Information
Type of surface Weathered rock mass Average inclination of
rock slope w.r.t.
Horizontal
[°]
85
Total length of the
stretch (L) [m] 250
Total Sloping Height
(H) [m] 20-50
Vegetation (if any) No Debris type(soil/
boulders) Soil mixed with Boulders
Surface of rock
Regular / Undulating / Bumpy / Overhanging
Approach to top portion of
Slope Yes / No Yes
Distance Required at the
top of slope (for Top
anchoring)
[m] 4
Type of strata at Top of
Cutting slope
Soil/ Rock/Rock with Soil cover
Rock with soil cover
Road blocked by
Volume: II Section: 1I Page No: 12
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Distance between slope
bottom and infrastructure [m] < 1.0
Whether any erosion
control measures to be
provided on the face:
Yes
No
Whether Toe protection
measures are to be
provided
Yes
No
Problem The principal problem in this stretch is of the rocks falling from the slope and blocking the road below. Since, the road is running closely to the foot of the slope, any unprecedented rockfall will lead to the closure of the road until the period of further clearance. On the slope, boulders mixed with soil are present and measures are to be taken to prevent the erosion of soil which finally leads to rockfall.
Proposed Solution To reduce the steepness of the slope, the soil portion at the top of the slope has to be removed and slope of 45° to 60° is to be made. Since large amount of the debris observed is of less than 0.5 -1 m in size, Steelgrid MO is proposed to be laid as simple drapery over the prepared slope. To prevent the debris from reaching on to the road, bottom anchoring may be done at frequent intervals for collecting debris and can be removed periodically.
Volume: II Section: 1I Page No: 13
Comprehensive CAT Plan of Satluj River Basin
Notes:
Site Details
Location Browni; At the Nalla; Problem of Debris Flow which flows in to the river
Stretch Details Stretch-2 General Information:
Type of surface Weathered rock mass with debris
Average inclination of rock slope w.r.t. Horizontal
[°] NA
Total width of the stretch (L)
[m] 10 – 15 m
Total Sloping Height (H)
[m] NA
Vegetation (if any) No Debris type(soil/ boulders)
Big Boulders
Surface of rock
Regular / Undulating / Bumpy / Overhanging
Approach to top portion of Slope
Yes / No NA
Steelgrid MO application
Flow of debris
Volume: II Section: 1I Page No: 14
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Distance Available at the top of slope (for Top anchoring)
[m] NA
Type of strata at Top of Cutting slope
Rock/soil/Rock with Soil cover
NA
Distance between slope bottom and infrastructure
[m] NA
Whether any erosion control measures to be provided on the face:
Yes
No
Whether Toe protection measures are to be provided
Yes
No
Problem The problem in this particular stretch is of the small sized boulders/debris being carried from the upstream by the flowing water in the nalla and is deposited onto the road causing obstruction to the vehicles moving on the road.
Proposed Solution Debris flow barriers are proposed to be placed at three locations across the nalla. The debris flow barriers intercept the flowing rocks and prevent them from moving further down the nalla thus preventing the debris from blocking the road. The debris flow barrier on the upstream should be of higher energy than that of the barriers provided on the downstream of the nalla.
Debris Flow Barrier
Volume: II Section: 1I Page No: 15
Comprehensive CAT Plan of Satluj River Basin
Notes: Site Details Location Browni Stretch Details Stretch-3 General Information:
Type of surface Soil slope with heavy erosion
Average inclination
of rock slope w.r.t.
Horizontal
[°] Above the road Below the road
60 45°
Total Length of the
stretch (L) [m] 100 m
Total Sloping Height
(H)
[m] Above the road Below the road
30 75
Vegetation (if any)
Yes(Shrubs and trees are present at some places of the stretch)
Debris type(soil/
boulders) Soil and small sized rocks
Debris Flow Barriers
Volume: II Section: 1I Page No: 16
Comprehensive CAT Plan of Satluj River Basin
Notes:
Approach to top
portion of Slope Yes / No Yes
Distance required at
the top of slope (for
Top anchoring)
[m] 3
Type of strata at Top
of Cutting slope
Soil/ Rock/Rock with Soil cover
Soil
Distance between
slope bottom and
infrastructure
[m] <1.0 m
Whether any erosion
control measures to
be provided on the
face:
Yes
No
Whether Toe
protection measures
are to be provided
Yes
No
Problem The stretches in this area are of steep soil slopes which pose the problem of slope instability and also subsidence of the road can be observed at some places. The slopes are also subjected to severe erosion finally leading to the failure of slopes. Further, the cuts made in the slopes for the formation of roads have lead to the instability of the slopes.
Proposed Solution To take account of the excessive erosion of the steep slopes above the road level, Bio Mat (erosion control mat) along with DT Mesh is proposed to be laid on the slope surface. A toe wall made of gabion can be constructed at the bottom of the slope to prevent any toe erosion or encroachment leading to the failure of the slope, which also helps in stabilizing the slope. For the portion of slope below the road level and for road subsidence, series of gabion walls are to be constructed at intermediate places to improve the stability of the slope and Bio Mat is proposed to take care of erosion on the slope. U pins of 0.6 m length are used to adhere Bio Mat to the slope which are placed at spacing of 3 m c/c. Bio Mat acts as erosion control mats and which after covering with vegetative soil will aid the local shrubs to establish firm roots.
Volume: II Section: 1I Page No: 17
Comprehensive CAT Plan of Satluj River Basin
Gabion Wall for Mumbai-Pune Express way
Typical Cross-section:
Costing:
Location: BROWNI Stretch: 1; Steep Slope with small sized boulders less than 0.5m nominal size with soil slope at the Top. Solution: Simple Drapery System at the Vertical Rock Face using Steel Grid MO system along with trimming of the top soil slope; Assumed Avg. Ht. 25.0m, length 200m
S.No Description Unit Qty Rate Amount (`)
1
Providing and laying of Simple Drapery System for protection of falling of loose boulder using SteelGrid-MO, Mesh type 10x 12, reinforced with 8.0mm steel cable over the entire slope, including providing anchors at the top and bottom, use of required accessories, complete.
Sq.m 5000 1500 7,500,000.00
2 Loose rock scaling on the slope Cum 1500 950 1,425,000.00
3 Trimming of the soil slope on the top to a safe angle
Cum 5000 250 1,250,000.00
Volume: II Section: 1I Page No: 18
Comprehensive CAT Plan of Satluj River Basin
4
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
LS LS
2,543,750.00
TOTAL
12,718,750.00
Location: Browni Stretch: 2; Large flow of Debris (Small to medium sized boulders debris flow with water on the Nalla) Solution: Passive system of Debris Flow protection using Flexible High Energy Debris Flow Barriers at various intervals ; Assumed Avg. width of Stretch: 10.0m, No. of Barriers : 3 No's
S.No Description Unit Qty Rate Amount (INR)
1
Providing and laying of High Energy Debris Flow Barrier System , 6m height comprising of Main Interception Nets and additional Nets , Flexible posts, detachable base plates adequately galvanised, lateral bracing cables & upslope cables with ground anchors as per design and foundation anchors for posts and with all accessories complete.
LM 30 300000 9,000,000.00
2 Removing of Loose Boulders / Debris Cum 30 950 28,500.00
4 Other miscellaneous civil works such as excavation, channelizing, access roads to the top etc.
LS LS
2,257,125.00
TOTAL
11,285,625.00
Location: Browni Stretch: 3, Soil slope with heavy erosion Solution: Simple drapery system using Steel Grid MO and Erosion control Mat, Bio Mat on the failed slope and 5m High toe Gabion wall bove the Road level & Series of Gabion walls of height 5m Each for Toe protection and Slope retension ; Assumed Avg. Ht. 105.0m, length 100m; Total No. of Gabion walls : 6 No's
S.No Description Unit Qty Rate Amount (`)
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, with a thermally bonded geotextile at the rear of Gabions, etc complete.
Cum 12000 2700 32,400,000.00
2 Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 10500 250 2,625,000.00
3 Cutting of soil slope to required level and inclination as per drawing
Cum 3150 400 1,260,000.00
4
Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 3150 250 787,500.00
Volume: II Section: 1I Page No: 19
Comprehensive CAT Plan of Satluj River Basin
5
Providing and laying of Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
Sq.m 10500 850 8,925,000.00
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
Sq.m 10500 -
7
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
LS 9,199,500.00
TOTAL 55,197,000.00
GRANTD TOTAL: 79,201,375.00
Volume: II Section: 1I Page No: 20
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details Location Dubling Bridge Stretch Details Soil Slope stability issues caused due to toe erosion at the bottom
by the River and surficial erosion on the slopes
General Information:
Type of surface Soil slope not protected by vegetation; and Toe erosion.
Average inclination of rock
slope w.r.t. Horizontal [°]
60
Total length of the stretch (L) [m] 200 Total Sloping Height (H) [m] 50 Vegetation (if any) No Debris type(soil/
boulders) Soil with small rocks
Approach to top portion of
Slope Yes / No Yes
Distance Available at the top
of slope (for Top anchoring) [m] <0.5
Type of strata at Top of
Cutting slope
Soil/Rock/Rock with Soil cover
Soil
Distance between slope
bottom and infrastructure [m] NA
Whether any erosion control
measures to be provided on
the face:
Yes
No
Whether Toe protection
measures are to be provided
Yes
No
Volume: II Section: 1I Page No: 21
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Problem The toe of the slope is being eroded by the flowing river and also the slope is made of soil which poses the problem of soil erosion. Also the flowing river is causing the problem of siltation on one side of the river at the meander.
Proposed Solution A gabion toe wall of height 5 m is proposed along the bottom of the slope to control toe erosion along with gabion mattresses of 4 m length and 0.5 m thick to prevent the scouring at the bottom. Bio Mat is proposed to be laid on the slope to prevent soil erosion along with u-pins at 3m c/c spacing. Local vegetation needs to be planted on the top of Bio Mat to enhance the protection against surficial erosion. Also to control the erosion at the bottom of the slope, groynes of 8-10 m are to be provided at two locations which help in the process of siltation.
Volume: II Section: 1I Page No: 22
Comprehensive CAT Plan of Satluj River Basin
Notes:
Volume: II Section: 1I Page No: 23
Comprehensive CAT Plan of Satluj River Basin
Costing: Location: Dubling Bridge Stretch: Soil slope not protected by vegetation and Toe erosion. Solution: Soil Slope protection with 5m High Gabion retaining wall to retain the road, Erosion control Mat, Bio Mat on the slope and 5m High toe Gabion wall at bottom along with Apron protection using 0.5m thk. And River training measures using Gabion Mattress along with some Groynes. Assumed Avg. Ht. 50.0m, length 200m; Total No. of Gabion walls : 2 No's S.No Description Unit Qty Rate Amount (`)
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for Gabion walls and Groynes, complete.
Cum 8000 2700 21,600,000.00
2 Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 10000 250 2,500,000.00
3 Cutting of soil slope to required level and inclination as per drawing
Cum 3000 400 1,200,000.00
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 3000 250 750,000.00
5
Providing and laying of Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
Sq.m 10000 850 8,500,000.00
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
Sq.m 10000 -
7
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for apron protection, complete.
Cum 1000 3200 3,200,000.00
8
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
LS LS 7,550,000.00
TOTAL 45,300,000.00
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location
Stretch Details
General Information:
Type of surface Nallas with lot of debris flow
Average inclination of rock
slope w.r.t. Horizontal [°]
Total width of the stretch
(W) [m]
Total Sloping Height (H) [m]
Vegetation (if any) No
Surface of rock
Approach to top portion of
Slope Yes / No
Distance Available at the
top of slope (for Top
anchoring)
[m]
Type of strata at Top of
Cutting slope
Soil/Rock/
with Soil cover
Distance between slope
bottom and infrastructure [m]
Whether any erosion
control measures to be
provided on the face:
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Gangarang Nalla
Nallas with lot of debris flow
NA
5-10
NA
Debris type(soil/
boulders) Big Boulders
Regular / Undulating / Bumpy / Overhanging
Yes / No NA
NA
Soil/Rock/Rock
with Soil cover NA
NA
Yes
No
Flow of debris
24
Boulders
/ Overhanging
Typical Cross-section
Whether Toe protection
measures are to be
provided
This stretch is a glacier prone nallas with
large amount of debris flows along with
heavy water flow.
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
section:
Toe protection
measures are to be Yes
No
Problem
glacier prone nallas with
large amount of debris flows along with
Proposed Solution
Debris flow barriers are
placed at three
The debris flow barriers intercept the
flowing rocks and prevent them from
moving further down the nalla thus
preventing the debris
road downstream.
the upstream is of higher energy as
compared to the barriers at other
locations
25
hensive CAT Plan of Satluj River Basin
Proposed Solution
Debris flow barriers are proposed to be
locations across the nalla.
The debris flow barriers intercept the
flowing rocks and prevent them from
moving further down the nalla thus
preventing the debris from damaging the
road downstream. The barrier provided on
the upstream is of higher energy as
compared to the barriers at other
Comprehensive CAT Plan of Satluj River Basin
Notes:
Costing:
Location: Gangarang Nalla
Stretch: Nallas with lot of debris flow
Solution: Passive system of Debris flow protection through the Nallahs using Flexible
High Debris Flow Barriers at various intervals ; Assumed Avg. width of Stretch: 10.0m,
No. of Barriers : 3 No's
S.No Description
1
Providing and laying of High Energy
Debris Flow Barrier System , 6m height
comprising of Main Interception Nets and
additional Nets , Flexible posts,
detachable base plates adequately
galvanised, lateral bracing cables &
upslope cables with ground anchors as
per design and foundation anchors for
posts and with all accessories complete.
2 Removing of Loose Boulders
3
Providing and laying of Spot rock bolting
for a depth of 5-6m, with a 32mm dia
continuous threaded bar including drilling
and grouting
4
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to
the top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
with lot of debris flow
Solution: Passive system of Debris flow protection through the Nallahs using Flexible
High Debris Flow Barriers at various intervals ; Assumed Avg. width of Stretch: 10.0m,
Unit Qty Rate Amount (INR)
Providing and laying of High Energy
Debris Flow Barrier System , 6m height
comprising of Main Interception Nets and
additional Nets , Flexible posts,
detachable base plates adequately
galvanised, lateral bracing cables &
ground anchors as
per design and foundation anchors for
posts and with all accessories complete.
LM 30 300000
9,000,000.00
Cum 30 950
28,500.00
Providing and laying of Spot rock bolting
6m, with a 32mm dia
continuous threaded bar including drilling Nos 32 28800
921,600.00
Other miscellaneous civil works such as
toe collection
system of loose rocks, access roads to LS LS
2,487,525.00
12,437,625.00
26
Solution: Passive system of Debris flow protection through the Nallahs using Flexible
High Debris Flow Barriers at various intervals ; Assumed Avg. width of Stretch: 10.0m,
Amount (INR)
9,000,000.00
28,500.00
921,600.00
2,487,525.00
12,437,625.00
Section 2:
Introduction
Site Details
Location Stretch Details
General Information
Type of surface
Average inclination of soil slope w.r.t. Horizontal
Total Length of the stretch (L) Total Sloping Height (H)
Vegetation (if any)
Approach to top portion of Slope Distance Required at the top of slope (for Top anchoring)
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Khadura Dhank
General Information:
Soil slope with heavy erosion
[°]
60 – 70 Degrees
[m] 1500 m
Sloping Height [m]
100 m
Yes Debris type(soil/ boulders)
Yes / No ----
at the top of slope (for [m] 5
27
hensive CAT Plan of Satluj River Basin
70 Degrees
Debris type(soil/ Soil with boulders
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Type of strata at Top of Cutting slope
Soil/Rock/Rock with Soil cover
Distance between slope bottom and infrastructure
[m]
Whether any erosion control measures to be provided on the face:
Yes
Whether Toe protection measures are to be provided
Yes
Problem The problem at this stretch can be divided as
soil erosion on the slope and the toe erosion
of the slope by the river water. Due to the
erosion of the soil on the slope, boulders
from the slope are falling into the river,
obstructing the water flow. Also the toe
erosion in a period of time may lead to the
global failure of the slope
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Soil/Rock/Rock with Soil
NA
Yes
No
Yes
No
The problem at this stretch can be divided as
soil erosion on the slope and the toe erosion
of the slope by the river water. Due to the
erosion of the soil on the slope, boulders
river,
obstructing the water flow. Also the toe
erosion in a period of time may lead to the
Proposed Solution A toe wall made from gabions is to be
placed at the toe of the slope to prevent
the erosion at the bottom of the slope
due to the river. The soil slope has to be
cut and trimmed to make an slope of 45°
- 60°. Over the prepared slope,
or Biomac can be laid to promote the
vegetation on the surface which can be
adhered to slope using 0.6 m length U
pins.
28
Proposed Solution
A toe wall made from gabions is to be
o prevent
the erosion at the bottom of the slope
has to be
cut and trimmed to make an slope of 45°
60°. Over the prepared slope, Bio Mat
or Biomac can be laid to promote the
which can be
adhered to slope using 0.6 m length U-
Notes:
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
29
hensive CAT Plan of Satluj River Basin
Comprehensive CAT Plan of Satluj River Basin
Costing:
Location: Khadura Dhank Stretch: Soil slope with heavy erosionSolution: Erosion control Mat, Bio Matbottom along with Apron protection using 0.5m thk. Gabion Mattress Assumed Avg. Ht. 100.0m, length 1500m;
S.No Description
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for Gabion walls and Groynes, complete.
2 Dressing of the soil-boulder slope to obtain a levelled surface
3 Cutting of soil slope to required level and inclination as per drawing
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
5
Providing and laying of Bio MatReinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
7
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for apron protection, complete.
8
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Stretch: Soil slope with heavy erosion Bio Mat on the slope and 5m High toe Gabion wall at
bottom along with Apron protection using 0.5m thk. Gabion Mattress Assumed Avg. Ht.
Unit Qty Rate Amount (
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for
ls and Groynes, complete.
Cum 30000 2700 81,000,000.00
boulder slope to Sq.m 150000 250
37,500,000.00
Cutting of soil slope to required level
Cum 45000 400 18,000,000.00
Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 45000 250 11,250,000.00
Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at
4m c/c, neccessary laps etc
Sq.m 150000 850 127,500,000.00
Spreading of vegetative soil over the Erosion Control Blanket and planting of Sq.m 150000
-
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with
equired sizes and quality etc for apron protection, complete.
Cum 3750 2500 9,375,000.00
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS 56,925,000.00
341,550,000.00
30
on the slope and 5m High toe Gabion wall at bottom along with Apron protection using 0.5m thk. Gabion Mattress Assumed Avg. Ht.
Amount (`)
81,000,000.00
37,500,000.00 18,000,000.00
11,250,000.00
127,500,000.00
9,375,000.00
56,925,000.00
341,550,000.00
Volume: II Section: 1I Page No: 31
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details Location Kaneri Stretch Details General Information:
Type of problem Landslide
Average inclination of rock
slope w.r.t. Horizontal 60°
Total Length of the stretch
(L) [m] 300 m
Total Sloping Height (H) [m]
30
Vegetation (if any) Yes Debris type(soil/
boulders) ------
Volume: II Section: 1I Page No: 32
Comprehensive CAT Plan of Satluj River Basin
Approach to top portion of
Slope Yes / No Yes
Distance required at the top
of slope (for Top anchoring) [m] NA
Type of strata at Top of
Cutting slope
Soil/ Rock/Rock with Soil cover
NA
Distance between slope
bottom and infrastructure [m] <1.0 m
Whether any erosion
control measures to be
provided on the face:
Yes
No
Whether Toe protection
measures are to be
provided
Yes
No
Problem The slope in this area is has failed causing lanslides and change in the level of the roads.
Proposed Solution To take account of the stability of the stability of the slope and the landslide, gabion walls as supposed to be placed at suitable locations on the slope.
Volume: II Section: 1I Page No: 33
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Notes:
Gabion Wall for Mumbai-Pune Express way
Volume: II Section: 1I Page No: 34
Comprehensive CAT Plan of Satluj River Basin
Costing:
Location: Kaneri Stretch: Landslide and slope stability Solution: 5m High toe Gabion walls above the Road level ; Assumed Avg. Ht. 30.0m, length 300m; Total No. of Gabion walls : 2 No's
S.No Description Unit Qty Rate Amount (`)
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, with a thermally bonded geotextile at the rear of Gabions, etc complete.
Cum 12000 2700 32,400,000.00
2 Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 9000 250 2,250,000.00
3 Cutting of soil slope to required level and inclination as per drawing
Cum 2700 400 1,260,000.00
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 2700 250 675,000.00
5
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
LS 7,317,000.00
TOTAL 43,902,000.00
Section 2:
Introduction
Site Details
Location
Stretch Details
General Information
Type of surface
Average inclination
of rock slope w.r.t.
Horizontal
Total width of the
stretch (W)
Total Sloping Height
(H)
Vegetation (if any)
Surface of rock
Approach to top
portion of Slope
Distance Available at
the top of slope (for
Top anchoring)
Type of strata at Top
of Cutting slope
Volume: II Section: II Page No:
Comprehensive CAT Plan of Satluj River Basin
Khoragla Nalla
General Information:
Nallas with debris flow
[°]
NA
[m] 15-20
Sloping Height [m] NA
No Debris type(soil/
boulders)
Regular / Undulating / Bumpy
Yes / No NA
Distance Available at
the top of slope (for [m] NA
of strata at Top Rock with Soil cover NA
Debris Flow
35
hensive CAT Plan of Satluj River Basin
Debris type(soil/ Big Boulders
/ Overhanging
Debris Flow
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Distance between
slope bottom and
infrastructure
[m]
Whether any erosion
control measures to
be provided on the
face:
Yes
Whether Toe
protection measures
are to be provided
Yes
Problem
This stretch is the glacier prone nallas with
large amount of debris flows along with
heavy water flow.
Volume: II Section: II Page No:
hensive CAT Plan of Satluj River Basin
NA
Yes
No
Yes
No
This stretch is the glacier prone nallas with
large amount of debris flows along with
Proposed Solution
Series of three high energy debris flow
barriers made of ring nets are to be
constructed at the upstream side of the
nalla to prevent the huge rock masses
from moving down the nalla.
36
high energy debris flow
are to be
constructed at the upstream side of the
nalla to prevent the huge rock masses
Notes:
Costing:
Location: Khoragla Nalla
Stretch: Nallas with lot of debris flow
Solution: Passive system of Debris Flow protection using Flexible High Energy Debris
Flow Barriers at various intervals ;
Barriers : 3 No's
S.No Description
1
Providing and laying of High Energy
Debris Flow Barrier System ,
comprising of Main Interception Nets
and additional Nets , Flexible posts,
detachable base plates adequately
galvanised, lateral bracing cables &
upslope cables with ground anchors as
per design and foundation anchors for
posts and with all acc
2 Removing of Loose Boulders
3
Providing and laying of Spot rock
bolting for a depth of 5
32mm dia continuous threaded bar
including drilling and grouting
4
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to
the top etc.
TOTAL
Volume: II Section: II Page No:
Comprehensive CAT Plan of Satluj River Basin
Location: Khoragla Nalla
Stretch: Nallas with lot of debris flow
Solution: Passive system of Debris Flow protection using Flexible High Energy Debris
Flow Barriers at various intervals ; Assumed Avg. width of Stretch: 20.0m, No. of
Unit Qty
Providing and laying of High Energy
Debris Flow Barrier System , 6m height
comprising of Main Interception Nets
and additional Nets , Flexible posts,
detachable base plates adequately
galvanised, lateral bracing cables &
upslope cables with ground anchors as
per design and foundation anchors for
posts and with all accessories complete.
LM 30
Removing of Loose Boulders Cum 30
Providing and laying of Spot rock
bolting for a depth of 5-6m, with a
continuous threaded bar
including drilling and grouting
Nos 32
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to LS LS
37
hensive CAT Plan of Satluj River Basin
Solution: Passive system of Debris Flow protection using Flexible High Energy Debris
Assumed Avg. width of Stretch: 20.0m, No. of
Rate Amount (INR)
300000
9,000,000.00
950
28,500.00
28800
921,600.00
2,487,525.00
12,437,625.00
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Kuppa valley Stretch Details
General Information
Type of surface Soil slope with heavy erosion
Average inclination of rock slope w.r.t. Horizontal
[°] Above the road Below the road
Total Length of the stretch (L)
[m]
Total Sloping Height (H)
[m]
Vegetation (if any) Yes
Approach to top portion of Slope
Yes / No
Distance Required at the top of slope (for Top anchoring)
[m]
Type of strata at Top of Cutting slope
Soil/ Rock/Rock with Soil cover
Volume: II Section: II Page No:
hensive CAT Plan of Satluj River Basin
Soil slope with heavy erosion
Above the road
Below the road
60-70 50-60°
500
200
Debris type(soil/ boulders)
Soil
Yes
5
Rock with Soil
38
Typical Cross
Distance between slope bottom and infrastructure Whether any erosion control measures to be provided on the face: Whether Toe protection measures are to be provided
Problem The main problem at this stretch is of the loose soil mixed with boulders. The steep slopes pose the problem of heavy erosion and slope instability. the base of the slope is causing the problem of erosion of soil at the bottom leadierosion. Since the slope is made of soil, the surface also has the problem of continuous soil erosion.
Volume: II Section: II Page No:
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
[m] <0.5 m
Whether any erosion to Yes
No
protection measures Yes
No
Problem
The main problem at this stretch is of the loose soil mixed with boulders. The steep slopes pose the problem of heavy erosion and slope instability. Baspa river flowing at the base of the slope is causing the problem of erosion of soil at the bottom leading to toe erosion. Since the slope is made of soil, the surface also has the problem of continuous
Proposed Solution The slope has to be trimmed and made to an angle of 45-with Biomac or adhered to the slope with UGabions walls of heifght 5 m are placed at intermediate locations on the slope below the road. A toe wall made of gabion is placed at the bottom of the slope to prevent toe erosion and 0.5 m thick gabion mattress is also placed at the bottom to take prevent scouring.Erosion control Mats to be covered with vegetative soil and planted with local shrubs.
39
hensive CAT Plan of Satluj River Basin
Proposed Solution
The slope has to be trimmed and made to -60° and is to be covered
with Biomac or Bio Mat and DT Mesh adhered to the slope with U-pins. Gabions walls of heifght 5 m are placed at intermediate locations on the slope below the road. A toe wall made of gabion is placed at the bottom of the slope to prevent toe erosion and 0.5 m
mattress is also placed at the bottom to take prevent scouring. Erosion control Mats to be covered with vegetative soil and planted with local
Comprehensive CAT Plan of Satluj River Basin
Volume: II Section: II Page No:
hensive CAT Plan of Satluj River Basin
40
Costing:
Location: Kuppa ValleyStretch: Soil slope with heavy surficial erosion, toe erosion from RiverSolution: Soil Stabilization using Erosion control Mat, High toe Gabion wall bove the Road level & Series of Gabion walls of height 5m Each for Toe protection and Slope retension ; Assumed Avg. Ht. 200.0m, length 500m; Total No. of Gabion walls : 6 No's
S.No Description
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVCMesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
2 Dressing of the soilobtain a levelled surface
3 Cutting of soil slope to required level and inclination as per drawing
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
5
Providing and laying of Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
7 Loose rock scaling on the slope
8 Trimming of the soil slope on the top to a safe angle
9
Other miscellaneous civil works such as providing proper system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: II Page No:
Comprehensive CAT Plan of Satluj River Basin
Location: Kuppa Valley Stretch: Soil slope with heavy surficial erosion, toe erosion from RiverSolution: Soil Stabilization using Erosion control Mat, Bio Mat on the failed slope and 5m High toe Gabion wall bove the Road level & Series of Gabion walls of height 5m Each for
protection and Slope retension ; Assumed Avg. Ht. 200.0m, length 500m; Total No. of Gabion walls : 6 No's
Unit Qty
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc,
Cum 40000
Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 100000
Cutting of soil slope to required level and inclination as per drawing
Cum 30000
at select areas with the excavated material to the required level and inclination as per drawings
Cum 30000
Providing and laying of Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at
4m c/c, neccessary laps etc
Sq.m 100000
Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
Sq.m 100000
Loose rock scaling on the slope Cum 2500
Trimming of the soil slope on the top to
Sq.m 500
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS
41
hensive CAT Plan of Satluj River Basin
Stretch: Soil slope with heavy surficial erosion, toe erosion from River on the failed slope and 5m
High toe Gabion wall bove the Road level & Series of Gabion walls of height 5m Each for protection and Slope retension ; Assumed Avg. Ht. 200.0m, length 500m; Total No.
Rate Amount (`)
40000 2700 108,000,000.00
100000 250 25,000,000.00
30000 400 12,000,000.00
30000 250 7,500,000.00
100000 850 85,000,000.00
100000 -
950 2,375,000.00
250 125,000.00
48,000,000.00
288,000,000.00
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Lal Dhank Stretch Details
General Information
Type of surface Fragmented Rocks on the erosion
Average inclination of rock slope w.r.t. Horizontal
[°]
Total Length of the stretch (L)
[m]
Total Sloping Height (H)
[m]
Vegetation (if any) Yes
Surface of rock
Regular / Undulating / Bumpy / Overhanging
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Fragmented Rocks on the slope with soil cover subjected to
[°] 60
500
500
Debris type(soil/ boulders)
Huge Boulders
Regular / Undulating / Bumpy / Overhanging
42
subjected to
Huge Boulders
Regular / Undulating / Bumpy / Overhanging
Typical Cross-section
Approach to top portion of Slope Distance Required the top of slope (for Top anchoring) Type of strata at Top of Cutting slope Distance between slope bottom and infrastructure/ road Whether any erosion control measures to be provided on the face: Whether Toe protection measures are to be provided
Problem The rocks on the slope are fragmented with joints and fissures. There is loose soil cover on the top which also causes the removal of small sized rocks.
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
section:
Yes / No ---
the top of slope (for [m] 10
Type of strata at Top Soil/Rock/Rock with Soil cover
Rock with soil cover
[m] ----
Whether any erosion control measures to Yes
No
protection measures Yes
No
Problem
The rocks on the slope are fragmented with joints and fissures. There is loose soil cover
which also causes the removal of
Proposed Solution HEA panels of 400 x 400/10 mm
double twisted mesh
cortical strengthening are proposed on
the surface after the removal of loosely
held rock masses.
43
hensive CAT Plan of Satluj River Basin
Rock with soil cover
Proposed Solution
of 400 x 400/10 mm and
double twisted mesh 10x12/3 with
cortical strengthening are proposed on
the surface after the removal of loosely
held rock masses.
Comprehensive CAT Plan of Satluj River Basin
Notes:
Costing:
Location: Lal Dhank Stretch: Fragmented Rocks on the slope with soil cover Solution: Simple Drapery System at the Vertical Rock Face using HEA Panel + DT Netting system iand cortical strengthening over the slope; Assumed Avg. Ht. 100.0m, length 500m
S.No Description
1
Providing and laying of Simple Drapery System for protection of falling of loose boulder using HEA Panel, size 400 x 400mm, 10.0mm steel cable with a Mechnanically woven Double Twisted Zn. + PVC Coated Wire Mesh, 2.70/3.70mm dia. over the entire slope, including providing anchors at the top and bottom, use of required accessories like top support etc, complete.
2 Loose rock scaling on the slope
3 Trimming/removal of any existing soil slope on the top to a safe angle
4
Supply and fixing of Steel Anchor bolts of 25mm dia. and depth of 3m with washer plates of size 150mm x150mm x 6mm in rock for cortical strengthening at 3m c/c including drilling of holes, inserting cement capsules inside the holes, other accessories etc.with all contractors materials, scaffolding, tools & plants, all lead & lift, contractors manpower etc, as complete and as shown in drawings.
4
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Stretch: Fragmented Rocks on the slope with soil cover Solution: Simple Drapery System at the Vertical Rock Face using HEA Panel + DT Netting system iand cortical strengthening over the slope; Assumed Avg. Ht. 100.0m, length
Unit Qty Rate Amount (
Providing and laying of Simple Drapery System for protection of falling of loose boulder using HEA Panel, size 400 x 400mm, 10.0mm steel cable with a
woven Double Twisted Zn. + PVC Coated Wire Mesh, 2.70/3.70mm dia. over the entire slope, including providing anchors at the top and bottom, use of required accessories like top support etc,
Sq.m 50000 4000 200,000,000.00
Loose rock scaling on the slope Cum 10000 950 9,500,000.00
Trimming/removal of any existing soil slope on the top to a safe angle
Sq.m 10000 250 2,500,000.00
Supply and fixing of Steel Anchor bolts of 25mm dia. and depth of 3m with washer plates of size 150mm x150mm
strengthening at 3m c/c including drilling of holes, inserting cement capsules inside the holes, other
ith all contractors materials, scaffolding, tools & plants, all lead & lift, contractors manpower etc, as complete and as shown in
No's 1111 7500 8,332,500.00
Other miscellaneous civil works such as proper drains, toe collection
system of loose rocks, access roads to LS
44,066,500.00
264,399,000.00
44
Solution: Simple Drapery System at the Vertical Rock Face using HEA Panel + DT Netting system iand cortical strengthening over the slope; Assumed Avg. Ht. 100.0m, length
Amount (`)
200,000,000.00
9,500,000.00 2,500,000.00
8,332,500.00
44,066,500.00
264,399,000.00
Section 2:
Introduction
Site Details
Location
Stretch Details
General Information
Type of surface
Average inclination
of rock slope w.r.t.
Horizontal
Total Length of the
stretch (L)
Total Sloping Height
(H)
Vegetation (if any)
Approach to top
portion of Slope
Distance Available at
the top of slope (for
Top anchoring)
Volume: II Section: 1I Page No: 45
Comprehensive CAT Plan of Satluj River Basin
Lippa Valley
Below the road level
General Information:
Soil slope subjected to erosion
[°]
45
[m] 200
Sloping Height [m] 8
Yes Debris type(soil/
boulders)
Yes / No Yes
Distance Available at
the top of slope (for [m] NA
45
hensive CAT Plan of Satluj River Basin
Debris type(soil/ Soil and small
sized rocks
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Notes:
Type of strata at Top
of Cutting slope
Soil/Rock/Rock with
Soil cover
Distance between
slope bottom and
infrastructure
[m]
Whether any erosion
control measures to
be provided on the
face:
Yes
Whether Toe
protection measures
are to be provided
Yes
Problem
The main problem is of the slope material at
the bottom being carried away by the
flowing water in the river. The slope is made
of soil which also causes erosion over the
surface of the slope.
8 m high Gabion wall on bank of river Godavari, Nasik
Volume: II Section: 1I Page No: 46
hensive CAT Plan of Satluj River Basin
Rock with NA
NA
Yes
No
Yes
No
main problem is of the slope material at
the bottom being carried away by the
flowing water in the river. The slope is made
of soil which also causes erosion over the
Proposed Solution
Over the slope, Bio Mat can be provided
to prevent the erosion of the slope.
high gabion wall and 0.5 m thick gabion
mattress can be constructed along the
bottom of the slope to protect the base of
the slope from the erosion effect of the
river water.
Gabion wall on bank of river Godavari, Nasik
46
Proposed Solution
can be provided
to prevent the erosion of the slope. 3 m
and 0.5 m thick gabion
can be constructed along the
bottom of the slope to protect the base of
effect of the
Section 2:
Introduction
Site Details
Location Stretch Details
General Information
Type of surface
Average inclination of rock slope w.r.t. Horizontal Total length of the stretch (L) Total Sloping Height (H)
Vegetation (if any)
Surface of rock
Approach to top portion of Slope Distance Required at the top of slope (for Top anchoring) Type of strata at Top Cutting slope
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Lippa Valley Above the road
General Information
Soil Slope with huge boulders
erage inclination of [°]
80
[m] 200
Sloping Height [m] 50
Yes Debris type(soil/ boulders)
Regular / Undulating / Bumpy
Approach to top portion Yes / No Yes
at the top of slope (for [m] 4
Type of strata at Top of Soil/ Rock/Rock with Soil cover
Rock with soil cover
47
Basin
Debris type(soil/ Boulders and soil
Regular / Undulating / Bumpy / Overhanging
Rock with soil cover
Comprehensive CAT Plan of Satluj River
Typical Cross-section:
Distance between slope bottom and infrastructure
[m]
Whether any erosion control measures to be provided on the face:
Yes
Whether Toe protection measures are to be provided
Yes
Problem
Loosely held huge rock boulders on the
slope are to be prevented from falling down
the slope.
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
< 1.0
No
No
Loosely held huge rock boulders on the
slope are to be prevented from falling down
Proposed Solution Scaling should be done to remove the
loose boulders on the surface of the
slope. After scaling, HEA panels 400x
400/10 along with double twisted mesh
10x12 is draped over the slope with top
and bottom anchoring.
48
Scaling should be done to remove the
loose boulders on the surface of the
HEA panels 400x
400/10 along with double twisted mesh
10x12 is draped over the slope with top
Notes:
Costing:
Location: Lippa ValleyStretch: 1, Soil slope subjected to erosionSolution: Erosion control Mat, bottom including 0.5 m thk Gabion mattress as apron protection; Assumed Avg. Ht. 8.0m, length 200m; Total No. of Gabion walls : 1 No
S.No Description
1
Providing and laying ofwoven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
2 Dressing of the soilobtain a levelled surface
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
5
Providing and laying of Bio Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
10
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
HEA + DT over the slope
Location: Lippa Valley Stretch: 1, Soil slope subjected to erosion Solution: Erosion control Mat, Bio Mat on the failed slope and 5m High toe Gabion wall at bottom including 0.5 m thk Gabion mattress as apron protection; Assumed Avg. Ht. 8.0m, length 200m; Total No. of Gabion walls : 1 No
Unit Qty
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
Cum 4000
Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 1600
Backfilling at select areas with the excavated material to the required level
inclination as per drawings Cum 480
Providing and laying of Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at
4m c/c, neccessary laps etc
Cum 1600
Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
Sq.m 1600
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS LS
49
Basin
on the failed slope and 5m High toe Gabion wall at bottom including 0.5 m thk Gabion mattress as apron protection; Assumed Avg. Ht.
Rate Amount (`)
4000 2700 10,800,000.00
1600 250 400,000.00
400 192,000.00
1600 850 1,360,000.00
1600 -
2,550,400.00
15,302,400.00
Comprehensive CAT Plan of Satluj River
Location: Lippa Valley Stretch: 2; Steep Slope with Moderately jointed rock slope with boulders of big size > 0.5m and < 1.0m. Solution: Simple Drapery System at the Vertical Rock Face using HEA Panel + DT Netting system ; Assumed Avg. Ht. 50.0m, length 200m
S.No Description
1
Providing and laying of Simple Drapery System for protection of falling of loose boulder using HEA Panel, size 400 x 400mm, 10.0mm steel cable with a Mechnanically woven Double Twisted Zn. + PVC Coated Wire Mesh, 2.70/3.70mm dia. over the entire slope, including providing anchors at the top and bottom, use of required accessories like top support etc, complete.
2 Loose rock scaling on the slope
3 Trimming/removal of any existing soil slope on the top to a safe angle
4
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Stretch: 2; Steep Slope with Moderately jointed rock slope with boulders of big size >
Drapery System at the Vertical Rock Face using HEA Panel + DT Netting system ; Assumed Avg. Ht. 50.0m, length 200m
Unit Qty Rate Amount (
Providing and laying of Simple Drapery System for protection of falling of loose
HEA Panel, size 400 x 400mm, 10.0mm steel cable with a Mechnanically woven Double Twisted Zn. + PVC Coated Wire Mesh, 2.70/3.70mm dia. over the entire slope, including providing anchors at the top and bottom, use of required accessories
tc, complete.
Sq.m 10000 4000 40,000,000.00
Loose rock scaling on the slope Cum 2000 950 1,900,000.00
Trimming/removal of any existing soil slope on the top to a safe angle
Sq.m 2000 250 500,000.00
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS 8,480,000.00
50,880,000.00
50
Stretch: 2; Steep Slope with Moderately jointed rock slope with boulders of big size >
Drapery System at the Vertical Rock Face using HEA Panel + DT Netting
Amount (`)
40,000,000.00
1,900,000.00 500,000.00
8,480,000.00
50,880,000.00
Section 2:
Introduction
Site Details
Location
Stretch Details
General Information
Type of surface
Average inclination of
rock slope w.r.t.
Horizontal
Total length of the
stretch (L)
Total Sloping Height
Vegetation (if any)
Surface of rock
Approach to top portion
of Slope
Distance Available at
the top of slope (for
Top anchoring)
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Namgia
General Information
Slope with several outcrops rock of heavy weathered rock
inclination of [°]
30
[m] --
Sloping Height (H) [m] 150
No Debris type(soil/
boulders)
Regular / Undulating / Bumpy
Approach to top portion Yes / No Yes
Distance Available at
the top of slope (for [m] NA
51
hensive CAT Plan of Satluj River Basin
Slope with several outcrops rock of heavy weathered
Debris type(soil/ Boulders
Regular / Undulating / Bumpy / Overhanging
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section
Type of strata at Top of
Cutting slope
Soil/ Rock/Rock with Soil cover
Distance between slope
bottom and
infrastructure
[m]
Whether any erosion
control measures to be
provided on the face:
Yes
Whether Toe protection
measures are to be
provided
Yes
Problem
The rocks from the slopes are rolling down
the slope and falling onto the infrastructure
at the base of the slope.
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Soil/ Rock/Rock with Soil cover
Rock
< 1.0
No
No
The rocks from the slopes are rolling down
the slope and falling onto the infrastructure
Proposed Solution A series of weirs with gabions can be
constructed on the slope to retain the
rocks from moving down the slope and
also vegetation can be also promoted on
the gabions.
52
Proposed Solution
A series of weirs with gabions can be
retain the
rocks from moving down the slope and
also vegetation can be also promoted on
Notes:
Costing:
Location: Namgia Stretch: Large slope stabilization with a water ChannelSolution: Series of Gabion weirs each of height 5m; Assumed Avg. Ht. 150.0m, length 200m; Total No. of Gabion walls : 5 No's
S.No Description
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
2 Dressing of the soilobtain a levelled surface
3 Cutting of soil slope to required level and inclination as per drawing
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
10
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Stretch: Large slope stabilization with a water Channel Solution: Series of Gabion weirs each of height 5m; Assumed Avg. Ht. 150.0m, length 200m; Total No. of Gabion walls : 5 No's
Unit Qty
Providing and laying of mechanically woven double twisted hexagonal shaped
Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
Cum 20000
Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 30000
Cutting of soil slope to required level and inclination as per drawing
Cum 9000
Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 9000
Spreading of vegetative soil over the Erosion Control Blanket and planting of
shrubs etc Sq.m 30000
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS
53
hensive CAT Plan of Satluj River Basin
Solution: Series of Gabion weirs each of height 5m; Assumed Avg. Ht. 150.0m, length
Rate Amount (`)
20000 2700 54,000,000.00
30000 250 7,500,000.00
400 3,600,000.00
250 2,250,000.00
30000 -
13,470,000.00
80,820,000.00
Comprehensive CAT Plan of Satluj River
Section 2:
Introduction
Site Details
Location Powari Pangi Nalla
Stretch Details Above the road level
General Information
Type of surface Slope with several outcrops rock of heavy weathered rock
Average inclination
of rock slope w.r.t.
Horizontal
[°]
Total Length of the
stretch (L) [m]
Total Sloping Height
(H) [m]
Vegetation (if any) Yes
Surface of rock
Regular / Undulating / Bumpy / Overhanging
Approach to top
portion of Slope Yes / No
Distance Available at
the top of slope (for
Top anchoring)
[m]
Type of strata at Top
of Cutting slope
Soil/Rock/Rock with
Soil cover
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Powari Pangi Nalla
Above the road level
Slope with several outcrops rock of heavy weathered rock
[°] 60
2000
150 - 200
Debris type(soil/
boulders) Huge Boulders
Regular / Undulating / Bumpy / Overhanging
Yes
---
Rock with Rock
54
Slope with several outcrops rock of heavy weathered rock
Huge Boulders
Regular / Undulating / Bumpy / Overhanging
Typical Cross-section
Distance between
slope bottom and
infrastructure/ road
Whether any erosion
control measures to
be provided on the
face:
Whether Toe
protection measures
are to be provided
Problem
The problem is of the large boulders rolling
down the slopes from high heights causing
damage and blockage of roads
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
section:
[m] <0.5 m
Whether any erosion
measures to Yes
No
protection measures Yes
No
The problem is of the large boulders rolling
down the slopes from high heights causing
damage and blockage of roads.
Proposed Solution
A toe wall made from gabions is to be
placed at the toe of the slope to prevent
the erosion at the bottom of the slope
due to the river. The soil slope has to be
cut and trimmed to make an slope of 60°.
Over the prepared slope, Bio Mat can be
laid to promote the vegetation on the
surface which can be adhered to slope
using 0.6 m length U
55
Basin
Proposed Solution
A toe wall made from gabions is to be
placed at the toe of the slope to prevent
the erosion at the bottom of the slope
due to the river. The soil slope has to be
cut and trimmed to make an slope of 60°.
Over the prepared slope, Bio Mat can be
te the vegetation on the
surface which can be adhered to slope
using 0.6 m length U-pins.
Comprehensive CAT Plan of Satluj River
Notes:
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
56
Costing:
Location: Powari Pangi
Stretch: Slope with several outcrops rock of heavy weathered rock
Solution: Erosion control Mat,
bottom along with Apron protection using 0.5m thk. Gabion Mattress Assumed Avg. Ht.
175.0m, length 2000m;
S.No Description
1
Providing and laying of mechanically
woven double twisted hexagonal
shaped Zn+PVC
Mesh wire Dia. 2.7mm / 3.7mm and
Mesh type 10x12 including lacing,
tying and filling of Gabions with stones
of required sizes and quality etc for
Gabion walls and Groynes, complete.
2 Dressing of the soil
obtain a levelled surface
3 Cutting of soil slope to required level
and inclination as per drawing
4
Backfilling at select areas with the
excavated material to the required
level and inclination as per drawings
5
Providing and laying of Bio Mat Turf
Reinforcement Mat made of an open
three dimensional synthetic mat made
of Polypropylene filaments with an
additional Hexagonal shaped Double
Twisted Wire Mesh of Mesh Type 10 x
12, Zn + PVC Coated 2.70/3.70 mm
wire dia. including providing U Pins at
every 3-4m c/c, neccessary laps etc
6
Spreading of vegetative soil over the
Erosion Control Blanket and planting of
local shrubs etc
7
Providing and laying of mechanically
woven double twisted hexagonal
shaped Zn+PVC
mattress of 0.5m thickness and 5m
length and of Mesh wire Dia. 2.7mm /
3.7mm and Mesh type 10x12 including
lacing, tying and filling of Gabions with
stones of required sizes and quality etc
for apron protection, complete.
8
Other miscellaneous civil works such
as providing proper drains, toe
collection system of loose rocks, access
roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Location: Powari Pangi
Stretch: Slope with several outcrops rock of heavy weathered rock
Solution: Erosion control Mat, Bio Mat on the slope and 5m High toe Gabion wall at
bottom along with Apron protection using 0.5m thk. Gabion Mattress Assumed Avg. Ht.
175.0m, length 2000m;
Unit Qty
Providing and laying of mechanically
woven double twisted hexagonal
shaped Zn+PVC Coated Gabions of
Mesh wire Dia. 2.7mm / 3.7mm and
Mesh type 10x12 including lacing,
tying and filling of Gabions with stones
of required sizes and quality etc for
Gabion walls and Groynes, complete.
Cum 40000
Dressing of the soil-boulder slope to
obtain a levelled surface Sq.m 350000
Cutting of soil slope to required level
and inclination as per drawing Cum 105000
Backfilling at select areas with the
excavated material to the required
level and inclination as per drawings
Cum 105000
Providing and laying of Bio Mat Turf
Reinforcement Mat made of an open
three dimensional synthetic mat made
of Polypropylene filaments with an
additional Hexagonal shaped Double
Twisted Wire Mesh of Mesh Type 10 x
12, Zn + PVC Coated 2.70/3.70 mm
. including providing U Pins at
4m c/c, neccessary laps etc
Sq.m 350000
Spreading of vegetative soil over the
Erosion Control Blanket and planting of
local shrubs etc
Sq.m 350000
Providing and laying of mechanically
woven double twisted hexagonal
shaped Zn+PVC Coated Gabion
mattress of 0.5m thickness and 5m
length and of Mesh wire Dia. 2.7mm /
3.7mm and Mesh type 10x12 including
lacing, tying and filling of Gabions with
stones of required sizes and quality etc
for apron protection, complete.
Cum 5000
Other miscellaneous civil works such
as providing proper drains, toe
collection system of loose rocks, access
roads to the top etc.
LS
57
Basin
Stretch: Slope with several outcrops rock of heavy weathered rock
on the slope and 5m High toe Gabion wall at
bottom along with Apron protection using 0.5m thk. Gabion Mattress Assumed Avg. Ht.
Rate Amount (INR)
2700
108,000,000.00
350000 250
87,500,000.00
105000 400
42,000,000.00
105000 250
26,250,000.00
350000 850
297,500,000.00
350000
-
2500
12,500,000.00
114,750,000.00
688,500,000.00
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Powari Pangi NallaStretch Details Below the road level
General Information:
Type of surface Soil slope with
Average inclination of rock slope w.r.t. Horizontal
[°]
Total Length of the stretch (L)
[m]
Total Sloping Height (H)
[m]
Vegetation (if any) No
Approach to top portion of Slope
Yes / No
Distance Available at the top of slope (for Top anchoring)
[m]
Type of strata at Top of Cutting slope
Soil/Rock/Rock with Soil cover
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Powari Pangi Nalla the road level
Soil slope with boulders subjected to erosion
[°] 45
2000
15-20
Debris type(soil/ boulders)
Soil and small sized rocks
NA
NA
Rock with NA
58
Soil and small sized rocks
Typical Cross-section
Distance between slope bottom and infrastructure Whether any erosion control measures to be provided on the face: Whether Toe protection measures are to be provided
Problem The portion of the slope below the road level
is facing the problem of toe erosion by the
high velocity waters of river Sutlej. The
velocity of the flowing water is around 4
m/s. Also the face of the slope is also being
subjected to erosion due to presence of
of loose soil.
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
section:
[m]
Whether any erosion control measures to Yes
No
protection measures Yes
No
Problem
portion of the slope below the road level
is facing the problem of toe erosion by the
high velocity waters of river Sutlej. The
velocity of the flowing water is around 4
m/s. Also the face of the slope is also being
subjected to erosion due to presence of lot
Proposed Solution Over the slope to take care of erosion,
Bio Mat is to be laid after the scaling of
the loose boulders and to avoid the
erosion of the slope toe due to river
water gabion wall can be constructed and
gabion mattress can be laid at the toe of
slope to prevent scouring action. The
height of the gabion wall from the river
bed should be more than the HFL of the
flowing river.
59
hensive CAT Plan of Satluj River Basin
Proposed Solution
Over the slope to take care of erosion,
is to be laid after the scaling of
the loose boulders and to avoid the
erosion of the slope toe due to river
wall can be constructed and
gabion mattress can be laid at the toe of
slope to prevent scouring action. The
height of the gabion wall from the river
bed should be more than the HFL of the
Comprehensive CAT Plan of Satluj River Basin
Notes:
8 m highGabion wall on bank of river Godavari, Nasik
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
8 m highGabion wall on bank of river Godavari, Nasik
60
Costing:
Location: Powari PangiStretch: 1, Soil slope with boulders subjected to erosionSolution: Erosion control Mat, bottom including 0.5 m thk Gabion mattress as apron protection; Assumed Avg. Ht. 20.0m, length 2000m; Total No. of Gabion walls : 1 No
S.No Description
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
2 Dressing of the soilobtain a levelled surface
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
5
Providing and laying of Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
7
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Location: Powari Pangi Stretch: 1, Soil slope with boulders subjected to erosion Solution: Erosion control Mat, Bio Mat on the failed slope and 5m High toe Gabion wall at bottom including 0.5 m thk Gabion mattress as apron protection; Assumed Avg. Ht. 20.0m, length 2000m; Total No. of Gabion walls : 1 No
Unit Qty
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, complete.
Cum 40000
Dressing of the soil-boulder slope to obtain a levelled surface
Sq.m 40000
Backfilling at select areas with the excavated material to the required level
inclination as per drawings Cum 12000
Providing and laying of Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at
4m c/c, neccessary laps etc
Cum 40000
Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
Sq.m 40000
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS LS
61
hensive CAT Plan of Satluj River Basin
on the failed slope and 5m High toe Gabion wall at bottom including 0.5 m thk Gabion mattress as apron protection; Assumed Avg. Ht.
Rate Amount (`)
40000 2700 108,000,000.00
40000 250 10,000,000.00
12000 400 4,800,000.00
40000 850 34,000,000.00
40000 -
31,360,000.00
188,160,000.00
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Rispa Stretch Details
General Information:
Type of surface Soil slope with
Average inclination
of rock slope w.r.t.
Horizontal
[°]
Total Length of the
stretch (L)
[m]
Total Sloping Height
(H)
[m]
Vegetation (if any) Yes
Approach to top
portion of Slope Yes / No
Distance Available at
the top of slope (for
Top anchoring)
[m]
Type of strata at Top
of Cutting slope
Soil/Rock/Rock with Soil cover
Distance between
slope bottom and
infrastructure
[m]
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Soil slope with boulders and heavy erosion
70
500 m
40 m
Debris type(soil/
boulders) Soil with boulders
Yes / No Yes
>3m
Soil/Rock/Rock with Soil
NA
62
with boulders
Typical Cross-section
Whether any erosion
control measures to
be provided on the
face:
Whether Toe
protection measures
are to be provided
Problem The major problem is of the instability of the
slopes and erosion of the soil on the slopes.
The slopes have failed making the slope
nearly vertical. Also at the toe of the slope, a
river is flowing which erodes the toe adding
to the instability of the slopes.
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
section:
Whether any erosion
control measures to Yes
protection measures Yes
Problem
The major problem is of the instability of the
slopes and erosion of the soil on the slopes.
The slopes have failed making the slope
nearly vertical. Also at the toe of the slope, a
which erodes the toe adding
to the instability of the slopes.
Proposed Solution Series of gabions
be constructed on the slope with
laid on the surface. At the b
slope gabion wall is to be constructed
along with gabion mattresses to avoid toe
erosion and scouring. Also, groynes are
to be constructed along the flow of river
to prevent erosion and increase siltation
on the banks.
63
hensive CAT Plan of Satluj River Basin
No
No
Proposed Solution
Series of gabions of 4 m are proposed to
be constructed on the slope with Bio Mat
laid on the surface. At the bottom of the
wall is to be constructed
along with gabion mattresses to avoid toe
erosion and scouring. Also, groynes are
to be constructed along the flow of river
to prevent erosion and increase siltation
Comprehensive CAT Plan of Satluj River Basin
Costing:
Location: Rispa Stretch: Soil slope with boulders and heavy erosionSolution: Erosion control Mat, Bio Mat5m Each for Toe protection and Slope retension including 0.5m thkapron protection; Assumed Avg. Ht. 40.0m, length 500m; Total No. of Gabion walls : 3 No's
S.No Description
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, for Gabion walls & groynes complete.
2 Dressing of the soil-boulder slope to obtain a levelled surface
3 Cutting of soil slope to required level and inclination as per drawing
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
5
Providing and laying of Bio MatReinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
7
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for apron protection, complete.
8
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Stretch: Soil slope with boulders and heavy erosion Bio Mat on the slope and Series of Gabion walls of height
5m Each for Toe protection and Slope retension including 0.5m thk Gabion mattress for apron protection; Assumed Avg. Ht. 40.0m, length 500m; Total No. of Gabion walls : 3
Unit Qty Rate Amount (
Providing and laying of mechanically woven double twisted hexagonal shaped
Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, for Gabion walls &
Cum 30000 2700 81,000,000.00
boulder slope to Sq.m 20000 250
5,000,000.00
Cutting of soil slope to required level
Cum 6000 400 2,400,000.00
Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 6000 250 1,500,000.00
Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at
4m c/c, neccessary laps etc
Sq.m 20000 850 17,000,000.00
Spreading of vegetative soil over the Erosion Control Blanket and planting of Sq.m 20000
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of equired sizes and quality etc for apron
Cum 1250 3200 4,000,000.00
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS 22,180,000.00
133,080,000.00
64
on the slope and Series of Gabion walls of height Gabion mattress for
apron protection; Assumed Avg. Ht. 40.0m, length 500m; Total No. of Gabion walls : 3
Amount (`)
81,000,000.00
5,000,000.00 2,400,000.00
1,500,000.00
17,000,000.00
4,000,000.00
22,180,000.00
133,080,000.00
Section 2:
Introduction
Site Details
Location Stretch Details
General Information
Type of surface
Average inclination of rock slope w.r.t. Horizontal Total length of the stretch (L) Total Sloping Height (H)
Vegetation (if any)
Approach to top portion of Slope Distance Available at the top of slope (for Top anchoring) Type of strata at Top of Cutting slope Distance between slope bottom and infrastructure
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Spillow
General Information:
Soil slope not protected by vegetation; and Toe erosion.
[°] 60
[m] 500
Sloping Height [m] 40
No Debris type(soil/ boulders)
Yes / No Yes
Distance Available at the top of slope (for [m] <0.5
Type of strata at Top Soil/Rock/Rock with Soil cover
Soil
[m] NA
65
hensive CAT Plan of Satluj River Basin
Soil slope not protected by vegetation; and Toe erosion.
Debris type(soil/ Soil with small rocks
Comprehensive CAT Plan of Satluj River Basin
Typical Cross-section:
Whether any erosion control measures to be provided on the face:
Yes
Whether Toe protection measures are to be provided
Yes
Problem The toe of the slope is being eroded by the
flowing river and also the slope is made of
soil which poses the problem of soil erosion
Also the flowing river is causing the problem
of siltation on one side of the river at the
meander.
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Yes
No
Yes
No
being eroded by the
flowing river and also the slope is made of
soil which poses the problem of soil erosion.
Also the flowing river is causing the problem
of siltation on one side of the river at the
Proposed Solution Series of gabions are constructed along
the sloe at intervals of 10 -15m. A gabion
toe wall of height 5 m is proposed along
the bottom of the slope to control toe
erosion and Bio Mat along with U
can be laid on the slope to prevent
erosion.
66
posed Solution
Series of gabions are constructed along
. A gabion
5 m is proposed along
the bottom of the slope to control toe
along with U-Pins
can be laid on the slope to prevent soil
Notes:
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
67
hensive CAT Plan of Satluj River Basin
Comprehensive CAT Plan of Satluj River Basin
Costing:
Location: Spillow Stretch: Soil slope not protected by vegetation; and Toe erosionSolution: Erosion control Mat, Bio Mat5m Each for Toe protection and Slope retension including 0.5m thk Gabion mattress for apron protection; Assumed Avg. Ht. 30.0m, length 500m; Total No. of Gabion walls : 2 No's
S.No Description
1
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, for Gabion walls complete.
2 Dressing of the soil-boulder slope to obtain a levelled surface
3 Cutting of soil slope to required level and inclination as per drawing
4 Backfilling at select areas with the excavated material to the required level and inclination as per drawings
5
Providing and laying of Bio MatReinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at every 3-4m c/c, neccessary laps etc
6 Spreading of vegetative soil over the Erosion Control Blanket and planting of local shrubs etc
7
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc for apron protection, complete.
8
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to the top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Stretch: Soil slope not protected by vegetation; and Toe erosion Bio Mat on the slope and Series of Gabion walls of height
5m Each for Toe protection and Slope retension including 0.5m thk Gabion mattress for apron protection; Assumed Avg. Ht. 30.0m, length 500m; Total No. of Gabion walls : 2
Unit Qty Rate Amount (
Providing and laying of mechanically woven double twisted hexagonal shaped
Coated Gabions of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of required sizes and quality etc, for Gabion walls
Cum 20000 2700 54,000,000.00
boulder slope to Sq.m 50000 250
12,500,000.00
Cutting of soil slope to required level
Cum 15000 400 6,000,000.00
Backfilling at select areas with the excavated material to the required level and inclination as per drawings
Cum 15000 250 3,750,000.00
Bio Mat Turf Reinforcement Mat made of an open three dimensional synthetic mat made of Polypropylene filaments with an additional Hexagonal shaped Double Twisted Wire Mesh of Mesh Type 10 x 12, Zn + PVC Coated 2.70/3.70 mm wire dia. including providing U Pins at
4m c/c, neccessary laps etc
Sq.m 50000 850 42,500,000.00
Spreading of vegetative soil over the Erosion Control Blanket and planting of Sq.m Sq.m
Providing and laying of mechanically woven double twisted hexagonal shaped Zn+PVC Coated Gabion mattress of 0.5m thickness and 5m length and of Mesh wire Dia. 2.7mm / 3.7mm and Mesh type 10x12 including lacing, tying and filling of Gabions with stones of equired sizes and quality etc for apron
Cum 1250 3200 4,000,000.00
Other miscellaneous civil works such as providing proper drains, toe collection system of loose rocks, access roads to
LS 24,550,000.00
147,300,000.00
68
on the slope and Series of Gabion walls of height 5m Each for Toe protection and Slope retension including 0.5m thk Gabion mattress for apron protection; Assumed Avg. Ht. 30.0m, length 500m; Total No. of Gabion walls : 2
Amount (`)
54,000,000.00
12,500,000.00 6,000,000.00
3,750,000.00
42,500,000.00
4,000,000.00
24,550,000.00
147,300,000.00
Section 2:
Introduction
Site Details
Location
Stretch Details
General Information
Type of surface
Average inclination
of rock slope w.r.t.
Horizontal
Total Length of the
stretch (L)
Total Sloping Height
(H)
Vegetation (if any)
Surface of rock
Approach to top portion of
Slope
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
Tikru slip
General Information:
Slope with several outcrops rock of heavy weathered rock
[°]
60
[m] 200
Sloping Height [m]
250
Yes Debris type(soil/
boulders)
Regular / Undulating / Bumpy / Overhanging
Approach to top portion of Yes / No Yes
69
River Basin
Slope with several outcrops rock of heavy weathered rock
Debris type(soil/
boulders) Boulders
Regular / Undulating / Bumpy / Overhanging
Comprehensive CAT Plan of Satluj
Typical Cross-section:
Distance Available at the top of
slope (for Top anchoring) [m]
Type of strata at Top of
Cutting slope
Soil/Rock/Rock
with Soil cover
Distance between slope
bottom and infrastructure [m]
Whether any erosion control
measures to be provided on
the face:
Yes
Whether Toe protection
measures are to be provided
Yes
Problem
The slope in this stretch
contains large amount of
boulders which are loosely held
to the surface. The bottom of
the slope has the problem of
toe erosion by high water
flows.
Rock fall
slope to reduce the energy of the falling rocks and a
rockfall barrier is proposed at intermediate position on
the slope
constructed at the bottom of the slope to
erosion and also to catch the falling boulders
prevent
mattress is also to be constructed at the toe to prevent
scouring due to river water.
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
[m] > 3
Soil/Rock/Rock
with Soil cover Rock with soil cover
[m] NA
No
No
Proposed Solution
Rock fall barrier is proposed at the higher position of
slope to reduce the energy of the falling rocks and a
rockfall barrier is proposed at intermediate position on
the slope .A gabion wall of height 5 m is to be
constructed at the bottom of the slope to prevent toe
erosion and also to catch the falling boulders thus
preventing them from falling into the river. A gabion
mattress is also to be constructed at the toe to prevent
scouring due to river water.
70
barrier is proposed at the higher position of
slope to reduce the energy of the falling rocks and a
rockfall barrier is proposed at intermediate position on
is to be
prevent toe
thus
A gabion
mattress is also to be constructed at the toe to prevent
Notes:
Also a catch pit behind the Gabion Walls
can be removed periodically
Costing:
Location: Tikru Slip
Stretch: Slope with several outcrops rock of heavy weathered rock
Solution: Passive system of Rock fall protection using Flexible High Energy Rockfall
Barriers at various intervals and Gabion wall at toe to catch the boulder in the trench.
Avg. Height of stretch: 150m; Assumed Avg. length of Stretch: 200.0m, No. of Barr
: 2 No's
S.No Description
1
Providing and laying of High Energy
Rock fall Barrier System having a
capacity of 3000 KiloJoules
comprising of Main Interception Nets
and additional Nets , Flexible posts,
detachable base plates adequately
galvanised, lateral bracing cables &
upslope cables in accordance with ETAG
027 with ground anchors as per design
and foundation anchor
with all accessories complete.
2 Removing of Loose Boulders
3
Providing and laying of Spot rock bolting
for a depth of 5
continuous threaded bar including
drilling and grouting
4
Providing and laying of mechanically
woven double twisted hexagonal shaped
Zn+PVC Coated Gabions of Mesh wire
Dia. 2.7mm / 3.7mm and Mesh type
10x12 including lacing, tying and filling
of Gabions with stones of required sizes
and quality etc, for Gabion wa
complete.
5
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to
the top etc.
TOTAL
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
catch pit behind the Gabion Walls can be constructed to collect the rocks which
can be removed periodically
Stretch: Slope with several outcrops rock of heavy weathered rock
Solution: Passive system of Rock fall protection using Flexible High Energy Rockfall
Barriers at various intervals and Gabion wall at toe to catch the boulder in the trench.
Avg. Height of stretch: 150m; Assumed Avg. length of Stretch: 200.0m, No. of Barr
Unit Qty
Providing and laying of High Energy
Rock fall Barrier System having a
capacity of 3000 KiloJoules, 6m height
comprising of Main Interception Nets
and additional Nets , Flexible posts,
detachable base plates adequately
galvanised, lateral bracing cables &
upslope cables in accordance with ETAG
027 with ground anchors as per design
and foundation anchors for posts and
with all accessories complete.
LM 400
Removing of Loose Boulders Cum 30
Providing and laying of Spot rock bolting
for a depth of 5-6m, with a 32mm dia
continuous threaded bar including
drilling and grouting
Nos 16
Providing and laying of mechanically
woven double twisted hexagonal shaped
Zn+PVC Coated Gabions of Mesh wire
Dia. 2.7mm / 3.7mm and Mesh type
10x12 including lacing, tying and filling
of Gabions with stones of required sizes
and quality etc, for Gabion walls
Cum 4000
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to LS
71
River Basin
can be constructed to collect the rocks which
Stretch: Slope with several outcrops rock of heavy weathered rock
Solution: Passive system of Rock fall protection using Flexible High Energy Rockfall
Barriers at various intervals and Gabion wall at toe to catch the boulder in the trench.
Avg. Height of stretch: 150m; Assumed Avg. length of Stretch: 200.0m, No. of Barriers
Rate Amount (INR)
300000
120,000,000.00
950
28,500.00
28800
460,800.00
2700
10,800,000.00
26,257,860.00
157,547,160.00
Comprehensive CAT Plan of Satluj River Basin
Section 2:
Introduction
Site Details
Location Tinku Nalla
Stretch Details
General Information:
Type of surface Nalla with debris
Average inclination of
rock slope w.r.t.
Horizontal
[°]
Total width of the
stretch (W) [m]
Total Sloping Height
(H) [m]
Vegetation (if any) No
Approach to top
portion of Slope Yes / No
Distance Available at
the top of slope (for
Top anchoring)
[m]
Type of strata at Top
of Cutting slope
Soil/Rock/Rock with
Soil cover
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
with debris flow
NA
5-10
NA
Debris type(soil/
boulders) Big Boulders
NA
NA
Rock with NA
72
Boulders
Typical Cross-section
Distance between
slope bottom and
infrastructure
Whether any erosion
control measures to
be provided on the
face:
Whether Toe
protection measures
are to be provided
Problem
The nalla here is of 5
carries rocks along with water and deposits
it onto the road below the nalla.
Volume: II Section: 1I Page No:
Comprehensive CAT Plan of Satluj River Basin
section:
[m] NA
Whether any erosion
control measures to Yes
No
protection measures Yes
No
Problem
The nalla here is of 5 – 10 m width and it
carries rocks along with water and deposits
it onto the road below the nalla.
Proposed Solution
To prevent the rocks from reaching the
road, two debris flow barriers ar
provided on the upstream of the nalla.
Also a culvert should be made at the
bottom of the road to allow for a free
passage of water downstream, thus the
problem of water flowing over the road
can be avoided.
73
hensive CAT Plan of Satluj River Basin
Proposed Solution
To prevent the rocks from reaching the
road, two debris flow barriers are to be
provided on the upstream of the nalla.
Also a culvert should be made at the
bottom of the road to allow for a free
passage of water downstream, thus the
problem of water flowing over the road
can be avoided.
Comprehensive CAT Plan of Satluj River Basin
Notes:
Costing:
Location: Tinku Nalla
Stretch : Nalla with debris flow
Solution: Passive system of Rock fall protection using Flexible High Energy Debris Flow
Barriers at various intervals. Assumed Avg. width of Stretch: 10.0m, No. of Barriers :
No's
S.No Description
1
Providing and laying of High Energy Debris
Flow Barrier System , 6m height
comprising of Main Interception Nets and
additional Nets , Flexible posts, detachable
base plates adequately galvanised,
bracing cables & upslope cables with
ground anchors as per design and
foundation anchors for posts and with all
accessories complete.
2 Removing of Loose Boulders
3
Providing and laying of Spot rock bolting
for a depth of 5-6m, with a 32mm dia
continuous threaded bar including drilling
and grouting
4
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to the
top etc.
TOTAL
Volume: II Section: 1I Page No:
hensive CAT Plan of Satluj River Basin
Solution: Passive system of Rock fall protection using Flexible High Energy Debris Flow
Barriers at various intervals. Assumed Avg. width of Stretch: 10.0m, No. of Barriers :
Unit Qty Rate Amount
(INR)
Providing and laying of High Energy Debris
Flow Barrier System , 6m height
comprising of Main Interception Nets and
additional Nets , Flexible posts, detachable
base plates adequately galvanised, lateral
bracing cables & upslope cables with
ground anchors as per design and
foundation anchors for posts and with all
LM 20 300000
6,000,000.00
Cum 30 950
28,500.00
Providing and laying of Spot rock bolting
6m, with a 32mm dia
continuous threaded bar including drilling Nos 16 28800
460,800.00
Other miscellaneous civil works such as
providing proper drains, toe collection
system of loose rocks, access roads to the LS
1,622,325.00
8,111,625.00
74
Solution: Passive system of Rock fall protection using Flexible High Energy Debris Flow
Barriers at various intervals. Assumed Avg. width of Stretch: 10.0m, No. of Barriers : 2
Amount
(INR)
6,000,000.00
28,500.00
460,800.00
1,622,325.00
8,111,625.00