+ All Categories
Home > Documents > Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a...

Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a...

Date post: 26-Sep-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
5
Volume 1: Issue 3 : To The End of The Line November 2015 Page 1 The long orange, yellow and gold fingers of Autumn have started to envelope the Dee Valley wherein at Corwen Central work has moved on a pace. Major developments have included the laying of a board crossing at the west end of the run round loop, clearance of a main drain by Welsh Water, the extension of the embankment, stability tests at Corwen East, and Corwen Central, an environmental award from the Campaign for the Protection of Rural Wales and the opening of a dedicated bank account for the Corwen Central Project Board Crossing At the close of last month a board crossing was installed to mark the point for the emergency evacuation route for the station via Green Lane. This would also allow wheel chair users a safe entrance and exit from the site. Main Drain After a somewhat delayed response from Welsh Water to come and clear the 300mm drain running under the formation towards the riverside treatment works a suitable vehicle arrived and cleared and flushed who knows what from the drain, allowing for a proper survey, discussions for which are still ongoing. The Embankment Daewoo 330 and dumper at work moving material from the Rhyl Spur Some heavy plant arrived on site at the beginning of the month in the shape of a
Transcript
Page 1: Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a preliminary to receiving and environmental award. The Corwen Central Project Team

Volume 1: Issue 3 : To The End of The Line November 2015

Page 1

The long orange, yellow and gold

fingers of Autumn have started to envelope the

Dee Valley wherein at Corwen Central work

has moved on a pace. Major developments have

included the laying of a board crossing at the

west end of the run round loop, clearance of a

main drain by Welsh Water, the extension of the

embankment, stability tests at Corwen East,

and Corwen Central, an environmental award

from the Campaign for the Protection of Rural

Wales and the opening of a dedicated bank

account for the Corwen Central Project

Board Crossing

At the close of last month a board crossing was

installed to mark the point for the emergency

evacuation route for the station via Green Lane.

This would also allow wheel chair users a safe

entrance and exit from the site.

Main Drain

After a somewhat delayed response from

Welsh Water to come and clear the 300mm

drain running under the formation towards the

riverside treatment works a suitable vehicle

arrived and cleared and flushed – who knows

what from the drain, allowing for a proper

survey, discussions for which are still ongoing.

The Embankment

Daewoo 330 and dumper at work moving material from

the Rhyl Spur

Some heavy plant arrived on site at the

beginning of the month in the shape of a

Page 2: Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a preliminary to receiving and environmental award. The Corwen Central Project Team

Volume 1: Issue 3 : To The End of The Line November 2015

Page 2

Daewoo 330 hydraulic excavator, a 10 ton

capacity Benford Dumper and road roller.They

were soon at work stripping back material from

the Rhyl spur and relocating it alongside the

treatment work’s fence in order to build up the

width of the station/run round area. The Rhyl

Spur has been relieved of about 3metres of its

western shoulder right down to ground level

and back to the “junction” with the Corwen

line. So far, this has resulted in the relocation of

about 6000 tons of material, for the new

embankment, which is being laid and

compacted in half metre layers.

Daewoo 330 “grading in”

Compaction Tests

The building of the embankment is not just a

matter of dumping lots of material and

ramming it down! The job requires some skill

and precision, after all the embankment will

have to carry the weight of trains and heavy

locomotives and not be seen to be slowly

slipping towards the river or sinking in the

middle, once it’s been asked to work for its

living! The photos show the work involved in

raising the embankment layer by layer, the

excavator grading in the piles of material and

carrying out some preliminary rolling and

compacting before the road roller completes the

job. The next part is to test the compaction –if a

downward pressure is applied to small areas on

the compacted site then to what extent does the

ground move or push outwards? The first tests

were carried out between the rails at Corwen

East. How did we get on?With the use of the

Excavator being made ready for jacking for the

pressure test

12ton Hydraulic Crane as a jacking item a

downward force of 5tonnes produced a 1.25mm

deflection after 4mins followed by another site

with a 7 tonnes force producing 1.25 mm

deflection in the same time.

Page 3: Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a preliminary to receiving and environmental award. The Corwen Central Project Team

Volume 1: Issue 3 : To The End of The Line November 2015

Page 3

The technicians from the testing company

“Celtest” declared the site “better than a

motorway, could even take a Jumbo Jet

landing!!!” – Praise indeed for our civil

engineers. On the new layering the 14 tonne

Daewoo excavator provided the jacking point

and better than satisfactory results were

recorded.

Campaign for the Protection of Rural Wales

(CPRW) award

RD-G and Dr.Jean Rosenfeld, Chairman CPRW

At the end of the last newsletter it was stated

that Corwen Central and Corwen East were

inspected by representatives of CPRW as a

preliminary to receiving and environmental

award. The Corwen Central Project Team were

informed in the last week of October that they

had been successful and a short ceremony to

mark the occasion took place at Corwen Central

on Saturday October 31st. The certificate and

plaque were presented to Richard Dixon-

Gough, the Corwen Central Project Manager by

Presentation Group : L-R Dr. Jean Rosenfeld, Chairman

CPRW, RD-G, Carys Matthews, Resources Officer

CPRW, Dr. Christine Evans, Chairman Clwyd Branch,

Tom & Kay Culhane , committee members, CPRW

Dr Jean Rosenfeld, National Chairman of

CPRW, supported by the nominating Clwyd

Branch Chairman Dr Christine Evans. Dr.

Rosenfeld said that CPRW were delighted to

make the award because the Corwen Central

Project was delivering sympathetic restoration

of an historic railway route, attracting visitors

to Corwen and encouraging business

development and stabilising employment in this

part of rural Wales. The presentation concluded

with a welcome round of Corwen Central Tea

and home made cakes courtesy of Dr. Evans

and John Mason.

New Bank Account

It has been a long held ambition of the Corwen

Central Project Team to be able to administer

its own funds for financing and managing the

Corwen Central Project. After seeking advice

Page 4: Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a preliminary to receiving and environmental award. The Corwen Central Project Team

Volume 1: Issue 3 : To The End of The Line November 2015

Page 4

from the Charities Commission as to the best

way to proceed it has been decided to operate a

separate account – named Corwen Central

Railway Development from within the

Llangollen Railway Trust. The CC’s view was

that a Trust with all the legal powers and

safeguards already existed at Llangollen and it

would be both sensible and effective to use

these facilities. Thus an independent bank

account has been established under the

umbrella of the LRT, but with signatory powers

resting exclusively with the Corwen Central

Project Management Team – Richard Dixon-

Gough, Phil Carson, John Mason and Paul

Bailey (Treasurer). Contributions to the

Projectcan be made payable to either the

Llangollen Railway Trust – marked CCRD or to

Corwen Central Railway Development and

forwarded to Mr Paul Bailey, Dolwen,

Bryneglwys, Corwen, Denbighshire LL21 9LY

Page 5: Volume 1: Issue 3 : To The End of The Line November 2015...inspected by representatives of CPRW as a preliminary to receiving and environmental award. The Corwen Central Project Team

Volume 1: Issue 3 : To The End of The Line November 2015

Page 5

Little and Large on the new embankment

Daewoo 330 and “Chicken 1”


Recommended