+ All Categories
Home > Documents > VOLVO INTERCHANGE - South Carolina Department … directional interchange ... (2) miles east of SC...

VOLVO INTERCHANGE - South Carolina Department … directional interchange ... (2) miles east of SC...

Date post: 07-May-2018
Category:
Upload: nguyenbao
View: 219 times
Download: 2 times
Share this document with a friend
1
PROJECT CONTACTS The SCDOT is constructing a new three-leg directional interchange along I-26 in Berkeley County, South Carolina. The interchange will provide access from I-26 to the new Volvo Car Drive which leads to Camp Hall Commerce Park and the Volvo facility. The new interchange will be located along I-26 at approximate mile marker 189 which is approximately two (2) miles east of SC 27/Ridgeville Road (exit 187) and approximately five (5) miles west of Jedburg Road (exit 194). The proposed interchange includes both at-grade and flyover ramps. VOLVO INTERCHANGE PROJECT UPDATE FEBRUARY 2018 Daniel Burton, PE SCDOT Resident Construction Engineer 843-688-6240 Mike Prudente Conti Project Manager 843-405-4352 PROJECT OVERVIEW Progress Update To Charleston To Columbia Volvo Car Drive Placement of geogrid on the south side of I-26. MSE wall construction on the south side of I-26. Ground improvements and pile driving complete on south side MSE wall and mass fill with geogrid started on south side I-26 median pile driving complete and concrete work began Erosion and sediment control continues on north side in preparation for ground improvements
Transcript

PROJECT CONTACTS

The SCDOT is constructing a new three-leg directional interchange along I-26 in Berkeley County, South Carolina. The interchange will provide access from I-26 to the new Volvo Car Drive which leads to Camp Hall Commerce Park and the Volvo facility. The new interchange will be located along I-26 at approximate mile marker 189 which is approximately two (2) miles east of SC 27/Ridgeville Road (exit 187) and approximately five (5) miles west of Jedburg Road (exit 194). The proposed interchange includes both at-grade and flyover ramps.

VOLVO INTERCHANGEP R O J E C T U P D A T E

FEBRUARY 2018

Daniel Burton, PESCDOT Resident Construction Engineer843-688-6240

Mike PrudenteConti Project Manager843-405-4352

PROJECT OVERVIEW

Progress Update

To Charleston

To Columbia

Volvo C

ar Driv

e

Placement of geogrid on the south side of I-26. MSE wall construction on the south side of I-26.

� Ground improvements and pile driving complete on south side

� MSE wall and mass fill with geogrid started on south side

� I-26 median pile driving complete and concrete work began

� Erosion and sediment control continues on north side in preparation for ground improvements

Recommended