VOWTAPProgress Report
VOWDADecember 2, 2015
DOE Grants VOWTAP Extension
• No Cost Time Extension until May 31, 2016
• Conditional upon achievement of two milestones– Issue request for proposals for the fabrication and construction
of VOWTAP and receive and formally evaluate bids. – Provide DOE a letter from Dominion’s Board or Authorized
Representative stating it will submit a Cost Recovery Rider to the State Corporation Commission no later than July 31, 2016
Major Construction Request For Proposals Issued
Transportation, Erection and Installation of the Inward Battered Guide Structure Foundations (IBGS) and Wind Turbine Generators (WTG) – 6 Bidders
Final Design, Manufacture, Transportation, Installation, Horizontal Directional Drilling and Termination of the Export and Inter-array Cables – 4 Bidders
• Engaged K2 to provide lessons learned and review scope of work for RFPs
• Issued November 17, 2015• Responses due January 15, 2016
Additional Pricing Activities Scheduled for Q1 2016
• Request for Proposals for smaller work scopes– Foundation fabrication– On shore interconnection station equipment and installation
• Updated estimates from project partners and industry contacts for remaining VOWTAP scope– Instrumentation– Commissioning– Project Management
• Final compiled estimate will be reviewed by a third party
Q4 2015
Develop and Issue major construction work RFPs
Engaged a recognized 3rd party offshore wind management company
Develop optimal scope of work packages
No later than May 1, 2016
Provide DOE with proof of milestone achievement
RFP results and final estimate
Dominion commitment letter regarding SCC submittal by July 31. 2016
Q1 2016
Issue small scope RFPs
Develop final estimate based on results of all RFPs
Analyze RFP results
Revise project estimates and risk profile
May 31, 2016
DOE supports funding for future budget periods
Confirm DOE funding commitment
Q2 2016
Dominion Governance Approvals to Proceed
Update stakeholders
Prepare filing
Achievable Schedule,Clearly Defined Milestones