Home > Documents > VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension...

VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension...

Date post: 17-Jan-2018
Category:
Upload: luke-rodgers
View: 217 times
Download: 0 times
Share this document with a friend
Description:
Major Construction Request For Proposals Issued Transportation, Erection and Installation of the Inward Battered Guide Structure Foundations (IBGS) and Wind Turbine Generators (WTG) – 6 Bidders Final Design, Manufacture, Transportation, Installation, Horizontal Directional Drilling and Termination of the Export and Inter-array Cables – 4 Bidders Engaged K2 to provide lessons learned and review scope of work for RFPs Issued November 17, 2015 Responses due January 15, 2016
6
VOWTAP Progress Report VOWDA December 2, 2015
Transcript
Page 1: VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

VOWTAPProgress Report

VOWDADecember 2, 2015

Page 2: VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

DOE Grants VOWTAP Extension

• No Cost Time Extension until May 31, 2016

• Conditional upon achievement of two milestones– Issue request for proposals for the fabrication and construction

of VOWTAP and receive and formally evaluate bids. – Provide DOE a letter from Dominion’s Board or Authorized

Representative stating it will submit a Cost Recovery Rider to the State Corporation Commission no later than July 31, 2016

Page 3: VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

Major Construction Request For Proposals Issued

Transportation, Erection and Installation of the Inward Battered Guide Structure Foundations (IBGS) and Wind Turbine Generators (WTG) – 6 Bidders

Final Design, Manufacture, Transportation, Installation, Horizontal Directional Drilling and Termination of the Export and Inter-array Cables – 4 Bidders

• Engaged K2 to provide lessons learned and review scope of work for RFPs

• Issued November 17, 2015• Responses due January 15, 2016

Page 4: VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

Additional Pricing Activities Scheduled for Q1 2016

• Request for Proposals for smaller work scopes– Foundation fabrication– On shore interconnection station equipment and installation

• Updated estimates from project partners and industry contacts for remaining VOWTAP scope– Instrumentation– Commissioning– Project Management

• Final compiled estimate will be reviewed by a third party

Page 5: VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

Q4 2015

Develop and Issue major construction work RFPs

Engaged a recognized 3rd party offshore wind management company

Develop optimal scope of work packages

No later than May 1, 2016

Provide DOE with proof of milestone achievement

RFP results and final estimate

Dominion commitment letter regarding SCC submittal by July 31. 2016

Q1 2016

Issue small scope RFPs

Develop final estimate based on results of all RFPs

Analyze RFP results

Revise project estimates and risk profile

May 31, 2016

DOE supports funding for future budget periods

Confirm DOE funding commitment

Q2 2016

Dominion Governance Approvals to Proceed

Update stakeholders

Prepare filing

Achievable Schedule,Clearly Defined Milestones

Page 6: VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

Questions