+ All Categories
Home > Documents > Waitsia Gas Project Commissioning and Operations ... · Commissioning and Operations Environment...

Waitsia Gas Project Commissioning and Operations ... · Commissioning and Operations Environment...

Date post: 30-Apr-2018
Category:
Upload: truongthu
View: 222 times
Download: 2 times
Share this document with a friend
18
Upstream Production Solutions Pty Ltd– ABN 26 166 665 952 Registered Office: 179 Great Eastern Highway Belmont, WA 6104 T: +61 3 8623 9800 This document is to be considered uncontrolled: When printed (unless formally issued as a ‘controlled copy’); and When saved electronically to an area outside of the IMS Waitsia Gas Project Commissioning and Operations Environment Plan Summary Upstream PS Controlled Document No. 21/HSEQ/ENV/PL06SUM Revision 2 Issue date: 11/07/2016 Waitsia Gas Project Commissioning and Operations Environment Plan Summary
Transcript

Upstream Production Solutions Pty Ltd– ABN 26 166 665 952 Registered Office: 179 Great Eastern Highway Belmont, WA 6104

T: +61 3 8623 9800

This document is to be considered uncontrolled: ‐ When printed (unless formally issued as a ‘controlled copy’); and ‐ When saved electronically to an area outside of the IMS

Waitsia Gas Project Commissioning and Operations

Environment Plan Summary

Upstream PS Controlled Document

No. 21/HSEQ/ENV/PL06SUM

Revision 2

Issue date: 11/07/2016

Waitsia Gas Project Commissioning and Operations Environment Plan Summary

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 2 of 18

1 Abbreviations Abbreviation Definition

ALARP As Low As Reasonably Practicable

APA APA Group

CBTA Competency Based Training Assessment

CPI Corrugated Plate Interceptor

DG Dangerous Goods

DGF Dongara Gas Field

EMS Environmental Management Standard

EP Environment Plan

EPCM Engineering, Procurement and Construction Management

ESA Environmentally Sensitive Area

GDE Groundwater Dependent Ecosystem

HPF Hovea Production Facility

HSEQ Health, Safety, Environment and Quality

HWSB Hovea Water Supply Bore

IMS Integrated Management System

LTS Low Temperature Separator

MMP Mercury Management Plan

MSS Management System Standards

OSCP Perth Basin Operations Oil Spill Contingency Plan

PFW Produced Formation Water

PL111 Waitsia Pipeline

PL64 Xyris Pipeline

PLC Programmable Logic Controller

PPE Personal Protective Equipment

SDS Safety Data Sheet

SOP Standard Operating Procedure

Waitsia Gas Project XPF and associated infrastructure (wells, flowlines, pipelines PL111 and PL64)

WIA Well Intervention Activity

XPF Xyris Production Facility

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 3 of 18

2 Contact Details Regulatory & Community Affairs Manager

AWE Limited

(08) 9480 1300

PO Box 574

WEST PERTH WA 6782

3 Location Waitsia Gas Project is within Production Licence L1, located in the northern Perth Basin on rural land located 340 km north of Perth and 16 km south east of Dongara (Figures 1 & 2). The key coordinates for the project are presented below.

Location Easting Northing

Xyris Production Facility (XPF) 314,715 mE 6,756,465 mN

Northern Hub 314,893 mE 6,762,386 mN

Senecio-03 Well 313,455 mE 6,762,447 mN

Waitsia-01 Well 316,398 mE 6,762,370 mN

4 Timeframe Waitsia Gas Project commissioning and operations activities are due to commence July 2016.

Waitsia Gas Project Commissioning and Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 4 of 18

Figure 1 Waitsia Gas Project Area

Source: Upstream Production Solutions 2016

Pye Road

XPF Access Track

Milo Road

Waitsia Gas Pipeline PL111

Waitsia-01 Flowline Senecio-03 Flowline

Xyris Pipeline PL64

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 5 of 18

5 Description of the Existing Environment A description of the environment in the Waitsia Gas Project area is included in Table 1. Figure 2 indicates sensitive receptors with respect to the Waitsia Gas Project.

Table 1 Description of the Environment

Aspect Detail

Climate Mediterranean climate characterised by seasonal patterns of hot, dry summers and mild, wet winters

Soils Sandy, well drained soils consisting of calcareous and siliceous sand underlain by aeolianite, which is often exposed

Surface water Irwin River (4 km north)

Ejarno Spring (500 m south of XPF)

Groundwater

Groundwater level is near, or at surface in the swamps and low lying areas, following the surface topography, but with lower relief

The nearest GDE is located 500 m southeast of the XPF along the margins of the Ejarno Spring.

Conservation Areas

Nearest Red Book area >10 km west

Yardanogo Nature Reserve >4 km south of XPF.

Nearest identified ESA is >4 km north

Vegetation

Area historically cleared

No ecological communities of national or state significance are known to occur within the area

Weeds (WoNS and declared weeds) are known to occur in the area

Fauna

Introduced fauna including stock and feral animals

Vegetated areas could provide habitat to 28 species of conservation significance

Operations will not impact on significant fauna habitat

Aboriginal Heritage Inspections have found that operations will not impact areas of cultural heritage significance

European Heritage Yardarino School Ruins 4 km north

Socio-economic

Irwin townsite 4 km north and town of Dongara 15km west

Land use within the surrounding region is agricultural, consisting of cropping, sheep and cattle farming

Dongara is the centre for a long standing oil and gas industry

Waitsia Gas Project Commissioning and Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 6 of 18

Figure 2 Sensitive receptors

Source: Upstream Production Solutions 2016

Waitsia Gas Project Commissioning and Operations

Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 7 of 18

6 Description of the Activity The scope of this EP is for the Waitsia Gas Project and includes the commissioning and operation of the following infrastructure:

Senecio-03 and Waitsia-01 Wells Senecio-03 and Waitsia-01 Flowlines Pipelines (PL111 and PL64) Northern Hub XPF Hovea Production Facility (HPF)

The commissioning of the Waitsia Gas Project will be undertaken by AWE and their contract operator Upstream PS with support from Enscope Engineering, Procurement and Construction Management (EPCM). Enscope EPCM will hand over the Waitsia Gas Project after commissioning to Upstream PS to operate.

All Waitsia Gas Project activities are within existing disturbance areas. Access is via Pye Road or Milo Road and existing access tracks (Figure 1).

6.1 Infrastructure

6.1.1 Well Head Compounds

The Senecio-03 and Waitsia-01 wellhead compounds are existing areas previously graded and prepared for drilling activities (Figure 1). The wellheads and bunded chemical injection facilities are within a fenced area with locked vehicle and personnel access gates. Above ground pipework connects the wellheads to the buried gas flowlines. Solar/battery power is utilised for controls and communication system, corrosion protection and lighting. Impressed current cathodic protection (CP) is maintained for production casing, wellheads and buried pipework. Chemicals injected onsite from bunded containers (<1000 L) include methanol, corrosion inhibitor and hydrogen sulphide (H2S) scavenger.

6.1.2 Flowlines

Buried carbon steel flowlines and an instrument airline connect Senecio-03 and Waitsia-01 to the Northern Hub. The flowlines were constructed in 2016 in accordance with AS2885 with a design life of 25 years. The flowlines are operated in accordance with AS2885. Line of site markers are field set and in accordance with AS2885 requirements. Impressed current CP is maintained on the flowlines. There are no pigging facilities on the flowlines.

6.1.3 Northern Hub

The Northern Hub (including bunded chemical injection facilities) is within a fenced area with locked vehicle and personnel access gates. The incoming fluid from each wellhead is combined before being passed into the buried PL111. Solar/battery power is utilised for controls and communication system and lighting. Impressed current CP is maintained for buried pipework. Chemicals injected onsite from bunded containers (<1000 L) include methanol, corrosion inhibitor and hydrogen sulphide (H2S) scavenger.

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 8 of 18

6.1.4 Waitsia Gas Pipeline

The Northern Hub is connected to the XPF via the buried carbon steel Waitsia Pipeline (PL111). The 6364 m pipeline was constructed in 2016 in accordance with AS2885 with a design life of 25 years. The pipeline is operated in accordance with AS2885. An instrument airline is installed to provide instrument air to the Northern Hub and Senecio-03 and Waitsia-01 well compounds. A pig launcher on a concrete bunded area is located at the Northern Hub and a pig receiver is provided upstream of the connection point to the XPF. Impressed current CP is maintained on the PL111.

6.1.5 XPF

The XPF is within a fenced area with locked vehicle and personnel access gates.

The facility is designed to produce up to 10mmscfd. The following equipment is operated at the XPF:

Slugcatcher - captures received liquids and controls slugs Closed unit absorbent bed (bunded) comprising:

Inlet filter coalesce / separator - removes liquid droplets Mercury guard bed - removes mercury Outlet particulate filter - removes any dust / particulates from gas stream

Liquid collection boot - removes bulk liquids from the well stream fluid (bunded) Gas/gas exchanger - pre-cools methanol treated gas prior to feed into the low

temperature separator (LTS) (bunded) LTS - conditions the methanol treated gas to export sales specifications by separating the

gas and liquid phases (bunded) Export coalescer and filter - removes liquid and dust from the export gas (bunded) Metering skid - provides metering, custody transfer and outlet flow control of ‘sales gas’

(bunded) Gas break out tank - receives site liquids under pressure from vessels on site and allows

evolved gas to vent (bunded) Liquid stock tank - receives liquids gravity fed from the gas break out tank with residence

time in tank allowing separation of water and condensate (bunded) Loading facility (bunded) comprising:

Bunded load-out bay Load-out pump (condensate / water) Load-in pump (methanol)

Gas engine alternator (GEA) - uses ‘sales gas’ for power generation at XPF including load-out pump, metering skid, air conditioning, site lighting and power for site buildings (bunded)

Diesel engine alternator (DEA) - provides back-up power generation (bunded) Instrument air system - consists of an electricity driven air compressor (bunded)

delivering compressed air to instruments at XPF, Northern Hub and Senecio-03 and Waitsia-01

Chemical management

Methanol injection - tank (bunded), pipework and pneumatic injection pumps (bunded) to deliver methanol into the gas stream to prevent hydrate formation

Corrosion inhibitor injection - container (bunded), pipework and pneumatic injection pumps (bunded)

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 9 of 18

Hydrogen Sulphide (H2S) Scavenger - container (bunded), pipework and pneumatic injection pumps (bunded)

Biocide - container (bunded), pipework and pneumatic injection pumps (bunded) Engine oil and coolant in GEA reservoirs Diesel, engine oil and coolant in DEA reservoirs

Shut down system - pneumatic loop system activated by:

Fusible loop ESD push-buttons Loss of instrument air Loss of power Remote initiated by APA or Control Panel Operator

Site drainage:

Process bunds drain to a low point with locked valve and connection for collection of contaminated liquids by vacuum trailer for transfer to the DPF Corrugated Plate Interceptor (CPI)

Loading bay drains to low point where a locked valve marked “Bund Drain Valve – To Be Kept Closed and Locked” allows contaminated liquids to drain into a holding tank for transfer to the DPF CPI

Tank bund designed to the requirement of AS1940 including capacity

Fire management equipment:

Fire extinguishers Fire hose reel for use during a tank / tank bund incident only by trained

professionals (DFES)

Laydown area comprising

Storage for unused or spare equipment Waste (with appropriate bunding)

Site office and associated amenities (eg, water tank supplied with town water, bottled drinking water, sewage)

6.1.6 Xyris Pipeline

The XPF is connected to the Parmelia Pipeline via the buried carbon steel Xyris Pipeline (PL64). The 400 m pipeline was constructed in 2004 in accordance with AS2885 with a design life of ~25 years. There are no pigging facilities on the pipeline.

A fenced compound at the connection to the Parmelia Pipeline contains an inlet tee, isolation valve, insulating gasket, vent valve, temperature transmitter and check valve. These facilities are managed by APA.

The pipeline was operated from 2004 to 2012 when it was placed into care and maintenance. Surveys undertaken in 2015 on the pipeline in preparation for recommissioning include:

ILI inspection - no significant issues

Pipeline hydro test - successful

Depth of cover survey - exceeds minimum requirements

Pipeline marker line of site survey (in accordance with AS2885)

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 10 of 18

Reintroduction of hydrocarbons is scheduled for during commissioning (Section 4.6). The pipeline is operated in accordance with AS2885.

6.1.7 HPF and DPF

The DPF is operated in accordance with the Dongara Gas Field Environment Plan [21/HSEQ/ENV/PL03] (DGF EP). The condensate from the XPF is taken to the DPF condensate loading bay and transferred into the DPF condensate storage tanks. This activity is managed under the DGF EP.

The HPF is under Care and Maintenance. Waitsia Gas Project operations will be conducted at the HPF in accordance with this EP.

Approximately 15 kL/week Produced Formation Water (PFW) from the XPF will be transferred to the existing lined HPF Evaporation Pond or the refurbished lined HPF ‘Turkey’s Nest’. The loading bay at both locations are bunded.

Chemicals for the Waitsia Gas Project are stored in the HPF Chemical Storage Shed.

Waste not stored at the XPF will be taken to the HPF or the DPF and stored on a hardstand area.

Where water is required for process or maintenance purposes (not usually required), water will be supplied from the licenced DPF Abstraction Bores or the licenced Hovea Water Supply Bore (HWSB) or town water supply.

6.2 Commissioning Details Commissioning of the Waitsia Gas Project includes the introduction of natural gas into the system (remote wells, flowlines, Northern Hub, PL111, XPF and PL64 into the Parmelia Pipeline).

Commissioning is estimated to take up to ten days and the activities include:

Venting ~700 m3 nitrogen gas (to zero pressure) into atmosphere before closing system (no hydrocarbon emissions, small slug of nitrogen will be exported with sales gas)

Wellhead control of the choke valve Methanol injection to control hydrates at the wellhead chokes Managing wellhead temperatures Managing flowline and pipeline temperatures and pressures Managing well flow rates Testing and confirming the correct operation and functioning of safety shutdown systems

under operational conditions Monitoring liquid levels at the slug catcher and liquids handling facility estimated Monitoring and controlling pressure and temperature at the LTS to achieve export quality

natural gas Methanol injection to control hydrates at the LTS Manning and monitoring the Programmable Logic Controller (PLC) at the DPF Control

Room with field operational support confirming correct field and PLC control responses Monitoring local control at the XPF Metering Facility Controlling flowrates at the XPF Metering Facility to achieve nominated delivery rates and

export quality natural gas

The DEA will be utilised during commissioning before switching to the GEA when stable process conditions have been achieved.

As gas is being introduced to the system during commissioning there will be some venting of gas (eg. breakout tank vent which vents under normal conditions and any process upsets).

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 11 of 18

Other activities that will be conducted for the first time at a time later than the commissioning period include:

Load-out condensate / PFW Load-in PFW at HPF

6.3 Operational Details Operational activities include:

Daily checks / field readings / work orders House keeping Maintenance (preservation of equipment) Repair activities under Engineering Management of Change (MOC) (restoration /(like-for-

like) replacement of above ground equipment) Chemical top-ups Chemical pump operation and maintenance Regular pigging Operation of drain points Bund management Venting (wellheads and plants) Load-in methanol Load-out and transport condensate / PFW Load-in PFW at HPF Monthly workplace inspections Monthly HSE meetings Closed unit absorbent bed loading and unloading (every three years) in accordance with

the Mercury Management Plan (MMP) [21/HSEQ/GEN/PL18] Waste management Weed management Maintenance of cleared areas (fire breaks, compounds, pipeline easements, access

tracks and laydown areas) Well tests Monitor evaporation pond level Inspection and reporting Groundwater monitoring at Senecio-03 and Waitsia-01 (annually) Auditing Reporting

6.4 Oil Spill Contingency Plan The preparedness planning and management of a spill associated with Waitsia Gas Project Commissioning and Operations is in accordance with the OSCP [21/HSEQ/GEN/PL02]. The OSCP defines how field and Perth office teams would respond to a hydrocarbon/chemical spill incident in a manner which minimises the impact on the environment. Spill sources applicable to Waitsia Gas Project commissioning and operations include:

Operational wells Above-ground pipework Buried flowlines Machinery/equipment Vehicles Storage Tanks

Waitsia Gas Project Commissioning and

Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 12 of 18

Transfer operations Chemicals in process or storage

One drill managed under the OSCP will be conducted annually.

6.5 Details of Chemicals and Other Substances No chemicals or other substances will be introduced into the Senecio-03 or Waitsia-01 well, reservoir or subsurface formation as part of Waitsia Gas Project Commissioning and Operations.

7 Environmental Impacts and Risks The environmental risks and management identified for the commissioning and operations activities ranked medium or above are presented in Table 2.

Waitsia Gas Project Commissioning and Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 13 of 18

Table 2 Risk Assessment Table

Risk identification Risk treatment

(Existing Safeguards / Management Methods)

Post treatment risk assessment

Aspect Source of Risk

Potential Environmental Impact

Consequence Likelihood Risk

Ranking

Fire Plant incident

Bush fire Loss of fauna,

habitat or personnel

Public third party damage

Loss of containment

Fire break maintained around facility

Weed management systems implemented

Designated smoking area

Upstream PS PTW in place for hot work activities

Perth Basin Operations Emergency Response Plan (ERP) includes evacuation, bushfire and process plant fire

Total Fire Bans

Operations comply with Harvest and Vehicle movement bans as implemented by Shire of Irwin

Fire extinguishers comply with relevant fire safety standards/hot work permit requirements

Vehicles and machinery parked in designated areas

Portable fire extinguishers as per ERP

Fire hose reel for tank / tank bund incident to be used by Fire Service personnel

Personnel training / induction / Emergency Response Competency Based Training Assessment (CBTA)

Monthly workplace inspections include checking fire breaks

Emergency Shutdown System

Emergency Drills conducted in accordance with ERP requirements (includes one fire drill per annum)

Impacted soil from foamed fire water will be removed immediately after a fire hazard has been controlled

Landowner liaison communicates with landowners during a fire event initiating on site or off site

MAJOR

(4)

VERY UNLIKELY

(B)

MEDIUM

(8)*

Direct impact from operations

Security Sabotage See loss of containment

Daily operational checks

Fenced compounds to deter access

SCADA (Supervisory Control And Data Acquisition) which allows personnel to view live process data would indicate any interference with process equipment

Signage where appropriate (eg. pipeline markers, authorised entry

SERIOUS

(3)

VERY UNLIKELY

(B)

MEDIUM

(6)

Waitsia Gas Project Commissioning and Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 14 of 18

Risk identification Risk treatment

(Existing Safeguards / Management Methods)

Post treatment risk assessment

Aspect Source of Risk

Potential Environmental Impact

Consequence Likelihood Risk

Ranking

only)Lighting around facility at night-time

Sensor cameras strategically placed at XPF; data downloaded by operations as per Preventative Maintenance Management Program Policy

Monthly Workplace inspections include security checks

Personnel present to supervise commissioning activities

Evaporation Pond / Turkey’s Nest load-in (HPF)

Condensate /

contaminant

carry-over

Incompatible

products in

pond (multiple

uses, e.g.

WIAs, existing

contaminants)

Extreme

weather event

Loss of

containment

and soil

contamination

Fauna

Human

exposure

Failure of

evaporation

pond wall

Single liner 2mm HDPE (Evaporation Pond) and 0.75mm Enviroliner (Turkey’s Nest) chemically resistant and suited to PFW containment.

Standard Operating Procedure(s) (SOP) for PFW load out management

Personnel training / induction / CBTA

Supervision of loading activities

PPE

Spill kits located in / adjacent to potential spill risk areas (kits fitted with tamper tags)

Sampling is conducted upstream (identifies level of contaminants)

Baseline soil samples were obtained prior to pond installation

Monthly workplace inspections to include checks on liner, water level, visual checks on condition of pond contents, checks for erosion and condition of pond wall

Pond maintained at or below 0.5 m allowing for a minimum 200% free board above this level

Visual level gauge for pond

Relined HPF Turkey’s Nest available as contingency pond

Fauna egress matting provided installed and its effectiveness maintained

Fencing of HPF to exclude large fauna

Fencing around HPF

ERP

Emergency drills conducted in accordance with ERP requirements (includes at least one spill drill per annum)

SERIOUS

(3)

UNLIKELY

(C)

MEDIUM

(9)

Unplanned event

Major loss of

containment

(eg. well

Fire Hazard

Greenhouse

gas emissions

Fusible loops

Emergency Shutdown (ESD)

Remote monitoring capability

SEVERE

(5)

EXTREMELY UNLIKELY

(A)

MEDIUM

(5)

Waitsia Gas Project Commissioning and Operations Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 15 of 18

Risk identification Risk treatment

(Existing Safeguards / Management Methods)

Post treatment risk assessment

Aspect Source of Risk

Potential Environmental Impact

Consequence Likelihood Risk

Ranking

integrity

failure,

pipeline /

flowline

rupture,

process

failure)

Spills and soil

contamination

Well casing designed to maintain well integrity

ERP includes unplanned gas release and process plant fire / explosion

OSCP and spill response equipment available on site

Pipe and vessel design

Bunded vessels/tanks to provide secondary containment

Cathodic protection system: wells, flowlines and pipelines (underground)

Waitsia Gas Project Commissioning and Operations

Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 16 of 18

8 Implementation Strategy The objective of the implementation strategy below is to describe how all aspects of the activity will be directed, reviewed and managed to ensure that all potential impacts and risks are continuously reduced to as low as reasonably practicable (ALARP):

(1) Ensure that the agreed environmental performance objectives and standards are met (2) Identify specific systems, practices and procedures to be used to ensure that

environmental risks and effects are reduced to ALARP (3) Establish a commitment to the protection of the environment (4) Establish a clear chain of command that sets out the roles and responsibilities of

Personnel in relation to the implementation, management and review of the EP (5) Ensure that each Employee or Contractor working on, or in connection with Waitsia Gas

Project Commissioning and Operations has the appropriate skills and training (6) Monitor, audit and review environmental performance and the Implementation Strategy (7) Maintain quantitative records (8) Develop and implement emergency and spill preparedness planning and response

capability (9) Report on environmental performance (10) Provide for appropriate consultation with relevant government authorities and other

interested persons or organisations

Details of AWE and Upstream PS’s systems, practices and procedures relating to the management of all potential impacts and risks of the activity are included in Table 3. The objective of these systems, practices and procedures is to continuously reduce the potential impacts and risks of the activity to ALARP.

Table 3 AWE and Upstream PS Systems, Practices and Procedures

Item Objective to achieve ALARP Location

Code of Practice for AWE & Upstream PS sites

To outline the main HSE criteria to be observed by AWE & Upstream PS

AWE Limited Health Safety & Environment Policy [AWE-HSE-POL-001]

Upstream PS Environmental Policy [00/SP/CPL/PO05(Env)]

Environment Plan To document environmental management of operations

Waitsia Gas Project Commissioning and Operations EP [21/HSEQ/ENV/PL06]

Oil Spill Preparedness and Response

To provide guidance on the management of a spill

OSCP [21/HSEQ/GEN/PL02]

Emergency Response

To provide guidance on the management of an emergency situation

ERP [21/HSEQ/GEN/PL01

Environmental Compliance Scheduling

To prompt environmental compliance requirements (reporting, auditing, licence renewal, document update)

Environmental Compliance Schedule [21/HSEQ/GEN/PL14]

HSE Management System Standards

To provide a framework comprising a set of performance standards, expectations and guidelines for effective management of aspects and impacts of operations

MSS [00/SP/CPL/PO03]

Waitsia Gas Project Commissioning and Operations

Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 17 of 18

Item Objective to achieve ALARP Location

Environmental Management Standard

To outline the organisational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing, and maintaining the environmental policy

Corporate EMS [00/HSEQ/ENV/PL01]

Preventative Maintenance Management

To provide a preventative maintenance management tool that stores records, schedules maintenance and documents activities undertaken

Preventative Maintenance Management Program

Standard Operating Procedures

To guide personnel on how to conduct tasks to meet environmental performance throughout operations

Upstream PS IMS

Permit to Work System

To ensure facilities are in a safe and environmentally acceptable condition before works starts and is kept in this condition until all personnel involved in the work have signed off completion

Upstream PS IMS

DPF Control Room

Training Management

To provide the framework for all personnel to have the competency for their respective roles for the management of safety and environmentally critical risks and daily work activities

Training Management Plan [00/BA/HR/PC54]

Audit Management

To plan and document the independent examination and verification of activities, records, processes, and other elements to determine conformity to documented requirements and standards

Audit Management – Quality Procedure [00/HSEQ/QA/PC01]

Clearing Vegetation Recording

To guide and document the conditions, approval and details of clearing activities to ensure compliance with clearing permits and legislation

Clearing Vegetation Record Form [21/HSEQ/ENV/PC04/FM01]

Landowner Communications

To guide all personnel working at AWE owned assets on interactions with landowners (including tenants and staff)

Landowner Communication Procedure [HSE-PR-059]

Environmental Reporting Documentation

To document details of activities and data required for environmental reporting purposes

Monthly Environmental Report [21/HSEQ/ENV/PL02/FM01]

Mercury Management

To provide guidance on the management of activities to be undertaken in a safe and environmentally responsible manner

Mercury Management Plan [21/HSEQ/GEN/PL18]

Waitsia Gas Project Commissioning and Operations

Environment Plan Summary

21/HSEQ/ENV/PL06SUM - Revision 2 Page 18 of 18

Item Objective to achieve ALARP Location

Sampling Surveillance Program

Outline groundwater and surface water monitoring program with guidance for compliance with WGP EP commitments

Waitsia Gas Project Surveillance Sampling Program [HSE-E-105]

Hazard and Incident Reporting

To outline the processes and requirements for hazard and incident reporting at Upstream PS sites

Hazard and Incident Reporting Procedure [00/HSEQ/GEN/PC23]

9 Consultation AWE has engaged with stakeholders since the planning phase for the drilling of the Senecio-03 and Waitsia-01 wells through to pipeline construction and XPF refurbishment planning. During this time stakeholders AWE has consulted with include:

Local Traditional Owner representatives Adjacent landowners and tenants APA Group – Parmelia Pipeline and Mondarra Gas Storage Facility Department of Environment Regulation Department of Fire and Emergency Services Department of Mines and Petroleum Department of Water Department of Health Local business owners and service providers Shire of Irwin Mid West Development Commission Mid West Chamber of Commerce Joint Venture Partner

AWE will continue to engage the above and additional stakeholders during the commissioning and operations phase of the project.

AWE also has a website specifically covering its Perth Basin activities (www.awemidwest.com.au). The website includes project specific pages as well as blogs highlighting updates and responding to particular topics of interest to our stakeholders. It also includes an option to subscribe to news feeds.


Recommended