+ All Categories
Home > Documents > Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec...

Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec...

Date post: 04-Jan-2016
Category:
Upload: geraldine-allen
View: 212 times
Download: 0 times
Share this document with a friend
Popular Tags:
30
" The M DG ’s are still achievable if we actnow.This w illrequire inclusive sound governance , increased public investm ent , econom ic grow th, enhanced productive capacity ,and the creation ofdecentw ork ." United Nations S ecretary General Ban-K i Moon.
Transcript
Page 1: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

"The MDG’s are still achievable if we act now. This will require inclusive sound governance, increased public investment, economic growth, enhanced productive capacity, and the

creation of decent work."

United Nations Secretary General Ban-Ki Moon.

Page 2: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Water and sanitation Project: Katanga ProjectDevelopment of draft Zero Project Scope

(12 -20 Dec 2008)

High-level resolutions taken at the Steering Committee meting for the Katanga Watsan Project (28th Nov 08) and operational actions taken at meeting of 2nd Dec 08):Res 1: that political buy-in by both parties is critical and the process be coordinated by DWAF as (water/sanitatoin)) sector leader with relevant institutions (DBSA, DFA, GP&LG and NEPAD BF)Res 2: that a Scope of Work outline be concluded by Mvd MerweB (APP), DNel (Hatch) and Lmuwila & ASubasuka (DBSA) and finalised after input by JRocha (NBF), RvTonder (SAACE) and WChunett (Turntown).

Time frames:•Zero Project Scope – 12 Dec 08 (completed)•Solicit inputs – 20 Dec (underway)•Incorporate input – 9 Jan (underway)•Circulate Draft Scope for comments (20 Jan)•Present draft Scope (early Febr)•Visit DRC multi-discpl team (mid Febr)•Present and recommend NBF cross sect- meeting (end Febr)•Adoption and define next steps (March 09)

Page 3: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Background and conceptually, it is important that any planning be informed by the following:

• RSA assumed the Chair of SADC during the SADC Summit from 17-18 Aug 08• Prior to this event, RSA Government Cabinet Lekgotla endorsed a strategy for RSA tenure as SADC Chair

containing several priorities for RSAs role in the region• The NEPAD Pre-summit Conference on Corridor Projects held in Sandton 8 Aug 08• The Corridor that is targeted in this ‘Project Scope’ has been prioritised at the Sandton Head of States

meeting• The need to identify priority corridors in which support from DTI could be leveraged• The DWAF Minister is requesting 3 projects to be implemented during her term (Katanga project strong

candidate, meet all requirements)• The need to leverage the competency and experience of DTI, DBSA, private sector and key role players in

the implementation of the project• The need to execute project within the existence of bilateral agreements on provincial (Gauteng/Katanga),

national (RSA/DRC) and Inter-state (Corridor)• That Council and Ministerial Decision on infrastructure development relating to specific countries (eg. DRC,

Angola and Madagascar) continue to guide the prioritisation of some of the projects to be pursued at national level

• The process must also focus on ‘quick wins’ where early harvest could be achieved, based on circumstances on the ground and not in compromising long-term sustainability.

Page 4: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

The outline project scope includes the following key areas and serves to:(i) solicit input from the project members; and (ii) build into a comprehensive

Scope of Work

• Slide 5: The service delivery model for Katanga watsan project (as pilot 1), but pilot 2, 3... also to apply. This model considers compliance, performance monitoring, ROI and sustainability

• Slide 6-7: Learning from the RSA experience - the importance of SWAP approach and PDSUnit – as linked to development in identified corridor

• Slide 8: Recipient of support is REGIDISO in Katanga (main but not only beneifiary)• Slide 9: Economic imperatives and constraints (important to identify upfront)• Slide 10-11: Opportunity map and strategic imperatives • Slide 12-13: Mapping out process that will ensure engagement of all stakeholders• Slide 14-15: Deployment of structures in project workflow model• Slide 16-21: PDSU strategic objectives and framework – towards setting up a central

Project Delivery Support Unit, to expand as other project join the ‘programme’• Slide 22-26: Scoping outline (implementation, establishment, roll out)• Slide 27: What , who, when, ....• Slide 28: Deliverables & Closing• Slide 90-30: Check and balances as comparing project scope against AfDB and AU

requirements

Page 5: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

WATER

SECURITY

New alternatives to provide a component of

the service delivery function

Economic Impact e.g. licensing,

pricing, industry, recycling, etc.

Resource Management

Service Delivery Management

Water Utilization Model

Infrastructure delivery

O&M Dimension

Institutional Dimension

Formalise appropriate allocation of roles &

responsibilities ROI & Sustainability

Performance ManagementCompliance

Deon Nel©

Page 6: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

SWAP

Agreed process for

harmonizationof systems

Government-Led process of

DonorCoordination

SystematicMechanism forConsultation of

beneficiaries

Clear & agreedSector policyAnd strategy

CommonPerformanceMonitoring/reporting

Sector MTEF(all local and

ExternalResources)

What is SWAP ?Sector Wide Approach.... an approach and mechanism that has worked well in infrastructure development in RSA, and resulted in meeting MDG targets ahead of target...

Page 7: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Conceptualising SWAP and PDSU – the RSA experience shows

the importance of :

Co-Ordination of funds

+(Bankable) Projects that consider TECHNICAL,

INSTITUTIONAL, FINANCIAL & ECONOMIC elements across the sector

=Sustainable water services

• PDSUs, aligned with NEPAD development corridors, and applying SWAP

will support countries in developing such bankable projects that will allow the

flow of donor funds – and the gearing of these donor funds – to deliver

sustainable water services towards AND BEYOND the achievement of MDG

target 7c

SWAP

Page 8: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

DRAFT SCOPING DOCUMENT

Katanga Water & Sanitation Pilot Project

Page 9: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

• Adequate supply of water & sanitation within the Katanga Province

• Satisfy growing demand from Mining & Industrial Sectors

• Institutional (capacity)

• Financial (budgets/revenue)

• Technical (infrastructure/O&M)

EXECUTIVE SUMMARY

ECONOMIC IMPERATIVES CONSTRAINTS

Page 10: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

GENERIC OPPORTUNITY MAP

Strategic Imperatives

Page 11: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Adequate supply of W&S to Katanga ProvinceEconomic Imperative 1

Economic Imperative 2

Satisfy growing demand for water from mining &

industrial sectors

Public Sector

Delivery Model

REGIDISO

Domestic Customers

Poor payment culture

Public Entities

Huge arrears

Industrial Customers

Most profitable

The

Economy

Page 12: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Mapping out the project workflow that will engage all stakeholders

Page 13: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Engagement Model

1. Political Agenda, goals and objectives confirmed2. Political Agreements aligned3. Political Stakeholder’s matrix prepared4. Project Scoping Objectives agreed5. Collation of project information6. Draft Scoping Document Prepared

1. Scope presentation to NBF Steercom2. Steercom to proceed with procurement 3. Procurement process agreed4. Engagement with Katanga Counterparts5. Commence with short term interventions (IMPLEMENTATION PHASE)6. Develop ToR for PDSU (ESTABLISHMENT PHASE)7. Project Development (PROJECT ROLL-OUT PHASE)

Page 14: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Adopting and deploying available structures to the project workflow model

Page 15: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

PDU Partnership Model

Maximise overlap and coordination between main structures/countries

PDSU

SSA/SADC

NEPAD

DWAF

CBO

PDU

Maximise overlap and coordination between major stakeholders

Page 16: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

STRATEGIC OBJECTIVE OF THE PDSUStrengthen regional & continental partnerships across the entire water

sector stakeholder spectrum focussing on:Private sector involvement

Mobilising resources & partnershipsDevelop strategic partnerships

Have an oversight role with sector initiatives, best practices, civil society & training.

Strategic fundamentals must underpin the UN MDG report

Page 17: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

The PDSU’s Strategic Framework:

1. Develop strategy with strategic enablers.2. It has to be a multi-pronged approach.3. Multi-pronged approach must create [development]

opportunities. For the creation of opportunities, there is a strong need for financing, donor partnerships, and strong governance.

3 must translate into infrastructure upgrades.4 must translate into economic growth.5 must translate into hunger alleviation.6 must translate into poverty alleviation.7 must translate into MDG’s.

Page 18: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Regional Model

AFRICA AGENDA

INFRASTRUCTURE

MDG’s POVERTYALLEVIATION

ECONOMIC PROGRESS

WATERSANITATION

Page 19: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

PDSU Business Model

ACCELERATE MDG’s

INDEPENDENCE

LEADERSHIPMULTI-

DISCIPLINARYINSTITUTIONAL

CAPACITY

PARTNERSHIPSPROJ ECT LINKAGES

VALUE ADD

Page 20: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

MDG Delivery Model

TARGETS

DIAGNOSTIC TOOLS

FUNDING GOVERNANCE MEASUREMENT

OWNERSHIPACCOUNTABILITY

Page 21: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

PDSU

Main driver

Project 1

MOU

Delivery Channels &

Support

Sector Representatives

Political Mandate

Political Mandate

Project 3Project 2

Project Sponsors

Regional Focus on

Delivery

Page 22: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

DRAFT SCOPING OUTLINEIMPLEMENTATION PHASE

• Element A1 – CAPACITY BUILDING (institutional framework) – ZAR 2.0m– Commercial audit (costs, revenue, profitability)– Commercial Gap analysis– Organisational audit (strategy, structure, skills, governance, stakeholders)– Organisational Gap analysis– Development of skills matrix– Develop training template– Optimise structure– Redefine strategy– Develop Performance Measurement template

Page 23: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

DRAFT SCOPING OUTLINE IMPLEMENTATION PHASE

• Element A2 – EQUIPMENT SUPPLY (technical) – ZAR 2.0m– Water & Sanitation asset audit– Define procurement schedule – Build asset register– Training needs and requirements fed through to element A1– Develop performance measurement criteria

• Element A3 – O&M NEEDS ASSESSMENT (service delivery) – ZAR 1.5m– Operational audit– Operational Gap analysis– Water & Sanitation Quality compliance audit– Quality Gap analysis– Training needs and requirements fed through to element A1– Develop performance measurement criteria

– Expert skills necessary for A1-A3• legal, financial, organisational, CRM, business processes, change management

Page 24: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

DRAFT SCOPING OUTLINE ESTABLISHMENT PHASE

• Element B1 – ESTABLISHMENT OF PDSU (technical) – ZAR 12.0m

– Refine ToR from base concept– Develop strategic role– Outline operational parameters– Equip with operational tool set (to make MDG delivery happen)– Political empowerment (direct report)– Change management programme– Performance measurement framework (balanced scorecard)– Prepare resource recruitment plan

– Expert skills necessary for B1• Sector specialisation, business process and workflow, project management, quality

assurance, environmental sustainability, regulatory, political acumen

Page 25: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

DRAFT SCOPING OUTLINE PROJECT ROLL-OUT PHASE

• Element C1 – WATER (project development) – ZAR 6.0m

– Build PDSU platform and interaction with stakeholders– Create WSDP’s (linked to MDG targets)– Define and prioritise projects– Prepare project tenders– Engage in procurement process(es)– Manage the delivery process– Progress reporting

• Element C2 – HOUSING (service delivery) – ZAR TBDm

– Match with economic growth plans– Determine housing roll-out plan

– Expert skills necessary for C1-C2• Skills set identifies for PDSU, with an emphasis on project management

Page 26: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Implementation & Benchmarking – R 6m, 4months ( Tasks: A1-A3)

02/2009-06/2009

Establishment of PDSU

-R 12m, 12months (Task B1)

Project Development & Implementation

-R 6m, 9months (Tasks C1-C2)

04/2009-03/2010

06/2009-03/2010

& beyond

Page 27: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

WHAT WHO WHEN GUIDELINES/BENCHMARKS DELIVERABLE

A1 02/09-06/09 Water Security model, NBF project opportunity map –

Appendix 2

Link to opportunity map and current challenges – Appendix 1

A2 02/09-06/09

A3 02/09-06/09

B1 04/09-03/2010

PDSU framework document & operational brief

Functional regional unit with political

support

C1 06/09-03/2010

Apply the HATCH FEL 2,3 project life cycle process Pilot project

Next level projectC2 06/09-

03/2010

Page 28: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

The End

Project Deliverables:

• Capacity building – leadership, technical, social• Supply equipment• O&M of equipment (new and existing – asset mngt)• Water/effluent quality testing and laboratory set up• Housing and recreational development (additional, aligned)• PDSUnit ‘centre of excellence’ (to grow & expand)• Lesson learning, capture and publish• Framework for other infrastructure projects (eg roads, energy, etc)

Page 29: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

Checking against:Checking against:

AfDB identified key considerations in implementing water and sanitation:AfDB identified key considerations in implementing water and sanitation:

Push higher up the political agenda;

Develop sound policies & strategies;

Prepare sustainable action & investment plans;

Put local authorities in the driving seat;

Build sector capacity with a focus on local players;

Develop sustainable financing strategies;

Initiate partnerships with the private sector;

Encourage innovation, cooperation and R&D;

Monitor progress and evaluate impact.

Page 30: Water and sanitation Project: Katanga Project Development of draft Zero Project Scope (12 -20 Dec 2008) High-level resolutions taken at the Steering Committee.

1. Develop &/or update national water management policies, regulatory frameworks, & programmes, & prepare national strategies & action plans for achieving the MDG targets for water & sanitation (W&S) over the next 7 years

2. mobilize increased donor & other financing for the W&S initiatives including national projects & rural W&S initiatives, the African Water Facility, Water for African Cities programme & the NEPAD Infrastructure Project Preparation Facility, as committed in the G8 initiatives on W&S

3. strengthen AMCOW as a key regional mechanism, & other regional stakeholders, as relevant, for promoting cooperation on W&S

Checking AgainstChecking Against

AU Declaration CommitmentsAU Declaration Commitments


Recommended