WATER CYCLE AND WASTE MANAGEMENT
LONGWARRY SALEYARDS
PREPARED FOR:
LONGWARRY SALEYARDS PTY LTD
JULY 2020
PAGE i 220035_WCWM_REO_003F.DOCX
Report Title: Water Cycle and Waste Management
Project: Longwarry Saleyards
Client: Longwarry Saleyards Pty Ltd
Report Ref.: 220035_WCWM_REO_003F.docx
Status: Final
Issued: 7 July 2020
Premise Australia Pty Ltd (Premise) and the authors responsible for the preparation and compilation of
this report declare that we do not have, nor expect to have a beneficial interest in the study area of this
project and will not benefit from any of the recommendations outlined in this report.
The preparation of this report has been in accordance with the project brief provided by the client and
has relied upon the information, data and results provided or collected from the sources and under the
conditions outlined in the report.
All maps, plans, and cadastral information contained within this report are prepared for the exclusive
use of Longwarry Saleyards Pty Ltd to accompany this report for the land described herein and are not
to be used for any other purpose or by any other person or entity. No reliance should be placed on the
information contained in this report for any purposes apart from those stated therein.
Premise accepts no responsibility for any loss, damage suffered or inconveniences arising from, any
person or entity using the plans or information in this study for purposes other than those stated above.
Version Revision
Date Details
Authorised
Name/Position Signature
003A 11/11/19 Draft for client review M Haege/Premise
003B 18/11/19 Final for Planning report M Haege/Premise
003C 19/12/19 Final for Approval M Haege/Premise
003D 05/05/20 Final for Approval M Haege/Premise
003E 29/06/20 SBR system, final M Haege/Premise
003F 07/07/20 Final – minor updates M Haege/Premise
PAGE ii 220035_WCWM_REO_003F.DOCX
TABLE OF CONTENTS
1. INTRODUCTION ..................................................................................................... 1
1.1 BACKGROUND ..................................................................................................................................................... 1 1.2 SCOPE OF THIS REPORT ................................................................................................................................... 2
2. WATER CYCLE ...................................................................................................... 2
2.1 FACILITY DESCRIPTION ..................................................................................................................................... 2
2.1.1 LOCATION .......................................................................................................................................... 2 2.1.2 OPERATIONS ..................................................................................................................................... 2 2.1.3 INFRASTRUCTURE ........................................................................................................................... 3
2.2 WATER DEMAND ASSUMPTIONS ................................................................................................................ 5
2.2.1 DOMESTIC WATER .......................................................................................................................... 5 2.2.2 LIVESTOCK .......................................................................................................................................... 5 2.2.3 TRUCK WASH .................................................................................................................................... 5 2.2.4 DUST SUPPRESSION ....................................................................................................................... 6 2.2.5 WASH DOWN ................................................................................................................................... 6 2.2.6 TROUGH WASH................................................................................................................................ 6
2.3 WATER SUPPLY .................................................................................................................................................... 7 2.4 WASTEWATER GENERATION .......................................................................................................................... 7
2.4.1 SOURCES ............................................................................................................................................. 7 2.4.2 DOMESTIC .......................................................................................................................................... 7 2.4.3 TRUCK WASH .................................................................................................................................... 7 2.4.4 TROUGH WASH................................................................................................................................ 8 2.4.5 WASH DOWN ................................................................................................................................... 8
2.5 WATER CYCLE ASSESSMENT .......................................................................................................................... 8
2.5.1 WATER CYCLE MODEL ................................................................................................................... 8 2.5.2 CLIMATE DATA ................................................................................................................................. 8 2.5.3 MODEL BREAKDOWN.................................................................................................................... 9 2.5.4 WATER CYCLE RESULTS ................................................................................................................ 9
3. SURFACE WATER MANAGEMENT .................................................................... 13
3.1 MANAGEMENT PHILOSOPHY ...................................................................................................................... 13
3.1.1 SETTING AND CATCHMENT DEFINITION ............................................................................ 13 3.1.2 SURFACE WATER MOVEMENT PATHWAYS ........................................................................ 16 3.1.3 EXISTING SURFACE WATER QUALITY .................................................................................... 17
3.2 ASSESSMENT METHODOLOGY ................................................................................................................... 17
3.2.1 STORMWATER QUANTITY ......................................................................................................... 17 3.2.2 STORMWATER QUALITY ............................................................................................................. 17
3.3 CONSTRUCTED WETLAND/DETENTION BASIN .................................................................................... 19 3.4 SURFACE WATER MODELLING RESULTS ................................................................................................. 19
3.4.1 PEAK FLOW ...................................................................................................................................... 19 3.4.2 QUALITY ............................................................................................................................................ 22 3.4.3 SITE YIELD ......................................................................................................................................... 22
3.5 SURFACE WATER MANAGEMENT CONCLUSIONS .............................................................................. 22
PAGE iii 220035_WCWM_REO_003F.DOCX
4. LIQUID WASTE MANAGEMENT ......................................................................... 23
4.1 EFFLUENT SOURCES ......................................................................................................................................... 23 4.2 EFFLUENT MANAGEMENT SYSTEM ........................................................................................................... 23
4.2.1 EFFLUENT QUANTITY ................................................................................................................... 23 4.2.2 DESCRIPTION .................................................................................................................................. 23 4.2.3 SBR ...................................................................................................................................................... 24 4.2.4 EFFLUENT QUALITY ...................................................................................................................... 25 4.2.5 COMMISSIONING ......................................................................................................................... 25
5. DOMESTIC EFFLUENT MANAGEMENT ............................................................. 26
5.1 INTRODUCTION ................................................................................................................................................. 26 5.2 PRIMARY TREATMENT .................................................................................................................................... 26 5.3 SECONDARY TREATMENT ............................................................................................................................. 26
6. SOLID WASTE MANAGEMENT .......................................................................... 26
6.1 INTRODUCTION ................................................................................................................................................. 26 6.2 SOURCES AND ESTIMATED QUANTITIES ................................................................................................ 27
6.2.1 TRUCK WASH .................................................................................................................................. 27 6.2.2 GENERAL REFUSE .......................................................................................................................... 27 6.2.3 STOCK MORTALITIES ................................................................................................................... 27 6.2.4 SPENT SOFT FLOOR...................................................................................................................... 27 6.2.5 SBR SLUDGE .................................................................................................................................... 27
6.3 SOLID WASTE STOCKPILES ........................................................................................................................... 28 6.4 SOLID WASTE MANAGEMENT ..................................................................................................................... 28
7. SYSTEM MANAGEMENT ..................................................................................... 29
7.1 EFFLUENT TREATMENT SYSTEM ................................................................................................................. 29
7.1.1 EFFLUENT QUALITY TARGETS ................................................................................................... 29 7.1.2 COMMISSIONING PERIOD ........................................................................................................ 29 7.1.3 COMMISSIONING PLAN ............................................................................................................. 30 7.1.4 ONGOING MONITORING........................................................................................................... 31 7.1.5 EFFLUENT SYSTEM INSPECTION ............................................................................................. 32
7.2 SURFACE WATER SYSTEM ............................................................................................................................. 32
7.2.1 COMMISSIONING PERIOD ........................................................................................................ 32 7.2.2 SURFACE WATER QUALITY MONITORING .......................................................................... 32
8. CONCLUSION ...................................................................................................... 33
9. REFERENCES ...................................................................................................... 34
APPENDICES
APPENDIX A Flood Assessment
TABLES
Table 2.1 – Livestock sales ......................................................................................................................................................... 2 Table 2.2 - Water demand and supply ................................................................................................................................ 7 Table 2.3 – Annual rainfall statistics ....................................................................................................................................... 9
PAGE iv 220035_WCWM_REO_003F.DOCX
Table 2.4 – Annual rainfall statistics ..................................................................................................................................... 11 Table 3.1 – Surface water catchments ................................................................................................................................. 16 Table 3.2 - Pollutant concentrations used in MUSIC modelling ............................................................................. 18 Table 3.3 – MUSIC catchment areas .................................................................................................................................... 18 Table 3.4 – TUFLOW modelling results ............................................................................................................................... 20 Table 3.5 – MUSIC Modelling Results ................................................................................................................................. 22 Table 7.1 – Summary of commissioning plan and actions ......................................................................................... 30
FIGURES
Figure 1: Proposed Longwarry Saleyards site layout ............................................................................................... 4 Figure 2: Longwarry Saleyards water cycle schematic – average annual volume in ML/year ............... 10 Figure 3: Catchment Setting ............................................................................................................................................ 14 Figure 4: Existing surface water movement ............................................................................................................... 15 Figure 5: Culvert locations ................................................................................................................................................ 20 Figure 6: 1% AEP Surface Level Impacts ..................................................................................................................... 21 Figure 7: 10% AEP Surface Level Impacts ................................................................................................................... 21
PAGE v 220035_WCWM_REO_003F.DOCX
ABBREVIATIONS
BOD Biochemical oxygen demand
kL Kilolitre (1,000 L)
L Litre
m2 Square metre
m3 Cubic metre (1 kL)
ML Megalitre (1 million litres)
NH3 Ammonia
TN Total nitrogen
TP Total phosphorus
TSS Total suspended solids
PAGE 1 220035_WCWM_REO_003F.DOCX
1. INTRODUCTION
1.1 BACKGROUND
Longwarry Saleyards Pty Ltd proposes to construct a new saleyard in Longwarry. The site, which would
be accessed from Sand Road between Thornell Road and the Princes Highway, comprises approximately
22.8 hectares of existing farmland.
The saleyard, known as the Longwarry Saleyards, would accommodate an annual throughput of up to
132,000 cattle (including 12,000 bobby calves). The facility would host an average of 146 sales per annum
including one fat cattle sale per week (total of 50 per annum), one cows & calves sale per week (total of
50 per annum), one store cattle sale per fortnight (24 per annum) and one dairy cattle sale per fortnight
(total of 22 per annum plus special sales as required by market conditions). The cattle sales would be
highly seasonal with larger sales occurring over the summer months, particularly in January.
The Longwarry Saleyards would comprise:
• A fully roofed saleyard with holding pens, sale pens, drafting and loading/unloading facilities;
• A central office building with offices, amenities and a café;
• Parking for trucks and cars;
• A three-bay truck wash and associated water storage tank;
• A maintenance shed and feed store;
• A surface water wetland/detention basin;
• Two rainwater tanks;
• A sequencing batch reactor (SBR) system to treat wastewater;
• Landscaping; and
• A sign.
Water for the facility would be provided through a combination of roof water harvesting, recycling and
connection to reticulated water supply. All liquid waste would be discharged offsite to sewer and an
integrated surface water management system would be used to effectively manage surface water. Solid
wastes would be temporarily stockpiled before being removed offsite.
This report presents an overview and assessment of the water cycle and waste management systems for
the proposed facility.
PAGE 2 220035_WCWM_REO_003F.DOCX
1.2 SCOPE OF THIS REPORT
This report presents:
• An assessment of the total water cycle at the facility including analysis of demand and supply;
• Details and assessment of the surface water management system; and
• Details and assessment of the liquid and solid waste management system.
2. WATER CYCLE
2.1 FACILITY DESCRIPTION
2.1.1 LOCATION
The site is located at 85 Thornell Road Longwarry, Victoria and can be accessed from Sand Road between
Thornell Road and Princes Highway. The site comprises approximately 22.8 hectares of existing farmland.
2.1.2 OPERATIONS
Annual throughput is expected to be up to 132,000 cattle. The facility would host an average of 146
sales per annum including one fat cattle sale per week (total of 50 per annum), one cows & calves sale
per week (total of 50 per annum), one store cattle sale per fortnight (24 per annum) and two dairy cattle
sales per fortnight (total of 22 per annum plus special sales as required by market conditions). The cattle
sales would be highly seasonal with larger sales occurring over the summer months.
The anticipated monthly sale breakdown and average sale numbers used for the water cycle modelling
are defined in Table 2.1.
Table 2.1 – Livestock sales
Month Proportion Head Average Sale Size
January 13.40% 17,688 1769
February 11.50% 15,180 1265
March 8.30% 10,956 913
April 6.10% 8,052 671
May 5.20% 6,864 490
June 4.30% 5,676 437
July 3.70% 4,884 407
August 4.10% 5,412 361
September 9.00% 11,880 990
October 11.50% 15,180 1084
November 11.20% 14,784 1232
December 11.70% 15,444 1931
Total 100% 132,000 904
PAGE 3 220035_WCWM_REO_003F.DOCX
2.1.3 INFRASTRUCTURE
Layout of the facility is shown on Figure 1. Details of infrastructure relevant to the water cycle are as
follows:
• Cattle pavilion roof area of 17,853 m2.
• The proposed central amenities building and landscaping occupies an area of 2,814 m2 with a roof area of 1,300 m2.
• The transport operator’s amenities, workshop and hay shed occupies an area of 364 m2.
• The paved area consisting of the trafficable areas and car park is approximately 33,343 m2 (sealed paved area of 30,693 m2 and unsealed paved area of 2,650 m2).
• The truck wash and solids stockpile pad cover areas of 1,540 m2 (roof area of 582 m2) and 1,035 m2 respectively;
• The effluent management system covers an area of 459 m2.
• The surface water wetland/detention basin occupies approximately 6,000 m2.
• The catchment area of the surface water wetland/detention basin is approximately 32,538 m2.
PAGE 4 220035_WCWM_REO_003F.DOCX
Figure 1: Proposed Longwarry Saleyards site layout
PAGE 5 220035_WCWM_REO_003F.DOCX
2.2 WATER DEMAND ASSUMPTIONS
The facility requires water to function. Assumptions relating to use and demand are outlined below.
2.2.1 DOMESTIC WATER
2.2.1.1 Staff, Agents and Patrons
• 4 full time staff present 6 days a week; each allocated 50 L/p/d.
• On sale days staff would increase by 18 (inclusive of 4 café); each allocated 25 L/p/d.
• On sale day and day before, 30 agent representatives would be present; each allocated 25 L/p/d.
• 150 patrons per store sale, each allocated 10 L/p/sale (being 6 L flush, 1 L hand wash and 3 L at the café).
• 30 patrons per cattle and calves sale, each allocated 10 L/p/sale (being 6 L flush, 1 L hand wash and 3 L at the café).
2.2.1.2 Transport Operator’s Amenities
• 20 transport operators would use the amenities block each sale day (have a shower etc and visit the café); each use is allocated 150 L/p.
2.2.1.3 Domestic Demand
The average annual domestic water demand derived using the above assumptions is 1.1 ML/year.
This demand would be split between the central amenities building and the transport operator’s
amenities.
2.2.2 LIVESTOCK
• Cattle drinking water allowance of 25 L/head/day.
• 50% stock numbers on day prior to sale, 100% stock numbers on day of sale and 5% stock numbers on day following sale.
2.2.3 TRUCK WASH
The anticipated average monthly sales distribution is shown in Table 2.1. These average sale numbers
were used to define the number of trucks coming in and leaving the facility using the following
assumptions:
• The breakdown of truck types bringing cattle into the facility is 28% B-double, 20% semi-trailers and 52% rigid trucks (same vehicle breakdown as the traffic assessment);
• The breakdown of truck types taking cattle from the facility is 28% B-double, 17% semi-trailers and 55% rigid trucks (same vehicle breakdown as the traffic assessment);
• The capacity of each truck type is:
– B-double 95 head
– Semi-trailer 65 head
– Rigid 15 head
PAGE 6 220035_WCWM_REO_003F.DOCX
• Every B-double, 80% of semi-trailers and 50% of rigid trucks delivering stock would use the truck wash;
• Washing time would be 70 minutes for B-doubles, 60 minutes for semi-trailers and 40 minutes for rigid trucks;
• The proposed truck wash at the facility would use hoses with a flow rate of approximately 1.6 L/s; and
• Two B-doubles and one semi-trailer would use the truck wash on non-sale days.
The above data therefore results in the following water consumption per truck wash:
• B-doubles 6.72 kL per wash
• Semi-trailers 5.76 kL per wash
• Rigid trucks 3.84 kL per wash
The average annual truck wash water consumption from this analysis is approximately 17.47 ML/year.
2.2.4 DUST SUPPRESSION
The water cycle modelling assumes that dust suppression watering of the entire soft floor area would
take place prior to each sale. This is conservative as it is likely that dust suppression watering would not
be required in the cooler months. Dust suppression would be distributed through sprinklers and/or hand
watering. The dust suppression system would allow coverage of the entire cattle yard soft floor area.
Assuming an application of 3 mm over the area under the cattle roof, the potential total water used each
time is 52.2 kL. The modelling assumed 50% of this volume would be used on dairy cow sale days.
It is unlikely dust suppression would be required at the solids stockpile area due to the moisture
contained in the solids. However, water connection points would be available at this location so that
stockpiles could be watered if required. No water allowance is made for this activity as it is unlikely to
be required.
2.2.5 WASH DOWN
The scales, drafting yards, calf yards and dairy would be cleaned weekly or after each sale. This activity
would be undertaken using hoses with a flow rate of 2.7 L/s and would take 1 hour per area
(approximately 10 kL per wash down area).
2.2.6 TROUGH WASH
Stock water troughs would be cleaned every fortnight to remove a build-up of dust. This would use
approximately 45 kL each time.
PAGE 7 220035_WCWM_REO_003F.DOCX
2.3 WATER SUPPLY
The principle of the water supply arrangement is to minimise demand on existing supplies through roof
and surface water harvesting. Table 2.2 summarises the various water demands, their main water source
and top-up supply.
Table 2.2 - Water demand and supply
Demand Main Supply Secondary Supply Top-up Supply
Stock water Roof water tank NA Reticulated potable
Domestic – toilets Roof water tank NA Reticulated potable
Domestic – potable Reticulated potable NA NA
Truck wash Truck Wash Roof Water Surface Water Wetland Reticulated potable
Dust suppression Roof water tank NA Reticulated potable
Scale wash down Roof water tank NA Reticulated potable
Water trough cleaning Roof water tank NA Reticulated potable
All water from the rainwater tanks would be filtered prior to reuse across the site and all water reused
from the surface water wetland would be filtered and disinfected prior to use at the truck wash.
2.4 WASTEWATER GENERATION
2.4.1 SOURCES
Liquid wastewater would be generated from domestic amenities, the truck wash, trough washing, wash
down and rainfall runoff from the solids stockpile area and uncovered sections of the truck wash area.
2.4.2 DOMESTIC
Domestic effluent generated from the central amenities building and transport operator’s amenities
would be managed using on-site effluent management systems for primary treatment (septic tanks) with
the treated effluent then further treated through the facility’s effluent treatment system before being
discharged offsite to sewer.
2.4.3 TRUCK WASH
Analysis of the expected truck wash number presented in Section 2.2.3 indicates an average annual
truck wash water demand of approximately 17.47 ML/year.
The main wash bays of the truck wash would have a roof which would collect runoff to be stored in and
reused from the truck wash tank. This roof collects approximately 0.42 ML/year of water, which would
contribute to the demand of the truck wash.
The runoff from the uncovered sections of the truck wash area would be collected at the base of the
sloped truck wash slab and discharge to the solids separation system. Outflow from the solids separation
system would be pumped to the SBR system.
Some water would be removed in the separated solids and some water used in the truck wash would be
removed as residual water on the truck. These losses are estimated as 2% of the water consumption
which equates to 0.35 ML/year.
PAGE 8 220035_WCWM_REO_003F.DOCX
Therefore, the truck wash wastewater volume used for the design and assessment of the wastewater
treatment system and reuse scheme is estimated to be approximately 17.12 ML/year.
2.4.4 TROUGH WASH
Stock water troughs would be cleaned fortnight to remove a build-up of dust. During warmer months,
the trough water would be discharged onto the soft floor system; it would therefore not add to the
liquid wastewater stream. In winter months, and if conditions required at other times, trough wash water
would be collected by a tanker and discharged at the solids separation system.
Cleaning the troughs has an annual water demand of 1.1 ML/year, which is conservatively assumed to
all flow to the wastewater treatment system.
2.4.5 WASH DOWN
Wash down water from scales, drafting yards, calf yards and dairy would be piped to the solids
separation system.
2.5 WATER CYCLE ASSESSMENT
2.5.1 WATER CYCLE MODEL
A daily water balance model was used to assess the overall water cycle for the proposed development
and site. The model is used to:
• estimate the average annual demand for each water system at the facility;
• optimise sizing of various storages;
• assess the ability of the proposed water supply sources to meet demand; and
• assess capacity and storage requirements for the effluent management system.
2.5.2 CLIMATE DATA
The model uses 130 years of daily SILO rainfall and evaporation data for the site (1 January 1889 to 31
December 2018). The SILO data interpolates rainfall and evaporation values from surrounding climate
stations to provide a long-term data set for the specific location.
Rainfall statistics derived from the SILO data are compared to available data for three stations
surrounding the site in Table 2.3.
The long-term average annual and median annual rainfall data from the SILO dataset is higher than the
Longwarry data but lower than the Drouin West data. The SILO data provides a reasonable
representation of climate for the area.
PAGE 9 220035_WCWM_REO_003F.DOCX
Table 2.3 – Annual rainfall statistics
Station BOM
Number Years of Data
Mean Rainfall
mm
Median Rainfall
mm
SILO Na 130
(1889-2018)
948.6 938.2
Longwarry 085209 62
(1907-1969)
907.9 873.2
Longwarry (Gooneparoo) 085208 47
(1969-2016)
896.5 887.6
Drouin West 085024 60
(1902-1962)
1000.4 975.5
2.5.3 MODEL BREAKDOWN
The water cycle is broken down into its various components and the inflows and outflows are modelled
as follows.
2.5.3.1 Storage Inflows
• Rainwater tanks – receive runoff from the roof of the livestock exchange facility and receive top up water from the reticulated potable supply;
• Truck wash tank – receives runoff from the roof of the truck wash and top up water from the surface water wetland and the reticulated potable supply;
• SBR – receives wastewater from the truck wash, trough wash and wash down. This system also collects runoff from solids stockpile area and the uncovered area of the truck wash;
• Constructed surface water wetland/detention basin – catches surface water runoff from the site (hardstand and trafficable areas; and balance of the open areas) and treats the water before
discharging off-site; and
• The open storages receive direct rainfall input.
2.5.3.2 Storage Outflows
• Rainwater tanks – water for dust suppression, the cleaning out of troughs, wash down and livestock drinking water and spill flows to the surface water wetland;
• Truck wash tank – water for the truck wash with spill flowing to the surface water wetland; • SBR – treated water is disposed into the South Easter Water sewerage; • Constructed surface water wetland/detention basin – excess water spills to existing drainage; and • Evaporation from open water storages.
2.5.4 WATER CYCLE RESULTS
The water cycle results are shown on Figure 2. The total modelled average annual water demand for the
facility is approximately 34.5 ML/year. Water would be supplied through a combination of harvested
roof, treated runoff from the constructed surface water wetland and reticulated potable supply. On-site
supply makes up about 27.8 ML/year which is approximately 81% of the annual demand. A summary of
the key water cycle components is provided in Table 2.4.
PAGE 10 220035_WCWM_REO_003F.DOCX
Figure 2: Longwarry Saleyards water cycle schematic – average annual volume in ML/year
6.68
Truck Wash Saleyards 0.38 0.55
Roof Runoff Potable Roof Runoff Potable
Area = 582 m2 Top-up Area = 1.79 ha Top-up
0.68 1.52 26.67 12.60 4.24 0.10 0.08
2.49 4.28
15.53 0.72
SpillCentral Amenities Building Driver Amentities
13.63
Spill 16.11
5 kL septic tank 5 kL septic tank
Truck Wash
StockWater
Dust Suppression
Wash Down
TroughWash
17.47 5.68 7.41 1.75 1.08
1.10
1.29
Truck wash and solids stockpile 17.94 Solids 19.02 20.1Area 2010 m2 Stockpile
System
Area = 3.25 ha
Reticulated Potable Supply
Catchment runoff
Sewer
2 ML Rainwater Tanks4 ML Wetland200 kL Truck Wash Tank
Packaged SBR Treatment System
PAGE 11 220035_WCWM_REO_003F.DOCX
Table 2.4 – Summary of Longwarry Saleyards water cycle components
Component Purpose Receives inflow
from Outflow goes to
Sizing and preliminary design details
Size
Lining Pond
surface
area
m2
Pond
freeboard
m
Rainwater tanks To provide capture and reuse of roof
water to reduce the potable water
demand.
• Cattle yard roof • Potable water top-
up (or a balance
tanks may be used)
• Stock drinking water • Dust suppression • Wash down • Trough wash • Amenities buildings • Evaporation
2 x 1 ML Na Na Na
Truck wash tank To provide a storage from which
water can be taken from for the truck
wash to increase reuse of water
onsite.
• Surface water wetland
• Truck wash roof • Top up from
potable water
supply
• Truck wash 200 kL Na Na Na
Surface water
wetland/Detention
Basin
To manage site runoff to achieve
zero adverse impact as measured by
site discharge (peak flow) and
surface water quality.
• Hardstand trafficable areas
• General site areas
• Truck wash tank • Off-site discharge • Evaporation
Total ~ 4 ML 0.3 m clay
with 200 mm
planting layer
in
macrophyte
areas
Total ~ 5,000 0.5 above
spillway
CFB tank Rainwater harvest for non-potable
use.
• CFB roof • Potable water top-
up
• CFB toilets 20 kL Na Na Na
Solids removal
system
Mechanical separation of solids from
the effluent stream. System typically
comprises a collection sump (in-
ground) with agitator and pump
which pumps effluent over a wedge
wire screen.
• Truck wash • Wash down of
receival areas and
scales
• Trough wash down • Surface runoff from
the truck wash pad
and solids stockpile
area
• SBR treatment system
Subject to
detailed design,
but nominally
around 30 kL
Collection
sump is
typically
concrete and
areas
surrounding
the screen are
typically
concrete
Na Na
PAGE 12 220035_WCWM_REO_003F.DOCX
Component Purpose Receives inflow
from Outflow goes to
Sizing and preliminary design details
Size
Lining Pond
surface
area
m2
Pond
freeboard
m
SBR treatment
system
Secondary treatment system to
reduce solids, nutrients and organic
load prior to discharge to sewer. A
system to treat an average daily flow
rate of 55 kL/day and maximum of
175 kL/day is proposed subject to
detailed design.
• Solids separation system
• Domestic septic tanks
• Sewerage 50kL inflow balance tank
13 m diameter
SBR tank
50kL treated
water balance
tank
PVC liners
would be
used in both
the selector
and SBR tanks
Na Na
Septic tanks Treatment of domestic effluent from
the central amenities building and
transport operator’s amenities.
• Amenities • SBR treatment system
2 x 5 kL Typically
concrete
Na Na
Potable supply Domestic demand and top-up
supply
• Reticulated supply Na Na Na Na Na
PAGE 13 220035_WCWM_REO_003F.DOCX
3. SURFACE WATER MANAGEMENT
3.1 MANAGEMENT PHILOSOPHY
The surface water management philosophy is to:
• Direct upslope runoff around the site or use existing topography to divide catchments.
• Define catchments and treat runoff according to the level of potential contamination present.
• Capture all general site runoff in a system of grass swales.
• Harvest roof water and minimise the interaction of surface water with stock wastes.
• Treat the balance of surface flows emanating from site runoff through a grass swale and constructed surface water wetland/detention basin system prior to discharge.
• Limit peak discharge from the developed areas of the site to pre-development levels using surcharge storage in the wetland/detention basin system.
• Limit post development runoff volume to around pre-development levels by reusing water from the wetland/detention basin system.
• Ensure that the surface water management system does not divert or harvest stormwater from beyond the site that would normally not pass through the site.
• Ensure that no stormwater leaves the site without appropriate treatment.
3.1.1 SETTING AND CATCHMENT DEFINITION
The catchment generally falls in a south-westerly direction and discharges via two constructed drainage
lines situated to the south and west of the site. The southern drainage line moves water through four
box culverts under Thornell Road. The site in its local catchment setting is shown on Figure 3.
PAGE 14 220035_WCWM_REO_003F.DOCX
Figure 3: Catchment Setting
Existing surface water movement occurs as overland flow and within constructed drains as illustrated on
Figure 4. The site is relatively flat and shallow channels have been cut to improve drainage.
There are two discharge points of the existing site – the eastern half of the site discharges to the south
through the box culverts (refer to Figure 4) where runoff currently discharges to the constructed
drainage channel. The western side of the site discharges to the west into a constructed drainage channel
which slopes to the south.
Overland flow from the north of the site is carried west by the drainage channel to the north of the site
and then flows south through the drainage channel to the west of the site.
Drainage channels
Site discharge point
PAGE 15 220035_WCWM_REO_003F.DOCX
Figure 4: Existing surface water movement
The proposed development would be located in four catchments that currently discharge to the south-
west. This would include all the built infrastructure (buildings and hardstand) for the facility.
The surface water management system would separate the development into two catchments types and
manage runoff according to the level of potential contamination present. The two catchment types are:
clean water and minor contaminants. Structures, drains, diversion banks/bunds and ground shaping
would be used to define and separate the catchments.
Existing drainage lines are located to the north, west and south of the site as shown on Figure 4. The
drainage line to the north would divert runoff from the northern catchments prior to reaching the site.
Table 3.1 provides a summary of the two catchment types, the pollutants likely to be present and the
fate of the surface water emanating from each catchment type.
All wastewater would be managed in a closed effluent management system (refer to Section 4). Transfer
of effluent would be managed with pumps, pipelines and storage tanks.
Drainage channels
Site discharge point
PAGE 16 220035_WCWM_REO_003F.DOCX
Table 3.1 – Surface water catchments
Catchment
type
Elements of the Proposed
Development Contained
with the Catchment
Likely Pollutants Fate of Catchment Runoff
Clean • Saleyard roof • Roof of central amenities
building
• Truck wash and workshop roofs
• Suspended solids • Metals • Minor microbial content
from birds and dust
Roof water from the saleyard
would be collected in the main
rainwater tank and used as the
principal supply of water for the
stock drinking, wash down,
trough wash and dust
suppression.
Roof water from the central
amenities building would be
diverted to the surface water
wetland.
Roof water from the truck wash
would be stored in the truck wash
tank and be used as a minor
source for the truck wash.
Minor
Contaminants
• Car/truck parking areas • Trafficable areas/roadways • Central amenities building • Grassed areas • Landscaped areas
• Suspended solids • Minor nutrients and salts
from stock wastes that may
discharge from heavy
vehicles
• Minor microbial content • Very minor oil and grease,
hydrocarbons and metals
from trafficable areas
• Minor nutrients from paddock runoff
All runoff from the central
catchment would be directed to
the surface water wetland system
for treatment prior to reuse or
discharge offsite.
A significant proportion of the water generated from the clean catchment (roofs) would be used in the
development. Any spill from the rainwater tanks would be collected and treated in the surface water
wetland system before discharging off-site.
Runoff from the balance of the development area that may contain minor contaminants would be similar
to urban/agricultural land runoff. The major pollutants identified for this catchment are suspended
solids, nutrients and microbial content. There is the potential for very minor oil and grease, hydrocarbon
and metal loads from trafficable areas. Therefore, an integrated surface water management system
comprising of grass swales and a constructed surface water wetland system is proposed to manage
pollutants from this catchment prior to discharge.
3.1.2 SURFACE WATER MOVEMENT PATHWAYS
Spill from the rainwater tanks would be collected and treated in the surface water wetland system before
discharging offsite.
Therefore, the only potential pathway for water to move from the central developed site is limited to the
outlet of the constructed surface water wetland. The location of the discharge point is shown by culvert
number 3 on Figure 4.
The undeveloped area to the west of the developed site would travel through grass swales to the
constructed drainage channel to the west of the site. The undeveloped area to the east of the developed
PAGE 17 220035_WCWM_REO_003F.DOCX
site would travel to the south through grass swales into the constructed drainage channel and through
to one of the culverts along the boundary.
3.1.3 EXISTING SURFACE WATER QUALITY
There is no data available on the quality of surface runoff currently leaving the site. Existing surface water
quality would be impacted by agricultural activities (predominately grazing) and to a lesser extent by
urban infrastructure (e.g. roads). Given these catchment influences, the site runoff is unlikely to comply
with the water quality objectives suggested for rivers and streams in SEPP (Waters of Victoria). Existing
surface water quality would be characterised during the surface water wetland commissioning phase to
provide background data. This is detailed in the draft Environment Improvement Plan.
Potential impacts on receiving waters would be managed by adopting a neutral or beneficial effect
design approach for the management of surface water runoff. This concept acknowledges that existing
land uses generate pollutants and when a land use changes, management measures should be put in
place to ensure that the post development pollutant loads are equivalent to, or less than, the existing
pollutant loads. This approach ensures that any existing beneficial uses of water will be protected and is
consistent with contemporary engineering practices.
3.2 ASSESSMENT METHODOLOGY
3.2.1 STORMWATER QUANTITY
The performance of the proposed stormwater management system was assessed using TUFLOW. This
model was used to estimate existing base case flows for the current site as per the details of the site
survey and aerial imagery, and the proposed case flows where topography and roughness are updated
to represent the proposed works.
A detailed description of the process and results can be found in Appendix A.
3.2.2 STORMWATER QUALITY
3.2.2.1 Model Description
The proposed stormwater management system and wetland configuration was modelled using the
Model for Urban Stormwater Improvement Conceptualisation (MUSIC) developed by the Cooperative
Research Centre for Catchment Hydrology.
MUSIC was developed as an aid to decision making and predicts the performance of stormwater quality
management systems. It enables users to evaluate conceptual designs of stormwater management
systems to ensure they are appropriate for their catchments. By simulating the performance of
stormwater quality improvement measures, MUSIC determines if proposed systems can meet specified
water quality objectives.
3.2.2.2 Pollutant Generation
The MUSIC software determines the pollutant loads generated by different land uses. By modelling the
pre-development land use, and a proposed stormwater management strategy, a comparison can be
made about the relative amounts of pollutant retention, and their expected concentrations.
A variety of land uses are proposed on the site, each with distinctive pollution generation characteristics.
The pollution generation rates assumed for the various land uses are listed in Table 3.2. Pollutant loads
PAGE 18 220035_WCWM_REO_003F.DOCX
are calculated based on these concentrations, the amount of rainfall and runoff and the effectiveness of
the proposed treatment systems.
The preliminary design of the constructed surface water wetland was modelled in the developed case.
Pollutant generation rates for the developed case were developed from the available literature.
Therefore, is it highly unlikely that significant nutrient runoff would occur from these areas.
Runoff from the hardstand areas was modelled as urban runoff as this provided higher pollutant loads
compared to commercial or industrial land use.
A summary of the pollutant generation rates used in the MUSIC modelling is provided in Table 3.2.
Table 3.2 - Pollutant concentrations used in MUSIC modelling
Pollutant
Average Concentration (mg/L)
Existing Agriculture Proposed
Roof (1)
Proposed
Sealed (1)
Proposed
Paddocks
Base
Flow
Storm
Flow
Base
Flow
Storm
Flow
Base
Flow
Storm
Flow
Base
Flow
Storm
Flow
Suspended
Solids 25 50 13 20 16 270 25 300
Phosphorus 0.20 1.1 0.15 0.13 0.14 0.50 0.2 1.2
Nitrogen 1.20 2 2.1 2 1.3 2.2 1.2 6.9
Source: (1) Fletcher et al (2004)
3.2.2.3 Catchment Areas
Catchment areas for each case modelled are summarised in Table 3.3.
Table 3.3 – MUSIC catchment areas
Model Area (ha) % impervious
Existing 7.285 0
Developed – roof 1.785 100
Developed – sealed 3.62 90
Developed – paddocks 1.88 0
The following soil properties were adopted for pervious catchment areas:
• Soil storage capacity 120 mm.
• Field capacity 50 mm.
3.2.2.4 Climate Data
Six minute rainfall and evaporation data for the period 15 August 1961 to 31 December 2000 was used
in the model from the Ellinbank Dairy Research Institute BOM Station (Station No. 085240). This data
was obtained from eWater which generates synthetic rainfall data for a given location based on
measured rainfall in surrounding areas.
PAGE 19 220035_WCWM_REO_003F.DOCX
3.3 CONSTRUCTED WETLAND/DETENTION BASIN
A constructed surface water wetland/detention basin system would provide stormwater quantity and
quality control for the site. The wetland system would include a permanent pool area that would
incorporate sedimentation zones, macrophyte zones and open water zones for water quality control.
The constructed wetland/detention basin would form part of a treatment train approach that would
improve the water quality of runoff leaving the site. Other components would include grass swales to
filter site runoff before it reaches the wetland system. The hydraulic residence time provided by the
wetland system would significantly improve water quality through sedimentation and nutrient uptake,
as well as providing oxidation and ponding to treat pathogens.
The proposed constructed wetland/detention basin shown conceptually in Figure 1 has the following
key design parameters:
• Inlet pond volume 2,000 m3;
• Macrophyte area 3,000 m2;
• Macrophyte area depth 0.4 m;
• Extended detention depth 0.5 m
• Additional Detention depth 0.6 m
• Total volume ~4,000 m3 @ normal water level (NWL).
The wetland macrophyte zone would have 200 mm high internal bunds that would trap water within the
macrophyte area in the event that greater than 200 mm of water is drawn from the wetland system. This
would maintain water in the macrophyte area.
Water for reuse in the facility would be drawn from the outlet pond. Prior to reuse, the water would go
through a filter and disinfection process to manage potential pathogens.
3.4 SURFACE WATER MODELLING RESULTS
3.4.1 PEAK FLOW
Peak site discharge through the five culverts under current and future site conditions was assessed using
TUFLOW. The locations of these culverts are shown in Figure 5. Results are summarised in Table 3.4
and detailed further in Appendix A.
PAGE 20 220035_WCWM_REO_003F.DOCX
Table 3.4 – TUFLOW modelling results
Culvert/
Tabledrain
ID
1 % AEP 10 % AEP
Base Proposed Impact Base Proposed Impact
No. 1 0.001 0.001 0.000 0.000 0.000 0.000
No. 2 0.086 0.060 -0.026 0.047 0.006 -0.041
No. 3 0.580 0.534 -0.046 0.211 0.185 0.026
No. 4 0.002 0.002 0.000 0.000 0.000 0.000
No. 5 0.390 0.346 -0.044 0.198 0.187 -0.011
No. 6 0.232 0.209 -0.023 0.123 0.122 -0.002
No. 7 0.182 0.125 -0.057 0.069 0.058 -0.011
The TUFLOW modelling results in the table above supports the results in Appendix A which
demonstrate there are no adverse impacts on neighbouring properties due to the development. In both
the 1% and 10% AEP events there no increase in peak discharges or peak flood levels external to the
site, as shown by impacts maps in Figure 6 and Figure 7. Consequently, there is no actionable flooding
nuisance resulting from the development.
Figure 5: Culvert locations
PAGE 21 220035_WCWM_REO_003F.DOCX
Figure 6: 1% AEP Surface Level Impacts
Figure 7: 10% AEP Surface Level Impacts
PAGE 22 220035_WCWM_REO_003F.DOCX
3.4.2 QUALITY
The MUSIC modelling results are summarised in Table 3.5 and show that the average annual pollutant
loads from the developed site are less than the existing loads. The water quality modelling demonstrates
that the downstream receiving environment would receive water with improved quality.
Table 3.5 – MUSIC Modelling Results
Parameter Existing
Post
Development
Pre-Treatment
Post
Development
Post-
Treatment
Post
Development
% Reduction
from Pre-
Treatment
Post
Development
% Reduction
from Existing
Flow (ML/yr) 19.1 47.9 13.2 72.4 29.6
TSS (kg/yr) 515 9890 306 96.9 40.6
TP (kg/yr) 4.38 19.4 2.22 88.6 49.3
TN (kg/yr) 23.8 104 17.5 83.2 26.5
3.4.3 SITE YIELD
The MUSIC model estimates existing average site yield from the catchment to be about 19.1 ML/year.
The proposed facility is estimated to discharge an average of about 13.2 ML/year; this is a decrease of
around 30%.
3.5 SURFACE WATER MANAGEMENT CONCLUSIONS
Surface Water Discharge Quantity
Mapping of the predicted impact due to the development to flooding on the site is shown in Figure 6
and Figure 7 as well as in Appendix A. The results show that onsite flooding is changed due to the
proposed works. However, these changes are contained within the site boundary and no flood levels
outside the site are impacted.
Surface Water Discharge Quality
The water quality treatment train including grass swales and the constructed surface water wetland is
designed to treat surface water from the site so that it is suitable for discharge from the site. Main
pollutants targeted for treatment are suspended solids and nutrients. In summary:
• The average annual load of suspended solids is reduced by 41% from 515 kg/year to 306 kg/year. Modelling results show the average suspended solids concentration in the water discharged from
the site falls from 26.3 mg/L to 25.5 mg/L.
• The average annual load of phosphorus is reduced by 49% from 4.38 kg/year to 2.22 kg/year. Modelling results show the average phosphorus concentration in the water discharged from the
site changes from 0.213 mg/L to 0.206 mg/L, essentially remaining the same.
• The average annual load of nitrogen is reduced by 26.5% from 23.8 kg/year to 17.5 kg/year. Modelling results show the average nitrogen concentration in the water discharged from the site
changes from 1.24 mg/L to 1.23 mg/L, essentially remaining the same.
Constructed wetlands remove contaminants through sedimentation, filtration, oxidation and plant
uptake. When considering the type of development in the catchment, the major pollutant sources are
PAGE 23 220035_WCWM_REO_003F.DOCX
suspended solids, organic matter, microbiological and nutrients. Constructed wetlands are sized to
target these major pollutants and in removing these, are also effective in removing other pollutants,
particularly particulate bound pollutants.
Surface Water Summary
Site discharge will occur in the same location as it does currently. Modelling shows that peak discharge
from the site is slightly modified from the current conditions, however there is no adverse impact to
flood levels outside of the site due to the proposed development. The concentrations of suspended
solids and nutrients in the water would essentially be unchanged and annual loads are expected to
decrease due to the development.
The water quality assessment indicates that the proposed surface water management system has a
neutral or beneficial effect on water quality. This will protect downstream beneficial uses consistent with
the principles of SEPP (Waters of Victoria).
4. LIQUID WASTE MANAGEMENT
4.1 EFFLUENT SOURCES
Liquid wastewater would be generated from the domestic amenities, truck wash, trough washing, wash
down and rainfall runoff from the solids stockpile area and uncovered sections of the truck wash area.
Domestic effluent generated from the central amenities building and transport operators amenities
would be managed using on-site effluent management systems for primary treatment with the effluent
then further treated through the facility’s effluent treatment system.
4.2 EFFLUENT MANAGEMENT SYSTEM
4.2.1 EFFLUENT QUANTITY
The design flow for the effluent management system is based on the peak weekly flow derived from the
water cycle modelling.
The peak weekly flow is 1,143 kL which equates to a design flow of 163 kL/day.
It is noted that this design value is 3.0 times the average daily flow through the system (55 kL/day) and
would provide a substantial design buffer to manage peak loads.
4.2.2 DESCRIPTION
The effluent management system includes:
• Solids separation;
• SBR wastewater treatment plant; and
• Pump station to transfer treated effluent offsite to the sewerage system.
PAGE 24 220035_WCWM_REO_003F.DOCX
4.2.3 SBR
Design
A sequencing batch reactor (SBR) will be used to treat effluent from the truck wash and wash down to
quality suitable for discharge as trade waste.
The SBR design basis is:
• Maximum flow rate 175 kL/day
• Average flow rate 55 kL/day
• Influent BOD
PAGE 25 220035_WCWM_REO_003F.DOCX
Helminth Removal
EPA Publication 464.2: Guidelines for Environmental Management – Use of Reclaimed Water (EPA, 2003)
notes that helminth removal can be achieved by methods such as sand or membrane filtration. The
proposed BSR will include a multimedia filtration system.
4.2.4 EFFLUENT QUALITY
The SBR system would treat the liquid waste to a standard suitable for discharge into South East Water
sewerage via a trade waste agreement.
The total modelled average annual effluent to be discharged from the site is approximately 20.1 ML/year.
The average, minimum and maximum daily discharges through the system to the sewerage were
modelled as follows:
• Average daily discharge of 55 kL;
• Minimum daily discharge of 0 kL;
• Maximum daily discharge of 163 kL.
The effluent treatment system design is expected to treat the effluent to the quality targets below for
discharge into South East Water sewerage:
• BOD ~ 20 mg/L
• TSS ~ 30 mg/L
• TN ~ 50 mg/L
• TP ~ 8 mg/L
4.2.5 COMMISSIONING
The effluent treatment system is based on biological processes that need to be effectively commissioned
to ensure the system provides a treated effluent that is fit for purpose. It is expected that the
commissioning period would be 12 months and would include the following stages:
• Testing system construction – mechanical and electrical testing, system filling and water tightness testing.
• Establishment of treatment processes – following initial filling, build-up of the required bacteriological populations would then commence. This could be enhanced by seeding the tanks
if it is considered necessary.
• Monitoring of system performance – once the system starts to establish the necessary biological populations, regular monitoring would be undertaken to track effluent treatment performance
through the system. This monitoring would typically include dissolved oxygen, pH, BOD/COD,
suspended solids and microbiological indicators.
PAGE 26 220035_WCWM_REO_003F.DOCX
5. DOMESTIC EFFLUENT MANAGEMENT
5.1 INTRODUCTION
The water cycle modelling indicates that the domestic wastewater load from the central amenities
building averages 1,314 L/day and ranges from 200 L/day to 3,325 L/day on peak sale days.
The modelled domestic wastewater load from the transport operator’s amenities averages 1,710 L/day
and ranges from 0 L/day to 2,975 L/day on peak sale days
Both systems would be designed to ensure they can manage increased loads during sale days.
The onsite effluent management system would be sized and constructed in accordance with AS/NZS
1547:2012 On-site domestic wastewater management and EPA Publication 891.3 Code of practice onsite
wastewater management (EPA, 2013). This latter reference applies to systems which treat up to a
maximum peak daily flow of 5,000 L/day. The design daily flow is within this limit.
5.2 PRIMARY TREATMENT
The domestic wastewater would receive primary treatment in a septic tank system. At this stage, it is
proposed to install a 5,000 L septic tank at both the central amenities building and transport operator’s
amenities.
AS/NZS 1547:2012 On-site domestic wastewater management requires that septic tanks retain the
average daily flow for at least 24 hours to settle the solids and float the scum effectively, so there is a
clear zone at the level of the discharge outlet. The proposed septic tanks would provide an average
hydraulic residence time of 3 to 5 days and greater than 24 hours for the peak day after allowing for
1,000 L sludge build-up.
5.3 SECONDARY TREATMENT
Discharge from the septic tanks would be pumped to the SBR and combined with the main effluent
stream for treatment and discharge to sewer.
6. SOLID WASTE MANAGEMENT
6.1 INTRODUCTION
As part of normal operations, the Longwarry Saleyards would generate a range of solid wastes including:
• Solids removed from the effluent treatment system (manure and organic matter from the solids separation system);
• Sludge recovered from the SBR;
• General waste and refuse; and
• Stock mortalities.
Less frequently the Longwarry Saleyards would generate spent soft floor material (woodchip/sawdust or
similar) from the cattle pavilion when replaced, which is assumed as an annual occurrence.
PAGE 27 220035_WCWM_REO_003F.DOCX
6.2 SOURCES AND ESTIMATED QUANTITIES
6.2.1 TRUCK WASH
Based on the solids removal efficiency and solids content of the effluent, approximately 1.5-2 m3/day of
solids is expected from the solids separation system.
Solids removed in the solids separation system form a pile in a concrete bunker. These are removed as
required and stockpiled. It is expected that the truck wash solids would be removed from the site as
soon as practicable but could remain on the stockpile area for up to 6 to 8 weeks. Therefore, up to
112 m3 could be stored onsite prior to being taken offsite.
6.2.2 GENERAL REFUSE
General municipal refuse would be generated by staff, agents, drivers and patrons. It is estimated one
small skip bin a week would be disposed of to a licensed waste facility. Appropriate waste receptacles
would be provided around the facility.
6.2.3 STOCK MORTALITIES
The proposed saleyards would provide less mortality risk to livestock compared to existing saleyard
facilities. The soft floor would minimise cattle slipping, and the covered yards would provide shelter for
animals in both hot and cold conditions.
Carcass disposal will be undertaken at a licensed waste facility.
6.2.4 SPENT SOFT FLOOR
The soft floor in the cattle pavilion would be turned (essentially lightly scarified) after each sale to
incorporate manure through the soft floor material. This post sale treatment would maintain aerobic
conditions and moisture control within the soft floor. This is an odour control measure.
The soft floor is progressively replaced over time. This material would be a valuable source of organic
matter and nutrients.
Spent soft floor material would be typically removed in rows. One run of pens would be approximately
140 m3 of soft floor material.
Spent soft floor material would be collected and stored in the solids stockpile area and disposed as soon
as practicable to an off-site licensed waste facility or composting facility.
A clean soft floor material laydown area would be provided to facilitate soft floor replacement.
6.2.5 SBR SLUDGE
Waste sludge from the SBR would be transferred automatically to the solids separation system as
required. The sludge would pass through the separation system with the filtrate returning to the
treatment process. Solids would be stockpiled with solids from the truck wash/soft floor and removed
as soon as practicable from site.
It is noted that sludge from the SBR is highly digested and has little organic content remaining which
significantly lowers the potential for odour from these solids.
PAGE 28 220035_WCWM_REO_003F.DOCX
6.3 SOLID WASTE STOCKPILES
Truck wash solids recovered from the solids separation system would be stockpiled in triangular
windrows with the following approximate dimensions:
• Based width = 6 m;
• Height = 1.5 m
• Batters = 1:2
• Length = 25 m
• Plan area (including 3 m access) = 340 m2
• Windrow surface area (for odour modelling) = 200 m2
• Windrow volume = 113 m3
• Access areas around each windrow = 3.0 m
Soft floor material would be stockpiled in triangular windrows with the following approximate
dimensions:
• Based width = 8 m;
• Height = 2 m
• Batters = 1:2
• Length = 20 m
• Plan area (including access) = 330 m2
• Windrow surface area (for odour modelling) = 230 m2
• Windrow volume = 160 m3
• Access areas around each windrow = 3.0 m
The area required for stockpiles is therefore a minimum of 670 m2. The nominated solids stockpile site
has an area of ~1,000 m2 and adequate dimensions to accommodate these stockpiles.
For odour modelling purposes:
• the truck wash material would require one windrow which would have a surface area for odour emissions of approximately 200 m2; and
• the maximum soft floor stockpile volume would require one windrow which would have a surface area for odour emissions of approximately 230 m2.
6.4 SOLID WASTE MANAGEMENT
There is no intent to utilise solid organic wastes on-site. All organic solids wastes would be removed off-
site as soon as practicable to a licensed waste facility or composting facility.
Recovered solids from the solids separation system and soft floor material would be temporarily
stockpiled on a sealed pad adjacent to the solids separation system, within a controlled drainage area,
with runoff draining back to the separation system collection sump. The stockpiling area would not be
covered to allow the solids to dry. The material would be transported off site when it is dry enough to
do so.
The duration of stockpiling prior to removal off-site would be monitored and determined by site
conditions and the operational objective of minimising the potential for offensive odours from this
PAGE 29 220035_WCWM_REO_003F.DOCX
source. Stockpiled material would be turned periodically to promote drying and aeration. Operational
experience from other sites provides the following indicative stockpiling activities:
• Truck wash solids – removed on average once per week and remain on the stockpile area for up to 6 to 8 weeks;
• Solids from the SBR – automatically transferred to the solids separation system and treated the same as truck wash solids.
• Soft floor material – replacement rotated and confined only to areas where the material has deteriorated beyond its useful life. Removal occurs on rotation over a 12 month period with
material remaining on the stockpile area for up to 3 to 4 weeks.
These timings are indicative only and would be confirmed through the EIP. Anecdotal data from other
sites indicates that these sources do not generate significant odour when managed as described. The
primary operational objectives would be to manage these solids to minimise odour generation.
Solids would be removed to appropriately approved and licensed facilities which would be detailed in
the EIP.
Quantities would be monitored by recording the amount of material taken off-site (truck numbers and
weight estimate).
7. SYSTEM MANAGEMENT
7.1 EFFLUENT TREATMENT SYSTEM
7.1.1 EFFLUENT QUALITY TARGETS
The effluent treatment system incorporates an SBR to treat the liquid wastes to a standard suitable for
discharging to sewerage. The proposed system is designed to ultimately achieve effluent quality meeting
the following targets:
• BOD ~ 20 mg/L;
• TSS ~ 30 mg/L;
• TN ~ 50 mg/L; and
• TP ~ 8 mg/L.
7.1.2 COMMISSIONING PERIOD
The effluent treatment system uses an SBR system to treat the liquid wastes to the required standards.
A commissioning period is required to effectively establish the treatment system. At a minimum this
would include:
• Testing system construction;
• Establishment of treatment processes; and
• Monitoring of system performance.
A commissioning period of 12 months is proposed from the commencement of operations to fully
commission the effluent treatment system to ensure it can consistently deliver treated water which meets
the design targets.
PAGE 30 220035_WCWM_REO_003F.DOCX
An outline of the commissioning process, controls, monitoring and reporting requirements is provided
in the following sections. The preliminary commissioning plan would be refined once detailed design is
completed.
7.1.3 COMMISSIONING PLAN
The preliminary commissioning plan and actions are outlined in Table 7.1. Details are provided in the
following section. System designers would be involved throughout the commissioning period and
would:
• Conduct training of site staff;
• Prepared commissioning and monitoring schedules;
• Review data and operational information;
• Respond to questions or operational issues;
• Oversee any changes to operational protocols;
• Regularly inspect the system commissioning progress; and
• Prepare a commissioning report.
Operations during the commissioning period would be undertaken by appropriately trained on-site staff.
Table 7.1 – Summary of commissioning plan and actions
Component Expected period Actions
Pre-commencement of operations 1-2 weeks Equipment testing
SBR establishment 16-20 weeks Effluent quantity recording
Effluent quality recording
Weekly system inspection
Adjust dosing
SBR stabilising/optimisation 20-24 weeks Effluent quantity recording
Effluent quality monitoring
Weekly system inspection
Adjust dosing
Online monitoring
Reporting 4 weeks Prepare commissioning report
7.1.3.1 Monitoring
Timing
Monitoring of the system would start at the commencement of truck wash operations. The following
monitoring would be undertaken during the operational phases.
1. Effluent quantity recording
2. Effluent quality monitoring
3. Weekly system inspection
Effluent Quantity Recording
Daily effluent quantity would be recorded through truck wash use.
AVDATA records of truck wash use would be downloaded and analysed to determine the average daily
effluent flow entering the system.
PAGE 31 220035_WCWM_REO_003F.DOCX
This data would be stored in digital records.
Daily rainfall records would be maintained.
Effluent Quality Monitoring
Where: Effluent monitoring locations would include:
E1 raw effluent from truck wash solids separation system discharge point
E2 outflow from SBR (discharge to sewer)
When: Samples would be collected every month commencing at the commencement of truck wash
operations (if effluent is present).
What for: Samples would be analysed for the following parameters:
E1 and E2
- Biochemical oxygen demand (BOD), mg/L
- Total suspended solids (TSS), mg/L
- pH
- E. coli, cfu/100mL
- Nitrogen suite (TN, TKN, NH3, NOx)
- Total phosphorus
7.1.3.2 Weekly System Inspection
The effluent treatment system would be inspected weekly during the commissioning period. The
inspection would note and record the following for the system:
1. Checks for leaks around tanks, reactor and pumping station/pumps;
2. SBR system monitoring panel and controls;
3. Chemical volumes;
4. Any solids build up; and
5. Any relevant operational comments – e.g. significant rain, higher than usual truck wash activity.
7.1.3.3 Reporting
A commissioning report shall be prepared after the initial 12 months of operation. This report would:
• Present an overview of the commissioning process;
• Present and discuss monitoring data;
• Describe any remedial actions or system modifications undertaken during commissioning; and
• Outline any management actions required to ensure the system meets the required quality.
7.1.4 ONGOING MONITORING
Ongoing system and environmental monitoring would be developed at the end of the commissioning
period and would be included in the EIP. It would include a combination of on-line system monitoring
and routine sampling.
PAGE 32 220035_WCWM_REO_003F.DOCX
7.1.5 EFFLUENT SYSTEM INSPECTION
The proposed treatment system is a robust, stable biological system that requires very little intervention
once fully commissioned. Normal plant management processes would include weekly inspection that
would target the following areas:
• SBR operation
• Dissolved oxygen levels
• Transfer pipe condition
Mechanical items (i.e. transfer pumps) would be subject to routine maintenance in accordance with
manufacturer’s recommendations and/or repaired as required. Routine monitoring would be used
throughout the commissioning period, and on a reduced frequency on an ongoing basis, to ensure the
system is functioning as expected.
7.2 SURFACE WATER SYSTEM
7.2.1 COMMISSIONING PERIOD
A commissioning period of up to 24 months is proposed from the commencement of operations to fully
commission the wetland system to ensure it can manage surface water flows from the site. Details would
be included in the EIP.
7.2.2 SURFACE WATER QUALITY MONITORING
The EIP would include the proposed monitoring program for surface water during and after
commissioning of the wetland. Samples would be collected four times per year and analysed for:
• Electrical conductivity;
• pH;
• Total suspended solids;
• Total nitrogen;
• Nitrate;
• Ammonia; and
• Total Phosphorus.
PAGE 33 220035_WCWM_REO_003F.DOCX
8. CONCLUSION
Assessment of the water cycle for the proposed Longwarry Saleyards demonstrates that adequate
supplies can be sourced through a combination of roof and surface water harvesting, and top up supplies
from the reticulated potable supply. The average annual water demand is 34.5 ML/year with
27.8 ML/year provided via water recycled or captured on site.
Surface water management would be based on separating catchments and managing runoff according
to the level of potential contamination present. Peak site discharge and quality would be managed
through a treatment train approach with grass swales and a constructed surface water
wetland/detention basin. The water quality assessment indicates that the proposed surface water
management system has a neutral or beneficial effect on water quality. This will protect downstream
beneficial uses consistent with the principles of SEPP (Waters of Victoria).
Liquid wastewater would be generated from the domestic amenities, truck wash, trough washing, wash
down and rainfall runoff from the solids stockpile area and uncovered sections of the truck wash area.
All liquid wastes would receive treatment in a SBR treatment system and would then be pumped offsite
to the sewerage system.
Solid wastes would include solids separated from the effluent management system, spent soft floor
material, stock mortalities and general waste and refuse. Recovered solids and soft floor material would
be stored in a designated solids stockpile area which has adequate area to manage the expected
maximum stockpiles. Stock mortalities would be removed from the site as required to a licensed waste
facility. General waste and refuse would be collected in receptacles and transferred to a small skip bin
for offsite disposal.
PAGE 34 220035_WCWM_REO_003F.DOCX
9. REFERENCES
EPA Victoria (Publication 891.3, 2013) Code of Practice, Onsite Wastewater Management
T. Fletcher, H. Duncan, P. Poelsma, S. Lloyd (2004) Stormwater Flow and Quality, and the Effectiveness of Non-Proprietary
Stormwater Treatment Measures – A Review and Gap Analysis
Marcos von Sperling and Carlos Augusto de Lemos Chernicharo (eds) (2005) Biological Wastewater Treatment in Warm Region
Climates.
Appendix A FLOOD ASSESSMENT
FLOOD ASSESSMENT
PROPOSED LONGWARRY SALEYARDS
PREPARED FOR:
LONGWARRY SALEYARDS PTY LTD
JULY 2020
FLOOD ASSESSMENT LONGWARRY SALEYARDS
LONGWARRY SALEYARDS PTY LTD
PAGE i GEO-0008 1903272 HIA_REV4.1.DOCX
Report Title: Flood Assessment
Project: Proposed Longwarry Saleyards
Client: Longwarry Saleyards Pty Ltd
Report Ref.: GEO-0008 1903272 HIA_Rev4.1.docx
Status: Final Rev4.1
Issued: 8 July 2020
Premise Australia Pty Ltd (Premise) and the authors responsible for the preparation and compilation of
this report declare that we do not have, nor expect to have a beneficial interest in the study area of this
project and will not benefit from any of the recommendations outlined in this report.
The preparation of this report has been in accordance with the project brief provided by the client and
has relied upon the information, data and results provided or collected from the sources and under the
conditions outlined in the report.
All data and information contained within this report are prepared for the exclusive use of Longwarry
Saleyards Pty Ltd to accompany this report for the land described herein and are not to be used for any
other purpose or by any other person or entity. No reliance should be placed on the information
contained in this report for any purposes apart from those stated therein.
Premise accepts no responsibility for any loss, damage suffered or inconveniences arising from, any
person or entity using the plans or information in this study for purposes other than those stated above.
FLOOD ASSESSMENT LONGWARRY SALEYARDS
LONGWARRY SALEYARDS PTY LTD
PAGE ii GEO-0008 1903272 HIA_REV4.1.DOCX
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................ 1
2. THE DEVELOPMENT ................................................................................................. 2
3. DATA .......................................................................................................................... 3
4. HYDROLOGIC ASSESSMENT .................................................................................... 4
4.1 METHODOLOGY .................................................................................................................................................. 4 4.2 DESIGN RAINFALL INTENSITY & TEMPORAL PATTERNS .................................................................... 4 4.3 RAINFALL LOSSES ............................................................................................................................................... 5 4.4 RESULTS .................................................................................................................................................................. 5
5. HYDRAULIC ASSESSMENT ....................................................................................... 6
5.1 METHODOLOGY .................................................................................................................................................. 6 5.2 MODEL EXTENT AND TOPOGRAPHY .......................................................................................................... 6 5.3 HYDRAULIC ROUGHNESS ................................................................................................................................ 7 5.4 HYDRAULIC STRUCTURES ............................................................................................................................... 9 5.5 BOUNDARY CONDITIONS ............................................................................................................................... 9 5.6 PROPOSED CASE MODEL CHANGES .......................................................................................................... 9 5.7 RESULTS ................................................................................................................................................................ 10
5.7.1 IMPACTS OF DEVELOPMENT .................................................................................................... 12 5.7.2 SENSITIVITY ANALYSIS ................................................................................................................ 12
6. CONCLUSION .......................................................................................................... 13
7. QUALIFICATIONS .................................................................................................... 14
8. REFERENCES ............................................................................................................ 15
FLOOD ASSESSMENT LONGWARRY SALEYARDS
LONGWARRY SALEYARDS PTY LTD
PAGE iii GEO-0008 1903272 HIA_REV4.1.DOCX
TABLES
Table 5.1 – Adopted Manning’s n Values ............................................................................................................................ 7 Table 5.2 – Flow through the culverts under Thornell Road ...................................................................................... 11 Table 5.3 – Total Discharges from Site ............................................................................................................................... 12 Table 5.4 – Flow Comparison from Basin for Sensitivity Analysis ............................................................................ 12
FIGURES
Figure 1: Site Location .......................................................................................................................................................... 1 Figure 2: WBNM Sub-Catchment Assumptions ......................................................................................................... 4 Figure 3: TUFLOW Model Extent ...................................................................................................................................... 6 Figure 4: TUFLOW Proposed Case Topography Assumptions ............................................................................. 7 Figure 5: TUFLOW Base Case Manning’s Assumptions .......................................................................................... 8 Figure 6: TUFLOW Proposed Case Manning’s Assumptions ................................................................................ 8 Figure 7: TUFLOW Proposed Case Wall and Bunds ............................................................................................... 10 Figure 8: Location of Culverts under Thornell Road and Table Drain Reporting Points ......................... 11
APPENDICES
Appendix A – Proposed Site Drawings
Appendix B – Base Case Flood Maps
Appendix C – Proposal Case Flood Maps
Appendix D – Predicted Flood Impacts
FLOOD ASSESSMENT LONGWARRY SALEYARDS
LONGWARRY SALEYARDS PTY LTD
PAGE iv GEO-0008 1903272 HIA_REV4.1.DOCX
EXECUTIVE SUMMARY
This Flood Assessment report details the impacts to flooding likely to arise from the proposed Longwarry
Saleyards Development located in Longwarry, Victoria. The report demonstrates how the development
meets the acceptable performance outcomes with respect to the Melbourne Water requirements.
The key aims of this Flood Assessment are to set adequate flood immunity levels for the proposed
livestock exchange and to demonstrate no adverse impacts to external properties within the catchment.
These aims have been met by developing an WBNM Hydrologic and TUFLOW Hydraulic flood model
(with Rainfall on Grid). These models included appropriate changes to the existing scenario model, to
reflect the proposed works. The proposed development and adopted stormwater infrastructure, which
were utilised within the modelling, demonstrated that the anticipated post-development flood regime
through and external to the site, demonstrates adequate mitigation which illustrates no adverse impacts
external to the site.
.
FLOOD ASSESSMENT LONGWARRY SALEYARDS
LONGWARRY SALEYARDS PTY LTD
PAGE v GEO-0008 1903272 HIA_REV4.1.DOCX
ABBREVIATIONS
AEP Annual Exceedance Probability
AHD Australian Height Datum
ARR19 Australian Rainfall and Runoff 2019
DTM Digital Terrain Model
fi Fraction impervious
IFD Intensity Frequency Duration
LiDAR Light Detection And Ranging
FLOOD ASSESSMENT LONGWARRY SALEYARDS
LONGWARRY SALEYARDS PTY LTD
PAGE 1 GEO-0008 1903272 HIA_REV4.1.DOCX
1. INTRODUCTION
Premise has been commissioned by Longwarry Saleyards Pty Ltd to prepare a Flood Assessment for the
proposed Longwarry Saleyards. The site is located on Thornell Road, on