Technical dataTotal plant output: 12 m³/hConductivity: < 0,06 uS/cmSiO2: < 20 ppb
Units in plantBiocide dosingDouble Pass Reverse Osmosis, DPRO C3-12/9NaOH dosingElectrodeionization unit, EDI 2-5000eMixed bed unit for off-siteregeneration, EUREX 1201
Reference 119289
Water for high pressure boilers with steam turbine
Industry Heat and power plantsApplication Boiler waterCountry Poland
Description
EC Gliwice is the strategic, local supplier of district heating for industrial and public buildings with ageneration capacity of 67 MWt.
SFW Energia needed to expand the power generation module. Installation of the steam turbineintroduced the need to use water in accordance with the standards PN-EN 12952-10 and PN-EN12952-12.
The water treatment plant is designed and built to supply boiler feed water for high-pressure boilers aswell as make-up water for the district heating network.
SILHORKO-EUROWATER has supplied project and main components for the construction of thecomplete water treatment plant as well as start up and final documentation
Raw water comes from municipal waterworks and is undergoing the following treatment steps: 1) Sandfiltration 2) Softening 3) Double pass membrane filtration (DPRO) with NaOH dosing between ROpasses 4) Electrodeionization-polishing (EDI).
Parallel to the EDI module is a fine polishing mixed bed installed as a security module..
Interested in more pictures or related references, please visit eurowater.com/references