+ All Categories
Home > Documents > Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014...

Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014...

Date post: 30-Sep-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
12
Presentation and boards developed by Stantec Waterbury, Vermont 2014-2018 Construction Projects
Transcript
Page 1: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

Waterbury, Vermont 2014-2018 Construction Projects

Page 2: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

I-89 to Montpelier

I-89 to Burlington

VT Route

100 t

o Stowe

North

VT Rou

te 1

00

to W

aitsfi

eld

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 3: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: 6 Miles of Highway Rehabilitation along US Route 2Construction: September 2013 – August 2014Cost: $7.1 million

Bolton-Waterbury

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 4: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: Reconstruction of Flood Damaged PropertyConstruction: January 2014 – January 2016Cost: $125 million

State Office Complex

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 5: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: Installation of a New Traffic Signal at Route 100/Interstate 89, Exit 10 Northbound Off-RampConstruction: June 2014 – August 2014Cost: $250,000

Signal at I-89 and VT-100 Intersection

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 6: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: 12 Miles of Pavement Resurfacing along VT Route 100Construction: July 2014 – October 2014Cost: $2.1 million

Waitsfield-Moretown-Duxbury

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 7: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

Municipal Project: Reconstruction of US Route 2/VT Route 100 North T-Intersection with a Modern RoundaboutConstruction: July 2014 – June 2015 (substantial completion November 2014)Cost: $3.9 million

Waterbury Roundabout

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 8: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

Municipal Project: 0.5 Miles of Sidewalk ImprovementsConstruction: August 2014 – October 2014Cost: $410,000

Stowe Street Sidewalk

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 9: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: Rehabilitation of Interstate 89 Mainline Bridges and Replacement of Exit 10 Northbound Off-Ramp BridgeConstruction: August 2014 – November 2016Phase 1: August 2014 – November 2014Cost: $11 million

I-89 Bridge Reconstruction

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 10: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: 8 Miles of Highway Rehabilitation along VT Route 100Construction: April 2016 – October 2017Cost: $10 million

Waterbury-Stowe

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 11: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

State Project: 1 Mile of Highway Reconstruction along US Route 2 (Main Street)Construction: April 2016 – October 2018Cost: $15 million

Waterbury Main Street

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018

Page 12: Waterbury, Vermontwatp.vtransprojects.vermont.gov/...VTrans_Waterbury_v2_PRESENTA… · 14/7/2014  · Other Projects Presentation and boards developed by Stantec • Smart Work Zone

Presentation and boards developed by Stantec

Other Projects

• Smart Work Zone Summer 2014 implementation

• Southbound On-Ramp Closure Trial period, 2015 – 2016

• Stowe VT-100 Bridge Reconstruction April 2014 – September 2014

• Stowe VT-108 Bridge Reconstruction Spring 2015

Spring 2014 Fall 2014 Fall 2015Spring 2015 Spring 2016 Fall 2016 Spring 2017 Fall 2017 Spring 2018 Fall 2018


Recommended