Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Non-Technical Summary
Introduction
The Brent Cross Cricklewood regeneration
scheme is located in northwest London and
comprises 151 hectares (ha) of land within the
London Borough of Barnet (LBB) (the ‘Site’). In
July 2014, LBB granted planning permission for
the regeneration scheme Masterplan, hereafter
referred to as the ‘2014 Permission’. The
consented proposals, applied for by the Brent
Cross Cricklewood Development Partners,
comprising Hammerson plc and Standard Life
Investments (the ‘Applicant’), are referred to as
the ‘Consented Scheme’.
The Site includes the existing Brent Cross
Shopping Centre to the north, the A41 and Brent
Cross London Underground Station to the east,
Cricklewood Lane to the south, the A5 to the west
and the M1 motorway to the northwest. The
location of the Site and extent of the 2014
Permission planning application boundary are
shown in Figure 1.
The Consented Scheme already has the benefit
of outline planning permission, with full details
also approved for alterations to road junctions
within the Site, known as the ‘Gateway
Junctions’. The Applicant has now progressed to
detailed design which, due to the scale of the
Consented Scheme, will come forward on a
phase by phase basis in line with the 2014
Permission. The Applicant is currently seeking
planning approval for details of the first phase of
the Consented Scheme referred to as ‘Phase 1A
(North)’. A series of Reserved Matters
Applications (RMAs) have therefore been
prepared to submit to the London Borough of
Barnet (LBB) which seek approval for elements
that will come forward as part of Phase 1A
(North). An RMA can be defined as an application
for further details in respect of an outline planning
permission which has already been given.
This document provides a Non-Technical
Summary of a report prepared by Waterman EED
Ltd and a consultant team to inform the planning
decision making process of the Phase 1A (North)
RMAs with reference to the likely significant
environmental impacts. The report is titled ‘Brent
Cross Cricklewood Environmental Statement –
Further Information Report’ and provides further
environmental information (where necessary) to
inform decision making to that which forms the
basis of the 2014 Permission.
Background
Brent Cross Cricklewood is one of London’s
major regeneration schemes and development of
the area is supported by both regional and local
planning policy. The Applicant first received
outline planning permission in October 2010 for
the redevelopment of Brent Cross Cricklewood.
An application was then submitted in October
2013 to amend the 2010 Permission and to
include additional design elements. The October
2013 planning application was submitted under
Section 73 of The Town and Country Planning
Act 1990 and is therefore referred to as the
‘Section 73 Application’.
Due to the scale of the regeneration project, the
proposals were subject to an Environmental
Impact Assessment (EIA) process undertaken in
line with relevant UK legislation (The Town and
Country Planning (Environmental Impact
Assessment) Regulations 2011 (the ‘EIA
Regulations’)). EIA is a process required under
UK law for certain development projects which
identifies the likely significant impacts that the
project has on the environment. The purpose of
the EIA process is to ensure that decision makers
are fully aware of the environmental impacts of a
project before making a decision on whether to
grant planning permission. Where an EIA is
required, information on the likely significant
impacts must be provided by the Applicant in an
Environmental Statement (‘ES’) to accompany
the planning application.
The findings of the EIA were reported in a Section
73 Environmental Statement dated October 2013
(referred to subsequently as the ‘s.73 ES’) and
summarised in a Non-Technical Summary. The
s.73 Application, s.73 ES, Non-Technical
Summary and accompanying drawings and
appendices are available for download at
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
www.brentcrosscricklewood.com. This Non-
Technical Summary does not summarise the
findings of the s.73 ES and therefore should be
read in conjunction with the s.73 ES and its Non-
Technical Summary.
The EIA Regulations also apply to the stages of
consent after outline planning permission is
granted, including RMAs. Since an ES has
already been submitted (the s.73 ES) and
permission granted, when granting permission for
the Phase 1A (North) RMAs LBB must ensure
that the environmental information before it is
‘adequate’. The ES Further Information Report
considers whether the s.73 ES remains valid and
therefore adequate for decision making. In some
instances, more environmental information is
provided to reflect the detailed design or new
baseline information. The Consented Scheme
authorised by the 2014 Permission with the
Phase 1A (North) RMAs elements in place (as a
whole) is hereafter referred to as the
‘Development’.
The 2014 Permission
The overall vision for the area is centred on
creating a new gateway for London and a vibrant
urban area for Barnet. The Consented Scheme
will be at the centre of a new mixed-use town
centre developed on both sides of the A406 North
Circular Road, along a new high street. The
existing Brent Cross Shopping Centre will be
integrated with new uses such as business, hotel
and residential linked to a network of new streets
and squares, with the intention for the Site to
attract people day and night to create a vibrant
new destination. The Consented Scheme will
deliver 7,500 new homes as well as new buildings
for three local schools, new health facilities and
high quality parks and open spaces. More than
£400 million will be invested in transport
infrastructure, including new roads, increased
capacity at key junctions and the creation of a
new railway station on the Midland Mainline and
Thameslink lines. The Illustrative Masterplan
presented in Figure 2 shows one way in which
the Consented Scheme could be delivered.
Phase 1A (North) RMAs
Phase 1A (North) is the first development phase
to be brought forward in line with the 2014
Permission and its extent and key features are
shown in Figure 3.
Through the Phase 1A (North) RMAs the
Applicant is now seeking permission for the
detailed design of infrastructure, open space, two
residential plots and a temporary bus station and
bus stops, via a series of individual RMAs.
Collectively, the RMAs are referred to as the
‘Phase 1A (North) RMAs’. The detailed design
for each element of the Phase 1A (North) RMAs
has been the subject of ongoing consultation with
LBB, statutory bodies and interested groups.
Public exhibition events for the Phase 1A (North)
RMAs were also undertaken in October 2014.
As the detailed design has been developed for
Phase 1A (North) elements, some minor
deviations from the 2014 Permission have been
identified. Approval for these has been sought
under planning conditions attached to the 2014
Permission and a S96A Application. The
deviations however, are limited and they are not
expected to give rise to significant environmental
impacts not already identified in the s.73 ES.
Details for temporary car parks, roads and
bridges will be subject to a separate RMA which
will be submitted to LBB in 2015. Details of a
temporary bus station and bus stops are included
within the Phase 1A (North) RMAs and as such
have been assessed within the ES Further
Information Report.
The elements included within the Phase 1A
(North) RMAs are set out below. Details of
components of the Consented Scheme not
described below will be submitted for approval in
the future either by the Applicant or Southern
Developer.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 1: Site Location
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 2: Revised Illustrative Masterplan
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 3: Phase 1A (North) Elements
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Infrastructure
The infrastructure that forms part of the Phase 1A (North) RMAs is summarised in Table 1 and identified in
Figure 4. The Gateway Junctions will also be delivered as part of Phase 1A (North) although they already
have detailed planning permission and therefore reserved matters approval does not need to be sought for
them.
Table 1: Description of Phase 1A (North) Infrastructure
Type of infrastructure
Infrastructure item and description
Primary and Secondary Routes
Claremont Avenue - The route in the Market Quarter Zone which links the new Claremont Road
North Junction with Tilling Road.
Templehof Avenue - The route connecting Market Quarter and Brent Cross East Zones across
Bridge Structure B1 (A406 Templehof Bridge).
Templehof Link Road - The route connecting Claremont Avenue and Templehof Avenue within
the Market Quarter Zone.
Tilling Road West Re-alignment and Diversion (Part 1) - The alterations to the existing Tilling
Road west of the new Claremont Avenue.
Prince Charles Drive Diversion - The diversion of Prince Charles Drive towards the south of
Brent Cross East Zone.
Claremont Road Junction North - The creation of a new junction between the existing
Claremont Road, new Claremont Avenue, Claremont Park Road and Orchard Lane.
Claremont Avenue Junction with Tilling Road - The creation of a new junction between existing
Tilling Road and new Claremont Avenue and including such realignment of Tilling Road as may be necessary in order to accommodate Bridge Structure B7 (Living Bridge).
High Street South (East Works) - Part of High Street South within Market Quarter zone.
Orchard Lane - A new road linking with the new Claremont Avenue / Claremont Park Road /
Claremont Road signal junction.
Brent Cross Pedestrian Underpass Works - Such works to the existing pedestrian underpass
beneath the A41 adjacent to the Brent Cross East Zone to include improvements to pedestrian links between the underpass and Brent Cross Shopping Centre.
Engineering Works
Eastern, Central and Western River Brent Alteration & Diversion Works -
The alteration and diversion works to the River Brent. This encompasses the stretch of the river between the M1 slip road onto the A406 North Circular in the West and the A41 Brent Cross flyover in the east.
Reconfiguration of the channel, south of the Shopping Centre, is designed to allow creation of the pedestrianised High Street North but also an attractive resource for the new and existing community, address current flooding problems and offer habitat for wildlife.
The works will be delivered in stages. The first will involve alterations to the eastern section around the new internal roundabout, created as a result of the A406/A41 modifications and particularly the new slip road off the A406, as well as around the western internal roundabout and River Brent Nature Park. The eastern section will be completed in line with the A41/A406 junction works.
Bridge Structures
Bridge Structure B1 (Replacement A406 Templehof Bridge) - The creation of a replacement
road bridge to provide a link over the A406 to link Market Quarter and Brent Cross East and West
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Type of infrastructure
Infrastructure item and description
Zones to include insofar as reasonably practicable provision for bus lanes, step free access and cycle access (without dismounting).
River Brent Bridges (as relevant to the Eastern, Western and Central River Brent Alteration and Diversion Works) - Two pedestrian and cyclist only bridges and nine vehicular bridges to be
provided (as part of the River Brent Alteration and Diversion Works and the River Brent Riverside Park) over the River Brent within Brent Cross East and West Development Zones.
Bridge Structure B6 (M1 Junction Pedestrian and Cycle Bridge) – A new pedestrian and
cycle bridge to provide a link between the Site at the Station Quarter Zone to the existing communities north of the Site to include insofar as reasonably practicable provision for step free access and cycle access (without dismounting).
Bridge Structure B7 (Living Bridge) (for approval purposes only) - A new pedestrian and cycle
bridge within the Northern Development to provide a link over the A406 between the Market Quarter Zone and the Eastern Lands Zone and the Brent Cross East Zone to include provision for step free access. The Living Bridge will include landscaped areas as well as a multi-use space for relaxing, events, activities and occasional markets. The northern and southern sections of the bridge will have parapet openings to enable views of the River Brent and surrounding Development. Cycles will have to dismount crossing the bridge.
Temporary Bus Station and Bus Stops
Access to the existing Brent Cross bus station on Prince Charles Drive will not be available during
construction of the Phase 1A (North). A temporary facility is therefore required to allow construction
works to progress for a period of four years until the new bus station has been constructed. A
Temporary Bus Station will be provided within Plot 114 (currently the south-west car park for the
Brent Cross Shopping Centre) to accommodate 18 bus ‘layover’ stands and four drop-off and four
pick-up spaces. Temporary bus stops will also be provided within Plot 113 (car park directly west of
Layfield Close) comprising four drop-off and four pick-up spaces. A 2.5 metre high fence will be
provided along the western boundary of Plot 113 to reduce environmental impacts. Details of the
temporary bus station were not available in the s.73 Application.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 4: Phase 1A (North) Infrastructure (for illustration purposes only includes some associated temporary works)
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Open Spaces
Claremont Park: Improvements to the
existing Claremont Way Open Space (total
area 1.95ha) including planting, play and
activity space with seating and cycle parking
provision. A minimum of 2,000m2 of play
space will be provided together with a picnic
area (minimum of 200m2);
Clitterhouse Playing Fields Part 1:
Improvements to the existing playing fields
(total area 18.2ha) providing new recreation
facilities and landscaping. Demolition of the
existing Clitterhouse Farm Buildings in the
south of the park was proposed in the s.73
Application but these will now be retained and
re-used and an element will be used for a
maintenance store as part of Phase 1A
(North). The remainder of the Farm Buildings
will be retained and refurbished by the
Southern Developer. Future uses are likely to
include a café as well as other community
uses. Key features of the improvements to the
Playing Fields include:
Landscape planting and selected tree
removal or replacement (the majority of
trees along the boundaries of the
existing Playing Fields will be retained);
Natural turf sports pitches (3 senior
pitches, 2 junior pitches (9 aside) and 2
mini soccer pitches (7 aside) in the
southeast – there will be no specific
lighting or full perimeter fences;
Outdoor gym;
Play space (minimum of 5,000m2);
Park pavilion building including
changing facilities, store, café kiosk and
public toilets;
Car (21 spaces), cycle parking (55
spaces), and a network of paths; and
Changes to ground levels to create
suitable playing surfaces.
Part 2 of the proposals for Clitterhouse
Playing Fields will be delivered by the
Southern Developer and includes creation
of AstroTurf pitches and the Clitterhouse
Stream area.
Central Brent Riverside Park: Creation of a
riverside park (total area 3.18ha) associated
with the central section of the realigned River
Brent. The detailed proposals comprise
planting, a river path providing pedestrian and
cycle access, bank stabilisation measures as
well as wildlife improvements.
Plots 53 and 54 Landscape: Private and
communal gardens will be provided to the east
of the new residential buildings with hedging
and trees planted along the eastern and
western boundary. A ‘doorstep’ playspace will
also be provided. ‘Green’ roofs will be
provided on all of the buildings to provide
wildlife habitat.
All open spaces in Phase 1A (North) are
illustrated in Figure 5.
Development Plots 53 and 54 (Brent Terrace)
New residential buildings are proposed at two
triangle shaped plots of land off Brent Terrace (as
shown on Figure 6). The buildings will provide
47 new homes with a mix of two and three
bedroom flats and three and four bedroom
houses. The buildings will be three storeys high
and a total of 47 car parking spaces will be
provided together with cycle storage. Access to
the accommodation and car parks will be
provided from Brent Terrace and a new turning
circle is proposed at the northern end of Brent
Terrace.
Plots 53 and 54 have been brought forward in
order to provide new homes for some of the
residents displaced by demolition of part of the
Whitefield Estate to allow construction of the
Living Bridge and associated road works. A small
gas-fired combined heat and power plant (CHP)
will be provided within Plot 53 to generate
electricity for the new housing.
Demolition and Construction
The areas identified for demolition in Phase 1A
(North) remain as identified in the s.73
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Application and include 60 units of the Whitefield
Estate, 25 units of the Rosa Freedman Centre, 8
units over shops facing Claremont Way, units
within Claremont Industrial Estate, Cardiff House
at northern end of Brent Terrace and buildings at
the corner of A5/A407 to allow for junction
improvements. The amount of land required to
deliver Phase 1A (North) remains the same as
presented in the s.73 Application apart from some
additional areas of land at the western
roundabout (off the A406) due to necessary
alterations in its design.
The construction information presented in the
s.73 Application remains valid. The majority of
information was set out in a Construction Impact
Assessment Addendum (‘CIA Addendum’) and
an Indicative Construction Programme. The
Applicant is required to submit more details in
relation to construction for approval before works
start, including Remediation Strategies, Code of
Construction Practice (CoCP), Construction
Traffic Management Plan (CTMP), Construction
Environmental Management Plan (CEMP) and a
Demolition and Site Waste Management Plan.
The Indicative Construction Programme and
phasing remains as set out in the s.73 Application
with the exception of the fact that Plots 53 and 54
will now be delivered as part of Phase 1A (North)
rather than 1C. This minor change does not affect
the findings of the s.73 ES. Construction is due
to commence in 2016 with completion of the
Masterplan as a whole in 2031.
Development of the Scheme and
Alternatives
The Scheme already has planning permission
and as such, the main alternatives set out in the
s.73 ES have not been re-visited as they remain
valid. Alternatives considered during detailed
design for the Phase 1A (North) RMAs are limited
since they were constrained by the limits of the
2014 Permission.
Highways Improvements
As detailed design modelling work results
determined the final road layouts, junctions and
traffic management required for the
Development, no main alternative highway
layouts were considered by the Applicant. The
layout of the western roundabout was however
altered from the initial design presented in the
s.73 Application as a result of detailed traffic
modelling which showed that an extra road was
required through the roundabout.
Bridge Structures
The Living Bridge design was amended following
consultation with LBB. Early designs did not allow
pedestrians to view the wider Development
including the Riverside Park from the Living
Bridge. In response, viewing panels have been
added to sections of the bridge with metal
fretwork.
A high level of cycle parking across the bridge is
included in the design with parking repositioned
following consultation, at the entrances to the
bridge with the majority on the northern end
where cyclists will likely arrive at the
Development.
The replacement to the existing Templehof
Bridge was designed in response to the
outcomes of the detailed design traffic model.
Through identifying alternative routes, the need to
accommodate abnormal loads was deemed to no
longer be required. It was also defined during the
detailed design stage that a circular ramp, rather
than a lift, will provide step-free access.
River Brent Re-alignment
The detailed design of the river alteration and
diversion works have been developed in line with
the parameters of the 2014 Permission, as such
no significant alternatives were considered
further by the Applicant.
Temporary Bus Station and Bus Stops (Plots 114
and 113 respectively)
During the construction works for Phase 1A
(North), the Brent Cross Shopping Centre Bus
Station will need to be relocated. Three options
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
were explored by the Applicant in 2014 to
accommodate the existing bus operations. The
first option included keeping the bus station in its
current location during Phase 1A (North)
construction and providing alternative temporary
access routes. However, a temporary bus station
location will still likely be required towards the end
of 1A (North) construction works. This was
therefore discounted. Two options were
considered for the location of a temporary bus
station; either in the south west Shopping Centre
car park (Plot 114), to the south of the River Brent
or in the north west Shopping Centre car park
(Plot 113), to the west of the existing John Lewis.
An options study was undertaken of a number of
the Shopping Centre car parks looking at
transport and access, noise and air quality
issues. Following this initial study, it was agreed
that the best solution was to provide the
Temporary Bus Station at Plot 114 in the south
west Shopping Centre car park and separate
Temporary Bus Stops at Plot 113.
Open Spaces
A number of design alternatives were considered
for Clitterhouse Playing Fields with input from
LBB and local community groups. The Phase 1A
(North) RMAs propose to retain and reuse the
Clitterhouse Farm Buildings rather than remove
them (as proposed in the s.73 Application). The
following main alternatives for the Clitterhouse
Playing Fields were explored:
Varying locations for play space;
Varying parking and access road locations
considered, with final plans choosing to move
them further away from existing and proposed
buildings; and
Access for maintenance vehicles considered
and discrete access incorporated into the final
design; and
Varying locations for maintenance store and
offices.
A number of alternatives were also considered to
explore the most efficient way of providing sports
pitches, to minimise impact on existing levels and
adjacent paths, while at the same time providing
improved gradients to the playing fields.
Alternatives to the final play space strategy were
also considered during the design development.
No significant design alternatives considered for
Claremont Park or the Central Brent Riverside
Park.
See Figure 5 for open spaces.
Plots 53 and 54 (Brent Terrace)
A reduced amount of units is now proposed within
Plots 53 and 54 from the early designs, but the
floorspace to be provided in the 47 replacement
units exceeds that of the 60 units to be
demolished in the existing Whitefield Estate and
secures some larger social rented units as
required by LBB. The Phase 1A (North) RMAs
now includes 30 units on Plot 53 (initially was 39
units) and 17 units on Plot 54 (initially was 21
units). See final plans on Figure 6. This is due to
restrictions and consideration of the building
height, distance to neighbouring buildings, design
standards and LBB requirements. The reduction
in housing numbers has allowed the building
lengths to be reduced, increasing the distance
from neighbouring properties. Approach to the ES
Further Information Report
The main aims of the ES Further Information
Report are to review the s.73 ES in light of the
detailed design of the Phase 1A (North) RMAs
and the current baseline conditions; assess
whether the s.73 ES remains valid for the
purposes of decision making, and / or provide
‘further environmental information’ to ensure that
the environmental information for the decision
making is adequate and takes into account all the
likely significant environmental impacts of the
Development and provides any other requisite
information (i.e. 2014 Permission with the Phase
1A (North) RMAs in place). The Report presents
any changes to the likely significant impacts and
other requisite information reported in the s.73 ES
as a result of the detailed RMA designs or the
availability of other new information.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
A ‘Statement of Conformity’ is provided for those
topics where environmental baseline information
presented in the s.73 ES remains valid, the
methodology remains valid and the detailed
design has been reviewed and found not to result
in any new or different likely significant
environmental impacts from those reported in the
s.73 ES or the need for any other requisite
information.
For some environmental topics, further
information and assessment has been provided
over and above that presented in the s.73 ES. In
most cases this is as a result of new baseline
information obtained in 2014 or to ensure the
assessments reflect the detailed designs now
available which were not available in the s.73
Application (as they were submitted in ‘outline’).
Where there are new or different likely significant
environmental impacts from those presented in
the s.73 ES these are reported along with
measures to avoid or reduce impacts (‘mitigation
measures’).
The scope of the ES Further Information Report
was discussed with LBB and their advisors,
Capita, in September 2014 and an EIA Scoping
Report was submitted to LBB in October 2014
which set out the proposed approach. LBB
provided an EIA Scoping Opinion in December
2014 which comments on the scope and content
of the ES Further Information Report.
The approach and methodology used in the s.73
ES has been applied wherever possible. A
summary of the approach to each technical
chapter considered in the s.73 ES is provided in
Table 2.
Land Use
The existing land uses within and surrounding the
Site were reported in the s.73 ES. These have
been reviewed and are deemed to remain valid
as there has been no significant change in the
land use from that reported in the s.73 ES.
Land Use Planning
The s.73 ES included a full review of relevant
planning policy and considered the s.73
Application against this. This review is not
required under the EIA Regulations and given
that the Scheme has planning permission it is not
appropriate to re-consider the detailed proposals
in this way. Since the s.73 ES was prepared,
however the following notable documents have
been published:
Revised Early Minor Alterations to the London
Plan, 2013;
Draft Further Alterations to the London Plan,
2014;
Supplementary Planning Guidance-
Sustainable Design and Construction, 2014;
and
NPPF Planning Practice Guidance, 2014.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 5: Phase 1A (North) Open Spaces – For Illustrative Purposes Only (only Central Brent
Riverside Park and Nature Park 5 in Phase 1A (North))
Figure 6: Plots 53 and 54 Proposal
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Table 2: Summary of Approach to ES Further Information Report
Chapter Title Approach and Content of the ES Further Information Report
Land Use Statement of Conformity
Land Use Planning Summarises new legislation, policy or guidance since the s.73 ES
Traffic and Transport Statement of Conformity with presentation of additional information on the latest transport
studies and model outputs
Socio-Economics Statement of Conformity
Noise and Vibration Further assessment in light of detailed design for Phase 1A (North) RMAs including
Temporary Bus Station and Bus Stops, and updated baseline monitoring
Townscape and Visual
Impact Assessment
Further assessment in light of detailed design for Phase 1A (North) RMAs including
Temporary Bus Station and Bus Stops, updated baseline photography and Accurate
Visual Representations (AVRs)
Ecology and Nature
Conservation
Further assessment in light of detailed design for Phase 1A (North) RMAs and
presentation of updated survey results (Phase 1 Habitat Survey and bat survey)
Water Resources and
Flood Risk
Statement of Conformity
Archaeology and
Cultural Heritage
Further assessment of detailed design with presentation of updated baseline information
and Written Scheme of Investigation for archaeology
Air Quality and Dust Further assessment in light of detailed design for Phase 1A (North) RMAs, updated
baseline monitoring and details of Temporary Bus Station and Bus Stops
Ground Contamination Statement of Conformity with summary of 2014 ground investigations and details of
Remediation Strategies prepared since the s.73 ES
Waste Statement of Conformity
Microclimate
- Wind
- Daylight,
Sunlight and
Overshadowing
Further assessment in light of detailed design for Phase 1A (North) RMAs and the
outcome of further modelling studies for wind and shading
TV, Radio and Mobile
Phone Reception
Statement of Conformity
Carbon Dioxide
Emissions
Statement of Conformity
Intermediate Years
Assessment
Statement of Conformity
Additional assessment summary included for the Temporary Bus Station and Bus Stops
during a typical year of operation
Cumulative Effects Further assessment and commentary for particular topics in light of the an updated
cumulative scheme list
Summary of Residual
Effects and Mitigation
Update in accordance with potential new or different significant effects identified in the
ES technical chapters
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Land Use
The existing land uses within and surrounding the
Site were reported in the s.73 ES. These have
been reviewed and are deemed to remain valid
as there has been no significant change in the
land use from that reported in the s.73 ES.
Land Use Planning
The s.73 ES included a full review of relevant
planning policy and considered the s.73
Application against this. This review is not
required under the EIA Regulations and given
that the Scheme has planning permission it is not
appropriate to re-consider the detailed proposals
in this way. Since the s.73 ES was prepared,
however the following notable documents have
been published:
Revised Early Minor Alterations to the London
Plan, 2013;
Draft Further Alterations to the London Plan,
2014;
Supplementary Planning Guidance-
Sustainable Design and Construction, 2014;
and
NPPF Planning Practice Guidance, 2014.
Traffic and Transport
Most major infrastructure elements within the
Consented Scheme will be delivered within
Phase 1A (North). Since the s.73 ES was
prepared, the detailed design of highway
improvements, bridges and other elements of the
Consented Scheme previously approved in
outline has been developed in consultation with
LBB and Transport for London (TfL). The s.73
Application was accompanied by a Consolidated
Transport Assessment (TA) which set out the
likely impacts of the Development on the highway
network, public transport, pedestrians and
cyclists.
The TA which accompanied the s.73 Application
was based on a traffic model known as the ‘BXC
- Transport Model’. Subsequent to the s.73
Application the Brent Cross Cricklewood Detailed
Design Model (‘BXC-DDM’) was produced to
inform the detailed highways design for the
Development for the purposes of informing the
technical approvals process for the highway
authorities’ functions. The BXC – DDM models
the Development as a whole and not specifically
impacts of Phase 1A (North) and the opportunity
has been taken to use output for the BXC – DDM
in relevant chapters.
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment.
Since the s.73 ES, further baseline data including
traffic counts on local roads have been obtained
in 2013 to inform the detailed design, although
these are not considered to affect the outcome of
the TA. A Reserved Matters Transport Report has
been prepared to accompany the Phase 1A
(North) RMAs which sets out the baseline traffic,
transport and access conditions in the areas
affected by this phase of the Development.
In terms of construction traffic, the s.73 ES and
Consolidated TA, a Construction Impact
Assessment Addendum (CIA), and Indicative
Construction Programme which accompanied the
s.73 Application formed the basis of the
assessment of impacts. The likely construction
phasing, routes, road closures and estimates of
construction traffic flows presented in these
documents remain unchanged from that included
in the s.73 Application. As such, construction
traffic impacts presented in the TA and s.73 are
considered to remain valid.
In line with the 2014 Permission the Applicant has
submitted a feasibility study on the use of a
Construction Consolidation Centre (CCC) which
is a distribution facility through which material
deliveries are channeled to construction sites to
improve overall resource efficiency. The
construction traffic impacts of the CCC are not
considered in this Report as the final option has
not yet been confirmed. In terms of construction
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
traffic the s.73 ES presented a worst-case since
it did not assume a CCC was in place and use of
a CCC can reduce road and freight traffic
significantly during the construction period. In
light of the CIA Addendum and Consolidated TA
still remaining valid and applicable to the Phase
1A (North) RMAs, with no additional information
on construction traffic or transport related
impacts, the conclusions of the s.73 ES with
regards to construction traffic remain valid.
Further construction design and planning will be
undertaken prior to the start of construction works
for Phase 1A (North) which will provide further
information on construction, notably within a
CTMP and Construction Worker Travel Plan.
With the temporary relocation of the bus station
and the provision of additional passenger
facilities at Plot 113, the local routing of services
will change which will have some impact on
journey times. There will be some disruption as a
result of these temporary facilities although this
will only be for a period of four years and the
impact on local residents and visitors is
considered to be negligible.
The Consolidated TA which accompanied the
s.73 Application provided detailed analysis of the
impact of the Development on traffic and junction
capacity based on the BXC-Transport Model.
Further analysis of junctions has been
undertaken using the BXC-DDM which has
resulted in some design adjustments to junctions.
Overall however, the BXC-DDM modelling shows
that local congestion predicted in 2021 and 2031
with the Development in place, particularly the
evening peak hour and Saturday, is consistent
with the findings of the BXC-Transport Model.
The Phase 1A (North) RMAs include a number of
public transport improvements including
replacement bus stops, new bus stops (four), a
new bus stand and new bus lanes. This will be a
beneficial impact as identified in the s.73 ES.
Phase 1A (North) RMAs will not result in any
direct impacts to rail or London Underground
infrastructure and are therefore are not
considered further in the ES Further Information
Report. The s.73 ES and TA remain valid in
relation to rail and London Underground.
Extensive facilities have been designed into
Phase 1A (North) to provide safe and convenient
routes for pedestrian and cyclists as well as cycle
storage. The impacts on pedestrians and cycles
therefore remain beneficial as described in the
s.73 ES and Consolidated TA.
The traffic and transport demands of the
Development (taking into account the details of
Phase 1A (North)) will be accommodated on the
highway, public transport, pedestrian and cycle
networks through the provision of appropriate
new junction and access arrangements, many of
which will be delivered as part of Phase 1A
(North). The s.73 ES identified a minor adverse
residual impact (i.e. the likely impact of the
Development, taking account of proposed
mitigation measures) associated with increased
traffic, which will include some congestion on the
highway network. Based on the findings of the
BXC-DDM traffic modelling and detailed design of
Phase 1A (North) this is considered to remain
valid. The Phase 1A (North) proposals will
however also deliver significant improvements to
facilities for pedestrians and cyclists, including
dedicated links, safe crossing locations and
increased accessibility to public transport
services / facilities, thereby helping to encourage
people to travel using more sustainable modes
than the car.
Socio-Economics
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The methodology and
significance criteria presented in the s.73 ES
Socio-Economic Chapter therefore remain valid.
Following a review of the baseline conditions
section of the s.73 ES it is deemed that this
remains valid for the purposes of decision
making, having been updated in 2013 with 2011
Census and other relevant data.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
The detailed designs of the residential units at
Plots 53 and 54, open spaces and other features
of Phase 1A (North) RMAs have been reviewed
to ensure the significant impacts of demolition
and disruption from temporary closure of open
spaces have been adequately assessed in the
s.73 ES. Additional commentary on these
elements have been included in the Report,
however no new or different significant impacts or
mitigation measures have been identified. The
detailed design of the Phase 1A (North) open
spaces in particular, will deliver significant
benefits for the local community through
improved sport and recreation areas, playspace
and landscaped open space. These areas
include the Clitterhouse Playing Fields
Improvements Part 1, Claremont Park and
Central Brent Riverside Park. Overall, the likely
significant socio-economic impacts identified in
the s.73 remain valid.
Noise and Vibration
Following a review of the s.73 ES and in light of
new industry best practice guidance for noise
assessments, further baseline noise monitoring,
traffic data available from the BXC-DDM and the
detailed design of Phase 1A (North) RMAs,
further environmental information has been
provided for noise and vibration impacts
associated with the completed Development.
Noise monitoring was undertaken on the Site in
Autumn 2014 to supplement survey results from
2013, with a focus on the areas affected by the
Phase 1A (North) works, including amenity areas,
Plots 53 and 54 and the Temporary Bus Station
and Bus Stops (Plots 114 and 113 respectively).
The Consented Scheme included a commitment
to delivery of a ‘low noise’ surface for the A406
North Circular and also a barrier to reduce noise
(an acoustic barrier) along the A406 to reduce
noise levels experienced by people walking along
the realigned River Brent (final details not yet
available). The Temporary Bus Station and Bus
Stops are assessed in the ES Further Information
Report since details of these were not available
in the s.73 ES.
The noise and vibration impacts from demolition
and construction works associated with Phase 1A
(North) in the s.73 ES are considered to remain
valid and no further environmental information is
provided. This is partly due to the fact that the
construction traffic data and Construction Impact
Assessment (CIA) Addendum remain valid.
A 2.5 metre high screen will be provided along the
boundary of Plot 113 to reduce noise emissions
from the temporary Bus Stops at the nearest
properties on Layfield Close. The impact of the
Temporary Bus Station and Bus Stops will be
negligible for the nearest properties on Layfield
Close and Brent Park Road (based on idling
times for buses of 20 and 60 seconds). No
significant vibration impacts are likely.
Vibration impacts remain valid as per the s.73 ES.
The assessment of impacts form the operational
(i.e. completed Development) has been updated
through noise modelling to ensure the findings
reflect the detailed designs now available, noise
monitoring and updated traffic data from the BXC
– DDM. The s.73 ES noise assessment was
based on the BXC Transport Model.
A 3-Dimensional noise model was created for the
Development including the detailed design of
Phase 1A (North) and the maximum building
heights of the 2014 Permission. New noise data
and traffic data from the BXC-DDM were then
applied to produce ‘noise contour plots’ which
graphically show the predicted noise levels with
and without the Development in 2031 (see Figure
7). Predicted noise levels from road traffic were
also calculated using best practice.
For the majority of the roads the change in noise
levels from Development related traffic will be
less than 1dB which will be negligible. Some
beneficial impacts ranging from minor to
substantial are predicted, mainly due to the
screening effect of new buildings within the
Development. Some minor adverse impacts are
predicted (Oaklands Road, Gladstone Park
Gardens, Tadworth Road, Waterloo Road, A5
(southbound from Geron Way), Geron Way
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
(roundabout link from A5 southbound). Where
moderate adverse impacts have been identified
(Roman Road, Geron Way, Link off Geron Way
Roundabout; and Link off Geron Way) these are
likely to be conservative as they are generally a
result of traffic speeds being below the predictive
accuracy of the calculation method (i.e. well
below 20 kilometers per hour). The moderate
adverse impacts are therefore likely to be
overestimated.
The detailed design of the housing been using
within Phase 1A (North), Plots 53 and 54, will be
require to incorporate measures to ensure
acceptable noise standards will be achieved.
Noise modelling confirms that the residential
buildings which face major roads (A406) and the
railway are likely to require mitigation. Other new
buildings may also require noise mitigation
measures although these will be addressed
through existing planning conditions.
An assessment of noise levels within open space
was undertaken which found suitable noise levels
at all open spaces except for around the
realigned River Brent and the Central Brent
Riverside Park, which is already exposed to high
levels of noise form the A406. A noise barrier
between the Riverside Park and the A406 will
help achieve more acceptable noise levels for
park users and no further mitigation measures
beyond those presented in the s.73 ES are
necessary.
Impacts from fixed plant and building services,
the CHP / energy centres and waste handling
facility are all deemed to remain negligible as
reported in the s.73 ES. All plant will be required
to meet certain design standards for noise, as per
existing planning conditions.
Noise from use of the football, Multi-Use Games
Areas and sports pitches at Clitterhouse Playing
Fields has been assessed. The usage is daytime
only with evening use when natural light allows,
as the sports areas are not floodlight. The
predicted noise levels at the nearest residential
properties are considered to be negligible with the
exception of the closest properties on Cotswold
Gardens and Prayle Grove where temporary
increases in the noise levels will be experienced
when the sports pitches are in use. This will be a
minor adverse impact (3 – 5 decibel increase).
Townscape and Visual Impact
Assessment
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The methodology and
significance criteria presented in the s.73 ES has
been reviewed and updated in line with best
practice guidance.
The assessment of landscape (now referred to as
‘townscape’ in the Report) and visual impacts in
the s.73 ES was based on 14 photographic
viewpoints. In order to assess whether any
significant impacts will arise from Phase 1A
(North) not already reported in the s.73 ES,
additional photographic viewpoints were taken in
2014 to capture the detailed proposals in the
context of the Consented Scheme, including the
Temporary Bus Station and Bus Stops. A 3D
model of the Development has been used to
prepare accurate visual representations of the
Phase 1A (North) proposals and a total of 25
viewpoints have been considered. Baseline
conditions presented in the s.73 ES have also
been updated as considered necessary.
Considering that the overall construction
programme and proposed construction methods
and locations remain as per that detailed in the
s.73 Application, the townscape and visual
impacts during construction set out in the s.73 ES
are considered to remain valid.
In addition to the construction impacts reported in
the s.73 ES, the Temporary Bus Station and Bus
Stops in Plots 114 and 113 respectively, have
been assessed for a four year duration. Details of
this facility were not available in the s.73
Application. Three viewpoints were taken from
nearby residential areas. The assessment found
that the temporary structures will not be visible
from public footpaths on nearby residential roads
and due to the screening by existing houses and
mature trees and the proposed acoustic screen at
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Plot 113. The visual impacts of the Temporary
Bus Station and Bus Stops will therefore be
negligible. The mitigation measures for
construction remain valid.
The assessment of the operational Development
has been updated with a focus on the detailed
design of Phase 1A (North). Updated townscape
impacts are provided for townscape character
areas TCA1: North Circular Corridor, TCA4: Brent
Terrace, TCA7: Clitterhouse Playing Fields,
TCA13: Claremont Way Public Open Spaces;
and the 25 viewpoints across the Site (see Figure
8). The impacts for Phase 1A (North) elements
will be highly localised with only four of the 20
townscape character areas being affected, three
with beneficial impacts and one (Brent Terrace)
experiencing a minor adverse impact at Plots 53
and 54 which will reduce to negligible once the
new hedge and vegetation is fully established. Of
the 25 viewpoints assessed only 10 will be
affected by the Phase 1A (North) RMAs. Seven
of these will have a beneficial impact whilst views
of Plots 53 and 54 from Brent Terrace will have a
moderate adverse impact including screening
from the new hedge. No additional mitigation has
been identified over and above that set out in the
s.73 ES and within planning conditions attached
to the 2014 Permission.
Ecology and Nature Conservation
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which effect the approach to or findings
of the assessment. The baseline information
presented in the s.73 ES has been reviewed and
it is considered in the most part to be valid. A
habitat survey was undertaken in Spring 2014
and additional bat surveys were undertaken in
Summer 2014 to update survey work presented
in the s.73 ES. The habitat survey confirmed
there had been no significant change since the
s.73 ES had been prepared. The bat survey
identified a roost of common pipistrelle bats in the
Clitterhouse Farm Buildings and a number of
trees with bat roost potential on the Site, primarily
within Clitterhouse Playing Fields. All other
protected species surveys presented in the s.73
ES were considered to remain valid.
The loss of a single bat roost at the Clitterhouse
Farm Buildings was identified in the s.73 ES as a
local adverse impact. These buildings will now be
retained within the Development and refurbished.
Whilst this will be beneficial in the longer term; a
minor adverse impact will arise due to
disturbance from the refurbishment works which
are likely to directly affect the bat roost present
there. The bat roost should now be replaced
within the refurbished Farm Building rather than
be provided for in adjacent retained trees (as
proposed in the s.73 ES). Further details will be
provided as part of a protected species licence
required for the work.
The assessment of construction ecology and
nature conservation impacts presented in the
s.73 ES is considered to remain valid taking into
account the detailed design of the Phase 1A
(North) RMAs and no significant ecological
impacts are identified in relation to the
construction or operation of the Temporary Bus
Station and Bus Stops.
Mitigation measures for construction impacts
identified in the s.73 ES are considered to remain
valid.
Impacts of the Development on the Brent
Reservoir Site of Special Scientific Interest (0.1
km west of the Site) remain not significant (as
reported in the s.73 ES) as the proposals for the
River Brent have not changed significantly from
those of the s.73 Application.
Habitats at Clitterhouse Playing Fields Site of
Local Interest for Nature Conservation (SLINC)
will be enhanced by the detailed design of the
Phase 1A (North) RMAs. The majority of mature
trees within the area of the Site affected by the
Phase 1A (North) RMAs will be retained,
especially within the Clitterhouse Playing Fields
SLINC (Appendix 2.1) eastern and southern
margins. As such, the impact on the Clitterhouse
Playing Fields SLINC will be minor beneficial in
the long-term rather than neutral as stated in the
s.73 ES.
Based on the detailed landscaping design for
Phase 1A (North) approximately 24.5 hectares of
open space will be created within this first phase
of the Development. The habitat to be provided
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
as part of Phase 1A (North) will be far more
diverse and beneficial to wildlife than the existing
habitats. There will be an overall increase in
public / open space for the Development as a
whole.
Detailed design of the landscaping has provided
further information, including bird and bat boxes
and native species planting at Clitterhouse
Playing Fields, the new Claremont Park, Living
Bridge, Central Brent Riverside Park and within
the landscaping at Plots 53 and 54. As such the
minor negative impacts identified in the s.73 ES
improve to minor beneficial in relation to ‘Habitat
Damage, Loss and Creation for Habitats outside
the River Corridor’.
Mitigation measures for operational impacts
identified in the s.73 ES have largely been
incorporated into the detailed design proposals,
therefore no new or different mitigation has been
identified.
Water Resources and Flood Risk
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The methodology and
significance criteria presented in the s.73 ES
Water Resources and Flood Risk Chapter
therefore remain valid. Since the s.73 ES was
prepared, the detailed designs for the works to
the River Brent have been developed in
consultation with the Environment Agency and
the detailed design of highway drainage and
surface water drainage from open spaces and
development Plots 53 and 54 has been further
developed.
The baseline conditions have been reviewed to
determine whether there have been any
significant changes since the s.73 ES was
prepared. This review included the results of the
groundwater sampling as part of a ground
investigation in 2014. The review indicated that
there have been no significant changes to the
water environment within the study area since the
s.73 ES.
A number of studies are progressing as part of
the detailed design and separate consent
process (Flood Defence Consent). These studies
are expected to be completed and submitted for
approval to the Environment Agency and LBB in
June 2015 although they will not give rise to
significant impacts which have not already been
identified in the s.73 ES. The studies being
undertaken will deal with more detailed matters
and provide more data.
An assessment of the impacts of highway runoff
on surface water has been undertaken to
determine whether there is an environmental risk
and if further mitigation measures are required. A
system of Sustainable Drainage Systems is
proposed to be incorporated within the highway
drainage network to intercept sediment, remove
contaminants and minimise
environmental/ecological risk. Taking into
account the proposed drainage system, there are
no changes to pollution and spill risk impacts
reported in the s.73 ES.
A shading study has been undertaken of the
River Brent and the structures that have the
potential to cause shading. The findings of this
study are that the realigned river will experience
shading where the bridges cross over the river.
However, the new landscape has been designed
to address this and the findings of the shading
study do not alter those of the s.73 ES which were
that no significant adverse impacts are expected.
In summary, no new or different impacts arising
from the Development have been identified in
respect of Water Resources and Flood Risk as a
result of the detailed design of the Phase 1A
(North) RMAs or Temporary Bus Station and Bus
Stops. No further mitigation has been identified
beyond that identified in the s.73 ES which will be
addressed by existing planning conditions
attached to the 2014 Permission. The s.73 ES
therefore remains valid.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 7: Noise Contour Plot for Daytime Noise ‘With Development’ Scenario in 2031
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 8: Views across Claremont Park, Brent Terrace and Clitterhouse Playing Fields
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Archaeology and Cultural Heritage
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. Since the s.73 ES was
prepared and in accordance with the 2014
Permission, proposals for further archaeological
investigation have been provided to and agreed
with the Greater London Archaeology Advisory
Service (GLAAS). In addition, a methodology for
investigation of those ground-intrusive works
identified for Phase 1A (North) has been
prepared (Phase 1A (North) Scheme of
Archaeological Investigation).
The Phase 1A (North) Scheme of Archaeological
Investigation reviewed all the data relevant to the
Phase 1A (North) RMAs presented in the s.73
ES, and included an up-to-date search of the
Greater London Historic Environment Records.
When the s.73 ES was prepared the significance
of impacts from the Development on heritage
assets was limited by the level of information
available at the outline stage. The updated
baseline as well as the Phase 1A (North) RMAs
detailed design, has allowed a quantified
assessment of the impacts on the heritage
resource to be undertaken. Mitigation measures
have also been refined. As a result, the
construction impacts presented in the s.73 ES
have been updated.
The heritage assets within the Site include the
Childs Hill Area of Special Archaeological
Significance (ASAS) designed by LBB. There is
also the potential for other archaeological
features including those in association with
Watling Street (a Roman Road), paleo-
environmental and pre-historic deposits relating
to the historic channel of the River Brent.
Clitterhouse Farm Buildings are considered to be
of local value.
Designated heritage features are shown on
Figure 9. The Grade II listed Brent Cross
Underground Station and Parade of Shops is
within the Site although the Phase 1A (North)
RMAs will not affect this or the nearby
Cricklewood Railway Terraces Conservation
Area.
The construction activity within Clitterhouse
Playing Fields is likely to have a permanent
impact of moderate to large adverse significance
on the designated Childs Hill Area of Special
Archaeological Significance (ASAS). This is
largely due to the undisturbed ground within the
Playing Fields which has the potential to contain
archaeology of value. A programme of ground
investigation has already been agreed with
GLAAS geophysical survey to better understand
this potential. Once, the results of the field
investigations are known the significance of the
residual impact may reduce.
An archaeological watching brief over ground
intrusive works will be undertaken at Watling
Street although slight adverse impacts will
remain.
The ground intrusive elements of the
Development will have a moderate adverse
significance on paleo-environmental remains
within the north of the Site with sampling of these
remains being undertaken. The impacts on pre-
historic deposits will range from moderate to large
adverse, should these be found to exist. With
mitigation in the form of a watching brief over
ground intrusive works the impact will be
moderate adverse.
Historical building recording will be undertaken of
the Clitterhouse Farm Buildings to inform the
details of the restoration process resulting in a
large beneficial impact.
No significant impacts are identified during the
operational phase of the Development.
Air Quality and Dust
Following a review of the s.73 ES and in light of
new guidance for air quality assessments, air
quality monitoring, traffic data available from the
BXC-DDM and the detailed design of Phase 1A
(North) RMAs, further environmental information
has been provided for air quality and dust
impacts.
The assessment of construction air quality and
dust has been updated to include the Temporary
Bus Station and Bus Stops at Plots 114 and 113
respectively to identify likely impacts on nearby
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
residents. It was also agreed with LBB that the
air quality assessment will be compliant with the
Design Manual for Roads and Bridges (DMRB)
methodology due to the highways infrastructure
involved in Phase 1A (North).
Baseline air quality monitoring (nitrogen dioxide)
was undertaken on the Site for a period of three
months between September and December 2014
to supplement the data reported in the s.73 ES
(14 monitoring locations). Overall, based on the
survey, estimated average exceed the annual
objective level set at the majority of the locations
(9 out of 14).
The construction air quality impacts remain valid
as per the s.73 ES as the construction traffic data
remains unchanged from that presented in the
CIA Addendum and the Consolidated TA of the
s.73 Application. The Temporary Bus Station and
Bus Stops impacts were predicted using air
quality modelling for the year 2019. There will be
no significant impact on nearby properties in
relation to particulates during the operation of
Temporary Bus Station and Bus Stops. For
nitrogen dioxide, there will be an increase in
annual average concentrations, with ‘large’
increases predicted at two properties on Brent
Park Road (No’s 136 and 140). This will represent
a moderate adverse impact. There will be a slight
adverse impact at a number of nearby properties
along Brent Park Road. The remaining
properties, notably on the western side of Brent
Park Road, and along Layfield Close, will not
experience any adverse effect. . Further
mitigation is however proposed such as limiting
bus idling times, encouraging green buses on
these routes and taking into account the acoustic
screen, the impacts are expected to be reduced
to a minor adverse.
The air quality assessment presented in the s.73
ES has been updated to incorporate the traffic
data from the BXC - DDM. Traffic data has been
provided for 2012 as the baseline year. A
computer model was created for the
Development taking into account the detailed
design of Phase 1A (North). The updated
baseline data (2012) and traffic data were applied
to the model predict pollutant emission
concentrations at nearby receptors (residents or
site visitors) with and without the Development in
2031.
The modelling results showed that there will be a
substantial adverse impact on nitrogen dioxide at
the junction of the A5 Cricklewood Broadway and
Cricklewood Lane, as well as moderate adverse
impacts locally along stretches of Cricklewood
Lane and Claremont Road and slight adverse
impacts at a number of residences along the main
A-Roads and a number of minor roads. The
majority of sensitive receptors will however
experience negligible impacts, whilst slight
beneficial impacts are also predicted at a number
of receptors. See Figure 10.
Measures to encourage non-car travel will be
implemented through the Framework Travel Plan
(FTP) for the Development. A draft FTP
accompanied the s.73 Application. The main
objectives of the FTP will be to reduce reliance on
the private car and encourage people to travel in
a more sustainable manner. Any reduction in
traffic flows through the implementation of the
FTP will further reduce predicted impacts on air
quality.
Air quality monitoring will be necessary at the
locations described above in line with planning
conditions attached to the 2014 Permission.
Where exceedances of the nitrogen dioxide
annual mean objective are confirmed, and can be
directly linked to the Development, mitigation
measures such as ventilation and filtration may
be required to ensure appropriate indoor air
quality.
The Phase 1A (North) RMAs do not include any
significant features of relevance to the
assessment of the energy centres, CHP, Waste
Handling Facility, odour and dust, or emissions
from rail movements. As such the s.73 ES is
considered to remain valid in respect of these
topics.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 9: Site Heritage Designations
Hatched area: Child’s Hill Area of Special Archaeological Significance
Green area: Paleo-environmental deposit potential
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 10: Nitrogen Dioxide Annual Average Concentrations ‘With Development’ in 2031
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Ground Contamination
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The methodology and
significance criteria presented in the s.73 ES
therefore remain valid.
The baseline information presented in the s.73
ES Ground Contamination Chapter has been
reviewed, taking into account the results of
ground investigations undertaken in 2014 and it
is confirmed that the s.73 ES remains valid with
regard to soil and groundwater quality and
ground-gas for the Phase 1A (North) area. There
have been no significant changes to the detailed
design from the outline parameters defined in the
s.73 ES. In respect of ground contamination, the
impacts identified in the s.73 therefore remain
valid.
An overarching Remediation Strategy and Site
Specific Remediation Strategies for Phase 1A
(North) have been prepared to discharge
Planning Conditions attached to the 2014
Permission. These documents set out how
contamination will be dealt with, based on the
findings of further investigation of the ground and
the detailed design. Measures to deal with
contamination and ground conditions are an
integral part of the Development and assuming
they are well implemented, the negligible impacts
identified in the s.73 ES from construction will
remain valid. Implementation of the remediation
strategies is not considered likely to give rise to
significant environmental impacts not already
identified in the s.73 ES.
Waste
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The methodology and
significance criteria presented in the s.73 ES
Waste Chapter therefore remain valid. The
baseline information presented in the s.73 ES has
been reviewed with reference to newly available
information on the North London Waste Plan
website and the 2014 ground investigation.
Waste from Plots 53 and 54 will be subject to
collection and recycling by LBB, whilst open
space ‘green waste’ will be collected by LBB and
composting will occur on Site for new residences
and parks where possible. No new or different
potential impacts, mitigation or residual impacts
arising from the Development have been
identified in respect of Waste, and thus the s.73
ES remains valid.
Microclimate (Wind)
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The wind baseline information
presented in the s.73 ES Microclimate Chapter
has been reviewed and its validity is confirmed.
An accurate scale model of the Phase 1A (North)
RMAs, including highways layout, bridges and
open spaces has been subject to testing in a wind
tunnel facility to predict the likely wind conditions
that will arise. The model was based on the
detailed design of Phase 1A (North) RMAs
together with the maximum height parameters for
buildings defined within the 2014 Permission to
identify potential wind impacts for pedestrians
using the spaces. The residential buildings
proposed at Plots 53 and 54 are below four
storeys in height and therefore are not considered
to require further assessment of wind speeds.
Test results show that wind conditions in some
areas of the Living Bridge (at the northern and
southern approach) are likely to be moderate
adverse due to downdraughts of wind from future
proposed tall buildings adjacent to the bridge.
The need for mitigation will be considered as part
of the design development of the adjacent
buildings, but could include localised soft
landscaping and building canopies. This will
create areas of the bridge that could be suitable
for longer periods of sitting, and therefore suitable
for outdoor seating such as cafes. Wind
conditions on the replacement Templehof Bridge
will be unsuitable for less abled pedestrians and
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
cyclists (a major adverse impact) if the adjacent
development plots are built to the maximum
height parameters permitted by the 2014
Permission. Mitigation cannot be determined
until the building heights of the future phases is
known, therefore appropriate measures will be
considered in the design development of the
adjacent phases.
With the introduction of the mitigation measures
into the future phases it is predicted that all Phase
1A (North) elements will be considered as
suitable, in terms of comfort and safety, for the
intended usage. The wind impacts associated
with Phase 1A (North) can therefore be
considered negligible.
Microclimate (Daylight, Sunlight and
Overshadowing)
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which have a material effect on the
approach to or findings of the assessment. The
daylight, sunlight and overshadowing baseline
information presented in the s.73 ES
Microclimate Chapter has been reviewed and
remains valid.
A study of the shading impacts of the bridges that
will cross the River Brent has been undertaken to
identify whether impacts will arise which were not
identified in the s.73 ES. The study was
undertaken using a 3-D model based on the
detailed design of the Phase 1A (North) RMAs
and the maximum height parameters of the rest
of the Consented Scheme. Results indicate that
the areas of the River Brent which will experience
lengthy periods of overshadowing are those
located directly beneath the bridge structures.
This is to be expected and has been accounted
for within the Central Brent Riverside Park
detailed design planting strategy. No significant
impacts are therefore expected.
A study has been undertaken of whether the
residential development at Plots 53 and 54 will
affect the amount of daylight and sunlight
received at neighbouring properties and whether
the buildings will shade the adjacent gardens.
The results indicate that the impact of the new
buildings on nearby properties and gardens will
be negligible.
No new or different impacts or mitigation
measures have therefore been identified in
respect of Daylight, Sunlight or Overshadowing.
TV, Radio and Mobile Phone Reception
There have been no significant changes to policy,
legislation or guidance since the s.73 ES was
prepared which affect the approach to or findings
of the assessment. The assessment
methodology and baseline information presented
in the s.73 ES has been reviewed and it is
deemed to remain valid and as such, no further
baseline study has been undertaken. The s.73
ES refers to construction of the Scheme starting
in 2011 and referred to 'digital TV switchover'
taking place in 2012. Digital switchover was
implemented in 2012.
The Phase 1A (North) RMAs include no
significant built structures deemed to be of a
scale which could impact TV, radio or mobile
phone reception. No new or different impacts or
mitigation measures have therefore been
identified in respect of TV, Radio and Mobile
Reception.
Carbon Dioxide Emissions
There have been no significant changes to
planning policy, legislation or guidance which
affect the approach to the carbon dioxide (CO2)
emissions assessment presented in the s.73 ES.
The s.73 ES chapter assessed whether the
change in CO2 emissions as a result of the
transport or energy use resulting from the
Consented Scheme were in accordance with the
policy requirements. It concluded that due to the
scale of the Consented Scheme there will be a
negative impact.
The Energy Strategy for the Scheme has been
revised since the s.73 ES. The s.73 Application
proposed a single energy centre that will be
fuelled by waste (Refused Derived Fuel) as the
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
preferred option for the Scheme. Further studies
conclude that refuse-derived fuel (the preferred
option in the s.73 ES) is not currently feasible or
viable and that natural gas is the favourable fuel.
There is now a preference for two energy centres
for the Site; one in the north as well as the original
proposal for one in the south of the Site. Detailed
information on these energy centres will come
forward in future phases and associated impacts
will be considered further at that stage.
The CO2 emission calculations and assessment
within the s.73 ES remain valid as they provided
conservative estimates. The overall negative
impact on CO2 emissions also therefore remains
valid.
A small-scale on-site gas-fired CHP will be
provided in the car park of Plot 53 to provide
energy for the residential units of both Plots 53
and 54. This could be joined in the future to a
Site-wide energy and heating system. The CO2
emissions from this plant will be negligible in the
context of the Development as a whole.
No new or different impacts or mitigation
measures have therefore been identified in
respect of carbon dioxide emissions, therefore all
of these remain as identified in the s.73 ES.
Intermediate Years Assessment
An intermediate years assessment was provided
in the s.73 ES which set out likely significant
impacts of the Scheme during the construction
period from commencement in 2016 to
completion in 2031. The s.73 ES Chapter
provides an assessment of the Consented
Scheme for three snapshots in time:
Quarter three of 2020 (nearing completion of
Phase 1 works);
Quarter two of 2023 (end of Phase 1 works
and ongoing construction of subsequent
phases); and
Quarter four of 2029 (nearing completion of
the Scheme, prior to new railway station
opening).
This Chapter has been reviewed and updated
where necessary to reflect the outcome of the
technical studies and detailed design of Phase 1A
(North) RMAs as well as the details of the
Temporary Bus Station and Bus Stops. The likely
impacts of the intermediate years remain valid as
reported within the s.73 ES with the exception of
archaeology impacts in 2020 which have
increased from negligible to moderate adverse,
and air quality in 2023 which has reduced from
moderate to minor adverse.
Cumulative Impacts
The cumulative schemes considered in the s.73
ES have been reviewed to consider development
schemes which have received planning
permission or which have been built out since the
cumulative assessment was presented in the
s.73 ES. The updated list of cumulative schemes
was agreed with LBB. See Figure 11.
The full list of cumulative schemes considered is
provided below with those previously considered
in the s.73 ES presented in bold:
West Hendon Regeneration (H/01054/13)
(under construction);
Plot 61, Edgware Road, Former Parcel
Force Depot (F/01932/11) (under
construction);
Beaufort Park, Former RAF East Camp,
Aerodrome Road (W00198AA/04) (under
construction);
Grahame Park Estate Regeneration,
Grahame Park Way (W01731JS/04).
Extension to the planning permission time
was sought in 2010 and granted
(H/0448/10) (under construction);
Former Colindale Hospital (H/00093/13);
British Library Newspapers, 130 Colindale
Avenue (H/05856/13);
Former Wickes, Mercedes Benz site,
Colindale, Brent (08/2823) (under
construction);
Homebase / Hydro House (H/05828/14);
Granville Road Estate: (F/04474/14);
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non-Technical Summary
N:\Projects\EED13492\101 & 102 RMA and Conditions\Reports\Working Drafts\12. Further Information Report -
ES\NTS\EED13492-101.R.0.2.2.ES Further Information Report Phase 1A (North) NTS.docx
Peel Centre (Ref: H/04753/14);
Hendon Road Football Club (Ref:
H/02747/14) (under construction);
Finchley Road/Platt’s Lane/Kiddepore Avenue
regeneration (Ref: 2013/0685/P and
2014/5416/P);
The Crest Boy’s Academy, Crest Road (Ref:
14/0326) (under construction);
Sarena House and Allied Manufacture, Grove
Park (Ref: 14/2930);
It should be noted that in granting permission for
any schemes that came after the 2010 planning
consent for the Brent Cross Cricklewood it is
reasonable to assume that the local planning
authorities will have had regard to the potential for
cumulative impacts from those subsequent
schemes in combination with the Development to
the extent considered necessary by the
authorities.
A review of the cumulative impact assessment
presented in the s.73 ES was undertaken with
consideration of the Phase 1A (North) RMA
design details and the new cumulative schemes.
The cumulative impacts reported in the s.73 ES
are deemed to remain valid with the addition of
some new impacts identified for Hendon Road
Football Club due to its proximity to the
Development and proposed overlap in
construction periods.
Summary of Residual Impacts and
Mitigation
For the majority of the technical assessments of
this ES Further Information Report the residual
impacts and mitigation remain consistent with the
s.73 ES, with the exception of the following
studies:
Archaeology and cultural heritage impacts
updated in light of site designations;
Ecology and nature conservation impacts
updated in light of detailed design resulting in
more beneficial impacts due to biodiversity
enhancements;
Townscape and visual impact assessment
updated based on the detailed design
resulting in moderate adverse impacts for
Plots 53 and 54 on Brent Terrace which will be
reduced through visual screening as the new
hedge establishes and matures to full height;
Noise modelling results identify minor adverse
impacts from road traffic noise and at some
amenity areas however both will be controlled
through noise barriers and building design in
future phases of the Development through
planning conditions;
Air quality modelling results identify moderate
to minor adverse impacts near Cricklewood
Lane and Claremont Road which will be
controlled through the application of the
Framework Transport Plan, ongoing air quality
monitoring to satisfy planning conditions and if
impacts persist mechanical ventilation would
be considered for nearby properties;
Temporary Bus Station and Bus Stops
assessment reports minor adverse impacts for
air quality with mitigation in place (restricted
idling times) but negligible noise impacts with
the application of a 2.5m high noise screen at
the bus stops;
Wind impacts updated for the detailed design
report moderate adverse impacts at the Living
Bridge for which mitigation such as canopies
to reduce the downdraught from tall buildings
in future phases and landscaping is proposed
which will reduce impacts to negligible.
Brent Cross Cricklewood – Phase 1A (North) RMAs
Volume 1: Environmental Statement Further Information Report
Non Technical Summary
Figure 11: Cumulative Scheme Locations