+ All Categories
Home > Documents > Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Date post: 26-Dec-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
204
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 December 17, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 Subject: Watts Bar Nuclear Plant (WBN) Unit 2 - Submittal of Pre-op Test Instruction The following approved WBN Unit 2 Pre-op Test Instruction (PTI) is enclosed: PTI NUMBER Rev. TITLE 2-PTI-063-06 0 Safety Injection System Check Valve Test If you have any questions, please contact Nick Welch at (423) 365-7820. Respectfully, Raymond A. Hruby, Jr. General Manager, Technical Services Watts Bar Unit 2 Enclosure SDOc3U
Transcript
Page 1: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000

December 17, 2012

U.S. Nuclear Regulatory CommissionATTN: Document Control DeskWashington, D.C. 20555-0001

Watts Bar Nuclear Plant, Unit 2NRC Docket No. 50-391

Subject: Watts Bar Nuclear Plant (WBN) Unit 2 - Submittal of Pre-op Test Instruction

The following approved WBN Unit 2 Pre-op Test Instruction (PTI) is enclosed:

PTI NUMBER Rev. TITLE

2-PTI-063-06 0 Safety Injection System Check Valve Test

If you have any questions, please contact Nick Welch at (423) 365-7820.

Respectfully,

Raymond A. Hruby, Jr.General Manager, Technical ServicesWatts Bar Unit 2

Enclosure

SDOc3U

Page 2: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

U.S. Nuclear Regulatory CommissionPage 2December 17, 2012

cc (Enclosure):

U. S. Nuclear Regulatory CommissionRegion IIMarquis One Tower245 Peachtree Center Ave., NE Suite 1200Atlanta, Georgia 30303-1257

NRC Resident Inspector Unit 2Watts Bar Nuclear Plant1260 Nuclear Plant RoadSpring City, Tennessee 37381

Page 3: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WATTS BAR NUCLEAR PLANT

UNIT 2 STARTUP

TITLE: Safety Injection System Check Valve Test

Instruction No: 2-PTI-063-06

Revision No: 0

PREPARED BY: Curt Evans DATE________PRINT NAME/ SIGNATURE

REVIEWED BY: Kurt McCormack DATE 6/ ((PRINT NAME/ SIGNATURE

INSTRUCTION APPROVAL

JTG MEETING NO: -

JTG CHAIRMAN: -DATE Il/z?/"

APPROVED BY: -L DATE (124/ -PRE RATIONAL STARTUP MANAGER

TEST RESULTS APPROVAL

JTG MEETING NO:

JTG CHAIRMAN: DATE

APPROVED BY: DATEPREOPERATIONAL STARTUP MANAGER

SMP-8.0, R4, Administration of Preoperational Test Instructions, Appendix B

Page 4: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 2 of 202

Revision Log

Revision Affectedor Change Effective Page

Number Date Numbers Description of Revision/Change

0000 ALL Initial Issue based on Unit 1 PTI-063-06I o IIr

Page 5: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 3 of 202

Table of Contents

1.0 INTRO DUCTION ................................................................................................... 4

1.1 Test Objectives ............................................................................................................. 4

1 .2 S c o p e ............................................ ................................................................................ 4

2.0 REFERENCES ..................................................................................................... 5

2.1 Perform ance References .......................................................................................... 5

2.2 Developmental References ...................................................................................... 5

3.0 PRECAUTIO NS AND NOTES .................................................................................. 7

4.0 PREREQ UISITE ACTIO NS .................................................................................... 10

4.1 Prelim inary Actions ..................................................................................................... 10

4.2 Special Tools, M&TE, Parts, and Supplies .............................................................. 13

4.3 Field Preparations ....................................................................................................... 14

4.4 Approvals and Notifications ................................................................................... 21

5.0 ACCEPTANCE CRITERIA ...................................................................................... 22

6.0 PERFO RMANCE ........................................................................................................ 25

6.1 Check Valve Flow Test at 1400 psig ± 20 psig ........................................................ 26

6.2 RCS Boundary Ck Valve Flow Test at NOP ................................... 46

6.3 RCS Boundary Valve Leakage Testing .................................................................. 53

7.0 POST-PERFO RMANCE ACTIVITIES ...................................................................... 193

8.0 RECO RDS .......................................................... ...................................................... 194

Appendix A: TEST PROCEDURES/INSTRUCTIONS REFERENCEREVIEW .................................................................................................. 195

Appendix B: TEM PO RA RY CO NDITIO N LOG ............................................................. 196

Appendix C: PERMANENT PLANT INSTRUMENTATION LOG .................................. 197

Appendix D: REACTOR BOUNDARY LEAKAGE LOG ............................................... 198

Appendix E: TOTAL REACTOR COOLANT BOUNDARY LEAKAGE ........................ 201

Page 6: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 4 of 202

Date

1.0 INTRODUCTION

1.1 Test Objectives

This test is being performed to ensure the Primary Safety Injection System toReactor Coolant System Loop Check Valves will perform their design function andhave acceptable leakage rates.

1.2 Scope

A. Verify the primary safety injection to reactor coolant loop check valves will openwith the Reactor Coolant System (RCS) at nominal RCS pressure.

B. Verify the Accumulator Outlet Check Valves will open with the Reactor CoolantSystem (RCS) at hot conditions.

C. Verify the primary safety injection to reactor coolant loop check valves will openwith the Reactor Coolant System (RCS) at normal operating pressure andtemperature. (CCP to supply opening pressure)

D. Verify acceptable leakage rate for Reactor Boundary Valves, (primary andsecondary), at normal RCS operating pressure and temperature.

E. Verify total Reactor Boundary Leakage, (primary and secondary), does notexceed Tech Spec requirements.

Page 7: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 5 of 202

Date

2.0 REFERENCES

2.1 Performance References

A. SMP-7.0, Control of Cleanness, Layup and Flushing

B. SMP-9.0, Conduct of Test

C. GOI-7, Generic Equipment Operating Guidelines

2.2 Developmental References

A. Unit 2 Final Safety Analysis Report - Amendment 109

1. FSAR Table 14.2-1, Sheets 22, 23, and 24, Safety Injection System TestSummary

2. FSAR Section 3.9.3.2, Pump and Valve Operability Assurance

3. FSAR Section 5.2.7.4, Intersystem Leakage Detection

B. Drawings

1. Flow Diagrams

a. 2-47W809-1 R3, Flow Diagram Chemical and Volume Control System(Boron Recovery)

b. 2-47W809-3 RO, Flow Diagram Chemical and Volume Control Systemand Boron Recovery System

(1) DRA T93090722002 RO

c. 2-47W810-1 R5, Flow Diagram Residual Heat Removal System

d. 2-47W81 1-1 R4, Flow Diagram Safety Injection System

e. 2-47W600-124 RO, Electrical Instruments and Controls

(1) DRA 53580-603 RO

(2) DRA 53580-604 RO

Page 8: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 6 of 202

Date

2.2 Developmental References (continued)

C. Documents

1. System Description

a. 2N3-63-4001, Rev 1, System Description For Safety Injection System

2. Test Scoping Documents

a. 2-TSD-63-6, SIS - Integrated Check Valve Flow and Integrity Test

3. Scaling Setpoint Documents

a. SSD-2-FI-63-75, RO

b. SSD-2-FI-63-76, RO

4. System Operating Instruction

a. 2-SOI-63.01 RO, Safety Injection System

Page 9: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 7 of 202

Date

3.0 PRECAUTIONS AND NOTES

A. Standard precautions shall be followed for working around energized electricalequipment in accordance with TVA Safety Manual Procedure 1021.

B. Steps may be repeated if all components cannot be tested in a step. However,if the test has been exited, prerequisite steps must be re-verified and aChronological Test Log (CTL) entry made.

C. Discrepancies between component ID tags and the description in aprocedure/instruction do not require a Test Deficiency Notice, TDN, inaccordance with SMP-14.0, if the UNIDs match, exclusive of place-keepingzeros and train designators (e.g. 2-HS-31-468 vs. 2-HS-031-0468) and thenoun description is sufficient to identify the component. If the component labelneeds to be changed, a Tag Request Form (TR Card) should be processed inaccordance with TI-12.14. Make an entry in the CTL and continue testing.

D. All open problems are to be tracked by a corrective action document andentered on the appropriate system punch list.

E. Problems identified during the test shall be annotated on the Chronological TestLog (CTL) from SMP-9.0 including a description of the problem, the procedurestep when/where the problem was identified, corrective action steps taken toresolve the problem, and the number of the corrective action document, if onewas required.

F. Observe all Radiation Protection (RP) requirements when working in or nearcontaminated areas.

G. Exercise caution when obtaining high pressure leakage flow through the testlines.

H. When operating either Safety Injection Pump, observe a minimum run time of20 minutes, followed by a minimum cool down of 45 minutes to lessen thepossibility of bearing damage due to short duration periods of pump operation.

1. Section 6.1 will inject lower temperature water from the RWST into the ReactorVessel at approximately 5320F. Preparation for expedient data collection isnecessary to limit the thermal transient of the injection line nozzles to theReactor Coolant System.

Page 10: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page8 of 202

Date

3.0 PRECAUTIONS AND NOTES (continued)

J. Section 6.2 will inject lower temperature water into the Reactor Vessel atNormal operating pressure and temperature. Preparation for expedient datacollection is necessary to limit the thermal transient of the injection line nozzlesto the Reactor Coolant System.

K. Section 6.3 will require isolation and subsequent placing in service of FlowIndicators 2-FI-63-75, SIS LEAK TEST HEADER HI FLOW, and 2-FI-63-76, SISLEAK TEST HEADER LO FLOW. "Isolation" and "Placing the indicator inservice" is defined as follows:

1. Isolation of Flow Indicators 2-FI-63-75 and 2-FI-63-76 is defined as havingthe High Side and Low Side Valve closed with the equalizing valve open.

2. Placing the Flow Indicator in service is defined as having the equalizingvalve closed with the High Side and Low Side valve open for normalin-service use.

3. To protect the equipment, placing the flow indicator in service must bedone in a certain sequence.

a. Open low side valve.

b. Close equalizing valve.

c. Open high side valve.

4. To protect the equipment, isolating the flow indicator from service must bedone in a certain sequence.

a. Close high side valve.

b. Open equalizing valve.

c. Close low side valve.

5. These conditions will only be established after the indicators have beenfilled, vented, and placed in normal service.

L. Valve Logic Testing for the Safety Injection System Test Lines is performed in2-PTI-063-05.

M. Section 6.3 places SI Pump A in operation and on mini-flow for long durationwhile manipulating Test Line Valves. If operating conditions require SI Pump Ato be shut down, SI Pump B may be used and vice versa. Annotate anychanges in the Chronological Test Log.

Page 11: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 9 of 202

Date

3.0 PRECAUTIONS AND NOTES (continued)

N. Section 6.3 places SI Pump A in operation and on mini-flow for long durationwhile manipulating Test Line Valves. To protect the pumps, monitor thefollowing ICS points for pump in service.

1. T1050A SIS PUMP A-A MOTOR PH AWNDG

2. T1051A SIS PUMP A-A MOTOR PH B WNDG

3. T1052A SIS PUMP A-A MOTOR PH C WNDG

4. T1053A SIS PMP A-A MTR OUTBRD GUIDE BRG

5. T1054A SIS PMP A-A MTR INBRD GUIDE BRG

6. T1 055A SIS PUMP B-B MOTOR PH A WNDG

7. T1056A SIS PUMP B-B MOTOR PH B WNDG

8. T1057A SIS PUMP B-B MOTOR PH C WNDG

9. T1058A SIS PMP B-B MTR OUTBRD GUIDE BRG

10. T1059A SIS PMP B-B MTR INBRD GUIDE BRG

0. Section 6.3 background leakage flow should be determined after the selectedflow indicator has been placed in service and any leakage flow has stabilized.

Page 12: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 10 of 202

Date

4.0 PREREQUISITE ACTIONS

NOTE

Prerequisite steps may be performed in any order unless otherwise stated and should becompleted as close in time as practicable to the start of the instruction subsection to whichthey apply.

4.1 Preliminary Actions

[1] VERIFY the test/performance copy of this Preoperational TestInstruction (PTI) is the current revision including any changenotices and as needed, each test person assisting in this testhas the current revision including any change notices.

[2] OBTAIN copies of the applicable forms from the latest revisionof SMP-9.0, AND

ATTACH to this PTI for use during the performance of this PTI.

[3] ENSURE changes to the references listed on Appendix A,have been reviewed and determined NOT to adversely affectthe test performance.

[4] VERIFY current revisions and change paper for referenceddrawings has been reviewed and determined NOT toadversely affect the test performance, AND

ATTACH documentation of current drawing revision numbersand change paper that were reviewed to the data package.

[5] EVALUATE open items in Watts Bar Integrated TaskEquipment List (WITEL), AND

ENSURE they will NOT adversely affect the test performance.

A. Subsection 6.1

B. Subsection 6.2

C. Subsection 6.3

Page 13: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 11 of 202

Date

4.1 Preliminary Actions (continued)

[6] ENSURE required Component Testing has been completedprior to start of test.

A. Subsection 6.1

B. Subsection 6.2

C. Subsection 6.3

[7] ENSURE outstanding Design Change Notices (DCN's),Engineering Document Construction Releases (EDCR's) orTemporary Alterations (TA's) do NOT adversely impact testing,AND

ATTACH documentation of DCN's, EDCR's and TA's thatwere reviewed to the data package.

[8] ENSURE a review of outstanding Clearances has been

coordinated with Operations for impact to the testperformance, AND

RECORD in Appendix B, Temporary Condition Log if required.

[9] VERIFY System cleanness as required for the performance ofthis test has been completed in accordance with SMP-7.0.

[10] VERIFY System has been filled and vented in accordance with2-SOI-63.01.

[11] VERIFY plant instruments, listed on Appendix C, PermanentPlant Instrumentation Log, are placed in service and are withintheir calibration interval.

[12] VERIFY Measuring and Test Equipment (M&TE) required fortest performance has been, (as required) filled, vented, placedin service, and recorded on Measuring and Test Equipment(M&TE) Log.

A. Subsection 6.1

B. Subsection 6.2

Page 14: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

IWBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 12 of 202

Date

4.1 Preliminary Actions (continued)

[13] VERIFY Measuring and Test Equipment (M&TE) calibrationdue dates will support the completion of this test performance.

A. Subsection 6.1

B. Subsection 6.2

[14] ENSURE components contained within the boundaries of thistest are under the jurisdictional control of PreoperationalStartup Engineering (PSE) and/or Plant Operations.

[15] ENSURE components contained within the boundaries of thistest have been tested and proven functional for the purposesof this test.

[16] PERFORM a pretest walkdown on equipment to be tested toensure no conditions exist that will impact test performance.

[17] CONDUCT a pretest briefing with Test and Operationspersonnel in accordance with SMP-9.0.

[18] ENSURE that communications are available for areas wheretesting is to be conducted.

[19] REVIEW preventive maintenance for system/componentscovered by this test, AND

VERIFY no conditions exist that will impact test performance.

Page 15: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 13 of 202

Date

4.2 Special Tools, M&TE, Parts, and Supplies

[1] ENSURE the following M&TE is available:

A. Eight (8) Differential Pressure Gauges with maximumranges of 0-10 psid (± 1.0%) (Subsections 6.1 and 6.2).

B. Polysonics Ultrasonic Flow Meter DHT-P 40 FPS withminimum range of 0-10 gpm (± 2 gpm), or equivalent(Subsection 6.1).

Page 16: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 14 of 202

Date

4.3 Field Preparations

[1] Prerequisites for Subsection 6.1

[1.1] REMOVE Pipe Caps downstream of the followingvalves:

A. 2-RTV-63-393A, RT VLV TO FE-63-122

B. 2-RTV-63-394A, RT VLV TO FE-63-122

C. 2-RTV-63-409A, RT VLV TO FE-63-162

D. 2-RTV-63-410A, RT VLV TO FE-63-162

E. 2-RTV-63-395A, RT VLV TO FE-63-123

F. 2-RTV-63-396A, RT VLV TO FE-63-123

G. 2-RTV-63-387A, RT VLV TO FE-63-160

H. 2-RTV-63-388A, RT VLV TO FE-63-160

I. 2-RTV-63-397A, RT VLV TO FE-63-124

J. 2-RTV-63-398A, RT VLV TO FE-63-124

K. 2-RTV-63-389A, RT VLV TO FE-63-161

L. 2-RTV-63-390A, RT VLV TO FE-63-161

M. 2-RTV-63-399A, RT VLV TO FE-63-125

N. 2-RTV-63-400A, RT VLV TO FE-63-125

0. 2-RTV-63-391A, RT VLV TO FE-63-159

P. 2-RTV-63-392A, RT VLV TO FE-63-159

Page 17: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 15 of 202

Date

4.3 Field Preparations (continued)

[1.2] INSTALL Differential Pressure Gauges at the followinglocations:

A. 2-FE-63-122, SIS FLOW TO CL 1 FLOWELEMENT

M&TE Cal Due Date

M&TE

M&TE

M&TE

B. 2-FE-63-162, SIS PUMP OUT LP 1 HL

Cal Due Date

C. 2-FE-63-123, SIS FLOW TO CL 2 FLOWELEMENT

Cal Due Date

D. 2-FE-63-160, SIS PUMP OUT TO LP 2 HL

Cal Due Date

E. 2-FE-63-124, SIS FLOW TO CL 3 FLOWELEMENT

Cal Due Date

F. 2-FE-63-161, SIS PUMP OUT TO LP 3 HL

Cal Due Date

G. 2-FE-63-125, SIS FLOW TO CL 4 FLOWELEMENT

Cal Due Date

H. 2-FE-63-159, SIS PUMP OUT TO LP 4 HL

Cal Due Date

M&TE

M&TE

M&TE

M&TE

[1.3] INSTALL Ultrasonic Flow Meter on 1" Safety InjectionAccumulator Fill Line upstream of valve 2-FCV-63-23,SIS ACCUM FILL LINE ISOLATION VLV.

Page 18: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 16 of 202

Date

4.3 Field Preparations (continued)

[1.4] ENSURE the RCS is at normal hot no-load temperature,with pressure at 1380 to 1420 psig.

[1.5] ENSURE the Safety Injection System is aligned for coldleg injection and the test may be performed as stated in2-PTI-068-01.

[1.6] OPEN the following root valves to place the temporary

differential pressure gauges in service:

A. 2-RTV-63-393A, RT VLV TO FE-63-122

B. 2-RTV-63-394A, RT VLV TO FE-63-122

C. 2-RTV-63-319A, RT VLV TO FE-63-122

D. 2-RTV-63-320A, RT VLV TO FE-63-122

E. 2-RTV-63-409A, RT VLV TO FE-63-162

F. 2-RTV-63-410A, RT VLV TO FE-63-162

G. 2-RTV-63-31 1A, RT VLV TO FE-63-162

H. 2-RTV-63-312A, RT VLV TO FE-63-162

I. 2-RTV-63-395A, RT VLV TO FE-63-123

J. 2-RTV-63-396A, RT VLV TO FE-63-123

K. 2-RTV-63-321A, RT VLV TO FE-63-123

L. 2-RTV-63-322A, RT VLV TO FE-63-123

M. 2-RTV-63-387A, RT VLV TO FE-63-160

N. 2-RTV-63-388A, RT VLV.TO FE-63-160

0. 2-RTV-63-313A, RT VLV TO FE-63-160

P. 2-RTV-63-314A, RT VLV TO FE-63-160

Q. 2-RTV-63-397A, RT VLV TO FE-63-124

R. 2-RTV-63-398A, RT VLV TO FE-63-124

Page 19: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 17 of 202

Date

4.3 Field Preparations (continued)

S. 2-RTV-63-323A, RT VLV TO FE-63-124

T. 2-RTV-63-324A, RT VLV TO FE-63-124

U. 2-RTV-63-389A, RT VLV TO FE-63-161

V. 2-RTV-63-390A, RT VLV TO FE-63-161

W. 2-RTV-63-315A, RT VLV TO FE-63-161

X. 2-RTV-63-316A, RT VLV TO FE-63-161

Y. 2-RTV-63-399A, RT VLV TO FE-63-125

Z. 2-RTV-63-400A, RT VLV TO FE-63-125

AA. 2-RTV-63-325A. RT VLV TO FE-63-125

BB. 2-RTV-63-326A, RT VLV TO FE-63-125

CC. 2-RTV-63-391A, RT VLV TO FE-63-159

DD. 2-RTV-63-392A, RT VLV TO FE-63-159

EE. 2-RTV-63-317A, RT VLV TO FE-63-159

FF. 2-RTV-63-318A, RT VLV TO FE-63-159

Page 20: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 18 of 202

Date

4.3 Field Preparations (continued)

[2] Prerequisites for Subsection 6.2.

[2.1] REMOVE Pipe Caps downstream of the followingvalves:

A. 2-RTV-63-407A, RT VLV TO FE-63-33

B. 2-RTV-63-408A, RT VLV TO FE-63-33

C. 2-RTV-63-401A, RT VLV TO FE-63-27

D. 2-RTV-63-402A, RT VLV TO FE-63-27

E. 2-RTV-63-403A, RT VLV TO FE-63-29

F. 2-RTV-63-404A, RT VLV TO FE-63-29

G. 2-RTV-63-405A, RT VLV TO FE-63-31

H. 2-RTV-63-406A, RT VLV TO FE-63-31

[2.2] INSTALL Differential Pressure Gauges at the followinglocations:

A. 2-FE-63-33, SIS BORON INJ TANK TO CL RCSLOOP 1.

M&TE Cal Due Date

B. 2-FE-63-27, SIS BORON INJ TNK FLOW TO CLRCS LOOP 4.

M&TE Cal Due Date

C. 2-FE-63-29, SIS BORON INJ TNK FLOW TO CL

RCS LOOP 3.

M&TE Cal Due Date

D. 2-FE-63-31, SIS BORON INJ TNK FLOW TO CLRCS LOOP 2.

M&TE Cal Due Date

Page 21: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 19 of 202

Date

4.3 Field Preparations (continued)

[2.3] ENSURE that RCS is at normal hot no-load temperatureand normal operating pressure (2235 psig ± 20 psig) inaccordance with 2-PTI-068-01.

[2.4] ENSURE the CVCS System is operating in normalletdown operation.

[2.5] OPEN the following root valves to place the temporarydifferential pressure gauges in service:

A. 2-RTV-63-407A, RT VLV TO FE-63-33

B. 2-RTV-63-408A, RT VLV TO FE-63-33

C. 2-RTV-63-333A, RT VLV TO FE-63-33

D. 2-RTV-63-334A, RT VLV TO FE-63-33

E. 2-RTV-63-401A, RT VLV TO FE-63-27

F. 2-RTV-63-402A, RT VLV TO FE-63-27

G. 2-RTV-63-327A, RT VLV TO FE-63-27

H. 2-RTV-63-328A, RT VLV TO FE-63-27

I. 2-RTV-63-403A, RT VLV TO FE-63-29

J. 2-RTV-63-404A, RT VLV TO FE-63-29

K. 2-RTV-63-329A, RT VLV TO FE-63-29

L. 2-RTV-63-330A, RT VLV TO FE-63-29

M. 2-RTV-63-405A, RT VLV TO FE-63-31

N. 2-RTV-63-406A, RT VLV TO FE-63-31

0. 2-RTV-63-331A, RT VLV TO FE-63-31

P. 2-RTV-63-332A, RT VLV TO FE-63-31

Page 22: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 20 of 202

Date

4.3 Field Preparations (continued)

[3] Prerequisites for Subsection 6.3

[3.1] ENSURE that RCS is at normal hot no-load temperatureand normal operating pressure (2235 psig ± 20 psig) inaccordance with 2-PTI-068-01.

[3.2] ENSURE the Safety Injection System is aligned for coldleg injection and the test may be performed as stated in2-PTI-068-01.

Page 23: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 21 of 202

Date

4.4 Approvals and Notifications

[1] OBTAIN permission of the Preoperational Startup Manager tostart the test.

Preoperational Startup ManagerSignature

Date

[2] OBTAIN the Unit 2 Supervisor's (US/SRO) or Shift Manager's(SM) authorization.

US/SRO/SM Signature Date

Page 24: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 22 of 202

Date

5.0 ACCEPTANCE CRITERIA

A. The following check valves will open with the RCS at normal hot no-loadtemperature and an RCS pressure of 1400 psig ± 20 psig:

1. 2-CKV-63-560,

2. 2-CKV-63-561,

3. 2-CKV-63-562,

4. 2-CKV-63-563,

5. 2-CKV-63-641,

6. 2-CKV-63-559,

7. 2-CKV-63-644,

8. 2-CKV-63-558,

B. The following checktemperature and an

1. 2-CKV-63-622,

2. 2-CKV-63-623,

3. 2-CKV-63-624,

4. 2-CKV-63-625,

C. The following checktemperature and an

1. 2-CKV-63-586,

2. 2-CKV-63-587,

3. 2-CKV-63-588,

4. 2-CKV-63-589,

SIS LI CL INJ CHECK (Step 6.1[5]A)

SIS L2 CL INJ CHECK (Step 6.1[6]A)

SIS L3 CL INJ CHECK (Step 6.1[7]A)

SIS L4 CL INJ CHECK (Step 6.1[8]A)

RHR HX DISCH CHECK (Step 6.1[19]A)

SIS L2 HL INJ CHECK (Step 6.1[20]A)

RHR HX DISCH CHECK (Step 6.1[21]A)

SIS L4 HL INJ CHECK (Step 6.1[22]A)

valves will open with the RCS at normal hot no-loadRCS pressure of 1400 psig ± 20 psig:

ACCUM 1 OUT CHECK (Step 6.1[35]A)

ACCUM 2 OUT CHECK (Step 6.1[43]A)

ACCUM 3 OUT CHECK (Step 6.1[51 ]A)

ACCUM 4 OUT CHECK (Step 6.1[59]A)

valves will open with the RCS at normal hot no-loadRCS pressure of 2235 psig ± 20 psig:

BORON INJ CHECK CL Li (Step 6.2[7]A)

BORON INJ CHECK CL L2 (Step 6.2[8]A)

BORON INJ CHECK CL L3 (Step 6.2[9]A)

BORON INJ CHECK CL L4 (Step 6.2[10]A)

Page 25: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 23 of 202

Date

5.0 ACCEPTANCE CRITERIA (continued)

D. When tested with the RCS at normal operating pressure (2235 psig ± 20 psig),the following primary and secondary check valve leak rates do not exceed 0.5gpm per nominal inch of valve size to a maximum of 5.0 gpm:

1. 2-CKV-63-581, BORON INJ CHECK, < 1.5 gpm (Step 6.3.2[23])

2. 2-CKV-63-543, SIS LI HL INJ CHECK, <1.0 gpm (Step 6.3.3[19])

3. 2-CKV-63-640, RHR HX DISCH CHECK, <4.0 gpm (Step 6.3.4[17])

4. 2-CKV-63-545, SIS L3 HL INJ CHECK, <1.0 gpm (Step 6.3.5[17])

5. 2-CKV-63-643, RHR HX DISCH CHECK, <4.0 gpm (Step 6.3.6[17])

6. 2-CKV-63-549, SIS L4 HL INJ CHECK, <1.0 gpm (step 6.3.7[17])

7. 2-CKV-63-547, SIS L2 HL INJ CHECK, <1.0 gpm (Step 6.3.8[18])

8. 2-CKV-63-551, SIS LI CL INJ CHECK, <1.0 gpm (Step 6.3.9[20])

9. 2-CKV-63-633, RHR PUMP DISCH CHECK, < 3.0 gpm (Step 6.3.10[17])

10. 2-CKV-63-553, SIS L2 CL INJ CHECK, <1.0 gpm (Step 6.3.11[17])

11. 2-CKV-63-632, RHR PUMP DISCH CHECK, •3.0 gpm (Step 6.3.12[17])

12. 2-CKV-63-555, SIS L3 CL INJ CHECK, <1.0 gpm (step 6.3.13[17])

13. 2-CKV-63-634, RHR PUMP DISCH CHECK, • 3.0 gpm (step 6.3.14[17])

14. 2-CKV-63-557, SIS L4 CL INJ CHECK, _< 1.0 gpm (Step 6.3.15[17])

15. 2-CKV-63-635, RHR PUMP DISCH CHECK, •3.0 gpm (Step 6.3.16[17])

16. 2-FCV-74-2, RHR SYSTEM ISOLATION VALVE & 2-FCV-74-8, RHRSYSTEM ISOLATION BYPASS VALVE Total Combined Leakage, is< 5.0 gpm (Step 6.3.17[26])

17. 2-CKV-63-622, ACCUM 1 OUT CHECK, <5.0 gpm (Step 6.3.18[19])

18. 2-CKV-63-623, ACCUM 2 OUT CHECK, • 5.0 gpm (Step 6.3.19[17])

19. 2-CKV-63-624, ACCUM 3 OUT CHECK, < 5.0 gpm (Step 6.3.20[17])

20. 2-CKV-63-625, ACCUM 4 OUT CHECK, <5.0 gpm (Step 6.3.21[17])

Page 26: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000"

Page 24 of 202

Date

5.0 ACCEPTANCE CRITERIA (continued)

21. 2-CKV-63-586, BORON INJ CHECK CL L1, 2-CKV-63-587, BORON INJCHECK CL L2, 2-CKV-63-588, BORON INJ CHECK CL L3,2-CKV-63-589, BORON INJ CHECK CL L4, Total Combined Leakage, is< 0.75 gpm (Step 6.3.22[15])

22. 2-CKV-63-560, SIS Li CL INJ CHECK, < 5.0 gpm (Step 6.3.23[15])

23. 2-CKV-63-561, SIS L2 CL INJ CHECK, <5.0 gpm 6.3.24[14])

24. 2-CKV-63-562, SIS L3 CL INJ CHECK, <5.0 gpm (Step 6.3.25[14])

25. 2-CKV-63-563, SIS L4 CL INJ CHECK, <5.0 gpm (Step 6.3.26[14])

26. 2-FCV-74-1, RHR SYSTEM ISOLATION VALVE & 2-FCV-74-9, RHRSYSTEM ISOLATION BYPASS VALVE Total Combined Leakage, is< 5.0 gpm (Step 6.3.27[14])

27. 2-CKV-63-641, RHR HX DISCH CHECK, <3.0 gpm (Step 6.3.28[14])

28. 2-CKV-63-559, SIS L2 HL INJ CHECK, <3.0 gpm (Step 6.3.29[14])

29. 2-CKV-63-644, RHR HX DISCH CHECK, <3.0 gpm (Step 6.3.30[14])

30. 2-CKV-63-558, SIS L4 HL INJ CHECK, <3.0 gpm (Step 6.3.31[14])

Page 27: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 25 of 202

Date

6.0 PERFORMANCE

The subsections of this test shall be performed per the flow diagram below.

Page 28: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 26 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig

NOTE

The temporary AP gauges that are installed are for obtaining qualitative data to provideindication that the associated check valves open.

[1] VERIFY all prerequisites listed in Section 4.0 for Subsection6.1 have been completed.

[2] VERIFY each of the following temporary differential pressuregauges reads 0 psid (± 0.10 psid):

A. Temporary AP gauge at 2-FE-63-122, SIS FLOW TO CL1 FLOW ELEMENT

B. Temporary AP gauge at 2-FE-63-123, SIS FLOW TO CL2 FLOW ELEMENT

C. Temporary AP gauge at 2-FE-63-124, SIS FLOW TO CL3 FLOW ELEMENT

D. Temporary AP gauge at 2-FE-63-125, SIS FLOW TO CL4 FLOW ELEMENT

CAUTION

Steps 6.1[4] thru 6.1[111] will inject RWST water into the Reactor Vessel. Close coordinationof test activities is necessary to limit the thermal transient on the injection line nozzles tothe Reactor Coolant System. Test data should be obtained as quickly as possible.

[3] NOTIFY Operations to adjust charging and letdown to balanceSI pump injection flow to maintain pressurizer level in anacceptable band.

Page 29: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 27 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[4] PLACE Hand Switch 2-HS-63-10 A, SI PMP A, to START,AND

VERIFY by light indication SAFETY INJECTION PMP 2A-A isRUNNING, AND

RECORD the start time of the SI Pump.

TIME

[5] RECORD the differential pressure across 2-FE-63-122, SISFLOW TO CL 1 FLOW ELEMENT.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-560, SIS LI CL INJCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-122, SIS FLOW TO CL 1 FLOWELEMENT, greater than 0.75 psig. (ACC. CRIT. 5.OA.1)

[6] RECORD the differential pressure across 2-FE-63-123, SIS

FLOW TO CL 2 FLOW ELEMENT.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-561, SIS L2 CL INJCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-123, SIS FLOW TO CL 2 FLOWELEMENT, greater than 0.75 psig. (ACC. CRIT. 5.OA.2)

Page 30: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 28 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[7] RECORD the differential pressure across 2-FE-63-124, SISFLOW TO CL 3 FLOW ELEMENT.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-562, SIS L3 CL INJCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-124, SIS FLOW TO CL 3 FLOWELEMENT, greater than 0.75 psig. (ACC. CRIT. 5.OA.3)

[8] RECORD the differential pressure across 2-FE-63-125, SISFLOW TO CL 4 FLOW ELEMENT.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-563, SIS L4 CL INJCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-125, SIS FLOW TO CL 4 FLOWELEMENT, greater than 0.75 psid. (ACC. CRIT. 5.OA.4)

[9] ENSURE 20 minutes have passed since the start of the SIPump noted in step 6.1[4] before proceeding to the next stepto ensure proper bearing lubrication.

[10] NOTIFY Operations to adjust charging and letdown to accountfor the loss of SI pump injection flow to maintain pressurizerlevel in an acceptable band.

[11] PLACE 2-HS-63-10A, SI PMP A, to PULL-TO-LOCK position,AND

VERIFY by light indication SAFETY INJECTION PMP 2A-A

STOPS, AND

RECORD the stop time of the SI Pump.

TIME

Page 31: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 29 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[12] VERIFY each of the following temporary differential pressuregauges reads 0 psid (± 0.10 psid):

A. Temporary AP gauge at 2-FE-63-162, SIS PUMP OUT LP1 HL

B. Temporary AP gauge at 2-FE-63-160, SIS PUMP OUTTO LP 2 HL

C. Temporary AP gauge at 2-FE-63-161, SIS PUMP OUTTO LP 3 HL

D. Temporary AP gauge at 2-FE-63-159, SIS PUMP OUTTO LP 4 HL

[13] PLACE 2-HS-63-22A, SI PMPS TO CL 1-2-3-4, to CLOSE,ANDVERIFY by light indication 2-FCV-63-22, SIS PUMP COLD

LEG INJ, CLOSES.

[14] PLACE 2-HS-63-156A, SI PMP A TO HL 1&3, to OPEN, AND

VERIFY by light indication 2-FCV-63-156, SIS PUMP OUTRCS LP 1&3 HL, OPENS.

[1.5] PLACE 2-HS-63-157A. SI PMP B TO HL 2&4, to OPEN, AND

VERIFY by light indication 2-FCV-63-157, SIS PUMP OUTRCS LP 2&4 H L, OPENS.

CAUTION

Steps 6.1[18] thru 6.1[25] will inject RWST Water into the Reactor Vessel. Closecoordination of test activities is necessary to limit the thermal transient on the injection linenozzles to the Reactor Coolant System. Test data should be obtained as quickly aspossible.

[16] ENSURE 45 minutes have passed since the stopping of the SIPump noted in step 6.1 [11] before proceeding to the next stepto ensure acceptable pump downtime before restart.

Page 32: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 30 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[17] NOTIFY Operations to adjust charging and letdown to balanceSI pump injection flow to maintain pressurizer level in anacceptable band.

[18] PLACE 2-HS-63-10A, SI PMP A, to START, AND

VERIFY by light indication SAFETY INJECTION PMP 2A-A isRUNNING, AND

RECORD the start time of the SI Pump.

TIME

[19] RECORD the differential pressure across 2-FE-63-162, SISPUMP OUT TO LP 1 HL.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-641, RHR HX DISCHCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-162, SIS PUMP OUT TO LP 1 HL,greater than 0.75 psid. (ACC. CRIT. 5.OA.5)

Page 33: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 31 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[20] RECORD the differential pressure across 2-FE-63-160, SiSPUMP OUT TO LP 2 HL.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-559, SIS L2 HL INJCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-160, SIS PUMP OUT TO LP 2 HL,greater than 0.75 psid. (ACC. CRIT. 5.OA.6)

[21] RECORD the differential pressure across 2-FE-63-161, SISPUMP OUT TO LP 3 HL.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-644, RHR HX DISCHCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-161, SIS PUMP OUT TO LP 3 HL,greater than 0.75 psid. (ACC. CRIT. 5.OA.7)

[22] RECORD the differential pressure across 2-FE-63-159, SISPUMP OUT TO LP 4 HL.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-558, SIS L4 HL INJCHECK, OPENS with RCS at 1400 psig (± 20 psig) by APacross 2-FE-63-159, SIS PUMP OUT TO LP 4 HL,greater than 0.75 psid. (ACC. CRIT. 5.OA.8)

[23] ENSURE 20 minutes have passed since the start of the SIPump noted in step 6.1[18] before proceeding to the next stepto ensure proper bearing lubrication.

[24] NOTIFY Operations to adjust charging and letdown to accountfor the loss of SI pump injection flow to maintain pressurizerlevel in an acceptable band.

Page 34: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 32 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[25] PLACE 2-HS-63-10A, SI PMP A, to PULL-TO-LOCK position,AND

VERIFY by light indication SAFETY INJECTION PMP 2A-A

STOPS, AND

RECORD the stop time of the SI Pump.

TIME

[26] PLACE 2-HS-63-156A, SI PMP A TO HL 1&3, to CLOSE,AND

VERIFY by light indication 2-FCV-63-156, SIS PUMP OUTRCS LP 1&3 HL, CLOSES.

[27] PLACE 2-HS-63-157A, SI PMP B TO HL 2&4, to CLOSE,AND

VERIFY by light indication 2-FCV-63-157, SIS PUMP OUTRCS LP 2&4 HL, CLOSES.

Page 35: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 33 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[28] PERFORM the following Valve Lineup:

A. VERIFY/CLOSE 2-FCV-63-118, SIS ACCUM TK 1 FLOWISOLATION VLV, AND

RECORD "as found" position. (2-HS-63-118A, CLACCUM 1 OUTLET)

As found position:

B. VERIFY/CLOSE 2-FCV-63-98, SIS ACCUM TK 2 FLOWISOLATION VLV, AND

RECORD "as found" position. (2-HS-63-98A, CL ACCUM2 OUTLET)

As found position:

C. VERIFY/CLOSE 2-FCV-63-80, SIS ACCUM TK 3 FLOWISOL VLV, AND

RECORD "as found" position. (2-HS-63-80A, CL ACCUM3 OUTLET)

As found position:

D. VERIFY/CLOSE 2-FCV-63-67, SIS ACCUM TK 4 FLOWISOLATION VLV, AND

RECORD "as found" position. (2-HS-63-67A, CL ACCUM4 OUTLET)

As found position:

E. CLOSE 2-ISV-63-601, SIS TEST LINE ISLN.

F. PLACE 2-HS-63-23, CLA FILL FROM SI PMPS, toOPEN. _

G. VERIFY 2-FCV-63-23, SIS ACCUM FILL LINEISOLATION VLV, is OPEN by light indication.

H. PLACE 2-HS-63-71A, CKV TEST LINE TO HUT, toOPEN.

1. VERIFY 2-FCV-63-71, SIS CHECK VLV LEAKISOLATION, is OPEN by light indication.

Page 36: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 34 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

J. DEPRESS 2-HS-63-187, TEST LINE ISOL, at HandSwitch Panel 2-XS-63-100, to OPEN 2-FCV-63-187, RHRSUPPLY TEST LINE.

K. VERIFY 2-FCV-63-187, RHR SUPPLY TEST LINE,OPENS by light indication.

NOTES

1) The following steps will place the SI Pump on mini-flow for long duration whilemanipulating Test Line Valves for Accumulator Check Valve Testing.

2) If operating conditions require SI Pump A to be shut down, SI Pump B may be used,and vice versa. Ensure that the outlet pressure is monitored for the appropriate pumpdischarge. Annotate any changes in the Test Log.

[29] ENSURE 45 minutes have passed since the stopping of the SIPump noted in step 6.1[25] before proceeding to the next stepto ensure acceptable pump downtime before restart.

[30] PLACE 2-HS-63-10A, SI PMP A, to START, AND

VERIFY by light indication SAFETY INJECTION PMP 2A-A isRUNNING, AND

RECORD the start time of the SI Pump.

TIME

NOTE

The Ultrasonic Flow Meter that is installed is for obtaining qualitative data to provideindication that the associated check valves open.

[31] VERIFY the Ultrasonic Flow Meter installed on the 1"Accumulator Fill Line indicates 0 gpm. (± 2.0 gpm).

Page 37: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 35 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

CAUTION

The following step will begin injecting RWST water into the Reactor Vessel. Closecoordination of test activities is necessary to limit the thermal transient on the injection linenozzles to the Reactor Coolant system. Test data should be obtained as quickly aspossible.

[32] NOTIFY Operations to adjust charging and letdown to balanceSl pump injection flow to maintain pressurizer level in anacceptable band.

[33] DEPRESS Hand Switch 2-HS-63-116, CL ACCUM 1, at2-XS-63-1 00, CKV LEAK TEST, on 2-M-6, to OPEN2-FCV-63-116, SIS ACCUM TK 1 CHECK VLV LEAK TEST.

[34] VERIFY 2-FCV-63-116, SIS ACCUM TK 1 CHECK VLV LEAK

TEST, OPENS by light indication.

[35] RECORD the flow as observed on Ultrasonic Flow Meter.

GPM (greater than 5.0 GPM)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-622, ACCUM 1 OUTCHECK, OPENS with RCS at normal hot no-loadtemperature and an RCS pressure of 1400 psig ± 20 psigby flow on Ultrasonic Flow Meter greater than 5.0 gpm.(ACC. CRIT. 5.0B.1)

[36] NOTIFY Operations to adjust charging and letdown to accountfor the loss of Sl pump injection flow to maintain pressurizerlevel in an acceptable band.

[37] DEPRESS Hand Switch 2-HS-63-116, CL ACCUM 1, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-116, SISACCUM TK 1 CHECK VLV LEAK TEST.

[38] VERIFY 2-FCV-63-116, SIS ACCUM TK 1 CHECK VLV LEAKTEST, CLOSES by light indication.

[39] VERIFY the Ultrasonic Flow Meter installed on the 1"Accumulator Fill Line indicates 0 gpm (± 2.0 gpm).

Page 38: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 36 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

CAUTION

The following step will begin injecting RWST water into the Reactor Vessel. Closecoordination of test activities is necessary to limit the thermal transient on the injection linenozzles to the Reactor Coolant System. Test data should be obtained as quickly aspossible.

[40] NOTIFY Operations to adjust charging and letdown to balanceSI pump injection flow to maintain pressurizer level in anacceptable band.

[41] DEPRESS Hand Switch 2-HS-63-96, CL ACCUM 2, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-96, SISACCUM TK 2 CHECK VLV LEAK TEST.

[42] VERIFY 2-FCV-63-96, SIS ACCUM TK 2 CHECK VLV LEAK

TEST, OPENS by light indication.

[43] RECORD the flow as observed on Ultrasonic Flow Meter.

GPM (greater than 5.0 GPM)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-623, ACCUM 2 OUTCHECK, OPENS with RCS at normal hot no-loadtemperature and an RCS pressure of 1400 psig ± 20 psigby flow on Ultrasonic Flow Meter greater than 5.0 gpm.(ACC. CRIT. 5.0B.2)

[44] NOTIFY Operations to adjust charging and letdown to accountfor the loss of SI pump injection flow to maintain pressurizerlevel in an acceptable band.

[45] DEPRESS 2-HS-63-96, CL ACCUM 2, at 2-XS-63-100, CKVLEAK TEST, to CLOSE 2-FCV-63-96, SIS ACCUM TK 2CHECK VLV LEAK TEST.

[46] VERIFY 2-FCV-63-96, SIS ACCUM TK 2 CHECK VLV LEAKTEST, CLOSES by light indication.

[47] VERIFY the Ultrasonic Flow Meter installed on the 1"Accumulator Fill Line indicates 0 gpm (± 2.0 gpm).

Page 39: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 37 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

CAUTION

The following step will begin injecting RWST water into the Reactor Vessel. Closecoordination of test activities is necessary to limit the thermal transient on the injection linenozzles to the Reactor Coolant System. Test data should be obtained as quickly aspossible.

[48] NOTIFY Operations to adjust charging and letdown to balanceSI pump injection flow to maintain pressurizer level in anacceptable band.

[49] DEPRESS Hand Switch 2-HS-63-78, CL ACCUM 3, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-78, SISACCUM TK 3 CHECK VLV LEAK TEST.

[50] VERIFY 2-FCV-63-78, SIS ACCUM TK 3 CHECK VLV LEAKTEST, OPENS by light indication.

[51] RECORD the flow as observed on Ultrasonic Flow Meter.

GPM (greater than 5.0 GPM)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-624, ACCUM 3 OUTCHECK, OPENS with RCS at normal hot no-loadtemperature and an RCS pressure of 1400 psig ± 20 psigby flow on Ultrasonic Flow Meter greater than 5.0 gpm.(ACC. CRIT. 5.0B.3)

[52] NOTIFY Operations to adjust charging and letdown to accountfor the loss of SI pump injection flow to maintain pressurizerlevel in an acceptable band.

[53] DEPRESS 2-HS-63-78, CL ACCUM 3, at 2-XS-63-100, CKVLEAK TEST, to CLOSE 2-FCV-63-78, SIS ACCUM TK 3CHECK VLV LEAK TEST.

[54] VERIFY 2-FCV-63-78, SIS ACCUM TK 3 CHECK VLV LEAKTEST, CLOSES by light indication.

Page 40: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 38 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[55] VERIFY the Ultrasonic Flow Meter installed on the 1"Accumulator Fill Line indicates 0 gpm (± 2.0 gpm).

CAUTION

The following step will begin injecting RWST water into the Reactor Vessel. Closecoordination of test activities is necessary to limit the thermal transient on the injection linenozzles to the Reactor Coolant System. Test data should be obtained as quickly aspossible.

[56] NOTIFY Operations to adjust charging and letdown to balanceSI pump injection flow to maintain pressurizer level in anacceptable band.

[57] DEPRESS Hand Switch 2-HS-63-68, CL ACCUM 4, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-68, SISACCUM TK 4 CHECK VLV LEAK TEST.

[58] VERIFY 2-FCV-63-68, SIS ACCUM TK 4 CHECK VLV LEAK

TEST, OPENS by light indication.

[59] RECORD the flow as observed on Ultrasonic Flow Meter.

GPM (greater than 5.0 GPM)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-625, ACCUM 4 OUTCHECK, OPENS with RCS at normal hot no-loadtemperature and an RCS pressure of 1400 psig ± 20 psigby flow on Ultrasonic Flow Meter greater than 5.0 gpm.(ACC. CRIT. 5.0B.4)

[60] NOTIFY Operations to adjust charging and letdown to accountfor the loss of SI pump injection flow to maintain pressurizerlevel in an acceptable band.

[61] DEPRESS 2-HS-63-68, CL ACCUM 4, at 2-XS-63-1 00, CKVLEAK TEST, to CLOSE 2-FCV-63-68, SIS ACCUM TK 4CHECK VLV LEAK TEST.

Page 41: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 39 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[62] VERIFY 2-FCV-63-68, SiS ACCUM TK 4 CHECK VLV LEAKTEST, CLOSES by light indication.

[63] ENSURE 20 minutes have passed since the start of the SIPump noted in step 6.1 [30] before proceeding to the next stepto ensure proper bearing lubrication.

[64] PLACE Hand Switch 2-HS-63-10A, SI PMP A, toPULL-TO-LOCK position.

[65] VERIFY by light indication SI Pump STOPS.

[66] PERFORM the following Valve Lineup:

A. PLACE Hand Switch 2-HS-63-23, CLA FILL FROM SIPMPS, to CLOSE, AND

VERIFY 2-FCV-63-23, SIS ACCUM FILL LINEISOLATION VLV, is CLOSED by light indication.

B. PLACE 2-HS-63-71A, CKV TEST LINE TO HUT, toCLOSE, AND

VERIFY 2-FCV-63-71, SIS CHECK VLV LEAK TESTISOLATION, is CLOSED by light indication.

C. DEPRESS 2-HS-63-187, TEST LINE ISOL, at HandSwitch Panel 2-XS-63-1 00, to CLOSE 2-FCV-63-187,RHR SUPPLY TEST LINE, AND

VERIFY 2-FCV-63-187, RHR SUPPLY TEST LINE,CLOSES by light indication.

D. OPEN 2-ISV-63-601, SIS TEST LINE ISLN.

E. VERIFY/PLACE 2-FCV-63-118, SIS ACCUM TK 1 FLOWISOLATION VLV, to the "as found" position as recorded inStep 6.1[28]A.

6.1[28]A As Found Position:

F. VERIFY/PLACE 2-FCV-63-98, SIS ACCUM TK 2 FLOWISOLATION VLV, to the "as found" position as recorded inStep 6.1[28]B.

6.1[28]B As Found Position:

Page 42: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 40 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

G. VERIFY/PLACE 2-FCV-63-80, SIS ACCUM TK 3 FLOWISOLATION VLV, to the "as found" position as recorded inStep 6.1[28]C.

6.1[28]C As Found Position:

H. VERIFY/PLACE 2-FCV-63-67, SIS ACCUM TK 4 FLOWISOLATION VLV, to the "as found" position as recorded inStep 6.1[28]D.

6.1[28]D As Found Position:

I. PLACE 2-HS-63-22A, SI PMPS TO CL 1-2-3-4, to OPEN,AND

VERIFY by light indication 2-FCV-63-22, SIS PUMPCOLD LEG INJ, OPENS.

[67] PLACE 2-HS-63-10A, Sl PMP A, to A-AUTO.

Page 43: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 41 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[68] NOTIFY the US/SRO/SM to return the following valves to their normalposition per 2-SOI-63.01 ATT 1V:

A. 2-RTV-63-393A, RT VLV TO FE-63-122

B. 2-RTV-63-394A, RT VLV TO FE-63-122

C. 2-RTV-63-395A, RT VLV TO FE-63-123

D. 2-RTV-63-396A, RT VLV TO FE-63-123

E. 2-RTV-63-397A, RT VLV TO FE-63-124

F. 2-RTV-63-398A, RT VLV TO FE-63-124

G. 2-RTV-63-399A, RT VLV TO. FE-63-125

H. 2-RTV-63-400A, RT VLV TO FE-63-125

I. 2-RTV-63-409A, RT VLV TO FE-63-162

J. 2-RTV-63-410A, RT VLV TO FE-63-162

K. 2-RTV-63-387A, RT VLV TO FE-63-160

L. 2-RTV-63-388A, RT VLV TO FE-63-160

M. 2-RTV-63-389A, RT VLV TO FE-63-161

N. 2-RTV-63-390A, RT VLV TO FE-63-161

0. 2-RTV-63-391A, RT VLV TO FE-63-159

P. 2-RTV-63-392A, RT VLV TO FE-63-159

Page 44: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 42 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[69] REMOVE/VERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-122, SIS FLOW TO CL 1 FLOW ELEMENT.

1st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-393A, RTVLV TO FE-63-122.

1 st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-394A, RTVLV TO FE-63-122.

1 st

CV

[70] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-162, SIS PUMP OUT LP 1 HL.

1st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-409A, RTVLV TO FE-63-162.

1 st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-41 OA, RTVLV TO FE-63-162.

1 st

CV

Page 45: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 43 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[71] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-123, SIS FLOW TO CL 2 FLOW ELEMENT.

A. INSTALL Pipe Cap downstream of 2-RTV-63-395A, RTVLV TO FE-63-123.

1st

CV

1st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-396A, RTVLV TO FE-63-123.

1st

CV

[72] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-160, SIS PUMP OUT TO LP 2 HL.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-387A, RTVLV TO FE-63-160.

1st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-388A, RTVLV TO FE-63-160.

1st

CV

Page 46: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 44 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[73] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-124, SIS FLOW TO CL 3 FLOW ELEMENT.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-397A, RTVLV TO FE-63-124.

1 st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-398A, RTVLV TO FE-63-124.

1 st

CV

[74] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-161, SIS PUMP OUT TO LP 3 HL.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-389A, RTVLV TO FE-63-161.

1 st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-390A, RTVLV TO FE-63-161.

1st

CV

Page 47: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 45 of 202

Date

6.1 Check Valve Flow Test at 1400 psig ± 20 psig (continued)

[75] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-125, SIS FLOW TO CL 4 FLOW ELEMENT.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-399A, RTVLV TO FE-63-125.

1 st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-400A, RTVLV TO FE-63-125.

1st

CV

[76] REMOVENERIFY REMOVED the Differential Pressure Gaugeacross 2-FE-63-159, SIS PUMP OUT TO LP 4 HL.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-391A, RTVLV TO FE-63-159.

1 st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-392A, RTVLV TO FE-63-159.

1 st

CV

[77] REMOVE Ultrasonic Flow Meter from the 1" Accumulator FillLine.

1 st

CV

[78] NOTIFY Hot Functional Test Director that Subsection 6.1 iscomplete.

Page 48: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 46 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP

NOTE

The Temporary AP gauges that are installed are for obtaining qualitative data to provideindication that the associated check valves open.

[1] VERIFY all prerequisites listed in Section 4.0 for Subsection,6.2 have been completed.

[2] VERIFY each of the following temporary differential pressuregauges reads 0 psid (± 0.10 psid):

A. Temporary AP gauge at 2-FE-63-27, SIS BORON INJTNK FLOW TO CL RCS LOOP 4.

B. Temporary AP gauge at 2-FE-63-29, SIS BORON INJTNK FLOW TO CL RCS LOOP 3.

C. Temporary AP gauge at 2-FE-63-31, BORON INJ TNKFLOW TO CL RCS LOOP 2.

D. Temporary AP gauge at 2-FE-63-33, BORON INJ TANKTO CL RCS LOOP 1.

NOTE

If Operating Conditions require CCP-2A-A to be shutdown, CCP 2B-B may be used andvice versa. Annotate any changes in the Chronological Test Log.

[3] ENSURE that only one Centrifugal Charging Pump (CCP)2A-A or 2B-B is running, and indicate below:

Centrifugal Charging Pump Running

[4] ENSURE the VCT is at a minimum 50% level as observed on2-LI-62-129, VOL CONT TK LEVEL, on 2-M-6.

Page 49: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 47 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP (continued)

CAUTIONS

1) The following step may cause fluctuation or drop in seal injection flow to the ReactorCoolant Pumps.

2) Steps 6.2[6] thru 6.2[1 1] will inject VCT water into the reactor vessel. Closecoordination of test activities is necessary to limit the thermal transient on the injectionline nozzles to the Reactor Coolant System. Test data should be obtained as quicklyas possible.

3) The VCT level should not be allowed to drop below 20%. Low VCT level willautomatically shift CVCS suction to the RWST.

[5] NOTIFY Operations to adjust charging and letdown to balancecentrifugal charging pump injection flow to maintainpressurizer level in an acceptable band.

[6] MANUALLY THROTTLE 2-FCV-63-25, SIS BORON INJTANK SHUTOFF VLV, until differential pressure of greaterthan 0.75 psid is observed on all AP gauges from Step 6.2[2].

[7] RECORD the differential pressure across 2-FE-63-33,

SIS BORON INJ TANK FLOW TO CL RCS LOOP 1.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-586, BORON INJCHECK CL L1, OPENS with the RCS at normal hot no-load temperature and an RCS pressure of 2235 psig ± 20psig by AP across 2-FE-63-33, SIS BORON INJ TANK TOCL RCS LOOP 1, greater than 0.75 psid.(ACC. CRIT. 5.OC.1)

Page 50: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 48 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP (continued)

[8] RECORD the differential pressure across 2-FE-63-31, SISBORON INJ TANK FLOW TO CL RCS LOOP 2.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-587, BORON INJCHECK CL L2, OPENS with the RCS at normal hot no-load temperature and an RCS pressure of 2235 psig ± 20psig by AP across 2-FE-63-31, SIS BORON INJ TANK TOCL RCS LOOP 2, greater than 0.75 psid.(ACC. CRIT. 5.OC.2)

[9] RECORD the differential pressure across 2-FE-63-29, SISBORON INJ TANK FLOW TO CL RCS LOOP 3.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-588, BORON INJCHECK CL L3, OPENS with the RCS at normal hot no-load temperature and an RCS pressure of 2235 psig ± 20psig by AP across 2-FE-63-29, SIS BORON INJ TANK TOCL RCS LOOP 3, greater than 0.75 psid.(ACC. CRIT. 5.OC.3)

Page 51: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 49 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP (continued)

[10] RECORD the differential pressure across 2-FE-63-27, SISBORON INJ TANK FLOW TO CL RCS LOOP 4.

psid (greater than 0.75 psid)

M&TE Cal Due Date

A. VERIFY Check Valve 2-CKV-63-589, BORON INJCHECK CL L4, OPENS with the RCS at normal hot no-load temperature and an RCS pressure of 2235 psig ± 20psig by AP across 2-FE-63-27, SIS BORON INJ TANK TOCL RCS LOOP 4, greater than 0.75 psid.(ACC. CRIT. 5.OC.4)

CAUTION

The following step may cause fluctuation or increase in Seal Injection Flow to the ReactorCoolant Pumps.

[11] NOTIFY Operations to adjust charging and letdown to accountfor the loss of centrifugal charging pump injection flow tomaintain pressurizer level in an acceptable band.

Page 52: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 50 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP (continued)

[12] CLOSE 2-FCV-63-25, SIS BORON INJ TANK SHUTOFF VLV,and VERIFY, by light indication at 2-HS-63-25A. BIT OUTLET,valve is CLOSED.

A. NOTIFY US/SRO/SM to return the following orifice rootvalves to their normal position per 2-SOI-63.01 ATT 1V:

* 2-RTV-63-407A, RT VLV TO FE-63-33

* 2-RTV-63-408A RT VLV TO FE-63-33

* 2-RTV-63-401A, RT VLV TO FE-63-27

* 2-RTV-63-402A RT VLV TO FE-63-27

* 2-RTV-63-403A, RT VLV TO FE-63-29

" 2-RTV-63-404A RT VLV TO FE-63-29

* 2-RTV-63-405A, RT VLV TO FE-63-31

* 2-RTV-63-406A RT VLV TO FE-63-31

[13] REMOVE the Differential Pressure Gauge across 2-FE-63-33,SIS BORON INJ TANK TO CL RCS LOOP 1.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-407A, RTVLV TO FE-63-33.

1st

CV

B. INSTALL Pipe Cap downstream of 2-RTV-63-408A RTVLV TO FE-63-33.

1st

CV

Page 53: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 51 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP (continued)

[14] REMOVE the Differential Pressure Gauge across 2-FE-63-27,SIS BORON INJ TANK TO CL RCS LOOP 4.

1 st

CV

A. INSTALL Pipe Cap downstream of 2-RTV-63-401A, RTVLV TO FE-63-27.

1 st

Cv

B. INSTALL Pipe Cap downstream of 2-RTV-63-402A RTVLV TO FE-63-27.

1 st

Cv

[15] REMOVE the Differential Pressure Gauge across 2-FE-63-29,SIS BORON INJ TANK TO CL RCS LOOP 3.

1 st

Cv

A. INSTALL Pipe Cap downstream of 2-RTV-63-403A, RTVLV TO FE-63-29.

1 st

Cv

B. INSTALL Pipe Cap downstream of 2-RTV-63-404A RTVLV TO FE-63-29.

1 st

CV

Page 54: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 52 of 202

Date

6.2 RCS Boundary Ck Valve Flow Test at NOP (continued)

[16] REMOVE the Differential Pressure Gauge across 2-FE-63-31,SIS BORON INJ TANK TO CL RCS LOOP 2.

A. INSTALL Pipe Cap downstream of 2-RTV-63-405A, RTVLV TO FE-63-31.

1 st

Cv

1 st

Cv

B. INSTALL Pipe Cap downstream of 2-RTV-63-406A RTVLV TO FE-63-31.

1 st

CV

[17] NOTIFY Hot Functional Test Director that Subsection 6.2 iscomplete.

Page 55: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 53 of 202

Date

6.3 RCS Boundary Valve Leakage Testing

6.3.1 Backflow Leakage Test Prep

NOTE

Subsection 6.3 must be performed at normal operating pressure (2235 psig ± 20 psig) tomeet acceptance criteria. If at any point, RCS pressure falls out of range, the test is to besuspended until RCS pressure has been restored to normal operational range.

[1] VERIFY all prerequisites listed in Section 4.0 for Subsection

6.3 have been completed.

[2] VERIFY/OPEN valve 0-ISV-62-1080, HOLDUP TANK UNIT 2.

[3] VERIFYIOPEN valve 2-ISV-62-953, HOLDUP TK IN COLLHDR.

[4] PLACE Hand Switch 2-HS-63-71A, CKV TEST LINE TO HUT,to OPEN, AND

VERIFY 2-FCV-63-71, SIS CHECK VLV LEAK TESTISOLATION, is OPEN by light indication.

[5] PLACE Hand Switch 2-HS-63-84, CKV TEST LINE TO HUT,to OPEN, AND

VERIFY 2-FCV-63-84, SIS CHECK VLV LEAK TEST ISOL, isOPEN by light indication.

Page 56: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 54 of 202

Date

6.3.1 Backflow Leakage Test Prep (continued)

NOTES

1) The following steps will place a Safety Injection Pump on Mini-Flow for long durationwhile manipulating Test Line Valves.

2) If Operating Conditions require SI Pump A to be shut down, SI Pump B may be used,and vice versa. Ensure that the outlet pressure is monitored for the appropriate pumpdischarge. Annotate any changes in the Chronological Test Log.

[6] PLACE Hand Switch 2-HS-63-10A, SI PMP A, to START,AND

VERIFY by light indication that SAFETY INJECTION PUMP2A-A is RUNNING.

Page 57: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

IWBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 55 of 202

Date

6.3.2 Backflow Leakage of 2-CKV-63-581, BORON INJ CHECK

NOTE

The following valve manipulations will be performed from Hand Switch Panel 2-XS-63-1 00,CKV LEAK TEST, at 2-M-6.

[1] DEPRESS Hand Switch 2-HS-63-187, TEST LINE ISOL, toOPEN 2-FCV-63-187, RHR SUPPLY TEST LINE, AND

VERIFY valve OPENS by light indication.

[2] DEPRESS Hand Switch 2-HS-63-174, BIT OUTLET, to OPEN2-FCV-63-174, SIS TEST LINE CHECK VLV TEST, AND

VERIFY valve OPENS by light indication.

NOTES

1) Isolation of Flow Indicators 2-FI-63-75 and 2-FI-63-76 is defined as having the HighSide Valve closed with the equalizing valve open.

2) Placing the Flow Indicator in service is defined as having the equalizing valve closedwith the High Side valve open for normal in-service use.

[3] ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LO FLOW, atPanel 2-L-554 (713 A1 -V).

[4] ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HI FLOW, atPanel 2-L-554.

[5] DEPRESS Hand Switch 2-HS-63-121, Sl PMPS TO CL, at2-XS-63-100, to OPEN 2-FCV-63-121, SIS FLOW TO CLCHECK VLV TEST, AND

VERIFY valve OPENS by light indication.

Page 58: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 56 of 202

Date

6.3.2 Backflow Leakage of 2-CKV-63-581, BORON INJ CHECK(continued)

NOTES

1 ) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow. (Panel 2-L-554, A13-V, El.713)

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[6] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[7] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[8] ISOLATE the Flow Indicator used in the previous step.

[9] CALCULATE a corrected test line leakage by subtracting theM&TE error listed below for the flow instrument used in Step6.3.2[7], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.2[7] - M&TE Error

=_ GPM1 st

Cv

Page 59: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 57 of 202

Date

6.3.2 Backflow Leakage of 2-CKV-63-581, BORON INJ CHECK(continued)

NOTE

The following step will provide SI pressure for testing 2-CKV-63-581, BORON INJ CHECK.

[10] DEPRESS 2-HS-63-24A, CLA MAKEUP FRM BIT OUTLET, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-24, SISACCUM FILL LINE ISOLATION VLV, and

VERIFY valve OPENS by light indication.

[11] PLACE Flow Indicator(s) in service, as required, to determineTest Line leakage flow in SIS Test Line.

[12] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[13] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.2[12]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.2[12] + M&TE Error

+ : GPM1 st

CV

Page 60: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 58 of 202

Date

6.3.2 Backflow Leakage of 2-CKV-63-581, BORON INJ CHECK(continued)

[14] RECORD the test pressure indicated by 2-PI-63-150, SI PMPA DISCH PRESS, on 2-M-6.

Test Pressure psig

[15] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve CLOSES by light indication.

[16] DEPRESS Hand Switch 2-HS-63-24A, CLA MAKEUP FRMBIT OUTLET, at 2-XS-63-1 00, CKV LEAK TEST, to CLOSE2-FCV-63-24, SIS ACCUM FILL LINE ISOLATION VLV, AND

VERIFY valve CLOSES by light indication.

[17] DEPRESS Hand Switch 2-HS-63-174, BIT OUTLET, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-174, SISTEST LINE CHECK VLV TEST, AND

VERIFY valve CLOSES by light indication.

[18] DEPRESS Hand Switch 2-HS-63-187, TEST LINE ISOL, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-187,RHR SUPPLY TEST LINE, AND

VERIFY valve CLOSES by light indication.

[19] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[20] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 61: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 59 of 202

Date

6.3.2 Backflow Leakage of 2-CKV-63-581, BORON INJ CHECK(continued)

[21] CALCULATE 2-CKV-63-581, BORON INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-581 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.2[13]

( )Step 6.3.2[9]

- ) --

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 62: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 60 of 202

Date

6.3.2 Backflow Leakage of 2-CKV-63-581, BORON INJ CHECK(continued)

[22] CALCULATE 2-CKV-63-581, BORON INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-581 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.2[21]

TEST PRESSURE = 6.3.2[14]

TEST LEAKAGEx V2235 + TEST PRESSURE =

x V2235 + =

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[23] VERIFY the leakage flow for 2-CKV-63-581, BORON INJCHECK, recorded in Step 6.3.2[22] is less than or equal to 1.5gpm. (ACC. CRIT. 5.0D.1)

[24] RECORD leakage flow from Step 6.3.2[22] on Appendix D,Reactor Boundary Leakage Log.

Page 63: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 61 of 202

Date

6.3.3 Backflow Leakage of 2-CKV-63-543, SIS LI HL INJ CHECK

NOTE

The following valve manipulations will be performed from Hand Switch Panel 2-XS-63-100,CKV LEAK TEST, at 2-M-6.

[1] DEPRESS Hand Switch 2-HS-63-117, SI PMPS TO CL 1, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-117, SISCL 1 CHECK VLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[2] DEPRESS Hand Switch 2-HS-63-188, TEST LINE ISOL, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-188, RHRSUPPLY TEST LINE, AND

VERIFY valve OPENS by light indication.

[3] DEPRESS Hand Switch 2-HS-63-21, TO HL 1&3, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-21, SISPUMP OUTLET TO SIS TEST LINE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[4] PLACE Flow Indicator(s) in service, as required, to determinebackground test line leakage flow in SIS Test Line.

Page 64: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 62 of 202

Date

6.3.3 Backflow Leakage of 2-CKV-63-543, SIS LI HL INJ CHECK(continued)

[5] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[6] ISOLATE the Flow Indicator used in the previous step.

[7] CALCULATE a corrected Test Line leakage by subtracting theM&TE error listed below for the flow instrument used in Step6.3.3[5], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.3[5] - M&TE Error

-_ = GPM1st

Cv

[8] DEPRESS 2-HS-63-163, SI-RHR TO HL 1 at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-163, RCS LP 1 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[9] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

Page 65: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 63 of 202

Date

6.3.3 Backflow Leakage of 2-CKV-63-543, SIS LI HL INJ CHECK(continued)

[10] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[11] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.3[10]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.3[10] + M&TE Error

- + = GPM1 st

Cv

[12] RECORD the test pressure indicated by 2-PI-63-150, SI PMPA DISCH PRESS.

Test Pressure psig

[13] DEPRESS Hand Switch 2-HS-63-163, SI-RHR TO HL 1, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-163,RCS LP 1 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[14] DEPRESS Hand Switch 2-HS-63-21, TO HL 1 & 3, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-21, SISPUMP OUTLET TO SIS TEST LINE, AND

VERIFY valve CLOSES by light indication.

Page 66: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 64 of 202

Date

6.3.3 Backflow Leakage of 2-CKV-63-543, SIS LI HL INJ CHECK(continued)

[15] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[16] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[17] CALCULATE 2-CKV-63-543, SIS LI HL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-543 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.3[1 1]

)Step 6.3.3[7]

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 67: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 65 of 202

Date

6.3.3 Backflow Leakage of 2-CKV-63-543, SIS LI HL INJ CHECK(continued)

[18] CALCULATE 2-CKV-63-543, SIS LI HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-543 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.3[17]

TEST PRESSURE = 6.3.3[12]

TEST LEAKAGEx V2235 + TEST PRESSURE =

xa/2235+ =

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[19] VERIFY the leakage flow for 2-CKV-63-543, SIS LI HL INJCHECK, recorded in Step 6.3.3[18] is less than or equal to 1.0gpm. (ACC. CRIT. 5.OD.2)

[20] RECORD leakage flow from Step 6.3.3[18] on Appendix D,Reactor Boundary Leakage Log.

Page 68: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 66 of 202

Date

6.3.4 Backflow Leakage of 2-CKV-63-640, RHR HX DISCH CHECK

[1] DEPRESS Hand Switch 2-HS-63-158, RHR TO HL, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-158, RHRFROM SIS SAMPLE, AND

VERIFY valve OPENS by light indication.

NOTES

1 ) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 69: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 67 of 202

Date

6.3.4 Backflow Leakage of 2-CKV-63-640, RHR HX DISCH CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.4[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.4[3] - M&TE Error

=_ GPM1st

CV

[6] DEPRESS 2-HS-63-163, SI-RHR TO HL 1 at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-163, RCS LP 1 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 70: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 68 of 202

Date

6.3.4 Backflow Leakage of 2-CKV-63-640, RHR HX DISCH CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.4[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.4[8] + M&TE Error

+ - GPM

1st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-163, SI-RHRTO HL 1, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-163,RCS LP 1 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-158, RHR TO HL, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-158,RHR RETURN FROM SIS SAMPLE, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 71: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 69 of 202

Date

6.3.4 Backflow Leakage of 2-CKV-63-640, RHR HX DISCH CHECK(continued)

[15] CALCULATE 2-CKV-63-640, RHR HX DISCH CHECK, backflowleakage at test pressure as follows:

2-CKV-63-640 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.4[9]

( )Step 6.3.4[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-640, RHR HX DISCH CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-640 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.4[15]

TEST PRESSURE = 6.3.4[10]

TEST LEAKAGEx V2235 + TEST PRESSURE

_xj2235+

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 72: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 70 of 202

Date

6.3.4 Backflow Leakage of 2-CKV-63-640, RHR HX DISCH CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-640, RHR HX DISCHCHECK, recorded in Step 6.3.4[16] is less than or equal to 4.0gpm. (ACC. CRIT. 5.0D.3)

[18] RECORD leakage flow from Step 6.3.4[16] on Appendix D,Reactor Boundary Leakage Log.

Page 73: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 71 of 202

Date

6.3.5 Backflow Leakage of 2-CKV-63-545, SIS L3 HL INJ CHECK

[1] DEPRESS Hand Switch 2-HS-63-21, TO HL 1&3, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-21, SISPUMP OUTLET TO SIS TEST LINE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 74: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 72 of 202

Date

6.3.5 Backflow Leakage of 2-CKV-63-545, SIS L3 HL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.5[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.5[3] - M&TE Error

-_ = GPM1st

Cv

[6] DEPRESS 2-HS-63-164, SI-RHR TO HL 3, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-164, RCS LP 3 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 75: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 73 of 202

Date

6.3.5 Backflow Leakage of 2-CKV-63-545, SIS L3 HL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.5[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.5[8] + M&TE Error

+ = GPM1st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-164, SI-RHR TO HL 3, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-164,RCS LP 3 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-21, TO HL 1 & 3, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-21, SISPUMP OUTLET TO SIS TEST LINE, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 76: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 74 of 202

Date

6.3.5 Backflow Leakage of 2-CKV-63-545, SIS L3 HL INJ CHECK(continued)

[15] CALCULATE 2-CKV-63-545, SIS L3 HL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-545 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.5[9]

( )Step 6.3.5[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-545, SIS L3 HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-545 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.5[15]

TEST PRESSURE = 6.3.5[10]

TEST LEAKAGEx V2235 +TEST PRESSURE =

x j2235+

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 77: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 75 of 202

Date

6.3.5 Backflow Leakage of 2-CKV-63-545, SIS L3 HL INJ CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-545, SiS L3 HL INJCHECK, recorded in Step 6.3.5[16] is less than or equal to 1.0gpm. (ACC. CRIT. 5.0D.4)

[18] RECORD leakage flow from Step 6.3.5[16] on Appendix D,Reactor Boundary Leakage Log.

Page 78: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 76 of 202

Date

6.3.6 Backflow Leakage of 2-CKV-63-643, RHR HX DISCH CHECK

[1] DEPRESS Hand Switch 2-HS-63-158, RHR TO HL, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-158, RHRFROM SIS SAMPLE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 79: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 77 of 202

Date

6.3.6 Backflow Leakage of 2-CKV-63-643, RHR HX DISCH CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.6[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.6[3] - M&TE Error

-_ _ GPM1st

Cv

NOTE

The following step will provide SI pressure for testing 2-CKV-63-643, RHR HX DISCHCHECK.

[6] DEPRESS 2-HS-63-164, SI-RHR TO HL 3 at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-164, RCS LP 3 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

Page 80: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 78 of 202

Date

6.3.6 Backflow Leakage of 2-CKV-63-643, RHR HX DISCH CHECK(continued)

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.6[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.6[8] + M&TE Error

+ = GPM1st

CV

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-164, SI-RHR TO HL 3, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-164,RCS LP 3 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-158, RHR TO HL, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-158,RHR RETURN FROM SIS SAMPLE, AND

VERIFY valve CLOSES by light indication.

Page 81: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 79 of 202

Date

6.3.6 Backflow Leakage of 2-CKV-63-643, RHR HX DISCH CHECK(continued)

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[15] CALCULATE 2-CKV-63-643, RHR HX DISCH CHECK, backflowleakage at test pressure as follows:

2-CKV-63-643 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.6[9]

( )Step 6.3.6[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 82: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 80 of 202

Date

6.3.6 Backflow Leakage of 2-CKV-63-643, RHR HX DISCH CHECK(continued)

[16] CALCULATE 2-CKV-63-643, RHR HX DISCH CHECK, backflow

leakage at rated pressure as follows:

2-CKV-63-643 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.6[15]

TEST PRESSURE = 6.3.6[10]

TEST LEAKAGEx V/2235÷ TEST PRESSURE =

xj2235+ =

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[17] VERIFY the leakage flow for 2-CKV-63-643, RHR HX DISCHCHECK, recorded in Step 6.3.6[16] is less than or equal to 4.0gpm. (ACC. CRIT. 5.0D.5)

[18] RECORD leakage flow from Step 6.3.6[16] on Appendix D,Reactor Boundary Leakage Log.

Page 83: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 81 of 202

Date

6.3.7 Backflow Leakage of 2-CKV-63-549, SIS L4 HL INJ CHECK

[1] DEPRESS Hand Switch 2-HS-63-167, TO HL 2&4, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-167, SISPUMP OUT TEST LINE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by

2-FI-63-76 ( or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 84: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 82 of 202

Date

6.3.7 Backflow Leakage of 2-CKV-63-549, SIS L4 HL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.7[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.7[3] - M&TE Error

=__GPM1st

Cv

[6] DEPRESS 2-HS-63-166, SI-RHR TO HL 4, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-166, RCS LP 4 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 85: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 83 of 202

Date

6.3.7 Backflow Leakage of 2-CKV-63-549, SIS L4 HL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.7[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.7[8] + M&TE Error

_+ = GPM1st

CV

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-166, SI-RHR TO HL 4, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-166,RCS LP 4 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-167, TO HL 2 & 4, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-167, SISPUMP OUTLET TO SIS TEST LINE, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 86: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 84 of 202

Date

6.3.7 Backflow Leakage of 2-CKV-63-549, SIS L4 HL INJ CHECK(continued)

[15] CALCULATE 2-CKV-63-549, SIS L4 HL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-549 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.7[9]

( )Step 6.3.7[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-549, SIS L4 HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-549 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.7[15]

TEST PRESSURE = 6.3.7[10]

TEST LEAKAGEx V/2235 + TEST PRESSURE =

X, 2235+ =

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 87: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 85 of 202

Date

6.3.7 Backflow Leakage of 2-CKV-63-549, SIS L4 HL INJ CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-549, SIS L4 HL INJCHECK, recorded in Step 6.3.7[16] is less than or equal to 1.0gpm. (ACC. CRIT. 5.0D.6)

[18] RECORD leakage flow from Step 6.3.7[16] on Appendix D,Reactor Boundary Leakage Log.

Page 88: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 86 of 202

Date

6.3.8 Backflow Leakage of 2-CKV-63-547, SIS L2 HL INJ CHECK

[1] DEPRESS Hand Switch 2-HS-63-167, TO HL 2&4, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-167, SISPUMP OUT TEST LINE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 89: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 87 of 202

Date

6.3.8 Backflow Leakage of 2-CKV-63-547, SIS L2 HL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.8[31, but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.8[3] - M&TE Error

-_ GPM1st

Cv

[6] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 90: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 88 of 202

Date

6.3.8 Backflow Leakage of 2-CKV-63-547, SIS L2 HL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.8[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.8[8] + M&TE Error

+ = GPM1st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-1,65, SI-RHR TO HL 2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-165,RCS LP 2 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-167, TO HL 2 & 4, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-167, SISPUMP OUT TEST LINE, AND

VERIFY valve CLOSES by light indication.

[13] DEPRESS Hand Switch 2-HS-63-117, SI PMPS TO CL 1, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-117, SISCL 1 CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[14] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

Page 91: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 89 of 202

Date

6.3.8 Backflow Leakage of 2-CKV-63-547, SIS L2 HL INJ CHECK(continued)

[15] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[16] CALCULATE 2-.CKV-63-547, SIS L2 HL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-547 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.8[9]

( )Step 6.3.8[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 92: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 90 of 202

Date

6.3.8 Backflow Leakage of 2-CKV-63-547, SIS L2 HL INJ CHECK(continued)

[17] CALCULATE 2-CKV-63-547, SIS L2 HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-547 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.8[16]

TEST PRESSURE = 6.3.8[10]

TEST LEAKAGEx V2235 + TEST PRESSURE =

x V2235+

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[18] VERIFY the leakage flow for 2-CKV-63-547, SIS L2 HL INJCHECK, recorded in Step 6.3.8[17] is less than or equal to 1.0gpm. (ACC. CRIT. 5.0D.7)

[19] RECORD leakage flow from Step 6.3.8[17] on Appendix D,Reactor Boundary Leakage Log.

Page 93: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 91 of 202

Date

6.3.9 Backflow Leakage of 2-CKV-63-551, SIS LI CL INJ CHECK

[1] PLACE Hand Switch 2-HS-63-22A, SI PMPS TO CL 1-2-3-4,to CLOSE AND

VERIFY valve 2-FCV-63-22, SIS PUMP COLD LEG INJ, isCLOSED by light indication.

[2] PLACE Hand Switch 2-HS-63-157A, SI PMP B TO HL 2&4, toOPEN AND

VERIFY valve 2-FCV-63-157, SIS PUMP OUT RCS LP 2&4HL, is OPEN by light indication.

NOTE

The following valve manipulations will be performed from Hand Switch Panel 2-XS-63-1 00,CKV LEAK TEST, at 2-M-6.

[3] DEPRESS Hand Switch 2-HS-63-117, SI PMPS TO CL 1, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-117, SISCL 1 CHECK VLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[4] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve OPENS by light indication.

Page 94: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 92 of 202

Date

6.3.9 Backflow Leakage of 2-CKV-63-551, SIS LI CL INJ CHECK(continued)

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[5] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[6] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[7] ISOLATE the Flow Indicator used in the previous step.

[8] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.9[6], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.9[6] - M&TE Error

-_ = GPM1 st

Cv

Page 95: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 93 of 202

Date

6.3.9 Backflow Leakage of 2-CKV-63-551, SIS LI CL INJ CHECK(continued)

NOTE

The following step will provide SI pressure for testing 2-CKV-63-551, SIS Li CL INJCHECK.

[9] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[10] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[11] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[12] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.9[11]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.9[1 ] + M&TE Error

+ = GPM1st

CV

Page 96: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 94 of 202

Date

6.3.9 Backflow Leakage of 2-CKV-63-551, SIS LI CL INJ CHECK(continued)

[13] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[14] DEPRESS Hand Switch 2-HS-63-165, SI-RHR TO HL 2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-165,RCS LP 2 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[15] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve CLOSES by light indication.

[16] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[17] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[18] CALCULATE 2-CKV-63-551, SIS LI CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-551 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.9[12]

)

Step 6.3.9[8]

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 97: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 95 of 202

Date

6.3.9 Backflow Leakage of 2-CKV-63-551, SIS LI CL INJ CHECK(continued)

[19] CALCULATE 2-CKV-63-551, SIS Li HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-551 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.9[18]

TEST PRESSURE = 6.3.9[13]

TEST LEAKAGEx V/2235 + TEST PRESSURE =

x j2235+

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[20] VERIFY the leakage flow for 2-CKV-63-551, SIS LI CL INJCHECK, recorded in Step 6.3.9[19] is less than or equal to 1.0gpm. (ACC. CRIT. 5.0D.8)

[21] RECORD leakage flow from Step 6.3.9[19] on Appendix D,Reactor Boundary Leakage Log.

Page 98: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 96 of 202

Date

6.3.10 Backflow Leakage of 2-CKV-63-633, RHR PUMP DISCH CHECK:

[1] DEPRESS Hand Switch 2-HS-63-112, RHR TO CL 1&4, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-112, SISCHECK VLV LEAK TEST ISOLATION VLV, AND

VERIFY valve OPENS by light indication.

NOTES

1 ) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

(4] ISOLATE the Flow Indicator used in the previous step.

Page 99: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 97 of 202

Date

6.3.10 Backflow Leakage of 2-CKV-63-633, RHR PUMP DISCH CHECK:(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.10[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.10[3] - M&TE Error

=_ GPM1st

CV

[6] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, and VERIFY valve OPENS by lightindication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 100: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 98 of 202

Date

6.3.10 Backflow Leakage of 2-CKV-63-633, RHR PUMP DISCH CHECK:(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.10[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.10[8] + M&TE Error

+ = GPM1 st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-117, SI PMPS TO CL 1, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-117, SISCL 1 CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-112, RHR TO CL 1&4, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-112, SISCHECK VLV LEAK TEST ISOLATION VLV, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 101: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 99 of 202

Date

6.3.10 Backflow Leakage of 2-CKV-63-633, RHR PUMP DISCH CHECK:(continued)

[15] CALCULATE 2-CKV-63-633, RHR PUMP DISCH CHECK, backflowleakage at test pressure as follows:

2-CKV-63-633 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.10[9] Step 6.3.10[5]

___ __ ) - _____

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[16] CALCULATE 2-CKV-63-633, RHR PUMP DISCH CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-633 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.10[15]

TEST PRESSURE = 6.3.10[10]

TEST LEAKAGEx V2235 + TEST PRESSURE

x 12235+

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

Page 102: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 100 of 202

Date

6.3.10 Backflow Leakage of 2-CKV-63-633, RHR PUMP DISCH CHECK:(continued)

[17] VERIFY the leakage flow for 2-CKV-63-633, RHR PUMPDISCH CHECK, recorded in Step 6.3.10[16] is less than orequal to 3.0 gpm. (ACC. CRIT. 5.0D.9)

[18] RECORD leakage flow from Step 6.3.10[16] on Appendix D,Reactor Boundary Leakage Log.

Page 103: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 101 of 202

Date

6.3.11 Backflow Leakage of 2-CKV-63-553, SIS L2 CL INJ CHECK

[1] DEPRESS Hand Switch 2-HS-63-121,Sl PMPS TO CL, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 104: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 102 of 202

Date

6.3.11 Backflow Leakage of 2-CKV-63-553, SIS L2 CL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.11 [3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.11[3] - M&TE Error

-_ _ GPM1st

CV

[6] DEPRESS 2-HS-63-97, SI PMPS TO CL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-97, SIS CL 2 CHECKVLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 105: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 103 of 202

Date

6.3.11 Backflow Leakage of 2-CKV-63-553, SIS L2 CL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.11[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.11[8] + M&TE Error

+ = GPM1st

CV

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-165, SI-RHR TO HL 2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-165,RCS LP 2 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 106: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 104 of 202

Date

6.3.11 Backflow Leakage of 2-CKV-63-553, SIS L2 CL INJ CHECK(continued)

[15] CALCULATE 2-CKV-63-553, SIS L2 CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-553 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.11 [9]

(G )GPM

Step 6.3.11 [5]

- (. ) =

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-553, SIS L2 HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-553 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.11[15]

TEST PRESSURE = 6.3.11[110].

TEST LEAKAGEx V2235 + TEST PRESSURE =

x j2235+

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 107: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 105 of 202

I

Date

6.3.11 Backflow Leakage of 2-CKV-63-553, SIS L2 CL INJ CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-553, SIS L2 CL INJCHECK, recorded in Step 6.3.11[16] is less than or equal to1.0 gpm. (ACC. CRIT. 5.0D.10)

[18] RECORD leakage flow from Step 6.3.11 [16] on Appendix D,Reactor Boundary Leakage Log.

Page 108: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 106 of 202

Date

6.3.12 Backflow Leakage of 2-CKV-63-632, RHR PUMP DISCH CHECK

[1] DEPRESS Hand Switch 2-HS-63-1 11, RHR TO CL 2&3, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-1 11, SISCHECK VLV LEAK TEST ISOLATION VLV, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 109: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 107 of 202

Date

6.3.12 Backflow Leakage of 2-CKV-63-632, RHR PUMP DISCH CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.12[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.12[3] - M&TE Error

-_ = GPM1st

CV

[6] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, and

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-_ _

Page 110: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 108 of 202

Date

6.3.12 Backflow Leakage of 2-CKV-63-632, RHR PUMP DISCH CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.12[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.12[8] + M&TE Error

- + = GPM1 st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-97, SI PMPS TO CL 2, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-97, SISCL 2 CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-1 11, RHR TO CL 2&3, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-1 11, SISCHECK VLV LEAK TEST ISOLATION VLV, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 111: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 109 of 202

Date

6.3.12 Backflow Leakage of 2-CKV-63-632, RHR PUMP DISCH CHECK(continued)

[15] CALCULATE 2-CKV-63-632, RHR PUMP DISCH CHECK, backflowleakage at test pressure as follows:

2-CKV-63-632 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.12[9] Step 6.3.12[5]

___ __ ) - _( _)_ =

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[16] CALCULATE 2-CKV-63-632, RHR PUMP DISCH CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-632 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.12[15]

TEST PRESSURE = 6.3.12[10]

TEST LEAKAGEx V2235+TEST PRESSURE =

xJ2235+

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

Page 112: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 110 of 202

Date

6.3.12 Backflow Leakage of 2-CKV-63-632, RHR PUMP DISCH CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-632, RHR PUMPDISCH CHECK, recorded in Step 6.3.12[16] is less than orequal to 3.0 gpm. (ACC. CRIT. 5.OD.11)

[18] RECORD leakage flow from Step 6.3.12[16] on Appendix D,Reactor Boundary Leakage Log.

Page 113: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 111 of 202

Date

6.3.13 Backflow Leakage of 2-CKV-63-555, SIS L3 CL INJ CHECK

[1] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 114: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 112 of 202

Date

6.3.13 Backflow Leakage of 2-CKV-63-555, SIS L3 CL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.13[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.13[3] - M&TE Error

=_ GPM1st

Cv

NOTE

The following step will provide SI pressure for testing 2-CKV-63-555, SIS L3 CL INJCHECK.

[6] DEPRESS 2-HS-63-79, SI PMPS TO CL 3, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-79, SIS CL 3 CHECKVLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 115: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 113 of 202

Date

6.3.13 Backflow Leakage of 2-CKV-63-555, SIS L3 CL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.13[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.13[8] + M&TE Error

+ = GPM1st

CV

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-165, SI-RHR TO HL 2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-165,RCS LP 2 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 116: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 114 of 202

Date

6.3.13 Backflow Leakage of 2-CKV-63-555, SIS L3 CL INJ CHECK(continued)

[15] CALCULATE 2-CKV-63-555, SIS L3 CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-555 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.13[9]

( )Step 6.3.13[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-555, SIS L3 HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-555 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.13[15]

TEST PRESSURE = 6.3.13[10]

TEST LEAKAGEx V2235 + TEST PRESSURE

x j2235+ =

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 117: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 115 of 202

Date

6.3.13 Backflow Leakage of 2-CKV-63-555, SIS L3 CL INJ CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-555, SIS L3 CL INJCHECK, recorded in Step 6.3.13[16] is less than or equal to1.0 gpm. (ACC. CRIT. 5.0D.12)

[18] RECORD leakage flow from Step 6.3.13[16] on Appendix D,Reactor Boundary Leakage Log.

Page 118: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 116 of 202

Date

6.3.14 Backflow Leakage of 2-CKV-63-634, RHR PUMP DISCH CHECK

[1] DEPRESS Hand Switch 2-HS-63-1 11, RHR TO CL 2&3, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-1 11, SiSCHECK VLV LEAK TEST ISOLATION VLV, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 119: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 117 of 202

Date

6.3.14 Backflow Leakage of 2-CKV-63-634, RHR PUMP DISCH CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.14[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.14[3] - M&TE Error

-_ = GPM1st

Cv

[6] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-1 00,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 120: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 118 of 202

Date

6.3.14 Backflow Leakage of 2-CKV-63-634, RHR PUMP DISCH CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.14[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.14[8] + M&TE Error

+ = GPM1st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-79, SI PMPS TO CL 3, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-79, SISCL 3 CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-111, RHR TO CL 2&3, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-1 11, SISCHECK VLV LEAK TEST ISOLATION VLV, and

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 121: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 119 of 202

Date

6.3.14 Backflow Leakage of 2-CKV-63-634, RHR PUMP DISCH CHECK(continued)

[15] CALCULATE 2-CKV-63-634, RHR PUMP DISCH CHECK, backflowleakage at test pressure as follows:

2-CKV-63-634 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.14[9]

( )Step 6.3.14[5]

- (. ) -

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 122: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 120 of 202

Date

6.3.14 Backflow Leakage of 2-CKV-63-634, RHR PUMP DISCH CHECK(continued)

[161 CALCULATE 2-CKV-63-634, RHR PUMP DISCH CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-634 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.14[15]

TEST PRESSURE = 6.3.14[10]

TEST LEAKAGEx V2235 TEST PRESSURE =

xV2235- +

GPM

Calculations Performed ByInitials Date

Calculations Verified By

Initials Date

[17] VERIFY the leakage flow for 2-CKV-63-634, RHR PUMPDISCH CHECK, recorded in Step 6.3.14[16] is less than orequal to 3.0 gpm. (ACC. CRIT. 5.0D.13)

[18] RECORD leakage flow from Step 6.3.14[16] on Appendix D,Reactor Boundary Leakage Log.

Page 123: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 121 of 202

Date

6.3.15 Backflow Leakage of 2-CKV-63-557, SIS L4 CL INJ CHECK

[1] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 124: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 122 of 202

Date

6.3.15 Backflow Leakage of 2-CKV-63-557, SIS L4 CL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.15[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.15[3] - M&TE Error

-_ = GPM1st

Cv

[6] DEPRESS 2-HS-63-69, SI PMPS TO CL 4, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-69, SIS CL 4 CHECKVLV LEAK TEST, and

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 125: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 123 of 202

Date

6.3.15 Backflow Leakage of 2-CKV-63-557, SIS L4 CL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.15[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.15[8] + M&TE Error

_+ = GPM1st

Cv

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP A DISCHPRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-165, SI-RHR TO HL 2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-165,RCS LP 2 HL FEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-121, SI PMPS TO CL, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-121, SISFLOW TO CL CHECK VLV TEST, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 126: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 124 of 202

Date

6.3.15 Backflow Leakage of 2-CKV-63-557, SIS L4 CL INJ CHECK(continued)

[15] CALCULATE 2-CKV-63-557, SIS L4 CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-557 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.15[9]

( )Step 6.3.15[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-557, SIS L4 HL INJ CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-557 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.15[15]

TEST PRESSURE = 6.3.15[10]

TEST LEAKAGEx V2235 +TEST PRESSURE =

x j2235+

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 127: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 125 of 202

Date

6.3.15 Backflow Leakage of 2-CKV-63-557, SIS L4 CL INJ CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-557, SIS L4 CL INJCHECK, recorded in Step 6.3.15[16] is less than or equal to1.0 gpm. (ACC. CRIT. 5.00.14)

[18] RECORD leakage flow from Step 6.3.15[16] on Appendix D,Reactor Boundary Leakage Log.

Page 128: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 126 of 202

Date

6.3.16 Backflow Leakage of 2-CKV-63-635, RHR PUMP DISCH CHECK

[1] DEPRESS Hand Switch 2-HS-63-112, RHR TO CL 1&4, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-112, SISCHECK VLV LEAK TEST ISOLATION VLV, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 129: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 127 of 202

Date

6.3.16 Backflow Leakage of 2-CKV-63-635, RHR PUMP DISCH CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.16[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.16[3] - M&TE Error

-_ _ GPM1st

Cv

[6] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 130: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 128 of 202

Date

6.3.16 Backflow Leakage of 2-CKV-63-635, RHR PUMP DISCH CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.16[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.16[8] + M&TE Error

+ = GPM

1st

CV

[10] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[11] DEPRESS Hand Switch 2-HS-63-69, SI PMPS TO CL 4, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-69, SISCL 4 CHECK VLV LEAK TEST, and

VERIFY valve CLOSES by light indication.

[12] DEPRESS Hand Switch 2-HS-63-112, RHR TO CL 1&4, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-112, SISCHECK VLV LEAK TEST ISOLATION VLV, and

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 131: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 129 of 202

Date

6.3.16 Backflow Leakage of 2-CKV-63-635, RHR PUMP DISCH CHECK(continued)

[15] CALCULATE 2-CKV-63-635, RHR PUMP DISCH CHECK,backflow leakage at test pressure as follows:

2-CKV-63-635 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.16[9]

( )Step 6.3.16[5]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-635, RHR PUMP DISCH CHECK,backflow leakage at rated pressure as follows:

2-CKV-63-635 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.16[15]

TEST PRESSURE = 6.3.16[10]

TEST LEAKAGEx V2235 + TEST PRESSURE =

x j2235+

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 132: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 130 of 202

Date

6.3.16 Backflow Leakage of 2-CKV-63-635, RHR PUMP DISCH CHECK(continued)

[17] VERIFY the leakage flow for 2-CKV-63-635, RHR PUMPDISCH CHECK, recorded in Step 6.3.16[16] is less than orequal to 3.0 gpm. (ACC. CRIT. 5.OD.15)

[18] RECORD leakage flow from Step 6.3.16[16] on Appendix D,Reactor Boundary Leakage Log.

Page 133: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 131 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.

NOTE

This subsubsection, 6.3.17, will require the RHR pumps to be isolated from the RWST andRCS Boundaries.

[1] RECORD the "as found" position for the following:

A. 2-HS-74-10A, RHR PUMP 2A-A (2-M-6)

As found position:

B. 2-HS-74-20A, RHR PUMP 2B-B (2-M-6)

As found position:

[2] VERIFY/PLACE the following Hand Switches to PULL TO LOCK:

A. 2-HS-74-10A, RHR PUMP 2A-A (2-M-6)

B. 2-HS-74-20A, RHR PUMP 2B-B (2-M-6)

[3] PLACE Hand Switch 2-HS-63-185, RHR SUPPLY TEST LINEVALVE, to OPEN, AND

VERIFY valve 2-FCV-63-185, RHR SUPPLY TEST LINE,OPENS by light indication.

[4] PLACE Hand Switch 2-HS-63-1, RHR PUMPS A-A & B-BSUCTION FROM RWST, to CLOSE 2-FCV-63-1, RWST TORHR PUMP FLOW CNTL VLV, AND

VERIFY valve CLOSES by light indication.

Page 134: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 132 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[5] RECORD the "as found" position for the following:

A. 2-HS-74-3, RHR PUMP A-A INLET FLOW CONTROLVLV (2-M-6)

As found position:

B. 2-HS-74-21, RHR PUMP B-B INLET FLOW CONTROLVLV (2-M-6)

As found position:

[6] VERIFY/CLOSE the following valves:

A. 2-FCV-74-3, RHR PUMP A-A INLET FLOW CONTROLVLV

B. 2-FCV-74-21, RHR PUMP B-B INLET FLOW CONTROLVLV

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[7] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

Page 135: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 133 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[8] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[9] ISOLATE the Flow Indicator used in the previous step.

[10] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.17[8], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.17[8] - M&TE Error

-_ = GPM1st

CV

NOTE

The following step will provide SI Pressure for testing 2-FCV-74-2, RHR SYSTEMISOLATION VALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASS VALVE.

[11] DEPRESS 2-HS-63-186, BETWEEN FCV-74-2, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-186, RHRSUPPLY TEST LINE, and

VERIFY valve OPENS by light indication.

[12] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

Page 136: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 134 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[13] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[14] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.17[13]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.17[13] + M&TE Error

+ = GPM

1 st

Cv

[15] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[16] DEPRESS 2-HS-63-186, BETWEEN FCV-74-2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-186,RHR SUPPLY TEST LINE, AND

VERIFY valve CLOSES by light indication.

Page 137: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 135 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[17] PLACE 2-HS-63-185, RHR SUPPLY TEST LINE VALVE, toCLOSE 2-FCV-63-185, RHR SUPPLY TEST LINE, AND

VERIFY valve CLOSES by light indication.

[18] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-1 00,CKV LEAK TEST, to CLOSE 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[19] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[20] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[21] VERIFY/PLACE the following valves to the "as found" positionas recorded in Step 6.3.17[5]:

A. 2-FCV-74-3, RHR PUMP A-A INLET FLOW CONTROLVLV

6.3.17[5]A As found position:

B. 2-FCV-74-21, RHR PUMP B-B INLET FLOW CONTROLVLV

6.3.17[5]B As found position:

[22] PLACE Hand Switch 2-HS-63-1, RHR PUMPS A-A & B-BSUCTION FROM RWST, to OPEN 2-FCV-63-1, RWST TORHR PUMP FLOW CNTL VLV, AND

VERIFY valve OPENS by light indication.

Page 138: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 136 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[23] VERIFY/PLACE the following Hand Switches to the "as found"position as recorded in Step 6.3.17[1]:

A. 2-HS-74-10A, RHR PUMP 2A-A)

6.3.17[1]A As found position:

B. 2-HS-74-20A, RHR PUMP 2B-B)

6.3.17[1]B As found position:

[24] CALCULATE 2-FCV-74-2, RHR SYSTEM ISOLATION VALVE,2-FCV-74-8, RHR SYSTEM ISOLATION BYPASS VALVE,backflow leakage at test pressure as follows:

2-FCV-74-2 and 2-FCV-74-8 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.17[14]

( )Step 6.3.17[10]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 139: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 137 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[25] CALCULATE 2-FCV-74-2, RHR SYSTEM ISOLATION VALVE,2-FCV-74-8, RHR SYSTEM ISOLATION BYPASS VALVE,backflow leakage at test pressure as follows:

2-FCV-74-2 and 2-FCV-74-8 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.17[24]

TEST PRESSURE = 6.3.17[15]

TEST LEAKAGEx /2235÷ TEST PRESSURE =

x V2235+

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[26] VERIFY the combined leakage flow for 2-FCV-74-2, RHRSYSTEM ISOLATION VALVE, and 2-FCV-74-8, RHRSYSTEM ISOLATION BYPASS VALVE, recorded in Step6.3.17[25] is less than or equal to 5.0 gpm.(ACC. CRIT. 5.0D.16)

[27] PLACE 2-HS-63-157A, SI PMP B TO HL 2&4, to CLOSE,AND

VERIFY valve 2-FCV-63-157, SIS PUMP OUT RCS LP 2&4HL, is CLOSED by light indication.

[28] PLACE 2-HS-63-22A, SI PMPS TO CL 1-2-3-4, to OPEN, andVERIFY Valve 2-FCV-63-22, SIS PUMP COLD LEG INJ, isOPEN by light indication.

Page 140: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 138 of 202

Date

6.3.17 Backflow Leakage of 2-FCV-74-2, RHR SYSTEM ISOLATIONVALVE, and 2-FCV-74-8, RHR SYSTEM ISOLATION BYPASSVALVE.(continued)

[29] RECORD leakage flow from Step 6.3.17[25] on Appendix D,Reactor Boundary Leakage Log.

Page 141: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 139 of 202

Date

6.3.18 Backflow Leakage of 2-CKV-63-622, ACCUM 1 OUT CHECK.

NOTE

Subsubsections 6.3.18, 6.3.19, 6.3.20, and 6.3.21 require the isolation of Accumulators 1,2, 3, and 4 from the RCS Boundary.

[1] DEPRESS 2-HS-63-188, TEST LINE ISOL, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-188, RHR SUPPLYTEST LINE, AND

VERIFY valve CLOSES by light indication.

[2] DEPRESS 2-HS-63-187, TEST LINE ISOL, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-187, RHR SUPPLYTEST LINE, AND

VERIFY valve OPENS by light indication.

[3] RECORD "as found" position of 2-HS-63-118A, CL ACCUM 1OUTLET.

As Found position:

[4] VERIFY/CLOSE 2-FCV-63-118, SIS ACCUM TK 1 FLOWISOLATION VLV.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[5] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

Page 142: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 140 of 202

Date

6.3.18 Backflow Leakage of 2-CKV-63-622, ACCUM I OUT CHECK.(continued)

[6] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[7] ISOLATE the Flow Indicator used in the previous step.

[8] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.18[6], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.18[6] - M&TE Error

=__GPM1 st

Cv

NOTE

The following step will provide leakage path for testing 2-CKV-63-622, ACCUM 1 OUTCHECK.

[9] DEPRESS 2-HS-63-116, CL ACCUM 1, at 2-XS-63-100, CKVLEAK TEST, to OPEN 2-FCV-63-116, SIS ACCUM TK 1CHECK VLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[10] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

Page 143: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 141 of 202

Date

6.3.18 Backflow Leakage of 2-CKV-63-622, ACCUM 1 OUT CHECK.(continued)

[11] WAIT for flow to stabilize,

RECORD the total leakage flow indicated by 2-FI-63-76(2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[12] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.18[11]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.18[1 1] + M&TE Error

+ = GPM1st

Cv

[13] RECORD the test pressure indicated by 2-PI-63-1!50, SI PMP ADISCH PRESS.

Test Pressure psig

[14] DEPRESS 2-HS-63-116, CL ACCUM 1, at 2-XS-63-100, CKVLEAK TEST, to CLOSE 2-FCV-63-116, SIS ACCUM TK 1CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[15] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

Page 144: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 142 of 202

Date

6.3.18 Backflow Leakage of 2-CKV-63-622, ACCUM I OUT CHECK.(continued)

[16] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[17] CALCULATE 2-CKV-63-622, ACCUM 1 OUT CHECK, backflowleakage at test pressure as follows:

2-CKV-63-622 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.18[12]

( )Step 6.3.18[8]

(. )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 145: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 143 of 202

Date

6.3.18 Backflow Leakage of 2-CKV-63-622, ACCUM 1 OUT CHECK.(continued)

[18] CALCULATE 2-CKV-63-622, ACCUM 1 OUT CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-622 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.18[17]

TEST PRESSURE = 6.3.18[13]

TEST LEAKAGEx V2235 +TEST PRESSURE =

x V2235 + =

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[19] VERIFY the leakage flow for 2-CKV-63-622, ACCUM 1 OUTCHECK, recorded in Step 6.3.18[18] is less than or equal to5.0 gpm. (ACC. CRIT. 5.0D.17)

[20] VERIFY/PLACE 2-FCV-63-118, SIS ACCUM TK I FLOWISOLATION VLV, to the "as found" position as recorded inStep 6.3.18[3].

6.3.18[3] As Found position:

[21] RECORD leakage flow from Step 6.3.18[18] on Appendix D,Reactor Boundary Leakage Log.

Page 146: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 144 of 202

Date

6.3.19 Backflow Leakage of 2-CKV-63-623, ACCUM 2 OUT CHECK.

[1] RECORD "as found" position of 2-HS-63-98A, CL ACCUM 2OUTLET.

As Found position:

[2] VERIFY/CLOSE 2-FCV-63-98, SIS ACCUM TK 2 FLOWISOLATION VLV.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[3] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[4] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[5] ISOLATE the Flow Indicator used in the previous step.

Page 147: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 145 of 202

Date

6.3.19 Backflow Leakage of 2-CKV-63-623, ACCUM 2 OUT CHECK.(continued)

[6] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.19[4], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.19[4] - M&TE Error

=_ GPM1st

CV

[7] DEPRESS 2-HS-63-96, CL ACCUM 2, at 2-XS-63-100, CKVLEAK TEST, to OPEN 2-FCV-63-96, SIS ACCUM TK 2CHECK VLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[8] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[9] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 148: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 146 of 202

Date

6.3.19 Backflow Leakage of 2-CKV-63-623, ACCUM 2 OUT CHECK.(continued)

[10] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.19[9]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.19[9] + M&TE Error

___ ___ _ + ___ ___ _ _ ___ ___GPM

1st

CV

[11] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[12] DEPRESS 2-HS-63-96, CL ACCUM 2, at 2-XS-63-1 00, CKVLEAK TEST, to CLOSE 2-FCV-63-96, SIS ACCUM TK 2CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 149: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 147 of 202

Date

6.3.19 Backflow Leakage of 2-CKV-63-623, ACCUM 2 OUT CHECK.(continued)

[15] CALCULATE 2-CKV-63-623, ACCUM 2 OUT CHECK, backflowleakage at test pressure as follows:

2-CKV-63-623 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.19[10]

( )Step 6.3.19[6]

- ( ) =

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

Page 150: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 148 of 202

Date

6.3.19 Backflow Leakage of 2-CKV-63-623, ACCUM 2 OUT CHECK.(continued)

[16] CALCULATE 2-CKV-63-623, ACCUM 2 OUT CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-623 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.19[15]

TEST PRESSURE = 6.3.19[11]

TEST LEAKAGEx V2235 +TEST PRESSURE =

x j2235+ =

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[17] VERIFY the leakage flow for 2-CKV-63-623, ACCUM 2 OUTCHECK, recorded in Step 6.3.19[16] is less than or equal to5.0 gpm. (ACC. CRIT. 5.00.18)

[18] VERIFY/PLACE 2-FCV-63-98, SIS ACCUM TK 2 FLOWISOLATION VLV, to the "as found" position as recorded in Step6.3.19[1].

6.3.19[1] As Found position:

[19] RECORD leakage flow from Step 6.3.19[16] on Appendix D,Reactor Boundary Leakage Log.

Page 151: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 149 of 202

Date

6.3.20 Backflow Leakage of 2-CKV-63-624, ACCUM 3 OUT CHECK.

[1] RECORD "as found" position of 2-HS-63-80A, CL ACCUM 3OUTLET.

As Found position:

[2] VERIFY/CLOSE 2-FCV-63-80, SIS ACCUM TK 3 FLOWISOLATION VLV.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[3] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[4] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[5] ISOLATE the Flow Indicator used in the previous step.

Page 152: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 150 of 202

Date

6.3.20 Backflow Leakage of 2-CKV-63-624, ACCUM 3 OUT CHECK.(continued)

[6] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.20[4], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.20[4] - M&TE Error

-_ _ GPM1st

Cv

NOTE

The following step will provide leakage path for testing 2-CKV-63-624, ACCUM 3 OUTCHECK.

[7] DEPRESS 2-HS-63-78, CL ACCUM 3, at 2-XS-63-100, CKVLEAK TEST, to OPEN 2-FCV-63-78, SIS ACCUM TK 3CHECK VLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[8] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[9] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 153: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 151 of 202

Date

6.3.20 Backflow Leakage of 2-CKV-63-624, ACCUM 3 OUT CHECK.(continued)

[10] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.20[9]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.20[9] + M&TE Error

- + = GPM1st

Cv

[11] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[12] DEPRESS 2-HS-63-78, CL ACCUM 3, at 2-XS-63-100, CKVLEAK TEST, to CLOSE 2-FCV-63-78, SIS ACCUM TK 3CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[13] •VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 154: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 152 of 202

Date

6.3.20 Backflow Leakage of 2-CKV-63-624, ACCUM 3 OUT CHECK.(continued)

[15] CALCULATE 2-CKV-63-624, ACCUM 3 OUT CHECK, backflow

leakage at test pressure as follows:

2-CKV-63-624 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.20[10]

( )Step 6.3.20[6]

- ( ) =

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[16] CALCULATE 2-CKV-63-624, ACCUM 3 OUT CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-624 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.20[15]

TEST PRESSURE = 6.3.20[11]

TEST LEAKAGEx V2235 +TEST PRESSURE =

x 12235+

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

Page 155: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 153 of 202

Date

6.3.20 Backflow Leakage of 2-CKV-63-624, ACCUM 3 OUT CHECK.(continued)

[17] VERIFY the leakage flow for 2-CKV-63-624, ACCUM 3 OUTCHECK, recorded in Step 6.3.20[16] is less than or equal to5.0 gpm. (ACC. CRIT. 5.0D.19)

[18] VERIFY/PLACE 2-FCV-63-80, SIS ACCUM TK 3 FLOWISOLATION VLV, to the "as found" position as recorded in Step6.3.20[1].

6.3.20[1] As Found position:

[19] RECORD leakage flow from Step 6.3.20[16] on Appendix D,Reactor Boundary Leakage Log.

Page 156: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 154 of 202

Date

6.3.21 Backflow Leakage of 2-CKV-63-625, ACCUM 4 OUT CHECK.

[1] RECORD "as found" position of 2-HS-63-67A, CL ACCUM 4OUTLET.

As Found position:

[2] VERIFY/CLOSE 2-FCV-63-67, SIS ACCUM TK 4 FLOWISOLATION VLV.

NOTES

1 ) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[3] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[4] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[5] ISOLATE the Flow Indicator used in the previous step.

Page 157: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 155 of 202

Date

6.3.21 Backflow Leakage of 2-CKV-63-625, ACCUM 4 OUT CHECK.(continued)

[6] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.21 [4], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.21[4] - M&TE Error

=_ GPM1st

CV

[7] DEPRESS 2-HS-63-68, CL ACCUM 4, at 2-XS-63-100, CKVLEAK TEST, to OPEN 2-FCV-63-68, SIS ACCUM TK 4CHECK VLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[8] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[9] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 158: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 156 of 202

Date

6.3.21 Backflow Leakage of 2-CKV-63-625, ACCUM 4 OUT CHECK.(continued)

[10] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.21 [9]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.21 [9] + M&TE Error

___ ___ _ + ___ ___ _ _ ___ ___GPM

1 st

CV

[11] RECORD the test pressure indicated by 2-PI-63-150, SI PMP ADISCH PRESS.

Test Pressure psig

[12] DEPRESS 2-HS-63-68, CL ACCUM 4, at 2-XS-63-100, CKVLEAK TEST, to CLOSE 2-FCV-63-68, SIS ACCUM TK 4CHECK VLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[13] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[14] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 159: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 157 of 202

Date

6.3.21 Backflow Leakage of 2-CKV-63-625, ACCUM 4 OUT CHECK.(continued)

[15] CALCULATE 2-CKV-63-625, ACCUM 4 OUT CHECK, backflowleakage at test pressure as follows:

2-CKV-63-625 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.21 [10] Step 6.3.21 [6]

( ) _ _ _ _ _

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[16] CALCULATE 2-CKV-63-625, ACCUM 4 OUT CHECK, backflowleakage at rated pressure as follows:

2-CKV-63-625 Leakage at rated pressure =

TEST LEAKAGE = Step 6.3.21[15]

TEST PRESSURE = 6.3.21 [11]

TEST LEAKAGEx V/2235 + TEST PRESSURE =

x j2235+ =

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

Page 160: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 158 of 202

Date

6.3.21 Backflow Leakage of 2-CKV-63-625, ACCUM 4 OUT CHECK.(continued)

[17] VERIFY the leakage flow for 2-CKV-63-625, ACCUM 4 OUTCHECK, recorded in Step 6.3.21 [16] is less than or equal to5.0 gpm. (ACC. CRIT. 5.0D.20)

[18] VERIFY/PLACE 2-FCV-63-67, SIS ACCUM TK 4 FLOWISOLATION VLV, to the "as found" position as recorded inStep 6.3.21 [1].

6.3.21 [1] As Found position:

[19] PLACE 2-HS-63-10A, SI PMP A, to PULL-TO-LOCK, AND

VERIFY SI Pump A is NOT RUNNING by light indication.

[20] DEPRESS 2-HS-63-187, TEST LINE ISOL, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-187, RHR SUPPLYTEST LINE, AND

VERIFY valve CLOSES by light indication.

[21] RECORD leakage flow from Step 6.3.21[16] on Appendix D,Reactor Boundary Leakage Log.

Page 161: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 159 of 202

Date

6.3.22 Backflow Leakage of 2-CKV-63-586, BORON INJ CHECK CL L1,2-CKV-63-587, BORON INJ CHECK CL L2, 2-CKV-63-588, BORONINJ CHECK CL L3, and 2-CKV-63-589, BORON INJ CHECK CL L4.

NOTE

Subsubsections 6.3.22 through 6.3.30 use RCS normal operating pressure, (2235 ± 20psig), for pressurization and therefore will not require correction calculations for leakagerate.

[1] DEPRESS 2-HS-63-188, TEST LINE ISOL, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-188, RHR SUPPLYTEST LINE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 162: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 160 of 202

Date

6.3.22 Backflow Leakage of 2-CKV-63-586, BORON INJ CHECK CL L1,2-CKV-63-587, BORON INJ CHECK CL L2, 2-CKV-63-588, BORONINJ CHECK CL L3, and 2-CKV-63-589, BORON INJ CHECK CL L4.(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.22[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.22[3] - M&TE Error

=_ GPM1st

CV

NOTE

The following step will provide the combined leakage path for testing check valves2-CKV-63-586, 2-CKV-63-587, 2-CKV-63-588, 2-CKV-63-589.

[6] DEPRESS 2-HS-63-24A, CLA MAKEUP FRM BIT OUTLET, at2-XS-63-1 00, CKV LEAK TEST, to OPEN 2-FCV-63-24, SISACCUM FILL LINE ISOLATION VLV, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 163: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Page 161 of 202

Date

6.3.22 Backflow Leakage of 2-CKV-63-586, BORON INJ CHECK CL L1,2-CKV-63-587, BORON INJ CHECK CL L2, 2-CKV-63-588, BORONINJ CHECK CL L3, and 2-CKV-63-589, BORON INJ CHECK CL L4.(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.22[8]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.22[8] + M&TE Error

+ = GPM1st

Cv

[10] RECORD the test pressure indicated by 2-PI-68-340, PZR PRESS.

Test Pressure psig

[11] DEPRESS 2-HS-63-24A, CLA MAKEUP FRM BIT OUTLET, at2-XS-63-1 00, CKV LEAK TEST, to CLOSE 2-FCV-63-24, SISACCUM FILL LINE ISOLATION VLV, AND

VERIFY valve CLOSES by light indication.

[12] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[13] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 164: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 162 of 202

Date

6.3.22 Backflow Leakage of 2-CKV-63-586, BORON INJ CHECK CL L1,2-CKV-63-587, BORON INJ CHECK CL L2, 2-CKV-63-588, BORONINJ CHECK CL L3, and 2-CKV-63-589, BORON INJ CHECK CL L4.(continued)

[14] CALCULATE combined backflow leakage of2-CKV-63-586, BORON INJ CHECK CL L1,2-CKV-63-587, BORON INJ CHECK CL L2,2-CKV-63-588, BORON INJ CHECK CL L3,2-CKV-63-589, BORON INJ CHECK CL L4,at test pressure as follows:

Combined Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.22[9] Step 6.3.22[5]

() - _(_ _ _=

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[15] VERIFY the combined leakage flow for2-CKV-63-586, BORON INJ CHECK CL L1,2-CKV-63-587, BORON INJ CHECK CL L2,2-CKV-63-588, BORON INJ CHECK CL L3,2-CKV-63-589, BORON INJ CHECK CL L4recorded in Step 6.3.22[14] is less than or equal to 0.75 gpm.(ACC. CRIT. 5.OD.21)

[16] DEPRESS 2-HS-63-188, TEST LINE ISOL, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-188, RHR SUPPLYTEST LINE, AND

VERIFY valve CLOSES by light indication.

[17] RECORD leakage flow from Step 6.3.22[14] on Appendix D,Reactor Boundary Leakage Log.

Page 165: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 163 of 202

Date

6.3.23 Backflow Leakage of 2-CKV-63-560, SIS LI CL INJ CHECK

[1] DEPRESS 2-HS-63-187, TEST LINE ISOL, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-187, RHR SUPPLYTEST LINE, AND

VERIFY valve OPENS by light indication.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[2] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[3] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[4] ISOLATE the Flow Indicator used in the previous step.

Page 166: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 164 of 202

Date

6.3.23 Backflow Leakage of 2-CKV-63-560, SIS LI CL INJ CHECK(continued)

[5] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.23[3], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.23[3] - M&TE Error

-_ = GPM1st

Cv

[6] DEPRESS 2-HS-63-117, SI PMPS TO CL 1, at 2-XS-63-1 00,CKV LEAK TEST, to OPEN 2-FCV-63-117, SIS CL 1 CHECKVLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[7] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[8] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 167: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System - 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 165 of 202

Date

6.3.23 Backflow Leakage of 2-CKV-63-560, SIS LI CL INJ CHECK(continued)

[9] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.23[8]:

Corrected Total Leakage = Step 6.3.23[8] + M&TE Error

+ = GPM1st

Cv

[10] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[11] DEPRESS 2-HS-63-117, SI PMPS TO CL 1, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-117, SIS CL 1 CHECKVLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[12] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[13] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 168: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 166 of 202

Date

6.3.23 Backflow Leakage of 2-CKV-63-560, SIS L1 CL INJ CHECK(continued)

[14] CALCULATE 2-CKV-63-560, SIS Li CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-560 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.23[9]

( )Step 6.3.23[5]

- ( )

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[15] VERIFY the leakage flow for 2-CKV-63-560, SIS LI CL INJCHECK, recorded in Step 6.3.23[14] is less than or equal to5.0 gpm. (ACC. CRIT. 5.0D.22)

[16] RECORD leakage flow from Step 6.3.23[14] on Appendix D,Reactor Boundary Leakage Log.

Page 169: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 167 of 202

Date

6.3.24 Backflow Leakage of 2-CKV-63-561, SIS L2 CL INJ CHECK

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.24[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.24[2] - M&TE Error

-_ = GPM1 st

Cv

Page 170: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 168 of 202

Date

6.3.24 Backflow Leakage of 2-CKV-63-561, SIS L2 CL INJ CHECK(continued)

NOTE

The following step will provide leakage path for testing 2-CKV-63-561, SIS L2 CL INJCHECK.

[51 DEPRESS 2-HS-63-97, SI PMPS TO CL 2, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-97, SIS CL 2 CHECKVLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.24[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.24[7] + M&TE Error

+ - GPM1st

CV

Page 171: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 169 of 202

Date

6.3.24 Backflow Leakage of 2-CKV-63-561, SIS L2 CL INJ CHECK(continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[10] DEPRESS 2-HS-63-97, SI PMPS TO CL 2, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-97, SIS CL 2 CHECKVLV LEAK TEST, and

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-561, SIS L2 CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-561 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.24[8]

( )Step 6.3.24[4]

- (. ) -

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[14] VERIFY the leakage flow for 2-CKV-63-561, SIS L2 CL INJCHECK, recorded in Step 6.3.24[13] is less than or equal to5.0 gpm. (ACC. CRIT. 5.0D.23)

[15] RECORD leakage flow from Step 6.3.24[13] on Appendix D,Reactor Boundary Leakage Log.

Page 172: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 170 of 202

Date

6.3.25 Backflow Leakage of 2-CKV-63-562, SIS L3 CL INJ CHECK

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.25[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.25[2] - M&TE Error

-_ = GPM1st

CV

Page 173: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 171 of 202

Date

6.3.25 Backflow Leakage of 2-CKV-63-562, SIS L3 CL INJ CHECK(continued)

NOTE

The following step will provide leakage path for testing 2-CKV-63-562, SIS L3 CL INJCHECK.

[51 DEPRESS 2-HS-63-79, SI PMPS TO CL 3, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-79, SIS CL 3 CHECKVLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.25[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.25[7] + M&TE Error

- + = GPM1 st

CV

Page 174: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 172 of 202

Date

6.3.25 Backflow Leakage of 2-CKV-63-562, SIS L3 CL INJ CHECK(continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG, Panel 2-M-5.

Test Pressure psig

[10] DEPRESS 2-HS-63-79, SI PMPS TO CL 3, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-79, SIS CL 3 CHECKVLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-562, SIS L3 CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-562 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.25[8] Step 6.3.25[4]

() _ _ _ _-

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[14] VERIFY the leakage flow for 2-CKV-63-562, SIS L3 CL INJCHECK, recorded in Step 6.3.25[13] is less than or equal to5.0 gpm. (ACC. CRIT. 5.OD.24)

[15] RECORD leakage flow from Step 6.3.25[13] on Appendix D,Reactor Boundary Leakage Log.

Page 175: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 173 of 202

Date

6.3.26 Backflow Leakage of 2-CKV-63-563, SIS L4 CL INJ CHECK

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test line leakage flow indicated by

2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.26[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.26[2] - M&TE Error

-_ = GPM1 st

Cv

Page 176: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 174 of 202

Date

6.3.26 Backflow Leakage of 2-CKV-63-563, SIS L4 CL INJ CHECK(continued)

NOTE

The following step will provide leakage path for testing 2-CKV-63-563, SIS L4 CL INJCHECK.

[5] DEPRESS 2-HS-63-69, SI PMPS TO CL 4, at 2-XS-63-100,CKV LEAK TEST, to OPEN 2-FCV-63-69, SIS CL 4 CHECKVLV LEAK TEST, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.26[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.26[7] + M&TE Error

- + = GPM1st

CV

Page 177: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 175 of 202

Date

6.3.26 Backflow Leakage of 2-CKV-63-563, SIS L4 CL INJ CHECK(continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG, Panel 2-M-5.

Test Pressure psig

[10] DEPRESS 2-HS-63-69, SI PMPS TO CL 4, at 2-XS-63-1 00,CKV LEAK TEST, to CLOSE 2-FCV-63-69, SIS CL 4 CHECKVLV LEAK TEST, AND

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-563, SIS L4 CL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-563 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.26[8] Step 6.3.26[4]

() _ _ _ _=

GPM

Calculations Performed ByInitials Date

Calculations Verified ByInitials Date

[14] VERIFY the leakage flow for 2-CKV-63-563, SIS L4 CL INJCHECK, recorded in Step 6.3.26[13] is less than or equal to5.0 gpm. (ACC. CRIT. 5.OD.25)

[15] RECORD leakage flow from Step 6.3.26[13] on Appendix D,Reactor Boundary Leakage Log.

Page 178: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 176 of 202

Date

6.3.27 Backflow Leakage of 2-FCV-74-1, RHR SYSTEM ISOLATIONVALVE and 2-FCV-74-9, RHR SYSTEM ISOLATION BYPASSVALVE

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test line leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Test Line Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

Page 179: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 177 of 202

Date

6.3.27 Backflow Leakage of 2-FCV-74-1, RHR SYSTEM ISOLATIONVALVE and 2-FCV-74-9, RHR SYSTEM ISOLATION BYPASSVALVE (continued)

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.27[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.27[2] - M&TE Error

-_ = GPM1st

Cv

[5] DEPRESS 2-HS-63-186, BETWEEN FCV-74-2, at2-XS-63-100, CKV LEAK TEST, to OPEN 2-FCV-63-186, RHRSUPPLY TEST LINE, and

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

Page 180: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 178 of 202

Date

6.3.27 Backflow Leakage of 2-FCV-74-1, RHR SYSTEM ISOLATIONVALVE and 2-FCV-74-9, RHR SYSTEM ISOLATION BYPASSVALVE (continued)

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.27[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.27[7] + M&TE Error

+ = GPM

1st

Cv

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[10] DEPRESS 2-HS-63-186, BETWEEN FCV-74-2, at2-XS-63-100, CKV LEAK TEST, to CLOSE 2-FCV-63-186,RHR SUPPLY TEST LINE, AND

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

Page 181: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 179 of 202

Date

6.3.27 Backflow Leakage of 2-FCV-74-1, RHR SYSTEM ISOLATIONVALVE and 2-FCV-74-9, RHR SYSTEM ISOLATION BYPASSVALVE (continued)

[13] CALCULATE combined backflow leakage 2-FCV-74-1, RHRSYSTEM ISOLATION VALVE and 2-FCV-74-9, RHR SYSTEMISOLATION BYPASS VALVE at test pressure as follows:

Combined Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.27[8] Step 6.3.27[4]

GPM

Calculations Performed ByInitials Date

Calculations Verified By

Initials Date

[14] VERIFY the combined leakage flow for 2-FCV-74-1, RHRSYSTEM ISOLATION VLV, and 2-FCV-74-9, RHR SYSTEMISOLATION BYPASS VLV, recorded in Step 6.3.27[13] is lessthan or equal to 5.0 gpm. (ACC. CRIT. 5.00.26)

[15] RECORD leakage flow from Step 6.3.27[13] on Appendix D,Reactor Boundary Leakage Log.

Page 182: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 180 of 202

Date

6.3.28 Backflow Leakage of 2-CKV-63-641, RHR HX DISCH

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test leakage flow indicated by

2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4) CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.28[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.28[2] - M&TE Error

=_ GPM1 st

Cv

Page 183: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 181 of 202

Date

6.3.28 Backflow Leakage of 2-CKV-63-641, RHR HX DISCH (continued)

[5] DEPRESS 2-HS-63-163, SI-RHR TO HL 1, at 2-XS-63-1 00,CKV LEAK TEST, to OPEN 2-FCV-63-163, RCS LP 1 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.28[7]:

Corrected Total Leakage = Step 6.3.28[7] + M&TE Error

- + = GPM

1 st

Cv

Page 184: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 182 of 202

Date

6.3.28 Backflow Leakage of 2-CKV-63-641, RHR HX DISCH (continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[10] DEPRESS 2-HS-63-163, SI-RHR TO HL 1, at 2-XS-63-1 00,CKV LEAK TEST, to CLOSE 2-FCV-63-163, RCS LP 1 HLFEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-641, RHR HX DISCH CHECK backflowleakage at test pressure as follows:

2-CKV-63-641 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.28[8]

( )Step 6.3.28[4]

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[14] VERIFY the leakage flow for 2-CKV-63-641, RHR HX DISCHCHECK, recorded in Step 6.3.28[13] is less than or equal to3.0 gpm. (ACC. CRIT. 5.0D.27)

[15] RECORD leakage flow from Step 6.3.28[13] on Appendix D,Reactor Boundary Leakage Log.

Page 185: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 183 of 202

Date

6.3.29 Backflow Leakage of 2-CKV-63-559, SIS L2 HL INJ CHECK.

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test leakage flow indicated by

2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.29[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.29[2] - M&TE Error

-_ = GPM1st

Cv

Page 186: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 184 of 202

Date

6.3.29 Backflow Leakage of 2-CKV-63-559, SIS L2 HL INJ CHECK.(continued)

[5] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-1 00,CKV LEAK TEST, to OPEN 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.29[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.29[7] + M&TE Error

+ = GPM

1 st

Cv

Page 187: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 185 of 202

Date

6.3.29 Backflow Leakage of 2-CKV-63-559, SIS L2 HL INJ CHECK.(continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[10] DEPRESS 2-HS-63-165, SI-RHR TO HL 2, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-165, RCS LP 2 HLFEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-559,SIS L2 HL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-559 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.29[8]

( )Step 6.3.29[4]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[14] VERIFY the leakage flow for 2-CKV-63-559, SIS L2 HL INJCHECK, recorded in Step 6.3.29[13] is less than or equal to3.0 gpm. (ACC. CRIT. 5.0D.28)

[15] RECORD leakage flow from Step 6.3.29[13] on Appendix D,Reactor Boundary Leakage Log.

Page 188: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 186 of 202

Date

6.3.30 Backflow Leakage of 2-CKV-63-644, RHR HX DISCH

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.30[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.30[2] - M&TE Error

=_ GPM1st

Cv

Page 189: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 187 of 202

Date

6.3.30 Backflow Leakage of 2-CKV-63-644, RHR HX DISCH (continued)

NOTE

The following step will provide the leakage path for testing 2-CKV-63-644, RHR HX DISCHCHECK.

[5] DEPRESS 2-HS-63-164, SI-RHR TO HL 3, at 2-XS-63-1 00,CKV LEAK TEST, to OPEN 2-FCV-63-164, RCS LP 3 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.29[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.29[7] + M&TE Error

+ = GPM

1 st

CV

Page 190: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 188 of 202

Date

6.3.30 Backflow Leakage of 2-CKV-63-644, RHR HX DISCH (continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[10] DEPRESS 2-HS-63-164, SI-RHR TO HL 3, at 2-XS-63-1 00,CKV LEAK TEST, to CLOSE 2-FCV-63-164, RCS LP 3 HLFEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[11] VERIFYIISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-644,RHR HX DISCH CHECK, backflowleakage at test pressure as follows:

2-CKV-63-644 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.30[8]

( )Step 6.3.30[4]

- ( ) -

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[14] VERIFY the leakage flow for 2-CKV-63-644, RHR HX DISCHCHECK, recorded in Step 6.3.30[13] is less than or equal to3.0 gpm. (ACC. CRIT. 5.OD.29)

[15] RECORD leakage flow from Step 6.3.30[13] on Appendix D,Reactor Boundary Leakage Log.

Page 191: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 189 of 202

Date

6.3.31 Backflow Leakage of 2-CKV-63-558, SIS L4 HL INJ

NOTES

1) 2-FI-63-75 has a range of 0-10 gpm. 2-FI-63-76 has a range of 0-1.0 gpm. If the flowis less than or equal to 1.0 gpm, 2-FI-63-76 should be used. If flow is greater than 1.0gpm, 2-FI-63-75 should be used to indicate leakage flow.

2) When placing the Flow Indicators 2-FI-63-75 and 2-FI-63-76 back in service,2-FI-63-75 should be placed in service first to determine background leakage greaterthan 1.0 gpm.

3) Do NOT place 2-FI-63-76 in service if flow is over 1.0 gpm.

[1] PLACE Flow Indicator(s) in service, as required, to determinebackground leakage flow in SIS Test Line.

[2] RECORD the background test leakage flow indicated by2-FI-63-76 (or 2-FI-63-75) at Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63- )

[3] ISOLATE the Flow Indicator used in the previous step.

[4] CALCULATE a corrected background leakage by subtractingthe M&TE error listed below for the flow instrument used inStep 6.3.31[2], but do not record a value less than zero:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Test Line Leakage = Step 6.3.31[2] - M&TE Error

- = _GPM1st

Cv

Page 192: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 190 of 202

Date

6.3.31 Backflow Leakage of 2-CKV-63-558, SIS L4 HL INJ (continued)

[5] DEPRESS 2-HS-63-166, SI-RHR TO HL 4, at 2-XS-63-1 00,CKV LEAK TEST, to OPEN 2-FCV-63-166, RCS LP 4 HLFEED TEST LINE, AND

VERIFY valve OPENS by light indication.

[6] PLACE Flow Indicator(s) in service, as required, to determineleakage flow in SIS Test Line.

[7] WAIT for flow to stabilize, THEN

RECORD the total leakage flow indicated by 2-FI-63-76(or 2-FI-63-75) Panel 2-L-554.

Total Leakage Flow GPM

Flow Indicator Used (2-FI-63-

[8] CALCULATE a corrected test line leakage by adding theM&TE error listed below for the flow instrument used in Step6.3.31[7]:

Instrument M&TE Error

2-FI-63-75 0.1 GPM

2-FI-63-76 0.01 GPM

Corrected Total Leakage = Step 6.3.31[7] + M&TE Error

- + = GPM

1 st

Cv

Page 193: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 191 of 202

Date

6.3.31 Backflow Leakage of 2-CKV-63-558, SIS L4 HL INJ (continued)

[9] RECORD the test pressure indicated by 2-PR-68-340, PZRPRESS-PSIG.

Test Pressure psig

[10] DEPRESS 2-HS-63-166, SI-RHR TO HL 4, at 2-XS-63-100,CKV LEAK TEST, to CLOSE 2-FCV-63-166, RCS LP 4 HLFEED TEST LINE, AND

VERIFY valve CLOSES by light indication.

[11] VERIFY/ISOLATE 2-FI-63-76, SIS LEAK TEST HEADER LOFLOW, at Panel 2-L-554.

[12] VERIFY/ISOLATE 2-FI-63-75, SIS LEAK TEST HEADER HIFLOW, at Panel 2-L-554.

[13] CALCULATE 2-CKV-63-558,SIS L4 HL INJ CHECK, backflowleakage at test pressure as follows:

2-CKV-63-558 Leakage at test pressure =

Total Leakage Flow - Test Line Leakage Flow =

Step 6.3.31 [8]

( )Step 6.3.31 [4]

( )

GPM

Calculations Performed By

Calculations Verified By

Initials Date

Initials Date

[14] VERIFY the leakage flow for 2-CKV-63-558, SIS L4 HL INJCHECK, recorded in Step 6.3.31 [13] is less than or equal to3.0 gpm. (ACC. CRIT. 5.OD.30)

[15] RECORD leakage flow from Step 6.3.31 [13] on Appendix D,Reactor Boundary Leakage Log.

Page 194: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 192 of 202

Date

6.3.31 Backflow Leakage of 2-CKV-63-558, SIS L4 HL INJ (continued)

[16] DEPRESS 2-HS-63-187, TEST LINE ISOL, at 2-XS-63-1 00,CKV LEAK TEST, to CLOSE 2-FCV-63-187, RHR SUPPLYTEST LINE, AND

VERIFY valve CLOSES by light indication.

[17] PLACE 2-HS-63-71A, CKV TEST LINE TO HUT, to CLOSE,AND

VERIFY Valve 2-FCV-63-71, SIS CHECK VLV LEAK TESTISOLATION, is CLOSED by light indication.

[18] PLACE 2-HS-63-84, CKV TEST LINE TO HUT, to CLOSE,AND

VERIFY Valve 2-FCV-63-84, SIS CHECK VLV LEAK TESTISOLATION, is CLOSED by light indication.

[19] CALCULATE total leakage flow by performing Appendix E.Total Reactor Coolant Boundary Leakage.

Page 195: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 193 of 202

Date

7.0 POST-PERFORMANCE ACTIVITIES

[1] VERIFY that Post-test calibration of the M&TE used to recordquantitative acceptance criteria has been satisfactorilyperformed, AND

RECORD the results on Measuring and Test Equipment(M&TE) Log.

[2] VERIFY that Post-test calibration of permanent plantinstruments used to record quantitative acceptance criteria hasbeen satisfactorily performed, AND

RECORD the results on Appendix C, Permanent PlantInstrumentation Log.

[3] NOTIFY the Unit 2 US/SRO of the test completion and Systemalignment.

Page 196: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 194 of 202

Date

8.0 RECORDS

A. QA Records

Completed Test Package

B. Non-QA Records

None

Page 197: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

Safety Injection SystemCheck Valve Test

2-PTI-063-06Rev. 0000Paqe 195 of 202

Appendix A(Page 1 of 1)

TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW

Date

I Additional copies of this table may be made as necessary.

PROCEDURE/ INITIAL AND DATE.INSTRUCTION (N/A for no change)

FSAR

Section 5.2.7.4

Section 3.9.3.2

Table 14.2-1 Sheets 22, 23 &24

2-TSD-63-6

Page 198: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 196 of 202

Appendix B(Page 1 of 1)

TEMPORARY CONDITION LOG

Date

Additional copies of this table may be made as necessary.

ITEM TEMPORARY CONDITION PERFORMED RETURNED TO NORMALNo. DESCRIPTION Step Performed By/Date Step Returned By/Date

No. CV By/Date No. CV By/Date

Page 199: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 197 of 202

Appendix C(Page 1 of 1)

PERMANENT PLANT INSTRUMENTATION LOG

Date

INSTRUMENT CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TESTOR DATE VENTED1 SERVICE1 QUANTITATIVE CAL DATE 2 CALIBRATIONINSTRUMENT ACC CRIT ACCEPTABLE 2

LOOP # INITIAL/DATEINIT/DATE INIT/DATE YES NO

2-FI-63-75

2-FI-63-76

2-PI-63-150

2-PR-68-340

t 1- t I

.1- 4- 4. L J

+ 4- 4- 4

I These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable. (N/A)

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

Page 200: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 198 of 202

Appendix D(Page 1 of 3)

REACTOR BOUNDARY LEAKAGE LOG

Date

RECORD VALVE NO. DESCRIPTION CALCULATE LEAKAGE ACCEPTABLESTEP STEP LEAKAGE6.3.2[24] 2-CKV-63-581 BORON INJ CHECK 6.3.2[23] _ 1.5 GPM

6.3.3[20] 2-CKV-63-543 SIS Li HL INJ CHECK 6.3.3[19] •1.0 GPM

6.3.4[18] 2-CKV-63-640 RHR HX DISCH CHECK 6.3.4[17] < 4.0 GPM

6.3.5[18] 2-CKV-63-545 SIS L3 HL INJ CHECK 6.3.5[17] •1.0 GPM

6.3.6[18] 2-CKV-63-643 RHR HX DISCH CHECK 6.3.6[17] < 4.0 GPM

6.3.7[18] 2-CKV-63-549 SIS L4 HL INJ CHECK 6.3.7[17] _< 1.0 GPM

6.3.8[19] 2-CKV-63-547 SIS L2 HL INJ CHECK 6.3.8[18] _< 1.0 GPM

6.3.9[21] 2-CKV-63-551 SIS Li CL INJ CHECK 6.3.9[20] < 1.0 GPM

6.3.10[18] 2-CKV-63-633 RHR PUMP DISCH CHECK 6.3.10[17] _ 3.0 GPM

6.3.11[18] 2-CKV-63-553 SIS L2 CL INJ CHECK 6.3.11[17] < 1.0 GPM

6.3.12[18] 2-CKV-63-632 RHR PUMP DISCH CHECK 6.3.12[17] -_ 3.0 GPM

6.3.13[18] 2-CKV-63-555 SIS L3 CL INJ CHECK 6.3.13[17] _ 1.0 GPM

6.3.14[18] 2-CKV-63-634 RHR PUMP DISCH CHECK 6.3.14[17] _ 3.0 GPM

6.3.15[18] 2-CKV-63-557 SIS L4 CL INJ CHECK 6.3.15[17] _ 1.0 GPM

6.3.16[18] 2-CKV-63-635 RHR PUMP DISCH CHECK 6.3.16[17] _ 3.0 GPM

6.3.17[29] 2-FCV-74-2 RHR SYSTEM ISOLATION VALVE 6.3.17[26] _ 5.0 GPM2-FCV-74-8 RHR SYSTEM ISOLATION BYPASS

VALVE

Page 201: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 199 of 202

Appendix D(Page 2 of 3)

REACTOR BOUNDARY LEAKAGE LOG

Date

RECORD VALVE NO. DESCRIPTION CALCULATE LEAKAGE ACCEPTABLESTEP STEP LEAKAGE6.3.18[21] 2-CKV-63-622 ACCUM 1 OUT CHECK 6.3.18[19] _< 5.0 GPM6.3.19[19] 2-CKV-63-623 ACCUM 2 OUT CHECK 6.3.19[17] < 5.0 GPM6.3.20[19] 2-CKV-63-624 ACCUM 3 OUT CHECK 6.3.20[17] < 5.0 GPM

6.3.21[21] 2-CKV-63-625 ACCUM 4 OUT CHECK 6.3.21[117] • 5.0 GPM6.3.22[17] 2-CKV-63-586 BORON INJ CHECK CL Li 6.3.22[15] • .75 GPM

2-CKV-63-587 BORON INJ CHECK CL L22-CKV-63-588 BORON INJ CHECK CL L32-CKV-63-589 BORON INJ CHECK CL L4

6.3.23[16] 2-CKV-63-560 SIS Li CL INJ CHECK 6.3.23[15] •5.0 GPM

6.3.24[15] 2-CKV-63-561 SIS L2 CL INJ CHECK 6.3.24[14] < 5.0 GPM6.3.25[15] 2-CKV-63-562 SIS L3 CL INJ CHECK 6.3.25[14] _< 5.0 GPM

6.3.26[15] 2-CKV-63-563 SIS L4 CL INJ CHECK 6.3.26[14] _< 5.0 GPM6.3.27[15] 2-FCV-74-1 RHR SYSTEM ISOLATION VALVE 6.3.27[14] • 5.0 GPM

2-FCV-74-9 RHR SYSTEM ISOLATION BYPASSVALVE

6.3.28[15] 2-CKV-63-641 RHR HX DISCH CHECK 6.3.28[14] < 3.0 GPM

6.3.29[15] 2-CKV-63-559 SIS L2 HL INJ CHECK 6.3.29[14] • 3.0 GPM

Page 202: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 200 of 202

Appendix D(Page 3 of 3)

REACTOR BOUNDARY LEAKAGE LOG

Date

RECORD VALVE NO. DESCRIPTION CALCULATE LEAKAGE ACCEPTABLESTEP STEP LEAKAGE6.3.30E15] 2-CKV-63-644 RHR HX DISCH CHECK 6.3.30j14] STE 3.0 GPM6.3.31[15] 2-CKV-63-558 SIS L4 HL INJ CHECK 6.3.31[14] <_ 3.0 GPM

Page 203: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 201 of 202

Appendix E(Page 1 of 2)

TOTAL REACTOR COOLANT BOUNDARY LEAKAGE

Date

INSTRUCTIONS FOR CALCULATING TOTAL RCS BOUNDARY LEAKAGE

NOTE

The calculation of Total RCS Boundary Leakage is for information only.

Sheet 2, is divided into two columns of valves; "VALVE(S) IN SERIES", (col 1),which are directly in series with the RCS boundary valve, and "RCS BOUNDARYVALVES" (col 4), which are direct boundary valves adjacent to the RCS.

As can be seen by the table, a boundary valve may have more than one valve inseries. For example, 2-CKV-63-560 has three valves in series; 2-CKV-63-551,2-CKV-63-622, and 2-CKV-63-633.

A. Record the LEAKAGE valves from Appendix D to the applicable "VLV LKG"column, (col 2 or col 5), for valves or valve combinations identified on sheet 2 ofAppendix E.

B. Total the valve leakage of the "series" of valves applicable to the RCSBoundary Valve and Record the sums in the "TOTAL SERIES VLV LKG", (col3).

Example: 2-CKV-63-641 has two series valves, 2-CKV-63-543 and 2-CKV-63-640. The sum of the valve leakage of those two valves will beentered in col 3.

C. Compare the valve leakage of the RCS Boundary valves, (col 5), to that of itsassociated series valve(s) leakage, (col 2 or col 3), and Record the lesserleakage value of the two in the "RCS BOUND LKG"' (col 6).

D. Add the "RCS BOUND LKG" column to determine Total RCS Leakage.

Page 204: Watts Bar, Unit 2 - Submittal of Pre-op Test Instruction ...

WBN Safety Injection System 2-PTI-063-06Unit 2 Check Valve Test Rev. 0000

Page 202 of 202

Appendix E(Page 2 of 2)

TOTAL REACTOR COOLANT BOUNDARY LEAKAGE

Date

VALVE(S) IN SERIES VLV TOTAL RCS BOUNDARY VALVES VLV RCSLKG SERIES LKG BOUND

COL 1 VLV LKG COL 4 LKGCOL 2 COL 3 COL 5 COL 6

2-CKV-63-581 N/A 2-CKV-63-5862-CKV-63-5872-CKV-63-5882-CKV-63-589

2-CKV-63-543 2-CKV-63-6412-CKV-63-6402-CKV-63-545 2-CKV-63-6442-CKV-63-6432-CKV-63-549 2-CKV-63-558

2-CKV-63-547 2-CKV-63-5592-CKV-63-551 2-CKV-63-5602-CKV-63-6222-CKV-63-633

2-CKV-63-553 2-CKV-63-5612-CKV-63-6232-CKV-63-632

2-CKV-63-555 2-CKV-63-562

2-CKV-63-624

2-CKV-63-6342-CKV-63-557 2-CKV-63-5632-CKV-63-6252-CKV-63-6352-FCV-74-2 N/A 2-FCV-74-12-FCV-74-8 2-FCV-74-9

6.3.31[19]TOTAL RCSLEAKAGE

Calculations Performed By:

Calculations Verified By:

Initials

Initials

Date

Date

r


Recommended