Webinar: The Project Manager in the NEC4 ECC what’s new and different? Richard Patterson and Robert Gerrard Delivering real value
Transcript
  • Webinar: The Project Manager in the NEC4 ECC

    what’s new and different?

    Richard Patterson and Robert Gerrard

    Delivering real value

  • Speakers

    The Project Manager in the NEC4 ECC: what’s new and different? 2

    Richard Patterson NEC4 drafter, Mott MacDonald

    Robert Gerrard NEC Users’ Group Secretary and NEC4 drafter

  • NEC4

    The Project Manager in the NEC4 ECC: what’s new and different? 3

    12 years of learning

    Significant evolution

    Not revolution

    The Project Manager in the NEC4 ECC: what’s new and different?

  • Agenda

    The Project Manager in the NEC4 ECC: what’s new and different? 4

    New and

    changed options

    Language

    Detail

    1-9

    1 2

    3

    5

    6

    4

  • NEC4 ECC

    The Project Manager in the NEC4 ECC: what’s new and different? 5

    New and changed

    ECC options

    W1 & W2 – Seniors Reps. first

    X8 Undertakings to Client and others

    W3 – Dispute Avoidance Board

    X9 Transfer of rights

    ‘collateral warranties’

  • NEC4 ECC

    The Project Manager in the NEC4 ECC: what’s new and different? 6

    New and changed

    ECC options

    Information Model

    Information Model Requirements

    Information Execution Plan

    X10 Information modelling

    X4 Ultimate holding company guarantee

    IP and license to use

    Retention of docs

    PII

    X11 Termination by the Client

    Contractor can propose changes to Client’s Scope to reduce OPEX

    Do a deal on Scope, Prices, Completion Date

    X22 ECI X21 Whole life cost

    Due skill and care

    X15 The Contractor’s design

  • NEC4 ECC

    The Project Manager in the NEC4 ECC: what’s new and different? 7

    Language

    X12 now ‘Multiparty

    collaboration’

    Risk Register (RIP) is ‘Early Warning Register’

    Scope

    ‘Employer’ is ‘Client’

    ‘Employer’s risk’ is ‘Client’s liability’

    10.1 split in two

  • The Project Manager in the NEC4 ECC: what’s new and different? 8

    Core clauses

    Detail

    1-9

    1 2

    3

    5

    6

    4

  • The Project Manager in the NEC4 ECC: what’s new and different? 9

    Core clauses

    General • Prompt for Scope to specify

    ‘communication system’ • PM prepares first Early Warning Register • ‘early warning meetings’ at ‘no longer

    interval’ than in Contract Data • Contractor’s proposals to change Client’s

    Scope • Options C and D – Prices not reduced – as

    ECC3 • Options A and B – if accepted Contractor gets

    the ‘value engineering percentage’ of saving

    1

    1

  • The Project Manager in the NEC4 ECC: what’s new and different? 10

    Core clauses

    The Contractor’s main responsibilities • Subcontracts – detailed improvements

    2

    2

  • The Project Manager in the NEC4 ECC: what’s new and different? 11

    Core clauses

    Time • Programme in form as in Scope • No response to a submitted programme

    in two weeks? • Contractor may prompt • Another week of silence? • Programme treated as accepted

    • Acceleration • Either can propose • Three weeks for quotation and PM’s

    response

    3 3

  • The Project Manager in the NEC4 ECC: what’s new and different? 12

    Core clauses

    Rebranded ‘Quality management’ • As PSC • Quality

    o quality management system as requirements in Scope

    o quality policy statement • For acceptance of PM

    o quality plan • For acceptance of PM • Changes for acceptance of PM • PM may instruct C to correct

    failures to comply

    4 4

  • The Project Manager in the NEC4 ECC: what’s new and different? 13

    Money

    Payment • Contractor application for payment

    required to get paid • Fee – no separate ‘subcontracted fee

    percentage’ • Defined Cost – no exclusion of cost of

    preparing compensation events (Options A and B)

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 14

    Money

    Final assessment • By PM four weeks after Defects

    Certificate • Contractor may prepare if PM has not

    done so • ‘conclusive evidence’ of final amount due

    – unless…….

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 15

    Money

    Final assessment…. more • WI or W2

    • referred to the Senior Representatives within 4 weeks

    • On and up to Adjudicator if Senior Representatives have not agreed within 3 weeks

    • On and up to tribunal within 4 weeks of Adjudicator’s decision

    • W3 • On and up to Dispute Avoidance Board • On and up to tribunal within 4 weeks of

    DAB’s recommendation

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 16

    Money

    A and B ‘Short Schedule of Cost Components’ • People based on People Rates • Charge based on ‘percentage for people

    overheads’ deleted • Payments to Subcontractors now allowed • Design and manufacture – no overhead

    %

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 17

    Money

    C,D,E Schedule of Cost Components • Just the one ‘Schedule of Cost

    Components’ • Charge based on ‘percentage for

    Working Areas overhead’ deleted • Payments to Subcontractors (now in SCC) • Design and manufacture – no overhead

    %

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 18

    Money

    C,D,E Finalisation of Defined Cost • Contractor notifies when ‘a part’ of

    Defined Cost is finalised • PM responds within 13 weeks • Contractor responds to ‘ comments

    within 4 weeks • PM accepts or corrects within 4 weeks • If PM misses a response time,

    Contractor’s assessment treated as correct.

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 19

    Money

    5

    5

  • The Project Manager in the NEC4 ECC: what’s new and different? 20

    Core clauses

    Compensation events • Additional compensation events in

    Contract Data part one • Proposed instructions given its own

    clause • New CE if quotation for proposed

    instruction not accepted • ‘dividing date’ between ‘actual’ and

    ‘forecast’ Defined Cost • delays assessed using Accepted

    Programme ‘current at the dividing date’

    6

    6

  • Detail

    1-9

    NEC4 ECC

    21

    New and

    changed options

    Language

    1 2

    3

    5

    6

    4

    The Project Manager in the NEC4 ECC: what’s new and different?

  • Poll……..Questions?

  • NEC Users’ Group Annual Seminar 2017 22 June - County Hall, London

    Official launch event of NEC4

    Attendees will receive a copy of the NEC4 ECC

    10% discount

    webinar10

  • 24

    Next NEC4 webinar

    NEC4 Alliance Contract: Increasing collaboration and integration 28 June 2017 – 13:00 BST

    neccontract.com/alliancewebinar

    Peter Higgins Chair of the NEC4 Contract Board

    Ian Heaphy NEC4 Contract Board

  • The Project Manager in the NEC4 ECC: what’s new and different?

    NEC4 training

    NEC4: Introduction to the Engineering

    and Construction

    Contract (ECC)

    NEC4: Introduction to

    the Design, Build and Operate

    Contract (DBO)

    NEC4: Introduction to

    the Term Service Contract (TSC)

    London 27 June 2017 03 July 2017

    London 28 June 2017

    London 29 June 2017

    neccontract.com/nec4training

  • Pre-order NEC4

    Pre-order your hard-copies of NEC4 ahead of launch guaranteeing you’ll have it dispatched following the release.

    There’s also a special 10% discount for pre-orders.

    Promocode

    NEC4PRE

    neccontract.com The Project Manager in the NEC4 ECC: what’s new and different?