+ All Categories
Home > Documents > Week 8 - Road Construction 1

Week 8 - Road Construction 1

Date post: 12-Jan-2016
Category:
Upload: ardita-buzhala
View: 16 times
Download: 0 times
Share this document with a friend
Description:
Road Construction 1
Popular Tags:
36
Sabrina Fawzia [email protected] L Block Room 309 ROADWORKS
Transcript
Page 1: Week 8 - Road Construction 1

Sabrina [email protected]

L Block Room 309

ROADWORKS

Page 2: Week 8 - Road Construction 1

Learning outcome

• Basic techniques of road construction• Plant and equipment selection• Types of pavements• Construction sequences• Mass haul diagram

Page 3: Week 8 - Road Construction 1

PLANT & EQUIPMENTEARTHMOVING MACHINERY• DOZERS• SCRAPERS• EXCAVATORS • TIP TRUCKS

COMPACTION EQUIPMENT• SHEEPSFOOT ROLLERS• TAMPING ROLLERS• SMOOTH-DRUM VIBRATORY SOIL COMPACTORS• PAD-DRUM VIBRATORY SOIL COMPACTORS• PNEUMATIC TIRED ROLLERS

Page 4: Week 8 - Road Construction 1

PLANT & EQUIPMENT (CONT.)

OTHER PLANT & EQUIPMENT

• WATER DISTRIBUTOR• DRILL & BLAST EQUIPMENT • PAVING MACHINES• BITUMEN SPRAYERS & EQUIPMENT• DE-WATERING EQUIPMENT

Page 5: Week 8 - Road Construction 1

100101

101102

102

103

106

105

104

No cut / no fill line

CUTTING FILL

Elevation

Plan

ROAD DESIGNNatural surface

Road gradeline

Page 6: Week 8 - Road Construction 1

Cross SectionExcavation (Cut)

ROAD DESIGN

Cross SectionEmbankment (Fill)

Page 7: Week 8 - Road Construction 1

Subgrade

Cross SectionFlexible Pavements (Typical)

Wearing CourseAsphalt / Bitumen Seal)

Base course

Sub-base course

Lower Sub-base course

Subgrade

Batter

Page 8: Week 8 - Road Construction 1

Subgrade strength

• Removing poor material in cutting and replacing with selected fill.

• Ensure compaction to a high dry density.• Providing adequate subsoil drainage.

Page 9: Week 8 - Road Construction 1

Why we need Subsoil Drainage

Page 10: Week 8 - Road Construction 1

Drainage pipe

Page 11: Week 8 - Road Construction 1

Sub soil drain

Page 12: Week 8 - Road Construction 1

Subsoil drainage location

Page 13: Week 8 - Road Construction 1

Soil stabilisation

• Stabilisation refers to any treatment of the soil that increases its strength.

• Stabilisation may be achieved by various agents, which include cement, lime, bitumen.

Page 14: Week 8 - Road Construction 1

California bearing ratio

C.B.R. = Test load/Standard load

Page 15: Week 8 - Road Construction 1

Types of pavements

Page 16: Week 8 - Road Construction 1

Flexible pavement

• Flexible pavement

Consists of several layers of materials Flexible pavement distributes loads over a

smaller area. It relies on a combination of layers for

transmitting load to the subgrade

Page 17: Week 8 - Road Construction 1

Rigid pavement

Rigid Pavement Consists of a concrete slab resting on subbase

material Distribute the load over a relatively wide area of

subgrade

Page 18: Week 8 - Road Construction 1

Contraction joints

A contraction joint is provided to controlcracking in rigid pavementsTransverse contraction joints can be cut at

right angles or skewed to the direction oftraffic flow to help with load transferDowel bars are used to transfer loads

across the joints.

Page 19: Week 8 - Road Construction 1

Expansion joints

• Expansion joints are constructed to allow pavements to expand and contract without damage to adjacent pavements or structures

Page 20: Week 8 - Road Construction 1

Construction joints

• A construction joint is a joint between slabs that results when concrete is placed at different times.

• This type of joint can be further broken down into transverse and longitudinal construction joints

Page 21: Week 8 - Road Construction 1

CONSTRUCTION SEQUENCEESTABLISHMENT• COMPOUNDS AND OFFICES

ROADWORKS• SURVEY• INVESTIGATION WORKS • ENVIRONMENTAL WORKS• CLEARING / STRIP VEGETATION & STOCKPILE

TOPSOIL• INSTALL MAJOR DRAINAGE STRUCTURES• BULK EARTHWORKS (CUTS AND FILLS)• INCLUDE IMPORT FILL (SHORTFALL FROM CUTS)• BOX FOR PAVEMENTS

Page 22: Week 8 - Road Construction 1

CONSTRUCTION SEQUENCE (CONT.)ROADWORKS (CONT.)

• INSTALL SUB-BASE PAVEMENTS • INSTALL BASE COURSE PAVEMENTS

(ALTERNATIVES ASPHALT OR CONCRETE PAVEMENTS)

• INSTALL PAVEMENT DRAINAGE• INSTALL WEARING SURFACE

(ASPHALT OR SPRAYED BITUMEN / AGGREGATE)• BATTER SLOPE PROTECTION (TOSOIL RE-

SPREAD & LANDSCAPING WORKS)• INSTALL ROAD HARDWARE / FURNITURE• LINE MARKING & ROAD SIGNS

Page 23: Week 8 - Road Construction 1

SURVEY

• SET OUT HORIZONTAL AND VERTICAL CURVES

• SET OUT SUPER ELEVATIONS (CROSSFALLS)

• MONITOR EARTHWORKS DURING CONSTRUCTION

• PREPARE “AS CONSTRUCTED” DRAWINGS

Page 24: Week 8 - Road Construction 1

EXISTING SUBSTRATE

PREPARING SUBSTRATE BENEATH FILLS(GROUND SURFACE TREATMENT)

150

PROOF ROLL EXISTING GROUND SURFACE

EXPOSE SOFT SPOTS

EXCAVATE SOFT SPOTS

FILL AND COMPACT SOFT SPOTS

REMOVE TOP SOIL & VEGETATION

TOP SOIL

CONSTRUCTION PROCEDURES

Page 25: Week 8 - Road Construction 1

EXCAVATIONS (CUTS) IN OTHERTHAN ROCK (OTR) AND IN ROCK

CONSTRUCTION PROCEDURES

DRILL AND BLAST

OTR EXCAVATION

REMOVED BY SCRAPERSDOZERS, EXCAVATORS

ROCK EXCAVATION

REMOVED BY DRILLINGAND BLASTING, RIPPING,LOADING OUT BY TRUCKS

Page 26: Week 8 - Road Construction 1

PREPARED SUBSTRATE

WIN FILL MATERIAL (FROM CUTS OR IMPORTED)

TRANSPORT FILL TO SITE

SPREAD FILL ON PREPARED SUBSTRATE

COMPACT FILL WHILE CONTROLLING MOISTURE

EMBANKMENTS (FILLS)

TRIM TO PROFILE

CONSTRUCTION PROCEDURES

Page 27: Week 8 - Road Construction 1

CUT OUT BOX

PREPARED SUBSTRATE

PLACE AND COMPACT GRAVEL SUB-BASE

GRAVEL PAVEMENTS

ROLL BOX / PREPARE SUBGRADE

PLACE & COMPACT GRAVEL BASE

FINAL TRIM TO GRAVEL PAVEMENTS

CONSTRUCTION PROCEDURES

COMPACTED EMBANKMENT

Page 28: Week 8 - Road Construction 1

CONSTRUCTION PROCEDURES

GUARD RAILS

DELINEATOR POSTS(GUIDE POSTS)

MULCHING OR GRASSING TOSTABLISE BATTERS

COMPACT ASPHALTPLACE ASPHALT WEARING COURSE

WEARING SURFACE AND ROAD FURNITURE

COMPLETED EMBANKMENT& GRAVEL PAVEMENTS

Page 29: Week 8 - Road Construction 1

SLOPE PAVING / PROTECTION

SURFACE DRAINS

PLACE & COMPACT PAVEMENTS & WEARING COURSE

CONSTRUCTION PROCEDURESIN EXCAVATIONS (CUTS)

ROLL BOX / PREPARE SUBGRADEROAD FURNITURE

SUB-SURFACE DRAINS

CATCH DRAINS

Page 30: Week 8 - Road Construction 1

REINFORCED CONCRETE BASE

BOX CULVERTWING WALLS

POROUSBACKFILL

HIGHLY COMPACTEDBACKFILL

COMPACTED BACKFILL

EMBANKMENT FORMATION

Plan

Section(Through Watercourse)

STREAM

BOX CULVERTS

Page 31: Week 8 - Road Construction 1

Box culvert

Page 32: Week 8 - Road Construction 1

Mass haul diagram

• The mass haul diagram is an excellent method of analysing linear earthmoving operation.

Page 33: Week 8 - Road Construction 1

MASS HAUL• CALCULATE QUANTITIES FOR CUT AND FILL FOR

SEGMENTS TYPICALLY AT REGULAR INTERVALS (EVERY 50m OR 100m)

• FOR EACH SEGMENT CALCULATE QUANTITY CUT TO FILL WITHIN SEGMENT

• FOR EACH SEGMENT CALCULATE QUANTITY EXCESS CUT OR SHORTFALL FILL

• DETERMINE MOST EFFICIENT HAULS FOR CUT TO FILL OPERATION

• TYPES OF EQUIPMENT SHOULD BE CONSIDERED FOR ACCOMPLISHING THE WORK.

Page 34: Week 8 - Road Construction 1

MASS HAUL DIAGRAM

Chainage (m)

0-100

100-200

200-300

300-400

400-500

500-600

600-700

700-800

Totals

Cut (m3) 200 1000 3000 2000 0 100 1000 0 7300 m3

Fill (compacted Vol m3)

500 300 0 500 3500 3500 500 500 9300 m3

Fill (m3) 575 345 0 575 4025 4025 575 575 10695 m3

Cut to Fill<100m

200 345 0 575 0 100 575 0 1795 m3

Cut less Fill i.e Excess Cut +ve shortfall Fill -ve

-375 280 3280 4705 680 -3245 -2820 -3395

Page 35: Week 8 - Road Construction 1

MASS HAUL DIAGRAM (CONT.)

Page 36: Week 8 - Road Construction 1

Balanced line

• A balanced line is a horizontal line of specific length that intersects the mass diagram in two places.

• The balance line can be constructed so that its length is the maximum haul distance for different types of equipment.


Recommended