Date post: | 29-Dec-2015 |
Category: |
Documents |
Upload: | nrl-nbl-rmln |
View: | 389 times |
Download: | 22 times |
Copyright - R.Turton and J. Shaeiwitz 2008
1
Chapter 7 - Capital Cost Estimation
Chemical Engineering Department
West Virginia University
Copyright - R.Turton and J. Shaeiwitz 2008
2
Outline Types of estimate Adjusting costs for changes in capacity Adjusting costs for changes in time Total plant cost estimates
Direct, indirect, etc. Lang Factors Module cost approach Effect of temperature and pressure
Capcost program
Copyright - R.Turton and J. Shaeiwitz 2008
3
Types of Capital Cost Estimate 1. Order of Magnitude Estimate
(Feasibility) + 40%, - 20% BFD , Process Modification
2. Study Estimate / Major Equipment + 30%, - 20% PFD , Cost Chart
Copyright - R.Turton and J. Shaeiwitz 2008
4
Types of Capital Cost Estimate (cont’d)
3. Preliminary Design (Scope) Estimate + 25%, - 15% PFD , vessel sketches , equip. diagrams
4. Definitive (Project Control) Estimate + 15%, - 7% PFD , P&ID, all vessel sketches, equip.
diagrams, preliminary isometrics
Copyright - R.Turton and J. Shaeiwitz 2008
5
Types of Capital Cost Estimates (cont’d)
Detailed (Firm or Contractors) Estimate + 6%, - 4% Everything included – ready to go to
construction phase Estimate low so actual cost will be high (+) Estimate high so actual cost will be low (-)
Why is + # > - #.?
Copyright - R.Turton and J. Shaeiwitz 2008
6
Cost of Estimate – See Also Table 7.2
1
23
5
4
Accuracy
Cost of Estimate (Time)
Copyright - R.Turton and J. Shaeiwitz 2008
7
Estimating Purchased Equipment Costs
Vendor quote Most accurate
- based on specific information- requires significant engineering
Use previous cost on similar equipment and scale for time and size
Reasonably accurate - beware of large extrapolation- beware of foreign currency
Use cost estimating charts and scale for time Less accurate Convenient
Copyright - R.Turton and J. Shaeiwitz 2008
8
Effect of Size (Capacity)n
b
a
b
a
A
A
C
C
Cost Equipment CostAttribute - Size
Cost Exponent
naa KAC
bn
b
CK
A
(7.1)
where
(7.2)
Copyright - R.Turton and J. Shaeiwitz 2008
9
Effect of Size (Capacity) cont.
n = 0.4 – 0.8 Typically Often n ~ 0.6 and we refer to Eq.
(7.1) as the (6/10)’s Rule Assume all equipment have n =
0.6 in a process unit and scale-up using this method for whole processes Order-of-Magnitude estimate
Copyright - R.Turton and J. Shaeiwitz 2008
10
Example 1
A New Plant Ordered a Set of Floating Head Heat Exchangers (Area = 100 m2) cost $92,000. What Would Cost be for a Heat Exchanger for Similar Service if Area = 50 m2 and n = 0.44 ?
Copyright - R.Turton and J. Shaeiwitz 2008
11
Example 1 - Solutionn
b
a
b
a
A
A
C
C
n
b
aba
A
ACC
$67,300aC
100 m2 Exchanger is not twice as expensive as a 50 m2 exchanger
Economy of Scale
44.0
100
50000,92
Copyright - R.Turton and J. Shaeiwitz 2008
12
Effect of Time Time increases – cost increases (inflation) Inflation is measured by cost indexes -
Figure 7.3 Chemical Engineering Plant Cost Index
(CEPCI) Marshall and Swift Process Industry Index
Numbers based on “basket of goods” typical for construction of chemical plants - Table 7.5
Copyright - R.Turton and J. Shaeiwitz 2008
13
Copyright - R.Turton and J. Shaeiwitz 2008
14
Table 7.5: The Basis for the Chemical Engineering Plant Cost Index
Components of Index Weighting of Component (%)
Equipment, Machinery and Supports: (a) Fabricated Equipment(b) Process Machinery(c) Pipe, Valves, and Fittings(d) Process Instruments and Controls(e) Pumps and Compressors(f) Electrical Equipment and Materials (g) Structural Supports, Insulation, and
Paint
371420
775
10100 61 % of total
Erection and Installation Labor 22
Buildings, Materials, and Labor 7
Engineering and Supervision 10
Total 100
Copyright - R.Turton and J. Shaeiwitz 2008
15
Equation for Time Effect
C = Cost I = Value of cost index 1,2 = Represents points in time at
which costs required or known and index values known
1
212 I
ICC
Copyright - R.Turton and J. Shaeiwitz 2008
16
Example 2
Cost of vessel in 1993 was 25,000, what is estimated cost today (Sept 2007 – CEPCI = 500)?
Copyright - R.Turton and J. Shaeiwitz 2008
17
Example 2 - Solution
820,34$359
500000,25
19931993
I
ICC now
now
Copyright - R.Turton and J. Shaeiwitz 2008
18
Example 3 - Accounting for Time and Size
2 heat exchangers, 1 bought in 1990 and the other in 1995 for the same service
A BArea = 70 m2 130 m2 Time= 1990 1995Cost = 17 K 24 KI = 358 381
Copyright - R.Turton and J. Shaeiwitz 2008
19
Example 3 (cont’d)
What is the Cost of a 80 m2 Heat Exchanger Today ? (I = 500)
Copyright - R.Turton and J. Shaeiwitz 2008
20
Example 3 - Solution
Must First Bring Costs to a Common TimeA = 70
A = 130
500(2007) 17 $23,743
358aC
500(2007) 24 $31,496
381bC
Copyright - R.Turton and J. Shaeiwitz 2008
21
Example 3 - Solution (cont’d)
nKAC $23,743 (70)nK$31,496 (130)nK
log 31,496 log(23,743)0.4565
log 130 log(70)n
0.4565
23,743$3,414
70n
CK
A
0.45653,414 80 $25,235C
Copyright - R.Turton and J. Shaeiwitz 2008
22
Example 4
Date Vessel Capacity
(m3)
Purchased Cost(pounds sterling = £)
Exchange Rate
1993 75 £ 7,800 $ 1.40/£
1998 155 £ 13,800 $ 1.65/£
2007 120 $ 2.00/£
How much ($) would the new vessel cost?
Copyright - R.Turton and J. Shaeiwitz 2008
23
Total Cost of Plant
Purchased cost – equipment f.o.b. Installed cost – Often 3 to 8 times
larger than purchased cost
Copyright - R.Turton and J. Shaeiwitz 2008
24
Installed Cost of Equipment (Table 7.6)
1. Direct Project Expenses Equipment Material for installation Labor for installation
2. Indirect Project Expenses Freight, insurance, and taxes Construction overhead Contractor engineering expenses
Copyright - R.Turton and J. Shaeiwitz 2008
25
Installed Cost of Equipment Table 7.6 (cont’d)
Contingency and Fee Contingency Contractor fee
Auxiliary Facilities Site development Auxiliary buildings Off-sites and utilities
Copyright - R.Turton and J. Shaeiwitz 2008
26
Lang Factors Table 7.7 Use multiplier depending on type of
plant to escalate equipment costs to installed costs
Flang = 4.74 Fluid processing plant
= 3.63 Solid-Fluid processing plant
= 3.10 Solid processing plant
Copyright - R.Turton and J. Shaeiwitz 2008
27
Lang Factors (cont’d)
n
ipiLangTM CFC
1
Purchased Cost of Major EquipmentFrom Preliminary PFD
(Pumps, Compressors, vessels, etc.)
Total Module Cost
Copyright - R.Turton and J. Shaeiwitz 2008
28
Module Factor Approach
• Table 7.8
• Direct, Indirect, Contingency and Fees are expressed as functions (multipliers) of purchased equipment cost at base conditions (1 bar and CS)
• Each equipment type has different multipliers
• Details given in Appendix A
opC
Copyright - R.Turton and J. Shaeiwitz 2008
29
Module Factor Approach
Bare Module Cost
Purchased Equipment Cost for CS and 1 atm pressure - Appendix A
Bare Module Factor(sum of all multipliers)
FBM = B1 + B2FpFM
Fp = pressure factor (= 1 for 1 bar)
FM = material of construction factor (=1 for CS)
1 2oBMF B B
op p p MC C F F
BMopBM FCC
Copyright - R.Turton and J. Shaeiwitz 2008
30
Module Factor Approach – Pressure Factors
Figure 7.6 Pressure Factors for Carbon Steel Vessels
Copyright - R.Turton and J. Shaeiwitz 2008
31
Module Factor Approach – Pressure Factors
Copyright - R.Turton and J. Shaeiwitz 2008
32
Illustrative Example
Compare Costs for 1. Shell-and-tube heat exchanger in
2001 with an area = 100 m2 for
Carbon Steel at 1 bar Carbon Steel at 100 bar Stainless Steel at 1 bar Stainless Steel at 100 bar
Copyright - R.Turton and J. Shaeiwitz 2008
33
Effect of Materials of Construction and Pressure on Bare Module Cost
P MOC Cp CBM
1 bar CS 25 K 25 K 82.3 K
82.3 K
1 bar SS 25 K 68.3 K
82.3 K
154 K
100 bar
CS 25 K 34.6 K
82.3 K
98.1 K
100 bar
SS 25 K 94.4 K
82.3 K
197.4 K
opC o
BMC
Copyright - R.Turton and J. Shaeiwitz 2008
34
Bare-Module and Total-Module Costs
BM – Previously Covered TM – Includes Contingency and
Fees at 15% and 3% of BM
all equip
1.18TM BMC C
Copyright - R.Turton and J. Shaeiwitz 2008
35
Grass-Roots Costs GR – grass-roots cost includes costs
for auxiliary facilities
Use base BM costs in GR cost (1 atm and CS) since auxiliary facilities should not depend on pressure or M.O.C.
all equip
0.50 oGR BM TMC C C
Copyright - R.Turton and J. Shaeiwitz 2008
36
Materials of Construction
Very important Table 9.9 – rough guide Perry’s – good source
Copyright - R.Turton and J. Shaeiwitz 2008
37
Capcost
Calculates costs based on input CEPCI – use current value of 500 or
latest from Chemical Engineering Program automatically assigns
equipment numbers
Copyright - R.Turton and J. Shaeiwitz 2008
38
Capcost
Copyright - R.Turton and J. Shaeiwitz 2008
39
Copyright - R.Turton and J. Shaeiwitz 2008
40
Copyright - R.Turton and J. Shaeiwitz 2008
41
Copyright - R.Turton and J. Shaeiwitz 2008
42
Summary
In general, information about costs must be scaled for capacity and time using appropriate cost exponents and indices
Total plant costs involve a variety of factors that vary with equipment type, operating pressure, and materials of construction.
For additions to existing facilities, the total module cost should be used but for totally new projects grass roots costs are appropriate.