WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016
Page 1 of 4
Prepared For: Atlanta Public Schools
Prepared By: Austin Nichols
Aerial Photo Aerial Photo
Aerial Photo Auditorium Stairs/Sidewalk
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016
Page 2 of 4
Chiller Walls Striped Track
‘ New Basketball Goals Gym/Auditorium Demo
Last Week’s Activities:
• Classroom Addition
o Finished installing door hardware
o Finished painting
o Began VCT install
• Auditorium
o Installed restroom fixtures
o Installed stage lights
• Administration Addition
o Installed Sunshade support
o Installed ACT grid
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016
Page 3 of 4
o MEP grid rough-in
• Administration Renovation
o Finished framing
o Hung ceiling
o Startup HVAC
• Gym Renovation
o Continued MEP rough-in
o Began installing rails
This Week’s Activities:
• Classroom Addition
o Began installing rubber base
o Finished installing VCT
o Finished installing shelves
o Began final cleaning
• Auditorium
o Began prep for sidewalk and steps
o Poured steps and sidewalk
o Demoed wall between auditorium and gym
• Administration Addition
o Finished MEP rough in
• Administration Renovation
o Began hanging drywall
o Finished MEP install
• Gym Renovation
o Continue MEP rough-in
o Continued framing
Next Week’s Activities:
• Classroom Addition
o Begin installing lockers
o Begin installing marker boards
o Begin cleaning
o Continue final cleaning
• Auditorium
o Continue finish paint
o Begin backstage VCT
• Administration Addition
o Begin installing epoxy flooring
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016
Page 4 of 4
o Begin installing restroom tile
o Finish priming walls
o Overhead ceiling inspection
• Administration Renovation
o Finish prime paint on walls
o Begin wall tile
o Begin epoxy flooring installation
• Gym Renovation
o Finish hanging new basketball goal
o Continue installing waste and vent installation
o Begin MEP overhead rough in new classrooms
Schedule:
• Status: Weather dependent
• Substantial Completion Dates:
o Classroom Addition: July 15, 2016
o Renovations: July 20, 2016
o Administration Addition: July 25, 2016
o Track and Field: September 1, 2016
o Auditorium Addition: September 1, 2016
o Gym Renovation: October 1, 2016
• Final Completion: December 31, 2016
Budget:
• Construction Budget: $15,920,000
• Budget Status: On Budget
• Gross Billed To Date: $10,118,024