Classroom Building at Charlottetowne & 5th Weekly Update May 29, 2020 Central Campus
Transcript
Page 1: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Classroom Building at Charlottetowne & 5th

Weekly Update May 29, 2020

Central Campus

Page 2: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Meetings & Milestones

• This Week:

• Install Projector Screens

• Continue First Floor Final Paint

• Continue First Floor Accent Paint

• Continue Installing Bio Med Ceiling Connections

• Continue First Floor Point Up

• Begin Installing First Floor Base

• Install Second Floor And Stair 2 Wood Handrail Trim

• Begin Second Floor Punch Work

• Continue Third Floor Punch Work

• Continue Fourth Floor Punch Work

• Continue Grading East Elevation

• Begin Landscaping

• Begin Installing Site Lighting

Page 3: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Meetings & Milestones

• Next Week:

• Install Projector Screens

• Continue First Floor Final Paint

• Continue Installing Bio Med Ceiling Connections

• Continue First Floor Point Up

• Continue Installing First Floor Base

• Install Second Floor And Stair 2 Wood Handrail Trim

• Continue Second Floor Punch Work

• Continue Third Floor Punch Work

• Continue Fourth Floor Punch Work

• Continue Grading East Elevation

• Continue Landscaping

• Continue Installing Site Lighting

Page 4: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Begin Fourth Floor

Final Clean

Location: Corridor 475

Page 5: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Fourth

Floor Punch Work

Location: Scrub 439

Page 6: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Install Owner Added

Lockers

Location: Corridor 371

Page 7: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Third Floor

Punch Work

Location: Elevator Lobby 373

Page 8: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Installing

Second Floor Wood

Handrails

Location: Corridor 272

Page 9: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Installing

Monumental Wood

Handrails

Location: Stair 2

Page 10: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Second

Floor Punch Work

Location: Virtual Anatomy 215

Page 11: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Install Ceiling

Service Panels

Location: Bio Med Shop 100

Page 12: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue First Floor

Final Paint

Location: Corridor 176

Page 13: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue First Floor

Accent Paint

Location: Classroom 110

Page 14: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Begin Installing First

Floor Rubber Base

Location: Quiet Room 104

Page 15: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Install Projector

Screens

Location: Dental Demo 102

Page 16: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Install Bike Racks

Location: Plan North

Page 17: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Begin Plan North

Landscaping

Location: Plan North

Page 18: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Place Plan West

Landscaping and

Site Lighting

Location: Plan West

Page 19: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Install Plan West

Light Bollards

Location: Plan West

Page 20: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Frame South

Entrance Exterior

Soffit

Location: Plan South

Page 21: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Plan South

Landscaping and

Site Lighting

Location: Plan East

Page 22: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Install Plan East Site

Lighting

Location: Plan East

Page 23: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Continue Site

Grading

Location: Plan East

Page 24: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Progress Photos

Place Plan East

Concrete Curb

Location: Plan East

Page 25: Weekly Update May 29, 2020 - Home | Central Piedmont · •Install Second Floor And Stair 2 Wood Handrail Trim •Continue Second Floor Punch Work •Continue Third Floor Punch Work

Conclusion of Weekly Update 05/29/2020