+ All Categories
Home > Documents > Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012:...

Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012:...

Date post: 24-Jun-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
28
Transcript
Page 2: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Welcome & Meeting Overview – Bill White, Massachusetts Clean Energy Center

Project Schedule – Chet Myers, Apex

Noise Mitigation Update – Bill White, Massachusetts Clean Energy Center

Project Update & Local Suppliers – Shawn Wyatt, Cashman-Weeks NB

Questions & Answers – All

Page 3: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Feb. 2010: MassCEC publishes Port and Infrastructure Analysis for Offshore Wind Energy Develop

Oct. 2010: Governor Patrick announces New Bedford as the location for the Marine Commerce Terminal

Nov. 2012: EPA releases its Final Determination

Dec. 2012: MassCEC releases construction bid for Project

Apr. 2013: MassCEC announces Cashman-Weeks NB

Apr/May 13: Ground Breaking/Start of Construction

Dec. 2014: Target Date for Completion of Construction

Page 4: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

July 24, 2012: EEA/EPA Final Determination

Dec. 19, 2012: NBMCT Pre-Bid Meeting

Jan. 3, 2013: New Bedford Public Meeting

Jan. 9, 2013: NBMCT Pre-Bid Meeting

Feb. 12, 2013: New Bedford City Council

March 5, 2013: New Bedford Public Meeting

April 2, 2013: New Bedford Public Meeting

May 7, 2013: New Bedford Public Meeting

June 4, 2013: New Bedford Public Meeting

July 2, 2013: New Bedford Public Meeting

Page 5: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• March 5, 2013: Introduction to offshore wind, European offshore wind terminal examples, environmental monitoring, bid summary

• April 2, 2013: Project schedule, CAD cell & dredging overview, environmental history of Main Terminal Site, environmental remediation plan

• May 7, 2013: Introduction of contractor, start of construction, environmental history of Main Terminal Site, noise mitigation

• June 4: 2013: Project schedule, construction update, overview of local suppliers to date, noise mitigation

Page 6: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• All project & meeting announcements, as well as past meeting presentations are available at: www.masscec.com/newbedfordterminal

• Our team email: [email protected]

• Sign up for our mailing list

Page 7: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford
Page 8: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Main Facility

Dartmouth Finishing Site

Transportation Corridor

Page 9: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• 1,000 ft of new bulkhead built to sustain loads of 4,000 pounds per square foot

• Deep dredge draft to 32 ft in front of bulkhead

• Approx. 28 acres of assembly and lay-down area

• Clean-up of approx. 250,000 cubic yards of low-level contaminated sediment

• Creation of Environmental & Habitat Restoration Areas

Page 10: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Next 90 Days

Dredge Along Terminal

Page 11: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Land-based Construction – Late June: Completed installation of erosion controls

– Late June: Completed clearing and grubbing at Main Site

– July: Begin to Excavate and Dispose Off-site of “Hot Spot” Contamination on Main Site

Page 12: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

In-Water Work

– June: Began probing for

obstructions along Terminal bulkhead

– July: Begin additional borings along bulkhead alignment for the piles that will be drilled into the bedrock

Page 13: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Dredging

– May - August: Dredge Bottom of CAD Cell 3

– July: Begin Capping Winter Flounder Area

– August: Begin Dredging at Terminal Site

Page 14: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• Soil impacted by PCBs > 50 ppm

• ~ 1,500 yd3 of material

• An area of ~ 13,000 sq ft

• Duration: 2 – 3 weeks

• Work to be completed by Mill City Environmental (MBE)

• Excavated and disposed offsite to Michigan

Green = Impacted by PCBs Red = Area visually impacted by petroleum hydrocarbons

Page 15: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford
Page 16: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• Close and insulate engine doors of dredge.

• Slow the bucket as it is opened, closed, and lowered to minimize the clap against the water.

• Remove grizzly screen (a strainer-like device) so that noise is lessened when material is dumped on barge.

Page 17: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• Replace the dredge bucket with a digging bucket that the dredge operator can control more precisely in order to minimize noise

• Some progress noted. Continuing to address complaints

Page 18: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• Cashman-Weeks NB brought another dredge barge to accelerate construction of CAD Cell 3

• “AJ Fournier” entered the Harbor June 24, 2013

– Hydraulic dredge bucket

• Cashman-Weeks NB expects to accelerate work on CAD Cell 3 – hopes to finish 20 to 30 days earlier

Page 19: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford
Page 20: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Trade

# of Workers

Minority

Female

Apprentices

NB Residents

South Coast Residents

Marine Operators Local 25 34 8 0 0 0 2

Laborers Local 385 7 1 1 2 4 5

Operators Local 4 3 1 0 0 0 1

Carpenters Local 56 (Pile Drivers) 3 0 0 0 0 0

Teamsters Local 59 1 0 0 0 0 1

Cashman Weeks NB 9 1 1 N/A 1 1

Apex Engineer & Design Team 9 0 0 N/A 4 5

Total 66 11 2 2 9 15

Page 21: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• Local 25 Marine Operators seeking local workers

• Local 25 Marine Operators placed a job posting in the New Bedford Standard-Times

Page 22: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Business City/Town Type of Service ABC Disposal Service, Inc. New Bedford Dumpster Service

AGM Marine, Inc. New Bedford Excavation Work For Investigations

Bayline Boat Yard New Bedford Boat Repair Work

C.E. Beckman Co. New Bedford Marine Wholesale

Cape Cod Staging & Equipment Corp. New Bedford Ladders/Scaffolding Service

Debross Oil Company New Bedford Fueling Services

Diligent Marine Services Fairhaven Marine Services

DJ Bass, Inc.; Rent-A-John/Elegant Restrooms New Bedford Port-A-John

Fairhaven True Value Hardware New Bedford General Supplies

Fathom Research LLC New Bedford Diving Services and Fish Inspections

Frade's Disposal, Inc. New Bedford Dumpster Service

General Supply & Metals, Inc. New Bedford Steel/General Supplies

Hathaway Mills LLC New Bedford Lease for JV Office

Hercules New Bedford Marine/Safety Supplies

Linberg Marine, Inc. Fairhaven Maritime Contracting Services

Levin Marine Supply Fairhaven Marine Supplies

Mid City Steel Westport Steel Supplier

33 local suppliers and subcontractors used by Cashman-Weeks NB & Apex

Page 23: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Business City/Town Type of Service New Bedford Welding Supply New Bedford Welding Supplies

Pier Oil, LLC/Luzo Fuel Inc. New Bedford Marine Fuel/Supplies

Pioneer Mooring Dartmouth Mooring and Anchor Services

R.A. Mitchell New Bedford Marine Master Tech

Raymond Piling Products Taunton Sheet piles / Pipe piles

Rick's Outboard Marine New Bedford Marine Equipment Service/Parts

Sea Fuels Marine Services, Inc. New Bedford Marine Fuel/Supplies

SK Marine Electronics New Bedford Marine Electronics Sales/Service

Shuster Corp. New Bedford Bearings/Hoses/ General Supplies

Thompson-Farland, Inc. New Bedford Surveying

Total Welding Supplies East Freetown Welding Supplies

Tucker-Roy Marine Towing Mattapoisett Marine Services

UMASS – Dartmouth – SMAST Fairhaven Winter Flounder Spawning Studies

Valtran, Inc. New Bedford Mobile Storage/Office & Temp. Fencing

Yard Smart Dartmouth Landscaping Services

Whaling City Marina New Bedford Boat Repair Services

Page 24: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

• MassCEC awarded a $250,000 Pathways Out of Poverty grant to the New Bedford Economic Development Council w/ BCC

• Bridge to Greener Futures project

– Provide motivated, low-income youth with academic, occupational, and life skills that lead to college and careers in clean energy with an emphasis on offshore wind

Page 25: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Businesses, residents already feeling boost from South Terminal

• June 22, 2013: New Bedford Standard Times interviewed Cashman-Weeks NB’s recent hire: apprentice, female, New Bedford Laborer Lianne Baptiste and a couple of local suppliers to project

http://www.southcoasttoday.com/apps/pbcs.dll/article?AID=/20130622/NEWS/306220328&cid=sitesearch

Page 26: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Can An Old Massachusetts Fishing Port Light The World Again?

• June 24, 2013: NPR’s Asma Khalid ran a national

story on the history of New Bedford, a description of the New Bedford Marine Commerce Terminal project, and interviews with local residents and business owners.

http://www.wbur.org/npr/190687185/can-an-old-massachusetts-fishing-port-light-the-world-again

Page 27: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Tuesday, August 6 Tuesday, September 3 Tuesday, October 1 Tuesday, November 5 Tuesday, December 3

First Tuesday of the Month 6:00 p.m. to 7:30 p.m. Third Floor, New Bedford Public Library

Please visit our website www.masscec.com/newbedfordterminal

for updated information about public meeting schedules

Page 28: Welcome & Meeting Overviewimages.masscec.com.s3.amazonaws.com › uploads... · July 24, 2012: EEA/EPA Final Determination Dec. 19, 2012: NBMCT Pre-Bid Meeting Jan. 3, 2013: New Bedford

Questions?


Recommended