Date post: | 30-Dec-2015 |
Category: |
Documents |
Upload: | janice-strickland |
View: | 214 times |
Download: | 0 times |
Welcome to the
OCR Academy
Overview of Rules & Law
Craig WeiseConstruction Reform Program
Director
Brief History
• How we got here today– Previous attempts– Ohio Construction Reform Panel– Construction Reform Demonstration
Projects
• HB 153 passed in June 2011
Multiple Prime
A/E Owner CM
Prime Prime Prime
General Contracting (GC)
A/E Owner
GC
Construction Manager at Risk (CMR)
A/E Owner
CMR
Design-Build (DB)
A/E Owner
DB
House Bill 153
• Retained current project delivery methods–Multiple Prime– CM as Agent
• Allows alternative project delivery methods– General Contracting (single prime)– CM at Risk– Design-Build
• Adjusted certain thresholds
Administrative Rules
General Information• 8 Administrative Rules required by
H.B. 153– 7 Rules have been finalized and
currently in effect – 5-year Inflation Adjustment Rule for the
$200K competitive bidding threshold will be finalized later
Administrative Rules
General Information• Rules do not apply to ODOT
horizontal construction, Ohio Turnpike Commission & governmental entities with “home rule” statute or separate authority
Administrative Rules
Contract Form Rule (effective 12.26.11)
• Applies to CMR and DB projects• State of Ohio forms–Mandatory for state
agencies/universities–Optional for all other public
authorities
Administrative Rules
Contract Form Rule (effective 12.26.11)
• Industry standard forms–AIA, ConsensusDOCS, DBIA, EJCDC,
CMAA–Must be modified to comply with
state & local laws–Public authority may supplement
form with project specific requirements
Administrative Rules
Subcontract Form Rule (effective 12.26.11)
• Applies to CMR, DB & GC (single prime) projects
• Mandatory for all public authority projects
• Contractor must use form for any subcontracts
Administrative Rules
Subcontract Form Rule (effective 12.26.11)
• Public Authority and Contractor may supplement form with project specific requirements
• In the event a conflicts exists between the subcontract form and any other part of the contract, the subcontract form provisions prevail
Administrative Rules
Surety Bonding Rule (effective 12.26.11)
• Applies to CMR and DB projects• Contractor to provide separate
performance & payment bonds prior to execution of contract equal to 100% of the contract sum
Administrative Rules
Surety Bonding Rule (effective 12.26.11)
• If contract sum increases at any time, the penal sum of the bonds are to be increased the same
• If at any time prior to final payment the surety fails, the CMR/DB is to replace bonds within 21 days
Administrative Rules
Best Value Selection Rule (effective 2.2.12)
• Applies to CMR and DB projects• “Best Value” is a two-step selection
process–Step 1: RFQ Phase–Step 2: RFP Phase
Administrative Rules
Prequalification of Subcontractors Rule(effective 2.3.12)
• Applies to CMR and DB projects• Establishes framework for criteria in
evaluating prospective bidders on subcontracts
Administrative Rules
Prequalification of Subcontractors Rule(effective 2.3.12)
• Similar to 9.312 factors, but pre-bid• Public authority may require
additional criteria• Same criteria used for evaluating
self-performed work if approved by public authority
Administrative Rules
Electronic Advertising Rule (effective 2.2.12)
• Applies to CM and CMR projects• Supplement newspaper
advertisement requirements
Administrative Rules
Electronic Advertising Rule (effective 2.2.12)
• Public authority may electronically advertise:– Newspaper websites– State public notification website– Public authority’s own official website– Trade association websites
Administrative Rules
Electronic Advertising Rule (effective 2.2.12)
• Content may indicate where to find full description
Administrative Rules
Electronic Bidding Rule (effective 2.2.12)
• Applies to multi-prime & GC (single prime) projects
• Optional for state agencies/universities
• May require registration or subscription w/fee– State may waive fees for certified EDGE
vendors
Administrative Rules
Electronic Bidding Rule (cont’d)
• Notice of electronic bidding in advertisement
• Electronic copy of bid guarantee will be included
• Publish electronic bid tabs after bid opening
HB 153 Provisions
Other Construction Reform related changes
• Increased competitive bidding thresholds for small projects to $200K
• Threshold based on total project cost (153.55B)
HB 153 Provisions
Other Construction Reform changes (cont’d)
• Threshold based on total project cost (153.55B)
• “Letterhead bidding” based on process established by each public authority
• Threshold not increased for every public authority
Overview of Rules & Law
Questions:
Craig Weise, AIA, CCM, PMP, LEED APConstruction Reform Program Director
Selection of Project Delivery Method PanelJeff Appelbaum/Steve Zannoni
Project Management ConsultantsThompson Hine LLP
Ken FisherTaft, Stettinius & Hollister LLP
Project Delivery Selection
Describe the process you follow when assisting owners (clients) in selecting a project delivery method.
Project Delivery Selection
What factors are considered in the decision making process and why are they important?
Project Delivery Selection
Share a recent example and what led that owner to select a particular delivery method for their specific project.
Project Delivery Selection
What is the biggest challenge for public owners when making this decision?