+ All Categories
Home > Documents > Welding Rny t

Welding Rny t

Date post: 07-Apr-2018
Category:
Upload: bimu1979
View: 224 times
Download: 0 times
Share this document with a friend

of 59

Transcript
  • 8/6/2019 Welding Rny t

    1/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    1

    NORTHEAST FRONTIER RAILWAY(CONSTRUCTION ORGANISATION)

    Office of the General Manager (Con)

    N.F. Railway, Maligaon

    TENDER DOCUMENTS

    TENDER NOTICE NO.CON/2011/JUNE/12

    TENDER NO.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Name of work: Welding of 52 Kg (72 UTS)/52 Kg (90 UTS) Rails in situ or in the depot or

    at location decided by Railway by using contractors own Mobile Flash Butt Welding Plant

    on running/non-running lines or on cess of consolidated formation or on ballast bed in the

    project area of Rangiya - Rangapara North, Rangapara North Tezpur, Rangapara

    North - Balipara and Balipara Bhalukpong in connection with Gauge Conversion with

    Rangiya Murkongselek Project.

    Approximate value of the

    Work (Tender Value)` 7,62,04,800.00

    Earnest Money to bedeposited

    ` 5,31,030.00

    Completion Period of the

    work

    5 (Five) Months

    Places of selling tender

    documents &receiving

    tenders

    In the Offices of the (a) General Manager (Construction),

    N.F.Railway, Maligaon, Guwahati-11 (b) Dy.Chief Engineer/Con,

    N.F.Railway, Rangiya Jn. & (c) OSD/CON/N.F.Railway,

    3, Koilaghat Street, 1st

    Floor, Kolkata-01,

    Availability of Tender

    Documents

    From 18-07-2011 and up to 11.00 hours of 02-08-2011

    Submission of tender From 26-07-2011up to 14.30 hrs. of 02-08-2011

    Date & place of opening of

    tenders

    05-08-2011at 10-00 hours at General Manager/Con, N.F.Railway,

    Maligaons Office

    Cost of Tender Form

    (Document)` 10,000/- per Tender

    Note- i) Tender documents are not transferable and cost of Tender document is not refundable.ii) Tender document should be submitted without detaching any pages.

  • 8/6/2019 Welding Rny t

    2/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    2

    NORTHEAST FRONTIER RAILWAY

    (Construction Organization)

    TENDER NOTICE NO.CON/2011/JUNE/12

    TENDER NO.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Name of work: Welding of 52 Kg (72 UTS)/52 Kg (90 UTS) Rails in situ or in the depot or

    at location decided by Railway by using contractors own Mobile Flash Butt Welding Plant

    on running/non-running lines or on cess of consolidated formation or on ballast bed in theproject area of Rangiya - Rangapara North, Rangapara North Tezpur, Rangapara

    North - Balipara and Balipara Bhalukpong in connection with Gauge Conversion with

    Rangiya Murkongselek Project.

    Forwarding Letter: Detailing Salient feature of the tender issued to:---------------------------------------- -----------------------------------------------------------------------------------

    ---------------------------------------------------------------------------------------------------------------------------

    (Tenderer(s) should write their name and postal address themselves, in case they are using documentdownloaded from internet)

    Details of Demand Draft/Railways Money Receipt towards cost of tender document.

    DEMAND DRAFT/ Railways Money Receipt No ____________________DATE __________

    ISSUED BY _____________________________________________________ BANK

    AMOUNT IN Rs. __________________________________

    Name and Contact Numbers of Key Personnels-

    1.

    -----------------------------------------------------------------------------------------------------------------------

    2.

    -----------------------------------------------------------------------------------------------------------------------3.

    -----------------------------------------------------------------------------------------------------------------------

    1.0 Sealed tenders have been invited for and on behalf of the President of India for the abovementioned work as per NIT.

    2.0 The tender document is hereby being issued to you on your request and on your havingdeposited the requisite cost of the tender document as per aforesaid details. The document is

    being issued with further condition that you agree to abide by the conditions laid down

    hereinafter in the tender document before submitting your tender. In case, the tenderer has used

    the documents downloaded from the internet, it is construed that the tenderer has agreed to as

    aforesaid.

    3.0 The tender document includes various chapters, drawings and annexures as enclosed, which areintegral parts of the tender documents.

    4.0 Detailed information of work and conditions may be seen in the Tender Document.

    5.0 Eligibility Criteria is abstracted as below:

    5.1 The tenderer(s) should have completed at least one similar single work for a minimum value of

    35% of advertised tender value of work..Note: (i) Similar nature of works physically completed within the qualifying period, i.e. the last 3

    financial years and current financial year (even though the work might have commenced before thequalifying period) should only be considered in evaluating the eligibility criteria.

  • 8/6/2019 Welding Rny t

    3/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    3

    (ii) The total value of similar nature of work completed during the qualifying period, and notthe payments received within qualifying period alone, should be considered.

    (iii) In the case of composite works involving combination of different works, even separate

    completed works of required value should be considered while evaluating the eligibility criteria.

    (iv) Similar nature of work means: Welding of Rails with mobile Flash Butt welding

    plant.

    5.2 Total Contract amount received during the last three years (i.e. current year and three previous

    financial years ) should be minimum of150% of advertised tender value of work supported by (a)

    Authenticated payment record of N.F.Railway or any other Government Department or PSUs etc.(b) Audited Financial Statement certified by Chartered Accountant

    6.0 JOINT VENTUREwill be permitted in this Tender.

    7.0PARTNERSHIP FIRM: In case the tenderer is a partnership firm, the work experience,solvency and turn over shall be in the name of partnership firm only.

    8.0 Tenderer(s) should submit the following details with tender documents:

    (a) List of Personnel Organization available on hand and proposed to be engaged for the subjectwork.

    (b) List of Plant & Machinery available on hand (own) and proposed to be inducted (owned andhired to be given separately) for the subject work.

    (c ) List of works completed in the last three financial years giving description of work, organization

    for whom executed, approximate value of contract at the time of award, date of award and date ofscheduled completion of work, date of actual start and actual completion of the work and final value

    of contract/final payment made to the contractor.

    (d) List of works on hand indicating description of work, date of award, contract value, and

    approximate value of balance work yet to be done.

    Notes: (i) In case of items (c) and (d) above, supportive documents/certificates from the

    Organizations with whom they worked/are working should be enclosed. (ii)Certificates from privateindividuals for whom such works are executed/being executed will not be accepted. (iii)Tenderer(s)

    are advised to submit those documents, which clearly show the fulfillment of Eligibility Criteria.

    9.0 All documents being submitted by the tenderer(s) along with their offer shall have to be attestedby the Gazetted Officer or self attested by the tenderer.

    10.0 Tenders not accompanied by requisite Earnest Money in the accepted form shall be summarily

    rejected. Earnest Money shall have to be deposited by all tenderers as per Clause 3.0 of Regulation

    for the Guidance of Tenderers.

    11.0 The tenderer has to give name and contact numbers of key personnels fully and clearly in the

    box provided above.

  • 8/6/2019 Welding Rny t

    4/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    4

    Guidelines and conditions for JOINT VENTURE

    JOINT VENTURE:

    If the tenderer(s) is/are a group of firm of Joint Venture firm, the Guidelines and Conditions issued byRailway Boards letter no 2002/CE-1/CT/37 dated 02.09.08 will be applicable which is abstracted

    below. The tenderer(s) have to follow these instructions and guidelines which constitute the part ofTender Document.

    Instructions on Joint Venture are incorporated in Tender Document based on the guideline issued by

    Railway Board vide letter No. 2002/CE-1/CT/37 dated 2.9.2008.

    1 Instruction for tenderers-(i) The tenderer has to go through the Guidelines and conditions of JOINT VENTURE as stated

    below.

    (ii) A Format for Memorandum of Understanding (MOU) is given as Annexure-JV MOU(iii) A Format for Joint Venture/Consortium Agreement is given as Annexure- JV

    (iv) JV /MOU should be drawn on Non Judicial Stamp of suitable value.(v) All the necessary documents and certifications as mentioned in the Guidelines and conditions of

    JOINT VENTURE should be attached with JV/MOU along with tender.

    Following special conditions will be applicable In case of joint venture.

    1. Separate identity/name shall be given to the Joint Venture firm. The name of the JOINT

    VENTURE firm should not be synonymous with the name of any one of its constituents.

    2. Number of members in a JV firm shall not be more than three if the work involves only one

    department (say Civil or S&T or Electrical) and shall not be more than five if the work involvesmore than one department.

    3. A member of JV firm is not permitted to participate either in individual capacity or as a member

    of another JV firm in the same tender.

    4. The tender form shall be purchased and submitted only in the name of the JV firm and not in thename of any constituent member.

    5. The Earnest Money Deposit (EMD) shall be submitted only in the name of the JV firm and not

    in the name of constituent member(s). However, in exceptional cases EMD in the name of leadpartner may be accepted subject to submission of specific request letter from lead partnerstating the reasons for not submitting the EMD in the name of JV firm and giving written

    confirmation from the JV partners to the effect that the EMD submitted by the lead partner may

    be deemed as EMD submitted by the JV firm.

    6. One of the members of the JV firm shall be the lead member of the JV firm who shall have a

    majority (at least 51%) share of interest in the JV firm. The other members shall have a share ofnot less than 20% each in case of JV firms with up to three members. In case of JV firm with

    foreign member(s), the lead member has to be an Indian firm with a minimum share of 51%.

    7. A copy of Memorandum of Understanding (MOU) executed by the JV members shall besubmitted by the JV firm along with the tender. The complete details of the members of the JV

    firm, their share and responsibility in the JV firm etc. particularly with reference to financial,technical and other obligations shall be furnished in the MOU as per the format given in Tender

    form as Annexure-JVMOU.8. Once the tender is submitted, the MOU shall not be modified/altered/ terminated during the

    validity of the tender. In case the tenderer fails to observe/ comply with this stipulation, the full

    Earnest Money Deposit (EMD) shall be forfeited. In case of successful tenderer, the validity of

    the MOU shall be extended till the currency of the contract expires.

    9. Approval for change of constitution of JV firm shall be at the sole discretion of the Employer

    (Railways). The constitution of the JV firm shall not be allowed to be modified after submissionof the tender bid by the JV firm except when modification becomes inevitable due to succession

    laws etc. and in any case the minimum eligibility criteria should not get vitiated. In any case the

  • 8/6/2019 Welding Rny t

    5/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    5

    Lead Member should continue to be Lead Member of the JV firm. Failure to observe thisrequirement would render the offer invalid.

    10. After the contract is awarded, the constitution of JV firm shall not be altered during the

    currency of contract except when modification become inevitable due to succession laws etc.

    and in any case the minimum eligibility criteria should not get vitiated. Failure to observe thisstipulation shall be deemed to be breach of contract with all consequential penal action as per

    contract conditions.11. On award of contract to JV firm, a single Performance Guarantee shall be submitted by the JV

    firm as per tender conditions. All the guarantees like Performance Guarantee, Bank Guaranteefor Mobilisation advance, machinery Advance etc. will be accepted only in the name of the JV

    firm and no splitting of guarantees amongst the members of the JV firm will be permitted.

    12. On issue of Letter Of Acceptance (LOA), an agreement as per format given in the tender among

    the members of the JV firm shall be executed and got registered before the Registrar of the

    Companies under Companies Act or before the Registrar/Sub-Registrar under the RegistrationAct, 1908. This agreement shall be submitted by the JV firm to the Railways before signing the

    contract agreement for the work. (This agreement format is invariably be part of the tender

    condition). In case the tenderer fails to observe/ comply with the stipulation, the full EarnestMoney (EMD) shall be forfeited and other penal actions due shall be taken against partners of

    the JV and the JV firm. The joint venture agreement shall have, inter-alia, following clauses:12.1 Joint and several liabilities: - The members of the JV firm to which the contract is awarded,

    shall be jointly and severally liable to the Employer (Railways) for execution of the project in

    accordance with General and Special conditions of the contract. The JV members shall also beliable jointly and severally for the loss, damages caused to the Railways during the course of

    execution of the contract or due to non-execution of the contract or part thereof

    12.2 Duration of the Joint Venture Agreement: It shall be valid during the entire currency of the

    contract including the period of extension if any and the maintenance period after the work is

    completed.12.3 Governing Laws: The Joint Venture Agreement shall in all respect be governed by and

    interpreted in accordance with Indian Laws.13. Authorized Member: Joint Venture members shall authorize one of the members on behalf of

    the Joint Venture firm to deal with the tender, sign the agreement or enter into contract in

    respect of the said tender, to receive payment, to witness joint measurement of work done, tosign measurement books and similar such action in respect of the said tender/ contract. All

    notices/ correspondences with respect to the contract would be sent only to this authorized

    member of the JV firm.14. No member of the Joint Venture firm shall have the right to assign or transfer the interest right

    or liability in the contract without the written consent of the other members and that of the

    employer (Railways) in respect of the said tender/contract.

    15. Documents to be enclosed by the JV firm along with tender:15.1 In case one or more of the members of the JV firm is / are partnership firm(s), following

    documents shall be submitted.(a) Notary certified copy of the Partnership Deed.

    (b) Consent of all the partners to enter into the Joint Venture Agreement on a stamp paper of

    appropriate value (in original).(c) Power of Attorney (duly registered as per prevailing law) in favour of one of the partners to

    sign the MOU and JV Agreement on behalf of the partners and create liability against the firm.15.2 In case one or more members is/ are Proprietary Firm or HUF, the following documents shall be

    enclosed:Affidavit on Stamp Paper of appropriate value declaring that his concern is a Proprietary

    Concern and he is sole proprietor of the Concern OR he is in position of KARTA of Hindu

    Undivided Family and he has the authority, power and consent given by other partners to act on

    behalf of HUF.

    15.3 In case one or more members is/ are limited companies, the following documents shall be

    submitted

    (a) Notary certified copy of resolutions of the Directors of the Company, permitting thecompany to enter into a JV agreement, authorizing MD or one of the Directors or Managers of

  • 8/6/2019 Welding Rny t

    6/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    6

    the Company to sign MOU, JV Agreement, such other documents required to be signed onbehalf of the Company and enter into liability against the company and / or do any other act on

    behalf of the company.

    (b) Copy of Memorandum and articles of Association of the Company.

    (c) Power of Attorney (duly registered as per prevailing law) by the Company authorizing theperson to do/ act mentioned in the para (a) above.

    15.4 All the members of JV shall certify that they are not black listed or debarred by Railways or anyother Ministry/ Department of the Govt. of India /State Govt. from participation in tenders/

    contract on the date of opening of bids either in their individual capacity or the JV firm orpartnership firm in which they were/are members / partners.

    16. Credentials & Qualifying criteria: Technical and financial eligibility of the JV firm shall be

    adjudged based on satisfactory fulfillment of the following criteria:16.1 Technical eligibility criteria:

    Either the JV firm or any one of the members of the JV firm should have to fulfil the TechnicalEligibility criteria 1 of NIT

    NOTE: Value of a completed work done by a Member in an earlier partnership firm or a JV

    firm shall be reckoned only to the extent of the concerned members share in that partnership

    firm/ JV firm for the purpose of satisfying his compliance of the above mentioned technical

    eligibility criteria in the tender under consideration.

    16.2 Financial eligibility criteria:

    The contractual payments received by the JV firm or the arithmetic sum of contractual paymentreceived by all the members of JV firm in the previous three financial years and the current

    financial year up to the date of opening of tender shall be at least 150% of the estimated value of

    the work as mentioned in the tender.NOTE: Contractual payment received by a Member in an earlier JV firm shall be reckoned only

    to the extent of the concerned members share in that JV firm for the purpose of satisfying

    compliance of the above mentioned financial eligibility criteria in tender under consideration.

  • 8/6/2019 Welding Rny t

    7/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    7

    Annexure-JVMOU

    NON JUDICIAL STAMP

    MEMORANDUM OF UNDERSTANDING (MOU)

    MEMORANDUM OF UNDERSTANDING (MOU)

    ENTERED INTO AT (place) THIS DAY OF . (Month) 2009

    Between

    1. ..(name of firm) having its registered office at (full address) (hereinafter

    referred to as (say X, short form of firm )) acting as the Lead Partner of the first part,

    And

    2. .. (name of firm) having its registered office at (full address) (hereinafter

    referred to as (say Y, short form of firm)) in the capacity of first Joint Partner of the

    other part.

    And

    3. .. (name of firm) having its registered office at (full address) (hereinafter

    referred to as (say Z, short form of firm )) in the capacity of 2nd

    Joint Partner of the otherpart.

    The expressions of X , Y & Z shall wherever the context admits , mean and include their

    respective legal representatives, successors-in-interest and assigns and shall collectively be

    referred to as the Parties and individually as the Party.

    WHEREAS the parties hereto have agreed to enter into a Joint Venture for the purpose of

    participation in Tender in respect of the project work of ------------------------------------

    (complete name of work to furnish)---- (hereinafter referred to as The Work) mentioned in

    Tender Notice No. . and Tender No. . invited by Chief Engineer

    (Con), Northeast Frontier Railway, Maligaon, Guwahati-781011 (hereinafter referred to as

    Employer).

    Whereas in the event the Joint Venture being successful in its bid, the parties have agreed to

    perform the contract in accordance with the agreed terms and conditions and thereof and in the

    spirit of mutual co-operation to achieve the objective of this Joint Venture, to the full

    satisfaction of the Employer.

    Now, therefore, for and in considerations and covenants hereinafter set forth, the parties hereby

    agree as follows:

    1. The following documents shall be deemed to form and be read and construed as an integral

    part of this Joint Venture.

    i) Tender Notice and

    ii) Tender Document

    iii) Any Amendment/ Corrigendum issued by the Employer

    iv) The tender submitted on our behalf jointly by the JV.

    2. The Parties have studied the documents and have agreed to participate in submitting a

    tender jointly under the name X-Y-Z (JV). (Name of JV to furnish).

    3. X(Name of lead partner) shall be the lead member of the JV for all intents

    and purpose and shall represent the Joint Venture in its dealing with the Employer. For this

    purpose of submission of bid proposals, the parties agree to nominate

    Shri (name with designation) of (name of the parties to

    which he belongs) as the leader duly authorized to sign and submit all documents and

    subsequent clarifications, if any, to the Employer. However, Shri . (name with

  • 8/6/2019 Welding Rny t

    8/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    8

    designation) shall not submit any such proposals, clarifications or commitments before

    securing the written clearance of the other partners, which shall be expeditiously given by X,

    Y to X (to be decided internally by the JV member).

    4. The Parties have resolved that the share of interest /participation in the Joint Venture shall

    be as under:

    (a) Lead Partner : at least 51%

    (b) Joint Venture Partner I : Not less than 20%

    (c) Joint Venture Partner-II : Not less than 20%

    5. JOINT AND SEVERAL RESPONSIBILITY

    The Parties undertake that they shall be jointly and severally legally liable to the Employer in

    the discharge of all the obligations and liabilities as per the contract with the Employer and

    for execution of project in accordance with General and Special Conditions of the Contract if

    the work is awarded to their JV. The parties shall be jointly and severally liable & responsible

    for fulfilling the obligations of the tender/tender document.

    The parties shall also be liable jointly and severally for the loss, damages caused to the

    Railway during the course of execution of the contract or due to non-execution of the contract

    or part thereof.

    6. ASSIGNMENT AND THIRD PARTIES.

    The parties shall co-operate throughout the entire period of this JV on the basis of exclusivity

    and neither of the Parties shall make arrangement or enter into agreement either directly or

    indirectly with any other party or group of parties on matters relating to the present Work.

    7. EXECUTIVE AUTHORITY

    The said Joint Venture through its authorized representative shall receive instructions,

    payments from the Employer. The management structure for the project shall be prepared by

    mutual consultations to enable completion of project to quality requirements within permitted

    cost and time.

    8. GUARANTEES AND BONDS.

    The Bank Guarantees, Earnest Money deposit etc and other Bond shall be furnished jointly by

    all the parties in the name of Joint Venture and that shall be legally binding on all the partners

    of the Joint Venture.

    9. BID SUBMISSION.

    Each Party shall bear its own cost and expenses for preparation and submission of the bid and

    all costs until conclusion of a contract with the Employer for the Project. Common expenses

    shall be shared by both the parties in the ratio of their actual participation.

    10.INDEMNITY

    Each party hereto agrees to indemnify the other party against its respective parts in case of

    breach/ default of the respective party of the contract works of any liabilities sustained by the

    Joint Venture.

    11.For the execution of the respective portions of works, the parties shall make their own

    arrangements as per mutual agreement/understanding between them from time to time to

    bring the required finance, plants and equipment, materials, manpower and other resources.

    12.VALIDITY.

    This MOU/Agreement shall remain in force till the occurrence of the earliest to occur of the

    following, unless by mutual consent, the Parties agree in writing to extend the validity for a

    further period,

    (a) The bid submitted by the Joint Venture is declared unsuccessful, or

    (b) Cancellation/ shelving of the Project by the Employer for any reasons prior to award of

    work.

  • 8/6/2019 Welding Rny t

    9/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    9

    (c) Execution of detailed JV agreement by the parties, setting out detailed terms after award

    of work by the Employer.

    13.The parties undertake not to make any modification/alteration/termination the MOU of Joint

    Venture during the validity of the tender.

    14.The parties undertake not to make any changes in this Joint Venture or terminate this Joint

    Venture, after submission of the tender bid except when modification becomes inevitable due

    to successive laws etc., without prior written consent of the Employer. The parties further

    undertake that in any case Lead Member shall continue to be the Lead Member of the JV.15.All the members of the JV shall certify that they are not black listed or debarred by Railways

    or any other Ministry/ Department of the Govt. of India /State Govt. from participation in

    tenders/ contract on the date of opening of bids either in their individual capacity or the JV

    firm or partnership firm in which they were/are members / partners.

    16.This JV shall be construed under the laws of India.

    Now the parties have joined hand to form the JV(MOU) on this day of (month) two

    thousand eight with reference to and in confirmation of their discussions and understanding brought

    on record on ..(Day) (Month) 2010.

    Lead Member Member-I Member -II.

    (X) (Y) (Z)

    (Name of signatory with designation and name of firm should be furnished)

    IN WITNESS WHEREOF THE PARTIES, have executed this JV the day, month and year first before

    written.

    Witness

    1.

    2.

    3.

  • 8/6/2019 Welding Rny t

    10/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    10

    Annexure-JV

    NON JUDICIAL STAMP

    JOINT VENTURE /CONSORTIUM AGREEMENT

    This Joint Venture/ Consortium Agreement executed at .(Name of place) on this

    day of ..(month & year) between M/s. X (name of firm) M/s. Y(name of

    firm) and M/s. Z .(name of firm) wherein Registered office of Ist , 2nd

    and third party is at

    respectively represented through their constituted attorney for the

    2nd

    party .. and for the third party. (The expression and words of the

    first, 2nd

    and 3rd

    party shall mean and include their heirs, successors, assigns, nominees execution,

    administrators and legal representative respectively).

    WHEREAS the parties herein above mentioned are desirous of entering into a Joint Venture/

    Consortium for submitting bid document and if contract awarded, carrying on Engineering and/ or

    contract works, in connection with Tender for . (name of work with tender

    no./Tender notice No.) as mutually decided between the parties of this Joint Venture/ Consortium.

    NOW THIS AGREEMENT WITNESSES AS UNDER:

    1. That in and under this Joint Venture/Consortium Agreement the work will be done jointly

    in the name and style of M/s (Joint Venture/Consortium of M/s X,Y,Z, with

    address).

    2. That all the parties shall be jointly and severally legally liable to the Employer in the

    discharge of all the obligations and liabilities as per the Contract with the Employer and

    severally and jointly responsible for the satisfactory/ successful execution/ completion of the

    work in all respects and in accordance with terms & General and Special Conditions of the

    Contract irrespective of share and role specified in JV agreement. All the parties shall be jointly

    and severaaly liable and responsible for fulfilling the obligations of the tender/bid document.

    All the parties shall also be liable jointly and severally for the loss, damage caused to the

    Railway during the course of execution of the contract or due to non-execution of the contract or

    part thereof.

    3. That the role and responsibility of each constituent of the said Joint Venture/ Consortium

    in details, covering all aspects of the planning and successful completion of the work shall be as

    under :

    The First Party shall be responsible for ( details may be furnished)

    The Second Party shall be responsible for ( details may be furnished)

    The Third Party shall be responsible for ( details may be furnished)

    4. The share of interest/ participation, profit & loss of each constituent of the said Joint Venture/

    Consortium shall be as under :(a) Lead Partner : at least 51%

    (b) Joint Venture Partner I : Not less than 20%

    (c) Joint Venture Partner-II : Not less than 20%

    5. That the parties of this Joint Venture/ Consortium shall depute sufficient no. of experienced staff

    as committed to commensurate with their role and responsibilities and as required for the

    successful completion of the works in close consultation with each other.

  • 8/6/2019 Welding Rny t

    11/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    11

    6. That the financial investment and other resources required for the successful execution/

    completion of work under this Joint Venture/ Consortium shall be brought in by the parties as per

    mutual agreement/ understanding between them from time to time.

    7. That all the Bank Guarantees like Performance Guarantee, Bank Guarantee for Mobilisation

    advance, machinery advance etc shall be furnished jointly by all the parties in the name of Joint

    Venture/ Consortium only.

    8. That all the parties nominate and authorize Shri (Name of representative) of

    .. (name of firm) as the representative of the JV and to sign the tender, ContractAgreement in respect of the said tender, to receive payment, to witness joint measurement of

    work done, to sign measurement books and all letter correspondence related to the above

    mentioned work on behalf of the Joint Venture.

    9. That all the above noted parties i.e. M/s. X, Y & Z undertake not to make any changes in this

    Joint Venture/ Consortium agreement during the currency of contract except when modification

    becomes inevitable due to successive laws etc. without prior consent of the Employer. The

    parties further undertake that in any case Lead Member shall continue to be the Lead Member of

    the JV.

    10. That all the parties undertake that no member of the Joint Venture firm shall have the right to

    assign or transfer the interest right or liability in the contract without the written consent of the

    other members and that of the employer (Railways) in respect of the said tender/contract.

    11. That all the members of the JV certify that they have not been black listed or debarred by

    Railways or any other Ministry/ Department of the Govt. of India /State Govt. from participation

    in tenders/ contract on the date of opening of bids either in their individual capacity or the JV

    firm or partnership firm in which they were members / partners.

    12. That Joint Venture agreement shall be valid during the entire currency of the contract including

    the period of extension if any and the maintenance period after the work is completed.

    13. That the Joint Venture Agreement shall in all respect be governed by and interpreted in

    accordance with Indian Laws.

    14. That this Joint Venture Agreement is pursuant the MOU entered in to at . (Place) this

    (Day) of (month)(Year) between above noted parties.

    NOW THE PARTIES HAVE JOINED HANDS TO FORM THIS JOINT VENTURE /

    CONSORTIUM ON THIS .. DAY OF .. WITH REFERENCE TO

    AND IN CONFIRMATION OF THEIR DISCUSSIONS AND UNDERSTANDING BROUGHT

    ON RECORD ON . (Date).

    IN WITNESS THEREOF THE ABOVE NAMED PARTIES HAVE SET THEIR

    RESPECTIVE HANDS ON THIS JOINT VENTURE/ CONSORTIUM AGREEMENT ON

    THE DAY, MONTH AND YEAR FIRST ABOVE MENTIONED IN THE PRESENCE OF

    THE FOLLOWING WITNESS :

    WITNESS:

    1. First Party

    2. Second Party3. Third Party

  • 8/6/2019 Welding Rny t

    12/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    12

    NORTHEAST FRONTIER RAILWAY

    (Construction Organization)

    (FIRST SHEET)

    Issued to/Downloaded

    From website by

    TENDER NO.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Name of work: Welding of 52 Kg (72 UTS)/52 Kg (90 UTS) Rails in situ or in the depot or atlocation decided by Railway by using contractors own Mobile Flash Butt Welding Plant onrunning/non-running lines or on cess of consolidated formation or on ballast bed in the project area of

    Rangiya - Rangapara North, Rangapara North Tezpur, Rangapara North - Balipara andBalipara Bhalukpong in connection with Gauge Conversion with Rangiya Murkongselek

    Project.

    Approximate Value (Tender value): ` 7,62,04,800.00

    To

    The President of India,

    Acting Through the Chief Engineer(Con),Northeast Frontier Railway, Maligaon,

    Guwahati 781 011.

    1. I/We .have read the various

    conditions to tender attached here to and hereby agree to abide by the said conditions. I/We

    also agree to keep this tender open for acceptance for a period of 120 days from the date fixedfor opening the same and in default thereof, I/We will be liable for forfeiture of my/our

    Earnest Money. I/We offer to do the work at the rates quoted in the attached Schedules andhereby bind myself/ourselves to complete the work in all respects within 5 (Five) months

    from the date of issue of letter of acceptance of the tender.2. I/We . also hereby agree to abide by

    the (i) N. F. Railway General Conditions of Contracts and Standard Special Conditions ofContracts, 1998 (ii) N. F. Railway Specifications (for Materials & Works), 1993, (iii) SpecialConditions and Specifications attached with the tender & (iv) Schedule of Rates (for Labours

    and Materials) of Northeast Frontier Railway, 1993 edition corrected up to date.

    3. A sum of 5,31,030.00 is hereby forwarded as earnest money. The full value of the earnest

    money shall stand forfeited without prejudice to any other rights or remedies, if:

    (a) I/We do not do execute the contract documents, within Seven days after receipt of notice

    issued by the Railway that such documents are ready, or

    (b) I/We do not commence the work within Ten days after receipt of the orders to this effect, or

    I/We withdraw or modify my/our offer within the validity date of the tender.

    4. Once the acceptance of the tender is communicated to us a legal and enforceable contract comes into being. If in accordance with the letter of the acceptance I/We fail to commence work within theperiod stipulated in the acceptance letter and fail to execute the formal agreement, I/We shall be

    liable for breach of the contract and the consequences of breach of any of the conditions of thecontract shall entitle Railway Administration to have work/job executed at my/our risk and cost and

    to claim extra cost/expenditure sustained by the Railway Administration.

    Signature of Witness:

    1. Address:

    2. Address:

  • 8/6/2019 Welding Rny t

    13/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    13

    NORTHEAST FRONTIER RAILWAY (CONSTRUCTION)

    (TENDER FORM SECOND SHEET)

    Regulations for the Guidance of Tenderers

    The following documents shall form part of the contract: -

    1. (a) Tender form -FIRST AND SECOND SHEET.(b) N.F. Railway General Conditions of Contract, Standard Special Conditions of

    Contract, 1998, and N.F.Railway Standard Specifications, Engineering department,1993 edition, corrected up-to-date, along with schedule of deletion/alteration to

    Standard Special Conditions of Contract - 1993 edition.

    (c) Schedule of Rates (for Labour and Materials) of Northeast Frontier Railway,Engineering Department 1993 edition corrected up-to-date.

    (d) Additional Special Conditions of Contract.(e) Special Conditions and Special Specifications for the work.(f) Schedule of items and Approximate Quantities and Abstract of Schedule of items of

    works and estimated cost.(g) Agreement forms.(h) Drawings.(i) Indian Railway Engg. Code 1999 latest Revised Edition.

    Instructions to tenderer(s) and conditions of tenders

    1. The drawings for the works can be seen in the office of the Chief

    Engineer/Construction/Northeast Frontier Railway, Maligaon, Guwahati - 781 011 at any timeduring office hours.

    2 (i) General Conditions of Contract, Standard Special Conditions of Contract, 1998 and (ii)Standard Specifications 1993 edition and (iii) Schedule of Rates (for labour and materials) ofthe Northeast Frontier Railway-1993 edition can be seen in the office of the Chief

    Engineer/Con/N.F.Railway or can be had on payment, if available.3. The Tenderer(s)/Contractor(s) have to quote rates in figures and words/percentage

    above/below/at par rate only in the schedule. The quantities in schedule of items of work are

    given in Annexure-I as a guide and are approximate only and are subject to variationaccording to the need during execution of the work. The Railway accepts no responsibility for

    the accuracy. The Railway does not guarantee work under the items of the schedule.

    4. The Schedule of quantities is issued in duplicate with the object of avoiding addition, alteration,overwriting and crossings etc. and to ensure submission of a fair copy, which should bear nosuch blemish. Only one copy of the Tender Schedule is to be submitted by the Tenderer(s).

    5. All documents and entries in the tender shall be either type written or in ink and in English.Tender containing erasures, additions and alterations to the tender documents are liable to be

    rejected. Any correction made by the Tenderer(s) in his entries must be attested by him. If rates

    expressed in figures and words do not agree, then the lower of the two rates will be taken into

    consideration and binding on the contractor.6. Rates should be quoted inclusive of sales tax or any other local tax, royalty etc. unless specified

    to the contrary in the tender documents.

    7. SIGNING OF TENDERS:7.1 The tenderer/Contractor shall sign each and every page of the Tender document.7.2 Any individual/s signing the Tender or other documents connected therewith should specify

    whether he is signing:i)As Sole Proprietor of the concern or his Attorney,orii) As a Partner or Partners of the Firm,or

    iii) For the Firm per procuration, oriv) As a Director, Manager or Secretary in the case of Limited Company.

    7.3 In the case of firms not registered under the Indian Partnership Act all the partners, or the

    attorney duly authorised by all of them should sign the tender and all other connecteddocuments. The original document empowering the individual or individuals to sign, the

    original partnership deed with registration certificates, if any, in case the tenderer(s) is a firm

  • 8/6/2019 Welding Rny t

    14/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    14

    and the Memorandum and Articles of Association in case the tenderer(s) is a Company shouldbe furnished to the purchaser for verification if required.

    8 EARNEST MONEY

    8.1 The tenderer(s) is required to deposit ` 5,31,030.00 only as earnest money for the performance

    of the tender who will keep the offer open for a period of 120 days from the date fixed foropening of tender, it being clearly understood that the tenderer(s) after submitting his tender

    will not resile from his offer or modify the rates, items and conditions thereof, failing which theaforesaid amount shall be liable to be forfeited by the Railway.

    8.2 The earnest money should be in cash or in the form of Deposit receipts, Pay orders or Demanddrafts executed by State Bank of India or any of the Nationalized Banks or by a scheduled

    Bank.8.3 The Earnest Money, when deposited in cash, should be remitted to the Divisional

    Cashier/CON/N.F.Railway, Maligaon, Guwahati-11 and the receipt obtained there-from should

    be enclosed with the tender as a proof of the deposit of the requisite earnest money.

    8.4 Deposit receipts or pay orders or demand draft from the State Bank of India or from any of the

    Nationalised Banks or a Schedule Banks should be drawn in favour of Financial Advisor &

    Chief Account Officer/CON/N. F. Railway/Maligaon and endorsed Account Payee andvalid at least upto the validity of tender offer. No conformation advise from the Reserve Bank

    of India will be necessary.

    8.5 A tender not accompanied with requisite earnest money, in the requisite manner as aforesaid,will be summarily rejected.

    8.6 Earnest money shall not be acceptable in the shape of Bank Guarantee Bond.8.7 In the event of tenderer(s) defaulting in not adhering to the conditions laid down in para 8.1 the

    Railway Administration shall be entitled to forfeit the full amount of earnest money deposited

    along the tender without prejudice to any other remedy available to the Railway.

    8.8 No interest will be paid on earnest money. The earnest money will be refunded to theunsuccessful tenderer(s) within a reasonable period of time. The earnest money deposited by

    the successful tenderer(s) will be retained towards the security deposit for the due and faithful

    fulfillment of the contract but shall be forfeited if the contractor fails to execute the agreement

    or start the work within time schedule vide clause 3(a), 3(b) & 3(c) of Tender Form (First sheet)

    or a reasonable time determined by the Engineer after notification of the acceptance of his/their

    tender.

    8.9 Railway shall be entitled to forfeit the earnest money specified for the particular work if thetenderer(s) fails/fail to execute the agreement or start the work within time as per clause 8.8.

    9 CREDENTIALS

    9.1 The tenderer(s) is/are required to submit along with his/their tender, authenticated documentsand certified details in support of their credentials and proof of their capacity to be able toundertake this work as per Annexure-A duly signed by the tenderer(s) himself/themselves also.

    It may please be understood that in the event of furnishing incomplete information or no

    information at all, Railway reserves the right to reject the offer outright, without making any

    reference to the tenderer(s).

    10 Tender must be enclosed in sealed cover super-scribed with Tender No. and must be sent by

    Regd. post/Speed post to the address of Chief Engineer (Construction), N.F. Railway,Maligaon, Guwahati-781 011 so as to reach this office not later than 14.30 hrs. on 02-08-2011

    or can be deposited in the Special Boxes allotted for the purpose in the offices mentioned in theTENDER NOTICE NO. CON/2011/JUNE/12 The boxes will be sealed at 14.30 hrs. of

    02-08-2011 . The tender will be opened on 05-08-2011 at 10.00 hrs at General Manager

    (Construction)/N.F.Railway, Maligaon`s Office. The tenders, which are received after the

    sealing of the tender box, are liable to be rejected.

    11 Non-compliance with any conditions mentioned above is liable to result in the tender beingrejected.

  • 8/6/2019 Welding Rny t

    15/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    15

    12 Acceptance of Tender:12.1 The authority for the acceptance of the tender will rest with General Manager/CON/N. F.

    Railway, Maligaon, Chief Engineer/CON/Maligaon, Dy Chief Engineer/Con of field units for

    and on behalf of President of India who does not bind himself to accept the lowest or any other

    tender nor does he undertake to assign reasons for declining to consider any particular tender ortenders. No tenderer(s) shall demand any explanation on the cause of rejection of his/their

    tender. No correspondence will be entertained with the tenderer(s) in respect of the rejection ofany or all tenders.

    12.2 Tender documents submitted by the tenderer(s) shall become the property of Railway and theRailway shall have no obligation to return the same. The cost of Tender Document is not

    refundable.

    12.3 If the tenderer(s) deliberately gives wrong information in his tender the Railway reserves theright to reject such tender at any stage.

    12.4 If a tenderer(s) expires after the submission of his tender or after the acceptance of his tender,the Railway shall deem such tender as cancelled. If a partner of tendering firm expires after the

    submission of or after acceptance of their tender the Railway shall deem such tender as

    cancelled unless the firm retains its character.

    12.5 The accepting authority reserves the right to divide the tender amongst more than one tenderers,if deemed necessary, and also to reject any or all tenders received without assigning any reasonand does not bind himself to accept the lowest or any other tender.

    13 Execution of Contract document :

    13.1 The tenderer whose tender is accepted shall be required to appear in the office of the GeneralManager/Con in person, or if a firm or corporation, a duly authorised representative shall so

    appear, to execute the contract documents within seven days after notice to do so. Failure to

    comply shall constitute a breach of the agreement effected by the acceptance of the tender in

    which case the full value of the earnest money accompanying the tender shall stand forfeitedwithout prejudice to any other rights or remedies.

    13.2 In the event of any tenderer, whose tender is accepted refusing to execute the contractdocuments as therein before provided, the Railway may determine that such tenderer has

    abandoned the contract and thereupon his tender and the acceptance thereof shall be treated as

    cancelled & the Rly. shall be entitled to forfeit the full amount of the earnest money and torecover the liquidated damages for such default equivalent to the amount of Performance

    Gaurantee.

    14. The tenderer shall keep the offer open for a minimum period of120 days from the date ofopening of the tender within which period the tenderer cannot withdraw his offer. This period

    may be extended further if so required by mutual agreement between the parties from time totime. Any contravention of this condition will make the tenderer liable for forfeiture of thissecurity deposit.

    15. Should a tenderer be a retired Engineer of the Gazetted rank or any other Gazetted Officerworking before his retirement whether in the executive or Administrative capacity or whether

    holding a pensionable post, or not in the Engineering Department of any of the Railway onwardand/or administered by the President of India for the time being or should a tenderer being

    partnership firm have as one of its partners a retired Engineer or a retired Gazetted Officer orshould a tenderer being incorporated company have any such retired Engineer or retired officer

    as one of its directors, or should a tenderer have in his employment any retired Engineer or

    retired Gazetted officer as aforesaid, the full information to the date of retirement of such

    Engineer or Gazetted officer from the said service and in case where such Engineer or Officerhad not retired from Government service at least two years prior to the date of the submission of

    this tender as to whether permission for taking such contract or , if the contractor be apartnership firm or an incorporated company to be one a partner or Director as the case may be

    or to take employment under the contractor has been obtained by the tenderer from the Engineeror the officer authorized by him in this behalf, shall be clearly stated in writing at the time of

    submitting the tender. Tenderers without the information above referred to or a statement to theeffect that no such retired Engineer or retired Gazetted officer is so associated with the tenderer,

    as the case may be shall be rejected.

  • 8/6/2019 Welding Rny t

    16/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    16

    16.0 Should a tenderer or contractor have a relative employed in Gazetted capacity in anydepartment of the N.F.Railway, or in the case of partnership firm or company incorporated

    under the company Law, should p partner or a relative of the partner or a share holder or a

    relative of a share holder be employed in Gazetted capacity in any department of the

    N.F.Railway, the authority inviting tender shall be informed of the fact at the time ofsubmission of tenders, failing which the tender may be rejected, or if such fact subsequently

    comes to light the contract may be rescinded in accordance with the provisions in Clause 62 ofthe General Conditions of Contract. A declaration form (proforma attached) to this effect

    should be signed and enclosed with the tender. (Annexure-B).

    17.0 The tenderer/s shall clearly specify whether the tender is submitted on his behalf or on behalf ofpartnership concern. If the tender is submitted on behalf of partnership concern, he should

    submit the certified copy of partnership deed along with the tender and power of attorney to

    sign the tender documents on behalf of partnership concern. If these documents are not enclosedalong with the tender documents, the tender will be treated as having been submitted by the

    person signing the tender in his individual capacity.

    18.0 The Railway will not be bound by any power of attorney granted by the tenderer or by changesin the composition of the firm made subsequent to the execution of the contract. It may,

    however, recognize such power of attorney and changes after obtaining proper legal advise the

    cost of which will be chargeable to the contractor.

    19.0 If the tenderer, whether a sole proprietor, limited company or a partnership firm wants to actthrough agents or individual partner/partners, should submit along with the tender or at a later

    stage a power of Attorney duly stamped and authenticated by a public notary or by a Magistrate

    in favour of the specific person/s whether he/they be partner/partners of the firm or any other

    persons, specially authorizing him/them to submit the tender, sign the agreement, receivemoney, witness measurement, signs measurement book , compromise , delete relinquish any

    claim or claims preferred by firm and sign "No claim certificate" and refer all or disputed items

    to arbitration.

    20.0 The Railway reserves the right to accept a tender in whole or in part or reject any tender or alltenders without assigning reasons for any such action.

    21.0 Negotiations with tenderer(s)The Railway reserve the right to hold negotiations with lowest who should be lowest, valid,

    eligible and technically acceptable tenderer considered for award of contract directly if the rates

    were not unreasonably high.

    22.0 Inspection of siteBefore submitting a tender, the tenderer/s will be deemed to have satisfied himself by actual

    inspection of the site and locality of the works, that all conditions liable to be encountered

    during the execution of the works are taken into account and that the rates he has entered in"Schedule of quantities and Rates" of the tender document are adequate and all inclusive to

    accord with the provision of the general and special conditions of contract for the completion ofthe works to the entire satisfaction of the Engineer. No claim shall be entertained from the

    contractor for making his own arrangements for approached roads from outside Railway landand contractor will bear entire expenses such as road taxes, payment on right of way etc. to

    outsiders.

    23.0 Examination of DocumentsThe submission of the tender shall be deemed to have been done after careful study and

    examination of the tender document with full understanding of the implications thereof. Anyclarification required by a tenderer shall be obtained from the office inviting tenders on any

    working day.

  • 8/6/2019 Welding Rny t

    17/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    17

    24.0 Tender documents are not transferable and cost of tender document is not refundable.

    25.0 Sequence of work25.1 The contractor(s) shall comply with the order of engineer in charge in regard to the sequences

    of tackling and progressing component parts of works.

    26.0 Preparation of PERT Chart

    26.1 The successful tenderer within 20 days after the contract is awarded, will make out a detailedPERT Chart along with detailed programme chart based on accepted scheme indicating

    various stages of execution, method of execution and completion of work in different stages

    keeping the period of completion in view and submit the same to the engineer for the

    consideration and approval. The above programme shall be strictly adhered to.

  • 8/6/2019 Welding Rny t

    18/59

  • 8/6/2019 Welding Rny t

    19/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    19

    2.4.2 Unless specifically provided otherwise in the Tender, any and all exceptions which the

    Tenderer may have to any of the clauses of the Standard Special Conditions of Contract or

    the additional Special Conditions of Contract if any as included in the Tender, shall be

    clearly stated in a statement annexed to the tender and identified as Annexure-D. Suchexception shall be listed in the format specified under the title "Schedule of Deviations". If

    the Tenderer has no exceptions, the annexure shall be submitted with a "NIL" statement. Ifthe contractor does not include the Annexure with the Tender it shall be conclusive evidence

    that the Standard Special Conditions of Contract and the additional Special Conditions ofContract with deletions/alterations if any are entirely acceptable to the Contractor.

    2.4.3 Any Deviations from the Standard Special Conditions of Contract and the additional Special

    Conditions of Contract if any, stated by the Tenderer in his tender shall be a part of the

    Contract only to such extent as have been explicitly accepted by the Railway and incorporated

    in the Contract.

    2.5 INTENT OF PLANS, SPECIFICATION AND CONTRACT DOCUMENTS:2.5.1 The work to be carried out under this contract shall, except as otherwise provided in these

    conditions, include all labour, materials,(except the materials to be supplied by Railway

    free of cost) construction plant, equipment and transport which may be required inpreparation of and for the full and entire execution and successful completion of the works.

    The description given in the Schedule of works shall, unless otherwise stated, be held to

    include carriage and cartage, carrying and hoisting, setting, fitting and fixing in position andall other labour, necessary in and for the full and entire execution and successful completion

    of the works as aforesaid in accordance with good practice and recognized principles and any

    urgent and temporary works fully contingent upon the works.

    2.6 INSPECTION AND ADMISSION TO SITE.

    2.6.1 The Contractor shall not be permitted to enter on (other than for inspection purpose) or takepossession of the site until instructed to do so by the Engineer in writing. The portion of the

    site to be occupied by the contractor shall be defined and/or shown in the site plan, or this

    shall be indicated by the Engineer, and the contractor shall on no account be allowed toextend his operation beyond these areas. The contractor shall not use or allow it to be used the

    site so allowed to him by the Railway for any purpose other than that of executing the work.

    The contractor shall make his own arrangement at his own cost for any additional landrequired by him for the purpose of execution of the work.

    2.6.2 The Contractor shall at his own cost provide, if necessary or if required on the site, alltemporary access thereto, to the satisfaction of the Engineer and shall alter, adopt and

    maintain the same as required from time to time and shall take up and clear them away as and

    when no longer required and make good all damage done to the site.

    2.6.3 The Tenderer(s) before quoting his rate shall carefully inspect the site and shall bedeemed to have satisfied himself about the nature and type of work including ancillary

    works necessary for satisfactory execution of work. Site accessibility, availability of

    required materials, need of suitable rollers for compaction of earthwork, drying and

    wetting of soil before compactions, arrangement for the testing equipment for qualitycontrol of earthwork and concrete etc. must be kept in view while quoting the rates.

    2.7 MODIFICATION OF DRAWINGS.The Railway reserves the right to alter/modify the drawings/design to suit the site conditions.

    If due to the change in drawings or designs there is any increase or decrease in quantities in

    the items of the schedule, payment shall be made only for the actual quantities executed at the

    accepted rates. If there is sufficient ground for granting extension of the date of completion on

    this account, the Railway will consider such request on the merits of each individual case.

    Such circumstances shall in no way affect or vitiate the contract or alter the character thereofor entitle contractor to damages or compensation thereof.

  • 8/6/2019 Welding Rny t

    20/59

  • 8/6/2019 Welding Rny t

    21/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    21

    2.8.7 For the tenders accepted at Zonal Railways level, variations in the quantities will be approvedby the authority in whose powers revised value of the agreement lies.

    2.8.7.1 For tenders accepted by General Manager, variations upto 125% of the original agreementvalue may be accepted by General Manager.

    2.8.7.2 For tenders accepted by Board Members and Railway Ministers, variations upto 110% of theoriginal agreement value may be accepted by General Manager.

    2.8.7.3 The aspect of vitiation of tender with respect to variation in quantities should be checked andavoided. In case of vitiation of the tender (both for increase as well as decrease of value of

    contract agreement), sanction of the competent authority as per single tender should be

    obtained.

    2.9 RATES:

    2.9.1 The Tenderer(s)/Contractor(s) have to quote only percentage increase/decrease/at par rate inthe schedule.The quantities in schedule of items of work are given in Annexure- I . In case

    of any difference in rates given in words & figures, the lowest rate shall be taken as correct.

    2.9.2 The rates for all the items of the schedule shall be inclusive of the cost of all arrangement for

    crossing frequently all obstructions, in course of the work over land or across water and thecost of providing and maintaining approach service roads and temporary bridging that

    may be necessary for bringing and removing the construction plants, machinery and

    materials to and from the site of the work including rent for use of private land and/or compensation for damage, if any due to intervening private land traversed by such approach

    service roads.

    2.9.3 The rates quoted by the contractor shall be the cost of complete work and shall include thecost of all labour and materials including transport, loading, unloading as well as sheds,

    construction plants, shuttering, scaffoldings and for which no separate payment is made to

    him, on satisfactory completion of the work shall remain the property of the contractor.2.9.4 The contractor shall entirely be responsible for ensuring safety of his labour, vehicles,

    construction plants and equipment while working. No extra payment shall be allowed to the

    contractor for any safety precautions to be observed during the execution of the work. Thecost of such precautions shall be deemed to have been included in the rates for all the items ofthe schedule.

    2.10 MATERIALS:

    2.10.1 The contractor shall at his own expense provide unless specified otherwise in schedule, allmaterials including cement reinforcement steel & dowel bars required for the works.

    2.10.2 All materials to be provided by the contractor shall be in conformity with the specificationlaid down in the Standard and Special Specifications of the tender and the contractor shall, ifrequired, furnish proof/test certificate, in support of this to the satisfaction of the Engineer.

    2.10.3 Cement and Steel for use in the works should be procured by the contractor from the mainproducer/their authorized dealers/authorized stockyard, which should conform to IS

    specification.2.10.4 Cement bags preferably in paper bag packing should bear the following information in

    legible markings.

    (i) Manufacturer's name.(ii) Registered Trade Mark of manufacturer, if any.(iii) Type of cement.(iv) Weight of each bag in kgs or No. of bags/Tone.(v) Date of manufacture, generally marked as wee of the year/year of manufacture,

    e.g. 30/01, which means 30th

    Week of 2009.

  • 8/6/2019 Welding Rny t

    22/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    22

    2.10.5 To ensure quality control, test certificates from the manufactures should be produced by the

    contractors which should conform to the relevant specifications (latest may be incorporated).

    2.10.6 Railways may also take samples during the course of work and get the cement and to steeltested ascertain their conformity to specifications.

    2.10.7 When such sampling is done, it should be as per BIS specifications.2.10.8 Tests on the samples to be carried out in the field should be given as below: -2.10.8 (a) Tests on cement to be as IS 4031. Some of the tests which may be carried out are :-

    (i) Compressive strength.(ii) Initial and final setting time.(iii) Consistency.(iv) Soundness.

    2.10.8 (b) Tests on steel samples will be carried out as per IS Specifications.

    2.10.9 The contractor shall be liable to render full accountal of all materials to be supplied byRailways for consumption on the works, and keep proper records regarding their use, which

    shall be made available for inspection when required. Without prejudice to be right of theRailway if it is detected that the quantity of cement and/or steel is less than the quantity

    ascertained/computed according to the prescribed specifications and approved drawings the

    cost of cement and/or steel not so used shall be recovered from the contractor(s) on the basisof the formula stipulated in clause 2.10.6.6.

    2.10.10For stacking cement the contractor shall at his own cost build suitable damp proof godowns atthe site of work and make all satisfactory storing arrangements to see that the strength of

    cement is not deteriorated.

    2.10.11The contractor shall indemnify the Railway, or any agent, servant or employee of the Railwayagainst any action claim or proceeding relating to infringement or use of any patent or designright and shall pay all royalties or other charges which may be payable in respect of any

    articles or materials or part thereof includes in the contract. In the event any claim being made

    or action being brought against the Railway or any agent, servant or employee of the Railway

    in respect of any such matters, as aforesaid the contractor shall be immediately notifiedthereof, provided that such indemnity shall not apply when such infringement has taken place

    in complying with the specific direction issued by the Railway but the contractor shall pay

    any royalties or other charges payable in respect of any such use.2.10.12 It shall be clearly understood that the rates to be quoted shall include all wastages and wash

    away either due to rains or storm or floods or other causes whatsoever. The rates shall also

    include the cost that may be necessary or stacking the materials at site of work.

    2.10.13SUPPLY OF MATERIALS BY RAILWAY ON LOAN BASIS

    2.10.13.1The items of Stores viz. R.S.Joists with cross bracings, CC Cribs with Clamps, P.Waymaterials, Wooden sleepers, rails & fittings only as may be required for making

    "Temporary arrangement" for execution of the work shall be supplied by the Railway onloan basis subject to the availability.

    2.10.13.2Materials to be supplied by the Railway shall be issued only to the extent of requirement.The contractor shall make his own arrangement for loading, unloading and transportation of

    the materials from Rly.'s Godown/Depots set up at RNY/RPAN/ or any otherStation/location between stations as directed by the Railway Engineer.

    2.10.13.3The Railway materials will be issued to the contractor as per provision of para 1269 of theIndian Railway Engg.Code, 1993-revised edition.

    2.10.13.4The contractor may also be issued the Railway materials directly from wagons, in whichcase a notice for taking delivery will be given by the Engineer or his representative and for

    which no extra payment shall be admissible. The contractor shall have to unload the wagonswithin the free unloading time admissible as per rules. In case of failure to do so within the

    free time, he shall be liable to pay demurrage charges. The rates quoted should include the

    cost of all transport, loading, unloading, re-handling, carriage with all lead lift & descent.

  • 8/6/2019 Welding Rny t

    23/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    23

    2.10.13.5The contractor at his own cost shall return and hand over all the Railway materials issuedon loan basis at the supply points/locations directed by the Engineer in serviceable and

    good conditions.

    2.10.13.6In case of failure of the contractor to return the Railway materials issued on loan basis inserviceable/sound and good condition the cost of the Railway Materials not returned shallbe recovered from the contractor at the recovery rate of excess materials supplied by the

    Railway should 1.5 time the cost of procurement which is inclusive of freight. The decisionof the Deputy Chief Engineer (Construction) regarding serviceability or otherwise of the

    materials returned shall be final.2.10.13.7If there is any delay on the part of the Railway in supplying materials which the Railway

    has undertaken to supply as above and if as a result thereof the completion of the work is

    delayed, the Railway will consider on specific request by the Contractor granting suitable

    extension of completion date for such loss of time. The Railway will however, not entertain

    any claim from the contractor on this regard due to any loss suffered by him on account ofhis labour or any other account as a result of delay in supply of materials.

    2.10.13.8For items at the percentage rate above, below or at par with N.F.Railway Schedule of Rates,1993 edition under the head "Any other items of works etc." the rates quoted shall includeall loading carrying and transport of materials supplied by the Railway from the points

    specified in clause 2.10.6.2.

    2.11 SITE FACILITIES:

    2.11.1 The quoted rates shall be deemed to include charges for all site facilities for labour that areconsidered necessary for execution of the work. Subject to availability of land the Railwaymay provide free site for labour camp, Construction of yard etc. close to site of work.

    2.11.2 No assurance can be given regarding the vulnerability of Railway land given for use to thecontractor to flooding during high floods. The Railway undertakes no responsibility or

    liability in this regard.

    2.11.3 The contractor shall make his own arrangements for arranging power supply, as may berequired for the work. The Railway may, however, assist in recommending his application to

    the Electricity Authority for the power supply and all cost to be borne by him/them.

    2.12 WATER SUPPLYThe contractor(s) shall make his/their own arrangement for potable water supply required for

    execution of the work. The contractor shall also provide and maintain at suitable places easily

    accessible to labour, sufficient supply of water for drinking.

    2.13 TAXES.2.13.1 The rates quoted shall include all taxes, direct or indirect, leviable under Central, State or

    Local Bodies Act or Rules Octrois, Tolls, Royalty, monopoly, seigniorages, cess and similar

    imposts that may be prevailing from time to time in respect of land, structures and all

    materials supplied in the performance of this contract.

    2.13.2 Whenever forest produces like sand, stone, timbers etc. are used in the work, the contractor(s)will have to furnish documentary proof that requisite royalty on such produces has been paidto the concerned departments.

    2.13.3 The work being "Work Contract" which is one and individual and which involves no separatecontract for the sale of materials, the contractor shall not be entitled to get any VAT and

    or any other taxes /levies etc reimbursed from the Railway Administration for the

    supply of materials.

    2.14 PLEA OF CUSTOM.2.14.1 The plea of "Custom" prevailing will not on any account be permitted as an excuse for

    infringement of any of the conditions of contract or specifications.

    2.14.2 The contract shall not be vitiated by any inadvertent omissions of any kind in the surveys,information, specifications, drawings or schedule of quantities.

    2.15 BONDED LABOUR SYSTEM: The tenderer shall note that bonded labour system iscompletely done away with on the Indian Railways including contractor's establishments on

    the Railways.

  • 8/6/2019 Welding Rny t

    24/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    24

    2.16 PROGRAMME AND COMPLETION PERIOD2.16.1 Since, the time is the essence of the contract, the tenderer shall note that in the event of his

    tender being accepted, he should be in a position to commence the work immediately and

    shall complete the same in all respect within the continuous period of5 (Five)months from

    the date of issue of acceptance letter whatever be the date of execution of work order oragreement.

    2.16.2 It shall be obligatory for the tenderer to submit his programme of work and time schedule, insuch a form as to facilitate monitoring of the work using the modern networking techniques,

    as to how he proposes to complete the work within the stipulated date.2.16.3 Within 20 days of the acceptance of the tender and before the work is commenced; the

    contractor shall have to submit a detailed programme for each major element of the work,using the modern networking techniques for Project monitoring, for approval of the Engineer.

    The construction programme will show the general methods, arrangements, order and timingfor all the significant activities in the works identifying the critical path for the work clearly,

    along with monthly cash flow. The programme shall clearly provide for and indicate the timerequired for the preliminaries before starting the work and shall indicate the dates of

    commencement and completion of the various sections of the work.

    2.16.4 The agreement or the approval of the programme by the Engineer shall not relieve thecontractor of any of his responsibilities to complete the whole works by the prescribed time.

    2.16.5 If the work does not commence within specified date of starting or if at the subsequent timethe rate of execution falls below the specific programme as indicated above, the RailwayAdministration (Construction Organization) will have the power to determine the end of the

    contract at any stage without incurring any liability on the part of the Railway Administrationfor any sort of compensation for the money invested by the contractor(s) or the loss incurred

    by him/them due to such termination of the contract. In all cases of incomplete work, eitherby termination of contract by the Railway Administration under consideration stated above or

    due to failure on the part of the contractor(s) to complete the work within stipulated date of

    completion of the Agreement, the Railway shall be entitled to take the action for rescinding

    the contract in terms of clause 62 of GCC-98.2.16.6 The Contractor shall submit to the Engineer, for approval, an updated Program, whenever the

    Engineer may so direct, to take account of the actual progress of the Contract Works so as to

    achieve completion either before the due date for completion or by the due date for

    completion or as soon as practicable thereafter. The Engineer may further require the

    Contractor to indicate the means by which the programmed progress will be achieved. If theContractor does not submit an updated Programme within a reasonable period as indicated bythe Engineer, the Engineer may withhold the payment of next on account bill until theoverdueProgramme has been submitted.

    2.17 EXTENSION OF COMPLETION DATE:

    2.17.1 Extension of time for the completion of the work shall be governed by Clause 17 of the GCC (Part-A) and SSCC(Part-B) - 1993 and the contractor shall be responsible for requesting such extension in terms thereof. While

    applying for such extension, a Bar Chart showing the work already done and the program for the work to be doneshall be prepared and shown in juxtaposition with the bar chart submitted in terms of contract conditions, giving

    reasons for activity-wise slippage. The Railway shall agree to such extension of time of completion, as considered

    justified.

    2.17.2 Extension under Clause 17(B) of GCC (Part-A) and SSCC (Part-B)-1993 provides for recovery of liquidated damagesfrom the contractor. While granting extension to the currency of the contract under Clause 17(B) of this GCC thecompetent authority may also consider levy of token penalty as deemed fit based on the merit of the case.

    2.18 PROGRESS OF WORKS.2.18.1 The contractor shall submit to the Engineer a monthly report giving progress of works by the third of the following

    month.

    2.18.2 It shall be ensured that the works are carried out according to the agreed programme and no change are madeexcept with the prior approval or at the instance of the Engineer.

    2.18.3 The contractor shall participate in periodical meetings with the Engineer to review the progress of the work. Incase a slippage in the time schedule due to the contractor's inability to perform as per agreed programme, thecontractor shall take such action as may be necessary to bring back his work to schedule without additional cost to

    the Railway, either by employing over time operations, increasing the number of shifts, capacity of constructionplants, or as directed by the Engineer.

    2.18.4 The contractor shall immediately inform the Engineer whenever there is or is likely to be any change in theschedule.

  • 8/6/2019 Welding Rny t

    25/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    25

    3.0 EXECUTION OF WORKS.

    3.1.1 INSPECTION OF SITE.

    3.1.1 The tenderer shall in their own interest examine the drawings, conditions of contract and specifications of work.

    They shall also inspect the site and satisfy themselves on their own as to the hydrological, climatic and physical

    conditions prevailing at site, the nature, extent and practicability of the works, all existing and required roads andother means of communication and across to the site, whether by water or land, availability of housing and other

    facilities, the source of supply of different materials and their adequacy, royalty, monopoly ferry charges, labour

    and probable site for labour camp, stores and godowns etc. They shall themselves obtain all necessary information

    as to risk, contingencies and other circumstances which may effect or influence their tender. No extra charges

    consequent on any insufficient appreciation or otherwise shall be entertained.3.1.2 It shall be deemed that the tenderer has inspected the site in all respect as explained in para 3.1.1 before quoting his

    rates and has satisfied himself about the nature and type of work including ancillary works necessary for thesatisfactory fulfillment of the contract.

    3.1.3 Should there be any discrepancy in, or any doubt or obscurity as to the meaning of any of the tender documents oras to any thing to be done or not to be done by the tenderer or the instructions to be observed by him, he must set

    forth in writing such discrepancies, doubts or of obscurities and submit the same to the General

    Manager/Construction, N.F.Railway, Maligaon, Guwahati for elucidation as soon as possible but not later than 10days before the last date fixed for receipt of tenders.

    3.2 SUPERVISION AND APPROVAL BY ENGINEER.3.2.1 All works embracing more than one process shall be subject to examination and approval by the Engineer at each

    stage thereof and the contractor shall give due notice to the Engineer or the authorised representative when suchstate is ready. In default of such notice, the Engineer shall be entitled to appraise the quantity and extent thereof,

    even at a later stage at the risk and cost of the contractor.

    3.2.2 The contractor will set up a properly equipped laboratory either in the field or at a suitable location to conduct testregarding quality control of concrete and other tests as required under the specification prescribed.

    3.2.3 The Engineer reserves the right to reject the whole or part of work executed, which in his judgment does notcomply with the requirements of the specifications. The decision of the Engineer shall be final and conclusive in

    this matter for all purposes.

    3.3 EXAMINATION OF WORK BEFORE COVERING UP.3.3.1 No work shall be covered up or put out of view without the approval of the Engineer or his authorised

    representative and the contractor shall accord full opportunity for examination and measurement of any work

    which is about to be covered up or put out of view and for examination of foundations before permanent work isput thereon. The contractor shall give 7 days notice to the Engineer or his representative whenever any such work

    of foundation is ready for examination and the Engineer or his authorised representative shall within reasonabletime, unless he considers it unnecessary and advises the contractor accordingly, attend for the purpose of

    examination and measurement of such foundations. In the event of failure of the contractor to give such notice he

    shall, if required by the Engineer, uncover such work at contractor's expense.3.3.2 Railway Officials concerned with the contract shall have powers at any time to inspect and examine any part of

    the works and the contractor shall give such facilities as may be required for such inspection and examination.

    3.3.3 The contractor shall uncover any part of work and or make openings in or through the same as the Engineer mayfrom time to time direct for his verification and shall reinstate and make good such part to the satisfaction of the

    Engineer at his own cost.

    3.4 REMOVAL OF OBSTRUCTIONS.3.4.1 Before the work is started, the site shall be cleared of all obstructions like trees and bushes along with their roots,

    heavy grass and shrubs by the contractor at his own cost.

    3.4.2 The contractor shall not have any claim in case of delay by the Railway in removal of trees or shifting raising,removing of telegraph or telephones or electric lines (overhead or underground) and other structure, if any, which

    may come in way of the work.

    3.5 STORES, SHEDS AND YARDS.3.5.1 The contractor shall provide at his own cost suitable storage arrangement for cement and steel to the satisfaction of

    the Engineer and the Engineer or his representative shall have the authority at all times to inspect the storagearrangement and contractor shall provide all facilities for inspection and check of materials. For the materials

    supplied by the Railway the contractor shall at all times maintain proper records showing the basis of the indent,the receipts and utilisation of the materials and these shall at all times be opened for inspection by the Engineer or

    his representative.

    3.5.2 The storage capacity for cement shall be for not less than 30 days requirement of cement for the work on hand andanticipated at the time at the rate of progress of work. The arrangement for storage shall be such as to ensure that

    utilization of cement is in order of its arrival at the stores.3.5.3 All the stores viz. steel and cement which are supplied by the Railway shall be stored by the contractor only at

    places approved by the Engineer. The storage and safe custody of these materials after issue shall be the

    responsibility of the contractor.3.5.4 Inflammable materials such as petrol, oil etc. shall be stored separately from other store and all the precautions as

    required under the Indian Explosive Act shall be taken by the contractor(s) and shall indemnify absolutely the

    Railway and its officers and employees against any claim or liability arising out of any accident or violation of any

    laws, rules and orders.

  • 8/6/2019 Welding Rny t

    26/59

    Tender No.CE/CON/RNY-RPAN-TZTB/F.B.Welding-52 Kg/2011/02

    Signature of tenderer(s)/contractor(s) for Chief Engineer/Con

    N.F.Railway,Maligaon.

    26

    3.6 TOOLS AND PLANTS.3.6.1 All construction plants, temporary works and materials provided by the contractor shall when brought to the site be

    deemed to be exclusively intended for the construction and completion of the work and the contractor shall notremove the same or any part thereof (save for this purpose of moving it from one part of the site to another)

    without the consent in writing of the Engineer.

    3.6.2 On completion of the work, the contractor shall remove from the site all the said constructionplants and temporary works remaining thereon and any unutilised materials provided by the

    contractor.3.6.3 The Railway shall not at any time be liable for the loss of injury to any of the said

    construction plant, temporary works of materials save as otherwise provided in thesedocuments.

    3.6.4 The contractor shall make his own arrangement for all construction plants and equipment,tools including spare parts, fuel and consumable stores and all labour required to ensure

    efficient and methodical execution of the work. The quoted rates shall be inclusive of allcharges as such items.

    3.7 NIGHT WORKS.3.7.1 The provision in clause 23 of the General Conditions of the contract shall be noted regarding

    execution of work between sunset and sunrise. If the Railway is however, satisfied that the

    work is not likely to be completed in time except by resorting to night work, by special order

    the contractor would be required to carry out the work, even at night, without conferring anyright on the contractor for claiming extra payment for introducing night work. In the event of

    night working, the contractor will make necessary adequate lighting arrangement for smooth

    execution of work.3.7.2 If the contractor works round the clock on all days including sundays and holidays, the

    Railway shall make arrangements for the supervision accordingly.

    3.8 REPRESENTATION ON WORKS.Regarding representation on works and supervision, the provisions in clause 12 of General

    Conditions of contract and clause 24 of Standard Special Conditions of Contract shall be

    applicable respectively.

    3.9 REMOVAL OF DEFECTIVE WORKS:If in the opinion of the Engineer, any of the works had been executed with improper materials

    or defective workmanship, the contractor when required by the Engineer, shall re-execute thesame and substitute proper materials and workmanship forthwith at his own cost and in caseof default of contractor in so doing within a week; the Engineer shall have full power to

    employ other persons to execute the work and the cost thereof shall be borne by the

    contractor.

    3.10 DISMANTLING3.10.1 When dismantling of any existing structure is involved to facilitate the Construction, the

    contractor shall submit the scheme for dismantling of the existing structure. Execution ofdismantling works shall be done after approval of Railway.

    3.10.2 The dismantling of stru


Recommended