WEST LEDA – SAT DIVING PLATFORMLEARNING EXPERIENCE
By
Ranjith Kumar &Kuldipak Pednekar
PROJECT OUTLINE
First of it’s kind project, as so far Sat diving system is never placed on any Jack up rig
S4 sat system is most compact diving system available in market.
Typical Fast Track project
Type: Jack up rig
Name: West Leda
Owner: Seadrill
Vessel Info
Type: Saturation diving
Name: S4 Sat system
Owner: Cal Dive
Diving system Info
INITIAL SCOPE OF WORK FROM SEADRILL
Design Saturation Diving System (4 person chamber) Platform at a height of 5 to 6m above main deck.
General Arrangement of all S4 diving equipment is provided.
Need to arrange equipment on platform
Weight of diving equipments around 100T
DESIGN PHILOSOPHY
Main chamber, HRC, Umbilical basket, Reclaim van, and Workshop to go on platform
In case of emergency, HRC (diving rescue boat) to be launched in sea by using onboard crane
Platform not to extend beyond anchor pocket arrangement
Platform to be well above Anchor winch
ISO FORMAT MINUTES OF ONBOARD MEETING WITH RIG MASTER
MEETING AT CAL DIVE WORKSHOP
Initial Preparation
General layout drawing showing all items of diving system
3D model prepared on basis of initial scope of work
Summary of meeting In case of emergency
HRC have to have its own launching system
Opening for HRC to launch
HRC launching davit with self powered winch arrangement
Two more containers to be added
Gas quads to be located on platform
ISO FORMAT MINUTES OF THE MEETING CONDUCTED AT CAL DIVE
KICK OFF MEETING AT PPL SHIPYARD
PARTIES PRESENT
Seadrill ABS PPL shipyard Cybermarine
SUMMARY
PPL has been given two weeks deadline to finish complete job
AutoCAD drawing to be provided to PPL
ABS was more concerned about Stability
DRAWING PREPARED
Platform structural drawing
Main deck structural drawing
INFORMATION TRANSMISSION
INFORMATION TRANSMISSION
Initial info received from client via email, same has been forwarded
Minutes of meeting prepared and sent
Design changes have been conveyed over phone
Hand sketches made at site sent via email
Drawings collected from client scanned and sent via email
Photos clicked by phone sent via mobile network
Maximum information collected and forwarded
SAMPLE HAND SKETCHES
SAMPLE CONCEPT HAND SKETCHES
SAMPLE DESIGN PHILOSOPHIES
INFORMATION TRACKING
Created hard copy of project file for easy reference
All layout drawings, information collected in hard copy format, concepts hand sketches and design philosophies maintained in project file
MODIFICATIONS DONE IN INITIAL STAGE
INTERFERENCES AT SITE
Interference of platform support bracings with vent pipe
Interference of offloading hose with support bracing
Interference of pipe with underdeck newly added web
VENT PIPE INTERFERENCE
PIPE INTERFERENCE WITH UNDER DECK WEB
DESIGN CHANGES
Overturning procedure Platform extension on offloading platform Introduction of HRC lifting spreader Collapsible beam design change Introduction of hydraulic ram arrangement and later
same is canceled Umbilical basket location change Opening on platform for umbilical to pass Fixed platform for HRC outboard access HRC frame height increase Change in HRC launch opening
DESIGN CHANGES
HRC leveling to match with flange on main chamber Collapsible foldable platform to access control panel
on main chamber which was later changed to fixed platform
New inboard platform to be added to access valves on reclaim van
Introduction of Air diving system HRC pull out pad eye Container access platform modification Pad-eye reorientation on HRC lifting spreader Winch shifted on platform
OVERTURNING PROCEDURE
ISSUES ENCOUNTERED
INCORRECT DETAILS HRC FRAME PULLEY
INCORRECT ORIENTATION OF PULLEY ON HRCFRAME
Extension plate was provided on aft where as it was required on fwd side
INCORRECT ORIENTATION OF PAD EYE ON HRCLIFTING SPREADER
Top pad eye orientation has been changed to suit sheave assembly with hydraulic pin
UMBILICAL BASKET
Wire lengths were different and drawing was not followed properly
Issue was solved by using wire at correct location
PHOTO GALLERY
PLATFORM WAITING FOR SAND BLASTING
•NEW ACCESS LADDER •PULLEY ON HRC FRAME
HRC HOOKED UP TO MAIN CHANBER
BOTTOM VIEW OF HRC LAUNCH OPENING
TOP OF HRC
COLLAPSIBLE BEAMS WITH PIN ARRANGEMENT
HRC PULL-OUT PAD EYE
HRC FRAME
PULLEY ON HRC FRAME
FIXED PLATFORM TO ACCESS PANEL DOOR
CONTAINER ACCESS PLATFORM
AIR DIVING SYSTEM
AIR DIVING LAUNCHING PAD EYE
HRC LIFTING WINCH
SHEAVE ON TOP OF HRC LIFTING FRAME
HRC LIFTING HYDRAULIC SHEAVE
THANKS FOR YOUR PATIENCE