TRANSMISSION LINE & SUBSTATION PROJECTS
COMPANY: ENTERGY SERVICES, INC.
CUSTOMER: ENTERGY SERVICES, INC. (SPO)
FACILITIES STUDY
EJO NO. F4PPAR0490
ICTT-2010-158
TRANSMISSION SERVICE FACILITIES STUDY
OASIS 75009407
Revision: 0
Rev Issue Date
Description of Revision Prepared
By Approved
By
B 7/14/11 Submitted to TPD, JET, for review/comments
RP AH
C 7/15/11 Approved with Revisions per comments from JET,TPD, and Director
RP AH
D 7/18/11 Formatted by TPD GWR
E 7/22/11 Update Schedule Data GWR
0 7/27/11 ICT Determines Upgrade Classification Sherri Maxey
Ben Roubique
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
2
TABLE OF CONTENTS
1. PROJECT SUMMARY 3 1.1 Background and Project Need 3 1.2 Scope Summary 3 1.3 Cost Summary 5 1.4 Schedule Summary 5
2. SAFETY REQUIREMENTS 5
3. GENERAL ASSUMPTIONS 5
4. GENERAL SCOPE OF WORK 6 4.1 Ebony 161 kV Switching Station: Add a 24 MVAR Capacitor Bank 6 4.2 Ebony 161 kV Switching Station: Upgrade the 24 MVAR Capacitor Bank to 36 MVARs 8 4.3 Moses 161 kV Substation: Add 12 MVAR Capacitor Bank 8
5. COST 10
6. UPGRADE CLASSIFICATION 10
7. SCHEDULE 10
8. RISK ASSESSMENT 12
9. CONFIRMED RESERVATIONS 13
10. PRE-888 TRANSACTIONS 18
11. STUDY QUEUE 19
12. ATTACHMENTS 20 12.1 Table of Acronyms 20 12.2 Drawings 21 12.3 Duration Schedule 21
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
3
1. PROJECT SUMMARY
1.1 Background and Project Need The purpose of this Facilities Study is to determine the availability of undesignation of 140 MW of yearly network transmission service on Entergy’s transmission system from 1/1/2012 to 1/1/2042. This study was performed on the latest available January 2012 – October 2012 monthly models, 2012–2020 winter, and 2013–2020 summer peak seasonal models, using PSS/E and MUST software by PTI). The Facilities Study identifies any transmission constraints resulting from the requested power transfer. The Facilities Study also includes cost estimates to correct any transmission constraints.
1.2 Scope Summary
The Facilities Study has identified some transmission constraints. The following projects are needed prior to the start of transmission service.
1.2.1 2011-2013 Approved Entergy Construction Plan Projects required by
1/1/2014 The following projects are approved in the 2011-2013 Entergy Construction Plan. These projects are required to be in-service prior to January 1, 2014:
Jonesboro - Hergett 161 kV line upgrade – 2012 Expected ISD.
1.2.2 Ebony 161 kV Switching Station: Add a 24 MVAR capacitor bank For this TSR, the following upgrade is required to be in-service by January 1, 2013:
For the loss of the West Memphis EHV 500/161 kV autotransformer, voltages at the following substations decrease below 0.92pu:
West Memphis EHV 161 kV
Ebony Switching Station 161 kV
Marion 161 kV
Hughes 161 kV
Kuhn Road 161 kV
Harrisburg Switching Station 161 kV
Lepanto 161 kV
Marked Tree 161 kV
Harrisburg 161 kV
Wynne Industrial 161 kV
Wynne South 161 kV
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
4
Trumann 161 kV
Wynne East 161 kV
Twist 161 kV
It is required that the 24 MVAR capacitor bank at Ebony 161 kV Switching Station be upgraded to 36 MVARs.
1.2.3 Ebony 161 kV Switching Station: Upgrade the 24 MVAR capacitor bank to
36 MVARs For this TSR, the following upgrade is required to be in-service by January 1, 2013. For the loss of the West Memphis EHV 500/161 kV autotransformer, voltages at the following substations decrease below 0.92pu.
West Memphis EHV 161 kV
Ebony Switching Station 161 kV
Marion 161 kV
Hughes 161 kV
Kuhn Road 161 kV
Harrisburg Switching Station 161 kV
Lepanto 161 kV
Marked Tree 161 kV
Harrisburg 161 kV
Wynne Industrial 161 kV
Wynne South 161 kV
Trumann 161 kV
Wynne East 161 kV
Twist 161 kV
1.2.4 Moses 161 kV Substation: Add 12 MVAR Capacitor Bank For this TSR, the following upgrade is required to be in-service by January 1, 2013.
For the loss of the West Memphis EHV 500/161 kV autotransformer, voltages at the following substations decrease below 0.92pu:
West Memphis EHV 161 kV
Ebony Switching Station 161 kV
Marion 161 kV
Hughes 161 kV
Kuhn Road 161 kV
Harrisburg Switching Station 161 kV
Lepanto 161 kV
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
5
Marked Tree 161 kV
Harrisburg 161 kV
Wynne Industrial 161 kV
Wynne South 161 kV
Trumann 161 kV
Wynne East 161 kV
Twist 161 kV
It is required that a 12 MVAR capacitor bank be installed at the Moses 161 kV substation.
1.3 Cost Summary
The estimated total project cost in 2011 dollars is $1,565,000. This does not include Tax Gross Up, which may apply (rate at this time is 27.16%).
The ICT has assigned $809,838 as Base Case upgrades, and $755,218 as Supplemental Upgrade based on Attachment T of Entergy’s OATT.
1.4 Schedule Summary
The requested in-service date is January 1, 2012. The duration of work scoped and estimated below is 14 months, starting from October 1, 2011, and is expected to be completed by December 31, 2012. Transmission service is projected to be available January 1, 2013, based on in-service of all required projects.
2. SAFETY REQUIREMENTS
Safety is a priority with Entergy. Safety will be designed into substations and lines. The designs will be done with the utmost safety for personnel in mind for construction, operation, and maintenance of the equipment. All employees working directly or indirectly for Entergy shall adhere to all rules and regulations outlined within the Entergy Safety manual. Entergy requires safety to be the highest priority for all projects. All Entergy and Contract employees must follow all applicable safe work procedures.
3. GENERAL ASSUMPTIONS Sufficient time will be allowed in approving the project enabling Entergy to prepare a PEP, and be able to complete the project as per schedule described below. The use of Facilities Study and estimates is not favored to commence an approved project. Assumptions have been made in developing estimates without performing site visits, surveys, and soil borings. During PEP, these tasks will be completed and could have an impact on estimates and schedule.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
6
All costs above represent good faith estimates in today’s dollars, are based on existing data, and could change considerably after development of detailed PEP. Price escalation for work in future years has not been included.
4. GENERAL SCOPE OF WORK
4.1 Ebony 161 kV Switching Station: Add a 24 MVAR Capacitor Bank Site Work
Install, fill and grade new area to prepare site for new capacitor bank.
Install 90 tons of crushed rock in the expanded fence area.
Install 45 tons of crushed rock after conduit and ground grid installation.
Foundation Work
Install three (3) 161 kv CCVT foundations (drilled piers).
Install foundation for one (1) 161 kv cap-switcher (Two (2) drilled piers).
Install foundation for one (1) 90’ lightning mast.
Install foundation for one (1) 161 kv, 24 MVAR capacitor bank (three (3) sets of two (2) pads).
Install one (1) pull box for conduit bank installation.
Install 500’ of conduit.
Install 300’ of ground grid.
Electrical Work
Install one (1) 161 kV 2000A disconnect vertical switch w/125VDC motor operator.
Install one (1) 161 kV 1200A existing disconnect vertical line switch with vacuum bottle, with 125 VDC motor operator to be used as a disconnect switch for the capacitor bank.
Install one (1) 161 kV, 24.0 MVAR cap bank, including steel structure.
Install one (1) 90’ lightning mast steel structure.
Install one (1) 161 kV cap-switcher with 150 ohm resistors.
Install three (3) CCVT pedestals.
Install nine (9) 161 kV porcelain post Insulator.
Install 200LF 336 MCM conductor and associated fittings.
Install 100LF 1272 MCM conductor and associated fittings.
Install above-ground “pigtails” to equipment and structures.
Install above-ground conduits to equipment.
Relay Work
Add an AC/DC split panel per Entergy standard PM0101 option C.
Add D20 RTU.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
7
Purchase and install 24” capacitor bank panel with SEL-451. An Entergy representative should also participate in conducting the training along with the SEL representative.
Purchase one (1) line trap on A Phase to block a 165 kHz carrier signal. Specifications include 400 amp and vertical pedestal mount.
Purchase, design and install three (3) CCVTs to monitor the bus voltage.
Purchase, design and install a resistive potential device on the capacitor bank neutral.
Purchase and install outdoor neutral NEMA Type 4X high voltage CCVT junction box.
Purchase and install outdoor NEMA Type 4X neutral potential junction box.
Purchase and install approximately 12 cables from the control house to the yard devices, including capacitor switcher, bus CCVT junction box, and neutral potential junction box.
RTU configuration will be required.
Relay settings will be required. Relay design and relay settings need to work closely together to ensure proper coordination between the capacitor bank protection and the line reclosing. For example, ensure the proper settings on the cap bank protection trips on the cap switcher when there is a fault on the line. The bank trip needs to be completed prior to the reclosing at the remote line ends.
Host database changes will be required.
Settings Work
Calculate and develop relay setting for the new SEL-451 capacitor bank relays.
Revise RTU configuration.
Construction and Outage Plan If this project is approved and enters the Energy Delivery’s (PM&C) process for executing projects, there will be constructability reviews performed during the definition phase. These reviews will try to incorporate any known hazards from a safety perspective, as well as any obstacles that could/would be experienced during the construction and installation process. After receipt of the final design drawings and details for each discipline of work, a determination will be made to either use the preferred supplier resources, perform a competitive bid process to award the work to an Entergy approved contractor, or to allow internal Entergy Resources to perform the work. Construction will be accomplished by pre-qualified electrical contractor crews under the supervision of Entergy personnel.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
8
4.2 Ebony 161 kV Switching Station: Upgrade the 24 MVAR Capacitor Bank to 36 MVARs
This upgrade provides for an additional 12 MVARs to the Ebony 161 kV Switching Station project referenced in the approved capital projects for 2011 – 2012 budget years. The upgrade from 24 MVARs to 36 MVARs would require an upgrade to the capacitor bank electrical equipment only. The site, foundation, and electrical support steel would be sufficient. There would also be some relaying and relay settings calculation modifications to be made due to the increase in the size of the capacitor bank.
4.3 Moses 161 kV Substation: Add 12 MVAR Capacitor Bank
For this TSR, the following upgrade is required to be in-service by January 1, 2013.
Site Work
Install, fill and grade new area to prepare site for new capacitor bank.
Install 90 tons of crushed rock in the expanded fence area.
Install 45 tons of crushed rock after conduit & ground grid installation.
Foundation Work
Install 3-161 kV CCVT foundations (drilled piers).
Install foundation for one (1) 161 kV cap-switcher (two (2) drilled piers).
Install foundation for one (1) 90’ lightning mast.
Install foundation for one (1) 161 kV, 12 MVAR capacitor bank (three (3) sets of two (2) pads).
Install one (1) pull box for conduit bank installation.
Install 500’ of conduit.
Install 300’ of ground grid.
Electrical Work
Install one (1) 161 kV 2000A disconnect vertical switch with 125 VDC motor operator.
Install one (1) 161 kV 1200A existing disconnect vertical line switch with vacuum bottle with 125 VDC motor operator to be used as a disconnect switch for the capacitor bank.
Install one (1) 161 kV, 12.0 MVAR cap bank, including steel structure.
Install one (1) 90’ lightning mast steel structure.
Install one (1) 161 kV cap-switcher with 150 ohm resistors.
Install three (3) CCVT pedestals.
Install nine (9) 161 kV porcelain post Insulator.
Install 200LF 336 MCM conductor and associated fittings.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
9
Install 100LF 1272 MCM conductor and associated fittings.
Install above-ground “pigtails” to equipment and structures.
Install above-ground conduits to equipment.
Relay Work
Add an AC/DC split panel per Entergy standard PM0101 option C.
Add D20 RTU.
Purchase and install 24” capacitor bank panel with SEL-451. An Entergy representative should also participate in conducting the training, along with the SEL representative.
Purchase one (1) line trap on A Phase to block a 165 kHz carrier signal. Specifications include 400 amp and vertical pedestal mount.
Purchase, design and install three (3) CCVTs to monitor the bus voltage.
Purchase, design and install a resistive potential device on the capacitor bank neutral.
Purchase and install outdoor neutral NEMA type 4X high voltage CCVT junction box.
Purchase and install outdoor NEMA type 4X neutral potential junction box.
Purchase and install approximately 12 cables from the control house to the yard devices, including capacitor switcher, bus CCVT junction box, and neutral potential junction box.
RTU Configuration will be required.
Relay settings will be required. Relay design and relay settings need to work closely together to ensure proper coordination between the capacitor bank protection and the line reclosing. For example, ensure the proper settings on the cap bank protection trips the cap switcher when there is a fault on the line. The bank trip needs to be completed prior to the reclosing at the remote line ends.
Host database changes will be required.
Settings Work
Calculate and develop relay setting for the new SEL-451 capacitor bank relays.
Revise RTU configuration.
Construction and Outage Plan
If this project is approved and enters the Energy Delivery’s (PM&C) process for executing projects, there will be constructability reviews performed during the definition phase. These reviews will try to incorporate any known hazards from a safety perspective, as well as any obstacles that could/would be experienced during the construction and installation process. After receipt of the final design drawings and details for each discipline of work, a determination will be made to either use the preferred supplier resources, perform a competitive bid process to award the work to an Entergy approved contractor, or to allow internal Entergy Resources to perform the work.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
10
Construction will be accomplished by pre-qualified electrical contractor crews under the supervision of Entergy personnel.
5. COST
The ICT has reviewed and determined whether each required upgrade will be considered a Base Plan Upgrade or a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT. The costs shown in the table include all applicable overheads, but do not include tax gross up. Entergy incurs a tax liability proportional to the amount of customer contributions.
Projected Costs including indirect cost are through 2011 dollars
6. UPGRADE CLASSIFICATION
The ICT has reviewed and determined whether each required upgrade will be considered a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT.
Task Total Cost Base Plan Supplemental FFRs Reference
Ebony 24 MVAR $ 809,838 $ 809,838 Section 4.1
Ebony 24 to 36 MVAR $ 48,028 $ 48,028 Section 4.2
Moses 12 MVAR $ 707,190 $ 707,190 Section 4.3
TOTAL COST: $ 1,565,056 $ 809,838 $ 755,218
7. SCHEDULE A detailed schedule will be prepared subsequent to customer approval to proceed with the project. Based on the Task duration schedules listed below, the overall project in-service date is projected to be January 1, 2013. Based on an assumed customer approval date of October 1, 2011, the following are approximate schedule dates:
All construction work requiring outages will be performed during acceptable periods of system condition to ensure reliable operation of the system, which most often is the off-
Project Title 2011 2012 Total
Ebony 161kV Switching Station - Install 24MVAR
Capacitor Bank 113,091$ 696,747$ 809,838$ Ebony 161kV Switching Station - Upgrade
24MVAR Capacitor Bank to 36MVAR's 259$ 47,769$ 48,028$ Moses 161 kV Substation: Add 12 MVAR
Capacitor Bank 101,337$ 605,853$ 707,190$ Total Project Cost: 214,687$ 1,350,369$ 1,565,056$
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
11
peak load season. Line outages will be discussed with the SOC and TOC, and the assumption is made that line outages will be executed as planned. However, an evolving system condition may result in cancellation of approved outages by the SOC/TOC, and may also result in additional schedule delay.
Substation construction will be coordinated with the transmission line outages when possible.
Construction resources are available when required.
Transmission line and substation projects will begin subsequent to definition phase of PEP.
This schedule does not account for non-typical adverse weather conditions.
Schedule durations are high level estimates at this time. A detailed schedule will be prepared upon project approval.
Scheduling assumptions and completion dates
Receive customer approval by October 1, 2011.
Completion of PEP/estimates by December 1, 2011.
Approval from customer to proceed with the project followed by creation of FP and work orders in place by January 1, 2012.
Commence engineering and permitting work by February 1, 2012.
Issue design packages to construction by June 1, 2012.
Construction work starting August 1, 2012, and complete by December 31, 2012.
It is assumed the outages are available as per Construction Plans.
The customer requested in-service date of January 1, 2012, is not attainable based on the duration assumptions made in this study.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
12
8. RISK ASSESSMENT
Risk Comment Impact
Material costs steel & Equipment
Rising steel, copper, fuel and other market conditions could greatly affect estimated cost.
**
Storm-water plan implementation
Best guess on SWPPP creation, implementation and monitoring can vary greatly dependant on outcome of environmental study.
*
Weather & Equipment Lead Times
Unexpected delays on material lead times, unusually inclement weather will impact schedule but might impact AFUDC costs as well.
**
Wetland mitigation Undetermined until environmental analysis is complete.
*
Outages may not be available
Preliminary schedule only considers general outage constraints. Specific project schedule may be delayed by days, weeks or months dependant on system conditions. Delays of months = increased project costs.
****
Scope based on design assumptions which may change Varied impact on cost and schedule.
****
*-low impact to cost, ** - moderate impact to cost, ***- high impact to cost, **** - very high impact to cost.
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
13
9. CONFIRMED RESERVATIONS
The following transactions were included in this Facilities Study:
OASIS PSE MW Begin End
569011 Entergy Services, Inc. (EMO) 242 3/1/2000 1/1/2014
759196 Entergy Services, Inc. (EMO) 143 1/1/2001 1/1/2021
759294 East Texas Electric Cooperative 31 1/1/2001 1/1/2018
1096986 Tennessee Valley Authority 73 9/1/2003 9/1/2013
1099991 (renewal) City Water & Light, Jonesboro 83 1/1/2010 1/1/2016
1099997 (renewal) City Water & Light, Jonesboro 168 1/1/2010 1/1/2016
1105665 Entergy Services, Inc. (EMO) 236 2/1/2003 2/1/2016
1105666 Entergy Services, Inc. (EMO) 91 2/1/2003 2/1/2027
1105668 Entergy Services, Inc. (EMO) 77 2/1/2003 2/1/2027
1126821 Entergy Services, Inc. (EMO) 101 5/1/2004 5/1/2029
1151106 Entergy Services, Inc. (EMO) 20 6/1/2010 6/1/2029
1168061 Entergy Services, Inc. (EMO) 80 8/1/2004 2/1/2028
1168408 Entergy Services, Inc. (EMO) 247 8/1/2004 2/1/2028
1289686 (undesignation) Entergy Services, Inc. (EMO) 1 6/1/2007 6/1/2030
1294132 Entergy Services, Inc. (EMO) 526 1/1/2006 1/1/2035
1309874 (renewal) East Texas Electric Cooperative 75 1/1/2009 1/1/2017
1309875 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017
1309876 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017
1356328 Muni Energy Agcy of Miss 40 6/1/2010 6/1/2040
1373643 City of Conway 25 3/1/2010 3/1/2040
1375299 Louisiana Generating LLC 11 3/1/2006 3/1/2013
1375559 CLECO Power LLC (Gen) 675 12/1/2006 12/1/2016
1380484 Osceola Light & Power 9 9/1/2009 9/1/2039
1381398 Constellation Energy Commodities Grp.
34 1/1/2006 1/1/2036
1381400 Constellation Energy Commodities Grp.
34 1/1/2006 1/1/2036
1381404 Constellation Energy Commodities Grp.
17 1/1/2006 1/1/2036
1381406 Constellation Energy Commodities Grp.
17 1/1/2006 1/1/2036
1383852 Arkansas Electric Cooperative Corp. 550 1/1/2007 1/1/2017
1385158 NRG Power Marketing 13 10/1/20070 10/1/2027
1387272 CLECO Power LLC (Gen) 11 4/1/2006 4/1/2016
1410022 Constellation Energy Commodities 60 3/1/2010 3/1/2040
1422708 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2007 1/1/2027
1425495 East Texas Electric Cooperative 50 3/1/2010 3/1/2045
1437089 Arkansas Electric Cooperative Corp. 349 1/1/2007 1/1/2012
1440189 Arkansas Electric Cooperative Corp. 84 1/1/2008 1/1/2012
1440190 Arkansas Electric Cooperative Corp. 104 1/1/2008 1/1/2012
1442453 NRG Power Marketing 320 6/1/2007 6/1/2026
1449495 Entergy Services, Inc. (EMO) 322 6/1/2009 6/1/2059
1456636 CLECO Power Marketing 10 10/1/2007 10/1/2012
1460876 Aquila Networks-MPS 75 3/1/2009 3/1/2029
1460878 Aquila Networks-MPS 75 3/1/2009 3/1/2029
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
14
OASIS PSE MW Begin End
1460879 Aquila Networks-MPS 75 3/1/2009 3/1/2029
1460881 Aquila Networks-MPS 75 3/1/2009 3/1/2029
1460898 Louisiana Energy & Power Authority 3 1/1/2009 1/1/2030
1460899 Louisiana Energy & Power Authority 5 1/1/2009 1/1/2030
1461442 Louisiana Energy & Power Authority 12 1/1/2009 1/1/2030
1464028 East Texas Electric Cooperative 168 1/1/2010 1/1/2040
1468113 Muni Energy Agcy of Miss 20 6/1/2011 6/1/2041
1470484 City of West Memphis 20 1/1/2011 1/1/2041
1470811 East Texas Electric Cooperative 186 1/1/2010 1/1/2040
1477069 Entergy Services, Inc. (EMO) 10 11/1/2007 11/1/2037
1480164 Entergy Services, Inc. (EMO) 725 1/1/2005 9/1/2033
1495910 Southwestern Electric 78 5/1/2010 5/1/2013
1498122 Constellation Energy Commodities Grp.
30 4/1/2012 4/1/2042
1498129 City of Conway 50 4/1/2012 4/1/2042
1499610 Entergy Services, Inc. (EMO) 300 1/1/2008 1/1/2038
1500582 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038
1500584 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038
1502952 Arkansas Electric Cooperative Corp. 330 1/1/2008 1/1/2030
1514102 East Texas Electric Cooperative 29 1/1/2008 1/1/2017
1514104 East Texas Electric Cooperative 35 1/1/2008 1/1/2017
1514105 (undesignation) East Texas Electric Cooperative 1 1/1/2008 1/1/2017
1517005 (renewal) NRG Power Marketing 103 1/1/2011 1/1/2026
1525820 (renewal) NRG Power Marketing 3 7/1/2009 7/1/2014
1527816 Westar Energy 6 10/1/2007 10/1/2012
1530287 Empire District Electric 50 3/1/2010 3/1/2030
1530288 Empire District Electric 50 3/1/2010 3/1/2030
1546108 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2011 1/1/2051
1552148 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2014
1555717 (undesignation) East Texas Electric Cooperative 1 1/1/2010 1/1/2015
1555718 Entergy Services, Inc. (EMO) 158 1/1/2010 1/1/2015
1557220 (undesignation) Entergy Services, Inc. (EMO) 1 7/1/2009 7/1/2018
1557221 Entergy Services, Inc. (EMO) 520 7/1/2009 7/1/2018
1557602 (undesignation) East Texas Electric Cooperative 1 1/1/2009 1/1/2017
1564001 (renewal) Louisiana Energy & Power Authority 6 4/1/2009 4/1/2014
1564356 (renewal) NRG Power Marketing 5 9/1/2009 9/1/2025
1566302 NRG Power Marketing 300 1/1/2008 1/1/2013
1585225 (renewal) City of Prescott 22 4/1/2009 4/1/2039
1585239 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2013
1585240 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2013
1598022 (renewal) NRG Power Marketing 103 7/1/2010 7/1/2015
1598291 Entergy Services, Inc. (EMO) 206 6/1/2012 6/1/2042
1598885 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014
1598886 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014
1601111 Constellation 5 1/1/2010 1/1/2015
1602650 NRG Power Marketing 5 7/1/2010 7/1/2020
1615102 (renewal) MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014
1615103 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
15
OASIS PSE MW Begin End
1615105 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014
1615108 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014
1629240 MidAmerican Energy, Inc. 7 3/1/2009 3/1/2014
1630065 NRG Power Marketing 40 1/1/2010 1/1/2015
1632265 Merrill Lynch Commodities 1 4/1/2009 4/1/2014
1632268 Merrill Lynch Commodities 25 4/1/2009 4/1/2014
1633701 NRG Power Marketing 20 1/1/2010 1/1/2019
1633702 NRG Power Marketing 20 1/1/2010 1/1/2016
1633703 NRG Power Marketing 20 1/1/2010 1/1/2016
1639337 Entergy Services, Inc. (EMO) 587 3/1/2009 1/1/2019
1639338 Entergy Services, Inc. (EMO) 103 3/1/2009 1/1/2019
1639339 Entergy Services, Inc. (EMO) 32 3/1/2009 1/1/2019
1639340 Entergy Services, Inc. (EMO) 122 3/1/2009 1/1/2019
1639341 Entergy Services, Inc. (EMO) 134 3/1/2009 1/1/2019
1640629 CLECO Power Marketing 58 5/1/2001 1/1/2021
1640630 CLECO Power Marketing 32 5/1/2001 1/1/2021
1643983 (renewal) NRG Power Marketing 300 1/1/2010 1/1/2015
1643984 (renewal) NRG Power Marketing 100 9/1/2010 9/1/2015
1644155 CLECO Power Marketing 9 4/1/2009 5/1/2016
1644215 NRG Power Marketing 83 1/1/2010 1/1/2025
1644908 CLECO Power Marketing 41 5/1/2009 5/1/2018
1648049 (undesignation) Entergy Services, Inc. (EMO) 1 6/1/2010 6/1/2013
1648050 Entergy Services, Inc. (EMO) 100 6/1/2010 6/1/2013
1648591 (undesignation) Entergy Services (SPO) 1 6/1/2010 6/1/2012
1648592 Entergy Services (SPO) 485 6/1/2010 6/1/2012
1655366 Missouri Joint Municipal 6 10/1/2009 10/1/2014
1658087 (undesignation) Entergy Services (SPO) 1 6/1/2012 6/1/2042
1658088 SMEPA 21 6/1/2012 6/1/2042
1659388 NRG Power Marketing 25 1/1/2011 1/1/2016
1665168 (renewal) Merrill Lynch Commodities 60 11/1/2009 11/1/2014
1665288 Merrill Lynch Commodities 15 1/1/2011 1/1/2017
1665492 (renewal) Merrill Lynch Commodities 16 11/1/2009 11/1/2014
1665493 (renewal) Merrill Lynch Commodities 4 11/1/2009 11/1/2014
1665899 Ameren Energy, Inc. 75 9/1/2009 9/1/2014
1668165 Entergy Services (SPO) 600 1/1/2013 1/1/2043
1669126 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016
1669127 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016
1676674 NRG Power Marketing 100 1/1/2011 1/1/2020
1676675 NRG Power Marketing 100 1/1/2011 1/1/2020
1677749 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015
1679179 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016
1679181 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016
1682716 (renewal) NRG Power Marketing 206 1/1/2011 1/1/2012
1685869 (renewal) Muni Energy Agcy of Miss 19 1/1/2010 1/1/2018
1689499 Missouri Joint Municipal 3 9/1/2009 9/1/2014
1690613 NRG Power Marketing 25 1/1/2011 1/1/2016
1694305 Entergy Services (SPO) 15 5/1/2010 5/1/2020
1694306 Entergy Services (SPO) 30 5/1/2010 5/1/2020
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
16
OASIS PSE MW Begin End
73454527 Hope Water & Light 10 10/1/2009 10/1/2032
73457918 South Miss Electric Power Assoc. 180 10/1/2009 10/1/2014
73573797 (renewal) American Electric Power 45 1/1/2011 1/1/2029
73586299 (renewal) American Electric Power 6 1/1/2011 1/1/2029
73595626 NRG Power Marketing 13 1/1/2012 1/1/2017
73723105 Arkansas Electric Cooperative Corp. 270 1/1/2010 1/1/2015
73724303 Arkansas Electric Cooperative Corp. 104 1/1/2010 1/1/2015
73741113 (renewal) Entergy Services, Inc. (EMO) 150 5/1/2010 5/1/2020
73741122 (renewal) Entergy Services, Inc. (EMO) 135 5/1/2010 5/1/2020
73774729 Arkansas Electric Cooperative Corp. 84 1/1/2010 1/1/2015
73820650 MOWR 5 3/1/2010 3/1/2040
73942862 (renewal) Muni Energy Agcy of Miss 13 6/1/2010 6/1/2015
73970673 Cargill Power Markets, LLC 40 1/1/2012 1/1/2016
73987480 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040
73987507 South Miss Electric Power Assoc. 180 6/1/2010 6/1/2015
73990804 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040
74001787 NRG Power Marketing 100 1/1/2011 1/1/2016
74001895 NRG Power Marketing 100 1/1/2011 1/1/2016
74001897 NRG Power Marketing 22 1/1/2011 1/1/2016
74001904 NRG Power Marketing 28 1/1/2011 1/1/2016
74001930 NRG Power Marketing 42 8/1/2006 8/1/2036
74001931 NRG Power Marketing 60 3/1/2010 3/1/2040
74001934 NRG Power Marketing 60 4/1/2012 4/1/2042
74233619 WRGS 15 4/1/2012 4/1/2017
74233670 (undesignation) Entergy Services, Inc. (EMO) 1 8/1/2012 1/1/2038
74236787 NRG Power Marketing 75 6/1/2012 6/1/2017
74236794 NRG Power Marketing 100 6/1/2012 6/1/2017
74236798 NRG Power Marketing 100 6/1/2012 6/1/2017
74305315 NRG Power Marketing 10 1/1/2014 1/1/2017
74305339 NRG Power Marketing 10 1/1/2013 1/1/2023
74356639 NRG Power Marketing 103 1/1/2011 1/1/2016
74356652 NRG Power Marketing 206 6/1/2012 6/1/2017
74356666 NRG Power Marketing 50 1/1/2013 1/1/2014
74370625 NRG Power Marketing 10 7/1/2010 7/1/2012
74514903 Entergy Services, Inc. (EMO) 20 6/1/2013 6/1/2029
74514911 Entergy Services, Inc. (EMO) 101 6/1/2013 6/1/2029
74691007 NRG Power Marketing 60 1/1/2013 1/1/2018
74728369 Brazos Electric Cooperative 100 1/1/2012 1/1/2017
74728395 Brazos Electric Cooperative 100 1/1/2012 1/1/2017
74728415 Brazos Electric Cooperative 100 1/1/2012 1/1/2017
74728420 Brazos Electric Cooperative 100 1/1/2012 1/1/2017
74758974 Entergy Services, Inc. (EMO) 804 5/1/2013 5/1/2058
74777205 (renewal) NRG Power Marketing 300 1/1/2013 1/1/2033
74777208 (renewal) NRG Power Marketing 300 1/1/2015 1/1/2035
74789476 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2016
74829975 (renewal) CLECO Power LLC (Gen) 35 1/1/2011 1/1/2016
74835023 AECI / APM 103 1/1/2012 1/1/2017
74881866 (renewal) NRG Power Marketing 8 3/1/2011 3/1/2021
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
17
OASIS PSE MW Begin End
74899954 (undesignation) Entergy Services, Inc. (EMO) 1 2/1/2012 2/1/2014
74899956 Entergy Services, Inc. (EMO) 100 2/1/2012 2/1/2014
74899968 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015
74899969 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2015
74901827 (undesignation) Entergy Services, Inc. (EMO) 1 2/1/2011 2/1/2041
74958042 NRG Power Marketing 34 1/1/2006 1/1/2036
74958045 NRG Power Marketing 34 1/1/2006 1/1/2036
74958047 NRG Power Marketing 17 1/1/2006 1/1/2036
74958048 NRG Power Marketing 17 1/1/2006 1/1/2036
75031610 Arkansas Electric Cooperative Corp. 220 1/1/2011 1/1/2016
75031638 Arkansas Electric Cooperative Corp. 72 1/1/2011 1/1/2016
75207302 (renewal) Entergy Services, Inc. (EMO) 1 7/1/2011 7/1/2016
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
18
10. PRE-888 TRANSACTIONS
OASIS PSE MW Begin End
1332606 East Texas Electric Cooperative 55 1/1/2006 1/1/2017
1412155 Entergy Services, Inc. (EMO) 1718 1/1/2007 1/1/2038
1412156 Entergy Services, Inc. (EMO) 741 1/1/2007 1/1/2038
1412158 Entergy Services, Inc. (EMO) 1867 1/1/2007 1/1/2038
1412160 Entergy Services, Inc. (EMO) 1142 1/1/2007 1/1/2038
1412161 Entergy Services, Inc. (EMO) 59 1/1/2007 1/1/2038
1412162 Entergy Services, Inc. (EMO) 148 1/1/2007 1/1/2038
1412163 Entergy Services, Inc. (EMO) 194 1/1/2007 1/1/2038
1412164 Entergy Services, Inc. (EMO) 1157 1/1/2007 1/1/2038
1412165 Entergy Services, Inc. (EMO) 1219 1/1/2007 1/1/2038
1412166 Entergy Services, Inc. (EMO) 683 1/1/2007 1/1/2038
1412167 Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038
1412168 Entergy Services, Inc. (EMO) 456 1/1/2007 1/1/2038
1412169 Entergy Services, Inc. (EMO) 739 1/1/2007 1/1/2038
1412170 Entergy Services, Inc. (EMO) 183 1/1/2007 1/1/2038
1412171 Entergy Services, Inc. (EMO) 64 1/1/2007 1/1/2038
1412172 Entergy Services, Inc. (EMO) 870 1/1/2007 1/1/2038
1412173 Entergy Services, Inc. (EMO) 129 1/1/2007 1/1/2038
1412174 Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038
1412175 Entergy Services, Inc. (EMO) 130 1/1/2007 1/1/2038
1412176 Entergy Services, Inc. (EMO) 65 1/1/2007 1/1/2038
1412177 Entergy Services, Inc. (EMO) 947 1/1/2007 1/1/2038
1412178 Entergy Services, Inc. (EMO) 61 1/1/2007 1/1/2038
1412179 Entergy Services, Inc. (EMO) 304 1/1/2007 1/1/2038
1412180 Entergy Services, Inc. (EMO) 351 1/1/2007 1/1/2038
1412181 Entergy Services, Inc. (EMO) 692 1/1/2007 1/1/2038
1412182 Entergy Services, Inc. (EMO) 1641 1/1/2007 1/1/2038
1412183 Entergy Services, Inc. (EMO) 433 1/1/2007 1/1/2038
1412184 Entergy Services, Inc. (EMO) 1926 1/1/2007 1/1/2038
1412185 Entergy Services, Inc. (EMO) 946 1/1/2007 1/1/2038
1412186 Entergy Services, Inc. (EMO) 1233 1/1/2007 1/1/2038
1498278 Entergy Services, Inc. (EMO) 75 8/1/2007 1/1/2017
1498281 Entergy Services, Inc. (EMO) 86 8/1/2007 1/1/2017
1498283 Entergy Services, Inc. (EMO) 68 8/1/2007 1/1/2017
1498284 Entergy Services, Inc. (EMO) 78 8/1/2007 1/1/2017
1498285 Entergy Services, Inc. (EMO) 11 8/1/2007 1/1/2044
1498286 Entergy Services, Inc. (EMO) 69 8/1/2007 1/1/2044
1498287 Entergy Services, Inc. (EMO) 14 8/1/2007 1/1/2044
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
19
11. STUDY QUEUE
OASIS PSE MW Begin End
74597193 NRG Power Marketing 300 1/1/2013 1/1/2018
74597198 NRG Power Marketing 300 1/1/2013 1/1/2018
74728400 Brazos Electric Cooperative 100 1/1/2012 1/1/2017
74799834 Cargill Power Markets 101 7/1/2012 7/1/2017
74799836 Cargill Power Markets 101 7/1/2012 7/1/2017
74799837 Cargill Power Markets 101 7/1/2012 7/1/2017
74799848 Cargill Power Markets 101 7/1/2013 7/1/2018
74799851 Cargill Power Markets 101 7/1/2013 7/1/2018
74799853 Cargill Power Markets 101 7/1/2013 7/1/2018
74846159 AEPM 65 1/1/2015 1/1/2020
74899933 Entergy Services (SPO) 322 2/1/2011 2/1/2041
74899972 (undesignation) Entergy Services (SPO) 1 1/1/2015 1/1/2045
74899974 (undesignation) Entergy Services (SPO) 1 1/1/2015 1/1/2045
74899976 (undesignation) Entergy Services (SPO) 1 1/1/2015 1/1/2045
74899980 Entergy Services (SPO) 584 1/1/2015 1/1/2045
74899988 (undesignation) Entergy Services (SPO) 1 6/1/2012 6/1/2042
74899989 Entergy Services (SPO) 485 6/1/2012 6/1/2042
74899996 Entergy Services (SPO) 450 6/1/2012 6/1/2042
74900000 Entergy Services (SPO) 620 6/1/2012 6/1/2042
74900014 Entergy Services (SPO) 35 6/1/2012 6/1/2042
74900016 Entergy Services (SPO) 20 6/1/2012 6/1/2042
75009400 (undesignation) Entergy Services (SPO) 1 1/1/2012 1/1/2042
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
20
12. ATTACHMENTS
12.1 Table of Acronyms
A Amperes
AC/DC Alternating Current / Direct Current
ACSR Aluminum Conductor Steel Reinforced
ACSS Aluminum Conductor Steel Supported
AFUDC Allowance for Funds Used During Construction
ATC Available Transfer Capability
CCN Certificate of Convenience and Necessity
CCVT Coupling Capacitor Voltage Transformer
EES Entergy Control Area
EHV Extra-High Voltage
FP Funded Project
ICT Independent Coordinator of Transmission
ISD In-Service Date
kV Kilo-Volt
LF Linear Feet
MCM (M) Thousand Circular Mils
MUST Managing and Utilizing System Transmission
MVA Mega-Volt Ampere
MVAR Mega Volt Ampere Reactive
MW Mega-Watt
NEMA National Electrical Manufacturers Association
NPDES National Pollution Discharge Elimination System
OASIS Online Access and Same-time Information System
OATT Open Access Transmission Tariff
OG&E Oklahoma Gas & Electric
PEP Project Execution Plan
PM&C Project Management & Construction
P&P Plan & Profile (drawing)
POR Point of Receipt
PSS/E Power System Simulation Program
PTI Power Technologies Incorporated
ROW Right of Way
RTU Remote Terminal Unit
SEL Schweitzer Engineering Labs
SES Steam Electric Station
SMEPA South Mississippi Electric Power Association
SOC System Operations Center
SHV Super High Voltage
SW Switch Station
SWEPCO Southwest Electric Power Company
SWPPP Storm Water Pollution Prevention Plan
TOC Transmission Operations Center
TSR Transmission Service Request
TVA Tennessee Valley Authority
USACE United States of America Corps of Engineers
VDC Voltage Direct Current
WOs Work Orders
OASIS 75009407 Entergy Services, Inc. (SPO) Facilities Study
21
12.2 Drawings
Description Drawing Number Page
Ebony Switch Station A4317SO1 22
Moses SES Substation A2206SO1 23
Ebony Substation One Line Substation Upgrades 24
Moses Substation One Line Substation Upgrades 25
12.3 Duration Schedule
Description Page
Preliminary Schedule 26
12 MVAR BXXXX
BXXXX150
Base PlanAdd 24 MVARCapacitor Bank
G
SupplementalAdditional 12
MVARCapacitor Bank
12 MVARBXXXX
BXXXX150
G
Add 12 MVARCapacitor Bank
G
Ebony Switch Station Locatiton
Add 24 & 12 MVAR Capacitor Bank
Moses SESLocation
Add 12 MVAR CapacitorBank
OASIS 75009407EJO F4PPAR0490
OASIS # 75009407 EJO F4PPAR0490 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
JET Meeting - Facility Study Review
PM with Project Team Input Develops OASIS Study documents
Entergy receives customer approval
Entergy completes PEP/Estimates
Approval from customer to proceed with the project followed by creation of FP and WOs
Commence engineering, and permitting work
Issue design packages to construction
Construction work in Ebony 161kV Switching Station and Moses 161kV Substation
It is assumed the outages are available as per Construction plans
Projected In-Service Date
2011 2012
Target ISD 12-31-2012