39
16 May 2017 WESTERN ROAD UPGRADES PROGRAM Netflow Industry Networking Event
Transcript
Page 1: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

16 May 2017

WESTERN ROAD UPGRADES PROGRAM

Netflow Industry Networking Event

Page 2: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

AGENDA

Welcome, Event Agenda & Speaker Introduction Andrew Bradley - ICN

Project Overview, Consortium Overview and Packages Graeme Symonds - Netflow

Damien Augustinus – Netflow

Chris Harper - Netflow

EOI Registration Process Andrew Bradley - ICN

Panel Q & A Damien Augustinus

Graeme Symonds

Chris Harper

Jacqui Berry

Cate Marr

Informal Networking

Page 3: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

OUR FOCUS IS TO ASSEMBLE A

TEAM OF SUBCONTRACTORS

AND SUPPLIERS THAT

UNDERSTANDS DELIVERY IN

THE LOCAL CONTEXT AND

FOSTERS STRONG LOCAL

RELATIONSHIPS.

INTRODUCTION

3

Page 4: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT OVERVIEW

Page 5: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT OVERVIEW

5

The Victorian Government is proposing a large-scale, strategically focussed Western Road Upgrades program to transform Melbourne’s outer suburban arterial road network and address the infrastructure gap generated by rapid land use change. The program is sometimes known as the Western Road Upgrades Program or The Project.

Western Road Upgrades Program scope will include:

- Development Phase Works:

• Arterial road upgrades: design, financing and construction of eight arterial road upgrades in Melbourne’s western suburbs.

• Initial rehabilitation works: delivery and financing of rehabilitation works within a maintenance area encompassing approximately 800 lane km of arterial roads (the Project Maintenance Area).

- Maintenance: delivery of maintenance (routine and periodic) and rehabilitation of arterial roads, structures and road side assets in the Project Maintenance Area, including incident response, with maintenance obligations commencing during the Development Phase. Duration of the Maintenance Phase is 20 years following completion of the Development Phase.

Page 6: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT OVERVIEW - OBJECTIVES

6

meet the growing vehicle travel demand by reducing congestion on arterial roads in Melbourne’s fast growing western

outer suburbs;

improve the reliability and performance of arterial roads and reduce vehicle operating costs through enhanced

maintenance outcomes;

promote investment and employment creation by improving the access to key economic centres and employment

clusters;

contribute to the creation of a safe and accessible road network that supports the health and wellbeing of all users and the

liveability of communities; and

seek a value for money solution for road users through innovative design, optimum risk allocation between the Project

parties and a whole of life approach to the design and maintenance of the arterial road network in scope.

Page 7: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT OVERVIEW – ARTERIAL ROAD UPGRADES

7

The winning bidder will be responsible for the design and construction of the upgrades on eight arterial roads:

1. Dunnings Rd & Palmers Rd to Overton Rd

2. Palmers Rd from Overton Rd to Western Freeway

3. Derrimut Rd from Sayers Rd to Dohertys Rd

4. Leakes Rd from Fitzgerald Rd to Derrimut Rd

5. Dohertys Rd from Fitzgerald Rd to Grieve Parade

6. Dohertys Rd from Foundation Rd to Palmers Rd

7. Forsyth Rd from Old Geelong Rd to Princes Freeway

8. Duncans Rd Interchange

The winning bidder will be responsible for the duplication of these roads and upgrade of existing pavements and structures.

Key element of the works will involve staging of all works to reduce disruption.

Page 8: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT OVERVIEW – INITIAL REHAB WORKS

8

Initial rehabilitation works on pavements and structures is required to meet the Project requirements. This is expected to include major resurfacing, regulation and/or rehabilitation of the pavements.

The diagram indicates the Western Road Upgrades network and the current pavement condition of roads within the Project Maintenance Area. Different levels of rehabilitation will be required to bring the entire network up to a consistent level of service.

Rehabilitation/strengthening works on nominated, or otherwise identified, structures is also to be completed during the Initial Maintenance Phase.

- For example, bridges and pedestrian overpasses at Dynon Road, Geelong Road, Princes Highway and Lewis Street that are expected to require rehabilitation works.

- It is expected that this work will include bearing replacement and replacement of expansion joints.

Rehabilitation Work to be undertaken concurrently with the arterial road network upgrade works.

Page 9: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT OVERVIEW – MAINTENANCE

9

The maintenance services for the pavements, structures, drainage and roadside assets within the Project Maintenance Area (approx. 800 lane km of arterial roads) include:

- routine maintenance (including inspections, incident response and reinstatement);

- periodic maintenance;

- rehabilitation; and

- the development and maintenance of asset management systems.

VicRoads will continue to be the Operator of the network and interface with customers through the existing Traffic Management Centre.

Page 10: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROJECT SCOPE AND PROCUREMENT

10

The Western Road Upgrades Program is being procured as an availability based PPP with the Victorian Government with a term of 20 years commencing from the completion of the Development Phase.

This RFP is in relation to the “Western Package”

- First road upgrade package that the Government has committed to funding and delivering under a PPP model. As such it is tendered on a stand-alone basis.

- Scope, procurement approach and timing of other road packages will be advised by the Government.

- Likely two other similar road packages to be procured consecutively (TBC).

The scope of the Project specifically excludes:

- Delivery of maintenance and rehabilitation of traffic signals, street lighting, and intelligent transport systems in the Project Maintenance Area.

- Operational responsibility and control of the Project Maintenance Area (which will remain with VicRoads).

Page 11: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

:

PROJECT TIMELINE

11

Page 12: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PROCUREMENT AND DELIVERY TIMELINE

12

EOI Released

8 November 2016

EOI

Submitted

9 December

2016

RFP

Released

March

2017

20-week

RFP

process

2 August

2017 Bid

Date

Contract

Close &

Financial

Close

Dec 2017

Development Phase

Start = Jan 2018

Duration is bid

variable

Initial Maintenance

Phase

(Duration is bid

variable)

Full Maintenance

Phase (20 years)

Page 13: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Consortium Overview

Page 14: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

CONSORTIUM MEMBERS

14

SERVICES CONTRACTOR

CONSORTIUM SPONSORS

FINANCIAL ADVISER

DESIGN & CONSTRUCTION

Page 15: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

NETFLOW

15

Netflow is a Joint Venture between Cintra and Plenary with a focus on tolled road concession projects in Australia and New Zealand

Netflow brings together two of the largest developers and managers of infrastructure globally:

- Cintra offers unparalleled international experience as a large investor and operator of toll roads and as a technology innovator

- Plenary is a leading developer, operator and manager of civil and social infrastructure assets in Australia and North America

Netflow harnesses Cintra and Plenary’s extensive in-house capabilities in design, construction, traffic and revenue analysis, project management, finance, road operations and maintenance, customer service and tolling technology.

Able to leverage collective organisational capabilities and subsidiaries:

- Ferrovial Agroman

- Broadspectrum

- Amey

- Plenary Asset Management

A range of future opportunities have been identified by Netflow, including these Victorian road packages.

Page 16: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

CINTRA

16

Type of Asset Toll road

Total Investment $4.7 billion

Equity % 43%

Concession Term 1999 – 2098

Project Description:

Toronto’s 407 ETR is the world’s first

fully electronic, barrier-free toll

highway.

The 108-kilometre highway stretches

from Burlington (SW of Toronto), to

Pickering (NE). Operations and

maintenance is performed in-house by

Cintra, including the toll collection

system that handles tolls from more

than one million user transponders.

407 ETR Ontario (Canada)

NTE Texas (USA)

LBJ Express Texas (USA)

I-66 Virginia (USA)

Type of Asset Toll road

Total Investment $2.7 billion

Equity % 57%

Concession Term 2009 – 2061

Project Description:

The NTE is a 21km highway dedicated

to improving mobility along a series of

highways vital to the region.

The NTE managed lanes is one of the

most innovative and complex road

buildings project in USA, which provide

services to one of the most congested

corridor in the country. NTE offers

faster, safer and more reliable travel.

Type of Asset Toll road

Total Investment $3.2 billion

Equity % 51%

Concession Term 2010 - 2061

Project Description:

The 27km LBJ Express managed lanes

project features some of the most

innovative congestion-management

solutions in the US. A tollway within a

freeway, users are provided the choice of

driving in non-tolled lanes or paying a toll

to bypass those lanes.

Combined with fully-electronic tolls and

dynamic pricing based on traffic, the toll

lanes allow for the movement of traffic at

more consistent and reliable speeds.

Type of Asset Toll road

Total Investment $4.0 billion

Equity % N/A

Concession Term 2016-2066

Project Description:

Cintra-led consortium was recently

named preferred bidder to deliver the I-

66 tollroad project.

The I-66 is one of the main arterial of

the region. The upgrade will include

three regular lanes in each direction,

two managed lanes in each direction ,

new and expanded transit services and

park-and-ride lots; and interchange

improvements to enhance safety and

reduce congestion,

Page 17: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PLENARY

17

Type of Asset Road

Total Investment $1.6 billion

Equity % 40%

Concession Term 2015 – 2043

Project Description:

The TSRC is a 41km bypass which runs

to the North of Toowoomba from

Warrego Highway to the Gore Highway

via Charlton.

The project will assist in reducing travel

time across the Toowoomba range by

up to 40 minutes.

Construction commenced in late 2015

with an estimated construction period of

three years.

Plenary and Cintra are equity investors.

Toowoomba SRC Queensland (Australia)

SH183 Managed Lanes

Texas (USA)

US36 Express Lanes Colorado (USA)

Sydney Metro NW New South Wales

(Australia)

Type of Asset Toll road

Total Investment $1.1 billion

Equity % N/A

Concession Term 2014 – 2039

Project Description:

The SH 183 Managed Lanes Project

involves the design, construction, short-

term financing, O&M of a 14 mile

portion of State Highway 183 through

the cities of Euless, Irving and Dallas in

Texas.

The SH 183 highway serves as a

primary arterial road between Dallas

and Fort Worth.

Type of Asset Rail

Total Investment $3.7 billion

Equity % 10%

Concession Term 2014-2029

Project Description:

A 36km rail link serving Sydney’s fast

growing north-west corridor. The

Sydney Metro Northwest will deliver

faster travel times to Sydney’s CBD at

least every four minutes during peak

periods.

The project includes eight new railway

stations, five existing railway stations

converted to rapid transit standard and

4,000 new commuter car parking

spaces.

Type of Asset Toll road

Total Investment $270 million

Equity % 100%

Concession Term 2014 – 2064

Project Description:

The dynamic tolled managed lanes

project promotes multimodal

transportation strategies that increase

travel choices and efficiency for all

modes - including general and

managed lanes, bus rapid transit,

bicycling and walking, while reducing

emissions and resource use. Now

completed, residents have more

options for cleaner, safer and less

congested travel.

Page 18: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

WBHO

18

Warrego Highway

Upgrade QLD

Princes Highway

Duplication Winchelsea, VIC

Tourle St &

Cormorant Road Newcastle, NSW

Durban Bus Rapid

Transit Durban, South Africa

Client Dep. of Transport

& Main Roads

Completion Date 2013

Value $118m

Reconstruction and widening of 90km of

flood damaged Warrego Highway in

variable subgrade conditions.

Works were completed in urban and

regional environments, and involved

highway traffic management, with over

20% of all traffic heavy freight vehicles.

Focus on local industry involvement and

community engagement: Over $25m

was spent on local services and

businesses.

Client VicRoads

Completion Date 2018

Value $60m

11.5km upgrade of Princes Highway, a

key regional route providing access for

freight to Victoria’s ports and airports.

Involves duplication between

Winchelsea and Armytage Road.

Delivery adjacent to live traffic (8,000+

vehicles daily), significant earthworks,

environmental management and

stakeholder engagement.

Targeting a practical completion date

over six months earlier than the contract

PC date.

Client Roads & Maritime

Services

Completion Date 2017

Value $50m

Duplication, described by Regional

Development Authority as project of

‘national significance’ and ranked as the

number one infrastructure priority for the

region in its 2014 Hunter Economic

Infrastructure Plan.

Involves duplicating 3.8km of Tourle

Street and Cormorant Road between

Industrial Drive at Mayfield West and

Egret Street at Kooragang, including

new bridge.

Client eThekwini

Transport

Completion Date 2017

Value $420m

Integrated rail and bus routes and a Bus

Rapid Transit System (BRT) comprising

dedicated lanes and interchange

facilities:

• 4km road route, involving upgrades,

new roads & structures

• New 4.3km route through CBD, with

traffic management, staging and

stakeholder engagement

• Brownfield construction of 2.5km of

BRT in Durban’s CBD

Page 19: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

BROADSPECTRUM / AMEY

19

Stewardship Maintenance Contract Sydney South Zone, NSW

Sheffield Streets Ahead PFI Sheffield, UK

Client Roads & Maritime Services

Contract Term 7 years 2014 – 2021 + 3 yr optional ext.

Value $700m – $1b

Manages and maintains over 670 carriageway kilometres of roads along with a wide

range of corridor assets including major slopes, noise walls, culverts, drainage and

verges. We also manage and maintain 201 bridges and 10 tunnels including major

structures such as the Anzac Bridge and the Mascot Tunnel under Sydney Airport.

Full asset management services from inspection and reactive/routine maintenance to

the identification, design and delivery of forward programs of work that includes

rehabilitation, renewal and improvement works of both roads and Bridges. We deliver

over 75 Projects per annum (Design and Construction) in Roads and Bridges ranging

from $500k to $50m per project.

Client Sheffield City Council

Contract Term 25 years 2012 – 2037

Value $4b

The Sheffield Streets Ahead Project is designed to upgrade and maintain the entire

infrastructure including the city’s roads, pavements, street lighting, bridges and street

scene over a 25 year contract period.

The contract involves an initial five year core investment period (CIP), this includes

treatment of over 1890km of carriageways and 3290km footways , Street lighting LED

upgrades, strengthening and refurbishment of over 40 structures, drainage

improvement, replacement of traffic signal equipment and tree management .

Following the CIP, the assets will be maintained at these improved, prescribed levels,

achieved throughout lifecycle investment over the remaining contract period

Page 20: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

PACKAGES

Page 21: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

WORKS PACKAGES

21

For the Western Road Upgrades Project scope of works, our focus is to assemble a team of subcontractors and suppliers that is well-resourced, understands delivery in the local context, brings strong local relationships, and addresses the State Government aims of local industry involvement and development.

Page 22: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

INITIAL CAPITAL WORKS PACKAGES

22

• Asphalt and Bitumen Seal, Supply and Placement

• PVC Pipe, Conduits and Fittings Supply

• Electrical and Telecommunication Pits Supply

• Traffic Signals Supply and Installation

• Quarry and Fill Material Supply

• Precast Stormwater Drainage RCP, RCBC and Pits Supply

• Kerb and Channel Subcontractor

• Ready Mix Concrete Supply

• Reinforcing Supply

• Precast Concrete Bridge Girders Supply

• Guard Fence Supply and Installation

• Bridge Rail, Parapet Rail and Anti-Throw Screens Supply and Installation

• Elastomeric Bearings and Expansion Joints Supply

• Precast Concrete Bridge Parapet Supply

• Piling Subcontractor (Supply and Construction)

• Bridge Girder Erection Subcontractor (Cranage)

• Concrete Pavement Subcontractor (Footpath, Traffic Islands, Medians etc.)

• Anti-Graffiti Coating Supply and Application

• FRP Subcontractor (Formwork, Reinforcing and Concrete Pouring)

• Structural Steelwork (Steel Bridge and Gantry Fabrication)

• Water and Sewer Main Relocations Subcontractor

• Stormwater Drainage Installation

Subcontractor

• Reinforced Earth Retaining Walls (Design and Construct Package)

• Road Signs Supply and Install

• Landscaping Subcontractor

• Road Line marking Subcontractor

• Road Lighting Subcontractor (Supply and Installation)

• Plant Hire

• Traffic Management Crews

• Traffic Management Equipment/Barrier Hire

• Rail Safety Officers

• Road Safety Audits and Traffic Management Design

Page 23: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

INITIAL CAPITAL WORKS PACKAGES (CONT.)

23

• Vacuum Trucks/Sweepers Hire

• Site Office/Shed Hire

• Telecommunication Relocations Subcontractor

• Fencing Subcontractor (Supply and Install)

• Property Inspection and Dilapidation Report

• Labour Hire

• Precast Concrete Panels

• Geotextile and Subsoil Drainage Material Supply

• Pipe Jacking and Drilling Subcontract

• Tree Removal Subcontractor

• Road Furniture Supply

• Bus Stop Shelter Supply and Install

• Temporary Fencing Hire

• Surveying Services Subcontractor

• Concrete/Pavement Saw-cutting Subcontractor

• Asphalt/Pavement Profiling Subcontractor

• Contaminated Material and Construction Waste Disposal Subcontractor

• Steel Fixing Subcontractor

• Rigging and Assembling Structural Steel Bridge Members Subcontractor

• Geotechnical Services and Onsite Soil Testing

• Security Subcontractor

• Enviro/Heritage Consultant

• Retaining Walls Subcontractors

• Fuel Supply

• Service Locating and NDD Subcontractor

• Coloured Bus Lanes Subcontractor

• Demolition Subcontractor

• Subsoil Drainage Installation Subcontractor

• Plexiglass Supply

• ITS (Intelligent Traffic System) and CCTV Subcontractor

Page 24: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

REHABILITATION AND MAINTENANCE PACKAGES

24

• General Chemicals Supply

• Landscaping Subcontractor

• Uniforms Supply

• Traffic Management

• Arborists Consultant and Subcontractor

• Road Sign Supply

• Road Line marking Subcontractor

Page 25: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

EOI REGISTRATION Andrew Bradley

Manager – Strategic Projects & Supply Chains ICN

Page 26: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Page

26

ICN PARTNERSHIP

Netflow are partnering with ICN

to promote project opportunities and maximise

reach to local suppliers.

Page 27: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Page

27

ICN – WHO ARE WE

Business network offering local sourcing procurement services

Page 28: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Page

28

VICTORIAN INDUSTRY PARTICIPATION POLICY (VIPP)

The policy ensures that local SMEs are given full

and fair opportunity to compete for government

contracts while still achieving value for money.

Page 29: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Page

29

VIPP STRATEGIC PROJECTS • Projects valued >$50 M

• Shortlisted bidders required to complete a

Local Industry Development Plan

• Victorian Government sets minimum local

content targets on all Strategic Projects

• Obligation for awarded contractors to meet

local content target

• Bidders are encouraged to seek goods and

services from local SMEs

• Awarded contractors will be required to

monitor and report local content from their

supply chains.

Page 30: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Page

30

ICN GATEWAY HOME PAGE

Page 31: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Page

31

ICN GATEWAY – HOW TO REGISTER INTEREST

Page 32: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

ICN GATEWAY – HOW TO REGISTER INTEREST

32

Page 33: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

ICN GATEWAY – HOW TO REGISTER INTEREST

33

Page 34: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

ICN GATEWAY – HOW TO REGISTER INTEREST

34

Page 35: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

ICN GATEWAY – HOW TO REGISTER INTEREST

35

Page 36: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

ICN GATEWAY – HOW TO REGISTER INTEREST

36

Page 37: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

ICN GATEWAY – HOW TO REGISTER INTEREST

37

Page 38: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

Plenary Damien Augustinus Bid Director

WBHO Cate Marr Estimating Manager

Chris Harper D&C Bid Director Jacqui Berry Community & Stakeholder Manager

AMEY / BROADSPECTRUM Graeme Symonds Bid Director

Page

38

PANEL Q & A

Page 39: WESTERN ROAD UPGRADES PROGRAM WBHO Presentation.pdf · PROJECT OVERVIEW 5 The Victorian Government is proposing a large-scale, ... - Ferrovial Agroman - Broadspectrum - Amey ... Concession

CONTACT

ICN Gateway link

www.netflow.icn.org.au

[email protected]


Recommended