Date post: | 18-Dec-2015 |
Category: |
Documents |
Upload: | sydney-mccarthy |
View: | 212 times |
Download: | 0 times |
Wetlands and Waterways Permits
Patti Caswell
Statewide Wetlands/Permits Program Coordinator Geo-Environmental, ODOT
Overview
1. The main actors: DSL and the Corps2. A recommended decision sequence
to navigate the permit process3. Avoiding permit process potholes4. Tools and references
State Removal-Fill Law
Waters of the state• Essential salmon habitat• Non-essential salmon habitat
Permit types• General Authorizations• General Permits (new) • Removal-Fill Permits
DSL Factoids • Admin. rule timeframes to issue• 50 cy permit threshold in non-essential habitat
DSL
Section 404 Clean Water Act
Section 10 Rivers and Harbors Act
Waters of the U.S.• 404 waters• Section 10 waters• Navigable waters
Permit types• Nationwide• Regional General• Individual
Corps Factoids• No hard timeframes to issue permits• No permit volume thresholds• ESA compliance critical• Tribal consultation critical
Corps of Engineers
Basic permit questions
• Do I need a permit for this project?• If so, what are the requirements to
obtain it?• How long will it take to get?
1. Is the project area jurisdictional?2. If yes, does an exemption apply?3. If a permit is required, do we qualify
for a “streamlined” permit?4. Is mitigation required?
A recommended decision sequence
1a. Jurisdiction (cartoon version)
Removal-Fill LawRemoval-Fill LawSection 404
Tidal Waters Fresh WatersRemoval-Fill Law &
Section 404
Section 10
Uplands
TidelandsCoastalWetlands Streams, ponds,
lakes, some ditches
FreshwaterWetlands
Section 10 if navigable
Uplands
OHWLMean High
Water
1b. Jurisdiction example
Coast Fork Bridge, I-5Willamette River, Lane Co.
High flow channel above OHW(not regulated)Upland
(not regulated)
OHWL
Wetlands
N
Willamette R.
1c. Challenging jurisdictional features
Roadside ditch
Natural stream channel
Culvert
Roadside ditch
Drainageditch “Dry” Wetlands
2. Do exemptions apply?
• Culvert replacements– cleaning sediment from barrel– installing larger diameter barrel within
the road prism– Not for:
• temporary road access fills• stream realignment• sand bag dams for temporary water
management?
2. Do exemptions apply?
• Repair/maintenance of transportation structures– repair of road scour that had riprap– scour around structures that had riprap– Not for:
• relocating structures• scour that was unprotected
3a. Do we fit a “streamlined” permit?
• DSL– General authorizations ~ mini individual
permits– General Permits (new and untried)
• Corps– Nationwide Permits– Regional General Permits
3b. Permit application timing
Permit target date
- 1- 2- 3- 4- 6 - 5- 8 - 7
JPA submittal time before target date(months)
DSL/Corps Individual Permit
GA & NWP
~ -3 wksFinal JPA Items In
NMFS BiOp
DEQ 401 Cert
DEQ SWMP SHPO OKTribal OK
1. Avoid impacts2. Minimize unavoidable impacts3. Rectify temporary impacts4. Compensate for permanent
unavoidable impactsa. Mitigation banks – first priorityb. Fee in lieu – second priorityc. Physical mitigation site – last option
unless a low cost, low risk option is available
4. Mitigation
Typical potholes
• Timing of wetland delineation/jurisdictional determinations
• Incomplete applications• Negative public comments during
app review• Final completeness items missing
before permit issuance• Surprise permit conditions
Preventing violations
Wetland
Contract special provisions
• No equipment
• No driving
• No disturbance
• Prevent sediment discharge into NWZ
No work zone
Construction Fencing
For detailed info—
• ODOT Geo-Environmental E-guide– http://www.oregon.gov/ODOT/HWY/GEOE
NVIRONMENTAL/e_guide.shtml
• ODOT Geo-Environmental Wetlands and Permits Manual– http://www.oregon.gov/ODOT/HWY/WETM
ANUAL/