William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility item by visual observation only; they do not test the operation of equipment or perform destructive testing of walls, ceilings or floors. Each facility item is ranked on a 7-point scale: rank 7 means the item is in new or in good condition and no work is required while rank 1 means the item has failed and has lead to an immediate life safety condition¹. The remaining ranks choices generally mean that the item requires regular maintenance (rank 5 or 6) or full replacement (rank 2, 3 or 4). For additional detail and definition on rank values as they relate to each assessed item, please visit the "CPS Guide to Biennial Facility Assessments" found on the Facilities Standards webpage under CPS Policies and Guidelines at http://www.cps.edu/About_CPS/Policies_and_guidelines/Pages/facilitystandards.aspx. Definitions for Quantity, Unit, Cost and Campus Total can be found at the end of this report.
Facility Assessment Report
Building Name Year Constructed Building Area (Sq Ft) Assessed Need Number of Floors
Campus Summary
Main 1912 38,000 $2,812,2903
Addition 1968 35,326 $1,820,4333
SITE $366,311
Campus Total $4,999,03573,326
Building: Main
Category: Building Exterior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Entrance
Entrance Control - Audio and Video Door 3.1 - Southwest Broken lens cover5EA1 $1,567
Exterior Doors - Exterior Steel Door Door 3 - Southeast 6EA2 $961
Exterior Doors - Exterior Steel Door Door 3.1 - Southwest 6EA2 $961
Exterior Doors - Exterior Steel Door Door 3.2 - West center 6EA2 $961
Exterior Doors - Exterior Steel Door Door 3.3 - West center 7EA1 $0
Exterior Stairs - Concrete Door 3 - Southeast 6LF10 $818
Foundation
Foundation - Concrete Entire Building 7LF526 $0
Superstructure - Steel with Clay Tile Arch Entire Building 7SF38,000 $0
Lighting
Exterior Lighting - Wall Mounted Entire Building 6EA4 $1,155
Roof System
Chimney - Brick Chimney- Stainless Steel Liner Roof 3 6LF70 $66,828
Coping - Clay Tile Roof 2 6LF55 $1,766
Coping - Metal Roof 1 5LF305 $12,893
Coping - Metal Roof 1 7LF51 $0
Coping - Metal Roof 2 7LF50 $0
Coping - Stone Roof 2 6LF130 $4,175
Page 1 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Building Exterior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Roof System
Coping - Stone Roof 3 6LF140 $4,496
Downspouts - Interior Downspouts Roof 1 7LF200 $0
Downspouts - Interior Downspouts Roof 2 7LF120 $0
Downspouts - Interior Downspouts Roof 3 7LF40 $0
Parapet - 16" - 30" Height Roof 1 6LF255 $10,188
Parapet - 16" - 30" Height Roof 2 6LF235 $9,389
Parapet - Parapet > 30" Roof 1 6LF50 $3,196
Parapet - Parapet > 30" Roof 3 6LF140 $8,949
Roof Structure - Steel / Metal Deck/ Concrete Topping Roof 1 7SF286 $0
Roof Structure - Steel with Clay Tile Arch Roof 1 7SF9,778 $0
Roof Structure - Steel with Clay Tile Arch Roof 2 7SF4,625 $0
Roof Structure - Steel with Clay Tile Arch Roof 3 7SF1,670 $0
Roof - Modified Bitumen Roof 1 7SF10,064 $0
Roof - Modified Bitumen Roof 2 7SF4,625 $0
Roof - Modified Bitumen Roof 3 7SF1,670 $0
Walls
Cornice - Metal Projecting Entire Building Heavily rusted4LF832 $719,686
Exterior Walls - Brick Entire Building 6SF19,811 $133,150
Exterior Walls - Prefabricated Metal Panel Wall Entire Building 5SF1,107 $7,187
Exterior Walls - Stone-Cast Entire Building 6SF2,148 $14,437
Windows
Guard - Guards perforated Entire Building Dented, damaged4SF300 $25,465
Guard - Guards perforated Entire Building 6SF894 $11,416
Guard - Guards wire guard Entire Building 5SF143 $2,192
Lintels - Steel Entire Building 7LF476 $0
Windows - Sash Aluminum Double-pane Entire Building Bad balances throughout4SF3,075 $403,624
Building Exterior Subtotal: $1,445,461
Building: Main
Category: Electrical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Emergency System
Automatic Transfer Switch Electrical Room also serves addition6EA1 $408
Emergency A/C Power - Corridors and Stairs Entire Building 6SF8,512 $2,556
Emergency A/C Power - Gym Entire Building / 1st Floor 6SF3,520 $1,309
Page 2 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Electrical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Emergency System
Emergency A/C Power - Students Toilets Entire Building 6SF1,280 $476
Emergency Generator- Outdoor- Diesel - Below 60 KW Site West Serves main and addition. 6EA1 $6,396
Exit Signs - Corridors and Stairs Entire Building 6EA12 $1,797
Exit Signs - Multipurpose Room Entire Building / 1st Floor 6EA4 $599
Security System - CCTV Entire Building 6SF38,000 $11,411
Security System - Intrusion Detection Entire Building 6SF38,000 $9,781
Main Service
Main Electrical Service - 2000 A 120/208/3PH Electrical Room Serves main and the addition. 6EA1 $8,232
PA System Entire Building Serves the main and addition. Control console
located in the addition.
6SF38,000 $12,498
Power Distribution
Lighting and Power Panels - 100 A Entire Building / Electrical Room 6EA1 $299
Lighting and Power Panels - 100 A Entire Building 6EA2 $598
Lighting and Power Panels - Above 100 A Entire Building / 1st Floor 6EA3 $1,491
Lighting and Power Panels - Above 100 A Entire Building 6EA3 $1,491
Main Distribution Panels - 400 - 600 amp Entire Building 6EA6 $3,166
Electrical System Subtotal: $62,509
Building: Main
Category: Safty System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Fire Alarm
Fire Alarm Panel Entire Building / Boiler Room Serves main and addition. No model number available.
6EA1 $6,406
Fire Alarm Strobe Lights Entire Building 6SF38,000 $13,585
Fire Alarm_System Entire Building 6SF38,000 $18,476
Safty System Subtotal: $38,466
Building: Main
Category: Mechanical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Air Conditioning
Condensing Unit- Roof Mounted - Less than 5 tons Roof Classroom split system.6EA1 $3,334
Condensing Unit- Roof Mounted - Less than 5 tons Roof Classroom split systems. 6EA13 $43,338
Page 3 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Mechanical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Air Conditioning
Air Handling Systems
Air Handling Unit- Built Up- Single Zone- Steam Coils - 8001 - 15000 cfm
Mechanical Room Serves the multipurpose room.5EA1 $34,007
Air Handling Unit- Built Up-Multi Zone- Steam Coils - 15001 - 25000 Mechanical Room Serves the classrooms. 5EA1 $66,438
Air Intake Mechanical Room / Roof 6EA1 $5,765
Air Intake Mechanical Room / Roof 6EA1 $5,765
Auxiliaries - 15001 - 25000 cfm Mechanical Room 5EA1 $14,899
Auxiliaries - 8001 - 15000 cfm Mechanical Room 6EA1 $4,341
Return Duct Work - Indoor- Vertical Shaft and Ducts Mechanical Room / 1st Floor 7LF50 $0
Return Duct Work - Indoor- Vertical Shaft and Ducts Mechanical Room / Entire Building 7LF300 $0
Zone Dampers Mechanical Room / 3rd Floor DDC controls not functioning properly due to software issues so controlled manually.
6EA6 $4,998
Zone Dampers Mechanical Room DDC controls not functioning properly due to software issues so controlled manually.
6EA17 $14,162
Boiler Systems
Boiler Auxiliary- Scotch Marine- Steam Low Pressure Boiler - 101 - 150
HP
Boiler Room 6EA2 $5,091
Chemical Feed System Boiler Room 6EA1 $1,078
Chemical Feeder Boiler Room 6EA1 $1,078
Combustion Dampers Boiler Room 6EA2 $818
Condensate Pump Boiler Room 6EA1 $2,021
Feed Water Pumps and Tank Boiler Room 3 pumps at 3/4 HP each.6EA1 $2,545
Non Condensing- Fire Tube- Scotch Marine- Steam- Low Pressure Boiler - 101 - 150 HP
Boiler Room Serve main building and heat exchanger for addition.
6EA2 $5,091
Piping - Condensate Pipe- Steel Boiler Room / Entire Building 6LF200 $378
Piping - Steam Pipe- Steel Boiler Room / Entire Building 6LF200 $378
Steam Traps Boiler Room / 1st Floor (2) AHUs and (1) steam unit heater. 5EA15 $19,723
Heat Exchangers
Heat Exchanger - Steam to Hot Water Shell Type Boiler Room Serves the addition. 6EA1 $0
Heating Devices
Unit Heater - Electric Entire Building / Electrical Room 6EA1 $278
Unit Heater - Gas Entire Building / Boiler Room 6EA1 $278
Unit Heater - Steam Entire Building / Electrical Room 6EA1 $278
Wall Heater - Electric Entire Building 6EA15 $2,084
Mechanical Plumbing
Hot Water Pump - Less than 10 Boiler Room Serve the addition. 6EA2 $2,222
Page 4 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Mechanical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Mechanical Plumbing
Hydronic Supply and Return - Galvanized 1st Floor 6LF100 $7,732
Temperature Control
DDC System Entire Building Software issues at head-end causing system to be run manually.
6SF38,000 $21,736
Thermostats - DDC Entire Building / 1st Floor Damaged and missing cover. 4EA1 $819
Thermostats - DDC Entire Building 6EA23 $0
Ventilation
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Roof 6EA2 $1,185
Mechanical System Subtotal: $271,858
Building: Main
Category: Plumbing System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Hot Water
Gas Heater - 150000 - 300000 BTU/HR Boiler Room Serves the main and addition. 6EA3 $930
Piping
Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF38,000 $7,608
Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF38,000 $9,238
Domestic Piping-Cold Water Risers Entire Building 6SF38,000 $7,064
Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF38,000 $5,977
Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF38,000 $7,064
Domestic Piping-Hot Water Return Lines Entire Building 6SF38,000 $5,434
Domestic Piping-Hot Water Return Risers Entire Building 6SF38,000 $5,434
Sanitary Piping Entire Building 6SF38,000 $34,778
Storm Piping Entire Building 6SF38,000 $33,147
Vent Piping Entire Building 6SF38,000 $25,540
Pumps
Pumps - Domestic Booster Pump-Simplex Entire Building / Boiler Room Serves the main and addition. 6EA1 $1,446
Pumps - Sump-Simplex Entire Building / 1st Floor Elevator sump pump. 6EA1 $745
Plumbing System Subtotal: $144,404
Building: Main
Page 5 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #100 (Kindergarten)
AC Units 1st Floor on the lighting panel3EA1 $6,086
Casework 1st Floor 6LF6 $152
Ceiling - Plaster/Drywall 1st Floor 6SF919 $3,180
Chalk Board 1st Floor 4LF24 $2,203
Doors - Side-lite 1st Floor 6SF24 $401
Doors - Transom Window 1st Floor 6SF24 $406
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Floor - Tile 1st Floor damaged5SF9 $52
Floor - Tile 1st Floor 6SF910 $1,991
Lighting - Pendent/Surface 1st Floor 7EA14 $0
Marker Board 1st Floor 7LF20 $0
Storage/ Closet 1st Floor 6SF64 $464
Walls - Plaster/Drywall 1st Floor 6SF1,481 $4,087
Classroom #101 (Special Education)
AC Units 1st Floor on the lighting panel3EA1 $6,086
Casework 1st Floor 6LF6 $152
Ceiling - Plaster/Drywall 1st Floor 6SF919 $3,180
Chalk Board 1st Floor 4LF24 $2,203
Doors - Side-lite 1st Floor 6SF24 $401
Doors - Transom Window 1st Floor 6SF24 $406
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Floor - Tile 1st Floor damaged5SF4 $23
Floor - Tile 1st Floor 6SF915 $2,002
Lighting - Pendent/Surface 1st Floor 7EA14 $0
Marker Board 1st Floor 7LF20 $0
Storage/ Closet 1st Floor 6SF64 $464
Walls - Plaster/Drywall 1st Floor 6SF1,481 $4,087
Classroom #102 (Special Education)
AC Units 1st Floor on the lighting panel3EA1 $6,086
Casework 1st Floor damaged5LF2 $418
Casework 1st Floor 6LF44 $1,111
Ceiling - Plaster/Drywall 1st Floor 6SF919 $3,180
Chalk Board 1st Floor 4LF4 $367
Doors - Side-lite 1st Floor 6SF24 $401
Doors - Transom Window 1st Floor 6SF24 $406
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Floor - Tile 1st Floor 6SF919 $2,011
Lighting - Pendent/Surface 1st Floor 7EA14 $0
Page 6 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #102 (Special Education)
Marker Board 1st Floor 7LF20 $0
Storage/ Closet 1st Floor 6SF64 $464
Walls - Plaster/Drywall 1st Floor water damage4SF10 $147
Walls - Plaster/Drywall 1st Floor 6SF1,471 $4,060
Classroom #103 (Pre School)
AC Units 1st Floor on the lighting panel3EA1 $6,086
Ceiling - Plaster/Drywall 1st Floor 6SF919 $3,180
Doors - Side-lite 1st Floor 6SF12 $201
Doors - Transom Window 1st Floor 6SF12 $203
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Floor - Wood 1st Floor 6SF919 $6,479
Lighting - Pendent/Surface 1st Floor 7EA14 $0
Marker Board 1st Floor 7LF16 $0
Storage/ Closet 1st Floor 6SF64 $464
Walls - Plaster/Drywall 1st Floor water damage4SF10 $147
Walls - Plaster/Drywall 1st Floor 6SF1,471 $4,060
Classroom #200 (Computer Lab)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF8 $202
Ceiling - Plaster/Drywall 2nd Floor 6SF919 $3,180
Chalk Board 2nd Floor 4LF16 $1,469
Charging Station 2nd Floor 6EA2 $969
Doors - Transom Window 2nd Floor 6SF24 $406
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Wood 2nd Floor Sub-floor popping and warping, needs replacing5SF919 $13,444
Lighting - Pendent/Surface 2nd Floor 7EA14 $0
Marker Board 2nd Floor 7LF22 $0
Storage/ Closet 2nd Floor 6SF64 $464
Walls - Plaster/Drywall 2nd Floor 6SF1,400 $3,864
Walls - Plaster/Drywall 2nd Floor water damage4SF10 $147
Wireless System 2nd Floor 6EA1 $372
Classroom #201 (Regular Classroom)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF6 $152
Ceiling - Plaster/Drywall 2nd Floor 6SF919 $3,180
Chalk Board 2nd Floor 4LF20 $1,836
Page 7 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #201 (Regular Classroom)
Doors - Transom Window 2nd Floor 6SF24 $406
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Wood 2nd Floor Sub-floor popping and warping5SF919 $13,444
Lighting - Pendent/Surface 2nd Floor 7EA14 $0
Marker Board 2nd Floor 7LF22 $0
Storage/ Closet 2nd Floor Missing door for storage closet5SF6 $97
Storage/ Closet 2nd Floor 6SF58 $421
Walls - Plaster/Drywall 2nd Floor 6SF1,470 $4,057
Walls - Plaster/Drywall 2nd Floor water damage5SF12 $61
Classroom #202 (Store Room)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor damage to door frame on closet5LF6 $1,254
Ceiling - Plaster/Drywall 2nd Floor 6SF919 $3,180
Chalk Board 2nd Floor 4LF16 $1,469
Doors - Transom Window 2nd Floor 6SF24 $406
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Wood 2nd Floor Subfloor popping and warping, needs replacement.
5SF919 $13,444
Lighting - Pendent/Surface 2nd Floor 7EA13 $0
Lighting - Pendent/Surface 2nd Floor Missing cover6EA1 $124
Marker Board 2nd Floor 7LF12 $0
Storage/ Closet 2nd Floor 6SF64 $464
Walls - Plaster/Drywall 2nd Floor 6SF1,481 $4,087
Classroom #203 (Regular Classroom)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF6 $152
Ceiling - Plaster/Drywall 2nd Floor 6SF919 $3,180
Chalk Board 2nd Floor 4LF14 $1,285
Doors - Transom Window 2nd Floor 6SF24 $406
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Wood 2nd Floor 6SF919 $6,479
Lighting - Pendent/Surface 2nd Floor 7EA15 $0
Marker Board 2nd Floor 7LF22 $0
Storage/ Closet 2nd Floor 6SF64 $464
Walls - Plaster/Drywall 2nd Floor water damage, 1 window broken (5 ft)4SF20 $294
Walls - Plaster/Drywall 2nd Floor 6SF1,460 $4,029
Page 8 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #204 (Computer Lab)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF6 $152
Ceiling - Plaster/Drywall 2nd Floor 6SF919 $3,180
Chalk Board 2nd Floor 4LF24 $2,203
Charging Station 2nd Floor 6EA1 $485
Doors - Transom Window 2nd Floor 6SF6 $102
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Wood 2nd Floor Sub-floor popping and warping, needs replacing5SF919 $13,444
Lighting - Pendent/Surface 2nd Floor 7EA12 $0
Marker Board 2nd Floor 7LF20 $0
Storage/ Closet 2nd Floor 6SF64 $464
Walls - Plaster/Drywall 2nd Floor 6SF1,415 $3,905
Walls - Plaster/Drywall 2nd Floor water damage4SF65 $956
Wireless System 2nd Floor 6EA1 $372
Classroom #205 (Faculty Lounge)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Ceiling - Plaster/Drywall 2nd Floor 6SF919 $3,180
Chalk Board 2nd Floor 4LF20 $1,836
Doors - Wood Doors inclu hw 2nd Floor 6EA2 $602
Floor - Tile 2nd Floor 6SF915 $2,002
Floor - Tile 2nd Floor tile damaged5SF4 $23
Lighting - Pendent/Surface 2nd Floor 7EA7 $0
Walls - Plaster/Drywall 2nd Floor 6SF1,180 $3,257
Walls - Plaster/Drywall 2nd Floor water damage4SF4 $59
Classroom #300 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF6 $152
Ceiling - Plaster/Drywall 3rd Floor 6SF919 $3,180
Doors - Transom Window 3rd Floor 6SF24 $406
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Wood 3rd Floor Sub-floor popping and warping, needs replacing5SF919 $13,444
Lighting - Pendent/Surface 3rd Floor 7EA14 $0
Marker Board 3rd Floor 7LF15 $0
Storage/ Closet 3rd Floor 6SF64 $464
Walls - Plaster/Drywall 3rd Floor 6SF1,417 $3,911
Page 9 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #301 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF6 $152
Ceiling - Plaster/Drywall 3rd Floor 6SF919 $3,180
Doors - Transom Window 3rd Floor 6SF24 $406
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Wood 3rd Floor 6SF919 $6,479
Lighting - Pendent/Surface 3rd Floor 7EA14 $0
Marker Board 3rd Floor 7LF15 $0
Storage/ Closet 3rd Floor 6SF64 $464
Walls - Plaster/Drywall 3rd Floor 6SF1,417 $3,911
Classroom #302 (Music Room)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF6 $152
Ceiling - Plaster/Drywall 3rd Floor 6SF919 $3,180
Doors - Transom Window 3rd Floor 6SF24 $406
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Wood 3rd Floor Sub-floor popping and warping, needs replacing5SF919 $13,444
Lighting - Pendent/Surface 3rd Floor 7EA14 $0
Marker Board 3rd Floor 7LF15 $0
Storage/ Closet 3rd Floor 6SF64 $464
Walls - Plaster/Drywall 3rd Floor 6SF1,417 $3,911
Classroom #303 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA2 $12,173
Casework 3rd Floor 6LF6 $152
Ceiling - Plaster/Drywall 3rd Floor 6SF919 $3,180
Doors - Transom Window 3rd Floor 6SF24 $406
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Wood 3rd Floor 6SF919 $6,479
Lighting - Pendent/Surface 3rd Floor 7EA14 $0
Marker Board 3rd Floor 7LF20 $0
Storage/ Closet 3rd Floor 6SF64 $464
Walls - Plaster/Drywall 3rd Floor 6SF1,417 $3,911
Classroom #304 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA2 $12,173
Casework 3rd Floor 6LF6 $152
Ceiling - Plaster/Drywall 3rd Floor 6SF919 $3,180
Page 10 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #304 (Regular Classroom)
Chalk Board 3rd Floor 4LF30 $2,754
Doors - Transom Window 3rd Floor 6SF24 $406
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Wood 3rd Floor Sub-floor popping and warping, needs replacing5SF919 $13,444
Lighting - Pendent/Surface 3rd Floor 7EA14 $0
Marker Board 3rd Floor 7LF8 $0
Storage/ Closet 3rd Floor 6SF64 $464
Walls - Plaster/Drywall 3rd Floor 6SF1,417 $3,911
Classrooms Subtotal: $382,556
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Administrative Suites/Offices
Ceiling - Lay-in 1st Fl Engineers Office, next to Boiler Room
6SF161 $483
Doors - Wood Doors inclu hw 1st Fl Engineers Office, next to Boiler
Room
6EA1 $301
Floor - Tile 1st Fl Engineers Office, next to Boiler
Room
6SF161 $352
Lighting - Pendent/Surface 1st Fl Engineers Office, next to Boiler Room
7EA2 $0
Power Distribution 1st Fl Engineers Office, next to Boiler Room
7EA12 $0
Walls - Masonry 1st Fl Engineers Office, next to Boiler Room
6SF438 $1,378
Gymnasia
Ceiling - Plaster/Drywall 1st Floor 6SF3,520 $19,430
Doors - Wood Doors inclu hw 1st Floor 6EA8 $2,408
Floor - Concrete 1st Floor asphalt- at door5SF67 $115
Floor - Wood 1st Floor 6SF3,453 $24,343
Lighting - Metal Halide/Sodium Vapor 1st Floor 7EA12 $0
Lighting - Pendent/Surface 1st Floor 7EA1 $0
Lighting - Wall Mounted 1st Floor 7EA7 $0
Sound System 1st Floor 6EA1 $41,654
Stage 1st Floor 6SF500 $2,889
Stage Curtain 1st Floor 6EA4 $0
Page 11 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Gymnasia
Stage Lift 1st Floor 6EA1 $6,510
Stage Lighting System 1st Floor 7EA1 $0
Stage-Stairs - Wood 1st Floor 6LF10 $117
Storage/ Closet 1st Floor 6SF80 $580
Walls - Plaster/Drywall 1st Floor 6SF2,246 $6,199
Walls - Structural Glazed Tile 1st Floor 6SF2,246 $7,066
Mechanical/ Service Rooms
Air Intake Plenums 1st Floor efflorescence on wall of North Warm Air Chamber5SF60 $799
Air Intake Plenums 1st Floor warm air chamber6SF1,224 $7,579
Boiler Room 1st Floor 6SF1,027 $7,358
Janitor's Closet 1st Floor Water damage on walls5SF12 $194
Janitor's Closet 1st Floor 6SF12 $86
Mechanical/ Service Rooms 1st Floor 6SF1,650 $11,821
Janitor's Closet 2nd Floor Wall damaged due to water damage5SF26 $419
Janitor's Closet 2nd Floor 6SF26 $186
Storage Room 2nd Floor 6SF42 $301
Janitor's Closet 3rd Floor 6SF48 $344
Storage Room 3rd Floor 6SF222 $1,590
Restroom
Accessories 1st Floor Boys- next to Tank Room 6SF290 $2,675
Ceiling - Plaster/Drywall 1st Floor Boys- next to Tank Room 6SF290 $1,004
Doors - Wood Doors inclu hw 1st Floor Boys- next to Tank Room 6EA1 $301
Floor Drain 1st Floor Boys- next to Tank Room 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Floor Boys- next to Tank Room 6SF290 $614
Hand Dryer 1st Floor Boys- next to Tank Room 6EA1 $230
Lavatory 1st Floor Boys- next to Tank Room 6EA2 $639
Lighting - Pendent/Surface 1st Floor Boys- next to Tank Room 7EA5 $0
Partitions 1st Floor Boys- next to Tank Room 6EA3 $891
Urinals 1st Floor Boys- next to Tank Room 6EA4 $1,344
Walls - Plaster/Drywall 1st Floor Boys- next to Tank Room 6SF455 $1,256
Walls - Plaster/Drywall 1st Floor Boys- next to Tank Room cracking5SF5 $26
Walls - Structural Glazed Tile 1st Floor Boys- next to Tank Room 6SF460 $1,447
Water Closet 1st Floor Boys- next to Tank Room 6EA3 $1,008
Accessories 1st Floor Girls- next to 103 6SF470 $4,335
Ceiling - Plaster/Drywall 1st Floor Girls- next to 103 6SF470 $1,626
Doors - Side-lite 1st Floor Girls- next to 103 6SF18 $301
Page 12 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Doors - Wood Doors inclu hw 1st Floor Girls- next to 103 6EA1 $301
Floor Drain 1st Floor Girls- next to 103 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Floor Girls- next to 103 6SF470 $995
Hand Dryer 1st Floor Girls- next to 103 6EA1 $230
Lavatory 1st Floor Girls- next to 103 6EA2 $639
Lighting - Pendent/Surface 1st Floor Girls- next to 103 7EA4 $0
Partitions 1st Floor Girls- next to 103 6EA4 $1,188
Walls - Masonry 1st Floor Girls- next to 103 6SF400 $1,258
Walls - Plaster/Drywall 1st Floor Girls- next to 103 6SF425 $1,173
Walls - Structural Glazed Tile 1st Floor Girls- next to 103 6SF325 $1,022
Water Closet 1st Floor Girls- next to 103 6EA3 $1,008
Accessories 1st Floor inside Room 102 6SF144 $1,328
Ceiling - Plaster/Drywall 1st Floor inside Room 102 6SF144 $498
Doors - Wood Doors inclu hw 1st Floor inside Room 102 6EA1 $301
Floor Drain 1st Floor inside Room 102 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Floor inside Room 102 6SF144 $305
Hand Dryer 1st Floor inside Room 102 6EA1 $230
Lavatory 1st Floor inside Room 102 6EA1 $320
Lighting - Pendent/Surface 1st Floor inside Room 102 7EA3 $0
Walls - Plaster/Drywall 1st Floor inside Room 102 6SF300 $828
Walls - Plaster/Drywall 1st Floor inside Room 102 water damage4SF8 $118
Accessories 1st Floor next to 103 6SF42 $387
Doors - Wood Doors inclu hw 1st Floor next to 103 6EA1 $301
Floor Drain 1st Floor next to 103 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Floor next to 103 6SF42 $89
Hand Dryer 1st Floor next to 103 6EA1 $230
Lavatory 1st Floor next to 103 6EA1 $320
Lighting - Pendent/Surface 1st Floor next to 103 7EA1 $0
Walls - Plaster/Drywall 1st Floor next to 103 6SF324 $894
Walls - Structural Glazed Tile 1st Floor next to 103 6SF46 $145
Water Closet 1st Floor next to 103 6EA1 $336
Accessories 1st Flr -In Engineers Office 6SF20 $184
Ceiling - Lay-in 1st Flr -In Engineers Office missing the tiles5SF20 $119
Doors - Wood Doors inclu hw 1st Flr -In Engineers Office old & in poor condition5EA1 $1,174
Floor - Concrete 1st Flr -In Engineers Office 6SF20 $11
Lavatory 1st Flr -In Engineers Office 6EA1 $320
Lighting - Lay-in 1st Flr -In Engineers Office 7EA1 $0
Page 13 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Walls - Masonry 1st Flr -In Engineers Office 6SF108 $340
Walls - Plaster/Drywall 1st Flr -In Engineers Office 6SF108 $298
Water Closet 1st Flr -In Engineers Office 6EA1 $336
Accessories 2nd Floor Boys- next to 205 6SF290 $2,675
Ceiling - Plaster/Drywall 2nd Floor Boys- next to 205 6SF290 $1,004
Doors - Wood Doors inclu hw 2nd Floor Boys- next to 205 6EA1 $301
Floor Drain 2nd Floor Boys- next to 205 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 2nd Floor Boys- next to 205 6SF290 $614
Hand Dryer 2nd Floor Boys- next to 205 6EA1 $230
Lavatory 2nd Floor Boys- next to 205 6EA2 $639
Lighting - Pendent/Surface 2nd Floor Boys- next to 205 7EA3 $0
Partitions 2nd Floor Boys- next to 205 6EA2 $594
Urinals 2nd Floor Boys- next to 205 6EA4 $1,344
Walls - Plaster/Drywall 2nd Floor Boys- next to 205 5SF460 $3,486
Walls - Structural Glazed Tile 2nd Floor Boys- next to 205 6SF460 $1,447
Water Closet 2nd Floor Boys- next to 205 6EA2 $672
Accessories 2nd Floor Girls- next to 203 6SF470 $4,335
Ceiling - Plaster/Drywall 2nd Floor Girls- next to 203 6SF470 $1,626
Doors - Side-lite 2nd Floor Girls- next to 203 6SF12 $201
Doors - Wood Doors inclu hw 2nd Floor Girls- next to 203 6EA1 $301
Floor Drain 2nd Floor Girls- next to 203 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 2nd Floor Girls- next to 203 6SF465 $984
Floor - Tile Ceramic/ Porcelain 2nd Floor Girls- next to 203 broken tile5SF5 $104
Hand Dryer 2nd Floor Girls- next to 203 6EA1 $230
Lavatory 2nd Floor Girls- next to 203 6EA3 $959
Lighting - Pendent/Surface 2nd Floor Girls- next to 203 7EA4 $0
Partitions 2nd Floor Girls- next to 203 6EA4 $1,188
Walls - Masonry 2nd Floor Girls- next to 203 6SF300 $944
Walls - Plaster/Drywall 2nd Floor Girls- next to 203 6SF400 $1,104
Walls - Structural Glazed Tile 2nd Floor Girls- next to 203 6SF325 $1,022
Water Closet 2nd Floor Girls- next to 203 6EA3 $1,008
Accessories 2nd Floor next to 205 6SF42 $387
Ceiling - Plaster/Drywall 2nd Floor next to 205 6SF42 $145
Doors - Wood Doors inclu hw 2nd Floor next to 205 6EA1 $301
Floor Drain 2nd Floor next to 205 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 2nd Floor next to 205 6SF42 $89
Lavatory 2nd Floor next to 205 6EA1 $320
Page 14 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Lighting - Pendent/Surface 2nd Floor next to 205 7EA1 $0
Walls - Plaster/Drywall 2nd Floor next to 205 6SF324 $894
Walls - Structural Glazed Tile 2nd Floor next to 205 6SF46 $145
Water Closet 2nd Floor next to 205 6EA1 $336
Accessories 3rd Floor Boys- Across from 300 6SF290 $2,675
Ceiling - Plaster/Drywall 3rd Floor Boys- Across from 300 6SF290 $1,004
Doors - Wood Doors inclu hw 3rd Floor Boys- Across from 300 6EA1 $301
Floor Drain 3rd Floor Boys- Across from 300 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 3rd Floor Boys- Across from 300 cracked tile5SF4 $84
Floor - Tile Ceramic/ Porcelain 3rd Floor Boys- Across from 300 6SF286 $605
Hand Dryer 3rd Floor Boys- Across from 300 6EA1 $230
Lavatory 3rd Floor Boys- Across from 300 6EA2 $639
Lighting - Pendent/Surface 3rd Floor Boys- Across from 300 7EA3 $0
Partitions 3rd Floor Boys- Across from 300 6EA3 $891
Urinals 3rd Floor Boys- Across from 300 6EA4 $1,344
Walls - Plaster/Drywall 3rd Floor Boys- Across from 300 6SF450 $1,242
Walls - Plaster/Drywall 3rd Floor Boys- Across from 300 water damage, cracking4SF10 $147
Walls - Structural Glazed Tile 3rd Floor Boys- Across from 300 6SF460 $1,447
Water Closet 3rd Floor Boys- Across from 300 6EA2 $672
Accessories 3rd Floor Girls- next to 303 6SF470 $4,335
Ceiling - Plaster/Drywall 3rd Floor Girls- next to 303 6SF470 $1,626
Doors - Wood Doors inclu hw 3rd Floor Girls- next to 303 6EA1 $301
Floor Drain 3rd Floor Girls- next to 303 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 3rd Floor Girls- next to 303 6SF470 $995
Hand Dryer 3rd Floor Girls- next to 303 6EA1 $230
Lavatory 3rd Floor Girls- next to 303 6EA3 $959
Lighting - Pendent/Surface 3rd Floor Girls- next to 303 7EA4 $0
Partitions 3rd Floor Girls- next to 303 6EA6 $1,782
Walls - Plaster/Drywall 3rd Floor Girls- next to 303 6SF627 $1,730
Walls - Structural Glazed Tile 3rd Floor Girls- next to 303 6SF627 $1,973
Water Closet 3rd Floor Girls- next to 303 6EA5 $1,680
Accessories 3rd Floor next to 304 6SF42 $387
Ceiling - Plaster/Drywall 3rd Floor next to 304 6SF42 $145
Doors - Wood Doors inclu hw 3rd Floor next to 304 6EA1 $301
Floor Drain 3rd Floor next to 304 6EA1 $1,059
Floor - Tile 3rd Floor next to 304 6SF38 $83
Floor - Tile 3rd Floor next to 304 broken tile5SF4 $23
Page 15 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Hand Dryer 3rd Floor next to 304 6EA1 $230
Lavatory 3rd Floor next to 304 6EA1 $320
Lighting - Pendent/Surface 3rd Floor next to 304 7EA1 $0
Walls - Plaster/Drywall 3rd Floor next to 304 6SF324 $894
Walls - Structural Glazed Tile 3rd Floor next to 304 6SF46 $145
Water Closet 3rd Floor next to 304 6EA1 $336
Rooms (Other Than Classrooms) Subtotal: $249,399
Building: Main
Category: Building Interior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Corridor
Ceiling - Plaster/Drywall 1st Floor damaged ceiling along door frame between main and addition
5SF7 $122
Ceiling - Plaster/Drywall 1st Floor 6SF3,280 $20,309
Drinking Fountains - Single Water Cooler 1st Floor 6EA1 $317
Floor - Tile/Sheet 1st Floor damaged tile5SF7 $40
Floor - Tile/Sheet 1st Floor 6SF3,280 $1,782
Doors - Steel Doors incl hw 1st Floor by elevator6EA2 $602
Lighting - Pendent/Surface 1st Floor 7EA15 $0
Walls - Concrete Block 1st Floor 6SF400 $1,173
Walls - Plaster/Drywall 1st Floor 6SF4,031 $17,869
Ceiling - Plaster/Drywall 2nd Floor 6SF3,600 $22,291
Drinking Fountains - Single Water Cooler 2nd Floor 6EA2 $633
Floor - Asphalt Floor 2nd Floor 5SF3,230 $11,455
Floor - Terrazzo 2nd Floor terrazzo section between addition and main6SF370 $3,106
Lighting - Pendent/Surface 2nd Floor 7EA15 $0
Stairs - Terrazzo 2nd Floor 6LF3 $28
Walls - Plaster/Drywall 2nd Floor cracking along north wall adjacent to north stairwell
6SF6 $37
Walls - Plaster/Drywall 2nd Floor 6SF6,206 $27,511
Ceiling - Plaster/Drywall 3rd Floor 6SF3,037 $18,805
Drinking Fountains - Single Water Cooler 3rd Floor 6EA2 $633
Floor - Asphalt Floor 3rd Floor 5SF3,037 $10,770
Lighting - Pendent/Surface 3rd Floor 7EA12 $0
Walls - Plaster/Drywall 3rd Floor 6SF5,157 $22,861
Page 16 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Main
Category: Building Interior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Safety
Metal Dedector sitting in tank room. pulled out when school needs
to use.
6EA1 $881
Security Cameras 6EA2 $388
Stairs
Ceiling - Plaster/Drywall North 6SF487 $3,566
Floor - Asphalt North 5SF294 $4,629
Handrails North 6LF128 $1,109
Lighting - Pendent/Surface North 7EA15 $0
Stairs - Asphalt North 5LF64 $2,708
Walls - Plaster/Drywall North 6SF1,100 $3,036
Ceiling - Plaster/Drywall South 6SF487 $3,566
Floor - Asphalt South 5SF294 $4,629
Handrails South 6LF128 $1,109
Lighting - Pendent/Surface South 7EA15 $0
Stairs - Asphalt South 5LF64 $2,708
Walls - Plaster/Drywall South 6SF1,100 $3,036
Vertical Conveyance
Elevator - Hydraulic Elevator 6EA1 $19,238
Wheelchair Lift - Platform Lift 6EA1 $6,690
Building Interior Subtotal: $217,637
Total Building Cost $2,812,290
Building: Addition
Category: Building Exterior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Entrance
Entrance Control - Audio and Video Door 1 - East 6EA1 $702
Entrance Control - Audio and Video Door 4 - North 6EA1 $702
Exterior Doors - Exterior Steel Door Door 1 - East 6EA6 $2,883
Exterior Doors - Exterior Steel Door Door 1.5 - Southeast 6EA2 $961
Exterior Doors - Exterior Steel Door Door 2 - Southeast 6EA2 $961
Exterior Doors - Exterior Steel Door Door 3.4 5EA1 $1,341
Exterior Doors - Exterior Steel Door Door 4 - North 6EA3 $1,442
Exterior Stairs - Concrete Door 4 - North 6LF36 $2,944
Page 17 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Building Exterior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Entrance
Exterior Stairs - Stone Door 1 - East 6LF10 $1,130
Ramp Handrail - Steel_Ramp Handrail Door 1.5 - Southeast 6LF15 $130
Ramps - Concrete Door 1.5 - Southeast 6LF20 $3,005
Stair Handrail - Steel_Stair Handrail Door 4 - North 6LF25 $217
Foundation
Foundation - Concrete Entire Building 7LF409 $0
Superstructure - Metal Deck/ Concrete Topping Entire Building 7SF35,326 $0
Lighting
Exterior Lighting - Parapet or Roof Mounted Entire Building 6EA3 $1,610
Exterior Lighting - Parapet or Roof Mounted Entire Building 4EA1 $5,095
Exterior Lighting - Wall Mounted Entire Building 6EA3 $866
Roof System
Coping - Metal Roof 1 6LF450 $14,453
Coping - Metal Roof 2 6LF75 $2,409
Coping - Metal Roof 3 7LF165 $0
Coping - Metal Roof 4 6LF75 $2,409
Coping - Stone Roof 3 6LF15 $482
Downspouts - Exterior Downspouts Roof 4 7LF3 $0
Downspouts - Interior Downspouts Roof 1 7LF105 $0
Downspouts - Interior Downspouts Roof 2 7LF15 $0
Downspouts - Interior Downspouts Roof 3 7LF30 $0
Parapet - 16" - 30" Height Roof 4 6LF75 $2,997
Parapet - Parapet < 16" Height Roof 3 6LF65 $1,385
Roof Structure - Steel / Metal Deck/ Concrete Topping Roof 1 7SF9,920 $0
Roof Structure - Steel / Metal Deck/ Concrete Topping Roof 2 7SF1,242 $0
Roof Structure - Steel / Metal Deck/ Concrete Topping Roof 3 7SF1,700 $0
Roof Structure - Steel / Metal Deck/ Concrete Topping Roof 4 7SF294 $0
Roof - Asphalt Gravel Ballast Roof 1 6SF9,920 $100,860
Roof - Modified Bitumen Roof 2 6SF1,242 $11,686
Roof - Modified Bitumen Roof 3 Ponding causing surface deterioration5SF50 $1,428
Roof - Modified Bitumen Roof 3 6SF1,650 $15,526
Roof - Modified Bitumen Roof 4 Ponding4SF294 $8,059
Walls
Exterior Walls - Brick Entire Building 6SF16,499 $110,890
Page 18 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Building Exterior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Windows
Guard - Guards perforated Entire Building 6SF1,795 $22,922
Lintels - Steel Entire Building 7LF852 $0
Windows - Sash Aluminum Double-pane Entire Building 5SF4,986 $268,586
Building Exterior Subtotal: $588,079
Building: Addition
Category: Electrical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Emergency System
Emergency A/C Power - Corridors and Stairs Entire Building 6SF9,168 $2,753
Emergency A/C Power - Lunchrooms Entire Building / 1st Floor 6SF1,749 $650
Emergency A/C Power - Students Toilets Entire Building 6SF1,598 $594
Exit Signs - Corridors and Stairs Entire Building 6EA12 $1,797
Exit Signs - Lunchroom Entire Building / 1st Floor 6EA3 $449
Security System - CCTV Entire Building 6SF35,326 $10,608
Security System - Intrusion Detection Entire Building 6SF35,326 $9,093
UPS - Less than 30 KW MDF Room 7EA1 $0
Main Service
PA System Entire Building Serves the main and addition. Control console located in the addition.
6SF35,326 $11,619
Power Distribution
Lighting and Power Panels - 100 A Entire Building / 1st Floor 6EA1 $299
Lighting and Power Panels - Above 100 A Entire Building / 1st Floor 6EA1 $497
Lighting and Power Panels - Above 100 A Entire Building 6EA4 $1,988
Electrical System Subtotal: $40,348
Building: Addition
Category: Mechanical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Heating Devices
Cabinet Heaters - With Hot Water Coil Entire Building Wall mounted thermostats. 6EA15 $5,315
Fin Tube - Hot Water Stairwell 6LF24 $227
Unit Heater - Electric Entire Building / 1st Floor Boy's Toilet Room. Integral thermostat.6EA1 $278
Page 19 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Mechanical System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Heating Devices
Unit Heater - Electric Entire Building / 3rd Floor Kitchen. Integral thermostat. 6EA1 $278
Wall Heater - Electric Entire Building 6EA2 $278
Mechanical Plumbing
Hydronic Supply and Return - Galvanized Entire Building 6LF800 $61,856
Temperature Control
Pneumatic System Entire Building 6SF35,326 $18,691
Thermostats - Pneumatic Entire Building / 1st Floor Unit ventilator thermostat.4EA1 $737
Thermostats - Pneumatic Entire Building / 1st Floor Cabinet heater thermostat. 4EA1 $737
Thermostats - Pneumatic Entire Building / 3rd Floor Unit ventilator thermostats.4EA2 $1,474
Thermostats - Pneumatic Entire Building for unit ventilators and for cabinet heaters. 6EA30 $0
Unit Ventilation
Unit Ventilators- Floor Mounted- Hot Water Heating Coils Only Entire Building / 1st Floor Serve the lunchroom. 5EA2 $17,126
Unit Ventilators- Floor Mounted- Hot Water Heating Coils Only Entire Building Serve the classrooms and some offices. 5EA25 $214,072
Ventilation
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Entire Building / Lower Roof 6EA1 $592
Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Entire Building / Roof 6EA3 $1,777
Exhaust Fans- Roof Mounted - 500 - 1500 CFM Entire Building / Roof 6EA1 $592
Exhaust Fans- Roof Mounted - Less than 500 CFM Entire Building / Roof 6EA2 $592
Type I Exhaust Hood- Kitchen Entire Building / 1st Floor No fire suppression system and equipment did not fit under the hood.
2EA1 $28,265
Type II Exhaust Hood- Warming Kitchen Entire Building / 1st Floor Dishwasher hood. 6EA1 $920
Mechanical System Subtotal: $353,807
Building: Addition
Category: Plumbing System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Hot Water
Electric Heater - Less than 20 KW Kitchen Serves the dishwasher. 6EA1 $682
Piping
Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF35,326 $7,072
Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF35,326 $8,588
Domestic Piping-Cold Water Risers Entire Building 6SF35,326 $6,567
Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF35,326 $5,557
Page 20 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Plumbing System
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Piping
Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF35,326 $6,567
Domestic Piping-Hot Water Return Lines Entire Building 6SF35,326 $5,052
Domestic Piping-Hot Water Return Risers Entire Building 6SF35,326 $5,052
Sanitary Piping Entire Building 6SF35,326 $32,330
Storm Piping Entire Building 6SF35,326 $30,815
Vent Piping Entire Building 6SF35,326 $23,743
Pumps
Pumps - Sump-Simplex 1st Floor Elevator sump pump. 6EA1 $745
Plumbing System Subtotal: $132,769
Building: Addition
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #109 (Kindergarten)
AC Units 1st Floor on the lighting panel3EA2 $12,173
Casework 1st Floor 6LF43 $1,086
Ceiling - Plaster/Drywall 1st Floor 6SF1,043 $3,609
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Floor - Tile 1st Floor 6SF1,043 $2,282
Lighting - Pendent/Surface 1st Floor 7EA22 $0
Storage/ Closet 1st Floor 6SF47 $341
Walls - Concrete Block 1st Floor 6SF1,059 $3,104
Work Sink 1st Floor 6EA1 $379
Classroom #113 (Pre School)
AC Units 1st Floor on the lighting panel3EA2 $12,173
Casework 1st Floor 6LF43 $1,086
Ceiling - Plaster/Drywall 1st Floor 6SF1,043 $3,609
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Floor - Tile 1st Floor old & lifting5SF1,043 $4,683
Lighting - Pendent/Surface 1st Floor 7EA17 $0
Storage/ Closet 1st Floor 6SF47 $341
Walls - Concrete Block 1st Floor crack 5SF3 $42
Walls - Concrete Block 1st Floor 6SF1,056 $3,096
Work Sink 1st Floor 6EA1 $379
Page 21 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #207 (Other Instructional Use)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF17 $429
Ceiling - Plaster/Drywall 2nd Floor 6SF788 $2,727
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor old5SF788 $3,538
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF18 $0
Walls - Concrete Block 2nd Floor 6SF916 $2,685
Classroom #208 (Regular Classroom)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF14 $354
Ceiling - Plaster/Drywall 2nd Floor 6SF788 $2,727
Chalk Board 2nd Floor 4LF28 $2,571
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor old5SF788 $3,538
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF16 $0
Walls - Concrete Block 2nd Floor 6SF916 $2,685
Classroom #209 (Store Room)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF14 $354
Ceiling - Plaster/Drywall 2nd Floor 6SF810 $2,803
Chalk Board 2nd Floor 4LF28 $2,571
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor old5SF810 $3,637
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF16 $0
Walls - Concrete Block 2nd Floor 6SF928 $2,720
Work Sink 2nd Floor does not appear to be working5EA1 $1,508
Classroom #210 (Other Instructional Use)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF14 $354
Ceiling - Plaster/Drywall 2nd Floor 6SF810 $2,803
Chalk Board 2nd Floor 4LF28 $2,571
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor 6SF810 $1,772
Page 22 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #210 (Other Instructional Use)
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF16 $0
Walls - Concrete Block 2nd Floor 6SF928 $2,720
Classroom #211 (Regular Classroom)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF14 $354
Ceiling - Plaster/Drywall 2nd Floor 6SF810 $2,803
Chalk Board 2nd Floor 4LF28 $2,571
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor old5SF810 $3,637
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF16 $0
Walls - Concrete Block 2nd Floor 6SF928 $2,720
Classroom #212 (Office)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF14 $354
Ceiling - Plaster/Drywall 2nd Floor 6SF788 $2,727
Chalk Board 2nd Floor 4LF18 $1,653
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor old5SF788 $3,538
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF26 $0
Walls - Concrete Block 2nd Floor 6SF916 $2,685
Classroom #213 (Art Room)
AC Units 2nd Floor on the lighting panel3EA1 $6,086
Casework 2nd Floor 6LF14 $354
Ceiling - Plaster/Drywall 2nd Floor 6SF788 $2,727
Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301
Floor - Tile 2nd Floor 6SF788 $1,724
Lighting - Pendent/Surface 2nd Floor 7EA16 $0
Marker Board 2nd Floor 7LF6 $0
Walls - Concrete Block 2nd Floor 6SF916 $2,685
Classroom #307 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF14 $354
Page 23 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #307 (Regular Classroom)
Ceiling - Plaster/Drywall 3rd Floor 6SF788 $2,727
Chalk Board 3rd Floor 4LF24 $2,203
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Tile 3rd Floor old5SF788 $3,538
Lighting - Pendent/Surface 3rd Floor covers missing6EA3 $372
Lighting - Pendent/Surface 3rd Floor 7EA13 $0
Marker Board 3rd Floor 7LF18 $0
Walls - Concrete Block 3rd Floor crack5SF3 $42
Walls - Concrete Block 3rd Floor 6SF913 $2,676
Classroom #308 (Regular Classroom)
AC Units on the lighting panel3EA1 $6,086
Casework 6LF17 $429
Ceiling - Plaster/Drywall damaged5SF3 $37
Ceiling - Plaster/Drywall 6SF789 $2,730
Chalk Board 4LF16 $1,469
Doors - Wood Doors inclu hw 6EA1 $301
Floor - Tile old5SF792 $3,556
Lighting - Pendent/Surface 7EA16 $0
Marker Board 7LF16 $0
Walls - Concrete Block 6SF916 $2,685
Classroom #309 (Science Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF17 $429
Ceiling - Plaster/Drywall 3rd Floor 6SF810 $2,803
Chalk Board 3rd Floor 4LF16 $1,469
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Tile 3rd Floor old5SF810 $3,637
Lighting - Pendent/Surface 3rd Floor 7EA16 $0
Marker Board 3rd Floor 7LF18 $0
Walls - Concrete Block 3rd Floor crack5SF5 $70
Walls - Concrete Block 3rd Floor 6SF923 $2,706
Work Sink 3rd Floor 6EA1 $379
Classroom #310 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF14 $354
Ceiling - Plaster/Drywall 3rd Floor 6SF792 $2,741
Page 24 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #310 (Regular Classroom)
Chalk Board 3rd Floor 4LF16 $1,469
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Tile 3rd Floor 6SF792 $1,733
Lighting - Pendent/Surface 3rd Floor 7EA16 $0
Marker Board 3rd Floor 7LF10 $0
Walls - Concrete Block 3rd Floor 6SF916 $2,685
Classroom #311 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF17 $429
Ceiling - Plaster/Drywall 3rd Floor 6SF810 $2,803
Chalk Board 3rd Floor 4LF16 $1,469
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Tile 3rd Floor old5SF810 $3,637
Lighting - Pendent/Surface 3rd Floor 7EA16 $0
Marker Board 3rd Floor 7LF10 $0
Walls - Concrete Block 3rd Floor crack5SF2 $28
Walls - Concrete Block 3rd Floor 6SF926 $2,715
Classroom #312 (Regular Classroom)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF7 $177
Ceiling - Plaster/Drywall 3rd Floor 6SF788 $2,727
Chalk Board 3rd Floor 4LF12 $1,102
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Tile 3rd Floor old5SF788 $3,538
Lighting - Pendent/Surface 3rd Floor 7EA16 $0
Marker Board 3rd Floor 7LF28 $0
Walls - Concrete Block 3rd Floor 6SF916 $2,685
Classroom #313 (Multi Purpose Room)
AC Units 3rd Floor on the lighting panel3EA1 $6,086
Casework 3rd Floor 6LF14 $354
Ceiling - Plaster/Drywall 3rd Floor 6SF787 $2,723
Ceiling - Plaster/Drywall 3rd Floor damaged5SF1 $12
Chalk Board 3rd Floor 4LF42 $3,856
Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301
Floor - Tile 3rd Floor old5SF788 $3,538
Lighting - Pendent/Surface 3rd Floor 7EA16 $0
Page 25 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Classrooms
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Classroom #313 (Multi Purpose Room)
Marker Board 3rd Floor 7LF48 $0
Walls - Concrete Block 3rd Floor 6SF916 $2,685
Classrooms Subtotal: $291,778
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Administrative Suites/Offices
AC Unit 1st Floor - Principal on lighting panel & improper bracing3EA1 $6,086
Ceiling - Plaster/Drywall 1st Floor - Principal 6SF163 $564
Doors - Wood Doors inclu hw 1st Floor - Principal 6EA1 $301
Floor - Carpet 1st Floor - Principal old 5SF163 $837
Lighting - Pendent/Surface 1st Floor - Principal 7EA4 $0
Power Distribution 1st Floor - Principal 7EA6 $0
Storage/ Closet 1st Floor - Principal 6SF9 $65
Walls - Concrete Block 1st Floor - Principal 6SF492 $1,442
AC Unit 1st Floor Main Office on the lighting panel & improper bracing3EA1 $6,086
Ceiling - Plaster/Drywall 1st Floor Main Office 6SF411 $1,422
Doors - Side-lite 1st Floor Main Office 6SF11 $184
Doors - Wood Doors inclu hw 1st Floor Main Office 6EA2 $602
Floor - Carpet 1st Floor Main Office runs, stained, old4SF271 $2,492
Floor - Tile Ceramic/ Porcelain 1st Floor Main Office 6SF140 $296
Lighting - Pendent/Surface 1st Floor Main Office 7EA7 $0
Power Distribution 1st Floor Main Office 7EA14 $0
Walls - Concrete Block 1st Floor Main Office 6SF549 $1,609
Walls - Plaster/Drywall 1st Floor Main Office 6SF183 $505
AC Unit 1st Flr- Conference Rm in Main Office on the lighting panel & improper bracing3EA1 $6,086
Ceiling - Plaster/Drywall 1st Flr- Conference Rm in Main Office 6SF360 $1,246
Doors - Wood Doors inclu hw 1st Flr- Conference Rm in Main Office 6EA2 $602
Floor - Carpet 1st Flr- Conference Rm in Main Office runs, stained, old4SF340 $3,126
Floor - Tile Ceramic/ Porcelain 1st Flr- Conference Rm in Main Office 6SF20 $42
Lighting - Pendent/Surface 1st Flr- Conference Rm in Main Office 7EA8 $0
Power Distribution 1st Flr- Conference Rm in Main Office 7EA10 $0
Storage/ Closet 1st Flr- Conference Rm in Main Office 6SF29 $210
Walls - Concrete Block 1st Flr- Conference Rm in Main Office 6SF549 $1,609
Walls - Plaster/Drywall 1st Flr- Conference Rm in Main Office 6SF183 $505
Page 26 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Administrative Suites/Offices
Ceiling - Plaster/Drywall 1st Flr- Kitchen Office 6SF66 $228
Doors - Wood Doors inclu hw 1st Flr- Kitchen Office 6EA1 $301
Floor - Tile Ceramic/ Porcelain 1st Flr- Kitchen Office 6SF66 $140
Lighting - Lay-in 1st Flr- Kitchen Office 7EA1 $0
Power Distribution 1st Flr- Kitchen Office 7EA4 $0
Walls - Concrete Block 1st Flr- Kitchen Office 6SF278 $815
Ceiling - Plaster/Drywall 2nd Floor Rm 212B- Counselor's Office 6SF243 $841
Doors - Wood Doors inclu hw 2nd Floor Rm 212B- Counselor's Office 6EA2 $602
Floor - Tile 2nd Floor Rm 212B- Counselor's Office 6SF242 $529
Floor - Tile 2nd Floor Rm 212B- Counselor's Office damaged5SF1 $6
Lighting - Pendent/Surface 2nd Floor Rm 212B- Counselor's Office 7EA4 $0
Power Distribution 2nd Floor Rm 212B- Counselor's Office 7EA6 $0
Walls - Concrete Block 2nd Floor Rm 212B- Counselor's Office 6SF612 $1,794
Ceiling - Plaster/Drywall 3rd Floor Rm 312B- Asst Principal 6SF243 $841
Doors - Wood Doors inclu hw 3rd Floor Rm 312B- Asst Principal 6EA2 $602
Floor - Tile 3rd Floor Rm 312B- Asst Principal 6SF243 $532
Lighting - Pendent/Surface 3rd Floor Rm 312B- Asst Principal 7EA4 $0
Power Distribution 3rd Floor Rm 312B- Asst Principal 7EA6 $0
Walls - Concrete Block 3rd Floor Rm 312B- Asst Principal 6SF612 $1,794
Kitchen
Ceiling - Plaster/Drywall 1st Floor 6SF494 $1,710
Doors - Wood Doors inclu hw 1st Floor 6EA2 $602
Floor - Tile Ceramic/ Porcelain 1st Floor 6SF494 $1,046
Lighting - Lay-in 1st Floor 7EA12 $0
Serving Line 1st Floor 6LF18 $1,071
Storage/ Closet 1st Floor door is scraping at top & ruining veneer5SF72 $1,161
Walls - Structural Glazed Tile 1st Floor 6SF1,008 $3,171
Library
AC Unit 1st Flr- Rm 108 on lighting panel, improper bracing & very old units3EA2 $12,173
Casework 1st Flr- Rm 108 6LF90 $2,273
Ceiling - Plaster/Drywall 1st Flr- Rm 108 6SF1,161 $4,018
Ceiling - Plaster/Drywall 1st Flr- Rm 108 damaged5SF2 $25
Doors - Wood Doors inclu hw 1st Flr- Rm 108 6EA2 $602
Floor - Tile 1st Flr- Rm 108 old 5SF1,163 $5,222
Lighting - Pendent/Surface 1st Flr- Rm 108 7EA24 $0
Walls - Concrete Block 1st Flr- Rm 108 6SF1,356 $3,975
Page 27 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Locker/Shower Room
Accessories 1st Flr- Kitchen Staff Locker Rm-
Across from kitchen
6SF62 $243
Ceiling - Plaster/ Drywall 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
6SF62 $215
Doors - Wood Doors inclu hw 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
6EA1 $301
Floor - Tile Ceramic/ Porcelain 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
6SF62 $131
Lavatory 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
6EA1 $320
Lighting - Lay-in 1st Flr- Kitchen Staff Locker Rm-
Across from kitchen
6EA1 $119
Lighting - Wall Mounted 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
7EA1 $0
Partitions 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
7EA1 $0
Student Lockers - One Tier 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
6EA3 $279
Walls - Concrete Block 1st Flr- Kitchen Staff Locker Rm- Across from kitchen
6SF252 $739
Water Closet 1st Flr- Kitchen Staff Locker Rm-
Across from kitchen
6EA1 $336
Lunch & Multipurpose Room
AC Unit 1st Floor on lighting panel3EA2 $12,173
Ceiling - Plaster/Drywall 1st Floor 6SF1,749 $6,053
Doors - Wood Doors inclu hw 1st Floor 6EA2 $602
Floor - Tile 1st Floor 6SF1,749 $3,827
Lighting - Pendent/Surface 1st Floor 7EA41 $0
Walls - Concrete Block 1st Floor 6SF1,760 $5,159
MDF_IDF
AC Unit 1st Floor unsure if on a dedicated circuit or lighting panel,
so assumption is made based on all other ACs
3EA1 $6,086
Doors - Wood Doors inclu hw 1st Floor 6EA1 $301
Finishes 1st Floor 6SF196 $1,399
Mechanical/ Service Rooms
Janitor's Closet 1st Floor floor tiles missing & door can't close, warped5SF59 $952
Mechanical/ Service Rooms 1st Floor 6SF44 $315
Storage Room 1st Floor 6SF95 $681
Vaults 1st Floor In Main6SF66 $473
Page 28 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Mechanical/ Service Rooms
Janitor's Closet 2nd Floor 6SF59 $423
Storage Room 2nd Floor 10' of tile damaged6SF443 $3,174
Janitor's Closet 3rd Floor no floor tiles5SF59 $952
Mechanical/ Service Rooms 3rd Floor 6SF43 $308
Storage Room 3rd Floor book room6SF136 $974
Restroom
Accessories 1st Floor Boys- Next to library 6SF244 $2,251
Ceiling - Plaster/Drywall 1st Floor Boys- Next to library water damaged throughout4SF244 $3,674
Doors - Wood Doors inclu hw 1st Floor Boys- Next to library 6EA2 $602
Floor Drain 1st Floor Boys- Next to library 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Floor Boys- Next to library 6SF244 $516
Lavatory 1st Floor Boys- Next to library 6EA3 $959
Lighting - Pendent/Surface 1st Floor Boys- Next to library 7EA4 $0
Partitions 1st Floor Boys- Next to library 6EA2 $594
Urinals 1st Floor Boys- Next to library 1 urinal is continually running6EA5 $1,680
Walls - Concrete Block 1st Floor Boys- Next to library 6SF611 $1,791
Water Closet 1st Floor Boys- Next to library 6EA2 $672
Accessories 1st Floor Girls- Across from Lunchroom 6SF272 $2,509
Ceiling - Plaster/Drywall 1st Floor Girls- Across from Lunchroom 6SF272 $941
Doors - Wood Doors inclu hw 1st Floor Girls- Across from Lunchroom 6EA3 $903
Floor Drain 1st Floor Girls- Across from Lunchroom 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Floor Girls- Across from Lunchroom 6SF272 $576
Lavatory 1st Floor Girls- Across from Lunchroom 6EA3 $959
Lighting - Pendent/Surface 1st Floor Girls- Across from Lunchroom 7EA4 $0
Partitions 1st Floor Girls- Across from Lunchroom 6EA6 $1,782
Walls - Structural Glazed Tile 1st Floor Girls- Across from Lunchroom 6SF708 $2,227
Water Closet 1st Floor Girls- Across from Lunchroom 6EA7 $2,352
Accessories 1st Floor, Unisex Staff In MDF Rm 6SF29 $267
Ceiling - Plaster/Drywall 1st Floor, Unisex Staff In MDF Rm 6SF29 $100
Doors - Wood Doors inclu hw 1st Floor, Unisex Staff In MDF Rm 6EA1 $301
Floor - Tile Ceramic/ Porcelain 1st Floor, Unisex Staff In MDF Rm 6SF29 $61
Lavatory 1st Floor, Unisex Staff In MDF Rm 6EA1 $320
Lighting - Lay-in 1st Floor, Unisex Staff In MDF Rm 7EA1 $0
Walls - Concrete Block 1st Floor, Unisex Staff In MDF Rm 6SF172 $504
Water Closet 1st Floor, Unisex Staff In MDF Rm 6EA1 $336
Accessories 1st Flr- In 113 6SF25 $231
Ceiling - Plaster/Drywall 1st Flr- In 113 6SF25 $87
Page 29 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Doors - Wood Doors inclu hw 1st Flr- In 113 6EA1 $301
Floor Drain 1st Flr- In 113 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Flr- In 113 6SF25 $53
Lavatory 1st Flr- In 113 6EA1 $320
Lighting - Lay-in 1st Flr- In 113 7EA1 $0
Walls - Concrete Block 1st Flr- In 113 6SF160 $469
Water Closet 1st Flr- In 113 6EA1 $336
Accessories 1st Flr- In Main Office 6SF42 $387
Ceiling - Plaster/Drywall 1st Flr- In Main Office 6SF42 $145
Doors - Wood Doors inclu hw 1st Flr- In Main Office 6EA1 $301
Floor - Tile Ceramic/ Porcelain 1st Flr- In Main Office 6SF42 $89
Lavatory 1st Flr- In Main Office cracked porcelain5EA1 $1,590
Lighting - Pendent/Surface 1st Flr- In Main Office 7EA1 $0
Lighting - Wall Mounted 1st Flr- In Main Office not working4EA1 $393
Walls - Concrete Block 1st Flr- In Main Office 6SF186 $545
Water Closet 1st Flr- In Main Office 6EA1 $336
Accessories 1st Flr- In Rm 109 6SF25 $231
Ceiling - Plaster/Drywall 1st Flr- In Rm 109 6SF25 $87
Doors - Wood Doors inclu hw 1st Flr- In Rm 109 6EA1 $301
Floor Drain 1st Flr- In Rm 109 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 1st Flr- In Rm 109 6SF25 $53
Lavatory 1st Flr- In Rm 109 6EA1 $320
Lighting - Lay-in 1st Flr- In Rm 109 7EA1 $0
Walls - Concrete Block 1st Flr- In Rm 109 6SF160 $469
Water Closet 1st Flr- In Rm 109 6EA1 $336
Accessories 2nd Floor Boys- Across from 209 6SF244 $2,251
Ceiling - Plaster/Drywall 2nd Floor Boys- Across from 209 water damaged5SF5 $62
Ceiling - Plaster/Drywall 2nd Floor Boys- Across from 209 6SF239 $827
Doors - Wood Doors inclu hw 2nd Floor Boys- Across from 209 6EA4 $1,204
Floor Drain 2nd Floor Boys- Across from 209 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 2nd Floor Boys- Across from 209 6SF244 $516
Lavatory 2nd Floor Boys- Across from 209 6EA3 $959
Lighting - Pendent/Surface 2nd Floor Boys- Across from 209 7EA4 $0
Partitions 2nd Floor Boys- Across from 209 6EA2 $594
Urinals 2nd Floor Boys- Across from 209 6EA5 $1,680
Walls - Concrete Block 2nd Floor Boys- Across from 209 6SF611 $1,791
Water Closet 2nd Floor Boys- Across from 209 6EA2 $672
Page 30 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Accessories 2nd Floor Girls- Across from 207 6SF272 $2,509
Ceiling - Plaster/Drywall 2nd Floor Girls- Across from 207 6SF272 $941
Doors - Wood Doors inclu hw 2nd Floor Girls- Across from 207 6EA4 $1,204
Floor Drain 2nd Floor Girls- Across from 207 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 2nd Floor Girls- Across from 207 6SF272 $576
Lavatory 2nd Floor Girls- Across from 207 6EA3 $959
Lighting - Pendent/Surface 2nd Floor Girls- Across from 207 7EA4 $0
Partitions 2nd Floor Girls- Across from 207 1 partition falling over 5EA1 $751
Partitions 2nd Floor Girls- Across from 207 6EA6 $1,782
Walls - Concrete Block 2nd Floor Girls- Across from 207 6SF708 $2,076
Water Closet 2nd Floor Girls- Across from 207 6EA7 $2,352
Accessories 2nd Floor, Staff- Across from 207 6SF60 $553
Ceiling - Plaster/Drywall 2nd Floor, Staff- Across from 207 6SF60 $208
Doors - Wood Doors inclu hw 2nd Floor, Staff- Across from 207 6EA1 $301
Floor - Tile Ceramic/ Porcelain 2nd Floor, Staff- Across from 207 6SF60 $127
Lavatory 2nd Floor, Staff- Across from 207 6EA1 $320
Lighting - Lay-in 2nd Floor, Staff- Across from 207 7EA1 $0
Lighting - Wall Mounted 2nd Floor, Staff- Across from 207 7EA1 $0
Walls - Concrete Block 2nd Floor, Staff- Across from 207 crack in cmu5SF4 $56
Walls - Concrete Block 2nd Floor, Staff- Across from 207 6SF266 $780
Water Closet 2nd Floor, Staff- Across from 207 6EA1 $336
Accessories 2nd Floor, Women's Next to 211 6SF82 $756
Ceiling - Plaster/Drywall 2nd Floor, Women's Next to 211 6SF83 $287
Doors - Wood Doors inclu hw 2nd Floor, Women's Next to 211 6EA1 $301
Floor Drain 2nd Floor, Women's Next to 211 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 2nd Floor, Women's Next to 211 6SF83 $176
Hand Dryer 2nd Floor, Women's Next to 211 6EA1 $230
Lavatory 2nd Floor, Women's Next to 211 6EA1 $320
Lighting - Lay-in 2nd Floor, Women's Next to 211 7EA1 $0
Walls - Concrete Block 2nd Floor, Women's Next to 211 6SF310 $909
Water Closet 2nd Floor, Women's Next to 211 6EA1 $336
Accessories 3rd Floor Boys- across from 309 6SF244 $2,251
Ceiling - Plaster/Drywall 3rd Floor Boys- across from 309 6SF244 $844
Doors - Wood Doors inclu hw 3rd Floor Boys- across from 309 6EA4 $1,204
Floor Drain 3rd Floor Boys- across from 309 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 3rd Floor Boys- across from 309 6SF232 $491
Floor - Tile Ceramic/ Porcelain 3rd Floor Boys- across from 309 cracked tile5SF12 $251
Page 31 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Lavatory 3rd Floor Boys- across from 309 6EA3 $959
Lighting - Pendent/Surface 3rd Floor Boys- across from 309 7EA4 $0
Partitions 3rd Floor Boys- across from 309 6EA2 $594
Urinals 3rd Floor Boys- across from 309 6EA5 $1,680
Walls - Structural Glazed Tile 3rd Floor Boys- across from 309 6SF611 $1,922
Walls - Structural Glazed Tile 3rd Floor Boys- across from 309 damaged5SF1 $64
Water Closet 3rd Floor Boys- across from 309 6EA2 $672
Accessories 3rd Floor Girls- Across from 307 6SF272 $2,509
Ceiling - Plaster/Drywall 3rd Floor Girls- Across from 307 6SF272 $941
Doors - Wood Doors inclu hw 3rd Floor Girls- Across from 307 6EA4 $1,204
Floor Drain 3rd Floor Girls- Across from 307 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 3rd Floor Girls- Across from 307 6SF272 $576
Lavatory 3rd Floor Girls- Across from 307 6EA3 $959
Lighting - Pendent/Surface 3rd Floor Girls- Across from 307 7EA4 $0
Partitions 3rd Floor Girls- Across from 307 6EA6 $1,782
Walls - Structural Glazed Tile 3rd Floor Girls- Across from 307 6SF708 $2,227
Water Closet 3rd Floor Girls- Across from 307 6EA7 $2,352
Accessories 3rd Floor Staff- Across from 307 6SF60 $553
Ceiling - Plaster/Drywall 3rd Floor Staff- Across from 307 6SF60 $208
Doors - Wood Doors inclu hw 3rd Floor Staff- Across from 307 6EA1 $301
Floor - Tile Ceramic/ Porcelain 3rd Floor Staff- Across from 307 6SF60 $127
Lavatory 3rd Floor Staff- Across from 307 cracks in porcelian5EA1 $1,590
Lighting - Lay-in 3rd Floor Staff- Across from 307 7EA1 $0
Lighting - Wall Mounted 3rd Floor Staff- Across from 307 7EA1 $0
Walls - Concrete Block 3rd Floor Staff- Across from 307 6SF270 $792
Walls - Concrete Block 3rd Floor Staff- Across from 307 cracks5SF5 $70
Water Closet 3rd Floor Staff- Across from 307 6EA1 $336
Accessories 3rd Floor, Women's Next to 311 There was no key to 312B, where this room is located. Asst Principal has only key & she was off for next 2 days. So rankings are assumed, based on identical restroom below (2nd Flr, Women's next to 211).
6SF82 $756
Ceiling - Plaster/Drywall 3rd Floor, Women's Next to 311 6SF82 $284
Doors - Wood Doors inclu hw 3rd Floor, Women's Next to 311 6EA1 $301
Floor Drain 3rd Floor, Women's Next to 311 6EA1 $1,059
Floor - Tile Ceramic/ Porcelain 3rd Floor, Women's Next to 311 6SF82 $174
Hand Dryer 3rd Floor, Women's Next to 311 6EA1 $230
Lavatory 3rd Floor, Women's Next to 311 6EA1 $320
Page 32 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Rooms (Other Than Classrooms)
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Restroom
Lighting - Lay-in 3rd Floor, Women's Next to 311 7EA1 $0
Walls - Concrete Block 3rd Floor, Women's Next to 311 6SF310 $909
Water Closet 3rd Floor, Women's Next to 311 6EA1 $336
Rooms (Other Than Classrooms) Subtotal: $233,837
Building: Addition
Category: Building Interior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Corridor
Ceiling - Lay-in 1st Floor in elevator hall6SF149 $447
Ceiling - Plaster/Drywall 1st Floor damaged- cracks & water damage5SF25 $436
Ceiling - Plaster/Drywall 1st Floor 6SF3,268 $20,235
Doors - Wood Doors include hw 1st Floor 6EA2 $602
Drinking Fountains - Single Fountain 1st Floor 6EA2 $551
Floor - Asphalt Floor 1st Floor by Gym5SF30 $106
Floor - Terrazzo 1st Floor 6SF1,862 $15,630
Floor - Tile Ceramic/ Porcelain 1st Floor in vestibule6SF72 $201
Floor - Tile/Sheet 1st Floor old tiles5SF1,329 $5,967
Floor - Tile/Sheet 1st Floor in elevator hall6SF149 $158
Lighting - Lay-in 1st Floor 7EA3 $0
Lighting - Pendent/Surface 1st Floor 7EA36 $0
Lighting - Wall Mounted 1st Floor 7EA2 $0
Walls - Concrete Block 1st Floor 6SF3,003 $8,803
Walls - Structural Glazed Tile 1st Floor 6SF2,491 $7,837
Ceiling - Lay-in 2nd Floor 6SF149 $447
Ceiling - Plaster/Drywall 2nd Floor cracks5SF25 $436
Ceiling - Plaster/Drywall 2nd Floor 6SF3,268 $20,235
Drinking Fountains - Single Fountain 2nd Floor 6EA3 $827
Floor - Terrazzo 2nd Floor 6SF200 $1,679
Floor - Tile/Sheet 2nd Floor new7SF3,242 $0
Lighting - Lay-in 2nd Floor 7EA3 $0
Lighting - Pendent/Surface 2nd Floor 7EA36 $0
Lighting - Wall Mounted 2nd Floor 7EA2 $0
Walls - Concrete Block 2nd Floor 6SF3,003 $8,803
Walls - Structural Glazed Tile 2nd Floor 6SF2,491 $7,837
Ceiling - Lay-in 3rd Floor in elevator hall6SF378 $1,135
Page 33 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Building Interior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Corridor
Ceiling - Plaster/Drywall 3rd Floor cracked5SF30 $523
Ceiling - Plaster/Drywall 3rd Floor 6SF1,642 $10,167
Doors - Steel Doors incl hw 3rd Floor 6EA2 $602
Drinking Fountains - Single Fountain 3rd Floor 6EA3 $827
Floor - Terrazzo 3rd Floor at North Stairs6SF100 $839
Floor - Tile/Sheet 3rd Floor new in elevator hall6SF378 $243
Floor - Tile/Sheet 3rd Floor Old tiles- down main hall5SF1,572 $7,059
Lighting - Lay-in 3rd Floor in elevator hall7EA6 $0
Lighting - Pendent/Surface 3rd Floor 7EA22 $0
Student Lockers - One Tier 3rd Floor 6EA101 $9,376
Walls - Concrete Block 3rd Floor 6SF1,656 $4,855
Walls - Concrete Block 3rd Floor cracked5SF4 $56
Walls - Structural Glazed Tile 3rd Floor 6SF1,611 $5,068
Safety
Camera Viewing Station Viewed in the Main office only6EA1 $683
Security Cameras 6EA3 $582
Security Cameras 6EA6 $1,164
Stairs
Ceiling - Plaster/Drywall North 6SF390 $2,855
Floor - Terrazzo North 6SF160 $1,343
Handrails North 6LF88 $763
Lighting - Pendent/Surface North 7EA4 $0
Stairs - Terrazzo North damaged nosing5LF10 $542
Stairs - Terrazzo North 6LF30 $278
Walls - Concrete Block North 6SF1,363 $3,996
Walls - Structural Glazed Tile North 6SF273 $859
Ceiling - Plaster/Drywall South 6SF150 $1,098
Floor - Terrazzo South 6SF74 $621
Handrails South 6LF48 $416
Lighting - Pendent/Surface South 7EA4 $0
Stairs - Terrazzo South nosing damaged5LF20 $1,085
Stairs - Terrazzo South 6LF20 $186
Walls - Concrete Block South 6SF594 $1,741
Walls - Structural Glazed Tile South 6SF119 $374
Vertical Conveyance
Elevator - Hydraulic Elevator 6EA1 $19,238
Page 34 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Building: Addition
Category: Building Interior
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Vertical Conveyance
Building Interior Subtotal: $179,815
Total Building Cost $1,820,433
SITE
Category: Site
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Athletic
Lighting Entire Site 5EA4 $22,936
Surface - Asphalt Entire Site 6SF12,143 $29,346
Civil/Drainage
Civil/ Drainage - Catch Basin Entire Site Location: Basket ball court, doesn't drain well5EA1 $2,570
Civil/ Drainage - Catch Basin Entire Site 6EA6 $6,563
Civil/ Drainage - Site Manhole Entire Site 7EA3 $0
Fencing
Fencing - Chain Link Entire Site 6LF248 $4,656
Fencing - New Standard Ornamental Entire Site 6LF1,502 $47,919
Landscape
Landscape - Grass Entire Site 6SF1,951 $1,618
Landscape - Hardscape- Asphalt Entire Site 6SF14,404 $34,810
Landscape - Hardscape- Concrete Entire Site 7SF773 $0
Parkway trees Entire Site 7EA44 $0
Planting Beds/ Area Entire Site 6SF4,549 $7,481
Play Area - Asphalt/ Hardscape Entire Site 6SF45,185 $109,199
Parking Lot
Surface - Asphalt NE Parking Lot 6SF19,484 $47,087
Surface - Concrete NE Parking Lot 6SF694 $1,677
Trash Enclosure - Chain Links NE Parking Lot 6SF636 $11,159
Playground
Equipment - School Age 5-12 Entire Site 7EA1 $0
Surface - Poured Surface Entire Site 6SF2,129 $15,588
Page 35 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
SITE
Category: Site
Item - Type Quantity Unit Rank Cost LocationGroup Comments
Sidewalks
Sidewalks - Internal Walks Entire Site 6LF167 $2,006
Sidewalks - Perimeter Sidewalks Entire Site 6SF10,915 $21,696
Signage
Flag Pole - Flag Pole Entire Site / Site - East 7EA1 $0
Marquee - Free Standing Back Lighted Entire Site / North West 7EA1 $0
Site Subtotal: $366,311
Total Site Cost $366,311
Campus Total ² ³
² As stated above, Total Assessed Campus Need does not include the addition of features not already in a particular facility, such as programmatic improvements, school-wide ADA compliance, air conditioning, space
reconfiguration or construction to alleviate overcrowding; these items are treated as separate capital needs. The Total Assessed Campus Need includes current deficiencies and is based on current unit cost estimates;
it does not reflect a complete project cost.
³ The overall condition of different items can change after an assessment date due to many variables, including newly occurring deficiencies, renovation or repairs and cost changes. These dollar figures in this report are
estimates only and are based solely on the data that was collected as of the assessment date in the footer below.
¹ It is very rare for assessors to find a feature in this condition. If assessors do, they are required to report it immediately to CPS, and CPS addresses it immediately. Thus, no features will be ranked “1” in this report; by the time the report is compiled, they have been resolved.
$4,999,035
Definitions
● Quantity
● Unit
means a basic estimate for each item needing some level of repair or replacement. Cost does not include all expenses that would be necessary to complete a repair or replacement project. This is because,
depending on the item and on the overall scope of a construction project, repair/replacement projects can include additional costs such as destructive testing, environmental needs, discovered conditions, and
additional work triggered by building codes.
means, for each item, the total number (or amount) of that item that exists and was evaluated.
means the generally accepted standard unit of measure for each item. Some items, like doors, are measured individually and use the unit of measurement “EA” for “each.” Other items, like
chimneys, are measured in terms of linear feet (“LF”). Still other items, like flooring, are generally measured in square feet (“SF”).
● Cost
● For the same reason, the Total Campus Need listed at the end of this report reflects only a portion of what it would actually cost to repair/replace all of the listed features.
● Campus Total also does not reflect features that do not yet exist at a particular facility, such as: programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration, or construction to
alleviate overcrowding; these are viewed as separate capital needs.
Page 36 of 37RYDER Assessment Date: 11/2/15
William H Ryder Math & Science Specialty ES8716 S Wallace St Chicago, IL 60620
Classroom Summary
Smart-
Board
Power
Strip
Window
Stop
Operable
Window
Area
Glazed
Window
Area
Noise
Level
Elect.
Outlets
Data
Outlets
Voice
Outlets
Area (SF)Floor Plan
Room
Number
Room
Number
Intended UsageCurrent Usage Room
Location
Main
YYY406090811919200200Regular ClassroomComputer Lab 2nd Floor
YYY4060901261919204204Regular ClassroomComputer Lab 2nd Floor
NYY404060811555205205Regular ClassroomFaculty Lounge 2nd Floor
NYY406090811919100100Regular ClassroomKindergarten 1st Floor
YYY4045904211919302302Regular ClassroomMusic Room 3rd Floor
NYY406090811919103103Regular ClassroomPre School 1st Floor
YYY406090811919201201Regular ClassroomRegular Classroom 2nd Floor
YYY406090811919203203Regular ClassroomRegular Classroom 2nd Floor
NYY404590811919300300Regular ClassroomRegular Classroom 3rd Floor
YYY404590811919301301Regular ClassroomRegular Classroom 3rd Floor
NYY4045904211919303303Regular ClassroomRegular Classroom 3rd Floor
YYY404590811919304304Regular ClassroomRegular Classroom 3rd Floor
YYY406090811919101101Regular ClassroomSpecial Education 1st Floor
YYY406090811919102102KindergartenSpecial Education 1st Floor
YYY406090811919202202Regular ClassroomStore Room 2nd Floor
Addition
YNY4044109641788213213Regular ClassroomArt Room 2nd Floor
NNY40571538511,043109109KindergartenKindergarten 1st Floor
YNY4044109662788313313Regular ClassroomMulti Purpose Room 3rd Floor
NYY4044109654788212212Regular ClassroomOffice 2nd Floor
YNY4044109651788207207Regular ClassroomOther Instructional Use 2nd Floor
YNY4044109652810210210Regular ClassroomOther Instructional Use 2nd Floor
NNY40571538511,043113113KindergartenPre School 1st Floor
YNY4044109651788208208Regular ClassroomRegular Classroom 2nd Floor
NNY4044109651810211211Regular ClassroomRegular Classroom 2nd Floor
YNY4044109641788307307Regular ClassroomRegular Classroom 3rd Floor
YNY4044109641792308308Regular ClassroomRegular Classroom
YNY4044109641792310310Regular ClassroomRegular Classroom 3rd Floor
YNY4044109641810311311Regular ClassroomRegular Classroom 3rd Floor
YNY40441092261788312312Regular ClassroomRegular Classroom 3rd Floor
YNY4044109641810309309Regular ClassroomScience Classroom 3rd Floor
YNY4044109641810209209Regular ClassroomStore Room 2nd Floor
Page 37 of 37RYDER Assessment Date: 11/2/15