Date post: | 23-Dec-2015 |
Category: |
Documents |
Upload: | margery-little |
View: | 218 times |
Download: | 0 times |
Wind in the UK – a growing market
Dr Gordon Edge
Director of Policy
RenewableUK
A word on who we are…
Wind starting to deliver
2004:250MW 2005:440MW 2006:630MW 2007:430MW2008:867MW2009:1,077MW
Operational wind farms
• 4,491MW– 3,450MW onshore– 1,041MW offshore
• 2,872 turbines
Ttt
H
H
H
H
H
H
H
H
L
K
Ttt
H
Wind farms under construction
• 1,656MW– 537MW onshore– 1,119MW offshore
• 614 turbinesH
H
H
H
H
H
Wind farms consented
• Considerable capacity consented but yet to start construction– 4,357MW onshore wind – 3,127MW offshore wind
• 13,600MW in total built, building or ready to build
The onshore planning logjam
• ~8,000MW of onshore capacity is built, building or ready to build
• However, nearly 20,000MW has entered the planning system since 2002
• ~2,500MW rejected• 7,700MW being held up in planning• Aviation issues a key problem
Moving ahead onshore
• Projects consented may still have barriers to delivery– Planning conditions may need to be discharged– Grid connections may still be awaited– Finance may not be in place
• Nonetheless, we anticipate delivery of ~1GW/year for the next five years– 2010 may see a dip in onshore delivery over 2009, mostly due to
finance issues
The UK has a healthy offshore pipeline
STW6.4 GW
Wind Farm Capacity (MW)
0
1000
2000
3000
4000
Installed UnderConstruction/Contracted
Consented Planned
10.000
20,000
47GW of leases in total…
Round3
32 GW
Extensions~ 1 – 2 GW
…But when are they delivered?
Near term delivery quite clear
Source: UK Offshore Wind: Staying on Track, report by Garrad Hassan for BWEA, June 2009
0
1
2
3
4
5
6
7
8
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Inst
alle
d ca
pac
ity G
W
Crown Estate
A healthy industry
Low case
Possible offshore delivery post-2015
Crown Estate
20% attrition, some projects delayed by 1 year
30% attrition, most projects delayed by 2 years
Installed in 2020:• High: 45GW; Medium: 24GW; Low: 14GW
Some uncertainties
• The Election– Unclear what effect a change of Government might have– May be changes in support mechanism, planning
• Implementation of ‘Connect & Manage’– Implications for connection, particularly in Scotland
• Implementation of the OFTO regime– Affects offshore projects particularly around 2013-16
• Charging for transmission services– Potential move to per MWh charges instead of per kW per year
So…
• Despite some uncertainty, the UK is moving to a market of:– ~1GW/year onshore, 2010-20– ~1GW/year offshore, 2010-15– ~3-4GW/year offshore, 2015-20
Let’s get to work!