Date post: | 24-Dec-2015 |
Category: |
Documents |
Upload: | melinda-gardner |
View: | 217 times |
Download: | 0 times |
Wind Energy Advantages of wind energy:
It is abundantly available everywhere and is free of cost.
A pollution free means of generating electricity
Reduces dependency on the non-renewable sources of energy.
Low cost when compared to other clean sources of energy.
US and wind energy:
According to reports of the American Wind Energy Association, wind energy accounts for 31% of the newly generated capacity installed over the 5 years. 2009-13.
Wind Energy and Future Prospects.
Wind Penetration Level refers to the fraction of energy produced by wind compared to the total generating capacity of a nation.
As of 2011, US had a penetration level of 3.3% which is expected to rise to 15% by 2020.
With such high penetration levels, the wind energy integration in the grid has to be highly reliable and uniform.
However, the variability of winds causes a major problem in efficient forecasting and distribution of the power.
Problem Introduction• Reliable power systems require a balance
between demand load and generation within acceptable limits. • supply and demand shocks create power surges
• Wind energy generation cannot be forecasted with sufficient accuracy due to the inherent variability of the wind.
• The variability makes wind a poor energy source.
Problem Scope and Objective
• To schedule the distribution of wind power generated at a farm into the city grid.
• The objective is to maximize profits which comes from providing energy per watt.
• There is a penalty imposed for non uniform power distribution.
• An external battery is provided which can be used to smoothen the non uniform generation by absorbing/supplying in cases of excess/shortage of power generation.
Assumptions• The wind power forecasting has been done assuming
Uniform, Normal and Wiebull distributions.
• Each unit of power supplied results in $1 profit.
• Penalty of $10 is imposed if the power input to the grid changes by more than 5 units between two consecutive time frames.
• Battery used has a capacity of 100 units of power.
• The rate at which the battery can accept or deliver electrical energy is unrestricted.
• Wind power is measured only at discrete time intervals.
Ramp RateRamp rate is defined as the difference
consecutive power outputs.
∆(x_t,x_t-1)<R in discrete time
∂x/∂t<R in continuous time
For smooth distribution of power, this ramp rate is limited by a quantity R. Violation of this limit is subjected to a penalty.
• Our objective is to maximize profits by reducing the ramp rate violations over a given time period T.
Model FormulationWind is a stochastic process W(t) with output Power
In our model Power goes between [0,100]
Battery has Battery capacity, current Battery used
System decides how much goes to the grid
The rest goes to Battery
Any remaining power that cannot be stored by the battery is lost
S (W(t), X_t-1, Bcap, Bused_t-1, R) outputs X_t
Mathematical FormulationSchedule Outputs To maximize Profit
Max ∑c(X_t)
S.T. ∑({abs(∆X_t)>R}/n < PBused_t-1+W(t) – X_t > 0
The solution to this problem would allow us to build optimal size batteriesUse wind much more efficiently
Ways to Solve (I)Dynamic Programming
This proves difficult because of state dependency,
nonviolation today drains a battery which might cause state violation tomorrow
Ways to Solve (II)Lagrangian Convex Optimization
Relax the Constraint but impose a penalty and maximize the profit
Check the Constraint if probability is low Decrease penaltyIf Probability of violation is highIncrease penalty
Each iteration of Lagrangian takes a long time
There is no way to know how quickly you converge
Ways to Solve (III)Markov Decision Process
Find stationary probabilities that maximize the profit
The issue is that the decision in our problem is continuous
Since X_t [0, Battery used + W(t)]
So you would need to discretize outputs otherwise this problem is infinitely large
Our MethodUse to simulation and
heuristics to establish Lower Bounds on profit
Upper Bounds are easily established by taking Expectation of the W(t) over [0,T]
Performance (uniform)
0 10 25 50 75 100 500 10000
10000
20000
30000
40000
50000
60000Profit vs Battery capacity (Uniform wind
distribution)
Conserva-tive
Battery Capacity (percent of the max wind)
Profit ($)
Violation (uniform)
025 75
500
0
5
10
15
20
Conservative
Percent Violation (uniform distributed wind)
Conservativegreedy
Battery Capacity
Percent Violation
Hybrids (Normal(50,50)
0 10 25 50 75 100 500 10000
10000
20000
30000
40000
50000
60000
Profit vs Battery capacity (normal)Conservative
Greedy
Hybrid
hand off
Target 30
Smart Target 30
Battery Capacity (percent of the max wind)
Profit ($)
Violations
0 10 25 50 75 100 500 10000
5
10
15
20
25
30
35
40
45
50
Percent Violation (normally distributed wind)
Conservative
greedy
hand off
Hybrid
Target 30
Smart Target 30
Battery Capacity
Percent Violation
Solving Weibull
0 10 25 50 75 100 500 10000
5000
10000
15000
20000
25000
30000
Profit vs Battery capacity (Weibull wind)
Conservative
Greedy
target 25
Smart Target 25
Smart Target 30
Battery Capacity (percent of the max wind)
Profit ($)
Percent Violation (Weibull)
0 10 25 50 75 100 500 10000
10
20
30
40
50
60
Percent Violation (uniform distributed wind)
Conservative
greedy
target 25
Smart Target 25
Smart Target 30
Battery Capacity
Percent Violation
ConclusionsFinding a Lower Bound Heuristic is Useful.
Unfortunately it is not a simple task.
It is more feasible to focus on creating a Heuristic for one situation
This problem remains difficult but finding a Lagrange that does better than our Heuristic is still possible and that can teach us a lot about the problem