Workplace Modernization ProjectWMP Update & Construction Phasing Plan
Phase Breakdown
Workplace Modernization ProjectAgenda
Department Impacts & Mitigation
Schedule
Questions
Project Status Update
Workplace Modernization ProjectProject Status Update
Package 1 (4th and 5th Floor) –Design Development
Package 1 Tender – August 2021 Construction October 2021 to July 2023
Construction phasing & mitigation planning
Standardization of technology
Workstation booking software –Interface development & pilot
1500 Hopkins Street (Swing Space) – Construction Underway
3rd Floor interim space – Construction DocumentsConstruction commence July 2021
General Contractor Prequalification closing April 6th
Workplace Modernization ProjectProposed Construction Schedule – Phase 1A
Impacted Departments
• Corporate Training
Estimated Schedule
July 2021 - September 2021 (3 Months)
PHASE 1A
3rd Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1A
Impacted Departments
• Corporate Training
Estimated Schedule
July 2021 - September 2021 (3 Months)
PHASE 1A
3rd Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1B & 1C
TEMPORARY FILING
5th Floor
Impacted Departments
• Economic Development
• Corporate Communications
• Strategic Initiatives
• Facilities DCAM
Schedule
Mid August - October 2021 (3 months)
Workplace Modernization ProjectProposed Construction Schedule – Phase 1B & 1C
Impacted Departments
• Works
• CAO & Regional Chair’s Office
• Transit
• Economic Development
• Facilities DCAM
Schedule
October 2021 - October 2022 (12 Months)
PHASE 1B
5th Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1B & 1C
Impacted Departments
• Temporary Filing
Schedule
July 2022-October 2022 (4 months)
PHASE 1C
5th Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1B & 1C
Works, CAO & Regional Chair’s Office targeted to
move in to new space October 2022!
5th Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1D & 1E
TEMPORARY FILING & STORAGE
4th Floor
Impacted Departments
• DCAM (Phase 1A)
• Finance (Risk & Insurance)
Schedule
February - April 2022 (3 months)
Workplace Modernization ProjectProposed Construction Schedule – Phase 1D & 1E
Impacted Departments
• Finance
Schedule
April 2022- February 2023 (11 Months)
PHASE 1D
Finance targeted to move in to new space
February 2023
4th Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1D & 1E
PHASE 1E
Impacted Departments
• Planning
Schedule
December 2022- July 2023 (8 Months)
4th Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1D & 1E
Planning & Economic Development, Transit & DCAM targeted to move
in to new space July 2023
4th Floor
Workplace Modernization ProjectProposed Construction Schedule – Phase 1
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR2021 2022 2023
Phase 1A3rd Floor
Corporate Training
Phase 1B5th Floor
Phase 1C5th Floor (cont.)
Phase 1DFinance
Phase 1EPlanning
* Schedule is tentative only & will need to be coordinated with the procured General Contractor.
APR MAY APR MAY
Move into temporary facilities4-6 weeks
Packing4 weeks
Clean-up Central Files8-12 weeks
Clean-up Individual Files6-10 weeks
Construction
JUN
Preliminary Clean-up of Individual Files
MAR
Workplace Modernization ProjectQuestions?