Works for construc on of the road sec on Norra Lanken
2007-SE-12090-P • Part of Priority Project 12
This project, as part of the Nordic Triangle railway/road axis (Priority Project 12), concerns Norra Länken, the northern link of the ring road (E20) of Stockholm. It encompasses approximately 11 km between Norrtull and Värtan (Frihamnen/Värta-
hamnen) and consists mainly of the execu on of nine concrete or rock tunnels and an interchange in Värtan, supplemented by the necessary traffi c management and telecommunica ons installa ons.
The project will lead to a be er quality infrastructure, safer and more effi cient transport, and a be er mul modal link between road and sea. Access and mobility will also improve due to increased road network capacity through the dual tunnel and surface road sec on. Road safety will also be improved thanks to the diversion of vehicles into tunnels in which there is no oncoming traffi c.
The Mid-Term evalua on confi rmed the very good progress made so far by the project, which can be recommended as a model. The main reasons for this progress lie in the robust monitoring system in place, the well performing risk management mechanism, as well as the long term strategy for effi ciency and results. Good performance has also been no ced in minimis-ing the environmental impact of the project. The project is expected to be completed in 2013 in line with the original plans.
Commission Decision:C(2008)7910Member States involved:Sweden
Implementa on scheduleStart date: June 2007End date: December 2013Es mated end year: 2013
Budget: Total project cost: €986,000,000EU contribu on: €56,150,000 Na onal budget: €929,850,000
Percentage of EU support: Works: 5.69%
The Mid Term evalua on confirmed the very goo
MAP Review
89
Works for construc on of the road sec on Norra Lanken
2007-SE-12090-P • Part of Priority Project 12
MAP Review
*Rounded fi gures
986.0
1,009.21,009.2
0
200
400
600
800
1,000
1,200
End2010
End2011
End2012
End2013
Planned, updated and revised cumulative costs (€ Million)*
Planned costs (Decision) Revised costs (MAP review) Updated costs (as reported by the beneficiary)
56.2
56.2
0
10
20
30
40
50
60
End2010
End2011
End2012
End2013
Planned and revised cumulative TEN-T contribution (€ Million)*
Planned TEN-T contribution (Decision) Revised planned TEN-T contribution (MAP review)
When the updated plans are confi rmed by the review, the curve of the updated costs reported by the benefi ciary overlaps the curve of the revised costs (MAP review)For comparison purposes, the updated and revised cost es mates are based on the exchange rate in force at the me of the Decision
90