+ All Categories
Home > Documents > Workshop #1 – Project Update Cunningham Center July 16, 2008.

Workshop #1 – Project Update Cunningham Center July 16, 2008.

Date post: 18-Dec-2015
Category:
Upload: clifford-blake
View: 214 times
Download: 0 times
Share this document with a friend
Popular Tags:
12
Workshop #1 – Project Update Cunningham Center July 16, 2008
Transcript
Page 1: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Workshop #1 – Project UpdateCunningham Center

July 16, 2008

Page 2: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Update Topics

• Review of the Workshop Agenda• The Elements of Project STEADI• Project Mission, Scope and Organization• Deliverables• Project Strategy and Timeline• Project Update• Conclusions

Page 3: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Workshop Agenda9:00 -- 9:15 Welcome and Introduction Dr. Carmen Cavezza9:15-- 9:30 Project Status Overview PM, John Fuller9:30 – 10:00 Modeling and Simulation: COL Mike Obermeyer

Soldier Battle Lab10:00--10:15 “Checkpoint”--A Simulation Duane Slaughter10:15—10:30Solar System—A Simulation Dr. Rodrigo Obando10:30—10:45 Break10:45—11:15 M&S Curriculum Strategy Dr. Wayne Summers11:15– 11:45 First Course Dr. Rodrigo Obando11:45—12:45Lunch and Guest Speaker Blanchard B

MCOE Simulation Challenges Dr. James Mowery12:45---1:00 Break1:00—2:00 The VMASC Experience Dr. Roland Mielke2:00 – 2:45 Panel John Fuller2:45 –3:00 Opportunities and Wrap Up John Fuller

Page 4: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Meeting Handouts

• Agenda• Biographies on Speakers• Survey• Letter• Evaluation

Page 5: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Project Scope

• Complete a market study to the determine specific modeling and simulation technology need: skills, knowledge and abilities

• Develop a curriculum at CSU to support the modeling and simulation technology need

• Conduct vision trips to view working models• Hire and / or train CSU faculty to teach the curriculum• Recruit students to enter the curriculum program• Conduct workshops to educate the community on the

project and status of the project• Establish student internships to support the new program• Establish a website to support the communication needs

of and promote Project STEADI

Page 6: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Project MissionTo produce the first course within a modeling and

simulation track within the Master of Science Degree in Applied Computer Science and complete all other elements of Project STEADI on time and within budget

Page 7: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Project Organization

Page 8: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Project Deliverables• VMASC Capstone Conference• Market Study • Two Vision Trips• Two Business Education Workshops• Operational Website• Curriculum Marketing Plan • Internship Program Established• First M&S Course Developed

Page 9: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Major Activities and Project Timeline

Activity Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Market Study

Faculty Training at Capstone Conf.

Curriculum Development

Website Development

Vision Trips

Business Education Seminars

Marketing Curriculum and Recruiting

Student Internship Program

Page 10: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Project STEADI Update

PROJECT OBJECTIVE STATUS

Market Study GT Study complete; ICAPP Funded Study due 8/31/08

Vision Trips Two complete; Two Pending

Web Site Operational; but will continue as a work in progress

Internships First one signed with Omega; to start in September

Promote and Market Media, Marketing and More drafted marketing plan

Educate the Faculty VMASC visit complete; Dr. Mielke is our consultant

Workshops This is the first; the second will be the first annual symposium

Develop Curriculum First Course to be introduced in January 2009 (Spring semester)

Page 11: Workshop #1 – Project Update Cunningham Center July 16, 2008.

Conclusions

• Mission is being accomplished on time and within budget

• Eight elements of Project STEADI being delivered on time and within budget

• Requirements of the Project are being exceeded in virtually all elements—all within budget constraints

• Opportunities abound for all stakeholders!