Date post: | 16-Jan-2016 |
Category: |
Documents |
Author: | morris-hoover |
View: | 215 times |
Download: | 0 times |
SM18 Test FacilityA. Siemko"Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
AT/MTM
Outline
Expected Hardware Commissioning And Machine Exploitation Needs
Expected MAR Project Needs
Teams to perform the cold tests1st estimate of infrastructure needs
Conclusions
AT/MTM
SM18 Test Facility at present in future The series tests of the LHC magnets in SM18 test facility are expected to be completed beginning 2007.
The test facility will then be modified to support the accelerator exploitation.
AT/MTM
Hardware Commissioning And Machine Exploitation NeedsDuring hardware commissioning and further machine exploitation there will be intermittent (most probably) need to replace cryo-magnets due to:
Performance failures Cryo and vacuum integrityElectrical integrityQuench performance
Beam-related accidents
AT/MTM
Hardware Commissioning And Machine Exploitation NeedsDuring hardware commissioning and machine exploitation there will be recurrent need to test and retest the spare magnets
Qualification of newly assembled magnet units (MS and DS)
Qualification of magnets after repair
Retest after long duration storrage
AT/MTM
Hardware Commissioning And Machine Exploitation NeedsExtended performance studies will have to be performed - as it is expected - at the request of the AB teams and AT equipment owners
Extended Performance Studies Quench performance studies Electrical integrity studies Cryo and vacuum integrity studiesMagnetic field performance studies
AT/MTM
Hardware Commissioning And Machine Exploitation NeedsQuench Performance Studies not performed during the series testsQuench performance limitation due to the beam losses Quench performance limitation due to the cooling limitations Re-assessment of the performance if questionable during hardware commissioning and exploitation
AT/MTM
Hardware Commissioning And Machine Exploitation NeedsElectrical Integrity Studies
Long term stability and limitation Reproduce at laboratory level issues encountered in the machine. Study solutions.R&D on new diagnostic techniques
Cryo-Integrity Studies not performed during the series testsThermal tests: heat loads - static vs. dynamic, efficiency etc.Mechanical studies to assess the mechanical and vacuum limitations
AT/MTM
Hardware Commissioning And Machine Exploitation NeedsExtended Magnetic Field Performance Studies Precision transfer function measurementsImpact of powering history on field qualityStability of harmonics Stability of field direction vs. mechanical stabilityDynamic effects Cold alignmentCorrectors performance and alignment
R&D on new magnetic measurement techniques
AT/MTM
Expected MAR Project NeedsStandard performance tests and measurements will have to be performed on newly assembled magnets and magnets after repair Certification or re-certification of magnets before installation
Extended performance studies at request of equipment owners
AT/MTM
Particular issues related to different magnet typesArc magnetsSpare policy:Substantial number of spares will be available at startup of LHCBut:Knowledge of magnet performance towards efficient commissioning and reaching the LHC nominal luminosity is limited.Need to perform extended performance tests on a number of spare magnetsField quality FAME for FIDEL Power tests beam induced quench levels
Expected at present rate of magnets to be repaired and re-qualified for the tunnel use seems to be very limited
AT/MTM
Particular issues related to different magnet typesInsertion magnetsSpare policy:Spare magnets and all other components are available to cover the needs of one Dispersion Suppressor (3 units) and one Matching Section (4 units). Any SSS from Q4 to Q10 can be assembled and replaced. Expected production duration of a new unit at best in 4-6 weeks.Almost all individual spare magnets will be cold tested in B4
In case of performance failure in the machine the insertion magnets will stay on the critical path for the HC and operation
We will need an efficient rescue and cold test facility operational all time during commissioning and accelerator exploitation
AT/MTM
Test of magnets after repair Radioprotection issuesA designated cluster which permits to work with the risk of exposure must be allocated and equipped for the purpose of retesting of the activated magnets (subject not studied yet)
Protection of the personnel Protection of the environment
Monitoring of the dose rates Local shielding
Use of personal protective equipmentAll personnel must be trained for this specific work
AT/MTM
Cold tests of Separation Dipoles and Low- QuadsAdaptation/modification of the test benches needs to be studied
AT/MTM
Equipment Dedicated to Separation Dipoles and Low- Quads
Dedicated test Equipment for Separation Dipoles and Low- Quads needs to be studied
AT/MTM
Teams to perform the cold testsAt present
Transport, preparation of magnets, their installation on the test benches and removal work is presently executed by external contractor (ICS)
Cryogenic test preparation and operation is presently executed by external contractor (ALLS)
Routine cold tests and measurements are presently executed exclusively by external Indian collaborators and temporarily detached AB operators
Special tests and measurements are assured by MTM and ACR experts
AT/MTM
Teams to perform the cold testsIn future
The external contractors know-how and relevant tooling must be re-in sourced to CERN teams (plus associated FSUs) before the end of the present contracts
Key CERN experts should be identified and/or trained (mechanical, electrical, electro-mechanical, vacuum, cryogenics technicians). Know-how transfer from US Labs should be included
The competence of the CERN cold test expert technicians and engineers should be preserved and integrated in the future extended performance tests and/or repair and retest activities
Cryo operation from CCC needs to be studied
AT/MTM
1st estimate of infrastructure needs - proposal8 stands ought to be available for testing any of the LHC arc and insertion magnet sets
1 stand for MB/Arc SSS power tests (existing)
1 stand for DS/MS power tests (existing)
1 stand for Separation dipoles (adaptation/modification to be studied)
1 stand for Low-b quadrupoles (adaptation/modification to be studied)
2 stands for magnets with the risk of exposure (adaptation/modification to be studied)
2 stands for FAME project (existing)
AT/MTM
1st estimate of infrastructure needs - proposalIt is economically favorable to maintain the present size of the SM18 magnet test facility rather then to decommission part of it
Remaining test stands can be put on stand-by to be ready for:Unforeseen major retest needs,GSI magnet tests?Planned OSQAR experiment.LHC upgrade programmesPossible SPS/PS supra upgrade
AT/MTM
AT/MTM
Conclusions SM18 test facility can fulfill all major cold test needs of LHC magnets related to:
MAR Project and also for the LHC exploitation
Required resources must still be defined in details and .allocated
AT/MTM