+ All Categories
Home > Documents > Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement...

Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement...

Date post: 16-Jan-2016
Category:
Upload: morris-hoover
View: 216 times
Download: 0 times
Share this document with a friend
Popular Tags:
21
Workshop 12/04/2006 AT/MTM SM18 Test Facility SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Transcript
Page 1: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

Workshop 12/04/2006

AT/MTM

SM18 Test FacilitySM18 Test Facility

A. Siemko

"Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

Page 2: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

OutlineOutline

Expected Hardware Commissioning And Machine Exploitation Needs

Expected MAR Project Needs

Teams to perform the cold tests 1st estimate of infrastructure needs

Conclusions

Page 3: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

The series tests of the LHC magnets in SM18 test facility are expected to be completed beginning 2007.

The test facility will then be modified to support the accelerator exploitation.

SM18 Test Facility at present in future SM18 Test Facility at present in future

Page 4: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Hardware Commissioning And Hardware Commissioning And Machine Exploitation NeedsMachine Exploitation Needs

During hardware commissioning and further machine exploitation there will be intermittent (most probably) need to replace cryo-magnets due to:

Performance failures Cryo and vacuum integrity Electrical integrity Quench performance

Beam-related accidents

Page 5: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Hardware Commissioning And Hardware Commissioning And Machine Exploitation NeedsMachine Exploitation Needs

During hardware commissioning and machine exploitation there will be recurrent need to test and retest the spare magnets

Qualification of newly assembled magnet units (MS and DS)

Qualification of magnets after repair

Retest after long duration storrage

Page 6: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Hardware Commissioning And Hardware Commissioning And Machine Exploitation NeedsMachine Exploitation Needs

Extended performance studies will have to be performed - as it is expected - at the request of the AB teams and AT equipment owners

Extended Performance Studies Quench performance studies Electrical integrity studies Cryo and vacuum integrity studies Magnetic field performance studies

Page 7: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Hardware Commissioning And Hardware Commissioning And Machine Exploitation NeedsMachine Exploitation Needs

Quench Performance Studies not performed during the series tests

Quench performance limitation due to the beam losses Quench performance limitation due to the cooling

limitations

Re-assessment of the performance if questionable during

hardware commissioning and exploitation

Page 8: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Hardware Commissioning And Hardware Commissioning And Machine Exploitation NeedsMachine Exploitation Needs

Electrical Integrity Studies

Long term stability and limitation Reproduce at laboratory level issues encountered in the

machine. Study solutions. R&D on new diagnostic techniques

Cryo-Integrity Studies not performed during the series tests

Thermal tests: heat loads - static vs. dynamic, efficiency etc. Mechanical studies to assess the mechanical and vacuum

limitations

Page 9: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Hardware Commissioning And Hardware Commissioning And Machine Exploitation NeedsMachine Exploitation Needs

Extended Magnetic Field Performance Studies Precision transfer function measurements Impact of powering history on field quality Stability of harmonics Stability of field direction vs. mechanical stability Dynamic effects Cold alignment Corrector’s performance and alignment

R&D on new magnetic measurement techniques

Page 10: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Expected MAR Project NeedsExpected MAR Project Needs

Standard performance tests and measurements will have to be performed on newly assembled magnets and magnets after repair Certification or re-certification of magnets before

installation

Extended performance studies at request of equipment owners

Page 11: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Particular issues related to Particular issues related to different magnet typesdifferent magnet types

Arc magnets Spare policy:

Substantial number of spares will be available at startup of LHC But:

Knowledge of magnet performance towards efficient commissioning and reaching the LHC nominal luminosity is limited.

Need to perform extended performance tests on a number of spare magnets

Field quality – FAME for FIDEL Power tests – beam induced quench levels

Expected at present rate of magnets to be repaired and re-qualified for the tunnel use seems to be very limited

Page 12: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Particular issues related to Particular issues related to different magnet typesdifferent magnet types

Insertion magnets Spare policy:

Spare magnets and all other components are available to cover the needs of one Dispersion Suppressor (3 units) and one Matching Section (4 units). Any SSS from Q4 to Q10 can be assembled and replaced. Expected production duration of a new unit at best in 4-6 weeks.

Almost all individual spare magnets will be cold tested in B4

In case of performance failure in the machine the insertion magnets will stay on the critical path for the HC and operation

We will need an efficient rescue and cold test facility operational all time during commissioning and accelerator exploitation

Page 13: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Test of magnets after repair Test of magnets after repair Radioprotection issuesRadioprotection issues

A designated cluster which permits to work with the risk of exposure must be allocated and equipped for the purpose of retesting of the activated magnets (subject not studied yet)

Protection of the personnel Protection of the environment

Monitoring of the dose rates Local shielding

Use of personal protective equipment All personnel must be trained for this specific work

Page 14: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Cold tests of Separation Dipoles Cold tests of Separation Dipoles and Low-and Low-ββ Quads Quads

Adaptation/modification of the test benches needs to be studied

Page 15: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Equipment Dedicated to Separation Equipment Dedicated to Separation Dipoles and Low-Dipoles and Low-ββ Quads Quads

Dedicated test Equipment for Separation Dipoles and Low-β Quads needs to be studied

Page 16: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Teams to perform the cold testsTeams to perform the cold tests

At present

Transport, preparation of magnets, their installation on the test benches and removal work is presently executed by external contractor (ICS)

Cryogenic test preparation and operation is presently executed by external contractor (ALLS)

Routine cold tests and measurements are presently executed exclusively by external Indian collaborators and temporarily detached AB operators

Special tests and measurements are assured by MTM and ACR experts

Page 17: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Teams to perform the cold testsTeams to perform the cold tests

In future

The external contractor’s know-how and relevant tooling must be re-in sourced to CERN teams (plus associated FSU’s) before the end of the present contracts

Key CERN experts should be identified and/or trained (mechanical, electrical, electro-mechanical, vacuum, cryogenics technicians). Know-how transfer from US Labs should be included

The competence of the CERN cold test expert technicians and engineers should be preserved and integrated in the future extended performance tests and/or repair and retest activities

Cryo operation from CCC needs to be studied

Page 18: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

11stst estimate of infrastructure estimate of infrastructure needs - proposalneeds - proposal

8 stands ought to be available for testing any of the LHC arc and insertion magnet sets

1 stand for MB/Arc SSS power tests (existing)

1 stand for DS/MS power tests (existing)

1 stand for Separation dipoles (adaptation/modification to be studied)

1 stand for Low-b quadrupoles (adaptation/modification to be studied)

2 stands for magnets with the risk of exposure (adaptation/modification to be studied)

2 stands for FAME project (existing)

Page 19: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

11stst estimate of infrastructure estimate of infrastructure needs - proposalneeds - proposal

It is economically favorable to maintain the present size of the SM18 magnet test facility rather then to decommission part of it

Remaining test stands can be put on stand-by to be ready for: Unforeseen major retest needs, GSI magnet tests? Planned OSQAR experiment. LHC upgrade programmes Possible SPS/PS « supra » upgrade

Page 20: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

Possible SM18 layout after series tests

Activated magnets

DS/MSLow-β

Sep. Dip.

MB/SSS power tests

FAME

A

B

C

D

E

F

OSQAR Exp.

FAME

Page 21: Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"

A. Siemko AT-MTM Workshop – 12 April 2006

ConclusionsConclusions

SM18 test facility can fulfill all major cold test needs of LHC magnets related to:

MAR Project and also for the LHC exploitation

Required resources must still be defined in details and ….allocated


Recommended