Workshop Proceedings
WENRA Workshop on Regulatory Aspects of Decommissioning
Berlin, 5-7 November 2019
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
2
Contact:
Stefan Theis (chair of WENRA WGWD) [email protected]
Matthias Hackstein (local organizer BMU) [email protected]
Sven Keßen (rapporteur) [email protected]
http://www.wenra.org/decom2019/
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
3
Welcome Address by Svenja Schulze (Federal Minister for the Environment, Nature Conservation and Nuclear Safety,
Germany)
Ladies and gentlemen,
In recent years, WENRA’s importance has steadily grown.
In addition to the original western European countries,
e.g. Ukraine, Russia, Canada and Japan are today also
represented in WENRA. This shows that WENRA’s work is
widely recognised and valued, even far beyond Europe’s
borders.
The large number of international participants in this
workshop highlights the growing interest around the
world in WENRA’s activities: more than 20 countries are
represented here today. This allows us to have an
intensive dialogue across national borders, which is
crucial for a sound set of rules and regulations on the
decommissioning of nuclear power plants. I am delighted
to have all of you here today.
As you know, Germany is phasing out nuclear power. The safety of our nuclear power plants has to be
guaranteed up to the very last day of operation. However, operators must continue to ensure the
highest possible level of safety during post-operation, decommissioning and dismantling of nuclear
power plants. I am therefore glad that this important issue is addressed in the workshop.
I believe that the international exchange of ideas contributes significantly to enhancing nuclear safety
around the world. Even though Germany is phasing out nuclear energy, it will continue to take on an
active role in the ongoing development and improvement of nuclear safety. I can assure you that my
colleagues and I will play a constructive part in this process also in the future. We are looking forward
to continuing our close cooperation.
Yours sincerely,
Svenja Schulze
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
4
Table of Contents
Welcome Address
by Svenja Schulze, Federal Minister, BMU, Germany ___________________________________ 3
Table of Contents _________________________________________________________________ 4
Site visit at Greifswald NPP decommissioning project _____________________________________ 6
Opening Session __________________________________________________________________ 9
WENRA Introduction
(Mina Golshan, ONR, United Kingdom) _______________________________________________ 9
International Safety Standards as a basis for the development of national regulations for
decommissioning (Nelli Aghajanyan, IAEA) __________________________________________ 11
Regulatory Aspects in Decommissioning: Experiences in Germany and Outlook
(Wolfgang Cloosters, BMU, Germany) ______________________________________________ 12
WENRA WGWD – How the SRLs work
(Stefan Theis, ENSI, Switzerland, Chair of WENRA WGWD) ______________________________ 13
WENRA WGWD – How SRLs are implemented and how “newcomers” benefit
(Tamara Suschko, SNRI, Ukraine) __________________________________________________ 14
Session 1: Decommissioning Strategies and Planning____________________________________ 15
Development of Rostechnadzor recommendations for planning of decommissioning during
operation of nuclear facilities (Danila Savin, SEC NRS) _________________________________ 16
The need for a sustainable decommissioning paradigm
(Kristina Gillin, Lloyd’s Register) ___________________________________________________ 17
Waste management and decommissioning strategies
(Vincent Cloître, Dorothée Conte, ASN, France) _______________________________________ 18
Graded approach of regulation for decommissioning – Considerations on the concepts: risk
informed, cost benefit analysis and reasonably practicable (Alain Ensuque, ENISS) __________ 19
Session 2: Regulatory Experience ___________________________________________________ 21
Inspection practice for NPP in decommissioning
(Theo Neuffer, UM BW, Germany) _________________________________________________ 22
Enabling Regulation – The Operator’s View
(Phil Hallington, Sellafield Ltd) ____________________________________________________ 23
Decommissioning authorization process and controls in Italy
(Fabrizio Trenta, ISIN, Italy) _______________________________________________________ 24
Authorization for and regulatory control of decommissioning in Sweden
(Martin Amft, Christoffer Forss, SSM, Sweden) _______________________________________ 25
Licensing Procedure and Inspection Fields in Decommissioning of Swiss NPP
(Klaus Germerdonk, ENSI, Switzerland) _____________________________________________ 26
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
5
Session 3: Limits of Harmonization and Specific Approaches ______________________________ 27
Harmonization challenges during WGWD benchmarking
(Stefan Theis, ENSI, Switzerland, Chair of WENRA WGWD) ______________________________ 28
Site decommissioning by dedicated decommissioning licensee: a US approach
(Corey DeWitt, Holtec) __________________________________________________________ 29
Decommissioning of the MZFR
(Ulrich Scholl, KTE) ______________________________________________________________ 30
Digitalization for Knowledge Management in Decommissioning
(Joaquin Toubes Tova, Tecnatom) _________________________________________________ 31
Session 4: Transition from Operation to Decommissioning _______________________________ 33
EDF Energy Planning for Decommissioning during Operation
(Jim Kershaw, EDF Energy) _______________________________________________________ 34
Lithuanian regulatory policy, challenges and activities during transitional period from operation
to decommissioning of Ignalina NPP (Saulius Stravinskas, VATESI, Lithuania) _______________ 35
The Development of Transition Period Requirements in the Slovak Republic
(Miroslav Drahos, UJD, Slovak Republic) _____________________________________________ 36
NEA Regulators’ Forum – Outcomes of RF/WPDD Workshop on Regulation of Decommissioning
(Mario Dionisi, ISIN, Italy; Martin Brandauer, NEA) ____________________________________ 37
Session 5: Final Stages of Decommissioning ___________________________________________ 39
End state requirements for waste and site
(Henrik Efraimsson, Åsa Zazzi, Martin Amft, SSM, Sweden) ______________________________ 40
Immediate dismantling and complete clean-out principles
(Coralie Ravier, ASN, France; Patrice François, IRSN) ___________________________________ 41
Recent developments in the regulation of UK nuclear sites in the final stages of
decommissioning & clean-up (Simon Morgan, ONR, United Kingdom) _____________________ 43
Closing Remarks
by Stefan Theis, ENSI, Switzerland, Chair of WENRA WGWD _____________________________ 44
Appendix A: Workshop Agenda _____________________________________________________ 46
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
6
Site visit at Greifswald NPP decommissioning project
On 5 November, the day before the start of the Berlin workshop, participants of the workshop travelled
to Greifswald to visit EWN Entsorgungswerk für Nuklearanlagen GmbH (EWN). The company is located
at the site of former Greifswald NPP, East Germany’s largest nuclear power plant at its time and
projected then to consist of 8 units. 4 of them were operational in 1990, unit 5 had begun with trial
operations. After German reunification and the subsequent shutdown of all East German NPPs, EWN
was founded as a publicly owned company for the decommissioning of these NPPs. Today, EWN group
is also tasked with the decommissioning of the prototype pebble-bed reactor in Jülich and the pilot
reprocessing plant in Karlsruhe, both in the Western part of Germany. The technical tour was organised
by BMU and EWN, and staff of EWN was cordially guiding the participants around, after Gudrun
Oldenburg of EWN had given an overview of the site’s history and layout, followed by a lively discussion
with the participants.
To facilitate the decommissioning of the East German NPPs, EWN constructed an extensive
infrastructure for the processing and storage of radioactive waste at the Greifswald site. The Interim
Storage Facility North (ISN), in particular, encompasses eight halls for the storage of spent fuel and
heat-generating as well as low and medium level radioactive waste, a total of 585 tons of spent fuel
and vitrified waste and ca. 27,000 tons of other radioactive material. To ensure the continued safe
storage of the spent fuel and heat-generating radioactive waste until the availability of a disposal
facility for these waste types, a new storage facility (called ESTRAL) is in the process of commissioning
next to the current ISN building. Low and medium level waste are, for the most part, foreseen to be
disposed of in the Konrad disposal facility, with its projected start of operation in 2027.
View of the steam generator within unit 6 of former Greifswald NPP © EWN GmbH
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
7
At the site, the participants had the opportunity to get a close look at the decommissioning of unit 6
of Greifswald NPP. Before cancellation of the project in 1989, the unit’s construction was almost
finished, but was stopped before nuclear fuel had been loaded into the core thus creating a virtually
ready-to-go nuclear power unit to visit without any radiologic concerns. The tour continued with the
ISN building where participants were shown the stored steam generators and the conditioning
installations. Participants used the occasion to discuss questions regarding the facility and its future,
e.g. the extended duration of storage for spent fuel in Germany, effects of the sea-water on the coast-
sited facility, and possibilities of further non-nuclear use of the buildings once the radioactive waste
had been shipped of for disposal.
WENRA and BMU want to express their gratitude to EWN for the possibility of visiting its Greifswald
site and for the time and efforts provided by all EWN staff.
The slides of Gudrun Oldenburg’s presentation can be found in the full version of the Proceedings.
The annulus housing the six main circulation pumps within unit 6 © EWN GmbH
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
8
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
9
Opening Session Chair: Christine Wassilew (BMU, Germany)
I.
WENRA Introduction Mina Golshan (Deputy Chief Inspector, ONR, United Kingdom)
We are here for a working-celebration of the 20th
anniversary of creation of WENRA, focusing on
decommissioning and waste management, a key area
that WENRA has championed for almost as long.
Over the past 20 years, WENRA has made a significant
contribution to nuclear safety worldwide:
• The WENRA Reference Levels have set a high
standard of safety and brought consistency of
approach amongst WENRA member states;
• WENRA’s initiatives to subject key fundamentals to peer review has resulted in the
development of more robust approaches to emergency arrangements and response
capability;
• More recently, as a strategic partner to the European Commission, WENRA is reviewing
arrangements for ageing management as many of our nuclear facilities have now been in
service for well over two decades.
This workshop is another timely initiative - with more than 200 reactors worldwide either in, or
approaching decommissioning and many other operations and facilities coming to their end of life, it
is time that as the WENRA community we focus on decommissioning and its regulation.
We have come a long way since the first generation of nuclear power plants and fuel cycle facilities
were designed; today we expect to see decommissioning considered as part of the design and during
the operation of any nuclear facility. However, despite all the progress we have made, most of us are
at the beginning of a long road, dealing with the legacy of the first generation. Some of us are dealing
with unique challenges - as we will hear during the course of this workshop.
To be clear, this is not ta criticism of our predecessors - quite the contrary, they were the trail blazers,
esteemed scientists and engineers that pushed the boundaries to help the society benefit from what
this industry offers. Their focus though at that time was ‘there and then’ and it was decided to leave
decommissioning challenges for another day. Today, we cannot afford to do that and neither should
we seek to. That is why as we celebrate our achievements so far and reflect on the learning, we should
also recognise that being satisfied with gradual progress is no longer good enough given the scale of
the challenge we face.
Operators, supply chain and regulators, we need to ‘up our game’ and aim for a step change - this is
our collective responsibility to enable safe, timely and sustainable decommissioning. That is not to say
that we overlook the safety fundamentals that have served us for many years, but it is about being
innovative in our thinking, our processes and the use of technologies at our disposal to accelerate
decommissioning and waste remediation. This is about expanding our horizons, learning from each
other as well as other industries with similar challenges.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
10
Taking this approach, aiming for a step-change, is no longer a “nice to do”, it’s now a necessity, because
that is the only way we can ensure that we maintain, and in some cases, regain the confidence of the
public in what we do. In so achieving, we ensure that future generations can also benefit from what
this industry has to offer.
As regulators, we play a pivotal role, in setting and standards and securing their implementation. As
we do so, we must also be clear in our expectations of what is safe enough and what is over-
conservative in the context of decommissioning. Because over-conservatism will hold back progress.
We must not allow ‘the Best, to become the enemy of the Good and of progress’.
Ladies and Gentlemen, I wish us all a constructive workshop and fruitful discussions.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
11
II.
International Safety Standards as a basis for the development of national regulations for
decommissioning Nelli Aghajanyan (Division of Radiation, Transport and Waste Safety, IAEA)
Decommissioning is the last phase in the lifetime of an authorized
facility and it comprises administrative and technical actions taken to
allow the removal of some or all of the regulatory controls from a
facility. It typically involves decontamination and dismantling of
systems, structures and components of the facility, but also might
involve demolition of building structures and site clean-up.
The International Atomic Energy Agency (IAEA) is the focal point for
coordination of international cooperation in relation to peaceful use
of nuclear technologies and nuclear energy, nuclear safety and
security, and protection of people and the environment from harmful
effects of ionizing radiation. The IAEA develops and maintains a set of
international Safety Standards, applicable to different facilities and
activities, that reflect an international consensus on what constitutes
a high level of safety for protecting people and the environment. The
Safety Standards cover, among other topics, decommissioning of facilities. In addition, the IAEA
implement numerous activities and projects to assist Member States with application of Safety
Standards.
This presentation provides an overview of the structure and status of the IAEA Safety Standards on
decommissioning, and describes recent developments related to revision of existing Safety Standards,
with an emphasis on regulatory perspectives in the planning for, in the implementation of and in the
completion of decommissioning actions, taking into account the principle of the graded approach to
regulation.
Furthermore, the presentation addresses some complementary IAEA activities to assist Member
States, such as (i) providing model regulations that may be used as a basis for either developing new
regulations on all aspects of safe decommissioning of facilities or for the assessment of the adequacy
of existing regulations and regulatory guides on decommissioning, and (ii) developing specialized
training modules and providing training courses specific to safe decommissioning of facilities, e.g. on
Regulatory Control of the Decommissioning of Facilities to support the needs of regulatory bodies and
their technical support organizations. In addition, the specialized training modules are developed on
Decommissioning Planning and Project Management, on Characterization to Support
Decommissioning and on Safety Assessment for the Decommissioning of Facilities that are targeted at
relevant national organizations in Member States engaged with these tasks.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
12
III.
Regulatory Aspects in Decommissioning: Experiences in Germany and Outlook Wolfgang Cloosters (Director-General, BMU, Germany)
In Germany, the phase-out of nuclear energy was initiated in 2000 by
the consensus on atomic energy policy and subsequently enshrined
in the Nuclear Phase-out Amendment Act in 2002. Following the 2011
Fukushima disaster, this phase-out was further consolidated and
accelerated in a broad political and social consensus. Fixed dates for
the shutdown of German nuclear power plants were laid down in the
Atomic Energy Act for the first time. Eight power plants were
immediately shut down in 2011. Others followed over subsequent
years. The last German nuclear power plant will be shut down by
2022 at the latest.
Over the last few years we have concluded a number of licensing
procedures for the decommissioning and dismantling of nuclear
power plants: 8 procedures in 2017 and 2018 and this year for
Gundremmingen Unit B.
This talk intends to provide an insight into the licensing procedure, the competences of the
participating authorities as well as the relevant legislative and sub-legislative requirements and
recommendations for decommissioning in Germany.
Special attention will be given to the role of guidelines in the legislative framework in Germany. While
decommissioning guidelines are not legally binding on third parties, they are drawn on by licensing
authorities in licensing procedures. In this way, the guidelines contribute to the current state of the art
in science and technology in German sub-legislative regulations and thus help maintain a high standard
of safety in the decommissioning of nuclear facilities.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
13
IV.
WENRA WGWD – How the SRLs work Stefan Theis (Head of Predisposal Department, ENSI, Switzerland; Chair of WENRA WGWD)
According to the WENRA policy statement WENRA countries commit
themselves to implement in their regulatory practice a comprehensive
set of safety reference levels (SRLs) which is understood as the agreed
minimum level of safety requirements which should be fulfilled by
licensees in any WENRA country. WENRA countries are expected to
implement these SRLs not on a case by case basis, e.g. as individual
license conditions, but in the generally applicable parts of their
regulatory systems, such as act, ordinance or mandatory regulatory
guide.
Member states are requested to demonstrate the SRL-implementation
in a self-assessment which is later on benchmarked in a panel session or
sub-group-session of the corresponding WENRA working group.
Identified needs for improvement are listed in a national action plan and
corrective actions presented to the WGWD later on.
The WENRA working group on waste and decommissioning (WGWD) has established 4 reports:
• Waste and spent fuel storage report (including part 3)
• Disposal report (only part 1 and 2, part 3 in preparation)
• Waste processing report (only part 1 and 2)
• Decommissioning report (including part 3).
All reports are structured in a similar way, in 4 or 5 safety areas each of which consists of a number of
safety issues the intention being that SRLs of corresponding safety areas and issues are formulated in
the same way in all reports.
Whilst early versions of the reports contain only a general part 1 and a part 2 with the SRLs, later
versions of the reports include a part 3 with detailed descriptions of the benchmarking results and the
improvements initiated in executing the national action plans of each individual country.
The decommissioning report contains 62 SRLs in the following four safety areas:
1. Safety Management (14 SRLs)
2. Decommissioning strategy and planning (15 SRLs)
3. Conduct of decommissioning (20 SRLs)
4. Safety verification (13 SRLs)
In the presentation the process of defining the SRLs, the benchmarking exercise and the results of the
national action plans will be explained.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
14
V.
WENRA WGWD – How SRLs are implemented and how “newcomers” benefit Tamara Suschko (SNRI, Ukraine)
In 2015, the State Nuclear Regulatory Inspectorate of Ukraine (SNRІU)
has become a member of the Western European Nuclear Regulator’s
Association (WENRA). Ukrainian legal and regulatory framework in the
field of nuclear energy use, including radioactive waste management
are quite comprehensive but need further improvement.
The SNRIU harmonizes its regulations with the requirements of the
European Union, IAEA recommendations, WENRA safety reference
levels. Membership in WENRA and participation in WENRA’s working
group encourages SNRIU to develop new regulations and revise existing
regulatory acts.
WENRA’s reports with Safety Reference Levels and benchmarking
procedure is a good mechanism to improve national regulations.
The only nuclear power plant in Ukraine that is under decommissioning is Chornobyl NPP. The license
for the decommissioning of the Chornobyl NPP was issued by the SNRIU in March 2002. For Chornobyl
NPP it was accepted deferred dismantling strategy, which supposes the following stages: shutdown
stage (cessation of operation), final shutdown and preservation, safe exposure and dismantling stage.
Today Chornobyl NPP is in on the final shutdown and preservation stage.
All other nuclear facilities in Ukraine which are under operation (NPPs, storages for spent fuel, research
reactor) have Decommissioning concepts (initial decommissioning plan), which were approved by the
regulatory body.
The above-mentioned aspects are outlined in the presentation.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
15
Session 1: Decommissioning Strategies and Planning Chair: Mario Dionisi (ISIN, Italy)
The need to develop integrated strategies and plans for nuclear decommissioning has grown in
importance ever since first-generation facilities have reached the end of their operational lifetime and
experience with the dismantling of the facilities and management of the radioactive decommissioning
waste accumulated. It is also one of the major interfaces between nuclear regulators and facility
operators. Regulators must define national strategies for decommissioning and radioactive waste
management with strict requirements for public and workers’ safety, while at the same time respecting
the operators’ more extensive on-the-ground knowledge and without overburdening their economic
resources. It is today understood that decommissioning is a major part of a facility’s lifetime, both in
terms of safety and costs. Planning for decommissioning is therefore now an important part of a
facilities design stage – a requirement that, nowadays, you can find reflected in both IAEA safety
standards as well as in WENRA safety reference levels. At the same time, opinions still evolve, e.g. due
to progress in technological options, a changing public outlook, or changing views of radioactive waste
management.
To illustrate this, Danila Savin from the Russian TSO Scientific and Engineering Centre for Nuclear and
Radiation Safety (SEC NRS) presents the development of planning recommendations by the Russian
supervisory body Rostechnadzor, detailing the steps and options to plan for decommissioning of a
nuclear facility while the facility is still under operation. Participants also discussed the possibilities of
different end-state options for decommissioned facilities and the difficulties in deciding which
operational information will prove important during decommissioning and therefore will have to be
recorded.
Kristina Gillin, Lloyd’s Register’s principal consultant for nuclear decommissioning and waste
management, by reflecting on experiences gained and lessons learned promotes a change of
perspective towards recognising nuclear decommissioning as a sustainability problem and therefore
as part of a bigger picture. This includes understanding decommissioning as a process of site
transformation, also with the aim in mind of enhancing public trust and understanding as well as
reducing the risk of site abandonment.
A changing approach to decommissioning, from a regulator’s point of view, can also be found in the
presentation of Vincent Cloître and Dorothée Conte of France’s ASN. Ongoing delays in several French
decommissioning projects, including legacy sites, and resulting safety concerns led to an understanding
that the currently predominant approach – a case-by-case authorization process – is by itself not
sufficient to deal with these delays. ASN thus asked the three major French operators to describe their
waste management and facility fleet decommissioning strategies and is in the process of assessing
them.
For ENISS, the European Nuclear Installations Safety Standards Initiative, Alain Ensuque presented the
views on applying a graded approach to decommissioning from the licensees‘ perspective. Aiming for
a realistic balance between investments for safety and the resulting safety improvements, ENISS
positions aim therefore to consider risk as well as cost-benefit analyses and the concept of reasonable
practicability.
The subsequent panel, concluding the session, dealt with questions how changes in approach and
perspective could affect the national programmes of EU member states according to Directive
2011/70/Euratom. A possible problem seen by operators was the availability of supplies and services
in an ever more globalized market and delays arising because of possible shortages; discussed was also
the role regulators could play, e.g. in assessing the qualification of suppliers.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
16
I.
Development of Rostechnadzor recommendations for planning of decommissioning
during operation of nuclear facilities Danila Savin (SEC NRS)
The slides of this presentation can be found in the full version of the Proceedings.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
17
II.
The need for a sustainable decommissioning paradigm Kristina Gillin (Lloyd’s Register)
Given the age distribution of the world’s nuclear fleet, a large increase
is anticipated in the number of reactors that will be shut down and
require decommissioning. It is therefore more important than ever to
reflect on the experiences gained to date and incorporate lessons
learned into future decommissioning-related endeavours. In doing so it
is vital to consider not only key aspects – such as technical, regulatory,
organizational or financial – but also the paradigm for nuclear back-end
management as a whole.
When stepping back and reflecting on the current paradigm, one clear
pattern emerges: Over the long term, things rarely go as planned. In
particular when it comes to plans for implementing disposal solutions
for spent fuel or radioactive waste. Although the underlying causes may
be interesting to reflect upon, for purposes of a paradigm-level lessons
learned they are hardly relevant. Instead, what is important to acknowledge is the fact that well-
meaning, ambitious plans for nuclear back-end management have a high probability of becoming
significantly delayed or cancelled.
As there is no indication that this reality will change any time soon, the current paradigm is clearly
unsustainable. And with increasing amounts of spent fuel and radioactive waste being stored
indefinitely, the risk that some sites will become abandoned prior to release from regulatory control
cannot be ruled out. Especially given the speed of change and associated risk of instability in society at
large.
This raises the question of responsibility for mitigating the risk that radiological inventories will be left
in a state that poses safety risks if a site becomes abandoned. Regulatory regimes generally require
plans to be in place for both decommissioning and waste management. But when it is known that
those plans have a high probability of not coming to fruition, at least not without major delays, is the
regulator not responsible for enhancing the requirements? If so, what would such enhancements look
like?
By recognizing that decommissioning is part of a bigger picture – the shutting down of an industrial
facility surrounded by communities that will be impacted one way or another – it becomes clear that
nuclear back-end management needs to be approached as a sustainability problem, as a complement
to resolving the technical challenges that lie ahead. The benefits of ensuring that nuclear
decommissioning and waste management are founded on sustainability principles are tremendous:
increased trust, less waste, lower costs and shorter timeline between productive uses on a site. As
well, reduced risk of major delays or dead ends – in turn, reducing the risk that nuclear sites will
become abandoned before long-term safety has been assured.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
18
III.
Waste management and decommissioning strategies Vincent Cloître, Dorothée Conte (ASN, France)
For the last ten years, the French nuclear safety
authority (ASN) has been confronted with
many postponements of dismantling by the
three major French operators, CEA, EDF and
Orano, whereas they had initially committed to
implement immediate dismantling. A lot of
decommissioning operations and a lot of
retrieval and packaging operations of these
licensees are significantly behind schedule.
Moreover, EDF wants to change its six Gas-
Cooled Reactors (GCR) decommissioning
strategy and postpone the end of their
decommissioning of several decades. For the
40 CEA installations under decommissioning (research reactors, laboratories, reprocessing plants,
etc.), the forecast duration of the decommissioning and legacy waste retrieval operations has been
very significantly increased, several decades for most of them. Decommissioning the old installations
is also a major challenge for Orano, which has to manage several large-scale decommissioning projects
(UP2-400 facility at La Hague, Eurodif Production plant, etc.), with some retrieval and packaging
operations subject to major delays.
These operations affect old or legacy installations, which were built in the 50’s or in the 60’s, which do
not comply with recent safety standards and still contain an important source term. For this reason,
these delays raise major safety concerns. They also lead to leaving the burden of managing
decommissioning and waste to future generation. ASN came to the conclusion that only assessing the
installations decommissioning files, giving the authorizations and supervising them was not enough to
evaluate and control the licensees’ ability to move forward efficiently with their decommissioning
programmes, to comply with the decommissioning schedules and to reduce rapidly the risks in their
installations. In other words, ASN concluded that a case by case authorization process is not enough,
and that a strategic overview was necessary.
ASN thus asked each of the three licensees to submit a file describing their waste management and
decommissioning strategy for their facilities fleet. The goal is to enhance the ASN appropriation of
these strategies and to evaluate the programmes priorities, according to safety, radiation protection
and environmental protection criteria. The evaluation also takes into account the adequacy of the
licensees’ organization, their human, material and financial resources, to carry out their
decommissioning programmes, and the consistency of the decommissioning strategy with the
availability of transport packages, waste storage and packaging facilities.
EDF, CEA and Orano submitted their decommissioning strategy files recently. For the Orano and the
CEA files, ASN assessed it with ASND (Defence Nuclear Safety Authority). ASN is working on its
conclusions on the three files and aims to publish its position by the end of the year 2019.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
19
IV.
Graded approach of regulation for decommissioning – Considerations on the concepts:
risk informed, cost benefit analysis and reasonably practicable Alain Ensuque (ENISS)
Context
As more and more nuclear power plants are reaching their end of life,
the number of reactors entering the decommissioning phase will
increase dramatically in the near future. The European licensee-
operators, within the ENISS organisation, are concerned about
delivering the related decommissioning programmes safely and
effectively.
Following the design, construction and operation of a nuclear facility,
the decommissioning, up to the delicensing, presents a risk profile
significantly different from the previous stages of the lifecycle. As
parts of the installation are removed, dismantled and
decontaminated, the nuclear and radiological risks are generally
reducing, notably following defuelling. However, during this phase, for some specific operations, the
radiological risk may, on the contrary, increase. Also, during decommissioning, the relative importance
of industrial safety risk may become critical.
ENISS views on the benefits of a graded approach applied to Decommissioning
Over the past few years, ENISS has conducted a thorough reflection on the implementation of a graded
approach to the activities carried out on a nuclear facility. This thinking was guided by key principles:
• Investment in Nuclear Safety should provide significant safety improvements;
• Investment required in providing risk reduction measures should be commensurate with the
safety benefit that will be obtained as a result of their implementation;
• Industry needs accepted methods to make the balance between investment for safety and
safety improvement.
Three concepts have been particularly considered with the objectives of proposing clear definitions
and understanding, as well as goals and criteria for application:
➢ Risk informed
➢ Cost benefit analysis
➢ Reasonably practicable
The application of these concepts and the associated benefits in the area of decommissioning are
illustrated through different typical situations or operations.
Conclusion
ENISS is keen to share and discuss views on these concepts with regulators and other operators to
contribute to an unambiguous understanding and develop processes and methodologies enabling a
safe and effective decommissioning of nuclear facilities.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
20
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
21
Session 2: Regulatory Experience Chair: Stefan Theis (Head of Predisposal Department, ENSI, Switzerland; Chair of WENRA WGWD)
Decommissioning of a nuclear facility not only changes the work of the site’s operator. The regulatory
body, responsible for reviewing license applications and site supervision, will have to adapt to the
change in activities, in the facility itself and in the radiological and conventional work safety risks
included. Operators and regulators will have to find a way to discuss and agree their needs without
compromising safety or hindering efficient implementation of the decommissioning plans. In this
session, examples and experiences from different countries are presented to illustrate the different
approaches taken by different countries to deal with changing interplay between operators and
regulators.
From the competent German authority for the Land of Baden-Württemberg, Theo Neuffer reports
about the challenges for the regulatory body when an NPP enters its decommissioning stage and
Germany’s approach to approving decommissioning activities. The importance of ongoing on-site
inspections is demonstrated by a comparison of dose rates to the operational stage, with little
differences to individual doses even though the overall activity of the facility decreases progressively.
Phil Hallington of Sellafield, Ltd discusses the challenges of managing a complex legacy site and the
recent changes operators, regulators and stakeholders have agreed. This includes the development of
a risk management framework and implementation of more efficient engagement mechanisms.
Fabrizio Trenta of Italy’s national regulatory authority ISIN describes the role of the regulator in a
nuclear environment that is marked by Italy’s decision to close most of the nuclear installations and
abandon far-reaching plans in the wake of the 1986 Chernobyl accident. The duties and functions of
ISIN within Italy’s decommissioning strategy are presented as well as the cooperation with SOGIN, the
1999 established operator for the decommissioning of nuclear installations and waste management.
The regulator and its role in the Swedish system is presented by Martin Amft of the Swedish Radiation
Safety Authority SSM. The approval and authorization processes for decommissioning work in Sweden
is explicated and experiences are discussed, as well as the planned approaches for coming
decommissioning activities.
In the case of the shutdown and planned decommissioning of Swiss Mühleberg NPP, Klaus Germerdonk
for ENSI presented the plans and their regulatory implementation. The regulatory requirements of the
operator are sketched out along with ENSI’s work in review, authorization and supervision to convey
how the regulator approaches the project.
The concluding panel discussed questions of furthering public trust and ensuring the independence of
regulators in the Sellafield example; the foundation of all, as Phil Hallington explained, was
transparency. Crucial is also the public understanding that there is no alternative to decommissioning
and dismantling. While regulators are responsible for supervising nuclear safety and conduct
inspections to do so, inspections for conventional workplace safety and especially for cyber-security
are either done by dedicated departments within the authorities or by different authorities altogether,
as a quick panel survey found. Distinct approaches to licensing decommissioning, in particular for the
transformation between the operational and decommissioning phase of facilities were discussed.
While approaches between countries do differ, all panellists stressed the importance to ensure clear
transitions between licenses.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
22
I.
Inspection practice for NPP in decommissioning Theo Neuffer (Ministry of the Environment, Climate Protection and the Energy Sector Baden-
Württemberg, Germany)
The supervision of a nuclear facility in decommissioning can be
divided more or less in three areas. First, there is the supervision of
the operation of the residual systems, then there is the supervision
of dismantling activities including also waste treatment, storage and
the clearance processes and finally in most cases the supervision of
the transformation process of the operator. The competent
regulatory body performs on-site inspections to all of these areas.
Since the dismantling activities differ strongly from the ones in
power operation not only the authorized party but the regulatory
body as well has to adapt. At least with the removal of the nuclear
spent fuel (NSF) the relevant protection goals are reduced to limit
the radiation levels of the workers, environment and the public and the safe enclosure of radiation.
The number of safety relevant systems is reduced strongly as well as linked in-service and maintenance
activities, which have been of special interest for the regulatory body during power operation.
Furthermore, the scheduled annual outage and all fuel handling vanishes.
However, the evaluation of operator data concerning radiation dose levels of workers show clearly,
that there are still topics in focus for the competent regulatory body. Especially at the beginning of
dismantling activities (depending on the dismantling-strategy of the authorized party) there are dose
relevant activities like dismantling of core equipment, core internals or components of the primary
circuit. The evaluation of operator data shows, that the average individual dose during
decommissioning is on equivalent levels compared to power operation. The difficulty for the
regulatory body comes with the fact, that dismantling activities are not that fixed and early scheduled
as e.g. the annual outage or cask handling activities of NSF. Hence, a permanent information flow has
to be guaranteed to schedule on-site inspections of the regulatory body.
To cope with this necessity, the regulatory body in Baden-Württemberg established an allowance-
process that is regulated in the decommissioning license. This allowance process is oriented on the
modification process and states, that decommissioning steps need to be reviewed and finally allowed
by the competent regulatory body before starting any actions. Therefore, the operator has to prepare
reports, which describe the planned dismantling activities and all measures that come along with it.
The regulatory body and its technical support organization review these reports, and finally the RB
approves the reports. Alongside this process, the regulatory body performs on-site inspections on a
regular basis.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
23
II.
Enabling Regulation – The Operator’s View Phil Hallington (Head of Policy, Sellafield Ltd)
This Presentation will briefly cover the history of Sellafield and the
background to the current Legacy management challenges on the
Site. The basis for safety justifications will be addressed in the context
of a cumulative risk profile for this complex Site. A Risk management
Framework has been developed in conjunction with Regulators and
key stakeholders to guide priorities and investment decisions. Specific
examples of the benefits to hazard and risk reduction, from adopting
Enabling Regulation will be given. A more effective engagement
mechanism between operators and regulators has been implemented
in recent years, which preserves the Enforcement actions and powers
of Regulators, whilst encouraging sustainable progress with hazard
and risk reduction on a complex Site. Practical experience of this way
of working will be shared.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
24
III.
Decommissioning authorization process and controls in Italy Fabrizio Trenta (ISIN, Italy)
In 1964, Italy was the third nuclear country in the world for installed
power behind USA and UK. In 1986 a wide national nuclear
programme was under development with 20 NPPs foreseen. In the
aftermath of the Chernobyl accident, the National program was
cancelled and the nuclear installations, 4 NPPs (Caorso, Latina,
Garigliano, Trino) and 5 Fuel cycle facilities (Eurex, FN, Itrec, OPEC,
Plutonio) were closed and only research reactors were maintained in
operation.
In the mid-nineties the Legislative Decree n. 230/1995 established
the process for the decommissioning authorization until the final
stage.
All nuclear installations were maintained in safe condition until the establishment in 1999 of the
national operator Sogin appointed for the decommissioning of the nuclear installations and for the
management of the waste deriving from the nuclear cycle. In 2001, the Government decided to change
the decommissioning strategy from safe storage to a single step decommissioning of all nuclear
installations and in 2012 the decommissioning authorizations were granted for Trino and Garigliano
NPPs and in 2014 for Caorso NPP. The decommissioning authorization for Latina NPP is foreseen by
June 2020.
According to the plan of the national implementer decommissioning activities are expected to be
concluded in 2035.
The spent fuel was sent abroad for reprocessing and a small amount remains to be shipped for
reprocessing in France.
In 2014, with the transposition of the Directive 70/2011/EURATOM, Legislative Decree n. 45,
established ISIN (National Inspectorate for Nuclear Safety and Radiation Protection) the new national
regulatory authority responsible, at national level, for nuclear safety and radiation protection,
completely independent from any other political and promotional body.
Among the activities that ISIN is required to perform, part of the duties and functions assigned by law
are: technical review and assessment on the documents submitted during authorization processes,
surveillance performed through on site controls and inspections on decommissioning activities,
radioactive waste management, transports, physical protection countermeasures, clearance activities
of materials, effluents discharges, radiation protection of workers, people and environment.
The law establishes, as final stage for decommissioning, the release of the sites without radiological
constrains: at all NPPs sites decommissioning activities are ongoing and control activities will be
showed during presentation.
Clearance of materials represents a focal point for the minimization of radioactive waste as well as the
availability of a national repository represents a primary requirement for the closure of the nuclear
cycle: the concept design for the national repository foresees a near surface disposal facility for
LLW/ILW and an facility dedicated to the long term storage of ILW/HLW, including spent fuel not
reprocessed.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
25
IV.
Authorization for and regulatory control of decommissioning in Sweden Martin Amft, Christoffer Forss (SSM, Sweden)
In 1972, Sweden’s first light water nuclear power reactor, Oskarshamn unit
1 (BWR), started its commercial operation. In the following years, 11 more
nuclear power reactors were commissioned at the sites Barsebäck (units
1–2, BWR), Forsmark (units 1–3, BWR), Oskarshamn (units 2–3, BWR), and
Ringhals (unit 1, BWR; units 2–4, PWR). The two units at the Barsebäck site
were permanently shut down in 1999 and 2005, respectively, and have
been in care and maintenance since then. The two oldest units at the
Oskarshamn site were permanently shut down in 2016 and 2017,
respectively. The two oldest units at the Ringhals site are scheduled to be
permanently shut down by the end of 2019 and 2020, respectively.
Additionally, there is the Ågesta PHWR, which has been in long-term care
and maintenance since the mid-1970’s.
Directly after permanent shut down, the spent nuclear fuel, the control rods, and the core
instrumentation are moved from the reactor to the nuclear fuel pool and within 18 – 24 months
transported to the Central Interim Storage Facility for Spent Nuclear Fuel, Clab, operated by Swedish
Nuclear Fuel and Waste Management Company (SKB). Additionally, certain other specified preparatory
activities are allowed to commence before the authorizations for decommissioning have been granted.
In the presentation, the authorizations for decommissioning according to the Act (1984:3) on Nuclear
Activities, the Environmental Code (1998:808), and regulations issued by the Swedish Radiation Safety
Authority (SSM) will be described. In addition to these authorizations, the licensee has to describe the
planned dismantling and demolition activities in greater detail in so-called work packages. Typically,
the dismantling and demolition activities for a nuclear power reactor are described as 10–12 work
packages. SSM has to be notified about these work packages in advance. A formal approval of the work
packages by SSM is not required though.
Although there was essentially a comprehensive regulatory system for decommissioning of nuclear
facilities in place, certain adaptations and completions to the requirements have recently been made
in order to facilitate for the operators to prepare their applications for decommissioning and
supporting documents. SSM achieved this by issuing additional licencing conditions for the seven units
which are permanently shut down or which will be shut down in the near future.
During 2016–2018, SSM authorized the segmentation of the reactor internals of Barsebäck units 1–2
and Oskarshamn unit 2. Formally, these work packages were conducted during care and maintenance
operation. The authorization processes and SSM’s experiences from the regulatory control of these
dismantling activities will be discussed in the presentation.
In December 2018 and April 2019, respectively, SSM authorized the (large scale) dismantling and
demolition of Oskarshamn units 1–2. SSM’s experiences from the review of these applications and
supporting documents will be discussed.
Finally, SSM’s planned approach for the regulatory control of the coming dismantling and demolition
activities, which will take place at seven units in parallel, will be described.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
26
V.
Licensing Procedure and Inspection Fields in Decommissioning of Swiss NPP Klaus Germerdonk (ENSI, Switzerland)
In late 2013, BKW Energy Ltd announced that Mühleberg
will be decommissioned by the end of 2019. The single 373
MWe boiling water reactor began operating in 1972. It will
be the first Swiss NPP to be decommissioned.
On 18 December 2015, BKW submitted the application
documents to decommission its NPP (the final
decommissioning plan) to the Federal Department of the
Environment, Transport, Energy and Communication
(DETEC). The application comprises the main report
detailing the decommissioning project’s conceptual
framework and three sub-reports: accident analyses and
emergency protection measures; the environmental
impact report and the nuclear security report.
The requirements for the final decommissioning plan are described in the Nuclear Energy Act, the
Nuclear Energy Ordinance and in ENSI’s Technical Guideline G17. The Decommissioning Guideline
ENSI-G17 is in accordance with the WENRA Safety Reference Levels and the respective IAEA Safety
Standards on decommissioning.
The BKW application documents were reviewed by the relevant authorities such as ENSI. Based on the
authorities’ advisory opinions, DETEC issued the decommissioning order regulating the
decommissioning process in June 2018 – more than one year before final shutdown. No objections to
the order were made to the Federal Administrative Court. The decommissioning order is legally
binding.
Immediately after final cease of nuclear power production on 20 December 2019, BKW Energy Ltd
plans to start some preparatory activities still under the operating license and the conditions of the
decommissioning order. An approval of ENSI for all the steps is required.
For the establishment of the technical post-operation an independent, redundant spent fuel cooling
system will be installed. Preparatory measures include the removal of components in the turbine hall
and the installation of material treatment facilities (cutting, decontamination and packaging).
To reach the final shut down status all necessary technical and organizational measures for the
establishment of the technical post-operation have to be applied and approved. Spent fuel has to be
transferred from the RPV into the spent fuel pool and updated technical specifications and regulations
are implemented. Subsequently, the operating license expires.
According to current planning, the decommissioning project is to be carried out in two phases. During
phase 1, in particular the dismantling of the RPV-internals and systems of the reactor building takes
place as well the removal of the spent fuel from the site.
ENSI will establish a specific on-site inspections program for the decommissioning work carried out by
BKW. Topics already identified are related to nuclear safety and security, staffing & organization, waste
management, dismantling and radiation protection. Relevant findings will be considered for the
oversight activities of ENSI and the overriding aspects related to decommissioning license
requirements.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
27
Session 3: Limits of Harmonization and Specific Approaches Chair: Simon Morgan (ONR, United Kingdom)
When countries developed their national regulations for nuclear safety, they could refer to the then
existing IAEA safety standards, but usually did so independently and as they saw fit. One of the main
reasons for WENRA to concern itself about harmonization of national nuclear regulations was to
support its member states to openly discuss their regulatory frameworks and experiences therewith
and to deduct sets of safety requirements that shall serve as a standard to measure the national
regulations against – thereby providing assistance to newcomers to the nuclear field as well as holding
the member states accountable for bringing their national regulations up to par. Nonetheless, many
countries have built regulatory systems that aren’t as easy subjects to harmonization as others are.
Other countries allow for even different approaches to decommissioning.
In the first talk of the session, Stefan Theis explained the WENRA approach of benchmarking national
regulations against WENRA safety reference levels and the limits this harmonization: what about
countries with only a single facility to regulate? What about countries issuing licensing guides that
don’t really fit within the WENRA’s understanding of general applicable regulations but may do their
job just as well?
Holtec’s Corey DeWitt presents an American market approach to decommissioning. In this approach,
Holtec as a dedicated decommissioning licensee acquires ownership of a decommissioning site include
the license, site properties, assets and liabilities, nuclear fuel, and existing organizations and trust
funds set up for decommissioning. By assuming full economic responsibilities and by combining
experiences gained in the decommissioning of several projects, Holtec tries to implement more
efficient and economically viable ways of decommissioning than single-facility operators would be able
to. As was made clear in the subsequent panel discussion, this requires the availability of sufficient
funding, in US cases in the form of trust funds; otherwise the transfer of the site and decommissioning
has to be postponed.
Ulrich Scholl of Kerntechnische Entsorgung Karlsruhe (KTE) gives a progress report on the
decommissioning of the MZFR multi-purpose research reactor at the Karlsruhe Institute of Technology
which is under decommissioning since 1987 and KTE’s experiences with the dismantling of the plant
and the cooperation with the supervising competent authorities.
A novel approach to digital knowledge management in decommissioning promises Joaquin Toubes
Tova of Tecnatom. Addressing the critical need of preserving knowledge about a facility’s design and
intricacies while most of the engineers of the design and operational stage will no longer be around
during the decommissioning of the facility, Tecnatom develops their own methods, using up-to-date
digital methods and the findings of contemporary neuroscience to capture and pass on tacit knowledge
about the facilities and to improve training efficiency.
Discussion in the panel centred around questions of how to navigate differences in understanding of
regulatory requirements between regulators, licensees and stakeholders and the role organisations
like WENRA and ENISS can play to facilitate a shared understanding.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
28
I.
Harmonization challenges during WGWD benchmarking Stefan Theis (Head of Predisposal Department, ENSI, Switzerland; Chair of WENRA WGWD)
According to the WENRA policy statement WENRA countries commit
themselves to implement in their regulatory practice a
comprehensive set of safety reference levels (SRLs) which is
understood as the agreed minimum level of safety requirements
which should be fulfilled by licensees in any WENRA country. WENRA
countries are expected to implement these SRLs not on a case by case
basis, e.g. as individual license conditions, but in the generally
applicable parts of their regulatory systems, such as act, ordinance or
mandatory regulatory guide.
Member states are requested to demonstrate the SRL-
implementation in a self-assessment which is later on benchmarked
in a panel session or sub-group-session of the corresponding WENRA working group. Identified needs
for improvement are listed in a national action plan and corrective actions presented to the WGWD
later on.
There are three possible benchmarking results:
A: full compliance, no action required; B: justified deviation, no action required and C: deviation, action required. Whereas results A and C seem to be straightforward, B leaves room for interpretations. Which type of
deviation is justified? Which ones are unjustified?
General considerations of the problem are developed in the presentation including several examples
from the exercises of the WGWD.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
29
II.
Site decommissioning by dedicated decommissioning licensee: a US approach Corey DeWitt (Holtec)
The slides of this presentation can be found in the full version of the Proceedings.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
30
III.
Decommissioning of the MZFR Ulrich Scholl (KTE)
The Multi-Purpose Research Reactor (German:
Mehrzweckforschungsreaktor, MZFR) located at the
Karlsruhe Institute of Technology (KIT), former Karlsruhe
Research Centre, was a pressurized heavy water reactor. It
was built between 1961 and 1965 and under operation
from 1965 until 1984. The main tasks during operation of
the Multi-Purpose Research Reactor were tests of fuel
elements, material development, training of staff,
electricity production and district heating of the Karlsruhe
research centre. The plant was shut down in 1984 and is
under decommissioning since 1987. It was decided to
dismantle the plant completely and to recultivate its site
(“green field”). Therefore, eight decommissioning licences
were applied for and regulators granted all.
The decommissioning project is currently in last phase of the eighth decommissioning licence. The
reactor internals, the reactor pressure vessel an all former operating systems were dismantled. If
necessary, substitution measures were taken. For example, the old ventilation system was replaced by
decentralised ventilation systems. It was already possible to release some buildings from the Atomic
Energy Act and to tear them down conventionally.
Currently, the focus of the dismantling works is to remove the remaining contaminations. These
contaminations are located inside the auxiliary buildings, the reactor building and the reactor
intermediate building. The most frequent kind of the contamination is Tritium. These decontamination
works require extensive dismantling of reinforced concrete structures. Therefore, it is necessary to
calculate statics for the remaining parts of the building and the replacement measures. For almost
every dismantling of the reinforced concrete structures, we had to apply for an advice of amendment.
The presentation will give a summary over decommissioning steps that are already completed. A more
detailed view on necessary specific approaches during the last decommissioning step follows. The
presentation will conclude with a brief outlook.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
31
IV.
Digitalization for Knowledge Management in Decommissioning Joaquin Toubes Tova (Tecnatom)
The amount of information that current organizations need to
manage is huge. Where to store it, how to classify it and
especially, how to distribute it, is usually an issue for managers,
human resources and training departments.
Furthermore, the way of learning has completely changed, as new
generations learn using technology. The new studies based on
neuroscience show the relationship between emotions, learning
and memory. It is demonstrated that knowledge is acquired easily
by doing rather than memorizing.
SOUL is a concept of Knowledge Management developed by
Tecnatom. SOUL takes advantage of digital transformation,
expert knowledge and social collaboration to transfer knowledge
through the organization and to external stakeholders.
In SOUL, the learning model is now centered on the trainee instead of the instructor. The activities are
customized and engaging for the trainees. The training is oriented to performance improvement. The
learning process is open and collaborative in order to promote social learning.
The design, operation and decommissioning of nuclear power plants usually embraces more than two
or three generations of engineers. The ones present during design will probably not be involved in the
operation and these will normally not all be involved in the decommissioning phase either.
Moreover, decommissioning is a critical area for the application of knowledge management systems,
as uncertainty is many times encountered and knowledge is generated along the process.
During the year Tecnatom has developed a pilot program for the application of SOUL to
decommissioning, developing a methodology to capture tacit knowledge and avoid losing it during
generational change, promoting multi-skilled professionals and improving training efficiency.
Tecnatom has applied the methodology to a real-case scenario related to the management of
radioactive waste. Operational experiences have been captured and digitalized and will be essential
for future decommissioning projects. SOUL allows for the use of advanced digital technologies such as
3D simulation, virtual reality and other software developed specifically by Tecnatom for radioactive
waste management and improving decommissioning operations.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
32
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
33
Session 4: Transition from Operation to Decommissioning Chair: Bengt Hedberg (SSM, Sweden)
Ending the operational life of a nuclear facility and entering into the decommissioning stage is a crucial
point for the safe, efficient and successful conclusion to a facility’s existence. Both regulators and
operators have to plan carefully to be able to find answer for the question posed by the occasion.
The first talk to shine some light on these questions is presented by Jim Kershaw of EDF Energy. In the
next ten years all seven Advanced Gas Reactors operator by EDF Energy will have to be closed, a
challenge EDF Energy has begun to tackle by commencing the planning for decommissioning ahead of
the first closure. The presentation details the underling strategy, goals and objectives as well as the
steps to implement them.
Saulius Stravinskas from VATESI, the State Nuclear Power Safety Inspectorate of Lithuania, describes
the authority’s regulatory work during the transition from operation to decommissioning of Ignalina
NPP and shows the progress which has been made in dismantling and decontaminating the facility. At
the same time, the infrastructure for the subsequent radioactive waste management in Ignalina is
developed.
In the Slovak Republic, legislative efforts are underway to clear up yet unaddressed, more complex
issues following the transfer of responsibility for decommissioning to a state organization authorized
by the Ministry of Economy. Miroslav Drahos from UJD, the Nuclear Regulatory Authority of the Slovak
Republic, presents a look back to how the transition period was understood in the past, and a look
forward to how the concept of transitioning now implies new requirements like the transfer of
installations and information from the former operator to the new organization and the cooperative
preparation of the final decommissioning plan.
A talk prepared by ISIN’s Mario Dionisi but ultimately given by Martin Brandauer from NEA summarizes
the topics and results of the 2018 international workshop on regulation of decommissioning –
organized by the Working Party on Decommissioning and Dismantling (WPDD) and the Radioactive
Waste Management Committee Regulators’ Forum (RF) within OECD/NEA. The workshop’s key
findings were presented.
The concluding panel discussions centred for a while on the end point of the transition and the
beginning of the actual decommissioning phase: does the transition end when the facility is free of
nuclear fuel or once activities at the site are performed under a dedicated decommissioning license.
While approaches differ between countries, all panellist could agree that these differences were of
minor importance as long as it was ensured that there was a clear and valid license at all times during
the process. With regards to the AGR decommissioning by EDF Energy, disposal options for the
graphite core were asked about; EDF Energy prepares for a period of SAFSTOR for the core which will
be reviewed by the regulator up to a point where a disposal option has been found. International
initiatives are researching options and facilitating exchange between experts, already. The panel ended
on a discussion about financial provision for decommissioning which is handled differently by almost
every country, but ways will have to be found to compare and assess the adequacy of financing.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
34
I.
EDF Energy Planning for Decommissioning during Operation Jim Kershaw (EDF Energy)
Context
EDF Energy operates a fleet of 7 Advance Gas Reactors and 1
Pressurised Water Reactor. The Advanced Gas Reactors (AGRs) will
start to close in 2023, with all closed by 2030. The pressurised water
reactor at Sizewell B is scheduled to close in 2035 or later, and is not
covered by this presentation.
As a long-term nuclear operator in the United Kingdom, EDF Energy
is committed to ensuring that it delivers a safe, timely and cost-
effective decommissioning and associated waste management.
Planning for decommissioning has already commenced ahead of the
first closure, and the presentation will share EDF Energy’s activities
with the WENRA workshop.
Presentation
The presentation to the WENRA workshop will set the context of the EDF Energy decommissioning
programme. It covers the following topics:
• An overview of the AGR decommissioning strategy
• The responsibilities for decommissioning
• The phases of station closures and decommissioning across the EDF Energy fleet.
• The phases of decommissioning for a single EDF Energy station.
• An overview of the discharge route for fuel from site to the waste facilities at Sellafield.
• The strategic goals and objectives of decommissioning.
• Regulatory interactions.
• Closing summary
Conclusion
An overview of the EDF Energy approach to the planning for decommissioning will be presented for
discussion.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
35
II.
Lithuanian regulatory policy, challenges and activities during transitional period from
operation to decommissioning of Ignalina NPP
Saulius Stravinskas (VATESI, Lithuania)
The slides of this presentation can be found in the full version of the Proceedings.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
36
III.
The Development of Transition Period Requirements in the Slovak Republic Miroslav Drahos (UJD, Slovak Republic)
The transition period has so far been applied twice in the Slovak Republic
and in both cases it was quite unusual. In the case of the A1 NPP1 due to
historical reasons, because the operation termination was relatively
long process itself and several decommissioning activities were carried
out on a case by case basis. In the case of premature shutdown of the
V1 NPP2 transition period was determined by gradual final shutdown of
the reactors and the original operating license validity. Standard
termination activities were performed on the basis of operating
documentation and, in addition, in accordance with “Operation
Termination Concept”, which was not required by the Atomic Act.
Additional transition periods are foreseen for the VVER units currently
in operation.
The current Atomic Act contains basic decommissioning requirements, many of which are also related
to the transition period. Despite prevailing efforts to extend operation of existing units worldwide,
including the Slovak Republic, Nuclear Regulatory Authority considers it important to re-establish and
lay down more detailed requirements for transition period.
A new draft of Atomic Act is currently being prepared. This draft contains a special section dealing
specifically with the operation termination. In defining the transition period requirements, it was
necessary to consider the facts that have occurred since the last update of the Atomic Act.
In particular, it is the ultimate responsibility of the Slovak Republic for decommissioning of nuclear
installations through a State organization authorized by the Ministry of Economy. This new fact implies
additional requirements, such as the establishment of conditions for the handover and takeover of
nuclear installation and associated land between the operator and the State organization. The draft
Act also regulates the cooperation of these organizations in the preparation of the final
decommissioning plan, the transfer of operational information relevant for decommissioning, as well
as cooperation in submitting the decommissioning application.
In this context, it should be noted that the National Nuclear Fund Act has recently abolished the
possibility of using the Fund's resources to cover the costs during the transition period, leaving this
responsibility fully to the operator.
Although some basic aspects of the transition period are quite unambiguous, Slovak legislation will
have to address several complex issues in the near future in order to create a clear legislative
environment for the transition period.
1 HWGCR, shutdown in 1977 after primary coolant system integrity accident, defueled in 1999 2 Two units of VVER, shut down in accordance with the Government Resolution in 2006 and 2008 as a condition for the accession of the Slovak Republic to the European Union
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
37
IV.
NEA Regulators’ Forum – Outcomes of RF/WPDD Workshop on Regulation of
Decommissioning Mario Dionisi (ISIN, Italy); presented by Martin Brandauer (NEA)
Within the OECD/NEA, the Working Party on Decommissioning and
Dismantling (WPDD) and the Radioactive Waste Management
Committee Regulators' Forum (RF) on 20-21 June 2018 organised an
international workshop on regulation of decommissioning at the OECD
Conference Centre in Boulogne-Billancourt, France.
The workshop was focused on the exchange and sharing of national
experiences and challenges in regulation of decommissioning of nuclear
facilities. The main objectives were to survey the heterogeneity of
challenges, to share national experiences and challenges in regulation of
decommissioning of nuclear installations, to identify best practices and
challenges, and to identify areas and topics for future cooperation.
The workshop addressed a variety of issues from a range of perspectives in four sessions:
• transitioning from operation to decommissioning;
• challenges in ongoing decommissioning activities;
• management of radioactive waste from decommissioning;
• stakeholder engagement and interactions.
Breakout sessions discussed in small groups and contributed to exploring and understanding the
interests and needs of the NEA member countries in the area of regulation of decommissioning.
The workshop has been attended by 61 participants from 19 countries, representing regulatory bodies,
nuclear facility owners and decommissioning implementers, as well as waste management
organisations.
Key issues to be further discussed and investigated in future OECD/NEA initiatives have been identified.
Purpose of the paper is to present these findings.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
38
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
39
Session 5: Final Stages of Decommissioning Chair: Pieter Lietava (SÚJB, Czech Republic)
While there are many ways to decommission a facility and several end states of your site – e.g., if some
of the site’s buildings or infrastructure will be remaining for a future non-nuclear use – there is virtually
always a need for a dedicated regulatory act to release the site and all that may remain on it from
regulatory control. Even if restrictions on further use of the area may be put in place, the site finally
stops being a nuclear facility after that. The site should be clear of any remaining radioactive waste at
this point, its management’s being another issue that needs addressing. The final stages of
decommissioning thus see the facility operator striving to implement the end state of the site as agreed
in the decommissioning plans and licenses; while the regulator’s job is to supervise his efforts and
verify that all obligations have been met. In this session, regulatory experts from Sweden, France and
the United Kingdom describe the regulatory approaches to the end of decommissioning in their
countries and share their experiences.
In the initial talk, Martin Amft of the Swedish Radiation Safety Authority SSM describes the national
approach to the management of radioactive decommissioning waste and the site end state. For waste
above clearance levels a variety of options for reuse in other nuclear facilities or for disposal exist or
are being planned, so the route of radioactive waste management can be tailored for the qualities of
the radioactive waste in question. For the site itself, there’s also the option to release it for unrestricted
or restricted use.
For ASN (in cooperation with the TSO National Institute for Radiological Protection and Nuclear Safety,
IRSN), Coralie Ravier portrays France’s strategy of immediate dismantling and complete clean-out and
release of the facility or site without restrictions. To this end, France’s regulatory framework has been
updated extensively in the past 15 years.
In his concluding talk, Simon Morgan of ONR presents recent regulatory developments in the UK,
including on delicensing nuclear sites, release of radioactive substances, and radioactive waste
management options up to disposal of radioactive waste.
The subsequent panel of the presenters then discussed the range of public involvement in the decision
making about decommissioning and how to define key measures to focus on for optimisation. In the
UK, for example, the regulator weighs all the aspects that need to be taken into account to try to get
a measure for optimisation. In France, the licensee has to deliver a clean-up strategy and provide
laboratory-confirmed proof of its implementation. The release of sites with restrictions on use in place
was questioned with regards to the principle not to shift burdens onto future generations. Panellists
agreed that a restricted site release is mostly important for sites that have critical other functions as
well or are restricted for non-nuclear reasons; furthermore, that it makes no sense to issue restrictions
that cannot be enforced.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
40
I.
End state requirements for waste and site Henrik Efraimsson, Åsa Zazzi, Martin Amft (SSM, Sweden)
New Swedish regulations on clearance of materials and building
structures and land were issued by SSM in mid-2018. Simultaneously,
Directive 2013/59/Euratom on radiation protection (“the European
BSS”) was implemented in the Swedish legal framework in the form
of the new Swedish radiation protection act and ordinance. The new
radiation protection act contains developed requirements on
clearance in connection with decommissioning of practices involving
ionizing radiation.
The presentation will describe the regulations on clearance, divided
into sections on 1) Clearance of materials, 2) Clearance of building
structures and 3) Clearance of land (often called Site release).
Examples for all three sections will be given on the application of the new regulations (and the earlier,
similar regulations on clearance) on recent and ongoing decommissioning projects, both from nuclear
and non-nuclear activities, in Sweden. Lesson learned so far will be described, as well as plans for
further development of the regulations.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
41
II.
Immediate dismantling and complete clean-out principles
Coralie Ravier (ASN, France), Patrice François (IRSN)
ASN doctrine regarding decommissioning is based on two major
principles:
− immediate dismantling strategy for all nuclear facilities;
− complete clean-out and release of the facility/site
without any restrictions;
Immediate dismantling strategy:
In accordance with IAEA recommendations, the legal and
regulatory framework in force in France imposes that licensees
of nuclear facilities adopt an immediate dismantling strategy
for all nuclear facilities: decommissioning has to be performed
as soon as the facility is permanently shutdown, without any
waiting period.
To support the immediate dismantling strategy, the legal and regulatory framework has been reviewed
and updated since 2007 to set the decommissioning requirements. Timeframes have been endorsed
to address all aspects of decommissioning in a timely manner including permanent shutdown
notification, the transition period processes, the regulatory review process, the publication of the
decommissioning authorization as well as the planning for decommissioning.
In practice, operators are required to anticipate decommissioning actions from the design stage and
to submit a decommissioning plan subsequently after the notification process for permanent
shutdown. As soon as the decommissioning decree comes into effect, operators have to carry out
decommissioning actions in the shortest delay according to an overall planning and milestones
endorsed in the license conditions.
The aim of this policy is to avoid that the weight of burden of decommissioning regarding technical
and financial aspects on future generations. Moreover, this strategy enables operators to take
advantage from the knowledge and the skills from teams that were working during the operational
phase.
Complete clean-out strategy:
There are no universal clearance levels in France to clear the materials and to release the buildings and
site from regulatory controls during decommissioning. The final end-state of the facility, the clean-out
objectives and the related methodology have to be elaborated and submitted by the operators in the
frame of the decommissioning plan approval.
ASN policy states that the licensee should deploy clean-out processes taking into account the best
scientific and technical knowledge available at the same time and under economically acceptable
conditions, with the aim of achieving an end-state in which all the hazardous and radioactive
substances have been removed from the nuclear facility. This objective allows to come back to the
initial site conditions as they were before the construction of the facility. According to these conditions,
the delicensing of the nuclear facility can be decided by the regulatory body without any institutional
controls.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
42
To achieve this objective, the requirements implemented into the legal and regulatory framework set
the conditions to establish at the design stage of the facility a waste zoning survey to identify areas
where radioactive processes are operated and to continuously update and review this survey until the
permanent shutdown of the facility in the perspective of decommissioning.
When the licensee cannot implement fully the ASN policy, in particular for complex decommissioning
projects, a graded approach can be implemented. The objectives are to go as far as reasonably possible
in the clean-out process and the decision to stop the clean-up works must be justified considering
acceptable economic and technical conditions. The decision to release the site from regulatory
controls is then driven putting into balance the remaining radiological conditions and the future and
potential uses of the facility and site. When this approach is not compatible with all uses, some
restrictions can be implemented by the regulatory body.
The complete clean-out strategy complies with the polluter pays principle and aims at removing any
residual risk for future generations.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
43
III.
Recent developments in the regulation of UK nuclear sites in the final stages of
decommissioning & clean-up Simon Morgan (ONR, United Kingdom)
This paper will cover recent developments in the UK in four separate
but complementary areas which, taken together, are expected to result
in significant improvements to the regulation of the final stages of
decommissioning and clean-up of nuclear sites in the UK:
The UK Government’s proposals to amend nuclear safety and
environmental protection legislation to allow regulators and site
operators to adopt optimised and more sustainable approaches to
decommissioning, radioactive waste management and clean-up on
nuclear sites.
The current development by ONR of regulatory guidance on new
criteria for: (1) ending the period of financial responsibility for nuclear
third-party liability aligned with recent international agreements on exclusions under the Paris
Convention; and (2) revocation of nuclear site licences when all remaining nuclear safety and nuclear
security matters have been fully resolved.
The development and publication of new guidance by the environmental regulators in the UK
establishing numerical and qualitative standards to be met before nuclear sites can then be released
from regulatory control, after clean-up activities involving work with radioactive substances have been
completed.
Initial results from ‘Lead & Learn’ projects carried out by the UK’s Nuclear Decommissioning Authority
(NDA), the site licence company Magnox Ltd and its specialist sub-contractors at nuclear sites in
Trawsfynydd, North Wales and Winfrith in the South West of England. These projects are providing
evidence that the proposed new legislative and regulatory approaches have the potential to result in
significant safety and environmental benefits, and allow more progress in decommissioning and clean-
up across NDA’s estate of nuclear sites.
The paper will explain how the UK Government, nuclear regulators, public bodies and the nuclear site
licensees are working together, in conjunction with extensive stakeholder engagement and public
consultation, to develop an integrated suite of proposals aimed at achieving significant safety,
environmental and decommissioning programme improvements for the nuclear sites in the UK
preparing for and undertaking the final stages of decommissioning and site clean-up.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
44
Closing Remarks by Stefan Theis (Head of Predisposal Department, ENSI, Switzerland; Chair of WENRA WGWD)
Dear ladies and gentlemen, dear colleagues,
I am glad! Why?
When the idea was launched to have a WENRA decommissioning workshop, I was not convinced at all,
that this would have an added value and could become a success.
Now, after 2 ½ days of intense exchange, a technical tour, a variety of interesting presentations and -
last not least- the lively discussions during the breaks and continuing in the evening: it was really worth
it.
Before elaborating on some personal impressions, I want to thank everybody who made this event
possible; starting with our host the minister of environment and reactor safety, but equally well to all
the authors, who took the chance to let us all benefit from their knowledge and experience. The
organizers will support that in compiling all the presentations and make them available on the WENRA
homepage to all of us and the public.
What key lessons learned will I personally take back home?
• Nuclear decommissioning has become a mature technology application; there is an increasing
number of comprehensive approaches taking into account
− availability of resources,
− interfaces with other facilities at the site,
− critical infrastructure for waste management on the national and international scene,
− training and knowledge management.
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
45
• Indicators for the “maturity” are amongst others
− an increasing number of young, engaged professionals are attracted,
− an increasing number of enterprises see their chances for revenues,
− major discussions are no longer about individual solutions to technical problems but
on best generic approaches in the framework of individual national situations.
What do they have in common?
Decommissioning is a “waste-driven” process, but: as any process in a free market
environment it is driven by the money available.
• We did not have a single presentation on the funding of decommissioning but a lot of side
discussions on this issue. Obviously, it is very essential that the regulatory system ensures
availability of the necessary financial resources as they are required for the safe dismantling
and decommissioning. This leads me to the role of the regulator which is especially delicate in
a developing and changing industrial field:
• Regulators are expected to set the scene by establishing boundary conditions for acceptable
industrial solutions in guidelines or comparable documents. If we do so in an early phase of
technological evolution, this might narrow the range of possible developments and -after
some years of learning experience- most likely we will have to adapt and improve our
regulations. This could be commented as “being too restrictive” and working with “moving
targets”.
• Taking “risk informed” decisions is requested from us as a novel approach but to do so we
need “risk informed” license applications! That does not mean that our experts will only start
to think about these new ideas, if we receive a license application. In the contrary they will be
available for any in depth technical discussion on chances and risks of new approaches with
the licensees. I personally see at least one problem with this new approach:
Would we in different risk environments take different decisions on the same problem?
According to the new proposals the answer might be yes. Would we, as regulators, be able to
explain this and -even more important- would we consider that as appropriate?
• Eventually regulators will have to change their view on ultimate responsibility for waste
management remaining with the waste producer until the very end of the story. If transfer of
licenses for decommissioning including the ownership of waste and spent nuclear fuel proves
to be an option for successful decommissioning and even speeding up these projects, my
answer is clearly positive: why not, as long as it fits into your legal framework!
• The last message is the most trivial one: Talk to each other! There is no better way to achieve
progress but dialogue: to understand the position and driving forces for decisions of our
counterparts, to open-minded understand new ideas and developments and arrive at critical
but sound judgement on their chances and risks in the best tradition of what we require from
our licensees: continuous learning and improvement.
Concerning the last message this workshop has been a real success; we talked a lot to each other,
officially in the plenum, during the breaks and on many other occasions.
Thanks again to all of you and have a safe trip home!
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
46
Appendix A: Workshop Agenda
Wednesday, 6 November
08:00 – 09:00 Registration, Coffee reception
09:00 – 10:30 Opening Session Chair: Christine Wassilew (BMU, Germany)
WENRA Introduction Mina Golshan (Deputy Chief Inspector, ONR, UK)
International Safety Standards as a basis for the development of national regulations for decommissioning
Nelli Aghajanyan (IAEA)
Regulatory Aspects in Decommissioning: Experiences in Germany and Outlook
Wolfgang Cloosters (Director-General, BMU, Germany)
WENRA WGWD – How the SRLs work
Stefan Theis (Chair of WENRA WGWD)
WENRA WGWD – How SRLs are implemented and how “newcomers” benefit
Tamara Suschko (SNRI, Ukraine)
10:30 – 11:00 Coffee Break
11:00 – 12:30 Session 1: Decommissioning Strategies & Planning
Chair: Mario Dionisi (ISIN, Italy) Rapporteur: Sven Keßen (GRS)
Development of Rostechnadzor recommendations for planning of decommissioning during operation of nuclear facilities
Danila Savin (SEC NRS)
The need for a sustainable decommissioning paradigm
Kristina Gillin (Lloyd’s Register)
Waste management and decommissioning strategies
Vincent Cloître, Dorothée Conte (ASN, France)
Graded approach of regulation for decommissioning – Considerations on the concepts: risk informed, cost benefit analysis and reasonably practicable
Alain Ensuque (ENISS)
Panel discussion All authors of the session
Welcome Address
Svenja Schulze (Federal Minister for the Environment, Nature Conservation and Nuclear Safety, Germany)
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
47
12:30 – 13:30 Lunch break
13:30 – 15:20 Session 2: Regulatory Experience Chair: Stefan Theis (Chair of WENRA WGWD) Rapporteur: Sven Keßen (GRS)
Inspection practice for NPP in decommissioning
Theo Neuffer (UM BW, Germany)
Enabling regulations from the operator’s view
Phil Hallington (Sellafield Ltd)
Decommissioning authorization process and controls in Italy
Fabrizio Trenta (ISIN, Italy)
Authorization for and regulatory control of decommissioning in Sweden
Martin Amft, Christoffer Forss (SSM, Sweden)
Licensing Procedure and Inspection Fields in Decommissioning of Swiss NPP
Klaus Germerdonk (ENSI, Switzerland)
Panel discussion All authors of the session
15:20 – 15:50 Coffee break
15:50 – 17:20 Session 3: Limits of Harmonization and Specific Approaches
Chair: Simon Morgan (ONR, UK) Rapporteur: Sven Keßen (GRS)
Harmonization challenges during WGWD benchmarking
Stefan Theis (Chair of WENRA WGWD)
Site decommissioning by dedicated decommissioning licensee: a US approach
Corey DeWitt (Holtec)
Decommissioning of the MZFR Ulrich Scholl (KTE)
Digitalization for Knowledge Management in Decommissioning
Joaquin Toubes Tova (Tecnatom)
Panel discussion All authors of the session
17:20 End of day 1
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
48
Thursday, 7 November
08:30 – 09:00 Coffee reception
09:00 – 10:30 Session 4: Transition from Operation to Decommissioning
Chair: Bengt Hedberg (SSM, Sweden) Rapporteur: Sven Keßen (GRS)
EDF Energy Planning for Decommissioning during Operation
Jim Kershaw (EDF Energy)
Lithuanian regulatory policy, challenges and activities during transitional period from operation to decommissioning of Ignalina NPP
Saulius Stravinskas (VATESI, Lithuania)
The Development of Transition Period Requirements in the Slovak Republic
Miroslav Drahos (UJD, Slovak Republic)
NEA Regulators’ Forum – Outcomes of RF/WPDD Workshop on Regulation of Decommissioning
Mario Dionisi (ISIN, Italy); presented by Martin Brandauer (NEA)
Panel discussion All authors of the session
10:30 – 11:00 Coffee break
11:00 – 12:30 Session 5: Final Stages of Decommissioning
Chair: Pieter Lietava (SÚJB, Czech Republic) Rapporteur: Sven Keßen (GRS)
End state requirements for waste and site
Henrik Efraimsson, Åsa Zazzi, Martin Amft (SSM, Sweden)
Immediate dismantling and complete clean-out principles
Coralie Ravier (ASN, France), Patrice François (IRSN)
Recent developments in the regulation of UK nuclear sites in the final stages of decommissioning & clean-up
Simon Morgan (ONR, UK)
Panel discussion All authors of the session
12:30 Closing Remarks Stefan Theis (Chair of WENRA WGWD)
12:45 End of workshop, departure
WENRA Workshop on Regulatory Aspects of Decommissioning Berlin, 5-7 November 2019
49