+ All Categories
Home > Documents > World Bank Document · 2017. 2. 27. · KOC Karamay Oil Corporation LPEB Liaohe Petroleum...

World Bank Document · 2017. 2. 27. · KOC Karamay Oil Corporation LPEB Liaohe Petroleum...

Date post: 29-Jan-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
38
Document of The World Bank FOR OFFICLAL USE ONLY Report No. 11121 PROJECT COMPLETION REPORT CHINA KARAMAY PETROLEUMPROJECT ( LOAN 2426-CHA) SEPTEMBER11, 1992 Industryand Energy OperationsDivision China and Mongolia Department East Asia and Pacific Regional Office This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • Document of

    The World Bank

    FOR OFFICLAL USE ONLY

    Report No. 11121

    PROJECT COMPLETION REPORT

    CHINA

    KARAMAY PETROLEUM PROJECT( LOAN 2426-CHA)

    SEPTEMBER 11, 1992

    Industry and Energy Operations DivisionChina and Mongolia DepartmentEast Asia and Pacific Regional Office

    This document has a restricted distribution and may be used by recipients only in the performance oftheir official duties. Its contents may not otherwise be disclosed without World Bank authorization.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • CURRENCY EQUIVALENTS

    Currency Unit - Yuan (Y)

    Appraisal (Sep 1983) $1.0 - Y 1.98(Feb 1992) $1.0 - Y 5.48

    FISCAL YEAR

    January 1 to December 31

    WEIGHTS AND MEASURES

    1 cubic meter (CM) - 35.3 cubic feet (CF)1 thousand cubic meters (MCM) - 35.3 MCF1 million cubic meter (MMCM) - 35.3 MMCF1 billion cubic meter (BCM) - 35.3 BCF

    1 thousand cubic meters of natural gas - 9.31 kilocalories1 ton oil equivalent (TOE) - 10.2 million kilocalories

    I barrel (bbl) 0.85 SG crude oil - 0.135 tons- 0.159 CM

    - 42 US gallons1 kilogram coal equivalent (KGCE) - 0.64 kg oil equivalent (KGOE)

    ABBREVIATIONS AND ACRONYMS

    CNOOC China National Offshore Oil CorporationCNPC China National Petroleum CorporationCNTIC China National Technical Import CorporationCOCOM Coordination Committee for Multilateral Export ControlEOR Enhanced Oil RecoveryGOC Government of the People's Republic of ChinaITC International Tendering Company of CNTICKOC Karamay Oil CorporationLPEB Liaohe Petroleum Exploration BureauLPG Liquified Petroleum GasMIS Management Information SystemMOF Ministry of FinanceMOPI Ministry of Petroleum IndustryPCR Project Completion ReportSPC State Planning Commission

  • THE WORLD BANK FOR OMCIAL USE ONLYWashington, DC 20413

    U S A.

    Omce of ir1ctn.CW-CaIOpematmn, lvaluatwHn

    September 11, 1992

    MEMORANDUM TO THE EXECUTIVE DIRECTORS AND THE PRESIDENT

    SUBJECT: Project Completion Report on ChinaKaramav Petroleum Proiect (Loan 2426-CHA)

    Attached. for information, is a copy of a report entitled "Project

    Completion Report on China - Karamay Petroleum Project (Loan 2426-CiA)" prepared

    by East Asia and Pacific Regional Office. No audit of this project has been made

    by the Operations Evaluation Department at this time.

    Attachment

    | This document has a restricted distribution and may be used by recipients only in the performanceof their olilcial duties. Its contents may not otherwise be disclosed without World Bank authorization.

  • FOR OFFICIAL USE ONLY

    PROJECT COMPLETION REPORT

    CHINA

    KARAHAY PETROLEUM PROJECT(Loan 2426-CHA)

    TABLE OF CONTENTSPage No.

    Preface .iEvaluation Su-ary ............. .. .. .. .. . ii

    PART I PROJECT REVIEW FROM BANK'S PERSPECTIVE

    Project Identity .................. . 1Background ............... ... . . . . .Project Objectives and Description .1Project Design and Organization. 2Project Implementation .......... ... ... . 2Project Results. 4Project Sustainability .......... ... ... . 8Bank's Performance. 8Borrower's Performance. 9

    Project Relationship ............ ..... . 9Consulting Services. 9Project Documentation and Data. 9

    PART II PROJECT REVIEW FROM BORROWER'S PERSPECTIVE .10

    Report of Karamay Oil Corporation .10Report of Liaohe Petroleum Exploration Bureau .12

    PART III STATISTICAL INFORMATION ..... . . . . . . . . . . . . 13

    Related Bank Loans .3.... .. . . . . . .. . . . . . 13

    Project Timetable .13Loan Disbursements ............ ..... . . 14Project Implementation .15Project Costs and Financing .16Project Results .17Status of Covenants ............ ..... . . 18Use of Bank Resources .......... .... ... . 25

    Annex 1 Economic Analysis . t

    Annex 2 Key Financial Indicators.

    This document has a restricted distribution and may be used by recipients only in the performanceof their official duties. Its contents may not otherwise be disclosed without World Bank authorization.

  • - i -

    PROJECT COMPLETION REPORT

    CHINA

    KARAMAY PETROLEUH PROJECT(Loan 2426-CHA)

    PREFACE

    This is the Project Completion Report (PCR) for the Karamay Petro-leum Project in China, for which Loan 2426-CHA in the amount of S100.3 millionwas approved on May 29, 1984. The loan was closed after two extensions onMarch 31, 1991. On May 26, 1989, an amount of $7 million from the loan wascanceled at the request of the Government. The last disbursement was made onJuly 25, 1991 and a final undisbursed amount of $3.8 million was canceled.

    The PCR was jointly prepared by the Industry and Energy Operations

    Division of the China and Mongolia Department of the East Asia and PacificRegional Office (Preface, Evaluation Summary, Parts I and III), and the Bor-rower (Part II).

    Preparation of this PCR was started during the Bank's PCR mission in

    February, 1992, and is based, inter alia, on the Staff Appraisal Report; the

    Loan and Project Agreements; supervision reports; correspondence between theBank and the Borrower; and internal Bank memoranda.

  • 'S

  • - ii -

    PROJECT COMPLETION REPORT

    CHINA

    KARAMAY PETROLEUM PROJECT(Loan 2426-CHA)

    EVALUATION SUMMARY

    Obiectives

    1. The objectives of the project were: (a) to provide support inexpanding the exploration program in the Karamay oil belt and its southernextension; (b) to evaluate the potential of heavy oil in the Karamay and

    Liaohe oil fields; and (c) to transfer modern technology which would in turn

    enhance efficiency in both exploration and production.

    Implementation Experience

    2. The project was implemented successfully. Its scope was expanded toinclude heavy oil production consequent to the success of the pilot schemes.

    As a result, the project costs increased by 28 percent. Most of the physicalcomponents were completed largely on schedule. However, the initial delays in

    procurement (about two years) led to significant delays in implementation of

    the various technical assistance and training components. These delays could

    be attributed to a number of reasons, including lack of experience with Bank

    procedures, fragmentation of responsibilities among various Chinese agencies

    and cumbersome internal clearance procedures.

    Results

    3. The project objectives have been substantially met. Specifically,

    both light oil and heavy oil reserves have been augmented. Oil productionwhich was declining at the inception of the project began to rise with produc-

    tion at the close of the project being 1.5 times that at the start. An opti-

    mal thermal recovery scheme for heavy oil is in place. The most satisfying

    result, however, is that technology transfer in exploration--seismic data

    acquisition and data processing, reservoir engineering, heavy oil production

    etc.--has taken place with the cooperation of foreign institutions, consul-

    tants and service and supply contractors. The Karamay Oil Corporation (KOC)

    has now a pool of geoscientists and petroleum engineers who have been trained

    in state-of-the-art technology, who also possess modern equipment, instruments

    and tools. It is the application of this newly acquired technology that led

    to the discovery of the additional oil-in-place and its production.

    Sustainability

    4. The significant increases in original oil-in-place during the proj-ect period and the success achieved in recovering heavy oil economically indi-

    cate that the project will run its full course. Oil production, which was 4.0

    million tons at the start of the project, was 5.75 million tons in 1990, and

    is planned to reach a peak of 6.7 millions in 1995/96 before natural decline

  • - iii -

    sets in. As for keeping up with modern technology, the China National Petro-

    leum Corporation (CNPC) and KOC regularly exchange knowledge and experience

    with other participanta in the world oil industry. Therefore, it is expected

    that the economic benefits derived from this project would be sustained (Part

    I, para. 7.1).

    Findings and Lessons Learned

    5. This was the third Bank-financed petroleum project in China. It

    followed the Daqing and Zhongyuan projects after about 16 months. But the

    beneficiary was another unit of CNPC, namely KOC, which is situated in the

    remote area of Xinjiang province of China. KOC's lack of experience with Bank

    procedures, together with the continuing inadequacy in interagency coordina-

    tion within China, resulted in procurement delays as in the case of the other

    two projects. KOC did not have the authority to procure Bank-financed goods

    directly, nor was it allowed to process loan disbursement applications

    directly. KOC had to procure through an authorized agent, the China National

    Technical Import Corporation (CNTIC), and disbursement applications were cen-

    trally processed by CNPC, formerly the Ministry of Petroleum and Industry.

    Delegation of greater authority for direct procurement and filing of disburse-

    ment applications to the project executing agencies would be desirable. On

    the Bank's part, project implementation schedules when prepared should provide

    for a time reserve for unforeseen problems.

    6. The Bank played a catalytic role in the transfer of modern technol-

    ogy to KOC. The Bank assisted KOC in picking the functional areas which

    needed strengthening and in the designing of the technical assistance program

    and of the training subcomponent. The Bank's involvement during the procure-

    ment phase and throughout the project implementation was appreciable. Bank

    staff assisted in selection of equipment, preparation of terms of reference

    for studies, interaction with consultants and review of consultant studies.

    However, in retrospect it appears that one or two studies assigned to consul-

    tants had a wider scope than was strictly necessary for the purposes of the

    project. The Bank could have assisted in trimming the scope to the needs and

    helped to avoid the protracted time consultants took to complete the studies

    (Part I, para. 8.1).

  • PROJECT COMPLETION REPORT

    CHINA

    KARAMAY PETROLEUH PROJECT(Loan 2426-CHA)

    Part I. PROJECT REVIEW FROM BANK'S PERSPECTIVE

    1. Project Identity

    Project Name: Karamay Petroleum Project

    Loan Number : 2426-CHARVP Unit : East Asia and Pacific RegionCountry ChinaSector : EnergySubsector Petroleum

    2. Background

    2.1 For over three decades until the end of the 1970s, China was remark-

    ably successful in following a policy of self-reliance in the development of

    its energy resources. However, the rate of oil and gas discovery started

    declining in the early 1980a. This adverse trend arose out of several fac-

    tors. Mainly, the prospective areas were becoming more complex to explore,

    and exploration and production techniques required updating to add to the

    reserves/recover a higher proportion of the oil-in-place. State-of-t'^r art

    technology had to be sought and manpower skills upgraded. Sophistica 1 d

    equipment, instruments and appliances were to be introduced.

    2.2 . In the early 1980s, GOC requested the Bank to provide technical

    assistance to enhance the productivity of Chinese oil companies, firstly by

    the identification of technological constraints and next, by facilitating

    effective appraisal and exploitation of hydrocarbon prospects through the

    selection of technologies which could be adopted rapidly to improve the qual-

    ity of ongoing exploration and production efforts.

    2.3 Karamay was the third project of a series of five Bank-financed

    petroleum projects in the country. This project has not only augmented t.f

    light and heavy oil reserves of KOC, resulting in a reversal of a potential

    decline in production to one of steady increase; it has also provided training

    for KOC staff in China and abroad. A pool of geoscientists and engineers well

    versed in modern methods of exploration and production of heavy oil has been

    created. The project also provided sophisticated equipment, laboratory and

    tools, which are now being utilized for accelerated exploration and develop-

    ment in Xinjiang province.

    3. Proiect Oblectives and Description

    3.1 The objectives of the project were (a) to provide support in expand-

    ing the exploration program in Karamay oil belt and its southern extension;

    (b) to evaluate the potential of heavy oil in the Karamay and Liaohe oilfields

    and to evolve the optimum method of thermal recovery to enhance the production

  • - 2 -

    of heavy oil; and (c) to transfer modern technology which would in turn

    enhance efficiency in both exploration and production.

    3.2 The project comprised of (a) exploration and evaluation of light-oil

    potential in the KOC operating area; (b) evolving the optimum recovery method

    for heavy oil in KOC and Liaohe areas; and (c) transfer of technology for oil

    exploration and heavy oil production, which were to be achieved through:

    (i) consultant studies (geological, reservoir engineering, training, utiliza-

    tion of South China sea gas and costing); (ii) carrying out of high-resolution

    and 3D seismic surveys, processing and interpretation; (iii) upgrading of data

    processing facilities; (iv) acquisition of computer equipment (hardware and

    software) and other sophisticated oilfield equipment; and, (v) establishing of

    a center for training of skilled workers and professionals.

    4. Proiect Design and Orxanization

    4.1 The exploration and appraisal for light oil was designed to progress

    through successive stages. Conventional, high-resolution and 3D seismic sur-

    veys would be followed by pinpointed exploration/appraisal/development drill-

    ing and thereafter more light oil would be produced. For heavy oil, the ongo-

    ing "huff and puff" pilot scheme of steam injection would be closely examined

    by consultants and modifications and improvements suggested for incorporation

    with a view to putting in place an optimal recovery method. The technical

    assistance component was elaborated for implementation as follows: (a) 2D

    (conventional and high-resolution) and 3D seismic surveys using modern equip-

    ment were planned before exploratory and delineation drilling was done, so

    that the success ratio of finding hydrocarbons could be raised; (b) pilot

    schemes for recovery of heavy oil were carefully designed using a multitude of

    data from Karamay and Liaohe and tested for reliability as possible in the

    laboratory, before field experimentation; (c) all opportunities for training

    were planned to be availed of, namely suppliers of equipment had to projide

    training in the operation and maintenance of the equipment, consultants carry-

    ing out studies had to associate KOC personnel with them, service contractors

    like the foreign seismic survey parties had to coopt KOC staff in the crews,

    specific institutional courses in petroleum subjects abroad were to be

    attended by selected professionals and a training center for skilled workers

    and professionals was to be organized with assistance from competent consul-

    tants. Such attention to project designing together with monitoring of the

    progress contributed to the achievement of all the objectives.

    4.2 KOC implemented the project with the assistance of consultants and

    contractors. It established a project team under the immediate direction of

    the Deputy General Manager to provide guidance and supervision for the execu-

    tion of the project. The Liaohe heavy oil component was implemented by Liaohe

    Petroleum Exploration Bureau (LPEB).

    5. Prolect Implementation

    5.1 The project was implemented successfully. In addition, the heavy

    oil component, which according to the original design of the project was lim-

    ited to evolving the optimum method of recovery of heavy oil, was expanded in

    scope to include systematic production of heavy oil employing steam injection,

    incorporating recommendations made in the consultant studies. This involved

  • - 3 -

    drilling of several wells to produce heavy oil. As a result, KOC maintained a

    steady increase both in light and heavy oil production. Delays occurred, how-

    ever, in procurement and the execution of various technical assistance compo-

    nents, with the closing date of the loan having to be extended by two years.

    These delays can be attributed to a number of reasons: (a) a lack of coordi-

    nation between related agencies--for example, KOC procures through an agent,

    the International Trading Corporation, disbursements are made by China

    National Petroleum Corporation (CNPC) and this tripartite allocation of work

    took time to move in harmony; (b) the slow process of soliciting and evalua-

    tion of bids; (c) protracted contract negotiations; (d) frequent revision of

    scope of contractual work and lack of clear understanding between client and

    consultant regarding contract administration (in the case of the reservoir

    study); (e) certain suppliers not fulfilling their contractual obligations in

    time; (f) the export restrictions and delays (of a supplier country) under the

    procedures of a coordination committee for multilateral export control (COCOM)

    in issuing export licenses--downgrading of the computers for seismic data pro-

    cessing to expedite its export had to be done; (g) complications due to fail-

    ure in following the Bank's guidelines for evaluation of bids (in the case of

    the training simulator). In future projects, the possibilities of such impe-

    diments bedeviling procurement should be kept in view in drawing up implemen-

    tation schedules.

    5.2 The deviations in implementation from what was envisaged during

    appraisal were mainly the following: (a) time slippage by about one to two

    years in the completion of the different components for reasons explained in

    the previous paragraph; (b) expansion of the project scope to include produc-

    tion of heavy oil; (c) of the five studies (geological, reservoir engineering,

    training curricula and training methods, costing and utilization of South

    China Gas), the last two were carried out by Chinese experts and not by out-

    side consultants. The costing study was satisfactory. The South China Gas

    utilization study, carried out in house by CNOOC, following a request from the

    Ministry of Energy to the Bank that CNOOC had the competence to make the study

    and should be so conducted, did not cover overall gas development economics

    and also omitted end user investments, which the Bank considered to be crucial

    elements of the study.

    5.3 Project Costs. The total financing required (including front-end

    fee of $0.25 million) amounted to $965 million equivalent, as compared to the

    appraisal estimate of $754 million equivalent (Table 5A in Part III).1/ The

    overrun is largely explained by the expansion in the scope of the project to

    include production of heavy oil through drilling of injection/production

    wells, and import of casings, tubing and other equipment and material for this

    purpose. Ninety delineation and 1,126 development wells for production of

    1/ KOC has calculated the actual project cost in US$ equivalent at $743.09

    million in Part II or as within the "budget" (para. 3.2 of Part II). This

    is due to KOC accumulating local currency costs to the end of 1991 and

    converting these costs to USS at the exchange rate as at the end of 1991.

    The PCR mission has taken th. local currency costs, year by year, and

    converted the yearly costs to USS, using each year's exchange rate. The

    exchange rate changed by gradual steps from $1 - Y 1.98 in 1984 to Sl -

    Y 5.24 in 1991.

  • heavy oil were drilled during the period 1985-89. The appraisal report had

    estimated that 160 wells would be drilled for delineation of heavy oil in

    Karamay. All the wells were shallow, going to a depth of about 600 meters.

    The other reason for cost overrun was that the foreign seismic crews were

    awarded additional survey work and an extension of contract by two years,

    resulting in more line kilometers being shot and more 3D coverage being car-

    ried out than was envisaged at first. On the other hand, savings (partly

    offsetting the increase in survey costs) in seismic data processing were

    achieved, due to more work being done at the data processing center than was

    estimated at appraisal. The total project cost increased by about 28 percent

    (36 percent in local costs and 14 percent in foreign exchange).

    5.4 Proiect Financing. A comparison of actual project financing with

    appraisal estimates is set out in Table 5A, Part III. Possible cofinancing

    with export credits did not materialize. Instead, tubular goods were cen-

    trally procured by MOPI and resold to various oilfields in local currency.

    The financing requirements for all the local currency were met by KOC's own

    resources.

    5.5 Disbursement. A comparison of actual disbursements with appraisal

    estimates is presented in Table 3, Part III. As noted earlier, procurement

    and related disbursements were delayed and the closing date was extended by

    two years. Actual costs of imported goods and services financed by the Bank

    were close to the appraisal estimates; the Bank loan disbursements constituted

    89.5 percent of the approved loan of $100.3 million. In May 1989, on a

    request from GOC, the Bank agreed to cancel $7.0 million of the loan, repre-

    senting the allocation for purchase of certain equipment which was dropped

    from the foreign purchase list. On closing of the loan, an undisbursed amount

    of $3.8 million was canceled.

    5.6 Loan Allocation. The original and actual loan allocation is shown

    in Table 5B, Part III. Unallocated amounts ($13.8 million) were largely real-

    located to equipment and seismic surveys.

    6. Prolect Results

    6.1 Proiect Oblectives. The project objectives have been substantially

    achieved. Without the project, it is assumed that the consequences, in the

    absence of any other action by COC/KOC, would have been: (a) light oil pro-

    duction would have declined from 4 million tons in 1984 to about 2.9 million

    tons in 1990 with a further reduction to about 1.4 million tons in 2004;

    (b) heavy oil production would have remained insignificant; and (c) KOC per-

    sonnel would not have been trained and would not have applied modern technol-

    ogy in the areas where opportunities were opened up to them under the project,

    nor would KOC have acquired relevant modern equipment. The project resulted

    in the following: (a) seismic surveys, conventional, high-resolution and 3D,

    were done using modern equipment and techniques, similarly in data processing

    leading to release of precise locations for exploratory/appraisal drilling and

    achievement of a success ratio of I in 3; (b) in sequel, more light oil as

    well as heavy oil reserves were discovered and produced, with light oil pro-

    duction maintained at or above 4 million tons per annum (para. 6.3) and heavy

    oil production increasing from almost nothing to about 25 percent of total oil

    production in 1990; (c) in respect of heavy oil, an optimum method for recov-

  • -5-

    ery through two-stage injection of steam was proved (huff and puff followed by

    steam drive); (d) KOC professional and technical staff were trained in moderntechnology in many areas of exploration, reservoir analysis and oil produc-tion; and (e) KOC acquired relevant modern equipment, tools and instruments.

    At Liaohe, however, while a design for a heavy oil pilot has been prepared byconsultants, and LPEB staff trained in modern heavy oil technology, the eco-nomics are not in favor of heavy oil production under the prevailing worldprices for crude oil. The details of the project results are discussed below.

    6.2 Seismic Data Acquisition and Processing. The highlights were(a) the effective interaction of KOC personnel with three foreign seismic dataacquisition crews; and (b) the installing of modern data processing equipment,the operation of which KOC personnel have become proficient. The project hasenabled KOC seismic crews to carry out surveys at the edge of Junggar basin,which was not technically feasible earlier. The productivity of KOC crews hascome up to international levels thanks to the modern seismographs, new trans-portation and ancillary equipment. The refurbished data processing center,with its state-of-the-art trained geoscientists, operates at 95 percent avail-ability and carries out, besides normal processing of data, 3D processing andspecial processing, all at a high-quality standard. Interpretation of themore detailed and precise data in the basins under KOC control has indicatedthat oil in place, being proved by drilling, is likely to be thrice the ear-lier estimates taking into account the deeper oil-bearing structures and iso-lated potential oil sands.

    6.3 Exploration/Development Drilling. In all, 370 exploration an!development wells were planned for light oil under the project. HoweverT, KOCdrilled 201 exploration/appraisal and 500 development wells (by March .989).KOC adjusted the drilling plans in various areas upon review of the explora-tion/appraisal results. Consequently, drilling was curtailed in WuerheHungchiba area, and major exploration/development was concentrated inHangshanzui--Chepaize and Karamay--Baiqukuan areas to maintain/improve lightoil production. Annual light oil Rroduction which would have declined from3.98 million tons in 1984 to 2.93 million tons in 1990 without the proiect,stayed around an average of 4.78 million tons during 1985-90 due to the proi-ect. Nevertheless, between 1991 and 1996 the median production is placed at4.4 million tons per annum, and thereafter a slow decline to 2.2 million tonsby the year 2000 is expected. With regard to heavy oil, it has been notedearlier that 90 exploration/delineation wells and 1,126 development wells weredrilled against the appraisal estimate of 160 exploration/delineation wells.Heavy oil production commenced at 20,000 tons in 1984. By steady steps itrose to 1.44 million tons in 1990. By the year 2000, the production isexpected to reach 2.68 million tons involving further investments beyond theproject investments.

    6.4 Heavy Oil Pilots. KOC had designed its own pilot before the projectand had been experimenting with it in one production district. Under theproject, foreign consultants advised on the design and construction of thesurface facilities and KOC adopted most of the recommendations, appreciatingthe technical and cost advantages. The consultants had also prepared thedesign of a thermal recovery project to be tried out in one of the blocks ofthis production district. This was an expansion of the "huff and puff" forsteam injection into a two-stage technique of "huff and puff" and a steam

  • - 6 -

    drive. KOC has adopted it. For Fenchang in another production district, the

    consultants had prepared a techno-economic study for development and proces-

    sing of extra heavy oil. It is not economic to develop this area at present.

    6.5 With regard to Liaohe comDonent, the consultant had designed a heavy

    oil pilot and had imparted training to a number of technical staff of Liaohe

    Petroleum Exploration Bureau (LPEB), abroad and in China. Thus, the transfer

    of technology took place successfully. However, the economic evaluation of

    the pilot showed that it would not be viable to invest in a heavy oil pilot in

    the designated area under the present prices for heavy oil in the world mar-

    ket.

    6.6 Technical Assistance. This comprised five studies, training and

    establishment of a training center: (a) The geological study was undertaken

    for a comprehensive understanding of the structural geology of the Junggar

    basin. KOC staff generally found that their own understanding of the basin

    was confirmed by the consultants. But the benefits to KOC were primarily in

    learning the consultant's research methods and methods of map compiling.

    (b) The reservoir study was aimed at successfully developing the tight con-

    glomerate Wuerhe reservoir. The recommendations of the consultants are being

    implemented and production decline which would have been about 90,000 tons

    annually, from the old fields in the reservoir is presently controlled at

    15,000 tons annually. ROC engineers who participated in the study by the con-

    sultants were exposed to modern technology in geological modelling, well log

    analysis, well test analysis and reservoir simulation. (c) The costing study

    was carried out by Chinese experts from other agencies and institutions. It

    is a good study with several recommendations on costing of discrete opera-

    tions, of light oil and heavy oil output separately, proper allocation of com-

    mon costs, reconciliation with finance accounts of costs from costing data,

    etc. KOC has accepted the recommendations. (d) The training study by con-

    sultants was to devise the training curricula for skilled workers and profes-

    sionals of KOC. The teachers were trained abroad, who in turn trained the

    local instructors. They conduct seven different types of courses at the

    training center. During the project period, about 1,900 skilled workers and

    professionals were trained. The training simulator obtained under the proj-

    ect, however, has not been commissioned due to a contractual snag under reso-

    lution, with the consequence that this sophisticated training aid is yet to

    benefit KOC trainees. Had the simulator been available as a training acces-

    sory, the quality of the training would have been enhanced. (e) The South

    China Gas Utilization study was carried out by CNOOC as mentioned in para.

    5.2.

    6.7 The overseas training part of technical assistance was effectively

    implemented. Thirty-three technical personnel were trained in various petro-

    leum subjects, in institutions abroad. Other opportunities which were availed

    of for training in and out of the country have been discussed in the forego-

    ing.

    6.8 The computer center in Karamay was equipped with modern hardware and

    software under this project to provide for the following: (a) database man-

    agement for oilfield development plans based on reservoir simulation and risk

    analysis; (b) reservoir engineering; and (c) storing and processing of admin-

    istrative data.

  • 7-

    Economic Evaluation

    6.9 The quantifiable benefits of the project are derived from the addi-

    tional production of both light crude oil and heavy crude oil by virtue of the

    accretion to the recoverable reserves made possible by the project. At

    appraisal no economic rate of return (ERR) was indicated; however the pros-

    pects for new discoveries of light oil and the heavy oil pilot project proving

    economic were rated high. In the event, as Annex 1 brings out, the project

    will have an economic rate of return of 31 percent, which is good.

    6.10 The ERR has been based on incremental volume of production of oil

    and the additional investment and operating costs under the project as well as

    needed to sustain the incremental production in the future. KOC has main-

    tained data on the cost of producing heavy oil, which commenced at 20,000 tons

    of output in 1984 and has since risen (in 1991) to 1.64 million tons/year. In

    1990, the cost of producing heavy oil was about $53/ton compared to a value of

    about $95/ton at the field. In that year, light oil cost $33/ton to produce

    compared to a value of about $110/ton at the field.

    Financial Performance

    6.11 KOC Finances. Salient features of KOC's finances (present and past)

    are summarized in Annex 2. During 1984-90, KOC had a production growth of

    4.5 percent annually, but annual operating costs registered an average

    increase of 19 percent, outpacing the former by a larger margin than was

    anticipated at appraisal. This was due to heavy oil production, the ratio of

    which to total oil production changed from 0.5 percent in 1984 to 25 percent

    in 1990. KOC's financial performance in this period was however good, the

    financial ratios were satisfactory and the internal cash generation sufficient

    to cover over 30 percent of capital investments and maintenance. GOC has

    recently raised the prices for crude oil under the two-tier formula in force

    from 1981, the upper tier of which applicable to production above 3.64 mn..llion

    tons in a year at about $95/ton currently is not too short of the interna-

    tional parity price as net backed to the field (see para. 6.10). The lower

    tier at about $40/ton currently applicable up to 3.64 million tons remains far

    short of such parity. In 1992 and beyond, this price will not adequately

    cover the cost of production of the first portion of 3.64 million tons. With

    the profits accruing in respect of the portion of the production above 3.64

    million tons, KOC would make overall profits, but sharp drops in internal cash

    generation will occur, specially after 1995/96 when total oil production is

    expected to peak at 6.7 million tons. GOC, it is presumed, will in due time

    make necessary revisions in the administered prices. KOC for its part should

    optimize costs of operation. Norms and targets exist in all varieties of

    operation, from exploration to production. A review of these norms and tar-

    gets with a view to tightening them and also taking on more profit-making

    activities, such as bidding for contracts in other parts of China or even

    abroad, is recommended.

    6.12 The conditionalities for this project did not include any tradi-

    tional financial performance covenant. Instead, the Bank's objective to pro-

    mote prudent financial management was achieved through KOC's compliance with a

    covenant which required the extension of the financial planning horizon and

    furnishing the Bank with a five-year rolling plan and its annual review.

  • - 8 -

    Further, ROC fulfilled its assurance that an evaluation of its costing would

    be undertaken with the assistance of consultants (para. 6.6(iii)].

    6.13 Proiect Finances. Financial projections made in respect of the

    project as such (Annex 2) show that if present prices remain unchanged in con-

    stant terms, the financial rate of return to KOC will be 11 percent, which is

    minimally acceptable. No estimate of the return was made at appraisal. Pri-

    marily, the low return is due to the higher costs of producing heavy oil, the

    proportion of which in the total additional oil will keep rising; at the same

    time the decline in light oil production which will set in after 1995/96 will

    make the unit cost of its production also high. It will be recalled that the

    project economic rate of return is estimated at 31 percent, which indicates

    that COC's share of the net benefits of the project will be far larger than

    KOC's. I

    Environmental Impact and Safety

    6.14 KOC has conducted its seismic, drilling and production operations in

    line with modern industrial practices. It has paid due attention to environ-

    mental and safety considerations. The oil and liquid wastes were collected

    and treated. Since most of the operations were conducted in isolated barren

    areas, the ecological hazards were minimized. Prior to the project, the

    ' safety procedures at Karamay were not satisfactory. However, the recommenda-

    tions made under the safety study for the Daqing and Zhongyuan projects and

    the heavy oil study were implemented by KOC, improving significantly the

    safety standards.

    7. Proiect Sustainability

    7.1 During the project period 1985-90, original light oil-in-place

    increased by 151 million tons to reach 195 million tons at the end of 1990.

    Original heavy oil-in-place went up from zero to 110.2 million tons at the end

    of 1990. In 1990 incremental production due to the project, of light and

    heavy oil, accounted for 2.82 million tons out of a total production of 5.75

    million tons. The planned production profile until 2004 shows that while the

    total production would peak at about 6.7 million tons in 1995/96 and decline

    to about 5.3 million tons by 2004, incremental production due to the project

    and subsequent investments of a lesser order to sustain the gains in produc-

    tion, would rise to about 4 million tons by 1995/96 and then gradually

    decline. The production increases have thus been significant until now and

    would tend to remain so over the next 10 to 12 years assuring sustainability

    of the project. The other characteristic of the project, the technical

    upgrading of KOC, would require efforts by KOC to maintain contact with the

    outside world for exchange of technical knowledge and experience and acquiring

    of useful new generation equipment to further improve its performance in the

    future.

    8. Bank's Performance

    8.1 The Bank played a catalytic role in the transfer of modern technol-

    ogy and institution building. Bank assisted KOC in picking the functional

    areas which needed strengthening and in the designing of the technical assis-

    tance program and of the training subcomponent. The Bank's involvement during

  • the procurement phase and through project implementation was appreciable.

    Bank staff assisted KOC in selection of equipment, observance of procurement

    procedures, preparation of terms of reference for various studies, review of

    consultant studies, and overall interaction with consultants. The interaction

    with the consultant engaged to propose optimum methods for recovery of heavy

    oil enabled the Bank to advise KOC to take up regular production of heavy oil,

    appropriately expanding the scope of the project to include such production.

    As noted in earlier paragraphs, heavy oil has become an important product of

    KOC for sustaining its economic success.

    8.2 China has appreciated the role of the Bank in all the five energy

    (oil and gas) projects approved by the Bank between 1983 and 1986. Bank

    involvement gave it a window to modern technology and the practical means of

    acquiring it. With their familiarity with technical progress in different

    aspects and different countries, of hydrocarbon exploration, development and

    production and with the know-how on how to get the best consultants, contrac-

    tors and suppliers of sophisticated equipment, Bank staff were in a unique

    position to assist China in the fulfillment of its longing to catch up on

    modernization.

    9. Borrower's Performance

    9.1 In spite of delays in procurement, the physical components were

    largely completed well within two years of the original schedule. In KOC, the

    coordination and monitoring of project implementation was satisfactory. Proj-

    ect expenditure was kept under control through periodic reviews of physical

    and financial progress. KOC staff were highly motivated to absorb new skills

    and use new technology. The sophisticated equipment imported through the

    project is being effectively utilized.

    10. Proiect Relationship

    10.1 The Bank and KOC developed a good working relationship and a spirit

    of cooperation prevailed throughout the course of project preparation and

    implementation.

    11. Consultant Services

    11.1 The consultants in general performed well and their reports were

    professionally prepared to the satisfaction of the client. Moreover, the

    consultants readily agreed to work with KOC personnel and pass on expertise in

    research and analytical methods.

    12. Proiect Documentation and Data

    12.1 Both the Staff Appraisal Report and loan documents provided an ade-

    quate framework for project implementation. Supervision reports provided an

    adequate review of the progress of the project. However, many supervision

    missions did not include a Financial Analyst and gaps in financial information

    and the financial progress of the project prevailed. KOC's own contribution

    to the PCR and its ready supply of documents during the PCR Mission went a

    long way in making the PCR as complete as possible.

  • PROJECT COMPLETION REPORT

    CHINA

    KARALAY PETROLEUM PROJECT(Loan 2426-CHA)

    Part II. PROJECT REVIEW FROM BORROWER'S PERSPECTIVE

    A. Report of Karamay Oil Corporation 2/

    1. Prolect Achievements

    1.1 KOC fully completed the exploration and development ororam. Withthe use of advanced technology and modern equipment, KOC found 264 milliontons (Mt) of oil-in-place (151 Mt light and 113 Mt heavy oil). In 1990, oilproduction was 5.75 Mt tons or 115 percent of projection for the year.

    1.2 The foreign seismic survey contract was extended by two years untilApril 1989 and the three foreign crews shot 17,334 km, and also performed 3Dseismic survey. The results provided better data for enlarging the reservoirareas and KOC's own quality of seismic survey work was enhanced.

    1.3 As for drilling during 1985-89, 291 exploration wells were drilled--201 for light oil discovery and 90 for heavy oil discovery. Sixty-eight per-cent of the wells had commercial zones of oil.

    1.4 The seismic data processing center at Urumchi was upgraded with theaddition of a Cyber 855S computer. The center processed 193,196 km of stan-dard-line km and 463 km2 of 3D data. The results enabled an efficient drill-ing program and reservoir evaluation. The imported Sperry 1100172 computerlocated in Karamay is assisting in storina and processing of oil field techni-cal data. It has, by enabling a better understanding of the reservoir, madecontributions in raising oil production.

    1.5 The consultants completed the study for the design and test of proj-ects for thermal recovery of heavy oil in Karamay. By 1989, the heavy oilpilot testing was completed. Development wells drilled for heavy oil andrecovery through steam injection using 36 steam generators helped to producegood quantities of heavy oil going up to 1.44 mt in 1990.

    1.6 The consultants' work on the conceptual process design of surfacefacilities for commercial development of heavy oil in District No. 9, designand study for the thermal recovery of heavy oil in District No. 9 Block 8 andfeasibility study for development and processin1 ef Vevvy oil in Fengchangarea were useful. The last is to be implemented.

    1.7 The consultants' training program in Canada for 14 KOC staff iscommended.

    1.8 The consultants did a good job in respect of the traininx study andestablishment of the training center for training skilled workers and Profes-sionalrs. Comprehensive teaching material for seven courses (drilling, produc-tion, downhole, mud, cementation well testing and logging) were provided. Sixprofessional teachers trained by the Council are qualified to give lectures on

    2/ Summarized from a comprehensive report prepared by KOC. A copy of thereport is in the project file.

  • the seven courses. The consultants provided a useful list of equipment andinstruments for the center. About 1,000 skilled workers and professionals arebeing trained each year at the center.

    1.9 Thirty-three professionals were trained in academic institutionsabroad--two obtained PhDs, 1 Masters, and 30 others instructions in petroleum

    subjects.

    1.10 Studies as required in the Project Agreement were undertaken. Thegeological study by consultants was not remarkable for its findings, but KOC

    staff got an insight into the research and organization methods of the consul-tant. The consultants carried out the reservoir study. There were someissues about the scope of the work which were resolved. The results of the

    study were appreciated by KOC as well as the incidental training of KOC staff.Costing study was done by domestic consultants who, it was felt, would have a

    better grasp of the financial system in China. KOC agrees that the lacunaspointed out exist and need remedying. (The training study is discussed inpara. 1.8. The South China Sea Gas Utilization study was done by CNOOC.)

    1.11 Equipment procurement proceeded without undue problems except forclaim adjustments on completion of contracts and the one case of an unful-filled contract for the training simulator. Six contracts for technical ser-vices and 37 contracts for purchases were handled. Seventy-two percent of the

    loan amount was utilized in these contracts. ICB procedures were applied to

    56 percent of the loan amount.

    2. Suggestions from KOC

    2.1 Procurement procedures need to be streamlined and the functions and

    responsibilities of agencies involved in procurement clearly defined lestschedules are not adhered to.

    2.2 Responsible agencies should give prior assurances about conformingto procurement schedules, accept and work to the time limits for processingeach phase.

    2.3 Standard procurement documents for different modes of procurement

    should be prescribed.

    3. Role of World Bank and KOC

    3.1 Bank staff made significant contributions in the light of inexperi-

    ence of KOC in the implementation of the project. Assistance was given in

    expediting decision-making, preparing terms of reference for consultants,execution of the thermal recovery of heavy oil, review of technical specifica-

    tions, evaluation of bids, and enhancement of procurement efficiency.

    3.2 KOC was responsible for implementation of the project. A projectteam under the Deputy General Manager provided guidance and coordination.Specific assignments of tasks to concerned departments was made. A technical

    cooperation department for purchase of equipment was nominated. KOC compiledTORs, procurement documents, evaluation reports and project progress reports.

    CNPC authorized KOC to have direct contact with the World Bank in procurement/

  • - 12 -

    implementation activities.3/ The project was implemented on schedule andwithin the budget. All covenants were observed.

    3.3 KOC had developed an effective relationship with the Bank.

    B. Report of Liaohe Petroleum Exploration Bureau (LPEB) 4/

    3.4 Project Achievement. Project objectives were all basically met.Two wells were picked, in consultation with the consultants for coring. Core,water and oil samples were flown to Canada. Petrophysical, geological, reser-voir engineering, drilling and completion technology studies were carried outby consultants associating LPEB experts. A thermal recovery (steam injection)technology and a technology to monitor it were devised. Conceptual design ofsurface gathering and transportation was prepared. A pilot block of 1 km2 wasselected to verify the results of the study. However, further implementationwas deferred on economic considerations.

    3.5 Proiect Economics. Eighty-seven wells would have been drilled inthe 1 km2 area selected. An investment of $162 million would have been made.But sale of oil, gas and condensate which would have been produced would haveearned $120 million at world parity prices. On the face of it, it was notadvisable to launch the field experimental project.

    3.6 Proiect Delay. The study had a one-year delay for various rea-sons.5/

    3.7 Experience Gained. LPEB is setting up heavy oil pilots using ther-mal techniques to improve heavy oil production from Shugong field (not part ofthe Bank project, but using experience gained in designing a pilot forLiaohe). LPEB benefited from the close working with the Canadian consultantand drew a number of lessons for administering such consultancy contracts moreefficiently in future.

    3/ Apparently, this was for follow-up after the International Trading Corpo-ration initiated procurement on behalf of KOC and had placed the orders;also, disbursements applications were processed by CNPC.

  • - 13 -

    PROJECT COHPLETION REPORT

    CHINA

    KARAMAT PETROLEUM PROJECT

    (Loan 2426-CiA)

    PART III. STATISTICAL INPORMATION

    Table 1; RELATED BANK LOANS

    Year of

    Loan Title Purpose approval Status Comments

    Zhongyuan-Wenliu Petroleum ex- 1983 Satisfactory Closing Date

    Petroleum Proj- ploration/ Original: 12/31186

    ect (Ln. 2252) development, TA Actual : 12/31/90

    and training

    Daqing Oilfield- Reservoir 1983 Satisfactory Closing Date

    Grotaiza Reser- Development TA Original: 06/30/86

    voir Development and Training Actual : 06/30/90

    Project (Ln.2231)

    Weiyuan Gas Gas Field re- 1985 Satisfactory Closing Date

    Field Technical habilitation TA Original: 06/30/90

    Assistance Proj- and Training Latest estimate:

    ect (Ln. 2580) 06/30/92

    Liaodong Bay Gas Field 1986 Completed Loan closed on

    Petroleum Proj- appraisal, TA Satisfactorily 12/31/89 (as orig-

    ect (Ln. 2708) and Training inally scheduled)

    Table 2: PROJECT TIMETABLE

    Item Actual Date

    Identification Mission May 2, 1983

    Appraisal Mission September 15, 1983

    Loan Negotiations April 16, 1984

    Board Approval May 29, 1984

    Loan Signature June 25, 1984

    Loan Effectiveness September 25, 1984

    Loan Completion March 31, 1991

  • - 14-

    Table 3: LOAN DISBURSEMENTS

    Cumulative Estimated and Actual Disbursements($ million)

    Bank FY 85 86 -87 88 89 90 91

    Appraisalestimate 8.0 40.0 94.0 100.3 100.3 100.3 100.3

    Actual 4.3 29.1 40.7 65.3 77.9 86.1 89.5

    Actual as % ofestimate 53.8 72.8 43.3 65.1 77.7 85.8 89.2

    Date of finaldisbursement: July 25, 1991

  • - 15 -

    Table 4: PROJECT IMPLEMENTATION

    EstimatedCompletion Date

    AppraisalProject Components estimate Actual/PCR estimate Months of Delay/a

    A. Karamay

    1. ExplorationSeismic field acquisition June 1986 Completed April 1987 10 monthsSeismic data processing December 1986 Completed June 1988 18 monthsDrilling of explorationand delineation wells December 1988 Completed December 1989 12 months

    2. Heavy OilFeasibility and design December 1984 Completed March 1988 39 months

    Field pilot tests June 1989 Completed December 1990 18 months

    3. Accuisition of EquipmentTender document and bidanalysis December 1987 Completed July 1989 19 months

    Receipt and installation December 1988 Completed June 1990 18 months

    4. StudiesHeavy oil study December 1987 Completed March 1988 3 monthsTraining study December 1987 Completed July 1988 7 months

    Geological study December 1987 Completed September 1988 9 monthsReservoir study December 1987 Completed January 1991 49 months /b

    Cost Study December 1988 Completed October 1987 10 months earlier

    5. TraininaEstablishment of TrainingCenter December 1985 Completed September 1989 45 mcr!:i /c

    Training of Professionals December 1987 Completed December 1990 36 monitis

    B. Liaohe Heavy Oil Pilot

    1. Heavy oil study and design December 1984 Completed January 1990 73 months /d

    2. Heavy oil pilot June 1989 Canceled Canceled

    /a The initial lag from appraised estimate were caused by the delays in (a) the procurementprocess leading to the signing of the finalized contracts, and (b) implementation of the

    contracts. Overall, the appraisal estimate vas too optimistic.Lb Reservoir Study. This study was delayed by the reasons given in para. 5.1. Basically, KOC

    modified the scope of work and the consultants were delayed in finalizing the repo t.

    c Trainin . No delays occurred during the contract execution./d Liaohe Heavy Oil Stud. There were initial delays, as discussed above. The contract wft

    signed in January 1988, about three years behind the appraisal estimate.

  • - 16 -

    Table 5: PROJECT COSTS AND FINANCING

    A. Project Cost.

    Aporateal gEtiat n YnM n ctual m on

    1xc Onge Total Locl Exchange oreignLocal chng Totaal ocal TEhang Total Local Exchange rotal Local Eachange Total

    Seisic Surveys 20.0 24.0 44.0 39.6 47.3 67.1 52.26 26.42 80.66 205.22 93.2$ 300.50Seismic data processing *.0 6.0 16.0 15.9 15.6 31.6 31.33 3.65 14.96 44.50 32.04 96.34Exploration and delineation well 298.0 132.0 430.0 390.0 261.4 651.4 396.67 178.00 374.67 1,557.62 699.04 2,256.66Heavy oil pilota3. 5 3 1l. 17.0 10.9 22.8 33.7 3.07 8.59 13.66 12.04 *3.00 57.04Supporting facilitia and arvic 2.0 10.5 32.3 9.9 20.6 24.7 101.23 *5.00 146.23 397.57 176.72 574.29Imported * uipmnt 6.0 27.0 33.0 11.9 53.5 65.4 65-.3 43.34 128.52 334.52 232.90 567.42Training of technical assietance 2.0 6.0 8.0 3.9 11.9 15.8 4.60 3.26 7.86 13.06 17.90 35.96

    Total base Cost 341.5 239.0 560.5 676.0 433.7 1.109.7

    Physical contingencies 34.0 21.0 55.0 67.3 41.6 108.9Price contingencies 68.5 33.0 101.5 135.6 65.3 200.9

    Total Proiect Cost 444.0 273.0 717.0 079.0 540.6 1,419.5 654.34 310.26 964.60 2,569.72 1 316.89 3,988.61Front-and fo 0.3 0.3 - 0.6 0.6 - 0.25 0.25 - 1.60 1.60Charges on use of foreign exchange 36.2 36.2 71.7 - 71.7 - - - - - -

    Total Finance 460.2 273.3 753.5 950.7 541.2 1.491.7 654.34 310.51 964.65 2.569.72 1320.49 3.890.21

    In nck Pln 460.2 - 460.2 950.7 - 950.7 634.34 223.00 677.34 2,569.72 675.77 3,445.49Sunslier credit or GOS 173.0 173.0 - 342.6 342.6 - - - - - -isa - 100.3 100.3 - 196.6 196.6 - 67.51 67.51 - 444.72 444.72

    Total 480.2 273.3 753.5 950.7 541.2 1,491.9 654.34 310.51 964.65 2,569.72 1,320.49 3,990.21

    B. Proiect Financing: IBRD Loan Allocation

    Planned(Loan Agreement) Actual$ million Z $ million Z

    KaramaySeismic surveys and interpretation 18.4 100 28.42 31.8Seismic data 7.7 100 3.65 4.1Heavy oil studies pilot 6.0 100 8.59 9.6Equipment for exploration and supportfacilities 38.5 100 33.34 37.2

    Computer center 5.0 100 8.54 9.5Laboratories 1.1 100 1.46 1.6Training center 1.65 100 0.73 0.8Overseas training 0.5 100 0.00 0.0Consultants services 3.3 100 2.53 2.8

    LiaoheHeavy oil study/pilot 3.3 100 1.99 2.2Consultant's services 0.8 100 0.00 0.0

    OthersFee 0.25 100 0.25 0.3Unallocated 13.8 100 0.00 0.0

    Total IBRD 100.3 100 89.50 100.0

  • _ 17 -

    Table 6: PROJECT RESULTS

    A. Economic Impact

    Appraisal Actual

    Economic Rate of Return Not Calculated 31%

    B. Financial Impact

    Appraisal Actual

    Financial Rate of Return Not Calculated 11%

    C. Studies

    Studies Status Impact of Study

    Heavy oil study Completed Transfer of modern technology.

    Improved heavy oil production by

    8 times.

    Training study Completed The Study has been a successful

    vehicle for transfer of modern

    technology. It has enhanced

    capacity/capability of training

    center, students and teachers.

    Geological study Completed Improved comprehension of

    structural geology of Junggar

    Basin; KOC's engineers learned

    modern research methods and map

    compiling methods.

    Reservoir study Completed Improved production and arrested

    decline from 90,000 tons per

    annum to 15,000 tons per annum.

    Cost study Completed Strengthened financial

    management and improved cost

    control.

    Heavy Oil Study Completed Improved comprehension of heavy

    Liaohe oil reserves and heavy oil

    production methods.

  • - 18 _

    Table 7: STATUS OF COVENANTS

    Section Covenant Status

    Prolect Agreement

    Section 2.08 KOC shall (a) carry out under terms of refer- Complied

    ence satisfactory to the Bank, a study of

    reservoir engineering in Wuerhe area; (b)review the results of such study with the

    Bank; and (c) agree with the Bank on anaction plan.

    Section 2.09 KOC shall (a) carry out under terms of refer- Compliedence satisfactory to the Bank, a regional

    sedimentological and structural study toinvestigate the composition and distributionof reservoir bodies; (b) review the results

    of such study with the Bank; and (c) agreewith the Bank on the consequent course ofaction.

    Section 2.10 KOC shall: (a) under terms of reference Compliedsatisfactory tb the Bank, carry out the studyfor the pilot projects under Part B (i) andthe techno-economic study under Part B (ii)of the Project, and shall review the findings

    of such studies with the Bank: (i) withrespect to the study on the design of thepilot projects; and (ii) with respect to the

    techno-economic study; and (b) agree with the

    Bank on the consequent action plan.

    Section 2.11 KOC shall carry out a study under terms of Compliedreference satisfactory to the Bank, of KOC'scosting.

    Section 2.12 KOC shall carry out under terms of reference Compliedsatisfactory to the Bank, a design of train-ing methods for skilled workers and shallreview the findings and agree with the Bankon the consequent action plan. The consul-

    tants to assist KOC in carrying out such adesign shall be appointed.

  • - 19 -

    Table 7: (cont'd)

    Section Covenant Status

    Section 2.13 KOC shall exchange views periodically with Compliedthe Bank on the results of the seismic pro-gram under Part A of the Project at Wuerhe-Hungchiba and Hongshanzui-Chepaizi areas, andagree with the Bank on the consequent impacton the design of the exploration program.

    Section 2.14 KOC shall review periodically with the Bank Compliedthe exploration program of KOC for the Proj-ect.

    Loan Agreement

    Section 3.01 (a) The Borrower declares its commitment to Compliedthe objectives of the Project as set forth inSchedule 2 to this Agreement, and, to thisend, shall carry out Part E of the Projectthrough MOPI with due diligence and efficien-cy and in conformity with appropriate admin-istrative, financial, engineering and petro-leum industry practices, and shall provide,promptly as needed, the funds, facilities,services and other resources required for thepurpose.

    (b) Without any limitation or restriction Compliedupon any of its other obligations under theLoan Agreement, the Borrower shall cause KOCto perform in accordance with the provisionsof the Project Agreement all the obligationsof KOC therein set forth, shall take or causeto be taken all action, including the provi-sion of funds, facilities, services and otherresources, necessary or appropriate to enableKOC to perform such obligations, and shallnot take or permit to be taken any actionwhich would prevent or interfere with suchperformance.

  • - 20 -

    Table 7: (cont'd)

    Section Covenant Status

    (c) The Borrower shall relend the equivalent Complied

    of $96,200,000 out of the proceeds of theLoan to KOC under a subsidiary loan agreementto be entered into between the Borrower andKOC, under terms and conditions which shallhave been approved by the Bank, which shallinclude, inter alia, same interest rate asspecified in Section 2.07 of this Agreement,and a repayment period not exceeding 20years. The Borrower shall bear the foreignexchange risk.

    (d) The Borrower shall exercise its rights Complied.

    under the Subsidiary Loan Agreement in suchmanner as to protect the interests of theBorrower and the Bank and to accomplish thepurposes of the Loan, and, except as the Bankshall otherwise agree, the Borrower shall notassign, amend, abrogate or waive the Subsid-iary Loan Agreement or nay provision thereof.

    Section 3.02 (a) In order to assist the Borrower in Complied

    carrying out the studies under Part E of theProject, the Borrower shall employ consul-tants and experts as necessary whose selec-tion, qualifications, experience and termsand conditions of employment shall be satis-factory to the Bank, in accordance with prin-ciples and procedures described in the"Guidelines for the Use of Consultants byWorld Bank Borrowers and by the World Bank asExecuting Agency" published by the Bank inAugust 1981.

  • - 21 -

    Table 7: (cont'd)

    Section Covenant Status

    (b) The Borrower shall complete the studies Complied

    and review the findings with the Bank:

    (a) by December 31, 1985 with respect to

    the gas utilization study under Part

    E (i) of the Project;

    (b) by March 31, 1985 with respect to

    the study on the design of the pilot

    projects for heavy oil recovery un-

    der Part E (ii) of the Project; and

    (c) by December 31, 1986 with respect to

    the techno-economic study under Part

    E (iii) of the Project.

    (c) Thereafter, the Borrower shall agree Complied

    with the Bank on the consequent action plan

    based on the studies referred to in (b)

    above.

    Section 3.03 (a) The Borrower undertakes to insure, or Complied

    make adequate provision for the insurance ot,

    the imported goods to be financed out of the

    proceeds of the Loan against hazards incident

    to the acquisition, transportation and deliv-

    ery thereof to the place of use or installa-

    tion, and for such insurance any indemnity

    shall be payable in a currency freely usable

    by the Borrower to replace or repair such

    goods.

    (b) The Borrower shall cause all goods and Complied

    services financed out of the proceeds of the

    Loan to be used exclusively for the purposes

    of the Project.

    Section 3.04 (a) The Borrower shall furnish to the Bank, Complied

    promptly upon their preparation, the plans,

    specifications, reports, contract documents

    and work and procurement schedules for Part E

    of the Project, and any material modifica-

    tions thereof or additions thereto, in such

    detail as the Bank shall reasonably request.

  • - 22 -

    Table 7: (cont'd)

    Section Covenant Status

    (b) The Borrower shall: (i) maintain rec- Compliedords and procedures adequate to record andmonitor the progress for Part E of the Proj-ect (including its cost and the benefits tobe derived from it), to identify the goodsand services financed out of the proceeds ofthe Loan related thereto, and to disclosetheir use in such Part of the Project; (ii)enable the Bank's representatives to visitthe facilities and works sites included inPart E of the Project and to examine thegoods financed out of the proceeds of theLoan related thereto and any relevant recordsand documents; and (iii) furnish to the bankat regular intervals all such information asthe Bank shall reasonably request concerningPart E of the Project, its cost and, whereappropriate, the benefits to be derived fromit, the expenditure of the proceeds of theLoan related thereto and the goods and ser-vices financed out of such proceeds.

    (c) Upon the award by the Borrower of any Compliedcontract for goods, works or services to befinanced out of the proceeds of the Loan, theBank may publish a description thereof, thename and nationality of the part to whom thecontract was awarded financed out of suchprice.

    (d) Promptly after completion of the Proj- Compliedect, but in any event not later than sixmonths after the Closing Date or such laterdate as may be agreed for this purpose be-tween the Borrower and the Bank, the Borrow-er, with the Assistance of KOC, shall prepareand furnish to the Bank a report, of suchscope and in such detail as the Bank shallreasonably request, on the execution andinitial operation of the Project, its costand the benefits derived and to be derivedfrom it, the performance by the Borrower andthe Bank of their respective obligationsunder the Loan Agreement and the accomplish-ment of the purposes of the Loan.

  • - 23 -

    Table 7: (cont'd)

    Section Covenant Status

    Section 4.01 (a) KOC shall maintain records and accounts Compliedadequate to reflect in accordance with con-sistently maintained appropriate accountingpractices its operations and financial condi-tion, including, without limitation to theforegoing, separate accounts reflecting allexpenditures on account of which withdrawalsare requested from the Loan Account on thebasis of statements of expenditures.

    (b) KOC shall retain, until one year aftet Compliedthe Closing Date, all records (contracts,orders, invoices, bills, receipts and otherdocuments) evidencing the expenditures onaccount of which withdrawals are requestedfrom the Loan Account on the basis of state-ments of expenditures, and shall enable theBank's representatives to examine such rec-ords.

    Section 4.02 KOC shall: (a) have its accounts and finan- Corr'iedcial statements (balance sheets, statementsof income and expenses and related state-ments) for each fiscal year audited, inaccordance with appropriate auditing princi-

    ples consistently applied, by independentauditors acceptable to the Bank.

  • - 24 -

    Table 7: (cont'd)

    Section Covenant Status

    (b) furnish to the Bank as soon as available, Compliedbut in any case not later than six monthsafter the end of each such year: (i) certi-fied copies of its financial statements forsuch year as so audited; and (ii) the reportof such audit by said auditors of such scopeand in such detail as the Bank shall havereasonably requested, including, withoutlimitation to the foregoing, separate opin-ions by said auditors in respect of theexpenditures and records referred to in Sec-tion 4.01 (b) of this Agreement, as to wheth-er the proceeds of the Loan are made avail-able to it and withdrawn from the LoanAccount on the basis of statements ofexpenditures have been used for the purposefor which they were provided; and

    (c) furnish to the Bank such other informa- Compliedtion concerning said accounts, financialstatements, records and expenditures, as wellas the audit thereof, as the Bank shall fromtime to time reasonably request.

    Section 4.03 KOC shall: (a) by October 1 of each year, Compliedreview with the Bank, KOC's current andfuture finances, including its trend of pro-duction costs, budget variance analysis,future investment program and related financ-ing arrangements; and (b) submit to, andreview annually with the Bank, as part of thereview of KOC's finances referred to in (a)above, its financial statements based on therolling five-year plans.

  • - 25 -

    Table 8: USE OF BANK RESOURCES

    A. Staff Inputs

    Stage of Project Actual Staff-Weeks

    Through Appraisal 43

    Appraisal through board approval/effectiveness 64

    Supervision 154

    Total 261

    B. Missions

    Stage of Number of SW in Specialization

    Project Cycle Month/year persons field represented

    Through AppraisalIdentification May 1983 7 4

    E, PE, G, FA

    Appraisal Sep 1983 6 3 PE, G, FA

    Appraisal throughBoard Approval May 1984

    Post AppraisalSupervision

    Supervision Jul 1984 2 1 PE, G

    Supervision Oct/Nov 1984 5 2 PS, PE, FA

    Supervision* Oct 1984 1 3 PS

    Supervision* Dec 1984 1 2 PS

    Supervision* May 1985 1 4 PS

    Supervision May 1985 5 1 C, FA, PE, PS

    Supervision* Sep 1985 1 3 PS

    Supervision Nov 1985 3 3 PS, FAG

    Supervision Mar/Apr 1986 1 4 PS

    Supervision Aug/Sep 1986 5 2 C, FA, PS, PE, FA

    Supervision Feb 1987 4 1 G, PE, PS, FA

    Supervision Oct 1987 3 2 PS, FA, PE

    Supervision* Mar 1989 3 1 PS, G, PE

    * Procurement supervision in combination with other projects, but only SW

    which were spent for supervision of Karamay Petroleum project have been

    counted.

    E - Economist PE - Petroleum Engineer

    FA - Financial Analyst PS - Procurement Specialist

    G - Geologist

  • CIHINA

    KARAHAY PETROLEUM PROJECT ANNEX 1Economic Analysis

    (in million US$)

    Incremental oil -- Total Coats----------- Total Net Nemo itemsunder Project Incremental due to Project Benefits Benefits Total oil Price of oil b/

    a/ Prodn light heavy

    Year Light Heavy Capex OM O&M Total HIT S/ ton S/ tonMM tons Light Heavy $110

    1984 6.29 6.29 (6.29) 4.001985 O-1" 1.06 195.94 29.59 6.21 231.74 180.60 (51.14) 4.95 201 160.801986 0.33 1.52 204.95 33.08 15.14 253.16 282.35 29.18 5.44 195.00 156.001987 0 49 1.75 258.06 35.95 22.94 316.95 164.08 (152.87) 5.65 99.00 79.201988 0.61 1.64 262.47 36.42 30.38 329.27 218.88 (110.39) 5.49 126.00 100.801989 1.06 1.29 142.60 31.40 50.46 224.46 182.55 (41.91) 5.43 99.00 79.20 a1990 1.44 1.38 71.90 33.87 63.37 169.14 275.98 106.84 5.75 120.00 96.001991 1.64 1.49 100.24 51.58 72.18 224.00 306.99 82.99 5.91 120.00 96.001992 1.80 1.74 67.32 58.69 79.22 205.22 323.97 118.75 6.18 113.15 90.521993 1.96 1.98 45.28 65.18 86.26 196.72 375.33 178.61 6.45 117.53 94.021994 2.07 2.13 41.87 68.20 91.10 201.17 421;26 220.09 6.58 123.37 98.701995 2.18 2.32 41.87 72.40 95.94 210.21 465.11 254.89 6.76 127.02 101.621996 2.28 2.30 37.30 70.07 100.34 207.71 510.83 303.12 6.73 135.68 108.551997 2.38 1.75 14.08 58.88 104.74 177.71 503.86 326.15 6.17 144.94 115.951998 2.48 1.11 0.00 46.45 109.14 155.59 482.94 327.35 5.53 154.82 123.861999 2.58 0.67 0.00 27.89 113.55 141.44 479.75 338.32 5.09 165.38 132.302000 2.68 0.54 0.00 22.53 117.95 140.48 514.62 374.14 4.97 176.66 141.332001 2.58 0.53 77.10 22.03 113.55 212.67 532.63 319.96 4.77 188.71 150.972002 2.48 1.03 93.59 45.19 109.14 247.93 635.84 387.91 5.14 201.58 161.262003 2.38 1.34 99.93 56.04 104.74 260.71 703.39 442.69 5.22 215.32 172.262004 2.80 1.65 108.38 69.23 100.34 277.95 786.98 509.03 5.36 230.01 184.01

    ERR= 30.7w

    a/ garamay oil is transported to refineries as follows: By pipeline to KaramayRefinery (1 am ton); to Dushanzi Refinery (2.5 mm tons); Urumchi Refinery (1.5 nun tons);and by train fron, Urumchi to Lanzhou (the excess) at about a freight of 60 yuan/ton.

    b/ Future prices are based on Bank projections. Transportation costs to Refineries are deducted.

  • Ainex 2_ 2

    . (1 o~ r

    CHINA

    KMAIAAY PETROLEUM PMOJECT

    Key Fina nciat Indicators

    (in mittion yumns)

    4 Opp U act 85 Opp OS ct 066pp S6 act 87 pp 87 ct ea act 89 ct 90 act 9l priv

    Sales

    Crude (PR tons) 4.1 4.3 4.3 4.8 4.8 5.0 5.3 5.6 5.5 5.3 5.6 5.6

    Av. Price realized

    C.-ude (Yuan/ton) 135 138 14? 144 175 163 175 156 167 225 255 32)

    Revenues (M Yuan) 503 568 619 663 784 781 858 838 s8s 1143 1370 1886Operating Expenses 408 396 442 524 s03 584 559 627 629 a88 1133 1505Net Income SS S4 76 68 11? 87 119 83 100 103 94 154

    Total Assets

    LonJ-term Debt 74 110 123 435 237 S69 297 649 802 1082 1160 1069Equ ty 1652 1475 1997 1626 1956 1752 2022 207r 2424 2783 3186 3519Debt Service 22 If 23 18 36 14 48 40 72 65 82 103Capitat Expenditur S52 699 n20 71 640 1116 640 1373 1096 1013 925 lIe?Net govt. take 122 262 278 331 422 363 441 329 .38 604 422 Mi

    Ope ating Ratio 0.82 0.70 0.77 0.79 0.68 0.75 0.69 0.75 0.71 0.78 0.83 0.o0Deb /Equity Ratio 4/96 7/93 6/94 21/19 11/89 25/75 13/8? 24/T6 5/1% 26/r2 211rl 13/tDebt Service coverage

    (times) 10.8 7.8 12.1 16.1 8.9 26.8 7.5 118 .6 3 L 9 S.8 I 2Current Ratio 2.0 2.2 2.1 4.5 2.0 1.S 1.9 t I I.? 2.4 I 6 1 SUnit Cost of Prodn.

    (luan/ton) OJ S2 92 99 95 147 97 102 104 158 192 2S9Lireit Cost o0 Prodn.

    (V/ton) 44.4 41.5 28.8 31.0 25.5 28.6 26.0 21.3 28.0 31 s 36.1 41.2

  • CHINA ANNEX 2

    KARAMAY PETROLEUM PROJECT Page 2 of 2

    Financial Analysis

    (in million yuans)

    Incremental oil Sales Capex due O0m Total Salem L Net Cash

    under Project Revenue to Project Coets Costs Income tax Flow

    a/ l/

    Year Light Heavy

    MM tons

    1984 9.90 9.90 (9.90)

    1985 0.11 1.06 467.60 486.02 88.81 574.82 56.47 (163.69)

    1986 0.33 1.52 728.40 638.50 150.22 788.72 115.22 (175.54)

    1987 0.49 1.75 843.90 822.02 187.57 1009.59 122.62 (288.31)

    1988 0.61 1.64 809.65 796.91 202.82 999.73 135.26 (325.35)

    1989 1.06 1.29 814.00 619.02 355.31 974.33 105.71 (266.04)

    1990 1.44 1.38 968.95 376.76 509.56 886.31 106.37 (23.73)

    1991 1.64 1.49 1364.11 549.31 678.18 1227.49 169.08 (32.46)

    1992 1.80 1.74 1534.26 368.89 755.72 1124.62 200.30 209.35

    1993 1.96 1.98 1702.90 248.15 829.88 1078.04 234.17 390.70

    1994 2.C7 2.13 1797.37 229.45 872.96 1102.41 247.72 447.24

    1995 2.18 2.32 1916.50 229.45 922.52 1151.98 269.02 495.50

    1996 2.28 2.30 1925.33 204.38 933.88 1138.27 255.93 531.14

    1997 2.38 1.75 1658.02 77.18 896.66 973.84 121.46 562.72

    1998 2.48 1.11 1347.89 0.00 852.64 852.64 53.92 441.34

    1999 2.58 0.67 1140.49 0.00 807.97 807.97 45.62 286.90

    2000 2.68 0.54 1098.08 0.00 810.80 810.80 43.92 243.35

    2001 2.58 0.53 1013.29 422.50 790.36 1212.86 40.53 (240.10)

    2002 2.48 1.08 1223.24 512.90 934.38 1447.28 48.93 (272.96)

    2003 2.38 1.34 1281.83 547.60 980.55 1528.15 51.27 (297.60)

    2004 2.28 1.65 1370.69 593.90 1039.59 1633.49 54.83 (317.63)

    FRR= 10.8i

    a/ Two tier pricing of a lower price upto 3.64 mm tone of total production and of a higher

    *lmost near international parity (adjusted for transportation to refineries) prevails.

    b/ Incremental capex is made up of both project investments and futtire iniveetmenta

    required to etiutaiin the pro )ect objectivetvc


Recommended