The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
REPORT NO.: RES31490
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
STRENGTHENING TAX SYSTEMS AND BUILDING TAX POLICY ANALYSIS CAPACITY
APPROVED ON APRIL 28, 2017
TO
THE ISLAMIC REPUBLIC OF PAKISTAN
GOVERNANCE
SOUTH ASIA
Regional Vice President: Annette Dixon Country Director: Patchamuthu Illangovan
Senior Global Practice Director: Deborah L. WetzelPractice Manager/Manager: Ismaila Ceesay
Task Team Leader: Charles Victor Blanco, Muhammad Waheed
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
ABBREVIATIONS AND ACRONYMS
CD Country DirectorDFID Department for International Development (United
Kingdom)EA Environmental AssessmentEAD Economic Affairs DivisionFBR Federal Board of RevenueFY Fiscal YearICT Information and Communications TechnologyMMIMSPDO
Market Monitoring and Intervention Unit Moderately SatisfactoryProject Development Objective
PSDP Public Sector Development ProgramTAGR Trust Fund for Accelerating Growth and Reform TF Trust FundTIUTOR
Tax Intelligence Unit Terms of Reference
USD United States Dollar
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
BASIC DATA
Product Information
Project ID Financing Instrument
P161463 Investment Project Financing
Original EA Category Current EA Category
Not Required (C) Not Required (C)
Approval Date Current Closing Date
28-Apr-2017 30-Apr-2018
Organizations
Borrower Responsible Agency
The Islamic Republic of Pakistan Federal Board of Revenue
Project Development Objective (PDO)
Original PDOThe PDO is to support policy informed decisions in domestic revenue mobilization.
Key Results include 1) Produce annual comprehensive tax expenditure analysis 2) Forecast annual tax revenues of FBR and provincial governmentsOPS_TABLE_PDO_CURRENTPDOSummary Status of Financing
TF Approval Signing Effectiveness ClosingNet
Commitment Disbursed Undisbursed
TF-A4946 28-Jul-2017 02-Aug-2017 02-Aug-2017 30-Apr-2018 4.90 0 4.90
Policy Waiver(s)
Does this restructuring trigger the need for any policy waiver(s)?No
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING
1. Aimed at strengthening tax systems and building tax policy analysis capacity, the Project (USD 4.9 million) was approved by the Bank on April 28, 2017 and became effective on August 2, 2017. The objective of the Project is to support policy informed decisions in domestic revenue mobilization. The Project, which is part of the Department for International Development (DFID) - funded Trust Fund for Accelerating Growth and Reform (TAGR), consists of two components: (1) Updating Tax Administration Data Centers to Strengthen the Federal Board of Revenue’s (FBR) Capacity in Information Technology, and (2) Building FBR’s Fiscal Research and Tax Policy Analysis Capacity. Under Component 1, the Project will update the Data Centers, including Storage, Servers and Network Equipment, and support the implementation of a change management program. The expected outcome is an integrated Information and Communications Technology (ICT) data center that effectively conveys tax information to decision makers. Under Component 2, the Project will support the set-up of a Tax Intelligence Unit (TIU) and a Market Monitoring and Intervention Unit (MMI), whose aim is to develop the Federal Board of Revenue’s (FBR) capacity to carry out sound tax policy analysis. The units will be responsible for designing, organizing, and directing a wide range of macroeconomic and tax analyses (e.g., direct, indirect, customs, trade).
2. Project activities experienced initial delays but are now underway. The reasons for the delay were (i) a request by FBR for additional consultations prior to the start of the Project, (ii) personnel changes within the Government of Pakistan due to the departure of the Secretary of the Economic Affairs Division (EAD), the authorized representative for signing the Grant Agreement, and (iii) the fact that the Project was initially not included in the Public Sector Development Program (PSDP) 2017-18 at the time of budget approval in June 2017, which effectively put a stop on implementation.1 All these issues are now resolved. The budget for the Project was allocated in January 2018, allowing the opening of the Revolving Fund Account and enabling the Project to commence disbursement. Project implementation has also started. Under component 1, the procurement process for the data center has been launched and is tentatively expected to be completed by December 2018. Under component 2, the terms of reference (TOR) for staff/consultants of the tax policy unit have been approved. Overall, the Project is currently being rated as moderately satisfactory (MS) and has no outstanding audits.
II. DESCRIPTION OF PROPOSED CHANGES
3. The proposed restructuring consists primarily of an extension of the Project closing date and related revisions to the results framework. The proposed restructuring responds to a request by the Economic Affairs Department (EAD) of the Government of Pakistan to restructure the Project through an extension of the Project closing date by 14 months from April 30, 2018 to June 30, 2019 (Letter No. 4(3)WB-IV/17 of February 12, 2018). Consistent with this request, the restructuring proposes an extension of the closing date until June 30, 2019 and related revisions of the dates and targets of the results framework, the disbursement estimates, procurement plan and implementation schedule. There are no other substantial changes to the Project. In particular, the Project Development Objective (PDO), the implementation arrangements, the Project cost and the Project’s risks and safeguards remain unchanged. The proposed changes of the restructuring are summarized below.
Extension of Project Closing Date: To allow for a successful completion of Project activities following the initial delays, it is proposed to extend the Project closing date by 14 months from April 30, 2018 to June 30, 2019.
Change in Results Framework: Consistent with the Project’s new closing date, the target dates of the results framework are being revised.
1 The Project’s PC-1, the Government’s internal project concept document, was prepared and approved in January 2017.
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
Change in Disbursement Estimates: The Project’s disbursement estimates have been updated reflecting the new closing date. It is estimated that the Project will disburse its entire funds in FY2019. USD 3.43 million (70%) of the Project amount is expected to be disbursed by December 31, 2018, while the remaining USD 1.47 million (30%) is expected to be disbursed by June 30, 2019.
Change in Procurement: The Project’s Procurement Plan has been updated in line with the new Project implementation schedule. There are no fundamental changes in substance to the procurement.
Change in Implementation Schedule: The sequence of activities remains the same, but the implementation schedule of the Project has been updated reflecting the new closing date of June 30, 2019. Activities under component 1 (Data Center) are now expected to be implemented from February 2018 to December 2018. Activities under component 2 (establishment of two research units) are scheduled to be implemented between March 2018 and June 2019.
The proposed changes are outlined in further detail in sections III. and IV. of the Restructuring Paper below. III. SUMMARY OF CHANGES
Changed Not Changed
Change in Results Framework ✔
Change in Loan Closing Date(s) ✔
Change in Disbursement Estimates ✔
Change in Procurement ✔
Change in Implementation Schedule ✔
Change in Implementing Agency ✔
Change in Project's Development Objectives ✔
Change in Components and Cost ✔
Cancellations Proposed ✔
Additional Financing Proposed ✔
Reallocation between Disbursement Categories ✔
Change in Disbursements Arrangements ✔
Change in Overall Risk Rating ✔
Change in Safeguard Policies Triggered ✔
Change of EA category ✔
Change in Legal Covenants ✔
Change in Institutional Arrangements ✔
Change in Financial Management ✔
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
Other Change(s) ✔
IV. DETAILED CHANGE(S)
OPS_DETAILEDCHANGES_RESULTS_TABLE
RESULTS FRAMEWORK
Project Development Objective Indicators PDO_IND_TABLE
Produce annual comprehensive tax expenditure analysisUnit of Measure: Yes/NoIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value No No Yes Revised
Date 01-Mar-2017 10-Aug-2017 30-Jun-2019
Forecast annual tax revenues of FBR and provincial governmentsUnit of Measure: Yes/NoIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value No No Yes Revised
Date 01-Mar-2017 10-Aug-2017 30-Jun-2019
Intermediate IndicatorsIO_IND_TABLE
Data Center is equipped with Blade Servers, Primary SAN and relevant networksUnit of Measure: Yes/NoIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value No No Yes Revised
Date 01-Mar-2018 10-Aug-2017 31-Mar-2019
Data Center servers and software are virtualized using the cloudUnit of Measure: Yes/NoIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value No No Yes Revised
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
Date 01-Mar-2017 10-Aug-2017 31-Mar-2019
Tax Intelligence Unit and the Market Monitoring and Intervention Unit offices are fully equippedUnit of Measure: Yes/NoIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value No No Yes Revised
Date 01-Mar-2017 10-Aug-2017 30-Jun-2019
Tax Intelligence Unit and the Market Monitoring and Intervention Unit are staffed with 9 positions supported by the projectUnit of Measure: NumberIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value 0.00 0.00 9.00 Revised
Date 01-Mar-2017 10-Aug-2017 30-Jun-2019
Monthly executive and detailed reports on the performance of revenue collectionsUnit of Measure: Yes/NoIndicator Type: Custom
Baseline Actual (Current) End Target Action
Value No No Yes Revised
Date 01-Mar-2017 10-Aug-2017 30-Jun-2019
OPS_DETAILEDCHANGES_LOANCLOSING_TABLE
LOAN CLOSING DATE(S)
TF StatusOriginal Closing
Revised Closing(s)
Proposed Closing
Proposed Deadline for Withdrawal
Applications
TF-A4946 Effective 30-Apr-2018 30-Jun-2019 30-Oct-2019
OPS_DETAILEDCHANGES_DISBURSEMENT_TABLE
DISBURSEMENT ESTIMATES
Change in Disbursement EstimatesYes
The World BankStrengthening Tax Systems and Building Tax Policy Analysis Capacity (P161463)
Year Current Proposed
2017 0.00 0.00
2018 0.00 0.00
2019 0.00 4,900,000.00
2020 0.00 0.00
2021 0.00 0.00
2022 0.00 0.00
2023 0.00 0.00