1
Document of
The World Bank
Report No: 74325-IQ
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING OF
IRAQ: PUBLIC FINANCE MANAGEMENT REFORM PROJECT (P110862)
(GRANT TF094552)
RVP APPROVAL DATE: JUNE 27, 2009
TO THE:
IRAQ- MINISTRY OF PLANNING AND DEVELOPMENT COOPERATION
January 25, 2013
Governance and Public Sector Management Unit,
Poverty Reduction and Economic Management (PREM) Department
Middle East and North Africa
This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
ABBREVIATIONS AND ACRONYMS
BCC Budget Call Circular
BETF Bank Executed Trust Fund
BORR Borrower
BSA Board of Supreme Audit
COTS Commercial Off-the Shelf
EA Environmental Assessment
GFS Government Financial Statistics
ICT Information and Communications Technologies
IFMIS Integrated Financial Management Information System
IG Inspector General
IPSAS International Public Sector Accounting Standards
ISDS Integrated Safeguard Data Sheet
ITF Iraq Trust Fund
MOF Ministry of Finance
MOFATC Ministry of Finance Accounting Training Center
MOPDC Ministry of Planning and Development Cooperation
PAD Project Appraisal Document
PDO Project Development Objective
PFM Public Financial Management
PMT Project Management Team
PRA Procurement Regulatory Agency
TA Technical Assistance
Regional Vice President: Inger Andersen
Country Director: Ferid Belhaj
Sector Manager:
Sector Director:
Guenter Heidenhof
Manuela Ferro
Task Team Leader: Arun Arya
3
Restructuring
Restructuring Type: Level II
1. Basic Information Project ID & Name P110862: IQ-Public Financial Mgmt Reform
Country Iraq
Task Team Leader Arun Arya
Sector Manager/Director Guenter Heidenhof/ Manuela Ferro
Country Director Ferid Belhaj
Original Board Approval Date 06/26/2009
Original Closing Date: 06/30/2013
Current Closing Date 06/30/2013
Proposed Closing Date [if applicable] 09/30/2013
EA Category C-Not Required
Revised EA Category C-Not Required
EA Completion Date
Revised EA Completion Date
2. Revised Financing Plan (US$m) Source Original Revised
BORR 0.00 0.00
IRTF 18.00 18.00
Total 18.00 18.00
3. Borrower Organization Department Location
Republic of Iraq Baghdad, Iraq
4. Implementing Agency Organization Department Location
Ministry of Finance Baghdad, Iraq
4
5. Disbursement Estimates (US$m) Actual amount disbursed as of 12/8/2012 5.60
Fiscal Year Annual US$ Cumulative US$
2010 121,785 121,785
2011 856,738 978,523
2012 3,333,349 4,311,872
2013 1,287,480 5,599,352
Total 5,599,352
6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N
Does the restructured projects trigger any new safeguard policies? If yes, please select
from the checklist below and update ISDS accordingly before submitting the package.
N
7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes
The Project Development Objective is to support the Government of Iraq's efforts to develop a more
effective, accountable and transparent public financial management.
7b. Revised Project Development Objectives/Outcomes Not applicable
5
IRAQ IRAQ: PUBLIC FINANCE MANAGEMENT PROJECT
TABLE OF CONTENTS
P110862
A. SUMMARY ........................................................................................................................... 6
B. PROJECT STATUS .............................................................................................................. 6
C. PROPOSED CHANGES ...................................................................................................... 8
D. APPRAISAL SUMMARY – ............................................................................................. 13
ANNEX 1: RESULTS FRAMEWORK AND MONITORING ............................................. 15
ANNEX 2: REALLOCATION OF PROCEEDS .................................................................. D-26
ANNEX 3: EXTENSION OF CLOSING DATE .................................................................. D-27
6
RESTRUCTURING PAPER
IRAQ: PUBLIC FINANCE MANAGEMENT PROJECT (P110862):
(GRANT TF094552) (RECIPIENT-EXECUTED)
A. SUMMARY
1. This Restructuring Paper proposes a Level II restructuring to (a) add a new
component, namely the “Integrated Financial Management Information System
(IFMIS)”; (b) re-allocation of Grant proceeds; and, (c) extend the project closing date, at
the request of the Recipient.
2. During the Mid-Term Review of the project in August 2011, it was agreed with the
Government that the Project’s impact would be significantly enhanced if an IFMIS is also
implemented. Component 1 on Budget Preparation and Component 3 on Budget
Execution Controls can deliver better results if implemented together with IFMIS. Under
the new IFMIS Component, the Ministry of Finance (MOF) plans to develop,
commission and test the prototype of IFMIS. Down the road, the Government also plans
to roll-out IFMIS to all public sector entities including all ministries, treasuries, spending
units and governorates at its own cost.
3. The project’s original closing date was June 30, 2013. The Government has
requested for a 3-months extension to the project closing date citing the reason that the
implementation of the Project could not start until mid-2011 due to three terrorist attacks
on the premises of the Ministry of Finance. With regard to the extension, given that the
Iraq Trust Fund is closing on 31 December 2013, we are requesting an extension up to 31
August 2013.
B. PROJECT STATUS
4. The Iraq Public Financial Management (PFM) project was started as an
emergency operation in July 2009 under the Iraq Trust Fund (ITF). The project is to be
completed in June 2013. The total estimated cost of the Project is US$18 million: i)
US$16 million to be Recipient-executed; and ii) US$2 million to be Bank-executed on
behalf of the Recipient. Under the Recipient-executed part, against the project cost of $16
million, $3.6 million (23 %) has been disbursed. Under the Bank-executed part, against
the project cost of $2 million, the entire $2 million (100 %) has been disbursed. Against
the total project cost of $18 million, $5.6 million (31 %) has been disbursed.
5. The progress made under the Recipient-executed part is as follows:
a) Component 1- Strengthening Budget Preparation: The inception reports for
(a) improving the budget strategy, content of and adherence to the Budget Call
Circular (BCC), and, (b) improving the methodology of investment project
preparation and evaluation, have been prepared.
b) Component 2 – Strengthening Public Procurement: Under the assignment on
developing the Standard Bidding Documents (SBDs), National Implementation
7
Manual (NIM), and Training Curriculum, draft outputs have been prepared.
Similarly, a workshop on international arbitration was organized to inform the
national stakeholders about international best practices. A contract for the
Training Needs Assessment has recently been signed and the work is about to
begin.
c) Component 3 – Strengthening Budget Execution: Consultants have submitted
their draft final reports on Cash Management and Commitment Control Systems.
The procurement process for the organization of internal financial controls is
ongoing and a contract for upgrading the MOF website for enhancing citizen’s
access on fiscal data has recently been signed.
d) Component 4 – Capacity Development: Consultants have prepared the Capacity
Development Plan of the Ministry of Finance Accounting Training Center
(MoFATC), which has been recently approved by the government. The actual
capacity building work is expected to start soon.
6. Initially, there were significant delays in procuring goods and signing consultancy
services contracts. The payment approval procedure used was not appropriate and led to
delays in payments. Accordingly, the last ISR rating of the Project in April 2012 was
Moderately Unsatisfactory. However, as per Bank’s task team’s advice, the payment
approval system has now been streamlined. The resignation of Finance Officer from the
project management team had led to a lack of an authorized signatory to issue payments,
which consequently led to payment delays. However, this issue stands resolved now. In
summary, the project has made some good physical progress under all components since
April 2012, but there have been delays in the payments, due to which disbursements have
not kept pace with the physical progress. The project has uncommitted funds of $6.78
million (44%) – but once the Government is able to sign the Integrated Financial
Management Information System (IFMIS) contract, all uncommitted funds would be
committed.
7. The progress under the Bank-executed part has been as follows:
8. Under the Bank-executed trust fund (BETF), US$2 million were allocated for the
technical assistance (TA) to support the implementation of the Grant and had two
components: (1) Strengthening Budget Preparation, and (2) Capacity Development of the
Board of Supreme Audit (BSA). All of the US$2 million allocated funds for the BETF
have been fully utilized and all planned activities completed. At the Government request,
a proposal for Additional Financing of $621,500 has been prepared for the approval of
the management. The component-wise progress is as follows:
a) Component 1 – Strengthening Budget Preparation: A fully functional Medium
Term Expenditure Framework (MTEF) has been developed and has been used for
preparing budget strategies for 2011-13; 2012-14; and 2013-15. The Iraqi
Medium-term Fiscal (IMF) model is also operational and being tested for the
budget strategy for the ‘2012-14’ period. A comprehensive historical database of
fiscal information is in place. The budget preparation process improved with an
increasingly detailed policy focus during strategy discussions. The use of the IMF
Model has delivered MoF the capability to undertake research on policy
8
components of the budget; trend analysis; and to fine-tune the top-down setting of
fiscal envelopes.
b) Component 2 - Capacity Development of the Board of Supreme Audit (BSA): The program aimed at building capacity, improving key audit practices and
methodologies. The BSA staff has enhanced their skills in financial, risk-based,
procurement, and performance audit. In addition, capacity has built around special
subjects such as oil audit, forensic audit, arbitration, contract management,
auditing of World Bank-financed projects, and Monitoring and Evaluation. The
program has trained about 270 auditors, including 10 master trainers investing
about 10,500 training hour. It has developed one audit manual and improved
another. Moreover, it provided the BSA with solid recommendations on how to
proceed at a number of areas from peer SAIs and experts who had experienced a
similar reform process.
Extension of the Project Closing Date:
9. The Government of Iraq, Ministry of Finance, has requested extension of the
project closure date citing that the implementation of the Project could not start until mid-
2011 because the premises of the Iraqi Ministry of Finance were exposed to three terrorist
attacks, which resulted in delaying the project. They have said that continuous fragile
security situation in Iraq posed a challenge for foreign consultants who found it risky to
travel to Iraq. While in Iraq, the security situation restrained their movements and the
time for which they could meet the government counterparts.
10. From the perspective of Bank’s task team, while the security has indeed caused
some implementation delays, there have been several other factors contributing to slow
progress. However, the main reason why the extension is necessary is that as a
restructuring process, a new component IFMIS is being added which requires a minimum
9 months’ time to be completed. At best, the above implementation schedule could be
reduced to 8 months. The task team, therefore, recommends extension of the project
closure date until 31 August 2013. These two extra months would enable the government
to ensure completion of ongoing activities in a timely and orderly manner. If this
extension is not given, the project objectives will be difficult to achieve. This is the first
and last extension of the project. A detailed explanation on the extension of project
closing date is included in Annex 3.
C. PROPOSED CHANGES
11. Results/indicators. See Revised Annex 1 below.
12. Components. It is proposed to introduce a new Component 5 on Integrated
Financial Management Information System (IFMIS) to the Project. Following is the
description of this component.
NEW Component 5 – Integrated Financial Management Information System
(IFMIS) ($6,000,000)
9
13. The Ministry of Finance, Government of Iraq, wants to implement IFMIS in two
phases:
a) Phase 1 – Prototype Development and Testing for the Supply and Implementation
of Integrated Financial Management Information System to be conducted in the
period January 2013 to August 31, 2013, and
b) Phase 2 – Pilot Implementation and Government wide Rollout based on the
results of phase 1 comprising:
i. Phase2A – Pilot Implementation – To commence on January 1, 2014 and
conclude on December 31, 2014
ii. Phase 2B – Government wide Rollout – To commence January 1, 2015
and be completed by June 30, 2016.
14. The Project would support only Phase 1 of this plan. Following the evaluation of
Phase 1, the Ministry of Finance, Government of Iraq, will implement the IFMIS
Government wide system in Phase 2 with other resources. The IFMIS would magnify the
impact of other components of the project in the following manner:
a) Provide capability to automate the budget preparation process to ensure complete
and accurate budget formulation and presentation (support Component 1);
b) Increase the ability of the Ministry of Finance to undertake central control and
monitoring of expenditure and receipts in government Ministries, departments and
spending units (support Component 3); and
c) Provide the Ministry of Finance with access to comprehensive and meaningful
information on budgetary, financial and operational performance during the
financial year (support Components 1 and 3).
15. The Bank’s task team has been engaged in a policy dialogue with the government
on IFMIS since August 2011. The IMF too has participated in this dialogue.
Implementation of the IFMIS was part of the Stand-by Arrangement (SBA) of IMF. The
Government has shown commitment to implement IFMIS which was evident from their
participation in a series of workshops organized by the Bank. A 30-member delegation
from the government participated in the Stakeholder’s workshop in Beirut in May, 2012,
wherein after detailed deliberations, the functional and technical specifications of the
IFMIS system were agreed upon. An agreement was signed with the Bank on the
roadmap and detailed technical and functional specifications. The Government has
clearly stated that “the Ministry of Finance is ready to participate in providing funds from
its budget for implementing IFMIS, over and above what can be provided, by the World
Bank, under the Iraq PFM Project.”
16. From a historical perspective, it may be pertinent to note that in 2003, the
Coalition Provisional Authority (CPA) and the International Monetary Fund (IMF) had
conducted assessments that identified a need for improvements in the Government of Iraq’s
(GoI) budget and financial control system. These assessments found that the GoI financial
structure provided limited ability to monitor Iraqi ministerial budgets and expenditures,
leaving the ministries vulnerable to fraud, waste, and misappropriation of funds. The CPA,
which then managed the budget, conceived the Iraqi Financial Management Information
System (IFMIS) as a solution to manage and oversee the GoI budget. The U.S. Agency for
International Development (USAID) was instructed by the CPA to implement an Iraqi
10
financial management information system, which entered into a broad-based contract with
BearingPoint, Inc. for that purpose. IFMIS represented only a small part of the total effort
and estimated cost under the contract. Bearing Point, in turn, provided a sub-contract to
FreeBalance to develop the design of IFMIS. Subsequently, during 2007-2009, Bearing
Point gave 11 Technical Assistance Orders (TAOs) to FreeBalance for maintaining the
ongoing operation of the system, mainly for BearingPoint staff, so that they knew how to
do it and could explain to GoI. In July 2007, the U.S. Embassy in Iraq ordered the
suspension of the IFMIS project because the BearingPoint project leader and his security
detail had been kidnapped and the GoI lacked support for the system.
17. The task under this Project is to build on a system that was implemented under the
USA Department of Treasury financing of about $30 million, where the Free Balance
System was used by the main contractor (Bearing Point). The Ministry of Finance,
Government of Iraq, after having used the FreeBalance system earlier, wants to continue
using it in future, with some upgradation and customization as per their specific
requirements. Considering that the US Department of Treasury had indicated that they
were no more interested in funding the PFM Project, the Government of Iraq has turned
to the Bank as the financier of last resort. The Government is satisfied with the Free
Balance Accountability software for which there is availability of trained Iraqi staff
which is familiar with the system.
18. The Ministry of Finance wants to use the FreeBalance Accountability Suite v7.0
configured in accordance with the Government of Iraq requirements to provide
automated financial management capability in the Budget Preparation and Budget
Execution functions. The proposed IFMIS will be based on implementation of the
required modules of the Commercial Off-the Shelf (COTS) FreeBalance Inc.
Accountability Suite version 7 with minimal customization.
19. The proposed IFMIS will include Common Application requirements across all
modules, including user access and responsibility controls, the General Ledger Module
incorporating a Budget Classification Structure (Chart of Accounts) suitable for Iraq, a
Budget Preparation Module (including provision to upload approved budget for
execution) and a Budget Execution Module which incorporates appropriate business
processes, Commitment Control and Accounting, Expenditure Processing and Payment,
Revenue recording (Tax, Non-Tax, Grant, Loan), and Cash Management, Banking and
Reconciliation functions. Finally, the IFMIS will provide Financial Reporting for
management purposes and to meet GFS and IPSAS reporting requirements by developing
specific reports for Iraq circumstances.
20. The award of contract to FreeBalance for the development and testing of IFMIS
prototype has been approved by the OPRC with the direction that the contract will be
revised based on its comments and will be cleared by the RPM. The contract is currently
undergoing revision by the government and will be submitted to the RPM for clearance
after the directions of the OPRC have been fully complied with. This is expected by
January 31, 2013.
21. In the unlikely event that the Bank does not approves this contract, a System
Requirement Study (SRS) for implementing IFMIS would be conducted as an
11
independent assignment, the outputs of which, could be used by the government for
designing the prototype, piloting and rolling-out of IFMIS, after this project is completed.
Cost of implementing IFMIS:
22. The cost of developing and testing IFMIS prototype will be as follows:
a) Cost for development and testing of prototype: Approximately US$4,900,000 will
be required for the acquisition of the IFMIS, including the initial System
Requirements Studies and subsequent Supply, Installation, and Commissioning of
the FreeBalance Accountability Suite V9.0 at Select Ministries, Treasuries, and
Independent Boards of the Government of Iraq.
b) Acquisition of ICT hardware for the system operation:
i. Establishing the Data Centre for the IFMIS: US$700,000
ii. Establishing the Disaster Recovery Site: US$300,000
c) Consultant’ services:
i. Engaging an international ICT specialist US$60,000
ii. Engaging a local PFM specialist US$40,000.
23. Accordingly, a total funding of US $6,000,000 will be required for this new
component. The Ministry of Finance, Government of Iraq, has agreed to finance
additional requirements for computer hardware, networks and on-site development in the
pilot ministries and agencies.
Financing:
24. Funding for the new component will come from the Project’s Unallocated
Category. The initial large unallocated amount of US$ 2.82 million was appropriate at the
start of the project, as the cost estimates did not include the numerous “downstream”
activities which were likely to arise from the consultant outputs, and, prior to those
outputs, it was not possible to accurately estimate the costs for these activities. However,
a number of the downstream activities did not materialize as expected, and other planned
activities have been modified or cancelled. As a result, this unallocated amount has risen
to US$ 7.00 million, which is sufficient to finance the IFMIS.
25. Project Costs:
12
Project Costs (US$m.)
Components/Activities Current
Proposed
Component 1 - Strengthening Budget Formulation &
Implementation
3.95
1.90
Component 2 - Strengthening Public Sector
Procurement
3.2 1.70
Component 3 - Strengthening Budget Execution &
Implementation
2.33 3.30
Component 4 - Capacity Development
and Project Management & Auditing
3.0
0.7
2.20
0.90
3.7 3.10
NEW Component 5 – Integrated Financial
Management Information System (IFMIS)
n/a 6.00
Unallocated 2.82 0.00
Total 16.00 16.00
Financial Management:
26. Project will continue using the same financial management and disbursement
arrangements, including accounting and reporting, internal controls, auditing and
budgeting. There are no overdue audit reports or overdue financial reports. The audit
report with audited financial statements and management letter for the year ended
December 31, 2011 were submitted to timely to the Bank. The external auditor has issued
unqualified “clean” opinions.
Re-allocation of Proceeds:
27. The proposed restructuring will be accompanied with reallocation of uncommitted
and unallocated funds under the project for the new component 5 of IFMIS. The
proposed re-allocation of proceeds under different categories of consultancy, goods and
incremental operating costs is included in Annex 2.
Procurement Management:
28. Procurement for this project will continue to be carried out in accordance with the
World Bank’s Procurement Guidelines as indicated in the Grant Agreement.
29. Procurement of Goods: Goods procured under the new Component 5 estimated at
$1,000,000 includes ICT hardware, and will be added to the Procurement Plan as ICB
and NCB packages to be completed before closing date.
30. Selection of Consultants: The new component would require initial System
Requirements Studies and subsequent Supply, Installation, and Commissioning of the
FreeBalance Accountability Suite V7.0 estimated at $4,900,000 to be added to the
Procurement Plan as Single Source selection as it is a buildup on previous FreeBalance
system installations, to benefit from the firm’s continued professional liability for the
system, and exceptional qualification for this specific assignment.
13
D. APPRAISAL SUMMARY –
Economic and Financial
31. The project, by introducing a modern PFM platform, will contribute to an
improved and more rigorous budget preparation process, provide a well regulated budget
execution methodology including control of cash resources, implement sounder
procurement and purchasing control and provide comprehensive and timely financial
reporting mechanisms subject to external audit. Improved business processes and
responsibility assignment within the IFMIS will help to minimize resource leakages, and
provide an accountability trail to identify those who indulge in leakages. The overall
fiscal impact of the project is, therefore, likely to be positive. Better overall resource
management, coordination amongst various government entities, and comprehensive and
timely available financial data will help to improve the allocation of public resources to
priority areas. A more efficient PFM system would curb irregularities in budget
execution; and generally improve fiscal transparency and accountability.
Technical
32. FreeBalance is a global provider of software solutions for public financial
management (PFM). The FreeBalance Accountability Suite is a commercial off-the-
shelf, Government Resource Planning (GRP) solution which is implemented globally
within governments across the world. Customers include the governments of
Afghanistan, Antigua and Barbuda, Canada, Guyana, Iraq, Jamaica, Kosovo, Kyrgyzstan,
Mongolia, Namibia, Pakistan, Palestine, Sierra Leone, Southern Sudan, Timor-Leste,
Uganda, and the USA.
33. The FreeBalance Accountability Suite supports good fiscal practice and
internationally recognized standards such as the United Nations Common Functions of
Government (COFOG), the IMF Government Finance Statistics (GFS), the IMF Code of
Good Practices on Fiscal Transparency, Generally Accepted Accounting
Principles (GAAP), International Financial Reporting Standards (IFRS), International
Public Sector Accounting Standards (IPSAS), Millennium Challenge Corporation
(MCC), Medium Term Expenditure Frameworks (MTEF), and, the World Bank Treasury
Reference Model.
Social and Environment
34. The proposed installation of IFMIS does not involve any physical structure or
construction, land acquisition and environmental impacts. IFMIS will be installed in the
existing government buildings. No new buildings are to be constructed. Only up-
gradation of existing computer rooms might be required before installation of IFMIS,
which is not expected to have an environmental impact. The project does not focus on
any particular population group. Therefore, the project will not trigger any environmental
and social safeguard policies. The project restructuring and additional financing is
classified as “Category C”.
14
Risks
35. The risks of adding a new component under the project through the proposed
restructuring are as follows:
(a) Considering the Project closing date is June 30, 2013, the remaining time left
under the project is only six months. If there are any delays at any stage of
implementation, there is a risk that the task might not be completed within project
time. As a mitigation measure, project closing date is being requested to be
extended by 2 months.
(b) The Government may not have the capacity to implement IFMIS as it requires an
understanding of public financial management as well as complex and integrated
IT systems. This may pose risk to the operations, management and sustainability
of IFMIS. This risk will be mitigated by establishing a core group of functional
and technical staff that would work with the FreeBalance team right from the first
stage of system study and design. Also, the government project management team
will be strengthened by recruitment of a new international ICT Advisor and Local
PFM consultant.
(c) The Government may not give timely clearances to interim deliverables of
FreeBalance leading to implementation delays. As a mitigation measure, the
Ministry of Finance has constituted an inter-departmental committee to review
and clear the IFMIS software prototype.
(d) There could be delays in procurement of hardware which is the responsibility of
the government. If that happens, it would lead to an overall implementation delay.
As a mitigation measure, the procurement process of hardware would be started
soon after signing the contract with FreeBalance. The compatible technical
specifications of the hardware have already been provided to the Government by
FreeBalance.
15
Annex 1: Results Framework and Monitoring
REPUBLIC OF IRAQ: Public Finance Management Reforms Project – Restructuring
Results Framework
Revisions to the Results Framework Comments/
Rationale for Change
PDO
Current (PAD) Proposed
The Project Development
Objective is to support
the Government of Iraq's
efforts to develop more
effective, accountable
and transparent public
financial management.
Continued
PDO indicators
Current (PAD) Proposed change*
1. Capital budget
execution rate increases
by at least 10 percentage
points
Continued
2. Outstanding balances
in Spending Units decline
by 30 percentage points,
as a share of the budget
Continued
3. At least 50% of
contracts above threshold
awarded competitively
Dropped There was a mistake in
formulating this indicator.
There was no baseline
estimated at the start of the
project. During the mid-term
review, the Ministry of
Planning reported that at the
start of the project, in 2009,
90 % of the contracts above
national threshold, were
being awarded
competitively. If that was the
case, the target of 50 %
should not have been set up
below the baseline. The
baseline of 90 % was
anyway satisfactory as per
international norms.
4. Ministry of Finance
training institute
providing training in all
operational aspects of
Continued
16
Revisions to the Results Framework Comments/
Rationale for Change
PFM project
Intermediate Results indicators
Current (PAD) Proposed change*
Intermediate Results (Component 1): Strengthening Budget Formulation and
Implementation
1. Draft sector strategies
completed and submitted
to all relevant parties for
comment/revision/etc.
Draft sector strategies prepared
Paraphrased to make it more
simplified and specific. The
Unit of Measure revised to a
logical field (Y/N) and the
yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
2. New procedures in
place for project
preparation and appraisal
Continued
The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
3. New macro-economic
and fiscal “team‟
established within MoF
Economic Policy
Division
Continued
The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
4. New budget
instructions approved and
guidelines ready
Continued
The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
5. New Budget Call
Circular (BCC) in use
Continued The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
Intermediate Results (Component 2): Strengthening Public Sector Procurement
1. Standard Bidding
Documents finalized
Sector specific Standard Bidding
Documents finalized for ministries
of health, education, electricity and
public works.
Paraphrased to make it more
simplified and specific. The
Unit of Measure revised to a
logical field (Y/N) and the
yearly targets revised
17
Revisions to the Results Framework Comments/
Rationale for Change
accordingly to reflect the
targets as per the original
PAD.
2. National Procurement
Manual finalized
Dropped The National Procurement
Manual was to be prepared
in line with the National
Procurement Law. Since the
Government has not yet
passed a National
Procurement Law and it is
not foreseeable in near
future, the National
Procurement Manual cannot
be finalized within the
project time frame.
3. Procurement Bulletin
board being fully
implemented, and housed
within Procurement
Regulatory Agency
Design of single portal website for
public procurement notices
prepared
Paraphrased to make it more
simplified and specific. The
Unit of Measure revised to a
logical field (Y/N) and the
yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
4. Training Needs
Assessment completed,
training curriculum
developed and first round
of „Train-the-trainers‟
completed
Continued The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
Intermediate Results (Component 3): Strengthening Budget Execution and
Implementation
1. First round of training
on new cash release
system completed with
selected pilot ministries
Continued The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
2. Detailed rules and
regulations for new
commitment control
system developed
Continued The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
18
Revisions to the Results Framework Comments/
Rationale for Change
PAD.
3. New financial/fiscal
performance system
developed, and tested in
three ministries
Dropped A new component 5 on
Integrated Financial
Management Information
System (IFMIS) is being
added to the project which
would develop
financial/fiscal performance
evaluation in three ministries
4. Training materials
developed for
financial/fiscal
performance system, and
training of Master
Trainers carried out
Dropped A new component 5 on
Integrated Financial
Management Information
System (IFMIS) is being
added to the project which
would develop training
materials for the
financial/fiscal performance
evaluation system.
5. Assessment of IG
system completed, and
documentation provided
clarifying mandate of
internal controllers
Continued The Unit of Measure revised
to a logical field (Y/N) and
the yearly targets revised
accordingly to reflect the
targets as per the original
PAD.
6. Website being
regularly updated
Website of Ministry of Finance
upgraded for enhancing citizen’s
access of fiscal data.
A regular updation of
website would not have
contributed to the PDO
unless the current website
was upgraded to enhancing
citizen’s access of fiscal
data.
7. IT assessment
completed, and functional
requirements for
upgraded system
developed
Dropped A new component 5 on
Integrated Financial
Management Information
System (IFMIS) is being
added to the project which
would conduct IT assessment
and develop functional
requirements for an upgraded
system.
Intermediate Result Component 4: Capacity Development and Project Management
1. Training program fully
in place
Training program fully in place in
MOFATC
Paraphrased to make it more
specific. The Unit of
Measure revised to a logical
19
Revisions to the Results Framework Comments/
Rationale for Change
field (Y/N) and the yearly
targets revised accordingly to
reflect the targets as per the
original PAD.
Intermediate Result (Component Five): Development and Testing of IFMIS Prototype
1. Prototype for IFMIS
developed
New As per goals and deliverables
of new component
2. Prototype for IFMIS
tested
New As per goals and deliverables
of new component.
20
Revised Results Framework and Monitoring
IRAQ: PUBLIC FINANCE MANAGEMENT REFORMS PROJECT
Project Development Objective (PDO): The Project Development Objective is to support the Government of Iraq's efforts to develop more effective, accountable and transparent public financial
management.
Revised Project Development Objective: n/a
PDO Level Results Indicators*
Co
re
D=Dropped
C=Continue
N= New
R=Revised
Unit of
Measure Baseline
Cumulative Target Values**
Frequency Data Source/
Methodology
Responsibility for
Data Collection YR 1
YR 2
YR 3 YR4
Indicator One:
Capital budget execution rate
increases by at least 10
percentage points
C % 75 82.5 Annual Capital Budget
Execution
Reports of the
MOPDC
MOPDC
Indicator Two:
Outstanding balances in
Spending Units decline by 30
percentage points, as a share of
the budget
C % 38 8 Annual Budget
Execution and
Cash Balance
Reports of the
MOF
MOF
Indicator Three:
At least 50% of contracts above
threshold awarded competitively
D % Not Known 50 Annual Monitoring
Reports of
Procurement
Regulation
Authority
MOPDC,
Procurement
Regulation
Authority
Indicator Four:
Ministry of Finance training
institute providing training in all
operational aspects of PFM
project
C Y/N Y Annual MOFATC
Reports,
Physical
Inspection
MOF, MOFATC
21
INTERMEDIATE RESULTS
Intermediate Result (Component One): Strengthening Budget Formulation and Implementation
Revised Intermediate Result (Component One): Strengthening Budget Formulation
Intermediate Result indicator
One:
Draft sector strategies
prepared
R Y/N N N N N Y Annual Strategy
documents
MoF, MoPDC,
PMT
Intermediate Result indicator
Two:
New procedures in place
for project preparation
and appraisal
C Y/N N N N N Y Annual GoI revised
regulations on
project
preparation
and appraisal
MoF, MoPDC,
PMT
Intermediate Result indicator
Three:
New macro-economic
and fiscal „team‟
established within MoF
Economic Policy
Division
C Y/N N N N N Y Annual Consultant
reports
GoI
regulations as
published
MoF, MoPDC,
Ministry of Oil,
IG and other
internal controls
Intermediate Result indicator
Four:
New budget instructions
approved and guidelines
ready
C Y/N N N N N Y Annual GoI new
budget
instructions
regulations as
MoF, MoPDC,
Intermediate Result indicator
Five:
New Budget Call Circular
(BCC) in use
C Y/N N N N N Y Annual GoI new
Budget Call
Circular
MoF, PMT
22
Intermediate Result (Component Two): Strengthening Public Sector Procurement
Revised Intermediate Result (Component Two):
Intermediate Result indicator
One:
Sector specific Standard
Bidding Documents
finalized for ministries of
health, education,
electricity and public
works.
R Y/N N N N N Y Annual Standard
Bidding
Documents
MoF, PRA,
PMT, Ministries
of health,
education,
electricity and
public works.
Intermediate Result indicator
Two:
National Procurement
Manual finalized
D Dropped
Intermediate Result indicator
Three:
Design of single portal
website for public
procurement notices
prepared
R Y/N N N N N Y Annual Website PRA, PMT,
MoPDC
Intermediate Result indicator
Four:
Training Needs
Assessment completed,
training curriculum
developed and first round
of ‘Train-the-trainers’
completed
C Y/N N N N N Y Annual Consultant
reports
Training
evaluations
PRA, MoF,
PMT, MoPDC
23
Intermediate Result (Component Three): Strengthening Budget Execution and Implementation
Revised Intermediate Result (Component Three): Strengthening Budget Execution
Intermediate Result indicator
One:
First round of training on
new cash release system
completed with selected
pilot ministries
C Y/N N N N Y Y Annual Consultant
reports
Training
evaluations
MoF, PMT, line
ministries
participating in
pilot
Intermediate Result indicator
Two:
Detailed rules and
regulations for new
commitment control
system developed
C Y/N N N N Y Y Annual Consultant
reports
GoI regulations
as published
Training reports
MoF, PMT
Intermediate Result indicator
Three:
New financial/fiscal
performance system
developed, and tested in
three ministries
D Current
reporting
does not
adequately
detail the
outstanding
stock of
advances
End PY1:
New
system for
financial
and fiscal
performan
ce
measurem
ent
developed
and
agreed
New
system
tested in
three
ministries
Training
materials
developed
Training of
“Master
Trainers”
completed
New
system in
place,
leading to
20%
reduction
in unused,
outstandin
g balances
in
Spending
Units
New system being
implemented
throughout GoI
30% reduction in
unused, outstanding
balances in
Spending Units
Semi-
annually
Consultant
reports
GoI regulations
as published
GoI financial
performance
reports
MoF, PMT, line
agencies
Intermediate Result indicator
Four:
Training materials
developed for
D Training
Needs
Assessme
nt carried
Ongoing
training
Ongoing training Training reports MoF, PMT, line
agencies
24
financial/fiscal
performance system, and
training of Master
Trainers carried out
out
Intermediate Result indicator
Five:
Assessment of IG system
completed, and
documentation provided
clarifying mandate of
internal controllers
C Y/N N N N Y Y Annual Consultant
reports
IG evaluation
reports
MoF, MoPDC,
IG, PMT,
Intermediate Result indicator
Six: Website of Ministry of
Finance upgraded for
enhancing citizen’s
access of fiscal data.
R Y/N N N N Y Y Annual Website MoF, PMT
Intermediate Result indicator
Seven: IT assessment completed,
and functional
requirements for
upgraded system
developed
D MoF
department
s
fragmented
in their
information
-sharing
ability
End PY1:
Assessme
nt
completed
of current
IT
environme
nt,
Functional
requiremen
ts for
upgraded
system,
including
for links
with FMIS,
developed
Procurem
ent started
for new
software
and
hardware
This
should
occur
regardless
of
whether it
is through
Project
financing,
internal
GoI
resources,
or other
donors
New software and
hardware are in
place and
contributing to
improved efficiency
of MoF operations
Plans in place for
rollout of system in
next phase
Semi-
annually
Consultant
reports
Technical
specifications
MoF, PMT
25
Intermediate Result (Component Four): Capacity Development and Project Management
Revised Intermediate Result (Component Four):
Intermediate Result indicator
One:
Training program fully in
place in MoFATC
R Y/N N N N Y Y Annual Twinning
institute reports
(particularly
Training Needs
Assessment)
Training
evaluations
MoF (training
institute)
Intermediate Result (Component Five): Development and Testing of IFMIS Prototype
Revised Intermediate Result (Component Five):
Intermediate Result indicator
One: Prototype for IFMIS
developed
N Y/N The
Government
has agreed on the scope
of IFMIS
design on which,
prototype
needs to be developed.
IFMIS
Prototype is
developed after
conducting a
SRS study involving all
stakeholders
Monthly, after
February 2013
onwards
Approval of the
prototype by the
Ministry of Finance
MOF
Intermediate Result indicator
Two:
Prototype for IFMIS tested
N Y/N Prototype is
yet to be developed.
Testing will
be done after it is
developed.
IFMIS
Prototype is tested in the
Ministry of
Finance, 3 pilot
Ministries
and the Board of
Supreme
Audit.
Monthly, after April
2013 onwards
Physical
inspection and testing of the
system by running
it on live data of pilot agencies
MOF, BSA, Pilot
Ministries, Bank Consultants
26
ANNEX 2: Reallocation of Proceeds
REPUBLIC OF YEMEN — IRAQ FINANCE MANAGEMENT PROJECT
P110862
{GRANT}
Restructuring Paper
1. Proceeds for REPUBLIC OF IRAQ PUBLIC FINANCE MANAGEMENT
PROJECT, [Trust Fund No. 094552], P110862 will be reallocated as follows:
Category of Expenditure Allocation % of Financing
Current Revised Current Revised Current Revised
(1) Goods (1) Goods 1,250,000 2,050,000 100 100
(2) Consultants’
services, including
audit, and Training
(2) Consultants’
services,
including audit,
and Training
12,850,000 13,600,000 100 100
(3) Incremental
Operating Costs
(3) Incremental
Operating Costs
300,000 350,000 100 100
Unallocated Unallocated 1,600,0001 0.00
TOTAL 16,000,000 16,000,000 100 100
2. The Iraq PFM project was started in July 2009 and has to be completed by June
2013. Under the Recipient-executed part, against the project cost of $16 million, $2.46
million (15 %) has been disbursed. Under the Bank-executed part, against the project cost
of $2 million, $1.99 million (99.9 %) has been disbursed. Against the total project cost of
$18 million, $4.46 million (25 %) has been disbursed.
3. Under the Recipient-executed part, the uncommitted funds are US$ 7.00 million,
which is about 44 % of the project cost. There is no additional requirement of funds
under the existing components and most funds are committed. There is no other purpose
for which the government wants to spend the uncommitted amount. Hence, the proposed
reallocation is necessary to provide funds for the new component 5 (IFMIS). It will be
done by reallocation of the uncommitted and unallocated funds under the project.
Considering the implementation of IFMIS will require additional funds under
consultancy, goods and incremental operating costs, commensurate increases have been
made in those categories as per above table.
1 The US$ 1.6 million cited here is from the Allocation of Proceeds table in the Conformed Copy of the
Grant Agreement, and Annex 4 of the Emergency Project Paper (EPP) which at the time of Negotiations
was taken as 10% of the total Project cost. The larger figure cited earlier – US$ 2.82 million – is the figure
used in the EPP Annex 3 (Summary of Estimated Costs): refer to EPP Annex 3 Note 2, “..the bulk of the
Unallocated has been included in the Consultant Services category, as this category represents the majority
of the downstream activities.”
27
ANNEX 3: Extension of Closing Date
1. The Iraq Public Financial Management (PFM) project was started as an
emergency operation in July 2009 under the Iraq Trust Fund (ITF). The project is to be
completed in June 2013. The total estimated cost of the Project is US$18 million: i)
US$16 million to be Recipient-executed; and ii) US$2 million to be Bank-executed on
behalf of the Recipient. Under the Recipient-executed part, against the project cost of
$16 million, $3.6 million (23 %) has been disbursed. Under the Bank-executed part,
against the project cost of $2 million, the entire $2 million (100 %) has been disbursed.
Against the total project cost of $18 million, $5.6 million (31 %) has been disbursed.
2. The Government of Iraq, Ministry of Finance, has requested extension of the
project closure date citing that the implementation of the Project could not start until
mid-2011 because the premises of the Iraqi Ministry of Finance were exposed to three
terrorist attacks, which resulted in delaying the project. The continuous fragile security
situation in Iraq posed a challenge for foreign consultants who found it risky to travel to
Iraq on their respective assignments. While in Iraq, the security situation restrained their
movements and the time for which they could meet the government counterparts.
3. The Government of Iraq, Ministry of Finance, has requested extension of the
project closure date citing that the implementation of the Project could not start until
mid-2011 because the premises of the Iraqi Ministry of Finance were exposed to three
terrorist attacks, which resulted in delaying the project. The continuous fragile security
situation in Iraq posed a challenge for foreign consultants who found it risky to travel to
Iraq on their respective assignments. While in Iraq, the security situation restrained their
movements and the time for which they could meet the government counterparts.
4. The task team partly agrees with the justification provided by the Government and
feels that the adverse security situation has been one of the several reasons leading to a
slow pace of project implementation in the initial part of the project leading to less than
3 % disbursement at the time of mid-term review in August 2011. The project involves
inputs from international consultants, who find it extremely difficult to operate in the
prevalent security environment. There are delays in issuing visas and restrictions on
their movements in Iraq. The more substantive reasons for the implementation delays
were as follows:
a) Significant delay in procuring goods and signing consultancy services contracts.
b) The payment approval procedure adopted by the Project Management Team
(PMT) was not appropriate and effectively delayed payment to consultants.
c) High level of uncommitted funds
d) Lack of full time staff
e) Lack of independent office for the PMT
5. Most of above factors have now been rectified and proposed restructuring and
addition of a new component on IFMIS would enable the project to increase its
commitments to 100 %. From thereon, a good contract management and Bank’s
28
supervision could ensure that the project is fully disbursed and the targeted results
achieved.
6. However, the main reason why the extension is necessary is that as a restructuring
process, a new component IFMIS is being added which requires a minimum 9 months’
time to be completed. A Contract is about to be signed under which the 9-month
implementation schedule is as follows.
Activity/Milestone Time-Period
(ii) System Requirement Study January – March 2013
(iii) Preparation of configuration
blue print for the prototype
April – June 2013
(iv) Establishment of ICT
infrastructure
February – April 2013
(v) Testing of Prototype at MoF July - August 2013
(vi) Testing of Prototype at 5
Treasuries, 3 Line Ministries and
Board of Supreme Audit
August - September 2013
7. At best, the above implementation schedule could be reduced to 8 months by
doing activities (v) and (vi) in parallel, during July-August 2013. The task team,
therefore, recommends extension of the project closure date until 31 August 2013. These
two extra months would enable the government to ensure completion of ongoing
activities in a timely and orderly manner. If this extension is not given, the project
objectives will be difficult to achieve. This is the first and last extension of the project.