+ All Categories
Home > Documents > World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL...

World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL...

Date post: 29-Jun-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
125
Document of The World Bank FOR OFFICIAL USE ONLY ReportNo. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department South Asia Regional Office This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
Page 1: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Document of

The World Bank

FOR OFFICIAL USE ONLY

Report No. 4293-IN

STAFF APPRAISAL REPORT

INDIA

CENTRAL POWER TRANSMISSION PROJECT

April 26, 1983

Regional Projects DepartmentSouth Asia Regional Office

This document has a restricted distribution and may be used by recipients only in the performance oftheir official duties. Its contents may not otherwise be disclosed without World Bank authorization.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

CURRENCY EQUIVALENTS.

Currency Unit = Rupee (Rs)Rs 1 Paise 100US$1 = Rs 9.5 1/

Rs 1 US$0.105 1/Rs 1 million = US$105,267 1/

MEASURES AND EQUIVALENTS

1 Kilometer (km) = 1,000 meters (m) = 0.6214 miles (mi)1 Meter (m) 3 39.37 inches (in)1 Cubic Meter (m ) = 1.31 cubic yard (cu yd) = 35.35 cubic feet (ft)1 Hectare (ha) = 10,000 m = 2.471 acres (ac)1 Kilogram (kg) = 2.2046 pounds (lb)1 Ton (t) = 1 meteric ton = 2,200 lbs1 Kilocalorie (kcal) = 3.968 British Thermal unit (Btu)1 Kilovolt (kV) = 1,000 volts (V)1 Kilovolt ampere (kVA) = 1,000 volt-amperes (VA)1 Megawatt (MW) = 1,000 kilowatts (kW) = 1 million watts1 Kilowatt hour (kWh) = 1,000,000 watt hours1 Megawatt hour (MWh) = 1,000 kilowatt hoursI Gigawatt hour (GWh) = 1,000 kilowatt hoursI Mega volt ampere (MVA) = 1,000 kilovolt ampere (kVA)1 Mega volt ampere reactive

(MVar) = 1,000 kilovolt ampere reactive (kVar)I Mega volt ampere reactive

hour (MVarh) = 1,000 kilovolt ampere reactive hour (kVarh)

ABBREVIATIONS AND ACRONYMS

AC - Alternating CurrentAIC - Average Incremental CostAPSEB - Andhra Pradesh State Electricity BoardCIF - Cost Insurance FreightCEA - Central Electricity AuthorityDC - Direct CurrentHT - High tensionHVDC - High Voltage Direct CurrentGOI - Government of IndiaIDA - International Development AssociationKfW - Kreditanstalt fuer WiederaufbauLOLP - Loss of Load ProbabilityLT - Low TensionMPC - Mysore Power CorporationNHPC - National Hydro Power CorporationNTPC - National Thermal Power CorporationOPEC - Organization of Petroleum Exporting CountriesPERT - Program Evaluation and Review TechniquePLCC - Power Line Carrier CommunicationREB - Regional Electricity BoardSEB - State Electricity Board

NTPC's FISCAL YEAR (FY)April i - March 31

l/ The US$/Rs exchange rate is subject to change. Conversions in thisreport have been made at US$l to Rs 9.5, which represents the projectedexchange rate over the disbursement period.

Page 3: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-1i-

FOR OFFICIAL USE ONLY

INDIA

CENTRAL POWER TRANSMISSION PROJECT

STAFF APPAISAL REPORT

Table of Contents

Page No.

I. THE POWER SECTOR ...... ............................ 1Background ...................................................Past Bank Group Involvement in the Sector .................... 2Bank Group's Strategy ......................................... 3Southern Region Demand and Supply ....................... 6

II. THE BENEFICIARY - NATIONAL THERMAL POWER CORPORATION LIMITED . 8Legal Status and Authorities ....... ... ....... *............ 8Organization and Management. ....... . . .... . 9Recruitmnt and Training .......... ........... ............. 10Accounting Organization and Systems . ...... ....... 12Audit ... D*s*@@*v@***@¢¢@@@v........................................ * . . . ..... 12

III. THE PROGRAM AND THE PROJECT ........ ......................... . 14The Program .. . .................... .. ............. 14

The Project .......................... 14Estimated Cost ...... .... ........ .. .. 15

Project Financing ............................................ 17Engineering ........ 17Construction and Procurement.. 18Disbursemernt .. . .. . . . ... ... 19

Ecology .... o ....... ........ ...... ........ ........ .... o. 19Project Risks ................................................... ......... 20

IV. FINANCIAL ANALYSIS .... ............ ........ ..................... 21A. NATIONAL THERMAL POWER CORPORATION LIMITED (NTPC) ........ 21

- Investment Program ..................................... 21- Future Earnings ............. . ...... .................... 21-NTPC Consolidated Operations ......... 22- NTPC Regional Operations 23- Taxation....... 23

This project was appraised by Messrs. Victor Antonescu (Power Engineer),John Creasor (Financial Analyst), Karl Jechoutek (Economist) and Yves Albouy(Economist), based on information obtained during a mission in September/October 1982.

This document has a restricted distribution and may be used by recipients only in the performance oftheir official duties. Its contents may not otherwise be disclosed without World Bank authorization.

Page 4: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Page No.

- Internal Cash Generation FY1977-FY1995 . . 23- NTPC's Financing Plan FY1983-FY1992 . . .24- Onlendiing Agreement . . ....................... ........... 25- Future Finances .... 26

- Borrowing Powers ..... ......... . .. 27

- Commercial Arrangements for Sale of NTPC Energy . .27

B. ANDHRA PRADESH STATE ELECTRICITY BOARD (APSEB) . .28- Investment Program .. 29- Future Earnings .. 29

- Internal Cash Generation. 29

V. JUSTIFICATION AND ECONOMIC ANALYSIS .. 30General .. 30Method of Analysis .. 30Intra-Regional Lines ....................... 30

Southern/Western Region Intertie . . .32Northern/Western Region HVDC Intertie . . 33Tariffs and Cost of Supply . . .33

VI. SUMMARY OF AGREEMENTS AND RECOMMENDATION ............ 36

ANNEXES

1. Power Sector Loans and Credits ................................ 372. Electricity (Supply) Act 1948 - Proposed Ammendments, October

1982 ........................................................ 383. Rates of Return of SEBs (FY1979 - FY1982) ..................... 434. All-India Sales and Energy Data 1974/75 to 1981/82 ............ 445. Long-term System Expansion Plan ............................... 456. Southern Region Sales and Energy Data 1979/80 - 1981/82 ....... 577. Southern Region: Installed Capacity, Peak Load and Energy

Requirement 1977/78 - 1981/82 ............................... 588. Southern Region Power Supply Restrictions ..................... 599. NTPC - Organizational Structure (Revised) ..................... 6010. NTPC - Manpower as of September 30, 1982 ...................... 6111. NTPC - Recruitment of Trainees ................................ 6212 NTPC - Organizational Structure Corporate Finance .. ........... 63

13. Project Description ........................................... 6414. Project Cost Estimates ........................................ 82

15. Implementation Schedule ...... ................................. 8616. Estimated Schedule of Disbursements .................. ......... 8717. Schedule of Commissioning of Power Plants and Power Generation

Versus Schedule at Time of Second Ramagundam Appraisal .88

Page 5: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-iii-

Page No.

18. Investment Program for the Period FY1977 through FY1996 ....... 8919. Comparison of Current Cost Estimates with Previous Appraisals 9020. Statement of Plant Capacity, Generation and Sales of Energy 9121. NTPC - Income Statement Covering Operations FY1983 through

FY1995 .9322. NTPC - Sources and Application of Funds for the Period FY1977

through FY1995 .............................................. 9423. NTPC - Balance Sheets FY1977 through FY1995 .... ............... 9524. NTPC - Assumptions for Financial Projections .... .............. 9625. NTPC - Income Statement Covering Operations FY1983 through

FY1995 - Northern Region ..............................---... 102

26. NTPC - Income Statement Covering Operations FY1983 throughFY1995 - Western Region ....................... ... 103

27. NTPC - Income Statement Covering Operations FY1983 throughFY1995 - Southern Region. ............... .. ........... 104

28. NTPC - Income Statement Covering Operations FY1983 throughFY1995 - Eastern Region .... 105

29. APSEB - Income Statement Covering Operations FY1980 throughFY1989 ...................................................... 106

30 APSEB - Net Internal Cash Generation FY1980 through FY1989 .... 10731. APSEB - Balance Sheet as at end of FY1980 through FY1989 ..... 10832. Southern Region - Additional Transmission Requirements 1995 ... 10933. Costs and Benefits of Intra-Regional Transmission ............ . 11034. Southern/Western Transmission Link: Least-Cost Solution 11...... I35. Northern/Western D.C. Link: Least-Cost Solution .............. 11236. APSEB Tariffs ................................................. 11337. Marginal Cost of Electricity Supply in Andhra Pradesh ... ...... 11538. Documents Available in the Project File ....................... 117

MAP

IBRD - 16845R

Page 6: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department
Page 7: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

I. THE POWER SECTOR

Background

1.01 The development of India's economy and the improvement of itspeople's standard of living depend to a large degree on the development ofthe power sector. Over the last two decades, power demand has grown twice asfast as the economy, and the power sector now takes the largest share ofpublic investment (12% of the Sixth Five-Year Plan outlay). This was due tothe rapid development of power-intensive industry and the expansion of ruralelectrification tor irrigation.

1.02 In spite of an increase in generating capacity from 5,600 MW in1960 to about 32,000 MW in 1982, power shortages have been experienced invarious -arts of the country for a number of years, and gaps between supplyand demand will impose major constraints for some years to come.

1.03 Before 1975, power facilities were planned, constructed andoperated by each State to meet its own needs. Because of the rapid growth ofthle power sector, the Government of India (GOI) decided to create newinstitutional structures in the sector, and to emphasize central planning ofgeneration and high voltage transmission with the ultimate objective ofcentral control through a national grid. The Central Electricity Authority{CFA) performed studies of a national power system, and GOI decidegvtoproceed with the construction of four large centrally-owned thermal powerstations located at coal fields, supplying bulk power to the States throughan interconnected 400 kV transmission system. The construction of thesepower stations (2,000 MW at Singrauli, 2,100 MW at Korba, 2,100 MW atRamagundam, and 600 MW at Farakka) was begun with Bank Group financialassistance. The first phase of the program comprised the first stage of 600MW at each plant, and its associated transmission. In addition, IDA Creditsfor the second stage of Singrauli (1,400 MW) and the second stage of Korba(1,500 MW), and a Bank loan for the second stage of Ramagundam (1,500 MW),have been approved. A proposal for the second stage of Farakka (1,500 MW)has been submitted recently for consideration by the Bank Group. The subjectof this report is the extension of NTPCts 400 kV transmission system toincrease the capacity of power transmission from Ramagundam to the Southernpart of the country and to interconnect the Northern, Western and SouthernRegional grids. A Bank loan of US$250.7 million is proposed.

1.04 The energy and power sectors and the problems associated with thelatter have been fully described in the Staff Appraisal Report No. 3608b-IN

Page 8: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-2-

dated November 30, 1981 for the Second Ramagundam Thermal Power Project.1/The following paragraphs deal only with the changes that have occurred sinceor with sector aspects directly related to the proposed project. Updatedinformation in regard to the Indian power sector is provided in Annexes 2 to5.

Past Bank Group Involvement in the Sector

1.05 The Bank has made thirteen loans for Indian power projects amountingto US$982.5 million, and fifteen IDA credits totalling US$2,096.0 million(Annex 1). Fifteen projects financed under the following loans and creditshave been completed: ten generating projects, the Beas Project (Credit89-IN), the first three transmission projects (Loan 416-IN, Credits 242-INand 377-IN) and the First Rural Electrification Project (Credit 572-IN). TheFourth Transmission Project (Credit 604-IN) is expected to be completed inthe first half of 1983. The Third Trombay Thermal Power Project (Loan1549-IN), Singrauli (Credit 685-IN), Korba (Credit 793-IN), and Ramagundam(Credit 874-IN and Loan 1648-IN) Thermal Power Projects, and the Second RuralElectrification Project (Credit 911-IN) are in an advanced stage ofimplementation. The credit for the Second Singrauli Thermal Project (Credit1027-IN) and the credit/loan for the first stage of the Farakka Thermal PowerProject (Credit 1053-IN and Loan 1887-IN) were approved in May and June 1980.Korba II (Credit 1172-IN) was approved in July 1981, Ramagundam II (Loan2076-IN) in December 1981 and the Third Rural Electrification Project (Loan2165-IN) in June 1982. The Trombay and Second Rural Electrification Projectsare on schedule. The three 200 MW units of the Singrauli Project and thefirst 200 MW unit of the Korba Project were commissioned on schedule. TheFarakka and Ramagundam Projects are proceeding satisfactorily after initialdelays.

1.06 A Project Performance Audit Report on the Second Power TransmissionProject (Credit 242-IN), issued on June 3, 1980, stated that the project hadbeen successful in assisting nine State Electricity Boards in extending theirtransmission systems to help meet their growing requirements. Utilizationof generating capacity in the nine SEBs exceeded the appraisal forecast.Institutional objectives mainly concerned the rehabilitation of the financesof the SEBs, and while the results achieved by project completion weremodest, improvement was continued by the Third and Fourth Power TransmissionProjects (Credits 377-IN and 604-IN). In FY 1980, seven of the nineparticipating SEBs reached their target rate of return of 9.5%. Theconclusions of the Report pointed to: (a) the difficulty for the Bank Groupin adequately supervising work other than procurement on the project, since

1/ Second Ramagundam Thermal Power Project Staff Appraisal Report (ReportNo. 3608b-IN) paragraphs 1.04 to 1.12 and 1.17 to 1.35.

Page 9: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-3-

it consisted of many sub-projects scattered all over India, and (b) theabsence of a close working relationship between the Bank Group and thebeneficiary SEBs, which made efforts for institutional improvementsdifficult. The Report suggested that more direct involvement with the SEBsin projects of this nature, where an efficient intermediary is not available,would be beneficial.

Bank Group's Strategy

1.07 The Bank Group's strategy in the Indian power sector has been tocooperate with GOI in finding solutions to the many difficult and politicallysensitive problems confronting the Indian electricity supply industry. TheBank's main objectives in the sector are:

(a) to eliminate power shortages by the installation of generationand transmis3ion capacity, and the promotion of measures toimprove the operation and maintenance of existing plant;

(b) to introduce long-range system planning on anationwide basis so as to assure implementation of a

-' least-cost power development program;

(c) to promote improvements in sector organization and training; and

(d) to strengthen the finances of the institutionsin the sector, particularly the State ElectricityBoards.

1.08 The States, through their Electricity Boards, develop and operatemost power facilities. Under the Constitution, power supply is a concurrentsubject, which means that responsibility is shared between the CentralGovernment and the State Governments, requiring full agreement between thembefore action can be taken. Despite many difficulties, improvements achievedso far have been encouraging. With the establishment of Regional ElectricityBoards (REBs), the National Thermal Power Corporation (NTPC) and the NationalHydro Power Corporation (NHPC), important steps towards an improvedorganizational structuy'e of the power sector have been made. CEA wasreorganized and its powers enlarged; amendments in the financial provisionsof the Electricity (Supply) Act clarified the requirements to be followed intariff setting, the financial performance of SEBs improved, the majority ofSEBs have completed tariff studies based on marginal cost pricing principles,CEA has prepared a national long-term power development plan, and theimplementation of increased investments in the sector will help eliminate thepower deficit.

1.09 Because of the rapid expansion of the power industry, all aspects ofthe sector needed to be reviewed and solutions found for its variousproblems. GOI established in 1978 the Committee on Power, which submitted

Page 10: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-4-

its conclusions to GOI in September 1980. They refer to all major aspects ofthe power sector including planning, project formulation and implementation;operation and maintenance; organization and management; finance, financialmanagement and tariffs; rural electrification; and research and development.The recommendations of the Committee on Power, most of which are satisfactoryin light of the Bank Group's strategy, form a basis for improvement of allthose aspects of the power sector. Implementation of the Committee'srecommendations has already started with those aspects that do not requireGOI's formal approval, such as better planning procedures and improvedoperating and maintenance management.

1.10 In accordance with undertakings agreed during negotiations for theSecond Korba Thermal Power Project, GOI submitted, in May 1982, a program forthe implementation of five categories of power sector improvements which theBank Group considered areas of high priority. Satisfactory progress has beenmade in these five areas for which some of the more recent activities andachievements are as follows:

(a) Performance of Thermal Power Plants

The Department of Power in GOI has established teams of specialists,including representatives from CEA, SEBs and manufacturers, to visit allthermal power plants with 100/120 MW and 200/210 MW generating units in thecountry to diagnose technical and operational problems, propose solutions,and assign responsibilities for their implementation. Repeat visits areplanned to assess progress.

(b) Coordination of Power Development and Growth in Other Sectors

The Bank Group received the draft national long-range plan for powerdevelopment in September 1982. This plan provides forecasts of power demandthrough the year 2000 and projects the generating capacity and equipment thatwill be required to meet this demand. The draft plan, which is expected tobe finally adopted by the Government, will provide the basis for bothfive-year plans andl annual investment programs.

(c) Intensification of Hydro-Electric Power Development

GOI is progressing with plans for a number of hydro projects, some ofwhich will be proposed for Bank Group financing and others for bilateralassistance. Several projects -- among them Vishnu Prayag (UP), Lohari Nag(UP), Naptha Zhakri (HP), Puyan Kutti (Kerala), and Lower Periyar (Kerala) --have reached advanced stages of project preparation. The Upper Indravatiproject, the first hydro-power project in India to be proposed for Bank Groupfinancing, is presently being appraised. In addition, GOI is planning tobegin investigations on what is expected to be the largest hydro-powerproject in the world -- the 15,000 MW Dihang project in north-eastern India,where a number of other projects are also under consideration.

Page 11: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-5-

(d) Strengthening the Role of the Central Sector in Power Generation andInter-state High-Voltage Transmission

(i) GOI, through NTPC, has under construction and partly inoperation over 9,000 MW of power generating capacity. Inaddition to the four ongoing Bank-Group financed super-thermalplants (Singrauli, Korba, Ramagundam and Farakka), which (exceptfor Farakka) are now in their second phases of construction, twolarge thermal power plants -- the 1000 MW plant at Rihand (UP)and the 1260 MW plant at Vindhyachal (MP) -- are also beingundertaken by NTPC. Agreements with the UK and USSR,respectively, for the financing of these plants were signed in1982 (para 4.10).

(ii) The proposed project is designed to reinforce the Centrally-owned NTPC power transmission grid, and provides the first stageof integration of the Northern, Western, and Southern regionalgrids, taking into account compatability for eventual energypooling.

(e) Establishment of Financial Objectives and Policies for theirImplementation, Principles for Evolving Rational Tariff Policies andImprovements in Management Information and Accounting Systems forState Electricity Boards.

(i) Draft legislation for amendment of the financial provisions ofthe Electricity (Supply) Act, 1948 has been prepared by GOI forsubmission to Cabinet at the next session of Parliament, earlyin 1983. These amendments will remove some of the anomalies inthe Act which have been in the past the source of a number ofproblems relating to the financial performance of the SEBs(Annex 2).

(ii) Management consultants have started the review of presentaccounting practices in two of the SEBs with the ultimateobjective of developing a uniform system of commercialaccounting for adoption by all of the SEBs. Their review willbe followed by preparation of a draft accounting manual bySeptember 1983 which will form the basis of the new accountingsystem scheduled for introduction in 1984. An accounting unitis at present being established within CEA to monitor thedevelopment of the new accounting system and the financialperformance of the SEBs.

(iii) With the Third Rural Electrification Project, approved in June1982, new financial performance criteria for the SEBs wereintroduced. These are designed to provide for reasonable

Page 12: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-6-

contributions by the SEBs to power investment, and to graduallyreduce State Government subsidies for rural electrifica;4ionlosses.

Southern Region Demand and Supply

1.11 Data concerning the all-India power demand and supply situation andoutlook are provided in Annex 4. The following paragraphs of this chapterdeal with the demand and supply situation of the Southern Region where theproposed project is located. The major authorities supplying the SouthernRegion are the Tamil Nadu, Andhra Pradesh, Karnataka and Kerala StateElectricity Boards, and the Mysore Power Corporation (MPC). In addition, anumber of small municipalities are engaged in power supply. All entities,except MPC, supply electricity to final consumers, but only the four SEBs andMPC own generation facilities. MPC supplies about 85% of the power madeavailable to consumers by the Karnataka SEB.

1.12 The Southern Region is the only fully integrated electricity supplyregion in India, controlled by a Regional Load Dispatch Center at Bangalore.Load frequency control equipment at Bangalore is now operational. The largehydro component in the system allows energy to be transferred during themonsoon from SEBs with a reservoir-spilling surplus to others in the Region,while in the early summer months thermal generation is maximized to husbandscarce water. In addition to its internal integration, the Region oftenoperates in parallel with the Western Region, particularly the States ofMaharashtra and Gujarat, and with Orissa in the Eastern Region.

1.13 In line with the national pattern, Regional consumption is heavilyoriented towards industry: about 61% of total consumption in the Region isattributable to industrial consumers, and about 18% to agriculturalconsumers. This pattern masks significant differences among States. Theshare of agricultural consumption in Tamil Nadu is about 27%, while 70-75% ofKarnataka's and Kerala's supplies go to industry and only 5-8% toagriculture. Tamil Nadu is the dominant State in the Region with about 40%of the total consumption of electricity. Sales in the Region have beengrowing at a steady rate of about 7% p.a. between 1970 and 1980, most ofthis in periods of supply restrictions. Generation and sales growth in1979/80 was a minimal 2% largely due to widespread supply difficulties andlow reservoir levels, followed by a return to normal growth in 1980/81 (Annex6).

1.14 Andhra Pradesh is the only State in the Region that has more than 50%thermal capacity; Kerala and Karnataka are solely hydro. While installedcapacity has grown at about 7% p.a. between 1970 and 1980, actually availablecapacity at peak showed a growth rate of about 7.5%, resulting in asignificant improvement in availability from about 65% to more than 70%. Asenergy consumption has been increasing at an annual rate of 7% the systemload factor decreased to about 57% in 1980, from more than 60% in the early

Page 13: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-7-

1970s, making the system peak more pronounced. In recent years, developmenthas been erratic. Installed capacity has been increasing at about 7% p.a.,but peak availability declined to just slightly above 60% of installedcapacity. Forced outages have suppressed the growth of peak demand,increasing the system load factor to more than 70% (Annex 7). As in previousyears, severe supply restrictions were imposed mainly in Karnataka andKerala, especially on industrial consumers in 1981/82, ranging from 10% to50% of potential demand or connected load (Annex 8).

1.15 Potential unconstrained peak capacity demand in the Region isexpected to grow at about 9% p.a. until 1995, energy demand at about 8%.Large capacity additions due to come on stream during 1982/83 and insubsequent years are expected to increase supply reliability almostimmediately. The expected loss of load probability during the 1980s isreasonably low, even with high forced outage rates. Much depends on timelyapproval and implementation of generation projects, and the provision ofappropriate transmission capacity (Annex 5).

Page 14: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-8-

II. THE BENEFICIARY - NATIONAL THERMAL POWER CORPORATION LIMITED

Legal Status and Authorities

2.01 NTPC, the beneficiary of the proposed credit, was established in 1975and is registered under the Companies Act, 1956. It is a company whollyowned by GOI and functions under the general supervision cf the Ministry ofEnergy. Its initial authorized share capital of Rs 1,250 million (US$132million) was increased to Rs 8,000 million (US$842 million) in June 1980 andRs 15,000 million (US$1,579 million) in September 1981. The paid-up capitalof the Corporation on Septeber 30, 1982 was Rs 10,047 million. TheCorporation has a Board of ten Directors including the Chairman and ManagingDirector.

2.02 Under its Memorandum and Articles of Association, NTPC has broadpowers to carry out its work. However, the tariffs to be applied as well asany changes in such tariffs, its investment plans and annual capital budgets,have to be approved by the Government. NTPC is also subject to periodicexamination by the Committee on Public Undertakings--a body established byGOI to monitor the performance of public sector enterprises.

2.03 The main objectives for which the Corporation was established are:

(i) to design, construct, and operate large central thermalpower stations and transmission systems; and

(ii) to transmit anid sell the power generated.

With the approval of the proposed project, NTPC will be constructing most ofthe EHV (extra high voltage) transmission system being established by theCentral Government to develop effective interconnected regional systems forultimate integration into a national grid. NTPC will own and operate this400 kV transmission system, over which power will be distributed from eachplant and sold in bulk to SEBs, as well as the inter and intra-regional linksbeing established under this project. Later these systems will be part ofthe 400 kV interconnected regional systems which, subsequently, is intendedto be integrated into the national grid.

2.04 NTPC's present program provides for the construction of six thermalpower stations (Singrauli, Korba, Ramagundam, Farakka, Rihand andVindhyachal). It is also possible that NTPC might ultimately take overownership of the 720 MW Badarpur station near Delhi, which is at presentbeing managed by NTPC on a management-fee basis. NTPC has also undertakeninvestigations for identifying additional sites for thermal power stations inthe Central sector. Based on these studies, feasibility reports submitted byNTPC for pithead developments at Kahalgaon (Bihar), Talcher (Orissa) andPench (Madhya Pradesh) are under consideration by COI. Feasibility studiesfor other sites, i.e., a Capital Region project near Delhi, Birbhum (WestBengal) and Mangur (Andhra Pradesh) are under formulation. The totalcombined capacity to be installed at these sites in the first instance is

Page 15: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-9-

likely to be about 4,000 MW while the ultimate potential is estimated to benearly 10,000 MW.

Organization and Management

2.05 NTPC has entered the operational phase of its development with thecommissioning of the first three generating units constructed by NTPC. Themost recently installed 210 MW unit at the Badarpur Thermal Power Stationnear Delhi was synchronized in December 1981 while the first two 200 MW unitsat Singrauli were commissioned in February 1982 and November 1982respectively.

2.06 JIi7PC's organization has so far been construction oriented to cater tothe predominant activity of construction work on the large power plants. Arevised corporate organization structure (Annex 9) has now been designedkeeping in view the beginning of the operations phase of the power plants andthe growth and expansion, in both power generation and transmission,envisaged for the Corporation in the years to come.

2X07 Earlier, NTPC had adopted a three-tier organization structure. Thefirst tier consisted of the corporate functions of Planning and Marketing,Personnel and Finance which were entrusted with normal corporate levelresponsibilities. The second tier consisting of other services relevant tothe construction phase of the projects such as Technical Services, Contractand Procurement Services, Quality Control, Expediting and Project ManagementServices were centralized as service functions and located at headquarters.The third tier, which embraced direct project activities, consisted of aproject organization for each of the four power plants which were underconstruction. Each project organization was headed by a General Managerentrusted with total responsibility for implementation of all aspects of theproject's construction program. Under this structure, the heads of thecorporate and service functions departments, as well as heads of projectorganizations, reported to the Chairman and Managing Director. This, withaccent on centralization at the corporate level, had some major advantageswhich undoubtedly served the organization well during the formative years.

2.08 However, with the recent addition of the Rihand and Vindhyachalprojects and the advent of the operational phase of both generation andtransmission, there has been a significant increase in the task before NTPCin terms of volume, dimension and complexity. The increased scale ofactivities, as well as the geographically dispersed nature of operations,brought into focus the need for greater decentralization. In consultationwith the Central Electricity Generating Board of U.K., an organizationalstudy was undertaken. As a result of this study, and in-house efforts, arevised organization structure was developed. The proposals formulated inthis regard have now been considered and approved by the Board of Directorsof the Corporation.

Page 16: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-10-

2.09 Under the new organizational structure (Annex 9), regional groupsheaded by Executive Directors have been formed with total responsibility forplanning, design, procurement, construction, commissioning, operations andmaintenance for thermal power stations and associated transmission facilitiesin each region. These activities will be carried out within the framework ofoverall guidelines laid down by the corporate headquarters. Teams for each

project have also been constituted at the regional level consisting of groupsfor planning, engineering, contracts and expediting and will be headed bysenior level officers. This will enable greater accountability of thetechnical support functions to the project organizations. At present theregional headquarters are functioning from Delhi. However, at an appropriatetime they will be shifted to suitable locations within the boundaries of therespective regions. The organizational set-up at project sites remains thesame as before.

2.10 Under the new set-up the role of the corporate center will be one ofpolicy making and providing functional guidance to the regional and projectorganizations. In addition to the corporate functions of Finance, Personneland Planning and Monitoring, a core engineering group responsible to Director(Technical) and a techno-commercial group responsible to Executive Director(Commercial) are proposed to be created. In order to ensure uniformimplementation of policies and corporate guidelines, various groups anddepartments at the regional and project levels will be functionallyresponsible to the corresponding staff departments at the Corporate Center.

2.11 The decentralized organizational structure should contributesignificantly to the effective management of the expanding Corporationthrough providing for a greater delegation of responsibility and authorityand through establishing accountability and measurement of performance onregional and sub-regional levels.

Recruitment and Training

2.12 NTPC is a young organization which is growing rapidly to meet thedemands of its large construction program. The next phase of expansion wil1involve the need to recruit and train operating staff. When all currentdevelopments have been completed and commissioned, NTPC will have a staff ofabout 21,000. The importance, therefore, of implementing training programsfor the various skills required during the construction and operationalphases cannot be too highly stressed. Manpower by category of staff atSeptember 30, 1982 and additional recruitment required to meet projectedrequirements by FY1990 are provided in Annex 10. NTPC's present manpowerrepresents 43% of its FY1990 requirement (48% for executives, 50% forSupervisors, and 37% for skilled and unskilled staff). These figures showthat recruitment is progressing at a sufficiently satisfactory level to meetoperational needs as plant completions progress and commercial operationsexpand.

Page 17: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-11-

2.13 NTPC has placed special emphasis on the importance of training in itsorganizational development, and programs are being developed by theCorporation which will be backed by 200 MW and 500 MW simulators, financedfrom the proceeds of Credits 793-IN and 1053-IN, as well as other modernfacilities for instructing and training the operating staff. Well plannedand well structured training programs have been developed for all categoriesof staff. The program is being effectively executed and is modified andimproved on a continuing basis in light of actual experience. Traineerecruitment, by category of staff, to date and projected requirements toFY1990 are set forth in Annex 11. Actual trainee recruitment to date as apercentage of projected requirements by FY1990 is 19% (executives 34%,Supervisors 18%, and skilled workers 9%).

2.14 Training programs which previously have concentrated onpre-operational activities such as Planning, Design and ConstructionManagement, are now aimed more at operations. Some of the current major

activities are:

(a) Training in professional engineering for executivetrainees.

(b) Training in professional engineering for supervisorytrainees.

(c) Accounting training for accounting and managerial staff.

(d) Management development programs.

(e) Seminars and lectures on selected topics.

(f) Familiarization courses for both accounting and managerialstaff on the accounting systems and procedures beingimplemented.

Mainly engineering graduates (mechanical, electrical, civil) are beingrecruited and inducted into a one-year training program. The first group of35 young executive trainees was recruited in February 1977. Since then sixmore groups consisting of 831 trainees have been recruited, the last of which(150 trainees) was recruited in September 1982. The training programs havebeen well designed to provide exposure to construction and operation,equipment manufacturing plants, engineering and project management services.For these purposes, assistance is taken from a large faculty of experiencedengineers and managers selected throughout the country. NTPC is alsoutilizing the facilities of the Central Electricity Generating Board (U.K.)for training of operation and maintenance staff.

2.15 The first two 200 MW generating unit (at Singrauli), which commencedoperation in February and November, 1982 respectively, have been adequately

Page 18: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-12-

staffed. Advance action has been taken for the requirement of subsequentunits for which 146 executives and 119 supervisors are in postion. NTPC hasfinalized comprehensive plans for training operational staff, particularlythe non-supervisory staff in the various technical and non-technical trades,and to provide foremen for the 200 MW units at Singrauli and Korba. Themanpower for these is being drawn from experienced staff as well as fromfresh recruitment. The personnel required for the first 200 MW unit at Korbaare already in position. Recruitment of operational manpower has alsocommenced for the subsequent units at Korba and Ramagundam. Key personnelrequired for the associated transmission systems, together with adequatesupport staff, are in position.

2.16 On-the-job training has high priority. The methodology includesclassroom lectures, participation in group exercises and discussionssupported by direct reading, audio-visual presentations and plant visits.Overall training plans and arrangements at this time are satisfactory.

Accounting Organization and Systems

2.17 NTPC continues to report good progress in the planning andimplementation of its finance and accounting organization (Annex 12) and inthe design and implementation of accounting systems and procedures. Thedesign of accounting systems for both the construction and operational phasesof NTPC's activities has been completed. Implementation of systems for theconstruction phase has been completed both at the corporate center atheadquarters, and also at the sites, while systems for the operational phasehave been designed and are being implemented at Singrauli. Consultants arebeing utilized for the on-going implementation of systems. To familiarizestaff with the systems and procedures, training courses are being conductedby the consultants in conjuction with staff members from NTPC's CorporateCenter.

Audit

2.18 The audit of NTPC's accounts and records is undertaken by aprofessional auditor appointed by the Company Law Audit Board, on therecommendation of the Comptroller and Auditor General of India. The auditoris normally a member of the Indian Institute of Chartered Accountants, andhis audit report on NTPC's financial statements is subject to comment by theAuditor General. For the audit of the accounts for FYs 1980, 1981 and 1982two auditors were appointed, Messrs.Raghu Nath Rai and Company and Messrs.Prasad Azad and Company, both firms of Indian Chartered Accountants. Therewere no adverse comments from the auditors on the accounts of each respectiveyear and the audits were satisfactory to the Bank. It should be borne inmind that NTPC's activities covered only project construction until FY 1982when power was sold for the first time. NTPC has already undertaken inconnection with previous credits and loans to furnish to the Bank Groupaudited financial statements within seven months of the end of the fiscal

Page 19: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-13-

year to which they relate, together with a certified report by the auditors,and a review of the accounts by the Director of Commercial Audits. Thisundertaking has been reconfirmed during negotiations for the proposed Loan.

Page 20: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-14-

III. THE PROGRAM AND THE PROJECT

The Program

3.01 NTPC's development program, previously consisting of four centralpower stations with associated 400 kV transmission (Singrauli, Korba,Ramagundam and Farakka), has recently been expanded to include two additionalpower stations, Vindhyachal and Rihand, as well as the proposed Fifth PowerTransmission Project. All power plants are situated at coal fields as theresulting reduced coal transport costs far outweigh the increased costs ofpower transmission. The Vindhyachal Project will be located near Waidhan inMadhya Pradesh with an initial capacity of 1,260 MW and ultimate envisagedcapacity of 2,260 MW, while the Rihand Project will be located near Bijpurin Uttar Pradesh with an initial capacity of 1,000 MW and an ultimatecapacity of 3,000 MW. With the addition of these two new projects NTPC'sapproved current development program, which is compatible with the India LongTerm Power Plan, will provide a total capacity of 9,060 MW.

The Project

3.02 The Project would provide for:

(i) an increased capacity of power transmission from the Ramagundamthermal power plant (2,100 MW final capacity) to the southern partof the country;

(ii) a strong power transmission tie between the predominantlyhydro-based Southern Regional grid and the predominantlythermal-based Western Regional grid; and

(iii) an asychronous inter-tie between the Northern and the WesternRegional grids which would permit larger power transfers to meetthe growing system needs in the context of the present stage ofsystem operation, control and communication facilities while alsoensuring the stability of the systems. K

3.03 The Project would include: about 550 km of 400 kV double-circuitlines, and 560 km of 400 kV single-circuit lines; the construction orextension of a number of related 400/220 kV substations; a back-to-back highvoltage direct current (HVDC) substation at the future Vindhyachal thermalpower plant as part of the 400 kV asynchronous link between the Singrauli andKorba thermal power stations; technical services for the carrying out ofdetailed equipment and system engineering and supervision duringconstruction, for the HVDC back-to-back line at Vindhyachal; and, metering,instrumentation and communication facilities. The proposed project alsoprovides power line carrier communication (PLCC) equipment for speechtransmission, line protection and data transmission on each 400 kV line.

3.04 The Central Power Transmission Project, which is described in detailin Annex 13, provides for the construction of the following 400 kV lines and400/220 kV substations (see attached map):

Page 21: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-15-

(a) Lines Approximate length

Ramagundam - Mangur, double circuit line 230 kmMangur - Vijayawada, double circuit line 160 kmVijayawada - Nellore, single circuit line 305 kmNellore - Red Hills, single circuit line 245 kmSingrauli - Vindhyachal, single circuit line 14 kmRamagundam - Chandrapur, double circuit line 158 km

(b) Substations

Ramagundam - extension for the 400 kV Ramagundam -Chandrapur line and for the second 400 kV

Ramagundam - Mangur circuit (the equipmentfor the first circuit is provided under theSecond Ramagundam Thermal Power Project)

Mangur - new (Ix315 MVA)Vijayawada - new (1x315 MVA)Nellore - new (lx315 MVA)

Red Hills - extension for the 400 kV Nellore - Red Hills lineChandrapur - extension for the 400 kV Ramagundam - Chandrapur

lineSingrauli - extension for the 400 kV Singrauli - Vindhyachal

lineVindhyachal- extension for the 400 kV Singrauli - Vindhyachal

line and a 500 MW twin modula (two 250 MW) HVDCback-to-back inter-tie linking the Singrauli andKorba thermal power plants.

Estimated Cost

3.05 The estimated cost of the Project, excluding interest duringconstruction, duties and taxes, and front-end fee is Rs 4,750 million US$500million) Based on the experience with similar projects in India, the directand indirect foreign currency costs are estimated at about Rs 1,864 million(US$193 million) and the local currency cost at Rs 2,916 million (US$307million). The estimated costs of the Project are set out in Annex 14 andsummarized in Table 3.1 below:

Page 22: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-16-

Table 3.1: ESTIMATED COST

Local Foreign Total Local Foreign Total------- Rs Million ------- US$ Million ----

400 kV lines 1,013.33 421.77 1,435.10 106.64 44.40 151.04400 kV substations 805.52 46.38 851.90 84.79 4.87 89.66Back-to-back HVDC

substation 79.53 733.92 813.45 8.37 77.25 85.62Metering and

Instrumentation 88.55 113.05 201.60 9.32 11.90 21.22PLCC Communications - 39.47 39.47 - 4.15 4.15

Sub-total 1,986.93 1,354.59 3,341.52 209.12 142.57 351.69

PhysicalContingencies 101.37 69.80 171.17 10.68 7.35 18.03

Price Contingencies 530.44 385.52 915.96 55.89 40.58 96.47Total 2,618.74 1,809.91 4,428.65 275.69 190.50 466.19

Consultancy - 23.75 23.75 - 2.50 2.50Engineering andAdministration 297.45 - 297.45 31.31 - 31.31

Total Project Cost 2,916.19 1,833.66 4,749.85 307.00 193.00 500.00(before duties andtaxes)

Duties and Taxes 617.50 - 617.50 65.00 - 65.00

Total Project Cost 3,533.69 1,833.66 5,367.35 372.00 193.00 565.00

Interest duringConstruction 490.31 - 490.31 51.58 - 51.58

Front-End Fee - 6.65 6.65 - 0.70 0.70

Total FinancingRequired 4,024.00 1,840.31 5,864.31 423.58 193.70 617.28

3.06 The estimates for the main items of equipment and materials are basedon the quotations received since 1980 for similar projects, such as the 400kV links and substations associated with the Singrauli, Korba, Ramagundam andFarakka power plants, with prices updated to mid-1982 levels. It has beenassumed that the foreign cost would represent the following percentages of

Page 23: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-17-

the total cost: 100% of the cost of equipment for the HIIVDC substation, themetering and instrumentation and the communication equipment; 80% of the costof steel in the towers for 400 kV lines; 50% of the cost of insulators andhardware; 36% of the cost of conductors and 20% of the cost of 400/220 kVtransformers. The rest of the substation equipment is assumed to contain nosignificant foreign components with the exception of the 50 MVar shuntreactors for which the estimated cif price has been considered as foreigncost. Inland freight and insurance is calculated at 4% of ex-works priceplus excise duty (8% of ex-factory component) for local supply, and 4% of cifcost plus custom duty plus landing charges on imported equipment. Customsduties and landing charges for imported equipment have been assumed as 50%and 2% of the cif cost. Excise and sales tax is charged at 4% each on theex-works cost. Erection is estimated at 8% of the electrical equipment cost.

3.07 Physical contingencies of 10% on construction costs and 5% on theequipment costs have been allowed to provide for unforseen factors. Inassessing price contingencies, it has been assumed that contracts will eitherbe on a fixed price basis or with ceiling on price inflation as was the casein the past with some of NTPC's contracts. Costs for equipment and erectionhave been escalated at 8.5% for FY1983, 8% for FY1984, 7.5% for FY1985, 7%for FY1986 and 6% yearly after FY1986 to allow for estimated price increases.

Project Financing

3.08 The proposed loan of US$250.7 million, representing about 50% of theproject cost (excluding duties and taxes and interest during construction andincluding the capitalized front-end fee), would be applied to the cif and/orex-factory prices of equipment and materials, and to the cost of consultants'services. The credit would cover all the foreign exchange costs and about18% of the local costs. GOI would provide the balance of the funds requiredin the form of loan and equity share capital.

Engineering

3.09 The 400 kV transmission system, being implemented by NTPC under theirthermal power projects and by the SEBs under the power transmission projects,has been based on the recommendation of CEA, and has been included in theLong Term Power Plan as part of the least-cost transmission component of thatplan. CEA had employed under the Fourth Power Transmission Project (Credit604-IN) consultants (Teshmont of Canada) for system planning. Theirrecommendations in 1977 have been continuously updated by CEA based onin-house studies to reflect changing system conditions. The major elementsof the 400 kV transmission design and construction have been standardized forall India and form the basis for detailed design of the lines.

3.10 NTPC has also carried out comprehensive engineering studies onover-voltage and stability problems to establish equipment parameters for thesystems implemented by them. As the digital model used in the studies is

Page 24: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-18-

limited in the representation of various non-linearities, over-voltagestudies are being taken up through the transient network analyzer techniquealso. These studies are being financed under the Second Korba Thermal PowerProject (Credit 1172-IN).

3.11 The proposed project consists of inter-regional links using both HVDCand 400 kV AC, as well as 400 kV AC intra-regional links. These have beenestablished by CEA on the basis of system studies aiming at evolving a powertransmission system based on requirements to the end of the decade. CEA,with the assistance of consultants, is extending these studies to 1995. Thebroad scope of these studies (not part of the project) includes:

- expansion of the 400 kV system with an overlay of higher ACvoltage (e.g. 765 kV);

- introduction of HVDC transmission of suitable voltage;

- staging of system development for the intermediate period; and

- economic evaluation and optimization of various alternatives.

3.12 As part of the proposed project, NITPC will undertake, with theassistance of consultants, detailed equipment and system engineering andsupervision during construction for the back-to-back HVDC link atVindhyachal. These technical services would require an input of about 190man-months of consultancy at an average rate of about US$13,000 per man-monthincluding salary, fees, international travel and subsistence.

Construction and Procurement

3.13 The Project involves construction of 400 kV transmission lines anderection of substations and high voltage D.C. terminal equipment for theback-to-back link. NTPC has been constructing through contractors 400 kVlines and substations effectively over the last few years under each of itsthermal power projects financed by the Bank Group. The same arrangement forconstruction of the lines and substations is proposed to be followed for thisproject too. W4hile NTPC would procure through international competitivebidding the conductors, line material such as insulators and hardware and theelectrical equipment including metering and instrumentation, for a totalamount of about US$145 million, separate contracts for supply and erectionof towers, stringing of conductors, design of structures, civil works andcommissioning of lines and substations, totalling about US$140 million, wouldbe entrusted to contractors based on local competitive bidding. The highvoltage DC back-to-back link, estimated at about US$118.5 million is atechnology being introduced for the first time in the Indian power sector andtherefore, the contract for the supply of equipment, would include adequateprovision for supervision of erection and commissioning. The engineeringof the link would be handled by competent consultants (see para. 3.12).

Page 25: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-19-

3.14 The project construction implementation schedule is shown in Annex15. Project completion is expected by March 1988.

3.15 Procurement of equipment and materials in an amount of about US$240million to be financed from the proposed credit would be on the basis ofinternational competitive bidding in accordance with the Association'sguidelines. Documents for individual contracts above US$2,500,000 equivalentwould be subject to prior review by the Association. Bidding documents forsuch equipment, and tender analyses and recommendations for award ofcontracts, would be prepared by NTPC, where necessary with the assistance ofits consultants, and approved by the Bank Group. The contracts could includecivil works in certain cases where these cannot be disassociated from theequipment contract, as for instance, the substation structure. Localmanufacturers would be expected to bid for almost all categories of equipmentand materials. A domestic preference of 15% or the import duty, whichever isless, would be applied in bid comparison for equipment and materialcontracts. To prevent administrative procurement delays, in cases where thelowest evaluated bidder is a foreign manufacturer, GOI agreed duringnegotiations to promptly grant import permission for such items.

Disbursement

3.16 Disbursements from the proposed credit would be made against 100%of the cost of consultants retained for the equipment and system engineeringand supervision during construction for the HVDC back-to-back substation atVindhyachal (para. 3.12) and against the cost of equipment and materials tobe financed from the proposed credit, on the following basis:

(a) 100% of the ex-factory cost of equipment and materials procuredin India subject to international competitive bidding; and

(b) 100% of the foreign cost of equipment and materials procuredabroad.

Estimated disbursements as provided in Annex 16, have been determined by NTPdand relate to the project implementation schedule (Annex 15). Although theperiod of disbursements (5-1/2 years) corresponds to that of the Bankdisbursements profile, the proportionate disbursements by semester differsomewhat to reflect NTPC's experience in implementation of transmissioncomponents of other projects for which their disbursement estimates haveproven reasonably accurate.

Ecology

3.17 No ecological problems are expected. Conductor sizes and spacingwill be designed to keep energy losses and radio interference withinacceptable limits. Since one 400 kV circuit is equivalent to approximately

Page 26: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-20-

three and a half 220 kV circuits, the amount of right of way is greatlyreduced and the appearance improved. The substations will be provided with afire fighting system which will conform to fire insurance regulations ofIndia and will be equipped with both AC and Diesel-driven pumps. Anautomatic heat-actuated emulsifying system is proposed for transformers.

Project Risks

3.18 The principal risk is the possibility of slippage which could giverise to delayed commissioning of the power transmission facilities. Suchpossible slippage would normally have no negative impact on the continuity ofelectricity supply, but would result in delay of the economic benefits ofsystem interconnection. To ensure effective coordination of the differentactivities during project implementation, NTPC will use PERT charts, whichnot only schedule the various physical activities but also indicate thephasing and quantum of inputs such as financial resources, manpower ofdifferent types, scarce materials, etc. In view of NTPC's previousexperience with transmission construction, it is expected that the risk ofslippage will be kept to a minimum through careful coordination andsupervision during construction, careful attention when placing contracts,and to the capability of manufacturers to meet the delivery schedule.

3.19 Other risk areas are in engineering design, equipment quality andcost overruns. These risks have been carefully assessed and the followingsafeguards taken:

(a) NTPC will be assisted by consultants in those areas where it hasnot sufficient experience, which should minimize problems dueto error at the engineering and design stages; and

(b) project costs are based on similar works currently in progressin India; provision has been made for cost escalation and thereshould be little risk of any substantial cost overrun.

3.20 There is also risk of damage due to fire, explosion, etc, which iscovered by insurance provided by the respective contractors during theconstruction stage and by GOI through its self-insurance policy aftercommissioning.

Page 27: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-21-

IV, FINANCIAL ANALYSIS

A . NATIONAUL THEWMAL POWER CORPORATIGN LIMITED (NTPC)

Investment Program

4.01 NTPC is currently in the seventh year of an investment program whichoriginally provided for the constrtuction of four large thermal power stationswith an aggregSate capacity of 7,300 P. together with about 6,000 circuitkilometers of associated 400 kV transmission lines, estimated to cost aboutRs 4l1,i00 million (US84,767 million), However, because of rescheduling andexpansio;,i of the construction program, the investment program has beensubjeet ro conitinuous review over the past six years, with appropriaterevisions being made during appraisal of the previous projects. Revisionswere made during appraisal of the proposed project to reflect (i) increase inthe expected base costs of equipment; (ii) increase in price contingencyfactors attributable to higher projected inflation rates; (iii) reschedulingof generating plant commissioning dates; (iv) provision for projects not yetidentified (3,000 MW), extending the investment program from FY1991 toFY1996; and (v) inclusion of the proposed project.

4.02 NTPC's currently revised investment program is set out in Annexes 18and 19 and indicates capital expenditure of Rs 159,162 million (US$16,754aill-on) over the twenty-year period FY 1977 to FY 1996, reflecting anincrease of 138% (Rs 92,295 million, US$9,715 million) over the investmentprogram as previous"ly revised during the Second Ramagundam appraisal (FY 1977to FY 1991). The increase in generating capacity and transmission facilitiesaccounts for about Rs 79,500 million (US$8,370 million) or 86% of the costincrease. The remaining 14% of the increase in the investment program is dueto increased costs for station and transmission facilities at Singrauli,Korba, Ramagundam and Farakka (Annex 19), largely attributable to (a) priceescalation resulting from slippage in commissioning of power units, (b)revision of construction and main plant equipment base costs to 1982 prices,(c) increase in foreign costs in terms of local currency resulting fromchanges in the exchange rate applied, and (d) increase in price contingenciesresulting from application of revised inflation factors. Financialstatements showing both past performance and future forecasts of NTPC'sconsolidated operations are provided in Annexes 21 through 23. Assumptionsupon which the forecasts are based are provided in Annex 24.

Future Earnings

4.03 NTPC commenced commercial operations in February 1982 when its first200 MW generating unit at Singrauli was commissioned. The growth of powergeneration and unit sales resulting from plant commissioning (Annex 17), andthe subsequent stabilization of generation, for the ensuing thirteen- yearperiod to FY 1995, is set forth in Annex 20. NTPC's projected earnings arebased on the assumption that NTPC will supply bulk power at 400 kV to StateElectricity Boards at regional tariff levels sufficient to enable it to earn

Page 28: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-22-

a 9.5% return on the historic value 1/ of average net fixed assets inoperation from FY199l when NTPC's sales volume is estimated to reach about83% of the maximum output of the four power projects Singrauli, Korba,Ramagundam and Farakka. Between FYs1984 and FY1990 NTPC should achieve aminimum rate of return of 8%. This return is heavily influenced by the pointin time within any given year of commissioning of assets and the assumptionof stabilization periods of generation plant. Consequently, duringFY1984-1990 the revenues, investment costs and operating expenditures shouldbe adjusted to reflect the hypothetical situation of fully operative andstabilized generation plant (for detailed explanation see Annex 21). Duringnegotiations an assurance was obtained that NTPC will achieve in FY17917,andmaintain thereafter, a rate of return of not less than 9.5% on the netaverage fixed assets in operation. Between FYs1984 and 1990 a minimum rateof return of 8% per year will be achieved using the adjusted assets,operating expenditures and revenues as explained above.

NTPC Consolidated Operations

4.04 The Income Statement set out in Annex 21 shows the projectedconsolidated operating results of NTPC from FY1983 through FY1995. Theforecast earnings performance of NTPC is satisfactory. On the basis of theprojections the average bulk supply price in FY1991 will be 43.9 paise(USc4.6) per kWh which represents an increase of 12.1 paise over the 31.8paise per kWh projected during the Second Ramagundam appraisal. The increaseof 12.1 paise is comprised of:

(a) Base fuel costs 2.8 paise per kWh

(b) Operations and Maintenance costs 1.1 paise per kWh

(c) Depreciation 2.0 paise per kWh

(d) Return at 9.5% on average netfixed assets in operation 6.2 paise per kWh

Total 12.1 paise per kWh

- of which 1.6 paise per kWh is attributable to the proposedtransmission project which is not directly revenue producing.

1/ Fixed assets are recorded at historical cost as the Government does notpermit NTPC to revalue to current price levels.

Page 29: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-23-

For the years FY1983 to FY1991 regional bulk supply tariffs have beenprojected to progressively increase from 32.2 paise per kWh in FY1983 to the43.9 paise per kWh (excluding fuel surcharge) required to achieve thecovenanted rate of return of 9.5% in FY 1991 (para. 4.03).

4.05 NTPC will become profitable in FY1983 and, as a consequence of therapid commissioning of plant from FY 1984, earnings will rise rapidlythereafter. The rate of return will continue to increase to 12.3% in FY1994when all generating units in each of the stations will be operating at fullcapacity.

NTPC Regional Operations

4.06 Regional income statements for the Northern, Western, Southern andEastern Regions set out in Annexes 25 to 28 showing the projected operatingresults for each region from FY1983-FY1995 are satisfactory. All fourRegions are projected to achieve a 9.5% rate of return in FY1991, thequalifying year (para. 4.03) for NTPC consolidated operations. Minor lossesoccur in FYs1984, 1985 and 1989 for the Southern Region, and in FYs1985 and1986 for the Eastern Region, which are acceptable at that stage in NTPC'sdevelopment program. Power sales from the generating stations in each regionwill be priced at a uniform regional bulk supply tariff (para. 4.17).Operating costs of the transmission facilities provided by the proposedproject will be recovered through the regional tariffs.

Taxation

4.07 NTPC is liable for income tax under the Income Tax Acts. However,because of the large capital expenditure program between FY 1979 and FY 1995,an income tax liability will not arise in the foreseeable future.Accordingly, a tax equalization reserve is not necessary.

Internal Cash Generation FY 1977 - FY 1995

4.08 A Statement of Sources and Applications of Funds covering NTPC's K

current investment program is provided in Annex 22. Internally generatedfunds are expected to contribute 12% to NTPC's investment program betweenFY1983 and FY1992 (Table 4.1), the year in which the last of the Bank Groupfinanced power units (Farakka) will be commissioned. Internal cashgeneration rises rapidly from FY1989 and is projected to provide 100% of theinvestment funds required by the investment program from FY 1993 to FY 1995(Rs 11,924 million, US$1,255 million). This latter three year period of theinvestment program covers only the provision for projects not yet identifiedas all defined and approved projects are projected as completed by FY 1992.Dividends on equity share capital are not included in the forecasts on theassumption that surplus funds would be applied to the expansion of NTPC'sactivities beyond its current investment program. From the Eirst year of

Page 30: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-24-

operations onward, debt service coverage is satisfactory at 1.3 times andabove.

NTPC's Financing Plan FY 1983 - FY 1992.

4.09 The financing plan for the ten year period FY1983-92 is set out in

Table 4.1 and is satisfactory. The investment cost of the proposed projectrepresents about 4% of the construction expenditures in the financing plan.

4.10 In addition to the proposed project and a provision for projects notyet identified, two new projects (Rihand and Vindhyachal) have been added tothe investment program and financing plan since approval of the SecondRamagundam project. The Rihand project (2 units of 500 MW) is beingimplemented by a consortium of British companies led by Northern EngineeringIndustries Limited and is being financed by the U.K. Government. The loanof p344 million bears interest of 7.75% per annum with principal repayable insemi-annual installments over ten years, excluding a five-year grace period.Equipment and materials, supplied by the U.S.S.R., for the Vindhyachalproject (six units of 210 MW and associated transmission facilities) arebeing financed by a credit of about U.S.S.R. roubles 317 million from theU.S.S.R. Government. The credit bears interest at 2-1/2% per annum withprincipal repayable in equal annual installments within a period of 17 yearsand with the first installment being payable in the third year after thefirst drawing from the credit. Interest and principal payments will be madein Indian currency.

4.11 Bank financing of the proposed project, US$250.7 million, togetherwith Bank Group financing of NTPC's investment program to date, in totalUS$2,101 million, represents about 17% of the total investment involved(excluding the provision for projects not yet identified).

Page 31: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-25-

Table 4.1 NTPC's FINANCING PLAN FY 1983-FY 1992

US$ Million

Rs Million Equivalent %

Source of Funds.

Internal Cash Generation 57,511 6,053 42

Less: Debt Service (37,533) (3,951) (28)Working Capital Increase (2,950) (310) 2)

Contribution to Investment 17,028 1,792 12

Capital Raised

GOI Equity Capital 56,145 5,910 41GOI Loans 1/ 63,933 6,730 47

Total Sources 137,106 14,432 100

Requirements:

Construction Program(including interest duringconstruction) 137,106 14,432 100

Onlending Agreement

4.12 The Bank Loan for the proposed project will be onlent to NTPC by GOIin accordance with an acceptable onlending agreement as a condition ofeffectiveness of the Credit. As in previous lending operations, the terms ofthe onlending agreement would provide for maturity in 20 years, including agrace period of 5 years, and repayment of principal in equal semi-annualinstallments, with interest payable on outstanding balances at not less than12% per annum, except as the Bank may otherwise agree. The rate of interestat which GOI currently lends to industrial and commercial undertakings in thepower sector is 12.5% per annum and reflects an increase from the rate of11.75% in effect at the time of the Second Ramagundam appraisal. The foreignexchange risk would be borne by the Government. An, assurance was obtainedduring negotiations that GOI will ensure prompt availability to NTPC of

1/ Includes onlending of IDA Credits/IBRD loans and KfW, OPEC, U.K. andU.S.S.R. loans.

Page 32: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-26-

sufficient funds to complete the project, including any additional fundswhich might be required due to cost overruns or other unforeseeable factors.

Future Finances

4.13 Actual and forecast balance sheets, at March 31 annually from FY1977through FY1995, are set out in Annex 23 and reflect a satisfactory financialposition for each of these years. The balance sheets reflect the phasedconstruction program, the commencement of commercial operations in FY1983,and the financing of NTPC's capital requirements by GOI through a combinationof long-term borrowing and equity capital, in a ratio which would normallynot exceed 1:1. Initially the equity portion of financing would be releasedby GOI followed by loan capital. Table 4.2 summarizes NTPC's financialposition at three significant points in its development.

(a) at March 31, 1983 - end of the year in which NTPC will becomerevenue earning;

(b) at March 31, 1989 - end of the year following the year inwhich the proposed project is completed; and

(c) at March 31, 1994 - end of the first year in which all ofgenerating units of the approved projects in the investmentprogram are operating at full capacity.

4.14 These forecasts indicate that by March 31, 1983, when NTPC becomesrevenue earning, total capitalization will be Rs 17,005 million (US$1,790million), divided between GOI loans (including the onlending of Bank Groupfinance) and equity capital in a ratio of 30/70. Six years later (March 31,1989), after the proposed project is completed, total capitalization willhave risen to Rs 113,973 million (US$11,997 million) reflecting a debt/equityratio of 48/52. No external debt or equity financing is forecast afterFY1992 for the current investment program and this, combined with asignificant increase in internal cash generation, will reduce the debt/equityratio to 33/67 by March 31, 1994.

Page 33: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-27-

Table 4.2: FINANCIAL POSITION OF NTPC.

At March 31 FY 1983 FY 1989 FY 1994(Rs Millions)

Fixed Assets at Cost 6,313 90,090 137,248Less: Depreciation 58 5,210 21,604Net Fixed Assets in Service 6,255 84,880 115,644Work-in-Progress 11,075 27,612 19,208Total Net Fixed Assets 17,330 112,492 134,852Short Term Deposits - - 3,864Working Capital (325) 1,481 2,635Total Net Assets 17,005 113,973 141,351

Financed by:Equity Capital 11,775 53,681 63,995Retained Earnings 45 5,119 31,176Total Equity 11,820 58,800 95,171

Long-Term Debt (including IDACredits/IBRD Loans) 5,185 55,173 46,180

Total Capitalization 17,005 113,973 141,351

Debt/Eqdity Ratio 30/70 48/52 33/67

Borrowing Powers

4.15 The Companies Act 1956 (Section 293.1d) limits borrowing by NTPC toan amount equal to the aggregate of the paid up share capital and "freereserves (i.e. those which are not set apart for specific purposes), exceptwith the consent of the Corporation in general meeting. During negotiations,an assurance was obtained that NTPC will inform the Bank Group beforehand ofany proposal to alter or modify existing limitations on the borrowing powersof its Board of Directors.

Commercial Arrangements for Sale of NTPC Energy

4.16 Under previous credits and loans GOI and NTPC agreed to prepare bulksupply contracts for the sale of energy to the SEBs on terms and conditionssatisfactory to the Bank Group. They also agreed to forward a final draft ofthe contracts for the Singrauli, Korba, Ramagundam and Farakka power stationssix months prior to the first sale of energy from each respective powerstation. Preliminary draft contracts have been provided to the Bank Groupfor Singrauli and Korba which in principle are acceptable,however finaldrafts for Singrauli and Korba which were due by August 1981 and July 1982respectively have not yet been provided. The reason for this delay is thatNTPC has not yet been able to reach agreement on the financial terms of salewith the relevant SEBs. In the interim NTPC has been selling power from theSingrauli station at the inter-State rate of 35 paise per kWh with agreement

Page 34: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-28-

that such sales would be retroactively adjusted to the bulk sale contractprice when final agreement has been reached. Consequently GOI and NTPC agreedduring negotiations that bulk supply contracts for the sale of electricityfrom the Singrauli and Korba power plants must be finalized and signed by allconcerned parties as a condition of effectiveness for the proposed project.It was clarified during negotiations that inter-regional sales of power wouldbe priced at the tariff rate of the receiving Region for committed powerallocation. WThere sales are in excess of the committed power allocation,the tariff rate of the generating Region would apply.

4.17 NTPC bulk supply contracts will establish regional tariffs which willbe applied to power sales in each respective region. Operating costsapplicable to the transmission facilities of-the proposed project areabsorbed by the relevant regional NTPC organizations. Recovery of suchcosts, therefore, is reflected in the projected regional tariffs as aseparate component of these tariffs. The regional income statements set outin Annexes 25 to 28 show the projected regional tariffs, in current rupees,from FY1983 to FY1995. The regional tariffs projected for FY1991, thequalifying year for NTPC to achieve the 9.5% rate of return, are as follows:

Paise/kWh(as of FY1991)

Northern Region - Singrauli )- Rihand ) 38.3

Western Region - Korba )- Vindhyachal ) 43.4

Southern Region - Ramagundam 53.1

Eastern Region - Farakka 46.0

NTPC Consolidated Average Tariff 43.9

Variations in the above tariffs reflect regional differences in capitalinvestment, coal costs, investment timing and level of energy generation inFY1991.

B. _NDHRA PRADESH STATE ELECTRICITY BOARD (APSEB)

4.18 APSEB will be the major beneficiary of the proposed project as thesubstations and 400 kV transmission lines at Ramagundam, Vijayawada andNellore will be located in the State of Andhra Pradesh. Consequently asignificant proportion of the power carried by these facilities will beconsumed in this State.

4.19 APSEB uses full commercial accounting for project and operationalactivities. Although internal reporting conforms to the commercial basis,

Page 35: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-29-

the annual audited statements of account do not as they are published inaccordance with the present requirements of the Electricity (Supply) Act1948. Amendments to the Act, anticipated to be incorporated in early 1983,will permit the presentation of audited accounts on a commercial basis.

Investment Program

4.20 The investment program for the seven year period FY1983 to FY1989envisages capital expenditure of Rs 21,433 million (US$2,256) and willprovide additional installed capacity of 1,760 MW (1,340 MW hydro and 420 MWthermal) or 81% over the present level. Power generation is projected toincrease by 7,554 GWh (90%) by FY1989 due to the added capacity and higherefficiency of new plant.

Future Earnings

4.21 The Income Statement set out in Annex 29 shows the actual andprojected operating results from FY1980 through FY1989, adjusted forinflation. The forecast earnings performance of APSEB is satisfactory,reflecting a rate of return ranging between 9.5% and 12.3% between FY1983 andFY1989. No State Government subsidies, covering rural electrificationlosses, are projected for this period as APSEB will be able to achieve asatisfactory cash generation without such State subsidization. The averageAPSEB tariff is projected to increase from 42.4 paise per kWh in FY1982 to55.5 paise per kWh in FY1989.

Internal Cash Generation

4.22 A statement of internal cash generation is provided in Annex 30showing actual and forecast cash generation for the period FY1980 throughFY1989. Net cash generation, as a percentage of three-year average ofcapital expenditure, ranges between 30.8% and 45.4% for the forecast periodFY1983 through FY1989 thus satisfying the covenant established under theThird Rural Electrification Project which requires a minimum 20% contributionto investment.

Page 36: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-30-

V. JUSTIFICATION AND ECONOMIC ANALYSIS

General

5.01 The proposed project, consisting of (i) a 400 kV network expansionwithin the Southern Region, (ii) a 400 kV transmission line linking theSouthern and Western Regions, and (iii) an HVDC back-to-back link betweenNTPC stations in the Northern and Western Regions, is justified as part ofthe least-cost transmission component of the recently completed long-termgeneration capacity expansion plan for the Indian power sector. It providesneeded additional transmission within the Southern Region, and establishesthe initial high-voltage inter-Regional links that will be the first steptowards an integration of the national grid.

Method of Analysis

5.02 In September 1982, CEA completed a 15-year least-cost generationexpansion plan, which is reviewed in Annex 5. Having determined the optimumplant program for the forecast demand in each Region, the plan develops anoptimum transmission grid configuration for that Region. This two-stepapproach is reasonable in India where selection of plant sites (hydro,pithead coal-fired) is fairly limited, and network costs do not influence theoptimal plant mix. This intra-Regional optimization results in a 400 kV gridconfiguration which encompasses, inter alia, the lines proposed under theproject. As the intra-Regional lines are justified by 1995 as part of theleast-cost program, the analysis centers on the rate of return of the

transmission lines, and the appropriateness of the timing of the investment.This is done by comparing the costs of the transmission facilities with thecost incurred in case of an outage.

5.03 The two inter-Regional transmission links are examined in comparisonto the investment that would be necessary to provide peaking capacity ineither Region in the absence of the project. The method compares the presentvalues of the transmission links and those of expansions of thermal capacityby amounts equivalent to the capacity made available by inter-Regionaltransmission. In addition, energy cost savings arising from transfers ofenergy between Regions with different generating costs are identified.

5.04 All costs are expressed in CIF (border price) terms or theirequivalents. For local cost components, a standard conversion factor of 0.8is used. Unskilled labor is valued at 75% of its market wage.

Intra-Regional Lines

5.05 The transmission options related to the least-cost generationexpansion plan are outlined for the year 1995 in Annex 32. In the long run,the transmission grid development in the Southern Region is straightforward,as capacity expansion takes place relatively more in the North, whereas loadgrowth is higher in the South.

Page 37: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-31-

5.06 The load flow studies performed by the CEA examine various conditionsfor the year 1989, the anticipated year of completion:

- maximum load, maximum thermal despatch- maximum load, maximum hydro dispatch- maximum load, normal dispatch, etc.

The variation in hydropower affects mostly the 220 kV network, and increasesonly marginally the North to South power flow on the 400 kV network. By farthe most constraining condition consists in sending out the maximum outputfrom the Ramagundam thermal plant operating as base load. In this condition,the proposed network would withstand single outages on the inland lines notcovered by the project, but this would be no longer true when one of thefollowing project components is delayed:

Section Shortage (MW)

(a) Ramagundam-Mangur 100 to 400(b) Mangur-Vijayawada 100 to 400(c) Vijayawada-Nellore 50 to 200(d) Nellore-Redhills 0 to 150

5.07 The shortages are in round figures; they vary according to which oneof the seven inland lines is tripped along the alternative route fromRamagundam to Redhills. They disappear during the wet quarter when the 500MW units are maintained and also another quarter on sections (c) and (d) when200 MW units are maintained. They are reduced by 20% at all times due toforced outages. The distribution of avoided shortages over the year is takenas follows:

Section 6 Months 3 Months 3 Months

(a) 80 to 320 MW 0 to 160 0(b) 80 to 320 MW 0 to 160 0(c) 40 to 160 MW 0 0(d) 0 to 120 MW 0 0

5.08 Assuming a 5% outage rate for each of the seven inland lines, theprobability of having an outage is 35%, i.e. 4.5 weeks per quarter. Furtherassuming a 90% availability for line sections (c) and (d), and 97.5%availability for sections (a) and (b), the total shortages avoided in 1989amount to 208 GWh on all four sections.

5.09 The cost of outages avoided as proxy for benefits is estimated as theeconomic costs incurred by consumers by the use of alternative energy duringperiods of power cuts. For the major consumer categories, this amounts tothe following values:

Page 38: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-32-

Regionalshare of total

Consumer category Value (Rs/kWh) consumption (%)

Industrial and similar 0.98 74

Agriculture 2.49 18Domestic/Commercial 3.33 18Weighted average 1.77 100

5.10 The economic internal rate of return of the intra-Regionaltransmission links is about 13% (Annex 33). The rate of return is notsignificantly sensitive to reasonable variations in costs and benefits. Theappropriateness of timing of the transmission links within the Region can begauged by comparing the annuitized cost of the links per kWh of outageavoided (about Rsl.10/kWh) with the estimated cost of outage in 1989 (Rs1.77/kWh). The differential indicates that the lines are justified in orbefore 1989.

Southern/Western Region Intertie

5.11 The AC link between the two Regions consists of a double circuit linebetween Ramagundam and Chandrapur. The 1,000 MW capacity of this linkresults, after netting out losses and taking into account availability, inabout 950 MW available capacity for the receiving Region. According to CEAcalculations, an increase of that magnitude in the peak demand would augmentthe Loss of Load Probability (LOLP) from the target of 1% to 1.8%, so thatthis support would be available at least 98.2% of the time. Netting out 2%of power losses, this link provides then a peaking capacity of 912 MW. Thiscapacity, in the absence of the link, would have to be provided by 2x5Q0 MWadditional capacity in the receiving Region. Under the circumstancesprevailing in India, this capacity would be coal-fired thermal.

5.12 The economic cost streams of the transmission link and thealternative solution of an increase in generating capacity are shown in Annex33. At any discount rate within a reasonable range, the transmission linksolution is the lower-cost option by a wide margin (Annex 34).

5.13 In addition to the justification as least-cost solution, theexistence of the transmission link will make possible energy transfers fromthe Western to the Southern Region during off-peak periods. The estimatedmarginal off-peak energy cost differentials in 1980 (in 1982 prices) areexpected to be about 3.7 paise/kWh during the wet (monsoon) quarter, andabout 6.7 paise/kWh during the dry season. Assuming an all-year weightedaverage differential of about 5 paise/kWh, a feasible transfer period ofabout 6,000 hours per year would result in an annual marginal energy costsaving of about Rs300/kW, or about Rs273 million per year for the available912 MW at the receiving end. By 1995, the wet season cost differential would

Page 39: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-33-

be negligible, but dry season transfers at a cost differential of about 2.8paise/kWh would still be feasible.

Northern/Western Region HVDC Intertie

5.14 This link consists of a 400 kV line between Vindhyachal and Korba,a new AC 400 kV substation and a HVDC back-to-back link at Vindhyachal, andan expansion of the AC 400 kV substation at Korba. After taking into accountavailability and losses, 466 MW of additional capacity could be madeavailable in the receiving Region. In the absence of the link, this would beprovided by a 500 MW thermal unit, most likely by expansion in one of thepithead coal-fired stations.

5.15 The economic cost streams of the DC link (including the full AC partof the link), and of the alternative solution of thermal capacity expansionare shown in Annex 35. At any discount rate within a reasonable range, theDC transmission link solution is the lowest-cost option by a ratio of almost2:1.

5.16 As in the case of the Southern/Western link, the interconnection willalso make off-peak energy transfers possible. In 1989 and the followingearly years, the flow would be from the Western to the Northern Regionbecause of off-peak marginal energy cost differentials of 6.5 paise/kWh (wet)and 3.2 paise/kWh (dry). In 1995, off-peak marginal energy costs during thedry period are approximately equal in both Regions, but wet season energywould flow from the North to the West because of a cost differential of about5.1/kWh resulting from accelerated hydro development in the North. Assumingagain initially 6,000 transfer hours per year, the annual marginal energycost saving would amount to about RslOO million, decreasing by 1995 to aboutRs7O million per year if only wet season transfers were made.

Tariffs and Cost of Supply

5.17 The main single beneficiary SEB under the project is the AndhraPradesh State Electricity Board. In recent years, average tariffs of APSEBhave been rising at a rate of about 11% per year to a FY82 level of 42.4paise/kWh (USc4.5), and industrial tariffs at a rate of about 20% p.a.Domestic and agricultural tariff development has been less encouraging asthese tariffs have actually decreased in real terms. Present tariffs aresummarized in Annex 36.

5.18 In 1975, the Bank, in collaboration with APSEB, prepared a marginalcost-based tariff study (Report No. 851-IN). Subsequently, several updatingexercises have been performed by the Bank as well as APSEB (Annex 37). Atpresent, APSEB staff is preparing a detailed recalculation of the 1975 study,which is expected to be completed early in 1983. In general, average tariffsin FY82 were slightly below or roughly equivalent to Average Incremental Cost

Page 40: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-34-

(AIC) estimatesl/ (40-50 paise/kWh), a situation which is unchanged fromearlier years. More detailed marginal cost estimates, however, yield asignificantly higher sales-weighted overall marginal cost (about 80 paise/kWhin FY82). This is due to the fact that APSEB's AIC is heavily influenced bya strong future emphasis on hydro development in the State, while, at themargin, non-APSEB thermal generation will have to satisfy demand.

5.19 Cross-subsidization among consumer categories in relation to themarginal cost structure continues to be evident. Industrial consumers paytariffs of about 50-55 paise/kWh, while their marginal cost is more likelyto be about 45 paise/kWh (at the same load factor). On the other hand,domestic consumers, whose marginal cost is about 130-150 paise/kWh, pay atariff of about 45-50 paise/kWh. Agricultural consumers enjoy an even largergap between cost of supply and tariff. This policy of cross-subsidization isAPSEB and Andhra Pradesh Government policy, and is unlikely to be abandonedin the near future for social and political reasons. However, APSEB has beenimproving its tariff structure in line with principles highlighted in the1975 Tariff Study, and plans to continue to do so. Improvements effected inrecent years include (i) the replacement of decreasing block tariffs in thedomestic category by an increasing system, (ii) the abolishing of thedomestic bulk supply category, (iii) the introduction of customer charges,(iv) the introduction of a two-part tariff for HT consumers, (v) theenforcement of a power factor penalty clause in industry, and (vi) theaddition of a fuel cost adjustment clause.

5.20 Further improvements to tariff structure and practice are necessary.The major changes would be:

(i) Power factor regulations need to be enforced in theagricultural sector, where 100,000 of 500,000 irrigationpumps do not have capacitors, but have not been obliged topay the power factor penalty.

(ii) The ratio between demand and energy charges for customers witha two-part tariff is severely distorted. Marginal capacitycost is much higher than the demand charge, while energycharges exceed marginal energy cost.

(iii) The fuel surcharge, while a welcome interim tool to reflectcost changes, may distort the above ratio even more in thelong run, if it is carried on and increased instead of absorbedinto the tariff at regular revisions. A check on its potentialmisuse as tariff adjustment substitute is called for.

1/ Depending on the valuation of large incremental purchases from outsidethe State during the later 1980's.

Page 41: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-35-

(iv) The first ("lifeline") consumption block for domestic consumersneeds to be reduced from the present 100 kWh/month to about25 kWh to justify the subsidized block for minimum needs. Atthe same time, the price per unit above this block should beincreased significantly.

(v) The heterogeneous group of non-domestic LT consumers (hotels,offices, shops, etc.) should be split to reflect consumptionpatterns, while the two LT industrial categories could becombined. The cottage industry category could usefully becombined with the domestic category.

(vi) Tariffs for irrigation consumers should rise in general after along period of stagnation. The ceiling on LT agriculturalconsumers' demand charge should be removed.

(vii) Street light tariffs for larger municipal corporations withability to pay should be raised to reflect cost.

(viii) Interstate exchange tariffs should be adjusted to reflectcost at the time of supply. APSEB is now discussing amarginal cost-based system with CEA and other SEBs.

5.21 The Chairman of APSEB reviewed the present status in regard to tariffrestructuring and gave assurance that the above points are being taken intoconsideration in the continuing process of the restructuring of APSEBtariffs.

Page 42: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-36-

VI. SUMMARY OF AGREEMENTS

Condition of Effectiveness

6.01 (a) GOI and NTPC should provide copies of bulk supply contractsfor the sale of electricity from the Singrauli and Korbapower plants, finalized and signed by all concerned parties(para. 4.16).

(b) The conclusion of a Subsidiary Loan Agreement between GOI andNTPC satisfactory to the Bank (para. 4.12).

Clarifications and Agreements Reached During Negotiations

6.02 During negotiations clarifications were obtained with regard totariff structure improvements to be implemented by APSEB (para. 5.21).

6.03 The following issues were raised with GOI and NTPC and satisfactoryagreements or assurances were obtained with regard to:

(a) audit (para. 2.18);

(b) import permission (para. 3.15);

(c) rate of return (para. 4.03);

(d) provision of the balance of capital to complete the project,including any additional funds which might be required to covercost overruns or other unforeseen factors (para. 4.12);

(e) borrowing (para. 4.15); and

(f) cost recovery and pricing of inter-regional sales of power(para. 4.16).

Recommendation

6.04 Subject to the foregoing the project forms a suitable basis for aBank Loan of US$250.7 million.

Page 43: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-37-ANNEX 1

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Power Sector Loans & Credit'

Project Loan No. Amount Remarks

US$m

Bokaro-Konar 23 18.5 CompleteDamodar 72 19.5 CompleteTata Andhra Valley 106 16.2 CompleteTata Trombay 164 9.8 CompleteThird DVC 203 25.0 CompleteKoyna 223 25.0 CompletePower Transmission 416 70.0 CompleteKothagudem II 417 14.0 CompleteTrombay III 1549 105.0Ramagundam 1648 50.0Farakka 1887 25.0Ramagundam II 2076 300.0Rural Electrification III 2165 304.5

982.5

Credit No.

Fourth DVC 19 18.5 CompleteKoyna II 24 17.5 CompleteKothagudem 37 20.0 CompleteBeas Equipment 89 23.0 CompletePower Transmission II 242 75.0 CompletePower Transmission III 377 85.0 CompleteRural Electrification 572 57.0 CompletePower Transmission IV 604 150.0Singrauli 685 150.0Korba 793 200.0Ramagundam 874 200.0Rural Electrification II 911 175.0Singrauli II 1027 300.0Farakka 1053 225.0Korba II 1172 400.0

2,096.0

Page 44: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-38-ANNEX 2Page 1 of 5 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Electricity (Supply) Act 1948

Proposed Amendments, October 1982

Existing Proposed

S.59 (Addition/deletion/Modification)

General principles for Board's Subsection (1) of Section 59 shall befinance - (1) The Board shall, substituted by the following:-after taking credit for anysubvention from the State "The Board shall, after taking creditGovernment under section 63, for any subvention from the Statecarry on its operations under Government under section 63, carrythis Act and adjust its tariffs on its operations under this Act andso as to ensure that the total adjust its tariffs so as to ensurerevenues in any year of Account that the total revenues in any yearshall, after meeting all of Account shall, after meeting allexpenses properly chargeable expenses properly chargeable toto revenues, including revenues, including operating,operating, maintenance and maintenance and management expenses,management expenses, taxes (if taxes (if any) on income and profits,any) on income and profits, depreciation and interest payable ondepreciation and interest all debentures, bonds and loans,payable on all debentures, leave such surplus which shall notbonds and loans, leave such be less than 3% of the net fixedsurplus, as the State Govern- assets employed by the Board or suchment may, from time to time, higher percentage of such assets asspecify. the State Government may, from time

to time, specify."(2) In specifying the surplusunder subsection (1), the StateGovernment shall have due regardto the availability of amountsaccrued by way of depreciationand the liability for loanamortization and leave:-

(a) a reasonable sum tocontribute towards thecost of capital works and

Page 45: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-39-ANNEX 2

Page 2 of 5

Existing Proposed

(b) where in respect of theBoard a notification hasbeen issued under sub-section (1) of section 12-A,a reasonable sum by way ofreturn on the capitalprovided by the StateGovernment under subsection (3)of that section and the amountof the loans (if any)converted by the StateGovernment into capital undersubsection (1) of Section 66-A.

S.67

Priority of liabilities of Board - Section 67 to be substituted by the(1) If in any year, the revenue following:-receipts are not adequate to enablecompliance with the requirements of "Priority of Liabilities of the BoardSection 59, the Board shall after - The Board shall distribute themeeting its operating, maintenance surplus of the revenues in any yearand management expenses after after meeting all the expensesprovision has been made for the referred to in subsection (1) ofpayment of taxes (if any) on income Section 59, to the extent suchand profits, distribute the revenue surplus is available and thereceipts, as far as they are avail- amounts accrued by way of depre-able, in the following order, namely:- ciation for the year, in the

following order, namely:-(i) payment of interest on loans

guaranteed under section 66; (i) repayment of principal of anyloan raised (including redemp-

(ii) repayment of principal of tion of debentures or bondsany loan raised (including issued) under section 65 whichredemption of debentures of becomes due for payment in thebonds issued) under section 65 year or which became due forwhich becomes due for payment payment in any previous yearin the year; and has remained unpaid;

(iii) payment of interest on loans (ii) repayment of principal of anyguaranteed under section 66; loan advanced to the Board by

the State Govt. under section 64(iv) payment of interest on sums which becomes due for payment

paid by the State Government in the year or which became duein pursuance of guarantees for payment in any previous yearunder Section 66; and has remained unpaid;

(v) payment of interest on loans and if any balance is left thereafter,advanced to the Board by the the same shall be utilized for otherState Government under section purposes specified in subsection (2)64 or deemed to be advanced of section 59 in such manner as theunder subsection (2) of Board may decide.section 60;

Page 46: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-40- ANNEX 2

Page 3 of 5

Existing Proposed

(vi) repayment of principal ofany loan guaranteed by theState Government undersection 66 which becomes duefor repayment in the year orwhich became due for paymentin any previous year and hasremained unpaid;

(vii) repayment of principal of anyloan advanced to the Boardunder section 64 whichbecomes due for payment in theyear or which became due forpayment in any previous yearand has remained unpaid:

and if any balance amount isleft thereafter, the sameshall be utilized for theother purposes specified-insection 59 in such manner asthe Board may decide.

(2) If for any reason beyond thecontrol of the Board, the revenuereceipts in any year are notadequate to meet its operating,maintenance and managementexpenses, taxes (if any) onincomes and profits and theliabilGities referred to inclauses (i) and (ii) of sub-section (1), the shortfall shall,with the previous sanction of theState Government, be paid out ofits capital receipts.

A new Section 67-A to be inserted asfollowing:-

"If for any reasons beyond the controlof the Board revenues in any year arenot adequate to meet all the expensesreferred to in subsection (1) ofsection 59, the interest on loansadvanced to the Board by the StateGovernment under section 64 or deemedto be advanced under subsection (2) ofSection 60 and charged to revenues inthat year to the extent of the short-fall shall not become payable to theState Government until revenues earnedin subsequent years are adequate alsoto meet such deferred liability ofinterest to the State Government."~

Page 47: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-41-ANNEX 2

Page 4 of 5

Existing Proposed

S.68

Charging of depreciation by Board - Charging of depreciation by Board -(1) Subject to the provisions (1) The Board shall provide eachof section 67, the Board shall year for depreciation such sumprovide each year for depreciation calculated in accordance with suchsuch sum calculated in accordance principles as the Central Governmentwith such principles as the Central may after consultation with theGovernment may after consultation the Authority, by notification inwith the Authority, by notification the Official Gazette lay down fromin the Official Gazette lay down time to time.from time to time.

(2) The provisions of this section(2) Where in any particular year shall apply to the changing ofdepreciation cannot be adjusted depreciation for the year in whichagainst revenues, the same may be the Electricity (Supply) Amendmentcarried over to subsequent years. Act, 1978, comes into force.

(3) The provisions of this section [In Section 68 of the Principal Act,shall apply to the changing of in subsection (1), the wordsdepreciation for the year in which "subject to the provisions ofthe Electricity (Supply) Amendment Section 67" and subsection (2)Act, 1978, comes into force. shall be omitted. Subsection (3)

of section 68 shall be renumberedas subsection (2)]

S. 69

Account of Audit - (1) The Board In subsection (1) of section 69 of theshall cause proper accounts and Principal Act, for the words "as mayother records in relation thereto be prescribed by the State Governmentto be kept, including a proper in consultation with the Comptrollersystem of internal check and and Auditor-General of India", theprepare an annual statement of words "as may be prescribed by theaccounts including the profit and Central Government in consultationloss account and the balance sheet with the Comptroller and Auditorin such form as may be prescribed General of India and the Stateby the State Government in consult- Governments'!shall be substituted.ation with the Comptroller andAuditor-General of India. No change in subsection 69(2) to (5).

(2) The accounts of the Boardsiall be audited by the Comptrollerand Auditor-General of India or bysuch person as he may authorize inthis behalf and any expenditureincurred by him in connection withsuch audit shall be payable by theBoard to the Comptroller andAuditor-General of India.

Page 48: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-42- ANNEX 2

Page 5 of 5

Existing Proposed

(3) The Comptroller and Auditor-General of India or any personauthorized by him in connectionwith audit of the accounts of theBoard shall have the same rights,privileges and authority inconnection with such audit as theComptroller and Auditor-General ofIndia has in connection with theaudit of Government accounts andin particular shall have the rightto demand the production of books,accounts, connected vouchers andother documents and papers, and toinspect any of the officers of theBoard.

(4) The accounts of the Board ascertified by the Comptroller andAuditor-General of Tndia or anyother person authorized by him inthis behalf together with theaudit report thereon shall beforwarded to the Authority and

to the State Government within sixmonths of the close of the year towhich the Accounts and audit reportrelate, and that Government mayissue such instructions to the Boardin respect thereof as deems fit andthe Board shall comply with suchinstructions.

(5) The State Government shall -(a) cause the accounts of the Boardtogether with the audit report thereonforwarded to it under subsection (4)to be laid annually before the StateLegislature; and

(b) cause the account of the Boardto be published in the prescribedmanner and make available copiesthereof on sale at a reasonalbe price.

Page 49: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Rates of Return ' of SEBs(FY 1979 - FY 1982)

(based on audited data, unless otherwise stated)

_ , F~~~~~~~~~~~~~~~~~~~~Y 1982FY 1979 FY 1980 FY 1981 Fo ecast

Keturn Return Return Return Return Return Return Returnto SEB incl. to SEB Incl. to SEB incl. to SEB incl.

State State State StateDuties Duties Duties Duties

Andhra Pradesh 9.5 9.5 9.5 9.5 9.5 9.5 9.5 9.5

Bihar 1.4 2.6 5.2 6.3 1.4 2.4 5.4 6.5

Gujarat 9.7 14.0 8.3 12.4 9.5 13.7 9.5 15.4

Haryana 10.0 14.4 5.5 9.2 0.3 3.4 9.5 13.5

Karnataka 15.7 20.6 12.5 16.7 13.3F 17.4F 11.4 15.4

Kerala 15.7 18.0 13.9 15.8 15.OF 17.3F 11.3 14.4

MadhyaPradesh 11.2 14.1 13.4 16.9 8.2 11.2 9.5 12.3

Maharashtra 14.2 15.7 9.5 11.0 9.5 12.2 9.5 12.3 w

Orissa 1.7 9.7 6.7 14.3 10.4 19.3 10.4 20.6

Punjab 9.5 11.9 9.5 11.7 9.5 11.7 9.5 11.8

Rajasthan 8.6 9.7 9.5 10.7 5.3F 6.4F 9.5 10.4

Tamil Nadu 9.5 10.4 9.5 9.9 9.5 9.8 9.5 9.8

Uttar Pradesh 1.8 2.4 9.5 10.1 6.4F 7.2F 9.5 10.4

West Bengal 9.5 11.0 9.5F 10.7F 9.5F 10.8F 9.5 10.9

F = Forecast

Target rate of return in general is 9.5%. When this was established in 1964, it was also |conceived that an average electricity duty equivalent to a return of 1.5% would be applied,making the total expected return 11%. Effective March 1978, GOI levied an additionalexcise tax of 2 paise/kWh on generation which is not included above. This would add anestimated 2-3 percentage points to the returns noted.

Not eligible for assistance under Rural Electrification Credits 572-IN and 911-IN: U.P.subsidy for Bural electrification from FY 1980 agreed in principle but detailed computationstill under discussion with State government.

Page 50: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

All India Sales and Energy Data 1974-75 to 1980-81.

1974-75 1975-76 1976-77 1977-78 1978-79 1979-80 1980-81 1981-82

(Provisional)

Installed capacity (Excl. non- 18317 20177 21814 23770 26681 28448 30214 32389

utility Plant) (MW)

Electricity Generated (GWh) 70191 79231 88333 91206 102432 104627 110821 122869

Electricity sold (GWh) 52682 60246 66608 68693 77293 78123 82473 89500

Electricity generated per 119.2 132.5 147.2 146.7 159.6 160 166.2 183

Capita (kWh)

Electricity consumed per 89.9 100.3 111.0 110.9 120.7 119.4 123.7 132Capita (kWh) utilities only

Proportion of Sales (%)

Agricultural & Irrigation 14.5 14.5 14.4 14.5 15.6 16.9 17.5 18.1

Railway Traction 2.9 3.1 3.3 3.5 3.8 2.9 2.8 2.9

Industry 62.1 62.4 62.5 61.6 61.7 59.7 58.6 57.1

Commerce 8.5 7.3 7.3 7.3 5.6 5.3 6.0 6.1

Domestic 8.5 9.7 9.5 10.0 9.8 10.8 11.3 11.6

Other (Public lighting, water 3.5 3.2 3.0 3.0 4.5 4.4 3.8 4.2works and Misc. etc.)

Annual growth of sales (%) 5.3 14.5 10.5 3.2 12.5 1.2 6.5 5.6

Losses (as percentage of kWh 20.5 19.4 19.7 1.9.6 20.0 20.5 20.5 20.5

sent out)

Source: CEA

Page 51: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-45-

ANNEX 5Page 1 of 12 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Long-Term System Expansion Plan

Demand Forecast

1. The Plan is based on a new CEA exercise in demand forecasting, usingdifferent methods for different consumer categories. The industrial demandforecast is based on empirical relationships between electricity consumptiongrowth and growth of value added in industry; irrigation pumping forecastsare dependent on the planned rate of new pump connections, the expectedutilization rates, and the replacement rate of diesel pumps. Residentialand commercial use is extrapolated from past relationship over time. Twogrowth scenarios, depending on assumptions about higher or lower growth ratesof industrial value added, have been developed. The results of theunconstrained forecast, by Region, are summarized in Table 1.

Page 52: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-46-ANNEX 5Page 2 of 12 pages

Table 1: Projections of Electricity Requirement and PeakDemand on Utility Systems

Region Scenario 1984-85 1989-90 1994-95 2000-01Electricity Requirements - GWh

(at Power Station bus)

Northern High 49411 77666 116420 178836Low 47173 71713 104943 155215

Western High 50406 76382 112979 175626Low 47458 68480 97096 144020

Southern High 40314 60032 86583 133368Low 37983 53777 74016 108361

Eastern High 27393 41356 59916 91900Low 25595 36516 50111 72206

North-Eastern High 2120 4028 6943 13051

Low 2004 3710 6299 11772

Peak Demands - MW

Northern High 9563 14938 22213 34025Low 9157 13906 20193 29779

Western High 8618 13211 19541 30377Low 8221 11935 17052 25293

Southern High 7204 10709 15444 23789Low 6835 9669 13306 19480

Eastern High 4767 7263 10523 16140Low 4458 6463 8869 12779

North-Eastern High 443 855 1495 2865

Low 420 792 1370 2635

2. While, by 1989/90, the new CEA estimate is pitched about midwaybetween all previous forecasts, it is on the high side by the year 2000.This is mostly due to the high sustained industrial growth assumptions in thehigh scenario. The average annual growth rates in All-India electricityconsumption resulting from this exercise are high initially (reflecting thegrowth from present suppressed demand levels), tapering off to about 7-8%p. a. by 1995 (Table 2).

Page 53: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-47-ANNEX 5Page 3 of 12 pages

Table 2: Projected Trends in Growth of Electricity Consumption

(percentage per annum)High LowScenario Scenario

1980-81 to 1984-85 12.81 11.291984-85 to 1989-90 8.93 7.981989-90 to 1994-95 8.17 7.331994-95 to 2000-01 7.62 6.81

3. The pattern of electricity consumption in various consumer categoriesis expected to undergo some change. The consumption in the agriculturalsector would gradually decline to about 13% from the present 18% by the endof the century due to saturation of demand for agricultural pumping. Therewould also be a slight decline in the share of industrial consumption, andan increase in consumption in residential, commercial and other categories.

4. Assumptions concerning the transformation of consumption forecastsinto energy generation and peak capacity requirements are (i) a reduction insystem losses in the two major Regions from more than 20% to 15-17%, and (ii)a decline in system load factor as restrictions on supply are relaxedgradually. For purposes of system expansion planning, CEA is using the highconsumption forecast scenario. While this scenario may be somewhat toooptimistic in the later years (high sustained industrial growth, littleemphasis on industrial energy conservation), its effect on generatingrequirements, and, consequently, capacity expansion, may be compensated by alikely failure to bring down system losses rapidly. The use of the highscenario as basis for the least-cost expansion plan is therefore the mostreasonable choice at this stage.

Least-Cost Capacity Expansion Plan

5. The model (WASP, version III) uses the committed generating projects(under construction or sanctioned by CEA for construction) as fixed input,and a list of new hydro and thermal projects with their associated capitaland recurrent costs as variable element, in determining the least-costexpansion sequence necessary to meet forecast demand. For each of the fiveElectricity Supply Regions, separate system optimizations were undertaken.Each optimization was subjected to sensitivity tests with respect to:

(i) constraints on the optimum hydro plant development because ofpossible delays;

(ii) the siting of coal-fired plants at pitheads or close to loadcenters;

(iii) the forced outage rate (FOR) of thermal plants; and

Page 54: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-48-ANNEX 5Page 4 of 12 pages

(iv) the discount rate.

6. The main variations affecting the expansion program are those ofhydro construction and forced outage rates. The results show that the "highhydro" option is usually cheapest (although not always significantly), andthat concentration of thermal power at pitheads would reduce the overallcosts considerably. High forced outage rates increase the costsignificantly. Table 3 summarizes the expansion scenarios for each majorRegion, subject to a maximum desirable loss of load probability of 1%,together with the least-cost transmission options for each generation option.

7. In general, the high hydro/low FOR option turns out to be theleast-cost expansion solution for all Regions. This option is examined withrespect to expected future fund constraints in the ongoing Sixth andforthcoming Seventh Plans. If no additional funds can be mobilized in thesetwo Plans, some capacity additions have to be postponed to the Eighth Plan,resulting in higher LOLP and lower peak reserve margins. Table 4 illustratesthe effect on reserve margins of a delay in capacity expansion. Table 5summarizes the final CEA judgement on desirable expansion programs in eachRegion, taking into account fund constraints, qualitative features, andpossible difficulties in bringing down FOR. The program aims at reachingLOLP of about 1% by the early 1990s.

Page 55: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-49-

ANNEX 5Table 3

Page 5 of 12 pages

Table 3: Regional Generation Expansion Options, 1982-95

High Hydro Low Hydro High Hydro Low Hydro Dispersed Gen. Dispersed Gen. Dispersed Gen. Dispersed Gen.High FOR High FOR Low FOR Low FOR High Hydro Low Hydro Low Hydro High Hydro

lHigh FOR Low FOR High FOR Low FOR

Northern Region

Additions (MW) 1982-85 3,873 3,873 3,873 3,873 3,873 3,8731985-90 10,581 10,390 7,469 7,469 10,601 7,8381990-95 10,108 11,542 10,170 10,897 10,028 10,388Total 24,562 25,724 22,012 22,239 24,502 22,099

LOLP (Z) 1995 0.361 0.562 0.307 0.589 0.384 0.524Energy not served (GUh) 1995 13 22 8 14 12 11Present value (Rs 10

Generation only 52.3 54.6 47.4 46.9 55.9 51.5Gen. plus least-cost transm. 64.1 66.5 57.1 57.7 66.1 58.6

Western Region

Additions (MW) 1982-85 4,712 4,712 4,712 4,712 4,712 4,712 4,712 4,7121985-90 9,394 9,054 6,499 6,844 9,894 7,604 8,654 6,9991990-95 8,645 9,185 8,293 9,455 9,085 9,275 11,375 7,263Total 22,751 22,951 19,504 21,011 23,691 21,591 24,741 18,974

LOLP (M) 1995 0.948 1.825 0.915 0.867 1.148 0.748 0.663 0.886Energy not served (GDh) 1995 34 30 27 24 36 17 20 24Present value (Rs 10

Generation only 61.7 63.1 56.0 58.4 67.7 65.7 69.0 62.8Gen. plus least-cost transm. 70.5 72.8 63.1 66.9 73.9 72.4 75.7 69.5

Southern Region

Additions (MW) 1982-85 2,896 2,896 2,896 2,8961985-90 4,942 4,892 4,942 4,8921990-95 6,516 6,826 5,293 5,381Total 14,354 14,614 13,131 13,169

LOLP (X) 1995 0.231 0.931 0.746 0.937Energy not served (DSJh) 1995 3 25 21 25Present value (Rs 10 )

Generation only 37.3 36.9 36.0 35.6Den. plus least-cost transm. 39.9 39.5 38.7 38.2

Eastern Region

Additions (MW) 1982-85 2,606 2,606 2,606 2,6061985-90 4,903 5,113 4,063 4,0631990-95 5,032 6,841 4,913 5,221Total 12,541 14,200 11,582 11,890

LOLP (X) 1995 0.813 0.989 0.892 0.997Energy not served (GPh) 1995 14.1 27.4 17.0 22.3Present value (Rs 10

Generation only 33.2 34.3 30.4 30.8Gen. plus least-cost transm. 35.9 36.9 33.0 33.3

Page 56: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-50- ANNEX 5Table 4Page 6 of 12

Table 4: Gross Reserve Margins (With and withoutFunds Constraints in VI Plan)

(All India)

-- Installed Cap. (MW) ---

After shift- PeakAs per WASP ing benefits Reduc- Demand --- % Reserve Margin ----Studies Due to funds tion in in High As per As perHigh Hydro/ Constraints Benefits Scenario Unrestricted Restricted

Year Low FOR in VI Plan (MW) (MW) Program Program

1985/86 50707 50469 238 33502 51.4 50.6

1986/87 56496 55619 877 36571 54.5 52.1

1987/88 61462 58932 2530 39836 54.3 47.9

1988/89 65641 61734 3907 43289 51.6 42.6

1989/90 70393 65328 5065 46976 49.8 39.1

VII PlanAdditions 24328 19263

1990/91 75318 70422 4896 50897 48.0 38.4

1991/92 82534 78784 3750 55060 49.9 43.1

1992/93 87539 87459 80 59487 47.2 47.0

1993/94 92690 92610 80 64191 44.4 44.3

1994/95 99738 99658 80 69216 44.1 44.0

VIII PlanAdditions 29345 34330

Page 57: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-51-ANN~EX 5Table 5Page 7 of 12 pages

Table 5: Desirable Power Program(All India)

81-82 82-83 83-84 84-85 85-86 86-87 87-88 88-89 89-90 90-91 91-92 92-93 93-94 94-95(Actual)

Existing capacity ason 31/3/82 (MW)

Hydro 12170Thermal 19357Nuclear 860

Sub-Total 32387

Additions (MW) from

(a) Committed ProjectsHydro 1140 1050 1780 1189 1965 783 822 614 480 385Thermal 3287 3590 4355 3100 2950 2320 1500 1000Nuclear

2 351/ 2-35-1 .Z-i 235 235

Sub-Total 4 /662 48-/ 613W 4524 3510 3103 2322 1614 480 385

(b) New ProjectsHydro 170 187 89 687 2180 4365 5616 4757 3374Thermal 420 1860 2660 3092 2810 1550 710 1920 2630Nuclear 235 235 - 470 705Sub-Total 590 2047 2749 3779 5225 6150 6326 7147 6709

Total (a) + (b) 4662 4875 6135 4524 5740 5150 5071 5393 5705 6535 6326 7147 6709

Cumulative capacity (NW) 32387 37049 41924 48059 52583 58323 63473 68544 73937 79642 86177 92503 99650 106359

Peak Load (MW)

(Inter-regional Diversitynot considered) 18023 25277 27765 30335 33216 36259 39495 42911 46570 50455 54585 58972 63629 68619

Energy Requirement (Twh) 115.28-! 141.66 155.31 169.64 185.57 202.46 220.32 239.33 259.46 281.17 304.20 328.78 354.91 382.84

1/ The above programme assumes that a capacity of 19866 MW would be added during the Sixth Plan.The inputs for the long-term planning study were finalised in August 1981. At that time, itwas envisaged that a capacity of 4662 MW would be commissioned during 1982-83. According topresent indications, it is expected that during 1982-83 a capacity of 3717 MW (including Nuclear)would be commissioned and erection in respect of 945 MW would be completed.

2/ Unconstrained: 128.89.

Page 58: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Desirable Power Program(Northern Region)

82-83 83-84 84-85 85-86 86-87 87-88 88-89 89-90 90-91 9-192 92-93 93-94 94-95

Existing Cap.as31/3/1982 (MW)

Hydro : 4143Thermal: 4928Nuclear: 440Sub-Total : 9511

Additions (MW) from

(a) Committed ProjectsHydro 322 453 318 139 444 197 377 354 250 250Thermal 750 1170 860 840 920 500 500 500 - -Nuclear - - - 235 235 - - - -

Sub-Total (A): 1072 1623 1178 1214 3W -697 877 854 250 250 n

(b) New ProjectsHydro - 105 792 1976 2807 1868 1893Thermal 810 1190 690 1050 210Nuclear 235 235

Sub-Total (B) = 810 1190 795 1842 2186 2807 2103 2128

Total (A+B) 1072 1623 1178 1214 1599 1507 2067 1649 2092 2436 2807 2103 2128

Cumulative capacity (MW) 10583 12206 13384 14598 16197 17704 19771 21420 23512 25948 28755 30858 32986

Peak Load (MW) 7945 8765 9563 10546 11570 12641 13761 14938 16260 17648 19094 20614 22213

Energy Requirement (MkWh) 41065 45223 49411 54554 59928 65555 71461 77666 84651 91987 99706 107839 116420

L.O.L.P. (%) with 1.448 0.735 0.632 0.835 0.750 0.918 0.654 0.798 0.715 0.382 0.051 0.027 0.018 w

Low F.O.R.

L.O.L.P. (%) with 4.847 2.731 2.677 3.258 3.105 3.627 3.161 3.544 3.382 2.151 0.645 0.401 0.273 0High F.O.R.

Page 59: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Desirable Power Program(Western Region)

82-83 83-84 84-85 85-86 86-'87 87-;88 88-89 89-90 90-91 91-92 92-93 93-94 94-95

Existing capacity ason 31/3/82 (MW)

Hydro : 1810Thermal: 6645Nuclear: 420Sub-Total : 8875

Additions (MW) from

(a) Committed ProjectsHydro 5 152 280 130 294 250 - -

Thermal 2010 1550 840 1020 980 1110 500 -

Nuclear - - -Sub-Total 2015 1702 1120 1150 1274 1360 500

U,

(b) New ProjectsHydro 90 - 80 445 970 790 920 1175 708Thermal 420 420 630 1040 920 710 500 710 920Nuclear ___235 235 235Sub-Total = = = = 510 420 710 1485 2125 1735 1420 1885 1863

Total (a) + (b) 2115 1702 1120 1150 1784 1780 1210 1485 2125 1735 1420 1885 1863

Cumulative Capacity (MW) 10890 12592 13712 14862 16646 18426 19636 21121 23246 24981 26401 28286 30149

Peak Load (MW) 7143 7859 8618 9425 10271 11193 12162 13211 14315 15494 16754 18101 19541

Energy Requriement (MkWh) 41961 46042 50506 54960 59806 64979 70495 76382 83766 89582 96866 104651 112979

L.O.L.P. (%) with 0.774 0.259 0.352 0.555 0.221 0.040 0.022 0.029 0.010 0.011 0.024 0.029 0.067Low F.O.R.

L.O.L.P. (%) with 7.565 3.897 4.704 6.166 3.346 1.110 0.694 0.851 0.479 0.491 0.708 0.745 1.160 0High F.O.R.

F-

Page 60: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Desirable Power Program(Southern Region)

82-83 83-84 84-85 85-86 86-87 87-88 88-89 89-90 90-91 91-92 9Y2-93 93-94 94-95

Existing capacity ason 31/3/82 (MW)

Hydro : 5098Thermal: 3034Nuclear: -Sub-Total 8132

Additions (MW) from

(a) Committed ProjectsHydro 695 395 610 810 1017 186 - -

Thermal - 210 1260 420 210 500 500 500Nuclear 235 235 - - - - -

Sub-Total 930 840 1870 1230 1227 686 500 500

(b) New ProjectsHydro 80 69 9 47 60 900 980 425 320Thermal 420 420 420 420 - - 710 1210

Nuclear ___ ___235 235

Sub-Total = 80 489 429 467 480 900 980 1370 1765

Total (a) + (b) 930 840 1870 1230 1307 1175 929 967 480 900 980 1370 1765

Cumulative Capacity (MW) 9062 9902 11772 13002 14309 15484 16413 17380 17860 18760 19740 21110 22875

Peak Load (M W) 6075 6621 7204 7819 8474 9173 9917 10709 11529 12408 13350 14361 15444

Energy Requirement (MkWh) 33989 37039 40314 43769 47451 51378 55564 60032 64634 69565 74846 80512 86583

L.O.L.P. (%) with 0.008 0.037 0.002 0.001 0.000 0.001 0.009 0.005 0.089 0.109 0.164 0.187 0.158

Low F.O.R.

L.O.L.P. (2) 0.068 0.201 0.043 0.021 0.009 0.051 0.196 0.593 0.852 0.700 0.875 0.567 0.937

with High F.O.R.r Dn

0n

Page 61: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Desirable Power Program(Eastern Region)

82-83 83-84 84-85 85-86 86-87 87-88 88-89 89-90 90-91 91-92 92-93 93-94 94-95

Existing capacity ason 31/3/82 (MW)

Hydro : 972Thermal: 4282Gas 100Sub-Total 5354

Additions (MW) from

(a) Committed ProjectsHydro 8 - 430 - 150 150 415 230 230 135Thermal 490 660 1230 820 840 210 - - - -Nuclear - - - - - - ---

Sub-Total 498 660 1660 820 990 360 415 230 230 135

(b) New ProjectsHydro 118 - 70 263 371 616 909 223Thermal 210 420 920 420 630 210 500 500Nuclear - __ - -

Sub-Total _ 328 420 990 683 1001 826 1409 723

Total (a) + (b) 498 660 1660 820 990 688 835 1220 913 1136 826 1409 723

Cumulative Capacity (MW) 5852 6512 8172 8992 9982 10670 11505 12725 13638 14774 15600 17009 17732

Peak Load (M)W 3992 4370 4767 5201 5670 6162 6693 7263 7836 8438 9091 9777 10523

Energy Requirement (MkWh) 23025 25146 27393 29845 32484 35247 38230 41356 44617 48046 51766 55672 59916 . |

L.O.L.P. (%) with 4.790 1,472 0.471 0.609 0.311 0.402 0.267 0.136 0.199 0.142 0.262 0.101 0.248Low F.O.R.

|1

L.O.L.P. (%) with 21.956 8.088 3.961 4.679 3.157 3.543 2.730 1.275 2.300 1.935 2.575 1.450 2,298High F.O.R.

D)

(12

Page 62: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

Desirable Power Program(North Eastern Region)

82-83 83-84 84-85 85-86 86-87 87-88 88-89 89-90 90-91 91-92 92-93 93-94 94-95

Existing Capacity ason 31i3/82 (MW)

Hydro : 147Thermal: 183Diesel : 53Gas : 132Sub-Total 515 MW

Additions (MW) from

(a) Committed ProjectsHydro 110 50 142 110 60 30 30Thermal 37 - 165 - - - -Nuclear - - - - _ _ _Sub-Total 147 50 307 110 60 30 30

(b) New ProjectsHydro 20 95 328 293 380 230Thermal 22 - - - - -Nuclear _- -Sub-Total - = =42 5- 328 2- 93 3~-80 230

Total (a) + (b) 147 50 307 110 60 30 72 95 328 293 380 230

Cumulative Capacity (MW) 662 712 1019 1129 1189 1219 1291 1386 1714 2007 2387 2617

Peak Load (MWn 340 387 443 511 586 667 751 855 957 1072 1198 1338 1495 m Fa

Energy Requirement (Mklh) 1623 1857 2120 2439 2788 3164 3576 4028 4500 5021 5597 6234 6943

L.O.L.P. (Z) with 0.021 0.021 0.014 0.017 0.020 0.026 0.120 0.412 0.540 0.049 0.036 0.000 0.000Low F.O.R.

L.O.L.P. (2) with 0.036 9.021 0.014 0.017 0.021 0.060 0.365 1.018 1.192 0.098 0.036 0.000 0.000 aHigh F.O.R. m

Page 63: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-57-

ANNEX 6

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Southern Region Sales and Energy Data 1979/80-1981/82

1979/80 1980/81 1981/82

Installed Capacity (MW)1/ 6,606 7,051 7,532

Electricity Generated (GWh)2' 24,662 26,313 31,613

Electricity Sold (GWh)-/ 19,884 21,767 23,262

Annual sales growth (%) 2.0 9.5 6.9

Electricity consumption by category (GWh):

Domestic 2,242 2,614 2,794

Commercial 1,342 1,446 1,567

Industrial 12,035 13,294 14,301

Agriculture 3,578 3,787 3,912

Other 688 623 688

l/ excluding 600 MW centrally owned generation at Neyveli

2/ including sales outside the Region

3/ including purchases from outside the Region

Page 64: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-58-

ANNEX 7

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Southern Region: Installed Capacity, Peak Loadand Energy Requirement 1977/78-1981/82

1977-78 78-79 79-80 80-81 81-82

Installed Capacity (}W)-/ 6,101 6,496 7,206 7,651 8,132

Peak Load (MW)-/ 4,058 4,471 4,385 4,905 4,924

Energy Requirement (GWh)-/ 22,012 25,317 25,492 28,252 31,407

1/ including Neyveli

2/ at station bus, restricted by supply

Source: CEA

Page 65: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-59-

ANNEX 8

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Southern Region Power Supply Restrictions

(% of potential demand)

Karnataka KeralaDemand Energy Demand Energy

April 1981 10-30 10-30 30-50 15-30

May 1981 10-15 10-30 30-50 15-30

June 1981 10-15 10-30 30-50 15-30

July 1981 - 10-30

August 1981 - 10-30

Sept. 1981

Oct. 1981

Nov. 1981

Dec. 1981

Jan. 1982 10-30** 10-30**

Feb. 1982 10-30** 10-30**

March 1982 10-30** 10-45** 24-45** -16 hrs/day cuton agriculturalconsumers

** Cut on Industries

Source: CEA

Page 66: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECTNational Thermal Power Corporation Limited

Organizational Structure (Revised)

Board ofDirectors

Chairman &

Directorr_IExecutive

Committee

MancgementCommlttee

Directai tor C ~~~~~~~~~~~~~~~~~~~~~~~ExctieDirectorDicg Director

Personnel Technical ~~~~~~~~~~ ~~~~~~~~~~~~~~Commercial Fnrc

c) e Administratior) Corrany& Training Secretory

I ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~C,

transmission | ExpEDPi&tnCorporate Oonration Engineering ~~~Panning& Cotat seiigMrketingMaaeit

_ } Engineering l l Servicos l l Services l l P Design Services Services Systems

Execulie Executive

0 ~~~~~~~~~~~~~~Director Dlrector- (Northern Region) (Western Region)

00

r° D

Pro ect Project Project Project 1 ProjectEngineering Headnersg Engineering n Hinv-l,norin | Engineering Engineering Eng neering

Ramagundom Singraucirian KortY) Faralkk)Vnhyca

LY] General General General Chiet 'jt ~~~~~~~~~~~~~~GoGeral ral aChtatGeneralSaaurrce NTPCroeli Rihanci Transmission Manager Manager Manag198transmisn Warl nager

Manager Manager Ma~~~~~~nagersislo Firakkc indrvchlRamagundam

Source NTPC October 1982 World Blank -24443

Page 67: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-61-

ANNEX 10

INDIA

CENTRAL POWER TRANSMISSION PROJECT

NATIONAL THERMAL POWER CORPORATION LIMITED

MANPOWER AS OF SEPTEMBER 30, '1982

Skilled or Engaged onExecutive Supervisory Unskilled daily basis Total

Singrauli 349 311 1,013 - 1,673

Korba 312 256 728 235 1,531Ramagundam 226 126 430 - 782

Farakka 112 105 241 30 488Vindhyachal 13 4 6 - 23

Rihand 14 2 1 - 17Badarpur 279 477 2,057 63 2,876

Corporate Center 427 130 284 25 874Western Region 103 - 6 - 109

Northern Region 69 1 1 - 71

Southern Region 34 - -_-_34

Total 'On theJob' 1,938 1,420 4,767 353 8,478

Trainees 215 134 293 - 642

Total Manpoweras at September30, 1982 2,153 1,554 5,060 353 9,120

Projected 1ian-power Require-ments FY1990 1/ 4,514 3,096 13,514 - 21,124

Present Manpoweras % FY1990requirements 48% 50% 37% - 43%

1/ Projected requirements for Corporate Centre, Singrauli (2,000 MW), Korba

(2,100 MW), Ramagundam (2,100 MW), Farakka (2,100 MW), Rihand (1,000 MW)and Vindhyachal (1,260 MW).

Source: NTPC October 1982.

Page 68: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-62-ANNEX 11

INDIA

CFNTRAL POWER TRANSMISSION PROJECT

NATIONAL THERMAL POWER CORPORATION LIMITED

Recruitment of Trainees

Executive Supervisory Skilled Total

FY1977 33 - - 33FY1978 46 27 - 73FY1979 92 - - 92FY1980 127 37 - 164FY1981 195 77 151 423FY1982 223 120 150 493

Actual Trainee RecruitmentFY1977-82 716 261 301 1,278

Projected Trainee RecruitmentFY1983-90 1,400 1,000 3,200 5,600

Total Required by FY1990 1/ 2,116 1,216 3,501 6,878

Actual Trainee Recruitment toFY1982 as % of total Requirementby FY1990 34% 18% 9% 19%

1/ Projected requirements for Corporate Centre, Singrauli (2,000 MW), Korba(2,100 MW), Ramagundam (2,100 MW), Farakka (2,100 MW), Rihand (1,000 MW)and Vindyachal (1,260 MW).

Source: NTPC October 1982.

Page 69: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

N.-a n -he--ci Power Copolon umTeOOigoflr- onol struptur-

Corporoto Fmoonc

EV3~~~~~~~~~~~~~~ r[0-o -t t0 .

iJ~~~~~~~~~~~~~~~~~~~Li ~ ~ ~ ~ ~ ~~~~~LCT F] *I E

A f .7--e 7 fI

Page 70: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-64- ANNEX 13Page 1 of 18 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

PROJECT DESCRIPTION

The project consists of the following major physical components:

1. 400 kV Transmission Lines (See Attachment 1)

Ramagundam - Mangur, double circuit 230 kmMangur - Vijayawada, double circuit 160 kmVijayawada - Nellore, single circuit 305 kmNellore - Red Hills, single circuit 245 kmSingrauli - Vindhyachal, single circuit 14 kmRamagundam - Chandrapur, double circuit 158 km

2. 400/220 kV Substations (See Attachment 2)

Ramagundam - extension, to connect the second circuit to Mangur(the equipment for the first circuit is part ofthe Second Ramagundam Thermal Power Project).

Mangur - new, to connect the two circuits to Ramagundam,the two circuits to Vijayawada and one 315 MVA,400/220 kV transformer.

Vijayawada - new, to connect the two circuits to Mangur, one

circuit to Nellore and one 315 MVA, 400/220 kVtransformer.

Nellore - new, to connect the single circuit lines toVijayawada and Red Hills and one 315 MVA,400/220 kV transformer.

Red Hills - extension, to connect the single circuit line toVijayawada.

Chandrapur - extension, to connect the double circuit line toRamagundam.

Singrauli - extension, to connect the single circuit line toVindhyachal.

Vindhyachal - extension for the single circuit line to Singrauliand the 500 MW HVDC back-to-back substation.

Page 71: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-65-Annex 13Page 2 of 18 pages

3. 500 MW High Voltage Direct Current (HVDC) Back-to-BackSubstation at Vindhyachal (See Attachment 3)

4. Meetering and Instrumentation (See Attachment 4)

Installation of tariff meetering systems and disturbancerecorders in important substations of the Northern, Western andSouthern Regional grids.

5. Communication System (See Attachment 5)

Power line carrier communication (PLCC) equipment complete forspeech transmission, line protections and data transmission oneach 400 kV transmission line.

Page 72: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-66- Annex 13

Attachment 1Page 3 of 18 pages

Salient Features of the 400 kV Transmission Line

1. Line Configuration

Single circuit lines would have a horizontal and double circuitlines a vertical configuration.

2. Equipment Description

Towers

Self-supporting latticed steel towers, fabricated from struc-tural steel angle sections will be used. A1 the components of the towerswill be hot-dip galvanized.

Normally, the following four types of towers will be used:- 'A' type suspension straight run tangent towers for up to

2 degrees angle of deviation;

- 'B' type tension towers for angles of deviation in the lineup to 15 degrees, also to be used as section towers;

- 'C' type tension towers for angles of deviation in the lineup to 30 degrees, also to be used as section towers indifficult terrain; and

- 'D' type tension towers for angles of deviation in the line upto 60 degrees and also as dead-end (terminal) towers.

In addition, special towers and foundations are envisaged formajor river and power line crossings and places where the right of way isrestricted or the terrain is particularly difficult. The design of thesetowers and foundations will be finalised after detailed soil investigationand route survey.

Conductors

Twin bundles of 54/7/3.53 'MOOSE' ACSR, or equivalent conduc-tors, will be used per phase, which will provide a power transfercapability of about 600 MW per circuit. As for all 400 kV NTPC lines, theintra-phase spacing will be 450 mm, which will result in the optimum withrespect to line inductance and line loss characteristics.

Page 73: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-67-

Annex 13Attachment 1

Page 4 of 18 pages

Earthwire and Lightning Protection

Suitable galvanized steel earthwire will be used to withstandtwo successive lightning strokes of 150 kiloampere. It will have a ten-sion-to-weight ratio about 20% higher than the power conductor. Sincethe lines would be passing for an appreciable length over hilly terrain,the shielding angle is intended to be reduced to 20 degrees in order tominimize snielding failure.

Grounding

The tower footing resistance will be kept below 10 ohms. Nor-mally pipe type grounding will be used. In case of rocky ground wherethe ground resistance is high, counterpoise earthing will be used to bringtower footing resistance down to an acceptable level.

Insulators and Hardware

High strength glazed procelain disc insulators will be used.Suspension strings will consist of 23 discs (255x145 mm) of 120 kNmechanical strength and tension strings will consist of 23 discs (280x170mm) of 160 KN mechanical strength.

3. Summary of Regulations and Practices for Routing 400 kV lines inIndia

Ground Clearance

As per item 77 of Chapter VIII of Indian Electricity Rules -1956 (as amended upto June 1979) the clearance above ground shall not beless than 5.20m plus 0.3m for every 33 kV or part thereof by which thevoltage of the line exceeds 33 kV. For 400 kV lines it works out at8.84m.

Compensation

No compensation is normally required for land in case of trans-mission lines. Compensation is, however, paid for plantations includingthe land involved. Land compensation is also involved in traversing urbanareas but 400 kV lines are usually routed in such a manner as to avoidurban areas. Compensation is made for the crop damaged, if any, duringerection work.

Forest Clearance

While fixing the alignment of the line all efforts are made toavoid reserved forest land. In cases where it is unavoidable as per

Page 74: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-68-

Annex 13Attachment 1Page 5 of 18 pages

Forest (conservation) Act - 1980 advance clearance from the Forest Depart-ment, Ministry of Agriculture, Govt. of India is required to be taken.For trees cut down in a reserved forest, the cost of planting three trees,for every tree cut down, is paid to the Forest Department of the StateGovernment.

For normal right of way, trees falling on the line route are tobe cut and compensation paid to the owner. A right of way of 26 m oneither side of the centre line of the route is provided.

4. Measures Adopted to Avoid Electrical Interference in Telecom Circuits

Growth of Power and Telecom Systems is vital to any country,especially for a developing country like India. Thus the concentration oftelecom and power lines in close vicinity is unavoidable as both have toexist in serving common consumers. This brings in problems of extraneousinduction encountered by the telecom circuits.

To avoid induction, the transmission line routes are selected insuch a way that the alignment, as far as possible, is away from open wiretelephone/telegraph line alignment by at least 8 km.

Sometimes in unavoidable circumstances it becomes impossible tomaintain the adequate separation between the power and telecom lines. Insuch cases, induced voltages in the paralleling telecom circuits arecomputed under actual conditions and the following protective measures areadopted as per present practice in India.

A.. Communication Circuits

i) For induced voltage up to 430 volt no protective measuresare considered necessary.

ii) Beyond 430 volt but up to 650 volt adequate numbers of gasdischarge (G.D.) tubes are installed on the affected telcomcircuits. Telecom authorities in such cases do not chargecompensation from power authorities.

iii) Beyond 650 volt and up to 2000 volt again adequate numbers ofG.D. tubes are installed on the affected telecom circuits, butin such cases, whoever, i.e. the power or telecom authority, is thelater entrant, has to pay the cost of such protective works.

iv) If induced voltage is much higher than 200 volt re-engineeringof the affected telecom circuits is done. The followingre-engineering works are commonly adopted in India.

Page 75: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-69-

Annex 13Attachment 1Page 6 of 18 pages

a) The telecom line is shifted from the existing alignment toa different route to maintain the desired separationdistance. The cost of re-routing the telecom line is paidby the later entrant (the power authority);

b) The removal of the affected overhead telecom alignment andthe provision of aluminium sheathed star quad cable of suitablecapacity with screening factor of 0.1 with provision of V.F.repeaters to compensate the cable loss; and

c) The removal of the overhead telecom alignment and the provisionof the circuit on other media like UHF/Microwave system etc.

B. Railway Block Circuits

Railway block circuits are provided basically for the safetyproblems of the trains, although such circuits may also be protectedagainst high induced voltages by the installation of gas discharge tubesand by changing the block instruments with 300 volt to 450 voltimmunization level.

In cases where induced voltage is higher, overhead block circuitsare removed and re-engineering of circuits like that of communicationcircuits is done at the cost of the later entrant.

Conduction

As the name implies, conduction is brought about by actualelectrical contact between power and telecom lines. Crossing of both thelines therefore is done under the following manner as per the codeprescribed by the Power and Telecom Co-ordination Committee constitutedby the Government of India.

i) Angle of crossing shall be as nearly a right angle as possible;

ii) Adequate clearances as prescribed by Central PTCC are to beadopted between power and telecom lines;

iii) Adequate guardings shall be provided at the crossings for thepower lines below 36 kV; and

iv) No guarding arrangements are considered necessary in case ofcrossings with high voltage power lines above 36 kV.

Page 76: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-70- Annex 13Attachment 2Page 7 of 18 pages

Salient Features of the 400 kV System and Substations

1. Insulation Coordination

The 400 kV system has been designed to limit the switchingovervoltage to 2.5 PU. The temporary overvoltage could be 2 PU for 1-3cycles. Consistent with these values and the protected levels provided bylightning arrestors, the following insulation levels have been adopted forthe 400 kV system:

a) Impulse withstand voltage 1,320 kVP for transformersand reactors1,425 kVP for otherequipment

b) Switching surge withstand voltage 1,050 kVP

c) Minimum creepage distance 10,000 mm

d) Maximum fault current 40 kA

e) Duration of fault 1 sec

f) Corona extinction voltage 320 kV rms

Compensation equipment has been provided to control the steadystate transient and dynamic overvoltage to specified levels. Detailedsystem studies for various combinations of operating conditions will beconducted to work out the required compensation. Tentatively 420 kV shuntreactors of 50 MVar capacity are foreseen. In the event of generators notcapable of charging the 400 kV lines in spite of adequate fixed compensa-tion, additional variable compensation may be provided.

2. Interconnecting Transformers

Power transformers will conform in general to IEC 76. the kneepoint voltage of transformers will not be less than 1.1 PU and the aircore reactance will not be less than 20% for two winding transformers and40% for autotransformers. Autotransformers will have a 33 kV tertiarywinding which shall be capable of being loaded to 1/3 of the transformerloading. The insulation level of the tertiary will not be less than 250kV peak for lightning impulse and 95 kV rms for power frequency voltages.

Page 77: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

- 71-

Annex 13Attachment 2Page 8 of 18 pages

3. Circuit Breakers

Circait breakers will conform in general to IEC 56 and shall beeither of air blast or SF6 type. The total break time for any current andany combination of other conditions shall not exceed 50 ms for 400 kVbreakers. The 400 kV breakers controlling line feeders will be providedwith preinsertion closing resistors of about 400 ohm with 8 ms insertiontime. The short line fault capacity shall be the same as the ratedcapacity and this is proposed to be achieved without the use of openingresistors.

4. Isolators

The isolators will conform in general to IEC 129. The 400 kVisolators will be horizontal center break and pantograph type dependingupon the layout arrangement adopted for each substation. They will havean individual pole operating mechanism. All isolators shall be preferablyof the motor operated type. Earthing switches shall be generouslyprovided to facilitate maintenance. These should be properly interlockedand allinterlocks shall be fail safe type.

5. Current Transformers

Current transformers will comply in general to IEC 185. Alltaps are to be obtained by secondary switching. Current transformers unitwith 5 secondaries (4 for protection and I for metering) are proposed.The accuracy of the protection cores shall be class PS and for meteringcore it shall be 0.5. The burden and the knee point voltage shall be inaccordance withn requirements of the system including possible feeds fortelemetering.

6. Capacitive Voltage Transformers

Voltage transformers will in general conform to IEC 86 and 186A.They shall have three secondaries out of which 2 shall be used for protec-tion and 1 for metering. The accuracy of protection core shall be 3P andfor metering shall be 0.5. The VTS provided on lines shall be suitablefor carrier coupling. The capitance of CVT shall be 4400 pf.

7. Lightning Arrestors

Station class, current limiting heavy duty lightning arrestorsare proposed which will be conforming in general to IEC 99. The ratedvoltage of LA and other characteristics shall be chosen in accordance withsystem requirements. LA would be provided near line entrances and neartransformers and reactors so as to achieve proper insulation coordinationfor the whole substation.

Page 78: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-72-

Annex 13Attachment 2Page 9 of 18 pages

8. Shunt Reactors

50 MVar, 420 kV Shunt reactors are envisaged. The shunt reac-tors would have linear characteristics up to 1.5 PU voltage. The neutralof these shunt reactors shall be grounded through adequately rated neutralgrounding reactors to facilitate single phase reclosure against trappedcharges. The neutral of shunt reactors shall be insulated to 132 kV andshall be protected by means of 132 kV class lightning arrestors.

9. Protection and Control

Suitable control and protective relaying system shall beprovided for all the 400 kV substations equipment and feeders whichinclude 400 kV transmission lines, bus bars interconnection transformersetc., and complete with all necessary equipment. The complete protectionequipment auxiliary relays, trip relays timers, annunciators, indicatinglamps, indicating instruments, meters, switches, semaphore indicators,mimic diagrams, name plates, terminals and associated equipments and otherinter-facing and auxiliary equipment like event-loggers, disturbancerecorders, master clocks, AC clocks and follower clocks, synchronisingtrolley, relay test kits etc., shall be provided. The protection systemshall be in accordance with the modern power system philosophy with equip-ment having high reliability and speed and the transmission lines protec-tion and auto reclosing single and three phase selection. The transmis-sion line protection system shall have maximum operating time up to tripimpulse to breaker (complete protection time including the applicablecarrier and trip relay operating times) for all type of faults anywhere inthe protected line sections during both maximum and minimum generationconditions of 30 ms at the nearest end and 50 ms at the other end (carriertransmission time may be taken as 20 ms provided that any time reductionin carrier time shall be directly reflected as a deduction in the maximumoperating time). The bus bar protection wold be provided for each bussection independently along with the check feature, so that in the eventof a fault, only the minimum number of the circuits shall be disconnectedat the same time ensuring complete fault isolation and shall be of highspeed type. The interconnecting transformer would be provided with dif-ferential protection, restricted earth fault protection,back-up protectionand overfluxing protection etc.

10. Bus Switching Schemes

Ramagundam and Red Hills - Breaker and half scheme.

Mangur, Vijayawada andNellore - Breaker and half scheme.

Page 79: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-73-

Annex 13Attachment 2

Page 10 of 18 pages

Chandrapur - Madhya Pradesh switchyard wheredouble main and transfer scheme

is adopted.

Singrauli, Vindhyachal - Double main and transfer schemelike in all NTPC thermal powerplants.

11. Layout

Breaker and Half Scheme

Rigid aluminium tubular bus bars are proposed. The cross-overs,

wherever required, could be of rigid or strung type with twin 'Moose' ACSR

conductor. Substation is of two levels, i.e. equipment and bus bar at

first level and cross-overs at second level.

Double Main and Transfer Scheme

Quadruple Moose ASCR flexible bus is proposed. The substation

is of three levels i.e. equipment at first level, bus bars at second level

and cross-over at third level. Bus selector isolators are pantographtype.

12. Substation and Support Facilities

Certain basic facilities required for operation and maintenance

of the substation are described below:

AC & DC Power Supplies

For catering to the requirements of three phase and single phase

AC and DC control and power supplies for the various substation equipment,

the following arrangement is envisaged:

a) AC supply:Supply from a nearby reliable medium voltage(33 kV, 11 kV or 6.6 kV) source would be drawn.

This would be stepped down to 415 volts for distributionwithin the substation through two transformers ofsuitable rating. For additional reliability, dieselgenerators of suitable capacity would be provideddepending upon the reliability of the MV supply.

b) DC supply:220V and 50V batteries of adequate capacity would beprovided. Each battery would have a boost charger,float charger and trickle charger.

Page 80: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-74-

Annex 13Attachment 2Page 11 of 18 pages

Workshop and Laboratory

Workshop and Laboratory facilities would be provided for peri-odical and preventive maintenance of the equipment.

Oil Evacuating, Filtering, Testing and Filling Apparatus

To monitor the quality of oil for satisfactory performance oftransformers and for periodical maintenance, necessary oil evacuating,filtering, testing and filling apparatus would be provided. Oil tanks ofadequate capacity for storage of pure and impure transformer oil would beprovided.

Fire Fighting System

Fire fighting system will, in general, conform to fire insuranceregulations of India. The system is proposed with both AC and dieseldriven pumps. Automatic heat actuated emulsifying system is proposed fortransformers.

Lightning and Communications

Adequate normal and emergency lightning and communication sys-tems would be provided.

Control Room

Switchyard control room would be provided to house the controland relay panels, PLCC equipment, telemetering equipment, digital analogueprocessing and recording equipment, etc. Air conditioning will beprovided in the building as functional requirement.

Transport Facilities

For movement and unloading of heavy apparatus like power trans-formers and reactors, rail tracks within the substation and mobile craneswould be provided. One tractor trailer of suitable capacity is proposedto be provided under this project for movement of heavy apparatus liketransformers and reactors to areas where proper railway sidings are notavailable.

Field Testing Equipment

One set of field testing equipment is proposed to be procuredunder the project.

Page 81: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-75-Annex 13

Attachment 2Page 12 of 18 pages

Hotline Washing Equipment

Hotline washing equipment would be provided at substations,depending upon need to be established after detailed investigations ofsite environment.

Staff Colony

Staff colony to house the personnel manning the substations,would be provided.

Page 82: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-76-Annex 13Attachment 3

Page 13 of 18 pages

500 MW HVDC Back-to-Back Substation at Vindhyachal

1. Solid State Valves

The solid state valves to be incorporated in the HVDC terminalswill comprise of a series-parallel combination of high power water cooledsilicon controlled rectifiers (thyristors) which, through control of theirfiring angle provide the means of power transfer from the AC to DC side orvice versa. The solid state valves must be of modular building blockdesign for easier design optimisation.

2. Convertor Transformer

Two convertor transformers banks, suitably designed to withstandthe insulation requirements of DC application will be used per pole tostep up or step down the AC voltage to the appropriate level before trans-formation to achieve optimum valve design. The secondary of the trans-formers shall be properly connected to achieve the required phase shiftfor proper convertor operation.

3. Reactors

Smoothing reactors will be provided on the DC side for absorp-tion of the ripple voltage generated during conversion.

4. Filters

AC and DC filters will be such as to offer a low impedance pathto ground for harmonics generated in the AC and DC systems.

5. Reactive Compensation

Reactive compensation equipment will be provided to restore theAC side power factor to near unity. These may be of static Var control,shunt capacitor banks, or synchronous condensers or a combination or thethree.

6. Communication Control and Instrumentation

Protection, monitoring, measuring, communication and auxiliaryequipment,as required for the high reliability operation and easy faultdetection and maintenance,will be provided.

Page 83: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-77-

Annex 13Attachment 4Page 14 of 18 pages

Installation of Tariff Metering Systems and DisturbanceRecorders in the Regional Grids in India

1. Background

The power systems in the country are being interconnectedthrough 400 kV transmission lines to evolve the regional grids. Theconstruction of thermal power stations by NTPC together with 400 kV linesis accelerating the process of interconnection in the regions. The powergenerated at NTPC's thermal power stations is allocated to the differentStates in the Region according to the policy laid down by the Governmentof India. The power to the beneficiaries sometimes flows through trans-mission systems in the integrated network belonging to other agencies suchas the States, the Damodar Valley Corporation (in the Eastern Region), theBhakra Beas Management Board (in the Nothern Region) etc., while in cer-tain areas NTPC's transmission system carries power generated by the Stategenerating stations for transmission within the States or sometimes out-side the States. The generation from the different agencies such as thepower generated by the National Hydro-Electric Power Corporation, theDepartment of Atomic Energy, the Neyveli Lignite Corporation and otheragencies also gets fed into the respective regional grids. In order tocompute the energy that is fed into the system from different sources andthe energy actually drawn by the different systems, a special meteringsystem is necessary.

2. Objectives of the Metering Schemes

The tariff metering schemes would provide for:

a) Metering MS, MVar, MVA, MWh, kVar and MVarh exports andimports continuously;

b) Facilities for recording (printing) data accordingto the prescribed format, and storing the datafor computing daily, weekly and monthly; and

c) Facilities for transmitting data through telemetrysystems to the control center in the State and/orin the Region.

The instruments will have facilities for dividing the day intodifferent periods to facilitate, if necessary, the introduction at a laterstage of time of day metering system. A single instrument shall becapable of accepting all the input information for a mnaximum of ten cir-cuits; at very large substations where the number of circuits is more thanten, two such instruments would be used. The basic element in the instru-ment is a conventional energy meter which again would receive the inputsfrom CTs and VTs in the substation or generating station. The energymeter would be interfaced to a microprocessor system which shall compute

Page 84: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-78-

Annex 13Attachment 4Page 15 of 18 pages

different quantities for record through a printout in the prescribedformat and also for display on demand. The display shall provide for theinstantaneous value in MW, MVar, '4VA and cumulative MWh, MVarh and alsofor display of cumulative figures for say a day, week or a month. Theprintout facility shall print out different quantities every 30 minutesand also over a period of 24 h as well as the cumulative figures over amonth.

The approximate cost of an instrument is US$120. The list ofstations where instruments of this type are proposed to be installed inthe Northern, Western and Southern Regions are given below. The stationswhere the instruments would be installed would undergo some change whenthe scheme is finally worked out in consultation with the Regional Elec-tricity Boards.

2. Disturbance Recorders

The interconnection of individual systems in the Region neces-sitates that operating conditions should be carefully monitored and,whenever abnormual conditions in the system arise these are also accuratelyrecorded so that the post-disturbance analysis could be carried out. Suchanalysis would facilitate taking corrective measures to prevent recurren-ces of the disturbances. The absence of suitable instruments for record-ing the system conditions before, during and after the disturbance, hasleft many of the disturbances in the systems incompletely analysed.

NTPC has been providing disturbance recorders on all its 400 kVlines. However, such recorders are not provided on some of the 400 kVlines in the Northern and Western Regions and generally in most of the 220kV systems in all the Regions.

3. List of Power Stations and Substations where Tariff Metering will beInstalled

Northern Region

Name of the Substations/Power Stations VoltageLevel (kV)

I. Narela 220/332. Hissar 220/132/113. Dadri 2204. Ganguwal 220/33/115. Dehar 4006. Bhakra 2207. Pong 220/66/113. Badarpur 220/33

Page 85: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-79-Annex 13Attachment 4Page 16 of 18 pages

9. M4uradnagar 220

10. Singrauli 400

11. Kanpur 400

12. Obra 400/22013. Raps 22014. Lucknow 400

15. Baira Siul 220

16. Panipat 220/400

17. G.N.T.P. 220

18. Anpara 22019. Bhakra R.B. 220

20. I.P. Station 33

21. Faridabad 36

22. UBDC 13223. Shanan 13224. Bassi 13225. Giri 132

26. Lower Jhelum 13227. Chenani 132

28. Upper Sindh 13229. R.P. Sagar 13230. Jawahar Sagar 13231. Rihand 13232. Obra Hydel 13233. Matatila34. Khatima 13235. Yamuna I & IV 132

36. Ramaganga 13237. Pathri (Ganga Canal)38. Chilla 13239. Harduaganj 220

Western Region

Name of Substation/Power Station Voltage Level (kV)

1. Gandhinagar 220

2. Wanakbori 400/2203. Asoj 400

4. Ukai 2205. Walthan 2206. Jetpur 400/1327. Kalwa 400/2208. Tarapur 2209. Trombay 220

10. Nasik 220

11. Bableshwar 132

Page 86: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-80-

Annex 13Attachment 4Page 17 of 18 pages

12. Bhusaval 400/22013. Koyna 13214. Karad 13215. Kolhapur 13216. Parli 22017. Indore 40018. Koradi 40019. Satpura 40020. Itarsi 40021. Jabalpur 40022. Bhilai 400/13223. Korba (MPEB) 40024. Korba (NTPC) 40025. Vindhyachal 40026. Bodaghar (Barsur) 132/22027. Chandrapur 400

Southern Region

Name of Substation/Power Station Voltage Level (kV)

1. Belgaumi 220/1102. Hubli 220/1103. Sharavati 2204. Shimoga 220/1105. Mysore 220/1106. Bangalore 400/220/1107. Sanem 400/220/ 1108. Idikki 2209. Siragiri 22010. Tuticorin 22011. Neyreli 400/220/11012. Kalpakkam 22013. Ennore 220/11014. Red Hills 400/220/11015. Cuddapah 400/220/11016. Gooty 220/13217. Munirabad 22018. Raichur 220/11019. Sri Sailam 220/13220. Nagarjun Sagar 400/ 220/ 13221. Hyderabad 400/22/13222. Vijayawada 400/22023. Kothagudem 220/13224. Mangur 400/22025. Lower Sileru 22026. Upper Sileru 22027. Ramagundam 400/132

Page 87: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-81-

Annex 13Attachmnent 5Page 18 of 18 pages

Communication System

Power Line Carrier Communication (PLCC) equipment complete for

speech transmission, line protections and data transmission will beprovided on each 400 kV transmission line. The protections for the trans-

mission lines and line compensating equipment will have 100% back-upcommunication channels. The PLCC equipment shall include the following:

a) Coupling device, line traps, carrier terminals, voice frequency

terminals, protection couplers, HF cables, trunk selectors,automatic exchange for 25 lines, spare parts, maintenance and

testing instruments. The equipment supplied will not belimited to the above and shall include all other equipment

which is necessary for the proper functioning of communicationsystem;

b) Coupling devices suitable for 4400 pf CVTs and forphase-to-phase coupling. The pass band of coupling devicesshall have sufficient margin for adding communication channelsin future, if required. Necessary protective devices for thesafety of personnel and low voltage parts and installationsagainst power frequency voltage and transient over voltageswill be provided;

c) Line traps broad band tuned and suitable for blocking

the complete range of carrier frequencies. Linetraps shall have the necessary protective devices such as

lightning arrestors for the protection of running pots;

and

d) Carrier terminals of single side band amplitude modulation

type and 4 kHz band width. The speech channels shall

be suitable for superimposing teleprinter and datasignals. The total transmission time for protectionsignals shall not exceed 20 ms. The carrier frequencies whichare already in operation in the area shall be kept in viewwhile selecting the carrier frequencies for the specified PLCClinks.

Page 88: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-82-

ANNEX 14Page 1 of 4 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Project Cost Estimates

Rs. Million US$ MillionLocal Foreign Total Local Foreign Total

1. 400 kV LINES

A. Ramagundam - Chandrapur(double circuit, 158 km)Preliminary works 9.50 - 9.50 1.00 - 1.00Towers 100.50 33.50 134.00 10.58 3.53 14.11Conductors & Earthwires 72.26 40.64 112.90 7.61 4.28 11.88Insulators & Hardware 12.81 8.59 21.40 1.35 0.90 2.25Accessories 7.50 - 7.50 0.79 - 0.79Miscellaneous 0.70 - 0.70 0.07 - 0.07

Sub-total A 203.27 82.73 286.00 21.40 8.71 30.11

B. Ramagundam - M_angur(double circuit, 230 km)Preliminary works 11.30 - 11.30 1.19 - 1.19Towers 135.90 45.30 181.20 14.31 4.77 19.08Condunctors & Earthwires 105.28 59.22 164.50 11.08 6.23 17.32Insulators & Hardware 18.60 12.50 31.10 1.96 1.32 3.27Accessories 10.80 - 10.80 1.14 - 1.14Miscellaneous 0.70 - 0.70 0.07 - 0.07

Sub-total B 282.58 117.02 399.60 29.75 12.32 42.07

C. Mangur-Vij ayawada

(double circuit, 160 km)Preliminary works 12.20 - 12.20 1.28 - 1.28Towers 74.32 24.78 99.10 7.82 2.61 10.43Conductors & Earthwires 72.13 40.57 112.70 7.59 4.27 11.86Insulators & Hardware 12.09 8.01 20.10 1.27 0.84 2.11Accessories 7.00 - 7.00 0.74 - 0.74'4iscellaneous 0.70 - 0.70 0.07 - 0.07Sub-total C 178.44 73.36 251.80 18.77 7.72 26.49

Page 89: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-83- ANNEX 14

Page 2 of 4 pages

0. Vijayawada-Nellore

(single circuit, 305 km)Preliminary works 9.60 - 9.60 1.01 - 1.01

Towers 88.50 39.50 128.00 9.32 3.11 12.43

Conductors & Earthwires 73.15 41.15 114.30 7.70 4.33 12.03Insulators & Hardware 11.81 8.09 19.90 1.24 0.85 2.09Accessories 7.00 - 7.00 0.74 - 0.74

Miscellaneous 0.70 - 0.70 0.07 - 0.07

Sub-total D 190.76 78.74 269.50 20.08 8.29 28.37

E. Nellore-Redhills(single circuit, 245 kin)Preliminary work 11.80 - 11.80 1.24 - 1.24

Towers 65.47 21.83 87.30 6.89 2.30 9.19Conductors & Earthwires 53.18 37.72 90.90 5.60 3.97 9.57Insulators & Hardware 11.82 7.18 19.00 1.24 0.76 2.00Accessories 6.10 - 6.10 0.64 - 0.64

Miscellaneous 0.70 - _ 0.70 0.07 - 0.07Sub-total E 149.07 66.73 215.80 15.68 7.03 22.78

F. Singrauli-Vindhyachal(single circuit, 14 km)Preliminary works 1.30 - 1.30 0.14 - 0.14

Towers 3.07 1.03 4.10 0.32 0.11 0.43Conductors & Earthwires 3.26 1.84 5.10 0.34 0.19 0.53Insulators & Hardware 0.58 0.32 0.90 0.06 0.03 0.09Accessories 0.30 - 0.30 0.03 - 0.03

Miscellaneous 0.70 - 0.70 0.07 -0 .07

Sub-total F 9.21 3.19 12.40 0.96 0.33 1.29Sub-total 1 1,013.33 421.77 1,435.10 106.64 44.40 151.04Physical Contingencies 52.68 21.92 74.60 5.55 2.31 7.86Price Contingencies 228.89 97.22 326.20 24.11 10.23 34.34TOTAL 1 1,294.99 540.91 1,835.90 136.30 56.94 193.24

2. 400 KV_SUBSTATIONS

A. MangurLand & Colony 74.90 - 74.90 7.88 - 7.88

Structure 3.50 - 3.50 0.37 - 0.37Civil works 6.40 - 6.40 0.67 - 0.67Construction charges 6.20 - 6.20 0.65 - 0.65

Equipment 58.94 8.96 67.90 6.20 0.94 7.14Sub-total A 149.94 8.96 158.90 15.77 0.94 16.72

Page 90: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-84- ANNEX 14

Page 3 of 4 pages

B. Vijayawada

Land & Colony 75.10 - 75.10 7.91 - 7.91Structure 3.60 - 3.60 0.38 - 0.38Civil works 6.90 - 6.90 0.73 - 0.73Construction charges 6.20 - 6.20 0.65 - 0.65Equipment 60.64 8.96 69.60 6.38 0.94 7.32

Sub-total B 1.52.44 8.96 161.40 ]6705 0 T4 1.7p9

C. NelloreLand & Colony 75.10 - 75.10 7.91 - 7.91Structure 3.60 - 3.60 0.38 - 0.38Civil works 6.90 - 6.90 0.73 - 0.73Construction charges 6.20 - 6.20 0.65 - 0.65Equipment 60.64 8.96 69.60 6.38 0.94 7.32

Sub-total C 152.44 8.96 161.40 16.05 0.94 16.99

D. RedhillsLand & Colony 4.10 - 4.10 0.43 - 0.43Structure 1.40 - 1.40 0.15 - 0.15Civil works 2.50 - 2.50 0.26 - 0.26Construction charges 2.30 - 2.30 0.24 - 0.24Equipment 19.10 6.50 25.60 2.01 0.68 2.69

Sub-total D 29.40 6.50 35.90 3.09 0.68 3.77

E. ChandrapurLand & Colony 18.00 - 18.00 1.89 - 1.89Structure 1.80 - 1.80 0.19 - 0.19Civil works 3.20 - 3.20 0.34 - 0.34Construction charges 9.00 - 9.00 0.95 - 0.95Equipment 27.60 13.00 40.60 2.91 1.37 4.28

Sub-total E 59.60 13.00 72.60 6.28 1.37 7.65

F. RamagundamLand & Colony 6.00 - 6.00 0.63 - 0.63Structure 2.50 - 2.50 0.26 - 0.26Civil works 4.10 - 4.10 0.43 - 0.43Construction charges 3.10 - 3.10 0.33 - 0.33Equipment 32.70 - 32.70 3.44 - 3.44

Sub-total F 48.40 - 48.40 5.09 - 5.09

G. SingrauliLand & Colony 2.50 - 2.50 0.26 - 0.26Structure 0.70 - 0.70 0.07 - 0.07Civil works 1.00 - 1.00 0.11 - 0.11Construction charges 1.00 - 1.00 0.11 - 0.11Equipment 10.50 - 10.50 1.11 - 1.11

Sub-total G 15.70 - 15.70 1.66 =

Page 91: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-85- ANNEX 14Page 4 of 4 pages

H. VindhyachalLand & Colony 24.30 - 24.30 2.56 - 2.56Structure 5.50 - 5.50 0.58 - 0.58Civil works 7.80 - 7.80 0.82 - 0.82Construction charges 13.00 - 13.00 1.37 - 1.37

Equipment 147.00 - 147.00 15.47 - 15.47

Sub-total H 197.60 - 197.60 20.80 - 20.80

Sub-total 2 805.52 46.38 851.90 84.79 4.87 89.66Physical Contingencies 40.28 2.32 42.60 4.24 0.24 4.48Price Contingencies 255.52 14.98 270.50 26.95 1.58 28.53TOTAL 2 1,102.32 63.68 1,165.00 115.98 6.69 122.67

3. BACK-TO-BACK HVDC VINDHYACHALSubstation (land structure 79.53 733.92 813.45 8.37 77.25 85.62etc. included under ACportion of the substation)Physical Contingencies 3.98 37.92 41.90 0.42 3.99 4.41Price Contingencies 25.69 244.71 270.40 2.70 25.76 28.46TOTAL 3 109.20 1,016.55 1,125.75 11.49 107.01 118.50

4. METERING & INSTRUMENTATIONEquipment 88.55 113.05 201.60 9.32 11.90 21.22Physical Contingencies 4.43 5.67 10.10 0.47 0.60 1.07Price Contingencies 20.25 25.85 46.10 2.13 2.72 4.85TOTAL 4 113.23 144.57 257.80 11.92 15.22 27.14

5. PLCC COMMUNICATIONSSystem - 39.47 39.47 - 4.15 4.14Physical Contingencies - 1.97 1.97 - 0.21 0.21

Price Contingencies - 2.76 2.76 - 0.29 0.29TOTAL 5 - 44.20 44.20 - 4.65 4.65

6. CONSULTANCY - 23.75 23.75 - 2.50 2.50

7. ENGINEERING & ADMINISTRA- 297.45 - 297.45 31.31 - 31.31TION

8. TOTAL PROJECT COST (BEFOREDUTIES & TAXES) 2,916.19 1,833.66 4,749.35 307.00 193.00 500.00

9. DUTIES & TAXES 617.50 - 617.50 65.00 - 65.00

10. TOTAL PROJECT COST 3,533.69 1,833.66 5,367.35 372.00 193.00 565.00

11. INTEREST DURINGCONSTRUCTION 490.31 - 490.31 51.58 - 51.58

12. FRONT-END FEE - 6.65 6.65 - 0.70 0.70

13. TOTAL FINANCING REQUIRED 4,024.00 1,840.31 5,864.31 423.58 193.70 617.28

Page 92: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-86-

U W if _ _ -oz _ t = 'i ------ ------ --------- -

XX L

e4 X O

4-J

o 4

~~ __ I

~~~ -3 2_ X_ _ _ E_ ' _ _i i % R %

Page 93: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-87-

ANNEX 16

INDIA

CENTRAL POWER TRANSMISSION PROJECT

ESTIMATED SCHEDULE OF DISBURSEMENTS

IDA Fiscal Year Cumulative US$

and Half-Year Million Equivalent % Undisbursed

1983

June 1983 - 100.0

1984

December 1983 3.5 98.6

June 1984 8.0 96.8

1985

December 1984 20.0 92.0

June 1985 55.5 77.8

1986

December 1985 90.0 64.0

June 1986 150.0 40.0

1987

December 1986 180.0 28.0

June 1987 227.5 9.0

1988

December 1987 240.5 3.8

June 1988 245.0 2.0

1989

December 1988 250.7

Page 94: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

NATIONAI THERMAL POWER CORPORATEON LIMITED

Schedule of Commissioning of Power Plants and Power Generation

'lersue

Schedule at Time of Second Ramagundam Appraisal (.January 1981)

FY1982 FY1983 FY1984 FY1985 FY1986 FY1987 FY1988 FY1989 FY1990 FY1991 FY1992 FY1993 FY1994 FY1995 FY1996Sate Date a Date a Date a Date * Date * Date Date a Date Dare Date * Date * Date R Date * Date *

Sigrauli I - 200 MW Units Feb 82- Oct 82 2 Aug 83 -- 200 MW Units Feb 83 - Feb 84 -

SingrauJ.i II - 500 MW Units Fob 87 5 Feb 88 5Korba I - 200 MW Units Jan 83 - Jul 83 -

200 MW Units Jan 84 -

Korba II -500 MW Units Jun 87 6 Jun 88 6 Jun 89 6Ramagundam I - 200 MW Units Feb 84 - Aug 84 -

- 200 MW Units Feb 85 -Ramagundam II - 500 MW Units Dec 87 3 Dcc 88 3 Dec 89 3

Farakka I - 200 M'' Uinits Jan 85(2) Jul 85 (2)200 MW Units Jon 86 (7)

Faral.ka It - 500 MW Units Apr 89 12 Apr 90 12 Apr 91 I'll

Rihand - 500 MW Units Jun 87 - Jun 88-Vindhyachal - 210 MW Units Jun 87 - Jun 88 - JuMn 89 -

- 210 MW Units Dec 87 - Dec 88 - Dec 89 -Projects 0ou yet Identified Mar 93- Oct 93 - Oct 94 - Oct 95-

- 500 MW Units Mar 94 - Mar 95 -TOTAL NTPC COMMISSIONING

Currently Scheduled:

Units - Fiscal Year 1 3 5 3 2 1 6 5 5 1 1 I 2 2 1 L- To date 1 4 9 12 14 15 21 26 31 32 33 34 36 38 39

MW Capacity - Fiscal Year 200 600 1,000 600 400 500 2,420 1,920 1,920 500 500 500 1,000 1,000 500- To date 200 800 1,800 2,400 2,800 3,300 5,720 7,640 9,560 10,060 10,560 11,060 12,060 13,060 13,560

Scheduled at Rama&undam

Appraisal:Units - Fiscal Year 1 3 5 3 2 2 3 3 3 1 - - -

- To date 1 4 9 12 14 16 19 22 24 25 25 25 25 25 25MW Capacity - Fiscal Year 200 600 1,000 600 400 1,000 1,500 1,500 1,000 500 8,300 8,300 8,300 8,300 8,300

-ToI US 200 800 1,800 2,400 2,800 3,800 5,300 6,800 7,800 8.300 8,300 8,300 8,300 8,300 8,300CURRENT SCHEDUtiE VRiSRAMAGUNDAM APPRAISAL

Capacity Increase/(Decrease)at FY Year End Due To:Additional Projects (MW) - - - - 920 1,840 2,260 2,260 2,260 2,760 3,760 4,760 5,260Commissioning Slippage (MW) - - - - _ (500) (500) (1,000) (500) (500) - - -

Power Generation (GWh) TOTAL.Increase/(Decrease) Due To: FY 1982-84Additional Projects - GWlI - - 1,758 5,538 9,223 11,858 12,430 12,534 14,575 67,916

% - - - - - - 9 20 27 29 28 28 32 23Commissioning Slippage Offsetby Earlier Stahilication - tlOll - 114 992 1.7.3 1.802 208 (1,646) (3,438) (3,816) (2,980) (1,396) (396) - 8,73 w

N - 10 27 24 16 1 (8) (13) (11) (7) (3) (1) - (3) xTotal Generation Iocrease/

(Decrease)- GWh - 114 992 1,783 1,802 208 112 2,100 5,407 8,878 11,034 12,138 14.575 59,143% - 10 27 24 16 1 1 7 16 22 25 27 32 20

late:* No. -soths later/(earlier) than schedolled at Ramalandao Appraisal

S-L-ce: NTPC October 1982

Page 95: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRIL POWER TRANSMISSION PROJECT

NATIONAL THERMAL POWER CORPORATION LIMITED

INVESTMENT PROGRAM FOR THE PRJIOD FY1977 THROUG. FY1996

(Rupees Million)

Year ending March 31st FY1977 FY1978 FY1979 PY1980 FY1981 FY1982 FY1983 FY1984 FY1985 FY1986 FY1987_FY1988 _FY1989 FY1990 FY1991 FY1992 FY1993 FY1994 FY1995 FY1996 Total

POWER STATION8

SINGRAULI 7 197 296 746 838 1,276 878 2,417 2.191 2,019 930 303 - - - - - - - - 12,098

XORBA - 16 281 303 635 1,131 2,377 1,541 2,581 2,934 2,427 1,491 619 41 - - - _ _ _ 16,377

RAMAGUNDAM - - 50 363 345 1,008 1,800 2,457 2,064 4,531 2,789 2,255 1,005 364 - - 1-,031

PARAKXA - - 4 94 363 496 647 1,950 2,735 2,313 2,537 3,140 3,498 1,531 1,014 557 _ _ _ _ 20,879

VINDHYAC{A1 - - - - - - 16 930 1,771 3,064 3,448 2,700 1,331 227 - - 1 - - 3,597

RIHAND _ _ _ - 579 1,323 2,933 3,372 2,699 1,824 9.82 - - - - - - 13,712

UNIDENTIFIEDNEW PROJECTS - - - - _ _ _ _ _ _ - 1,123 4,132 6.052 9.809 9,351 6.262 3,546 2,116 590 42,981

TOTAL 7 213 631 1,506 2,181 3,911 6,407 10,618 14,275 18,233 14,830 12,836 11,567 8,215 10.823 9.908 6,262 3,546 2.116 590 138.675

TRANSMISSION WORKS

SINGRAULI _ 12 68 115 149 79 822 836 906 210 - - - - - - - - - - 3,197

KORBA _ - - 32 157 177 206 671 476 362 115 - - - - - - - - - Z146

RAMAGUNDPM _ - - 3 39 255 260 1,114 1,456 578 345 7 - - - - - - - - 4,057

FARiKA - - - - 1 6 111 367 408 315 337 242 35 - - - - _ _ _ 1,822

VIND4YACKAL - _ _ - _ - 5 203 807 1,059 909 313 55 - - - - - _ - 3,351

CENTRAL TRANSMISSION _ -_ _ _ 35 459 1,738 2,581 913 138 - - - -5864

TOTAL - 12 68 150 346 517 1,439 3,650 5.791 5.105 2,619 700 _ 90 - - - - - 20,487

GRAND TOTAL 7 225 699 1,656 2,527 4,428 7.846 14.268 20,066 23,338 17,449 13,536 11.657 8,215 10,823 9,908 6,262 3,546 2,l16 590 159,162

(Includes interest during -nulructinn)

Source: NTPC October 1972

Page 96: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-90-

C E ANNEX 19

C� 0CC)-.)).� CCC. <CC CC C CitC C -8-� I I I I

C C-,C CC CCCo o -CC C C

CCCL C�t� CCLCL� CLC�C I I I II I

C)CLECL CCC CCC

CCCLI C i I

OCICLI �

CC-. CCL - I

�SCCL CC> CCLV I I di

OCOCI CCII III

CL C CC

CL -CCCL CCCC CL

I I II

CL CL CCLC C-C ICL CL CL CCLC .0--C

F CL C C- 0 C�-C. CCCL CC CL�-�CL C 0 CCL CL C C CC 0CC CCC -,CCL

CC CCC CCC CCCL -CC C - CCH C C CLI-CL CCC) CCLC 0CC

-� I-C-- - ---- I-

I- CC CCC CCCL 0CC C� CCLC C C CCCL C C

00< C - C - CI CC CL

CLI C) - C C C

C C . 0CC CCLC CLCC CCCLC-CC CCCL 0CC) CLH.CC CL

CL CCLC. CCLC CCCL 0CC) II HC- II I I I CLCF-CL

C CI C CL 0CC <CC CCC) CL C CL

C C. FHC 00 CL - CL CL CL CL C I CL CL CL

<I CCCL CCC CCLC CCC000 0CC CLCLC -C-CC

0CC. 0CC) CCCL CCC I I CCC) II] II I I C

CCC CCCL CCCL CL C CLCL C CL .-. CL CL CL

CLI CL CL

CCC CLCC CCCL CCC CCCC CCC CCC CCC

CCC. 0�-,C CCC) CCC CCLC I I II .11 I I C

CC- -CCC CCC C C C

0CC CCCL CLCC C)CCCCCL C-C CC-C

CC0) CCC -0CC CCLCC. CCL C

-C CCL I -C<C CL CL CL[CL

C

CCC CCC CCC CCCL CLCC-C CCCL CC 000CCCL 0CC CCCL CC-C III II I I I C

C C CL 0CC C-.C CC-C C C CL

00 CL CL CL C C CL -C

CL H CCC CCC CCLC 0CC CC C' CCC COO CC

1C C-CO I I I I I I I I C

C C. C-C -CCCL CCC) CCCL I IC. I-CLCLI -

0CC C C.-C- OCIC 0

NJ CCCL �CCC.�CL4 COC CCC II I I I I I I C

CL C

C C.

C CL CC CL�C C VC CC) C CC - C CL 00 CL CL C

C C C CL CLC C - - C C C C C C C CC C

CL C C C C C C C CL C C C S-H C -H S -� -- C C C C CC CLC C.C C CC. C 'C C C C C CC C CC H

�CLCH C CCL CC - 'CC C.CL CC- CL .- ICLCC C -C�r CCLCCL C�C2 C-H C�CC NC CL CL

C CC CC C CC C CC C ICC CCC CL C C I- S CLI-OH CCL CC-H CC CCCH CC CC. CC CCC CCL CCL C., CC-CC-CL- C .20CLCCLCC CC.-SCC CCHCC CC�CC COCLCC CC�ICC CLC.�.C C <CLCOOC-. C.CCC.-I CCCCC C.CCCCI C.CCC� CCCC- COCCI-- CC CL F-C)CCCC.C CCCC.C CC<C.C CCL.-C.C CCCLI-C CLCC CC.�I-C CC CL 00 CCL--CF-.F-I CL'CCICH CLCF-.F-. CL--CLF-H ->CF-.H CCLF-'I- >-CLHH CCL CL F-.C-

- . . - - - - - - C) C

CL C C -C C CL C CL C - CL

Page 97: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PFOJECT

NATIONAL THERMAL POWER CORPORATION LIMITED

STATEMENT OF PLANT CAPACITY, GENERATION AND SALES OF ENERGY

Year ending March 31st FY1982 FY1983 FY1984 FY1985 FY1986 FY1987 FY]988 FY1989 FY1990 FY1991 FY1992 FY1993 FY1994 FY1995

CAPACITY (MW)

Singrauli 200 600 1,000 1,000 1,000 1,500 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000Korba 0 200 600 600 600 600 1,100 1,600 2,100 2,100 2,100 2,100 2,100 2,100Ramnagundam 0 0 200 600 600 600 1,100 1,600 2,100 2,100 2,100 2,100 2,100 2,100Farakka 0 0 0 200 600 600 600 600 1,100 1,600 2,100 2,100 2,100 2,100Vindhyachal 0 0 0 0 0 0 420 840 1,260 1,260 1,260 1,260 1,260 1,260Rihand 0 0 0 0 0 0 500 1,000 1,000 1,000 1,000 1,000 1,000 1,000Unidentified New Projects 0 0 0 0 0 0 0 0 0 0 0 500 1,500 2,500

TOTAL 200 800 1,800 2,400 2,800 3,300 5,720 7,640 9,560 10,060 10,560 11,060 12,060 13,060

GENERATION (GWh)

Singrauli 83.0 1,082.0 3,213.0 4,981.0 5,500.0 5,708.0 7,083.3 8,958.3 10,166.7 11,000.0 11,000.0 11,000.0 11,000.0 11,000.0Korba 0.0 124.0 1,371.0 2,846.0 3,300.0 3,300.0 4,341.7 6,216.7 8,633.3 10,508.3 11,425.0 11,550.0 11,550.0 11,550.0Ramagundam 0.0 0.0 83.0 1,215.0 2,781.0 3,300.0 3,716.7 5,216.7 7,383.3 9,633.3 11,050.0 11,550.0 11,550.0 11,550.0Farakka 0.0 0.0 0.0 124.0 1,371.0 2,846.0 3,300.0 3,300.0 4,550.0 6,550.0 9,050.0 10,800.0 11,550.0 11,550.0Vindhyachal 0.0 0.0 0.0 0.0 0.0 0.0 716.0 2,621.0 4,931.0 6,525.0 6,930.0 6,930.0 6,930.0 6,930.0Rihand 0.0 0.0 0.0 0.0 0.0 0.0 1,041.7 2,916.7 4,291.7 5,333.3 5,500.0 5,500.0 5,500.0 5,500.0Unidentified New Projects 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 104.2 2,145.4 7,019.9

TOTAL 83.0 1,206.0 4,667.0 9,166.0 12,952.0 15,154.3 20,199.4 29,229.4 39,956.0 49,549.0 54,955.0 57,434.2 60,225.4 65,099.9

STATION USE (GWh)

Singrauli 7.5 97.4 289.2 448.0 495.0 513.8 637.5 806.2 915.0 990.0 990.0 990.0 990.0 990.0Korba 0.0 11.2 123.4 256.1 297.0 297.0 390.8 559.5 777.0 945.7 1,028.3 1,039.5 1,039.5 1,039.5Ramagundam 0.0 0.0 7.5 109.4 250.3 297.0 334.5 469.5 664.5 867.0 994.5 1,039.5 1,039.5 1,039.5 -Farakka 0.0 0.0 0.0 11.2 123.4 256.1 297.0 297.0 409.5 589.5 814.5 972.0 1,039.5 1,039.5 0 0Vindhyachal 0.0 0.0 0.0 0.0 0.0 0.0 64.4 235.9 44'3.8 587.3 623.7 623.7 623.7 623.7Rihand 0.0 0.0 0.0 0.0 0.0 0.0 93.7 262.5 386.3 480.0 495.0 495.0 495.0 495.0Unidentified New Projects 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 9.4 193.1 631.8

TOTAL 7.5 108.6 420.1 825.0 1,165.7 1,363.9 1,817.9 2,630.6 3,596.1 4,459.5 4,946.0 5,169.1 5,420.3 5,859.0

Page 98: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

FY1982 FY1983 FY1984 F'Y1985 FY1986 FY1987 FY1988 FY1989 FYl990 FY1991 FY1992 FY1993 FY1994 FY1995

ENERGY SENT OUT (GWh)

Singrauli 75.5 984.6 2,923.8 4,532.7 5,005.0 5,194.6 6,445.8 8,152.1 9,251.7 10,010.0 10,010.0 10,010.0 10,010.0 l0,010.0

Korba 0.0 112.8 1,247.6 2,589.9 3,003.0 3,003.0 3,950.9 5,657.2 7,856.3 9,562.6 10,396.8 10,510.5 10,510.5 10,510.5

Ramagundam 0.0 0.0 75.5 1,105.6 2,530.7 3,003.0 3,382.2 4,747.2 6,718.8 8,766.3 10,055.5 10,510.5 10,510.5 10,510.5

Farakka 0.0 0.0 0.0 112.8 1,247.6 2,589.9 3,003.0 3,003.0 4,140.5 5,960.5 8,235.5 9,828.0 10,510.5 10,510.5

Vindhyachal 0.0 0.0 0.0 0.0 0.0 0.0 651.6 2,385.1 4,487.2 5,937.7 6,306.3 6,306.3 6,306.3 6,306.3

Rihanad 0.0 0.0 0.0 0.0 0.0 0.0 947.9 2,654.2 3,905.4 4,853.3 5,005.0 5,005.0 5,005.0 5,005.0

Unidentified New Projects 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 94.8 1,952.3 6,388.1

TOTAL 75.5 1,097.4 4,171.4 8,341.0 11,786.3 13,790.5 18,381.4 26,598.8 36,359.9 45,090.4 50,009.1 52,265.1 54,805.1 59,240.9

TRANSMISSION LOSS (GWh)

Singrauli 1.9 24.6 73.1 113.3 125.1 129.9 161.1 203.8 231.3 250.3 250.3 250.3 250.3 250.3

Korba 0.0 2.8 31.2 64.7 75.1 75.1 98.8 141.4 196.4 239.1 259.9 262.8 262.8 262.8

Ramagundam 0.0 0.0 1.9 27.6 63.3 75.1 84.6 118.7 168.0 219.2 251.4 262.8 262.8 262.8

Farakka 0.0 0.0 0.0 2.8 31.2 64.7 75.1 75.1 103.5 149.0 205.9 245.7 262.8 262.8

Vindhyachal 0.0 0.0 0.0 0.0 0.0 0.0 16.3 59.6 112.2 148.4 157.7 157.7 157.7 157.7

Rihand 0.0 0.0 0.0 0.0 0.0 0.0 23.7 66.4 97.6 121.3 125.1 125.1 125.1 125.1

Unidentified Neu Projects 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.4 48.8 159.7

TOTAL 1.9 27.4 106.2 208.4 294.7 344.8 459.6 665.0 909.0 1,127.3 1,250.3 1,306.8 1,370.3 1,481.2

ENERGY SALES (GWh)

Singrauli 73.6 960.0 2,850.7 4,419.4 4,879.9 5,064.7 6,284.7 7,948.3 9,020.4 9,759.8 9,759.8 9,759.8 9,759.8 9,759.8

Korba 0.0 110.0 1,216.4 2,525.2 2,927.9 2,927.9 3,852.1 5,515.7 7,659.9 9,323.5 10,136.8 10,247.7 10,247.7 10,247.7

Ramagundam 0.0 0.0 73.6 1,078.0 2,467.4 2,927.9 3,297.6 4,628.5 6,550.9 8,547.2 9,804.1 10,247.7 10,247.7 10,247.7

Farakka 0.0 0.0 0.0 110.0 1,216.4 2,525.2 2,927.9 2,927.9 4,037.0 5,811.5 8,029.6 9,582.3 10,247.7 1(1,247.7 7

Vindhyachai 0.0 0.0 0.0 0.0 0.0 0.0 635.3 2,325.5 4,375.0 5,789.3 6,148.6 6,148.6 6,148.6 6,148.6

Rihand 0.0 0.0 0.0 0.0 0.0 0.0 924.2 2,587.8 3,807.8 4,732.0 4,879.9 4,879.9 4,879.9 4,879.9

Unidentified New Projects 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 92.4 1,903.5 6,228.4

TOTAL 73.6 1,070.(1 4,140.7 8,132.6 11,491.6 13,445.7 17,921.8 25,933.7 35,451.0 43,963.3 48,758.8 50,958.4 53,434.9 57,759.8

Station use as % of generation FY1982 - FY1995 - 9.00%

Transmission losses as % of generation FY1982 - FY1995 - 2.28% (2.5% of energy sent out).

Source: NTPC October 1972

Page 99: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-93-

INDIA ANNEX 21

CENTRAL POWER TRANSMISSION PROJECT

NATIONAL THERMAL POWER CORPORATION LIMITRD

INCOME STATRMKNT COVERING OPERATIONS FY1983 THROUGH PY1995(Rupees Million)

Year ending March 31st Fl983 PY1984 Y19835 EY1986 FY1987 FY1988 PY1989 FY1990 PYI991 FY1992 PY1993 FY1994 FY1995

TOTAL SALE OF ENERGY (atl) 1,070 4,141 8.133 11,492 13,446 17,922 25,934 35,451 43,963 48,759 30,958 53,435 57,760

REVENUE - SULK SUPPLY (PAI1S/1W) 32.24 33.93 36.22 38.47 39.90 40.49 41.32 42.60 43.94 45.25 46.47 48.48 48.62

Fuel Surcharge - 0.72 1.39 2.01 2.66 3.11 3.58 4.25 5.08 6.03 7.02 7.83 8.33Central EBine (Pa"/K) 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80

OPERATING REVENUE

Sales - Bulk Supply 345 1,405 2,946 4.421 5,365 7.257 10,715 15.103 19,317 22.080 23.678 25,372 29,081Salon - Fuel Sur-har-g - 30 113 231 358 557 928 1,506 2,234 2,938 3.575 4,182 4,809Central Euciee 20 76 151 212 249 331 479 655 812 901 939 1,011 1,066

TOTAL OPERATINGO REVKNUE 365 1.311 3,210 4,864 5,972 8,145 12,122 17,264 22,363 25,919 20,192 30,565 33,956

OPERATING EXPENSES

Singrauli - Furl 87 259 401 443 460 569 717 812 878 878 979 870 878- Fuel Snroh-rge 22 69 115 154 236 359 479 602 691 793 88 991- 0 68 R 58 97 115 111 128 205 265 265 265 265 265 265- DeFreciation 56 102 143 143 143 264 375 375 375 375 375 375 375

Korhb - Fuel 8 93 193 224 224 294 421 584 711 773 782 782 782- Fuel Sercharge 8 33 58 78 126 217 354 499 621 713 803 898-3 4 1 14 76 95 95 95 168 238 330 346 346 346 346 346- Depreciarion 70 118 118 118 118 253 356 508 508 100 5008 508

Ranagu-dam - Furl 9 132 302 359 404 566 801 1,045 1,199 1,253 1,253 10253- Fuel Surcharge 11 49 87 128 224 384 594 794 910 1,088 1,228- 2 6 n 12 93 125 125 164 271 357 406 406 406 406 406- Depr-ciation 92 155 155 155 335 476 590 590 590 590 590

F-rakka - Fuel 11 127 263 305 303 432 604 634 995 1,065 1,065- Fuel Surcharge 9 39 67 89 155 273 450 629 777 887- 0 & 9 19 115 155 155 155 245 353 353 353 353 353- Depreciati.n 94 193 193 193 193 331 500 647 647 647

Vindhyachal - Furl 83 304 572 757 804 804 804 804- Fuel Surcharge 18 71 145 211 272 336 405- 04M 122 231 310 340 340 340 340 340- Depr-ciatiu' 215 353 422 422 422 422 422

Rihand - Fuel 124 346 509 633 652 652 652 652- Fuel Surcharge 21 63 121 171 221 273 329- 049M 115 251 274 274 274 274 274 274- Depr-ciation 213 415 415 415 415 415 415

niddentified3on Project - Fuel 17 341 1,115

- Fuel SuSrh-rge 27 71- 0 6M 12 223 350- Depr-ciati-n 216 653

Trucsuinsion - 0 & M 2 6 12 27 40 60 70 73 73 73 73 73 73

- Depreciati-n 2 21 34 120 170 282 348 380 380 380 380 380 380

Ceutrul Tcaenniuulees Prciect 3 22 30 30 30 30 30 30 30

- DNpreciatiun 66 153 153 153 153 153 153 153

Central Euele @ 1.8 P/RWh gcneruted 20 76 151 212 249 331 479 654 812 900 941 1,011 1,066

YOTAL OPERATING EXPENNES 197 812 1,704 2,646 3,225 4,678 7,602 10,423 12,935 14,408 15,486 16,984 19,159

OFERATING INCOME (BeEfre Interest) 168 669 1.506 2,218 2,747 3,467 4,520 6,840 9,428 11,510 12,708 13,581 14,797

Less Interest cn Loan 575 1,067 2,134 3,620 4,957 3,730 6,259 6,053 5,686 5,224 5,824 6,366Seduce: InterestrcapitaliRed 202 237 452 1.038 2,126 2.357 1,69 765 271- - -Net I-ureet Chargeahbl to Operut-ios 91 318 614 1,117 1,499 2,500 4,035 5,494 5,782 5,824 4,484 7,757 8,431Frofit: 77 381 892 1,101 1,248 967 485 1,346 3,346 5,824 7,484 7.757 8,431-

Def-rred Expe.ue Written off 32 - - - - - - - -

Net Eanings 45 381 892 1,101 1,248 967 485 1,346 3,346 5,024 7,484 7,757 8,431

Average fixed acets tn use 3,471 9,320 16,405 22,667 29,870 51,024 76,348 91,488 99,232 101,077 103,518 110,447 120,845

Rate of Recurn (Op-ratieg iccee 4.8 7.5 9.2 9.9 9.2 6.8 5.9 7.5 9.5 11.4 12.3 12.3 12.2bofre interest as I of average net

fixed assets ia use).

Adj-sted Nate of Esters 2., - 11.4 12.4 11.1 10.7 8.0 8.5 9.9 11.2 - - -

Operating Matit (Operating onpenses 53.9 53.7 53.1 54.4 53.8 57.4 62.7 60.4 57.8 55.6 54.9 55.6 56.4an Z of cpet-ticg revenue)

1/ Detenei.ed en the bhees ef:(i) assets i.u en edjuoted by CpplyiYe to unit i-vest-eet rests, the retio of the -sb-e of =neths following

tnebh of toe.stsslniDg e the total -nethe In par (12);(i) unit sales (GVh) adjusted by spplying the rati deteened iR (i) sbove, to unit seine of oebh geDer-tin6

unit ssosi- g operetin 't full stabilieed gee..rting capacity;(iii) revenue ad op=ratint sepenses edjnted te reflect adjusted nntes end nit .. Ies on raluulatnd In (i) and (ii)

above.

SOURC: RIITP October 1972

Page 100: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-94-A19NEX 22

0 '0' '0 4004< 440104 "'4'" �'40 44 404404404 " -, 04 04 4- 04 40444 4') 44 04

2 <#-� 04. -4 '0 '02 2 -�

- '0 0 0 '0 '0 044". '0 '0 4"04 00 44 00 04 41 4'. 44-4 04 04 0404 '44 4" I 0 04 4'40 I -

0 4' 04 "' �"' 04 444 '00 4" -

"0 - 00 '4 44

0' � '0�4 04' '0-0'

04 0 04 04 I F 04 40 N N'0 . - 0

40 40 04 '0 '0

0 0" '0 �04 04 '0 '00 04 0404� - '0 444" 40 o 04 4440 44' '404 '0 4 4 � 0 0 4j '0 04'0

.4404-0444 444 '4'

04 '0 N 0400 40 4404 -4 '0

04 40 00 04'0 04 04004 '0 '0 '044 0 0404- 04 04 40 0 44 44 400040 44

00 o -<00-4.440 '0 '0 0, '0 004 '0 04�40 400 04 4440404 CC 40 � 04'- o o.-� 04

44 '0 40 0' 4004 '0

04 0 44 444 040 0 44' 444 '440� 444!'0"'0 04 00004 '440404044 0004 '0

0 40 '0 '004 '0 '0 '0

04 " 00 '44 '00 '0 '0 '0 '040 0 '000 '0 00040 0 44.0

'04 04 '0 0 '0 0444 444 '004

04 0' 44-40404 0

44' I04 -4 0 04 '0 0444 04 04 04 4404-4 04 '0 044400- 04 004-4 04 -4 0 '440< '0 040 440, 44 4 4 4

0 04 N 44 44 04 N

'0 00 000 N04 04 04 N '044 0 0404 44 0400000 04 - 40< 4" 004 0 '0 00 '0N N� 04 - 440 44 N 44

0' '0 04 00 44 '0 4040 40 44

04 444 '044-44 444'04'9 40 2 .2204 -44 04 00 0444 '0 0 '0 04 '0 04

00 0 0000 0' - 44 0 44 4040 40 0

0'00'

'0 44 00 00 00 04 000 04 040404440 '0 44 '0 04 '0'0 04 40 04 04 I I N 04 00

� 2 '0 '0 '0 40

-4 00

2 44 00 0440 4440440 '0 00 '004 '0 444 40 00 44 '0 04 100 I 44 -444 40 .4404 0 00 04 0

40 '004 00 4' 00 44

'� $42 $4 4 44412 04 44 '0 04

04 04040 0 04 00 '004 4 4 I 004 ,, 04 . 4 4 44 4'0, '00 444 '0 '-4 '0

2 400 40 -44

111400 00 III $4 $4

-04

-000 00 00 4" 04 0

04 I I I � 04 I I - I 44

N - <'0 44 44 40 -0'04 I I-, 44040 40 4 .I - '44 404440' 40 40

04 I . 4 0 '0 I I 441 '00404' 04 44

,0'

0 '00 4-4

2 o 440 40040 044 44 04 0 40 0

040 40 '0 4-4 04414 4404 0 0 404049 0'� 2 �4 '0 44 00 14 0 0-40 00

�400 0940 49 0 0 0'444 144 40 000 49 40 C 04 40""' -'40 4" 0 '-4 '� 4900440 4

44 144 .- 4' 4014 04414040 40040 '44 14 144000 0404. 40 401444 0 04 0004 '4400-0400 "ii044 04 00 000 040 04,

000 40400, -4 400 . 14>044-4404-014 00 040 44014 <-0 j - 1404:004-4014014 00.0044�4 400 '0 44000440040490 0'

40000 4400 40 0 0 04414 '0044 44044400 44 ,- 04-0 0044 0'

Page 101: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

NATIONAL THERMAL POWER CORPORATION LIMITED

BALANCE SHEETS FY 1977 THROUGH FY 1995(Rupees Million)

Year ending March 31st FY1977 FY1978 FY1979 FYL980 FY1981 FY1982- fFY1983 FY1984 FY1985 FY1986 FY1987 FY1988 FY1989 FY1990 EY1991 FY1992 PY1993 FY1994 FY1995

ASSETS

Gross Fined Assets 4 23 88 219 436 686 6,313 12,636 21,064 26,176 36,880 70,341 90,090 105,986 111,433 116,194 123.148 137,248 151,792(Historic Cost)Less Depreciation - - - 8 251 638 1,268 2,047 3,125 5,210 7,891 11,065 14,408 17,898 21,604 25 ,747Net Fined Assets in Use 4 23 88 219 436 686 6,255 12,385 20,426 24,908 34,633 62,216 84.880 98,095 100,368 101.7R6 105.250 115,644 126.045Work-in-Progress 3 209 844 2,369 4,678 8,856 11,075 19,020 30,658 48,884 55,629 35,704 27,612 19,931 25,307 30,454 29,762 19,208 6,780Total FPxed Assets 7 232 932 2,58S 5,114 9,542 17,330 31,405 51,084 73,792 90,462 102,920 112,492 118,026 125,675 132,240 135,012 134,852 132,825Short Term Deposits - - - - - - - -- - - - 361 3,864 9.904

CURRENT ASSETS

Cash 23 31 42 67 L36 28 3 6 11 13 19 35 45 53 56 58 62 69 76Receivables - - 10 21 59 85 29 117 246 368 447 605 893 1,259 1.610 1,840 1,973 2,115 2,290Inventories - - 1 6 11 58 60 126 211 262 369 703 901 1,060 1,114 1,162 1.232 1,372 1,518Other Debtors 2 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2Total Current Assets 25 32 54 95 207 172 94 251 470 645 837 1,345 1,841 2,374 3,036 3,378 3,644 3,997 4,441Deferred Expenses 2 3 5 11 19 32 - - = _ - -

TOTAL ASSETS 34 267 991 2,694 5,340 9,746 17.424 31,656 51,534 74,437 91,299 104,265 114,333 120,400 128,457 135,302 139,642 142,274 146,615

EQUITY 6 IIABILITIES

EQUITY

Share Capital - Issned 12 258 968 2,591 4,628 7,850 11,775 22, 797 36,371 44,650 47,10 50,117 53,681 57,426 63,995 63,995 63,995 63,995 63,995Share Deposits 22 - - - - - -Retained Earnings - - - - - - 45 426 1,318 2,419 7 4,634 5,119 6 465 10,111 15,935 23,419 31,176 39,607

A QUITY 34 Y598 968 I 1 4,628 7,850 11,820 23,223 37,889 47,069 50,777 54,751 58,800 63.891 74,106 79.930 87,414 95,171 103,602

LIABILITIES

Loans - 479 1.080 5,185 7,618 13,781 27,239 40,362 49,280 55,173 56,000 53,696 54,724 50,506 46,288 42,070Current Liabilities _ 8 23 103 233 _816 419 815 84 129 160 234 360 509 655 756 830 923 1,051

TOTAL EQUITY & LTABI1ITIES 34 266 991 2,694 5,340 9,746 17,424 31,656 51,554 74,437 91,299 104,265 114,333 120,400 128,457 135,302 138,642 142,274 146,615

Debt - Equity Ratio - - - 9/91 12/88 30/70 25/75 27/73 37/63 44/56 47/53 48/52 47/53 42/58 41/59 37/63 33/67 29/71

1/ Audited Accounts

Source: NTPC October 1982

Page 102: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-96-

ANNEX 24Page 1 of 6 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

National Thermal Power Corporation Ltd.

Assumptions for Financial Projections

1. The financial statements in this report display NTPC's financialoperations for the period FY1977 through FY1995. They comprise incomestatements (Annex:es 21, and 25 to 28), with supporting statement of plantcapacity, energy generation and sales (Annex 20), source and application offunds (Annex 22), with supporting investment program (Annex 18), andsummarized balance sheets as at March 31 of each year (Annex 23).

2. Projections for FY 1983 throught FY 1995 are based on the followingassumptions:

(a) Commissioning of generating plant as reflected in Annex 17.

(b) Energy Output

200 MW Units - First 6 months: 2,500 hours operation- Next 6 months : 4,000 hours operation- Second year : 5,500 hours operation

500 MW Units - First Unit Commissioned at Each Station- First year : 2,500 hours operation

- Second year: 4,000 hours operation- Third year : 5,000 hours operation- Fouth year : 5,500 hours operation

500 MW Units - Subsequent Units of Each Station- First year : 2,500 hours operation- Second year: 4,000 hours operation- Third year : 5,500 hours operation

Page 103: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

ANNEX 24

Page 2 of 6 pages

(c) Fuel Cost (Basic) Escalation

Singrauli - Based on 0.600 kg/kWh and )0.589 kg/kWh, for 200 and )500 MW respectively, at )Rs. 127.87/ton in FY 1983 )

Korba - Based on 0.666 kg/kWh and )0.665 kg/kWh, for 200 and )500 MW respectively, at ) FY1982 - 10.0% p.a.Rs. 96.88/ton in FY 1983 ) FY1983 - 8.5% p.a.

FY1984 - 8.0% p.a.Ramagundam- Based on 0.542 kg/kWh and ) FY1985 - 7.5% p.a.

0.541 kg/kWh, for 200 and ) FY1986 - 7.0% p.a.500 MW respectively, at ) FY1987Rs. 175.95/ton in FY 1983 ) Onwards- 6.0% p.a.

Farakka - Based on 0.729 kg/kWh and )0.728 kg/kWh, for 200 and )500 MW respectively, at )Rs. 102.86/ton in FY 1983 )

Rihand - Based on 0.590 kg/kWh for )500 MW, at Rs. 134.03/ton )in FY 1983 )

Vindhyachal- Based on 0.577 kg/kWh for )210 MW, at Rs. 134.03/ton )in FY 1983 )

An additional 5% is added to cost for fuel oil needed forstarting and for low load operation, plus tax of Rs. 5 perton.

(d) Calorific Value of Coal

Singrauli - 4,000 Kcal/kgKorba - 3,500 Kcal/kgRamagundam - 4,300 Kcal/kgFarakka - 3,200 Kcal/kgRihand - 4,000 Kcal/kgVindhyachal- 4,110 Kcal/kg

(e) Heat Rate Kcal/kWh

Stations 200/210 MW 500 MW Boiler Efficiency

Singrauli 2,060 2,027 86%Korba 2,030 2,027 87%Ramagundam 2,030 2,027 87%

Page 104: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-98-ANNEX 24

Page 3 of 6 pages

Farakka 2,030 2,027 87%Rihand - 2,027 87%Vindhyachal 2,030 - 87%

(f) O&M Expenses

Power Station - 2.5% on original cost of 200 MW plant.- 2.0% on original cost of 500 MW plant.

Transmission - 0.5% on original cost.

(g) Depreciation

Power Station - 3.1% of original cost.

Transmission - 2.6% of original cost.

(h) Tariffs5

NTPC has an obligation to achieve a rate of return of not less

than 9.5% on the forecast average net fixed assets in service

by FY1991. On this basis, and bearing in mind the time it takesfor che generating plant to reach an operating level of 5,500hours a year, regional average tariffs have been calculated whichresult in a consolidated average NTPC tariff of 32.2 paise/kWhfor FY1983. Regional average tariffs have been progressivelyincreased for each subsequent year to levels resulting in anaverage NTPC tariff of 43.9 paise/kWh in FY1991 which issufficient to achieve the required 9.5% rate of return in thatyear. The regional tariffs include provision for the recoveryof operating costs of the proposed project.

(i) Fuel

Fuel costs are based on 1982-83 prices for all projects as indicated

in paragraph 2(c). Variations in fuel costs will be recovered

as a tariff fuel surcharge. The projected fuel cost increasesare shown separately on the income statements.

(j) Project Costs

(i) Singrauli

Construction costs are based on June 1982 prices escalatedat rates given in the schedule below except for ordersalready placed where escalation is applied from award datesonward.

Page 105: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-99-

ANNEX 24Page 4 of 6 pages

(ii) Korba

Construction costs are based on June 1981 prices escalatedat rates given in the schedule below.

(iii) Ramagundam

Construction costs based on January 1982 prices for Phase Iand June 1982 prices for Phase II, escalated at ratesgiven in the schedule below.

(iv) Farakka

Construction costs are based on December 1981 pricesescalated at rates given in the schedule below.

(v) Vindhyachal

Construction costs are based on April 1982 pricesescalated at rates given in the schedule below.

(vi) Rihand

Construction costs are based on January 1982 pricesescalated at rates given in the schedule below.

(vii) Escalation Schedule

Price Escalation

a. 10% per annum for FY 1982b. 8.5% per annum for FY 1983c. 8% per annum for FY 1984d. 7.5% per annum for FY 1985e. 7% per annum for FY 1986f. 6% per annum for FY 1987 and onward.The turbo-generators and boilers are, however, subject tothe following maximum price escalation from the date oforder:

Singrauli 200 MW units - 25%

Korba, Ramagundam andFarakka 200 14W units - 20%

500 MW units for allprojects - 15% Turbine Generators

20% Steam Generators

Page 106: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-100-

ANNEX 24

Page 5 of 6 pages

Physical Escalation

Civil works - 10% of construction costs

Equipment - 5% of the equipment costs

(k) Capital Requirements

(i) The proposed credit would be relent by the GOI to NTPC

for a period of 20 years from the date of withdrawal ofthe first installment including a five year initial grace

period, and repayable in equal semi-annual installmentsof principal, together with interest at the rate of 12.5%per annum on unpaid balances.

(ii) Other capital requirements would be advanced by GOI in

the form of debt and fully paid up equity capital, providedthat the unpaid debt at the end of each year would notexceed the sum of the issued share capital and the "free"reserves, that is to say, those which are not required forspecific purposes. Advances would be in the form of equitycapital followed by loan capital.

(iii) GOI loans (including the onlending of both the proposed

credit and also previously approved credits and loan)are assumed to finance either defined projects orindividual generation units and transmission lines includedin NTPC's investment program. Interest on the loans up to

the date of commissioning of each unit of plant would be

charged to construction, while subsequent interest accrualswould be charged to revenue. Repayment of principal is

assumed in 30 semi-annual installments commencng on thefirst anniversary following the end of the five year graceperiod.

(1) Working Capital

Variations in working capital represent the difference between

the sums of the individual items making up current assets less

current liabilities at the beginning and at the end of the year.

(m) Balance Sheets (Annex 23)

Current Assets

(i) Receivables are assumed at a level equivalent to one-twelfth

of the revenue for the year;

(ii) Inventories are assumed at 1% of gross assets at the end

of the year; and

Page 107: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-101-

ANNEX 24Page 6 of 6 pages

(iii) Current liabilities are assumed at a level of one month'sfuel cost, plus 4% of the annual operating and maintenanceexpenses.

Page 108: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

NATIONAL THERMA1, POWER CORPORATION LIMITEDINCOME STATEMENT COVERING OPERATIONS FY1983 THROUGH FYl995

NORTHERN REGION

(Rupees Million)0-oo0-0-o osoososo-0 -000-== o=osono =o----0~= =0o=0=mooovs-0=oo o aO o -o -o -o=oo0=a=o =o =ooovOOO oo==== o=0=oo =0 =0=0 =O=CF:O =0=o =O=Oveos= ooovsoo a

Year Ending March 31 FY1983 FY 1984 FY1985 FY1986 FY1987 FY1988 FP3909 FY 1990 FY 1991 FY1992

Y1993 F71l994 FY 1995

-0-0'0-0-00..=0. 0s0'OS -:|:O OSODo - Eo=0-0-0-0-02 0-0- oso 0=o0o0- =o=o 0o=y0 0-0 0S:0= 0= 0==sOOO o=0=o=0=o-- 0- =o= 0=0=o= 0O=O o.=o= o-0.0= C=O=o=o =o.co-o=o-o=o -0.0=0-=0-0.6

Sale of energy (Gwh) 960 2851 4419 4880 5065 7209 10536 12828 14492 14640 14732 15984 18248

Revenue Bulk Supply (P/Kwh) '31.90 32.69 33,49 34.28 35.06 35.86 36.66 37.45 38.26 39.03 39.83 40,62 41.41

Oentral excise (p/Kwh) 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.e 1.8 1.8

ODeratinc Revenue

Sales - Bulk supply 306 932 1480 1673 1776 2585 3862 4804 5544 5714 5868 6492 7556

sales - fpel Surcharge - 22 69 115 154 236 380 542 723 862 1006 1178 1371

Cntral Utxcise 18 53 82 90 94 133 195 237 268 270 270 319 348

7btal Operatina Revenue 3 24_4 78 4 447 5583 5 - 989

Oneratina Ax?e&ses

Singraili - Fuel 87 259 401 443 460 568 717 812 878 878 878 878 878

- Fuel Surcharge - 22 69 115 154 236 359 479 602 691 785 885 991

- 0 & M 8 58 97 115 115 128 205 265 265 265 265 265 265

- Deprecietion 56 102 143 143 143 264 375 375 375 375 375 375 375

Rihand - Fuel - - - - - 124 346 509 633 652 652 652 652

- Fuel Surcharge - - - - - - 21 63 121 171 221 273 329

- 0 & M - - - - - 115 251 274 274 274 274 274 274

- Depreciation - - - - - - 213 415 415 415 415 415 415

New Projects- Fuel - - - - - - - - - - 17 324 774

- Fuel Surcharge - - - - - - - - - - - 20 51

- 0 & M - - - - - - - - - 12 200 282

- Depreciation - - - - - - - - - - - 216 432

Transmission- 0 & M 2 2 4 10 17 20 22 22 22 22 22 22 22

- Deprecintion 2 11 11 51 83 96 113 113 113 113 113 113 113

Central Excise * 1.8P/unit sent 18 53 82 90 94 133 195 237 268 270 270 319 348

Total Operating xIxpenses 173 507 807 967 1066 1684 2815 3564 3966 4126 4299 5231 6201

Operating Income(Before 151 500 824 911 958 1270 1620 2019 2569 2720 2845 2758 3074Intereste -_

Less:Interest on Loans 128 184 374 831 1263 1481 1582 1564 1477 1349 1220 1622 1997

DeductsInterest Capitalised 50 16 164 498 823 731 285

Net Interest Chargeable to 78 168 210 333 440 750 1297 1564 1477 1349 1220 1622 1997Operations

Profit/(Loss) 73 332 614 578 518 520 323 455 1092 1371 1625 1136 1077Write off deferred expenses 32 - - - - - -

Net Earnings 41 33j .7t3 _7 ji3 1092 1371 1625 1136 1077Average Rate Base 2764 4245 5539 6760 9121 16006 24719 27926 27022 26119 29692 32260 38301 c

Rate of Return(fterating 5.5 11.8 14.8 13.4 lO.5 7.9 6e5 7,2 9,5 10.4 9.6 8.5 0.0Income as % of Rate Base)

Operating Ratio(Operating 53.4 50.3 49.5 51,5 52.7 57,0 ;3.4 63,9 60.7 60.3 60.2 65,6 66,9Expenses as % ofOperatingRevenue)

Source: NTHPC November }1982

Page 109: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

NATIONAL THERMAL POWER CORPORATION LIMITED

INCOMF STATE1MENT COVEBING OPERATIONS FY 1983 THROUGH rY 1995WESTERN REGION

(Rupees Million)=o=0-0=osw0 - O"Oe 00_ =o=oe o=-o. OcOeo= o=O-O=O-OsO -O -OsOs 0O.Oco=O= O.Oc O.O= O=Oe OeOe O=O O-O=O- 0o0=0=o=o=0=.O=O=OeO=O=OeOeO=O=O = =O-=O=-.O=O=O e= 0= =oeowo=oeo0=0.0.0-00o O-O"O

Year Ending March 31 FY1983 FP 1984 FY1985 FY 1986 FY1987 FY19 8 8

FY 1989 FY 1990 FY1991 FY1992

FY1993 FY 1994 FY 1995

Sale of Energy (Gwh) 110 1216 2525 2928 2928 4487 7841 12035 15113 16285 16396 16396 16396

Revenue - Bulk supply (P/kwh) 35.45 36.27 37.30 38.29 39.34 40.36 41.37 42.38 43.40 44.42 45,44 46.45 47.47

Central 3xcise (P/Kwh) 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.. 8.8 1.8 .1.8

Onerating Revenue

Sales - Bulk Supply 39 441 942 1121 1152 1811 3244 5100 6559 7234 7450 7616 7783

Sales - Fuel Surcharge - 8 33 58 78 126 235 425 644 832 985 1139 1303

Central Excise 2 22 47 54 54 83 145 222 279 302 303 303 303

Total Operating Revenue 41 471 1022 1233 1284 2020 3624 5747 7482 8368 8738 9058 9389

Oneratiln ExNenses

Korba - Fuel 8 93 193 224 224 294 421 584 711 773 782 782 782- Fuel Surcharge - 8 33 58 78 126 217 354 499 621 713 803 898

-O & M 14 76 95 95 95 168 238 330 346 346 346 346 346

- DepreciFtion - 70 118 118 118 11 253 356 508 508 508 508 508

Vindhyachal - Fuel - - - - - 83 304 572 7 57 804 804 804 804

- Fuel Surcharge - - - - - - 18 71 145 211 272 336 405

-0&M - - - - - 122 231 310 340 340 340 340 340

- Depreci6tion - - - - - - 215 333 422 422 422 422 422

Transmission- O & X - 3 3 7 11 25 34 36 36 36 36 36 36

- Depreciation - 4 13 34 34 112 157 184 184 184 184 184 184

Central Sxcise * 1.8P/unit sent 2 22 47 54 54 83 145 222 279 302 303 303 303

Total Operating Expenses 24 27 502 590 1131 2233 3352 4227 4547 4710 4864 5

Operating Income Expenses 17 195 520 643 670 889 1391 2395 3255 3821 4028 4194 4361l.rIr ~nesre5

LesssInterest on Loans 122 194 238 476 1062 1680 2027 2152 2059 1912 1765 1618 1471

Deduct Interest Capitalised 109 58 20 218 761 865 654 157 - - - _ -

Net Interest Chargeable to 13 136 218 258 301 715 1373 1995 2059 1912 1765 1618 1471Operetions

Profit/(Loss) 4 59 302 385 369 174 18 400 1196 1909 2263 2576 2890

Write of deferred Expenses - --

Net Earnines 4 59 302 385 369 174 18 400 1196 1909 9263 2576 286

Average Rate Base 2400 3304 4558 4831 5854 13676 24169 31378 34257 33143 32029 30915 29801

Rate of Return(OperFting 0.7 509 11.4 13.3 11.4 6.5 5.6 7.6 9.5 11.5 12.6 13.6 14.6Income as % of Rate Base)

Operating Ratio(Operating 58.5 58.6 49.1 47.8 47.8 56.0 61.6 58.3 56.5 54.3 46.1 53.7 46.4Expenses as % of OperatirgRevenue)

Source: RTPC November 1982

Page 110: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

NATIONAL THERMAL POWER CORPORATION LIMITEDINCOME STATEMENT COVERING OPERATIONS FY1983 THROUGH FY1995

SOUTHERN REGION(Rupees Mi11ioniY

Year Ending March 31 FY1983 FY 1984 Fy1985 Fyr986

Py 1987 Fy 1988 FY1989 FY 1990 FY1991 FY 1992 FY1993 FY19 9

4 PY1995

-000_ CO_OleO_OO=O=OEMO= 0_0 =0_ 0~000000- 00=C=OOO .OOO-0ot O0=0l Oc=0=0=0= 0 0= Cs =0=Ooe0.00= 0= Oe= =0 O=0 O= O=O=O=O z O=Oe ==O=OO O = O= O0- =0 OC O==0 --O-Q-O= O- C onOa =C0O=O o_-C~0

Sale of Energy (Gwh) - 74 1078 2467 2928 3298 4629 6551 8547 9804 10248 10807 12868

ftvenue - Bulk Supply (P/Kwh) - 43e24 44.62 46.04 47.44 48.88 >0.27 51.69 53.10 54.50 55.92 57.33 58.74

Central Excise (P/Kwh) - 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8

Ooaratina Revenue

Sales - Bulk Supply - 32 481 1136 1389 1612 2327 3386 4538 5343 5731 6196 7559

Sales - Fuel Surcharge - - 11 49 87 128 224 384 594 794 955 1088 1248

Central Excise - 1 20 46 54 61 85 121 158 181 189 200 226_____________________ _ , _ ___ ___ _ _ 20 _ _ 8 5 7 8

Total Operatina Revenue _ 12 1530 180 2636 .3891 5290 6318 6 875 748

onergting Xxo-enses

Ramagundam - Fuel - 9 132 302 359 404 566 801 1045 1199 1253 1253 1253

- ruel Surcharge - - 11 49 87 128 224 384 694 794 955 1088 1228

- O & M - 12 93 125 125 164 271 357 406 406 406 406 406

- Depreciation - - 92 155 155 155 335 476 590 590 590 590 590

New Projects-Puel - - - - - - - - - - - 17 341

-Fuel Surcharge - - - 20

-0 & M _ 23 223

-Depreciation - - - - - - - - - - - 221

Transmission-4&M - 1 4 6 11 32 36 36 36 36 36 36 36

-Depreciation - 6 10 24 33 120 188 188 188 188 188 188 18B

Central Sxcisa * 1.8P/unit sent - 1 20 46 54 61 85 121 158 181 189 200 226

Tbtal OneratinO Exvenses - 62 Z 707 824 1064 1705 2363 3017 3394 3617 3801 4732

OperatintXg Income(Before 4 150 524 706 737 931 1528 2273 2924 3258 3683 4301Interest)

Less$Interest on Loans 44 163 298 536 902 1201 1353 1484 1316 1217 1117 1548 1951

DeductsInterest Capitalised 44 149 129 232 526 563 407 178 - - - - -

Net Interest Chargeable to - 14 169 304 376 648 946 1306 1316 1217, 1117 1548 1951operf tionls

Profit/(Loss) - (10) C 19) 240 330 89 (15) 222 957 1707 2141 2135 2350

Write Off deferred Expenses - - - - - - - - - -

Net Earnings - ) 19 220 330 89 (15) 222 957 1707 2141 2135 2350

Average Rate Base 212 1771 4581 5915 7700 13338 19283 22807 23929 23151 22373 29542 35707

Rate of Return(Operating - 0.2 3.3 8.8 9.2 5.5 4.8 6.7 9.5 12.6 14,6 12.5 12.0Income as % of Rate Base)

Operating Ratio(Operating - 87.8 70.7 57.4 53.8 59.1 64,7 60.7 57.0 53.7 52.6 50.8 52.4Expenses as % of OperatingRevenue)

Source: NTPC Novemher 1982

Page 111: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

NATIONAL THERMAL POWER CORPORATION LIMITEDINCOME STATEMENT COVERING OPERATIONS FY1983 THROUGH FY1995

EASTERN REGION(Rupees Million)

Year Ending March 31 E'Yl1983 py19B4 Fy975 Fyr1 98b Y 1987 ~'Yl py1 99 FY1 90 FY1991 FY 1992 FYl993 py1994 py1995

Sales of Energy (Gwh) - - 110 1216 2525 2928 2928 4037 5812 8030 9582 10248 10248

Revenue - Bulk Sup,ly (P/Kwh) - - 29.23 40.38 41.50 42.64 43.78 44.91 46.04 47.18 48.31 49.45 50.58

Central Excise (P/Kwh) - - 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80 1.80

OPERATING REVENUE

Sales - Bulk Supply - _ 43 491 1048 1249 1282 1813 2676 3789 4629 5068 5183

Sales - Fuel Surcharge - _ 9 39 67 89 155 273 450 629 777 887

Central Excise - _ 2 22 47 54 54 75 107 148 177 189 189

Total Opeiating Revenue -4- 45 522 T134 1370 1 2043 3056 4387 5435 6034 6259

0PEi-ATING EXPE2 SES

Farakka - Fuel. - - 11 127 263 305 305 420 604 834 995 1c65 1065- Fuel Surcharge _ - - 9 39 67 89 155 273 450 629 777 887

- 0 & M - - 19 115 155 155 155 245 353 353 353 353 353- Depreciation - - - 94 193 193 193 193 331 500 647 647 647

Transmission - 0&M - - 1 4 4 5 8 9 9 9 9 9 9- Depreciation - - 11 20 20 42 47 47 47 47 47 47

Central Excise @ 1'9P/Unit sent - _ 2 22 47 54 54 75 107 148 177 189 189Total Operating Expenses - _ 382 721 799 846 1144 1724 2341 2857 3087 3197Operating Income (Before Interest) 12 140 413 571 579 899 1332 2046 2578 2947 T062Less I Interest on Loans - 34 156 313 398 496 109 0 1201 1209 1122 1035 948Deduct Interest capitalised - 34 139 91 16 109 349 431 271Net Interest chargeable to operations - - 17 222 382 387 420 629 930 1209 1122 1035 948Profit/(Loss) - - (5) (82) 31 184 159 270 402 837 1456 1912 2114Write off Deferred Expenses _ - - - - - - - - - - -Net Earnings _ ) (82) 31 184 -159 270 3 131 1456 1912 2114

Average Rate Base 3455 5161 6760 6980 7287 9377 14023 18664 1°,424 17730 17036Rate of Return (Operating Incomeas % of rate base) 0.3 2.7 6,1 8.2 7.9 9.6 9.5 10.9 13.3 16.6 17.9Operating Ratio (Operating Expenses as% of operating Revenue) 73.0 73.2 63.6 58.3 59.4 56.0 56.4 53.4 52.6 51.2 51.1

Source: NTPC November 1982

Page 112: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDTA

CENTRAL POWER TRANSMISSION PROJECT

ANDHRA PRADESH STATE ELECTRICITY BOARD

INCOME STATEMENT COVERING OPERATTONS FY1980 THROUGH FY1989(Qunses Mi ilion)

Year endiing March 31st FY1980 FY1981 FY1982 FY1983 FY1984 FY1985 FY1986 FY1987 FY1988 FY1989

Total Energy Sales (GWh) 4,770 5,328 6,635 7,382 8,339 9,827 11,922 12,804 13,484 14,580

Average Tariff (Ps/kWh) 34.1 37.8 42.4 46.0 46.9 47.5 48.0 48.5 50.8 55.5

OPERATING REVENUE

Energy Sales 1,628 2,011 2,814 3,396 3,909 4,668 5,722 6,113 6,845 8,087

State Government Subsidies 95 117 41 - - - - - - -

Other Income 29 39 34 37 38 _ 39 _ 40 41 42 43

TOTAL OPERATING REVENUE 1,752 2,167 2,889 3,433 3,947 4,707 5,762 6,154 6,887 8,130

OPERATING EXPENSES

Power Purchases 36 47 48 49 50 230 499 720 882 1,137

Fuel 415 530 805 918 1,088 1,148 1,228 1,302 1,580 1,891

Employee Costs 350 376 589 705 804 909 1,023 1,302 1,580 1,891

Depreciation 210 258 313 355 436 500 571 626 899 831

Central Excise Duty 75 93 123 134 151 L70 197 202 215 230

Other Operating Expenses 187 214 289 298 328 358 388 415 458 501

TOTAL OPERATING EXPENSES 1,273 1,518 2,]47 2,457 2,837 3,315 3,908 4,408 5,090 6,021

OPERATINC INCOME (Before Interest) 479 649 742 976 1,110 1,392 1,856 1,748 1,797 2,109

Less: Interest on Loans 425 500 505 616 686 774 867 973 1,115 1,291

Deduct:Interest Capitalized 123 119 134 113 74 73 104 150 169 168

Net Interest Chargeable to Operations 302 381 431 503 612 701 763 823 _ 946 1,123

NET EARNINGS 177 268 311 473 498 891 1,093 925 851 986

Rate of Return (9) 9,5 9.5 9.5 10.3 9.5 10.3 12.3 10.6 9.5 9.5

Operating Ratio (OperatingExpenses as % of Operating Revenue) 72.7 70.1 74.3 71.6 71.9 70.4 67.8 71.6 73.9 74.1

Source: CEA October 1982

Page 113: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

TNDIA

CENTPAL POWER TRANSMISSION PROJECT

ANDHRA PRADESH STATE ELECTRICITY BOARD

NET INTERNAL CASH GENERAT1ON FY1980 THROUGH FY1989

Year Ending March 31st FY1980 FY1981 FY1982 FY1983 FY1984 FY1985 FY1986 FY1987 FY1988 PY1989

CAPITAL ASSETS INVESTMENT

Capital Investment 1,386 1,364 1,504 1,742 2,171 2,524 2,913 3,166 3,729 4,337

Interest during construction 123 119 134 113 74 73 104 150 169 l6R

TOTAL 1,509 1,483 1,638 1,855 2,245 2,597 3,017 3,316 3,898 4,505

DEBT SERVICE

Interest on Loans 425 500 565 616 686 774 867 973 1 ,115 1,291

Deduct: Interest Capitalized 123 119 134 l13 74 70 1'0 150 169 168

Net Interest Chargpahle to Operations 302 381 431 503 612 701 763 823 946 1,123

Loan Principal Repayments 103 135 233 277 284 308 413 438 448 458

TOTAL 405 516 664 780 896 1,009 1,176 1,261 1,394 1,591

INTERNAL CASH GENERATION

Operating Income 479 649 742 976 1,110 1,392 1,856 1,748 1,797 2,109

Depreciation 210 258 313 355 436 500 571 62b 699 831

Consumer Contributions 18 17 26 25 25 25 25 25 25 25

Consumer Security Deposits 60 65 139 73 75 75 75 75 75 75 .

TOTAL 767 989 l,220 1,429 1,646 1,992 2,527 2,474 2,596 3,040 tt

Less: Debt Service 405 516 664 780 896 1,009 1,176 1,261 1,202 1,581

NET INTERNAL CASH GENERATION 362 473 556 649 750 983 1,351 1,213 1,202 1,459

Contribution to Investmcnt 29.0 30.7 33.5 33.9 33.6 37.5 45.4 35.6 30.8 32.4

Net Cash Generation as 7 of

Capital Assets Investment)

Source: CEA Octoher 1982

Page 114: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

INDIA

CENTRAL POWER TRANSMISSION PROJECT

ANDHRA PRADESH STATE ELECTRICITY BOARD

BALANCE SHEET AS AT END OF FY1980 ThROUGH PY1989

(Rupees Million)

Year Ending March 31st FY1980 FY1981 FY1982 FY1983 FY1984 FY1985 FY1986 FY1937 FY1988 FY1989

------------ Actual…------------

Assets

Gross Fixed Assets (Historic Cost) 8,193 9,615 10,525 13,526 15,845 18,229 20,010 22,383 26,183 30,542Less: Depreciation 1,641 1,898 2,211 2,566 3,002 3,502 4,073 4,699 5,398 6,229

Net Final Assets in Use 6,552 7,717 8,314 10,960 12,843 14,727 15,937 17,684 20,785 24,313Work-in-Progress 2,210 2,152 2,746 1,487 1,339 _1,479 2,611 3,404 3,333 3,311

Total Net Fixed Assets 8,762 9,869 11,060 12,447 14,182 16,206 18,548 21,088 24,118 27,624Investments/Intangible Assets 38 27 51 10 10 10 10 10 10 10Working Capital 248 364 150 60 - - - - - -

Total Assets 9,048 10,260 11,261 12,517 14,192 16,216 18,558 21,098 24,128 27,634

Equity and Liabilities L

Equity

Capital Subventions 12 12 12 12 12 12 12 12 12 12Consumer Contributions 142 159 185 210 235 260 285 310 335 360

Retained Earnings 96 245 476 836 1,260 1,878 2,867 3,642 4,324 5,142

Total EquitM 250 416 673 1,058 1,507 2,150 3,164 3,964 4,671 5,514

Liabilities

Long-Term Debt 7,853 8,802 9,364 10,121 11,222 12,468 13,651 15,236 17,394 19,882

Consumer Security Deposits 363 428 567 640 715 790 865 940 1,015 1,090Staff Super-Annuation Funds 184 216 259 300 350 410 480 560 650 750Interest Accrued on State Loans 398 398 398 398 398 398 398 398 398 398

Total Liabilities 8,798 9,844 10,588 11,459 12,685 14,066 15,394 17,134 19,457 22,120

Total Equity and Liabilities 9,048 10,260 11,261 12,517 14,192 16,216 18,558 21,098 24,128 27,634

Debt/Equity Ratio 97/3 95/5 93/7 91/9 88/12 85/15 81/19 79/21 79/21 78/22

Soulrce: CEA October 1982

Page 115: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-lO9-

ANNEX 32

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Southern Region: Additional Transmission Requirements 1995

High Hydro Low HydroHigh Low High Low

400 kV System Element FOR FOR FOR FOR

Line-circuit km 3411 3411 3281 3281

Sub-stations-Nos. 4 4 4 4

Inter-connecting 6000 6000 6000 6000transformers-MVA

Line Bays-Nos. 40 40 36 36

Line Reactor-MVAR 100 100 100 100

Bus Reactor-MVAR 900 900 900 900

Cost-Rs million 4810 4810 4630 4630

Page 116: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-110-

ANNEX 33

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Costs and Benefits of Intra-Regional Transmission

Econ. Cost

Year of transmission (Rs m.) Outage (GWh) Value (Rs m.) Net (Rs m.)

82/83 11.3 - - 11.3

83/P4 148.5 _ _ 148.5

84/85 562.5 _ _ 562.5

85/86 P35.2 - - 835.2

86/87 296.9 - - 296.9

87/88, 59.4 - - 59.4

88/89- 14.8 207.7 367.6 352.8

2013/14

IRP 13.2%

NPV 8% 1,010

10% 510

12% 161

IRP (cost+10%) 12.1%

IRR (benefit-1O%) 12.0%

Page 117: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-111-

ANNEX 34

INPIA

CENTRAL POWER TRANSMISSION PROJECT

Southern/Western transmission link: least-cost solution

Year Cost of transmission Alternative new generating capacity

(Rs m.) (P.s m.)

82/83 2.3 273

83/84 30.4 685

84/85 115.8 959

85/86 171.1 1,096

86/P7 60.8 821

87/88 12.1 365

88/8'-2013/14 2.9 105

PV 5% 376 5% 4,863

8 340 8 4,214

10 320 10 3,891

12 302 12 3,625

15 279 15 3,303

Page 118: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-112-

ANNEX 35

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Northern/Western DC Link: Least-Cost Solution

Year Transmission Cost New generation capacity (500 MW)

(Rs m.) (Rs m.)

82/83 7:3.7 147

83/84 133.1 252

84/85 312.2 546

85/86 430.2 546

86/87 1Q7.3 420

87/88 94.7 189

88/89-2013/14 12.3 52.5

PV 5% 1,227 2,427

8 1,105 2,101

10 1,039 1,938

12 981 1,804

15 908 1,641

Page 119: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-113-

ANNEX 36Page 1 of 2 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

APSEB Tariffs

Consumer category Tariff (as of Oct 1982)

Low voltage

Domestic (paise/kWh): up to 100 kWh/mo. 45

above 100 kWh/mo. 50

Commercial (paise/kWh) 90

Industrial (paise/kWh): general 50

cottage ind. 35

Agricultural:

energy (paise/kWh) 16

capacity (Rs/HP/mo.) 2.0

(ceiling Rs 10)

Public lighting:

energy (paise/kWh)

- panchayat 42

- municipalities 48

Page 120: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-114-ANNEX 36Page 2 of 2 pages

- corporations 50

capacity (Rs/fixture/mo.) 2.0

General Purpose (paise/kWh) 60

High voltage

Category I: energy (paise/kWh) 40

fuel surcharge (paise/klh) 2.74

capacity (Rs/kVA/mo.) 25.0

Category IT: energy (paise/kWh) 47

fuel surcharge (paise/kWh) 2.74

capacity (Rs/kVA/mo.) 30.0

Agricultture: energy (paise/kWh) 16

capacity (Rs/HP/rno.) 2.0

Power intensive (minimum 403 kWh/kMTA/mo.) 32

fuel surcharge (paise/kWh) 2.74

Page 121: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-115-

ANNEX 37Page 1 of 2 pages

INDIA

CENTRAL POWER TRANSMISSION PROJECT

Marginal Cost of Electricity Supply in Andhra Pradesh

T. 1975 Tariff Study estimates (1974/75 prices) I/

11 kV LT

consumers consumers

Energy (paise/kWh) 11.5 13.7

Capacity (Rs/kW/mo)

- generation and transmission 33.7 41.0

- distribution 4.1 41.1

- total 37.8 82.1

II. 1978 Bank estimates (1978/79 prices) 1/

11 kV 11 kV

Average Rural Average Rural

Capacity (Rs/kW/mo)

Generation 40 47 50 65

Transmission and distribution 27 35 61 77

Total 67 82 111 142

1/ Before application of diversity and load factor considerations.

Page 122: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-lib-

ANNEX 37Page 2 of 2 pages

11 kV 11 kV

Average Rural Average Rural

Energy (paise/kWh)

Dry season peak 23 29 29 35

Dry season off-peak and

Wet season peak 12 15 15 18

Wet season off-peak 0 0 0 0

!II. 1981 Bank estimates (1980/81 prices)

Average

Domestic Industry Agriculture (sales-weighted)

Total cost (paise/kWh) 110 30-40 100-120 68

IV. 1982 Average Incremental Cost (1982 prices)

(paise/kWh) 45-50 1/

1/ Purchases from other States and NTPC valued at similar cost as APSEBgeneration. If purchases were valued at NTPC-s Southern Region AIC, orat hydro rates prevalent in the Southern Region, APSEB's AIC would bein the range of 40-45 paise/kWh.

Page 123: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

-117-

Annex 38

INDIA

CENTRAL POWER TRANSMISSION PROJECT

National Thermal Power Corporation Limited

Documents Available in the Project File

1. National Grid Development Project, Feasibility Report;National Thermal Power Corporation Ltd., Augt.t 1982

2. India, Long Term Power Plan, Generation Expansion Program(1981-82 to 1994-95) (5 volumes)Central Electricity Authority, Ministry of Energy (Departmentof Power), Government of India

September 1982

3. NTPC, Sixth Annual Report 1981-82September 17, 1982

Page 124: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department
Page 125: World Bank Documentdocuments.worldbank.org/curated/en/... · Report No. 4293-IN STAFF APPRAISAL REPORT INDIA CENTRAL POWER TRANSMISSION PROJECT April 26, 1983 Regional Projects Department

F7 AFGHANISTAN"-

•A' HAA I

PAKISTAN K. ~~~~~~~~~~,N2 '>7 ~~~~~C H I N A

U T~ ~ ~ ~ ~ ~~~~~~~~7 6

K 'C~~~~~~~~~~~~~~~~~~~~~~~~~~~I~Kl IAH

( '~~~(o-~~~ ~~ SKKN: S~~HUTAN / AU

010 p p t U ~~~~~~~~~~~~~~~~~ p ~ ~ ~ ~ ~ ~ 9 6,,AZ A T A ' ~ ~ . .'-.. ~ ~ ~ ; ~ A

9 Aooog h ~ ~ ~ ~ < ~ ,FGALA220 7

7r~~~~~~~~k -f ~~~~~~~~~~~~~~~~~~~~~~~~~~~B N L R

C, JARA7 MtR_

A,. - - , - -- 'WE,E H4¶U ooipjr. C 0< <-- -u ~ ~ ~ ~ ~ ~ ~ B U R MA

-27M -'ARA A VTR A A

Ch!rho- J

IJ ~ 3' - I N D'1 A

4 roercoodo ICENTRAL POWER~~ tororsodo ~~TRANSMISSIQN PROJECTF A! Op~~~~~~~~~ 400 kV Grid

WA1Vruoobod A NJ H 1-R A

~~ RAyESF], ___ ___ AFAR:~~400k LIs

KARKA JAKA% C:dph 400C SobroooNoflr -13D0 BoA r oolr-ok

>1 H ~~~~~~~0 no'F. Pow-rBobo

BorooIro& 37 -< RCol4lI 400W ki.o

7 - -- oiyoro Poooot Booboos-n -- -yd -F.--

ScIon, - -~~~~~~~~~R-o 5d.4

oA AppIr

KERALA, N A UJoarr

SRI LANKA T -!r


Recommended