WP1 - Pixel detectors for HEP tracking and ImagingRichard Plackett (SR) and Timo Tick (ESR)
ACEOLE 12 Month Meeting, 1st October 09
-2-
Richard Plackett – 1st 6 months
• 6 week secondment to PANalytical – Formal internal training on XRD/XRF – On the job training with Pan experts implementing new
techniques based on Medipix2 chip • Automatic Known Good Die (KGD) testing and
classification – MATLAB based wafer probing system– Prerequisite to large area tiling– Formal training course on MATLAB– On the job training on chip behaviour and classification by
local experts • A significant number of wafers sucessfully
tested• Reports in Collaboration meetings
-3-
Automatic Wafer CharacterisationA KS PA200 probestation was automated to allow the automatic testing of readout chips at the wafer level
A custom optical feedback system allows automatic alignment and chip finding to test wafers and individual assemblies
Karl Suss PA200 Probestation
Reconstructed chip positions on a Medipix1
Microscope video feed Target image Correlation
Peak finding Position reconstruction
-4-
Richard Plackett – LHCb activitiesTimepix / Pixel VELO Testbeam Activity
Testbeam Results
Plans for Future Timepix Telescope
RICH Photon Detector Upgrade Proposal
Medipix3 radiation sensitivity measurements
Slides from presentations to VERTEX09 and LHCb RICH upgrade meetings.
-5-
Recent Testbeam ActivityA Timepix like chip is a candidate for a Pixel VELO upgrade
• Required to demonstrate suitability for tracking• Measure efficiency and resolution• Provide information for VELOPIX design
• 3 testbeams at CERN SPS with 120GeV Pions– June: as Medipix Group to test Telescope concept– July: Running parasitically from CMS SiBit telescope – August: Running parasitically from EUDET/LCFI testbeam
• Significant improvements to telescope design at each testbeam
-6-
Testbeam Telescope V1 and V2The first testbeam in June proved we could do tracking with Medipix2 chips and the synchronisation scheme worked
The July testbeam took two weeks of data across all areas of interest.This experience allows us to significantly improve the design of the Timepix Telescope
-7-
Timepix Telescope4 Timepix, 2 Medipix planes in telescope
Symmetric positioning of planes around Timepix DUT
Telescope planes mounted at nine degrees in x and y
DUT position and angle controlled remotely by stepper motors
Measurements of resolution with angle, threshold, sensor bias, 3D sensor and timewalk
-8-
Angled Planes to Boost ResolutionHits that only affect one pixel have limited resolution (30um pixel region)
Angling the sensor means all tracks charge share and use the ToT information
55um
300um 10o
Timepix (ToT) tracked position vs cluster reconstructed position
-9-
Results – Resolution Vs Track Angle
2.5um Estimated track contribution
to residual
Rotation about Y axis
PRELIMINARY: UNCALIBRATED DATA!!
The tracking uncertainty of the telescope is very competitive, with uncalibrated, uncut data, 2.5um is comparable to EUDET running with
30um pixels (Timepix is 55um)
-10-
Results – 3D Sensors Efficiency
The sub-pixel resolution of the telescope allows us to see the efficiency losses due to the anode and cathode holes in the silicon.
Perpendicular particles passing through a doped hole will deposit less charge in the silicon
Glasgow double sided CNM sensor
-11-
Design Lessons for VELOPIX• Analogue IS better than Binary, even with 55um pixels, even with
clusters and charge sharing
• Clustering WILL significantly increase hit multiplicity
• Interactions within the sensor will occur often and need to be handled to avoid overflowing the chips for that event
• From this data we will determine how many bits ToT we need and optimise on chip the data transport
Timepix (ToT) 5um Medipix (binary) 11um
-12-
Plans for a future Timepix Telescope
We plan to add fast readout systems and software synchronisation• High resolution (<3um) as current telescope• Track timing down to 10ns• Link to PMT/external device for trigger and integration of DUTs• Maximum track rate increased up to ~200kHz• Convenient, flexible device as current telescope• Should become baseline LHCb telescope for upgrade work
New Readout
Timing unit
DUT
New Readout
-13-
LHCb RICH SystemLHCb RICH must also upgrade to 40Hz electronicsRequires at least HPD photon detector planes to be replacedPossible to use VELOPIX as base for new MCP photon detectorThe Medipix group already has collaborators with experience in this areaRequires high density through Silicon Via technology
Photon
Photoelectron
Electron shower
Quartz window and photocathode as HPD and MAPMT
200V/mm drift field
MCP cascade amplification (~1kV)
Bare readout chip array (no bump bonds)
A Proximity focused MCP tube could perform as well as an HPD with many additional advantages…40MHz digital readout Magnetic field toleranceLow vacuum volumeHigher resolutionAvoids 20kV supply simplifying services
-14-
400Mrad Irradiation• Used a calibrated X-ray machine (Seifert RP149)• Beam profile is smaller than the Medipix3 → Two runs:
On the Pixel Matrix 60MradThreshold Variation
Gain Variation
Noise Increase
On the Periphery 400Mrad Check DACs
E-fuses
Logic functionality
60 MRad
460 MRad
400 MRad
-15-
Performance after 460MRadThreshold Noise
Yiel
d ar
tifac
t
b 190.733061= σ 35.304781= Fit 0.000026=
0 2 4 6 8 10 12 14 16 18 200
200
400
600
800
THL [ke-]
Cou
nts
σ=1.72 ke-
µ=9.3 ke-
b1 8.798851= σ1 1.591887= Fit1 0.000247=
0 20 40 60 80 100 120 140 160 180 2000
2000
4000
6000
8000
10000
noise[e-]
Cou
nts
σ=12.9 e-
µ=71.6 e-
Threshold can be re-tuned using 5 bit equalisation
-16-
0 15 30 45 60 75 90 105 120 135 1500
1000
2000
3000
4000
5000Pixel Non-IrradiatedPixel Irradiated at 460 MRad
THL [DAC step]
Pixe
l cou
nts
Performance after 460MRad
Yiel
d ar
tifac
t
Qin=2ke-
0 100 20040
60
80
100
Row Number
Noi
se [e
-]
Row
[0:2
55]
After 460MRad there is essentially no gain variation observed
-17-
Richard Plackett - Conclusions• First months devoted to learning materials analysis techniques,
MATLAB and Medipix2/Timepix chip operation• Automatic wafer probe test system developed and successfully
operated• A series of test beams were carried out using a large number of
Timepix assemblies• Excellent test beam results led LHCb VELO to adopt that
approach for the upgrade• Along the way we developed a very accurate and convenient
particle telescope we would like to take further, currently being used in SPS crystal collimator studied
• New ideas for a large area tiled photon detector were developed• There is the possibility of the VELO chip being used in MCPs or
HPDs in the RICH upgrade.• Measurements on the behaviour of the Medipix3 chip 0.13um
indicate its suitability for sLHC and other high dose applications (such as x-ray materials analysis and CT)
Timo Tick - Outline
• Low-cost bumping and flip chip solutions• Through Silicon Via (TSV) process development• Large area tiling
• GOAL:
TSVs Read out chip
Work carried out together with Sami Vaehaenen in the framework of WP6 of PH detector R and D
Low-cost bump bonding - motivation
• Bump bonding (BB) costs for a single detector unit have been over € 200• Readout chip (ROC) : sensor chip (SC) : bump bonding (cost ratio) = 1:2:7!
• Imagine building a square meter sized area from detectors with unit area of 1.5 cm2 with 200 € BB unit costs 667 detectors required for and the total BB cost is 1.3 M€!
• More pixel detectors are desired to be used in SLCH and the total area will cover tens of square meters - the cost issues is evident
• Reliable and cheap bumping technologies do not exist yet for ultra-fine-pitch (UFP) applications, such as Alice/Atlas/CMS/Medipix chips
• Here’s a cost estimation how the costs should be shared between readout chip (ROC) bumping, sensor chip (SC) bumping and FC bonding
• In the calculated graph, sensor bumping costs are dominating, but in reality flip chip bonding services have become more expensive
23%
42%
35%
Cost structure - bump bonding of single detectorNo thinning of readout wafers
ROC bumping & dicing SC bumping & dicing Flip chip bonding
Low cost bump deposition solutions • Way to realize the goal is to benchmark the manufacturing technologies used in commercial
electronics and adapt them for pixel wafers.• Study the technologies and find the essential limits (minimum bump size and pitch) for a low-cost
technology to be realized.• To provide cost savings processes have to become faster and the use of expensive and non-
flexible process equipment should be avoided or minimized.• Reliable and cheap bumping technologies do not exist yet for ultra-fine-pitch (UFP) applications,
such as Alice/Atlas/CMS/Medipix chips.• Focus is directed at applying electroless deposition process (Ni/Pd/Au) under bump metallization
(UBM), which is a low-cost solution and enables various solder transfer and flip chip bonding technologies.
• Solder transfer tools combined with electroless UBM’s has a very high potential to be the ultimate low-cost bumping solution.
Electroless Ni/Au UBM deposition was demonstrated with 55 µm pitch.
Flip chip development work • Flip chip bonding can be done using with or without solder bumps. Anisotropically conductive
adhesives (ACF) enable assembly without solder.• The flip chip work can be divided to two main categories:
1. Optimization of tooling and tuning of software parameters for existing FC bonders (FC150’s).2. Search for new bonding equipment which could boost up the throughput, but could still
fulfil the resolution criteria.• ± 5 µm accuracy should be good enough for pixel detector assembly.
• Nickel and carbon nanofibers in polymer matrix will be tested. The films with aligned fibres are the best candidates for achieving ultra-fine pitch with area array pixels.
• Chip-to-wafer bonding process is desired to be developed, because it increases the cost efficiency of flip chip assembly.
• A report on low cost bumping solutions (D11) is almost ready for publication (due month 10)
ACF’s are interesting because no solder is needed.
TSV development• Joint development project started with VTT 1.7.2009, duration 12 months
– Step 1: (3 months)• Study and evaluation of the available techniques at VTT for the TSV process• Selection of candidate processes• Definition process parameters for individual process steps/equipment
– Step 2: (6 months)• Optimize process and manufacture prototype vias on dummy wafers• Preparation the 2 medipix2/3 wafers for processing
– Step 3: (3 months)• Manufacture TSV’s on real medipix2/3 wafers
Time (month) Deliverable Partner0 Layout of test vehicle CERN1 Masks for test vehicle VTT3 Detailed TSV process description VTT8 Supply of 2 Medipix2/3 wafers CERN9 TSV Assemblies based on test vehicle VTT
10 Test report on test vehicle assemblies CERN11 Delivery of Medipix2/3 assemblies VTT12 Test report on Medipix2/3 assemblies CERN
Done
Test vehicle• Test vehicle was designed to serve the flip chip and the through silicon via (TSV)
development work. • Test vehicle has daisy chain and Kelvin test structures to characterize the
interconnection yields and resistances at three interfaces:• Flip chip bumps (20852/chip)• TSV’s (196/chip)• BGA joints (100/chip)
• Test chips can be used for gathering reliability data during accelerated thermal stress testing.
• Layout has been designed to be used also in wafer-level assembly tests• Chip-to-wafer-bonding• Wafer-to-wafer bonding
• 24 silicon wafers were processed at VTT to evaluate electroless UBM deposition, low-cost flip chip techniques and BGA connections
• Probe card for test vehicle has been designed and acquired - ready for measurements
TSV development• Detailed process description has been agreed with VTT and CERN
– Development of process is started with 6” dummy wafers although CERN wafer are 8”– Test vehicle layout is used to process test chips for yield and quality evaluation– Via etching test are currently being made at VTT
• Plan is to move to 8” processing as soon as possible – process description has been done by Sami and Timo
• Formal training on TSV at ECTC, san Diego• Informal on the job training at CERN with S. Vaehaenen and during 2 visits (3
weeks in total) with experts at VTT
Large area tiling• Study of large area tiling possibilities of detectors (with TSV’s) has been
made: Report by the end of Nov. (D13 - 12 month deliverable)– Two concepts exist:
• Research focused on BGA mounted detector modules• Work is done in parallel with TSV development develop solutions to BGA
mount detectors with TSV’s as soon as they arrive– Carrier board selection and evaluation– BGA bump type selection and evaluation– Set up BGA bumping and assembly procedures
• GOAL: to be ready to design the backside layout of the detector chip and to BGA mount the detectors as soon as chips with TSVs come out
Carrier board and BGA bump selection
• Carrier board requirements for area array solder mounting large silicon chips– Low CTE, high density signal wiring (multilayer wiring), high current wiring for powering and
good heat conductivity• Selected candidates: Multilayer ceramics (LTCC), Carbon composite laminates (CCL) and
silicon
• 3 different BGA bump types were chosen for evaluation:– Non collapsible plastic core BGA
• Light weight solution, radiation hardness to be proved– Collapsible BGA
• Standard technique, reference– Land Grid Array (no bump)
• Simplest and cheapest solution, reliability needs to be proved
PCBGABGA
LGA
Silicon LTCC CCL FR-4CTE [ppm/K] 2.6 6 2-10 16Thermal Conductivity [W/mK] 13 2-3 ~100 (bulk 600) 0.25Density [g/cm2] 2.3 3 1.55-1.9 1.9Young’s modulus [GPa] 130 350 > 100 15
Carrier board and bump type evaluation
• LTCC – Test board has been designed• To evaluate the reliability of the three chosen bump types with temperature cycling tests• Test the radiation hardness of the plastic core balls• Set up a prototype bumping and assembly procedure in CERN SMD lab.• Status: waiting for UBM deposition on dummy chips
• CCL – Suppliers have been contacted to acquire reliability data• Mechanical properties received from the supplier need to be verified• Board reliability and radiation tests need to be done• If these preliminary tests are passed, BGA joint evaluation can be done• Status: Negotiating with material supplier
• Silicon – Collaboration with Gigatracker project• BGA reliability is not the issue with silicon carriers• Cooling and high current wiring is and solutions to these issues are being investigated in
gigatracker project• Gigatracker is not using TSVs but same solutions apply
• Timo investigated the processing possibilities at VTT and presented them to Gigatracker cooling group
• Status: Agreement to collaborate, Gigatracker group contacting VTT
Conclusions - Timo Tick
• First months devoted to understanding needs in HEP and other applications
• Low cost bumping approaches studied together with S.Vaehaenen
• TSV project established with VTT• Large area tiling based on BGA – candidate solutions
identified• Test vehicle designed with S. Vaehaenen for low cost
bumping, TSV and BGA evaluation• Test vehicle wafers processed at VTT by Timo and Sami• Formal training undertaken at ECTC conference
• PhD thesis in print – defence 27th November